appendix i next steps study · 2 way cycle track begins 2 stage bike boxes installed existing...

34
APPENDIX I NEXT STEPS STUDY DECEMBER 2017

Upload: others

Post on 15-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

APPENDIX I

NEXT STEPS STUDY

DECEMBER 2017

Page 2: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

2 MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

Page 3: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

APPENDIX I

NEXT STEPS STUDY

3MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

The Next Steps Study includes planning level cost estimates, phasing considerations, and construction details for several key projects recommended in the University & Colorado Stations Multi-Station Plan & Mobility Study.

Projects were selected to be included in the Next Steps Study based on community input, feasibility, timing, and potential funding sources. The Next Steps Study provides an additional level of concept design analysis and builds further public support before projects move to final design and implementation.

Page 4: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

4

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

APPENDIX INEXT STEPS STUDYintroduction and document organizationThis Next Steps Study provides more detail on select projects identified in the University & Colorado Multi Station Plan & Mobility Study. Projects listed on the facing page represent the primary recommendations from this study and were selected from the Multi Station Plan & Mobility Study based on feasibility, community input, and potential funding opportunities. Projects are organized in this document by study area planning zone. The UNIVERSITY STATION ZONE covers all projects west of (and including) University Boulevard. UNIVERSITY PARK CONNECTIVITY ZONE is comprised of projects between University Boulevard and Colorado Boulevard. The COLORADO STATION ZONE includes all projects east of (and including) Colorado Boulevard. Each project description includes conceptual graphics, timing and dependencies considerations and a recommended implementation priority.

public involvement and outreachInitial project concepts were vetted during a public meeting in May 2017 and final recommendations were presented to stakeholders in September 2017. Key stakeholders in the area, Lincoln Property Company (developer and owner of Colorado Center) and University of Denver (DU), partnered with the City and County of Denver to provide critical input and recommendations for these projects. The University Park Community Council neighborhood organization and its partners also contributed crucial insight towards crafting a community vision for this study.

potential funding sources

Potential funding sources for these projects include 2017 General Obligation Bond, Denver's Capital Improvement Program, federal funding as distributed through Denver Regional Council of Governments' (DRCOG) Transportation Improvement Program, or other grants and private funding.

acknowledgments

PARTNERSCity and County of DenverUniversity of DenverLincoln Property Company

PROJECT TEAMKaren Good, AICPProject ManagerDenver Public Works

Michael Butters, PE, CFMProject ManagerJacobs Engineering

Evgeniya Tyson, PETransportation EngineerJacobs Engineering

Chris Vogelsang, PEPrincipalOV Consulting

Max LubarskyPlanner OV Consulting

Page 5: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

5MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

* Planning Level Cost Estimates in 2017 Dollars. Detailed cost breakdowns in Appendix II.

Intersection: Franklin & Buchtel $1.1M 9

Cycle Track: Franklin - High $1.6M 10

Cycle Track: High - RTD Station & Urban Roundabout $2.3M 11

Cycle Track: RTD Station - University $1.6M 12

Buchtel Mid-block Crossing $150K 13

Intersection: University & Buchtel $2.0M 14

Intersection: University & Asbury $600K 15

Intersection: University & Evans $1.5M 16 - 17

Clayton Ave Pedestrian Crossing $50K 19

Cycle Track:University - Colorado $1.8M 20

Intersection: St. Paul & Buchtel $400K 21

Intersection: Monroe & Buchtel $300K 22

Asbury Ave Neighborhood Corridor $700K 23

Colorado & Frontage Rd (Co. Cntr. North) $1.0M 25

Intersection: Colorado & Buchtel $900K 26

Colorado Center Drive Bicycle Connection $250K 27

Cycle Track:Colorado Center Drive $1.2M 28

Intersection: Colorado & Evans $1.2M 29

PROJECT PLANNING LEVELCOST ESTIMATE

IMPLEMENTATIONPRIORITY

TOTAL PRIORITY PROJECTSTOTAL ALL PROJECTS

UN

IVER

SITY

STA

TIO

N Z

ON

EU

NI.

PARK

CO

NN

ECTI

VIT

Y ZO

NE

COLO

. STA

TIO

N Z

ON

E

1

PAGE

PRIORITY

3

PRIORITY

3 PRIORITY

3

PRIORITY

3

PRIORITY

3

PRIORITY

3

PRIORITY

2PRIORITY

2PRIORITY

1PRIORITY

1

PRIORITY

1PRIORITY

1PRIORITY

1PRIORITY

1PRIORITY

1

PRIORITY

1PRIORITY

1

PRIORITY

1N

A

E

F

G

H

J

K

P

I

M

L

O 1O 2O 3

O 4

O 5O 6

$8.55M

$18.65M

Page 6: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

6

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

EVANS AVEFI

LMO

RE S

T

CLAY

TON

ST

UN

IVER

SITY

BLV

D

JOSE

PHIN

E ST

JOSE

PHIN

E ST

COLU

MBI

NE

ST

CLAY

TON

ST

FILM

ORE

ST

ASBURY AVE

JEWELL AVE

MEXICO AVE MEXICO AVE

IOWA AVE

COLORADO AVE

Cycle Track

Clayton Ave Crossing

IO4

UNIVERSITY PARK CONNECTIVITY ZONE

UNIVERSITY PARK CONNECTIVITY ZONE

University Blvd. - Colorado Blvd.

Franklin & Buchtel

Cycle Track

Cycle Track

Cycle Track

Mid-block Crossing

University & Buchtel

University & Asbury

University & Evans

A

F

G

H

O

O

OE

1

2

3

UNIVERSITY STATION ZONE

UNIVERSITY STATION ZONE

High St. Roundabout - Garage

Garage - University Blvd.

Franklin St. - High St.

Page 7: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

7MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

EVANS AVE

COLO

RAD

O B

LVD

JACK

SON

ST

GARF

IELD

ST

MAD

ISO

N S

T

COO

K ST

ADAM

S ST

STEE

LE S

T

ST. P

AUL

ST

MIL

WAU

KEE

STM

ILW

AUKE

E ST

ST. P

AUL

ST

ADAM

S ST

COO

K ST

MAD

ISO

N S

T

MO

NRO

E ST

JACK

SON

ST

JEWELL AVE

COLORADO AVE

MEXICO AVE

IOWA AVE

Colorado & Buchtel

Colorado & Evans

CO Cntr. Bike Connection

Cycle Track

CO Cntr. North Frontage Rd.

M

L

N

O O5 6

COLORADO STATION ZONE

COLORADO STATION ZONE

Colorado Blvd. - I-25 Ped Bridge

Colorado Blvd. - I-25 Ped Bridge

Asbury Ave Corridor

St. Paul & Buchtel

Monroe & Buchtel

P

J

K

UNIVERSITY PARK CONNECTIVITY ZONE

UNIVERSITY PARK CONNECTIVITY ZONE

Page 8: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

NEXT STEPS STUDY

UNIVERSITY STATION ZONE

Page 9: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

9MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

The intersection of Franklin Street and Buchtel Boulevard marks the westernmost edge of the proposed two-way cycle track. A complete intersection reconstruction is required in order to match the new street design of Buchtel, while maintaining the existing 12 ft. shared use path on the north side of Buchtel. Two-stage bike boxes are installed at three legs of the intersection, providing clear stopping zones for bicyclists transitioning from the adjacent, directional bike facilities.

• Long-term focus project that connects cycle track facility to existing bike routes at Franklin.

• Lower priority because existing shared use path currently provides a bicycle connection.

• Requires coordination amongst Regional Transportation District (RTD) and City of Denver to resolve ROW issues.

INTERSECTION: FRANKLIN ST. & BUCHTEL BLVD.PROJECT

PRIORITY3

2 way cycle track begins

2 stage bike boxes installed

Existing median to be removed

12 ft. shared use path to remain

One WB lane removed, curb to curb measurement reduced

BUCHTEL

FRAN

KLIN

PROJECT KEY MAP

OPINION OF PROBABLE COST

$1.1M

TIMING & DEPENDENCIESPROJECT DESCRIPTION

A

A

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 10: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

10

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

CYCLE TRACK: FRANKLIN ST. TO HIGH ST.OPROJECT

PROJECT KEY MAP

Section 1 of the proposed two-way cycle track spans 1,050 ft. from Franklin Street to High Street. Significant construction elements include removal and rebuild of the existing median. Vehicle lanes are reduced in this section to one in each direction, creating more space for pedestrian and bicycle mobility and encouraging slower traffic speeds. Design in this segment maintains the existing 12 ft. path on the north side of Buchtel Boulevard and widens the south side sidewalk to 8 ft.

PROJECT DESCRIPTION

1

O1

OPINION OF PROBABLE COST

$1.6M

• Franklin & Buchtel intersection (PROJECT A) should be constructed in conjunction with this section of cycle track.

• Lower priority because existing shared use path currently provides a safe bicycle connection.

PRIORITY3

TIMING & DEPENDENCIES

(LOOKING EAST)

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 11: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

11MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

CYCLE TRACK: HIGH ST. TO DU STATION & ROUNDABOUTOPROJECT

Single lane roundabout to be installed

Reconfigured access to RTD garage and new signal installed

Street section includes permeable pavement in parking lanes

Bus activity relocated to curbside

Access to University Station Apts. remains unchanged

New Station Area Plaza

+/- 30,000 SF

PROJECT KEY MAP

HIGH

BUCHTEL

Construction of a single lane, urban roundabout at High Street and Buchtel Boulevard creates the opportunity to re-imagine the station area plaza and reconfigure vehicle access to the station parking garage. RTD Bus operations move to a curbside location and could integrate with an enhanced mobility hub. Vehicle travel lanes are reduced to one in each direction to match new roadway from Franklin Street to High Street. A new, signalized intersection marks the entrance to the station parking garage and creates a more defined and safer pedestrian crossing to DU’s Cable Center and other campus activities.

PROJECT DESCRIPTION

2

O2

OPINION OF PROBABLE COST

$2.3M

• Cycle track could be installed without roundabout construction

• Roundabout construction is needed to change access to garage and accommodate RTD operations

• Final design should compliment DU Master Plan efforts and its overall vision for the corridor.

PRIORITY2

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 12: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

12

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

CYCLE TRACK: DU STATION TO UNIVERSITY BLVD.OPROJECT

PROJECT KEY MAP

Extending from east edge of station’s parking garage to University Boulevard, Cycle Track Section 3 creates a street section that accommodates both the daily activity and special event needs of DU while providing multi-modal connectivity. Permeable pavement could be included at on-street parking locations and the 12 ft. sidewalk is maintained on the north side of Buchtel Boulevard.

PROJECT DESCRIPTION

3

O3

OPINION OF PROBABLE COST

$1.6M

• Final design should compliment DU Master Plan efforts and its overall vision for the corridor.

• Should be constructed in conjunction with intersection improvements at Buchtel & University (PROJECT F)

PRIORITY2

TIMING & DEPENDENCIES

(LOOKING EAST)

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 13: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

13MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

• Primary focus project due to its relative low cost and importance for creating another pedestrian crossing near DU and RTD Station.

• Recommended to be constructed at same time as Cycle Track Section 3 (PROJECT O3) which removes median and reconstructs curb line, but could be installed independently of cycle track.

PRIORITY1

Signing treatments alert drivers to mid-block crossing

Signing treatments follow Denver guidelines

'Shark tooth' striping reinforces stopping location for drivers

Removal of existing median as part of PROJECT O3

Location connects RTD Station and DU campus

DU Ritchie Center / Cable Center Parking Lot

TIMING & DEPENDENCIES

E MID-BLOCK PEDESTRIAN CROSSING AT DU RITCHIE CENTER

PROJECT KEY MAP

E

The RTD station and several large apartment buildings sit just north of DU campus across Buchtel Boulevard between High Street and University Boulevard. However, with no marked crossing along this 1,700 ft. stretch, many visitors cross Buchtel Boulevard at the mid-block in order to access campus activities.Project E proposes a mid-block ‘Z’ crossing across Buchtel Boulevard, connecting to DU Ritchie Center and intra-campus pedestrian paths. The ‘Z’ crossing forces walkers to shift their vision towards oncoming traffic, providing clear vehicle visibility before making a crossing decision.

PROJECT DESCRIPTION

PROJECT

OPINION OF PROBABLE COST

$150K

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 14: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

14

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

Buchtel Boulevard and University Boulevard undergo significant safety enhancements for both pedestrians and vehicles in this reconstruction project. East of University Boulevard, Buchtel Boulevard is realigned to reduce the angle at which vehicles approach the intersection. The roadway realignment avoids impacts to designated parkland at Prairie Park and concept investigations reveal no ROW acquisition cost is required. Intersection reconstruction includes removing one thru lane of traffic on Buchtel Boulevard and changing traffic signalization to include controlled right turns and a protected bike phase.

INTERSECTION: UNIVERSITY BLVD. & BUCHTEL BLVD.PROJECT F

• Top priority project based on safety improvements and community input.

• Signal phasing and intersection realignment should be completed in conjunction with cycle track.

• Requires coordination with Denver Parks & Recreation.

PRIORITY1

TIMING & DEPENDENCIES

Added right turn lane allows signal phasing strategy

that controls right turns to reduce auto/bike conflicts

Lanes at intersection throat reduced to one left turn and one thru/right

Detached sidewalks maintained throughout design

New raised median created

One thru lane removed on Buchtel, both left turns onto University remain

Removed channelized right turns on north and south approaches

Prairie Park Designated Park Land

Red right turn arrow controls auto movement during green bike phase UN

IVER

SITY

BUCHTEL

PROJECT KEY MAP

OPINION OF PROBABLE COST

$2.0M

PROJECT DESCRIPTION

F

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 15: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

15MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

G INTERSECTION: UNIVERSITY BLVD. & ASBURY AVE.PROJECT

Right and left turn lanes removed

New bulb-outs reduces pedestrian crossing distances

No changes to existing University Blvd roadway

ASBURY

UNIV

ERSI

TY

PROJECT KEY MAP

G

Asbury Avenue is a key neighborhood connector running through the heart of DU campus. This redesigned intersection at Asbury Avenue and University Boulevard shortens pedestrian crossing distances and encourages slower speeds through the neighborhood while maintaining north-south traffic conditions on University Boulevard. Bulb-outs on the north side of Asbury Avenue provide additional water quality intervention opportunities and shadows on-street parking. Serving as an informal entry to DU campus, this new intersection becomes safer and more comfortable for pedestrians.

PROJECT DESCRIPTION

OPINION OF PROBABLE COST

$600K

• Final design of intersection should not be undertaken until adoption of DU Master Plan

PRIORITY3

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 16: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

16

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

OPTION A INTERSECTION: UNIVERSITY & EVANSH

Identified conflict zone

Right turn lane removed

Right turn lane removed

Pedestrian crossing distances shortened

EVANS

UNIV

ERSI

TY

PROJECT KEY MAP

H

Pedestrian counts conducted on May 25, 2017 revealed 1,500 people crossing this intersection of arterial roadways between 11:00AM and 1:00PM. This reinforces the importance of prioritizing pedestrian safety improvements at this intersection.This reconstruction project tightens the intersection at all four approaches, bringing the pedestrian crossing distances down to 56 ft. To accommodate this change, right turn lanes are removed along Evans Avenue, both eastbound and westbound. RTD bus stop is moved slightly north to accept on-street boarding along the new curb line.

PROJECT DESCRIPTION

PROJECT

OPINION OF PROBABLE COST

$1.5M

PRIORITY1

TIMING & DEPENDENCIES• Options A and B are both valid alternatives

for this intersection. Further coordination is required between Denver Public Works and DU.

• Top priority project based on critical safety improvements at a high crash intersection.

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 17: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

17MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

OPTION B INTERSECTION: UNIVERSITY & EVANSHAdded right turn lane allows signal phasing strategy to control right turns and reduces auto/ped conflicts

Identified conflict zone

Current RTD bus operations unchanged

Bulb outs shorten crossing distances for peds

Current landscaping and tree locations remain

Red right turn arrow controls auto movement during ped walk phase

EVANS

UNIV

ERSI

TY

PROJECT KEY MAP

H

Pedestrian counts conducted on May 25, 2017 revealed 1,500 people crossing this intersection of arterial roadways between 11:00AM and 1:00PM. his reinforces the importance of prioritizing pedestrian safety improvements at this intersection.This intersection reconstruction project adds a right turn lane at southbound University Boulevard, allowing traffic signal phasing to control all right turns with red arrows and giving pedestrians a designated crossing phase. Crossing distances are also shortened by creating larger sidewalks on the northeast and northwest corners.

PROJECT DESCRIPTION

PROJECT

OPINION OF PROBABLE COST

$1.5M

• Options A and B are both valid alternatives for this intersection. Further coordination is required between Denver Public Works and DU.

• Top priority project based on critical safety improvements at a high crash intersection.

PRIORITY1

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 18: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

NEXT STEPS STUDY

UNIVERSITY PARK CONNECTIVITY ZONE

Page 19: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

19MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

I PEDESTRIAN CROSSING AT CLAYTON & BUCHTEL

Back of existing sidewalks remain unchanged

Signing treatments follow Denver guidelines

New high-visibility crosswalk markingsAdditional conflict markings for cycle track crossing

Shortened pedestrian crossing

PROJECT KEY MAP

I

Providing better neighborhood access to Historic Buchtel Trail and Prairie Park, this new pedestrian crossing at Clayton Street can also calm traffic along Buchtel Boulevard. Engagement with local residents and neighborhood advocates identified this location as most desirable, sitting halfway between St Paul Street and University Boulevard. Design elements at this crossing are consistent with Denver’s Uncontrolled Pedestrian Crossing Guidelines (2016) for Level A treatments and include signing and striping improvements.

PROJECT DESCRIPTION

PROJECT

OPINION OF PROBABLE COST

• High priority project due to community input, relative ease of implementation, and low cost.

• Mid-block crossing treatments could be installed independently of cycle track construction.

• Recommended to be coordinated with associated interventions at Clayton & Asbury (PROJECT P) and Cycle Track Section 4 (PROJECT O4)

PRIORITY1

TIMING & DEPENDENCIES

CLAY

TON

BUCHTEL

$50K

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 20: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

20

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

O CYCLE TRACK: UNIVERSITY BLVD. TO COLORADO BLVD.PROJECT

PROJECT KEY MAP

This stretch of cycle track connects University Boulevard and Colorado Boulevard, spanning the full distance of the University Park Neighborhood. Replacing the existing directional bike facility, the southside cycle track minimizes impacts to the nature and use of Historic Buchtel Trail and facilitates safe crossings of University Boulevard and Colorado Boulevard. The southside location also connects directly with DU on the west, and the pedestrian bridge over I-25 on the east. Sidewalks on the south side are widened to 8 ft., replacing 3 ft. ‘rollover’ sidewalks in many locations.

PROJECT DESCRIPTION

4

O4

OPINION OF PROBABLE COST

$1.8M

• High priority project because of neighborhood and community benefits and importance to overall connectivity for both RTD stations.

• Coordination with Denver Parks & Recreation and Forestry required to ensure health of existing trees.

• Further analysis of cross-street conflicts needed.

PRIORITY1

TIMING & DEPENDENCIES

(LOOKING EAST)

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 21: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

21MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

J INTERSECTION: SAINT PAUL AVE. & BUCHTEL BLVD.PROJECT

Two stage bike box helps transition to St. Paul neighborhood bikeway

New high-visibility crosswalk markings for N/S crossing

Curb reconstructed to accomodate N/S crossing

Back of existing sidewalks remain unchanged

Shortened pedestrian crossing

ST. P

AUL

BUCHTEL

PROJECT KEY MAP

J

To accommodate the two-way cycle track and improve pedestrian safety, the intersection at St. Paul Avenue and Buchtel Boulevard is reconstructed. A two-stage bike box is installed to help bicyclists transition between the cycle track and the neighborhood bikeway along St. Paul / Steele Avenues. New high-visibility, north-south crosswalks across Buchtel Boulevard, create better connections to the Historic Buchtel Trail.Enhanced signage and pedestrian signals are also installed to improve pedestrian visibility and safety.

PROJECT DESCRIPTION

OPINION OF PROBABLE COST

$400K

• Intersection improvements should be implemented at same time Cycle Track Section 4 (PROJECT O4) is constructed.

• Construction and design should be coordinated with Denver Parks & Recreation and Forestry to ensure health of existing trees.

PRIORITY1

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 22: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

22

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

K INTERSECTION: MONROE ST. & BUCHTEL BLVD.

Intersection reconstructed to eliminate 'pork chop islands'and reduce right turn speeds

Pedestrian crossing is simplified and shortened

Existing Asbury & Monroe connection remains unchanged

High-visibility continental crosswalk markings at all approaches

Signing treatments follow Denver guidelines

BUCHTEL

ASBURY

K

Crossing Monroe Street becomes significantly easier in this intersection reconstruction. Free right turn ‘pork chop’ islands are removed from Monroe Street to reduce vehicle turning speeds and total crossing distance of Monroe Street is reduced from 115 ft. to 32 ft. This new crossing for pedestrians and bicyclists limits vehicle conflicts and encourages slower speeds along the entire Buchtel corridor, reducing its appeal as an alternative to I-25. A longer-term and more complex alternative to this project includes removing the median on Monroe to allow full vehicle movements at Asbury Avenue.

PROJECT DESCRIPTION

PROJECT KEY MAP

PROJECT

OPINION OF PROBABLE COST

$300K

• High priority project due to community input and critical safety improvements associated with cycle track and street crossings.

• Should be constructed with associated cycle track section (PROJECT O4)

PRIORITY1

TIMING & DEPENDENCIES

MO

NRO

E

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 23: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

23MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

P ASBURY AVENUE NEIGHBORHOOD CONNECTOR

Neighborhood traffic calming circles installed

* Project improvements extend from University to Monroe. Graphic is illustrative of similar improvements along entire corridor.

Raised table crossings installed

North side sidewalks widened to 8 ft.

Enhanced pedestrian crossings connect to improvements along Buchtel Blvd.

Sidewalk networks repaired where necessary

PROJECT KEY MAP

P

Extending through DU campus and the University Park Neighborhood, improvements to Asbury Avenue prioritize pedestrians and bicyclists. Traffic calming devices (raised table crossings and neighborhood traffic circles) are coupled with a completed sidewalk network to create a comfortable and attractive neighborhood walk. Crossings of Asbury Avenue are strategically located to leverage improvements along Buchtel Boulevard and reinforce pedestrian access to Historic Buchtel Trail, Prairie Park, and the new cycle track. Project extends along Asbury from University Blvd. to Monroe St.

PROJECT DESCRIPTION

PROJECT

OPINION OF PROBABLE COST

$700K

CLAY

TON

COLU

MBI

NE

• Long-term priority project, but improvements may be phased based on funding availability or adjacent development.

• Specific traffic calming devices or pedestrian crosswalk types may be altered with further traffic analysis or community input.

PRIORITY3

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURYBUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 24: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

NEXT STEPS STUDY

COLORADO STATION ZONE

Added southbound left turn lane for local vehicle access

Page 25: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

25MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

M COLORADO CENTER NORTH ACCESS

Vehicle acceleration lane removed

Realigned right turn lane provides for more direct pedestrian crossing

Raised table crossing installed

Enhanced wayfinding for vehicles promotes north entrance to Colorado CenterAdded southbound left turn lane for local vehicle access

Colorado CenterProperty Line

PROJECT KEY MAP

M

North of Colorado Center Drive, the S. Frontage Road is an underutilized access point to the shops, offices, and residences at Colorado Center. Intersection reconstruction and additional wayfinding adds emphasis to this approach to Colorado Center, taking some vehicle traffic off Colorado Center Drive and complementing its enhanced future pedestrian and bicycle facilities (PROJECT O6).Realigning the right turn lane from Colorado Boulevard to S. Frontage Road also encourages slower vehicle speeds and provides more direct pedestrian crossings.

PROJECT DESCRIPTION

Colorado CenterUA Theatre & IMAX

S FRONTAGE RD

COLO

RADO

I-25 EXIT 204

SB I-25 RAMP

PROJECT

OPINION OF PROBABLE COST

$1.0M

• Lower project priority due to coordination complexities.

• Project needs to coordinate with Colorado Department of Transportation (CDOT) for roadway alignment, drainage facilities and potential traffic operations impacts.

• Project may be funded with adjacent development.

PRIORITY3

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 26: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

26

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

L INTERSECTION: COLORADO BLVD. & BUCHTEL BLVD.PROJECT

Added bulbout reduces crossing distance

New raised median constructed

Graphic shows cycle track continuing to I-25 bridge, as described in PROJECT O6

Project includes signal phasing strategy

that controls right turns and reduces auto/bike conflicts

One thru lane removed to accomodate cycle track

Red right turn arrow controls auto movement during green bike phase

L

A key consideration in locating the cycle track on the south side of Buchtel Boulevard is providing a safe passage for bicyclists across Colorado Boulevard. This strategy includes adding an exclusive bike/ped phase to the signal timing at this intersection. A single eastbound thru lane is removed to accommodate the cycle track, and bulbouts are added on the north side of Buchtel Boulevard to shorten the crossing distance of Colorado Boulevard. A raised median is added to the south leg of the intersection to improve bicycle and pedestrian mobility.

PROJECT DESCRIPTION

PROJECT KEY MAP

OPINION OF PROBABLE COST

$900K

• High priority project due to community input and critical safety improvements associated with cycle track and street crossings.

• Further coordination with CDOT is necessary.

PRIORITY1

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 27: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

27MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

O COLORADO CENTER DRIVE BICYCLE CONNECTION

PROJECT KEY MAP

This project keeps bus operations on Colorado Center Drive and constructs an 8-10 ft. shared use path that connects the Buchtel Boulevard cycle track from Colorado Boulevard to the I-25 pedestrian bridge. In order to reduce transit riders conflict with bicycles, this design assumes that the RTD lot is used as a shared use facility on the north end. Removal or modification of the eastbound right turn lane from Colorado Center Drive to Birch Street should be considered to create more pedestrian and bicycle space.

PROJECT DESCRIPTION

5

Possible intersection reconfiguration to remove right turn island

10' shared use path

Connection to I-25 pedestrian bridge

No changes to existing street section or RTD bus operations

New signing directs users to path

Path transitions to shared lane markings through RTD parking lot

PROJECT

O 5

OPINION OF PROBABLE COST

• High priority project that helps connect Colorado Station and University Station and leverages I-25 pedestrian bridge investment.

• Design must be coordinated with RTD and Colorado Center to ensure safe and conflict-free shared use path connection while maintaining efficient bus operations.

PRIORITY1

TIMING & DEPENDENCIES

$250K

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 28: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

28

NEXT STEPS STUDY

MULTI STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

CYCLE TRACK: COLORADO CENTER DRIVEOPROJECT

PROJECT KEY MAP

In this ‘ultimate’ condition, RTD bus operations are moved south of the station platform in conjunction with redevelopment of the existing parking lot and adjacent sites. One westbound drive lane is removed in order to provide a consistent bicycle connection to the I-25 pedestrian bridge and maintain 8 ft. sidewalks along both sides of Colorado Center Drive.On-street parking is also added to Colorado Center Drive to support potential future ground floor retail and to enable a 'main street' type of environment.

PROJECT DESCRIPTION

6

O 6

OPINION OF PROBABLE COST

$1.2M

• Long-term priority project that assumesexisting RTD Park-N-Ride is redeveloped and bus operations move off Colorado Center Drive.

• Should be coordinated with larger developmentstrategy for area south of Colorado Center betweenEvans and I-25.

PRIORITY3

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 29: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

29MULTI-STATION PLAN & MOBILITY STUDY - UNIVERSITY & COLORADO STATIONS

NEXT STEPS STUDY

N INTERSECTION: COLORADO BLVD. & EVANS AVE.PROJECT

New right turn lanes angled to allow increased viewing distance between vehicles and pedestrians

Large pedestrian refuge islands created

New raised median constructed

Raised table crossing slows traffic on channelized right turns

PROJECT KEY MAP

COLO

RAD

O

EVANS

N

Both Colorado Boulevard and Evans Avenue are busy arterial roadways that play critical roles in the overall transportation network. Adjacent land uses include auto-oriented retail, but newer residential developments are expected to attract more pedestrian and bicycle traffic. Elements of this intersection redesign include increased sight distances for right turning vehicles and large pedestrian refuge islands. Design accommodates current RTD bus operations and traffic conditions along both roads.

PROJECT DESCRIPTION

OPINION OF PROBABLE COST

$1.2M

• High priority project due to community input and critical safety improvements associated with key intersection.

PRIORITY1

TIMING & DEPENDENCIES

HIG

H

UN

IVER

SITY

ST. P

AUL

EVANS

ASBURY

BUCHTEL

MO

NRO

E

COLO

RAD

O

FRAN

KLIN

Page 30: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

APPENDIX II

NEXT STEPS STUDYSUPPORTING DOCUMENTS

Page 31: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

TO: Chris Vogelsang, PE FROM: Chessy Brady, RTD DATE: 08/03/17 RE: Response to memo of 6/30/17 titled “Future Bicycle Connection Opportunities

near Colorado Station”

We have reviewed your memo and have assembled a summary of concerns and recommendations from across many RTD departments.

Concerns: Several departments agree that mixing pedestrians, bicyclists and buses in a small space threatens the safety of the station area. With high bus activity surrounding the plaza and parking area, the proximity of Alignments A and B to the bus bays could increase the risk of bike/pedestrian collisions and serious accidents. It is preferred that areas in close proximity to RTD transit platforms be “walk your bike” zones; this applies to all 3 alignments. The layout at US36 & McCaslin, for example, has generated complaints, particularly from an ADA perspective.

Additionally, the Planning Department is concerned that Alignments A and B would require several infrastructure changes such as relocating the bus bays and TVMs.

The Rail Operations Department has concerns about Alignment C because the path would run through the traction power substation yard. As drawn, this would present security issues and limit access to the north side of the substation.

Recommendations: Capital Programs recommends the separation of bike and pedestrian movements by keeping the multi-use trail off/out of the plaza area altogether to avoid any bike/pedestrian conflicts. Capital Programs is also curious to see how the connection through the Colorado Boulevard intersection would lay out.

Several departments recommended replacing a westbound lane with a protected two-way bike facility on the north side of Colorado Center Drive. Center-running bike lanes were also mentioned.

The Safety, Security and Asset Management Department recommends moving the bicycle path south towards Evans before turning back north to the pedestrian bridge.

Takeaways: • Alignments A and B cause the greatest number of concerns across RTD departments.

• Alignment C does not create the same level of concern but exact routing could eliminateit as an option if it infringes too much on the substation yard, disrupts bus movementson Birch, or is determined to be unsafe for pedestrians. Special care would have to betaken in running the route between the PnR and the sidewalk to avoid ped/bikecollisions. Note that in the case of Alignment C, the path could just be a bike lane for

Page 32: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

most of the distance, not necessarily a shared use path; perhaps 10’ width is unnecessary, especially at the tightest points.

• Placing the bike lanes on the north side of Colorado Center Drive reduces concernsabout bike/ped/bus interactions but does not eliminate them because there are buses onthe north side as well.

• Sharrows or on-street bike lanes on Colorado Center Drive would be less desirable froma biker perspective, but would cause fewer issues to RTD than the other options.

Page 33: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

1

Max Lubarsky

From: Burton, Adrienne B. - DPR PARKS Plan Design & Build Project Mgmt <[email protected]>

Sent: Wednesday, July 5, 2017 9:52 AMTo: Chris VogelsangCc: Max LubarskySubject: RE: Buchtel - Prairie Park Designated park Land

Categories: CC Message

Hi Chris, 

You are correct that designated park land cannot be used for public roadway improvements, however, a sidewalk would most likely be an acceptable addition contingent upon Parks review.  Also, Parks does maintain the current Buchtel trail.  

Let me know if you have any questions! 

Thanks, 

Adrienne Burton, PLA, LEED AP ND | West Denver Parks Planner Planning, Design & Construction, Parks & Recreation | City and County of Denver p: (720) 913-0627 | [email protected] 

From: Chris Vogelsang [mailto:[email protected]]  Sent: Wednesday, June 28, 2017 2:35 PM To: Burton, Adrienne B. ‐ DPR PARKS Plan Design & Build Project Mgmt <[email protected]> Cc: Max Lubarsky <[email protected]> Subject: Buchtel ‐ Prairie Park Designated park Land 

Adrienne‐ we’ve reviewed the materials DPR provided and see that our concept level improvements would impact Designated Park Land at the University/Buchtel intersection.  I wanted to confirm that your opinion is that Designated Park Land can’t be used for public roadway improvements.  Max and I were thinking about Cheeseman Park’s situation with RTD and the traveling public using 12th Ave through the Park and just want to confirm for sure that no part of the Designated Park Land can be used.  Even if we could put a concrete sidewalk in the Designated Park Land as part of the Buchtel Trail that would be something useful for us to know as it would provide a little more room for us to work with in improving the University/Buchtel intersection or peds and bikes.  Maybe that would be possible as long as DPR owned and maintained the concrete path?  I’m not even sure who currently maintains the Buchtel Trail.  It’s in the Park boundary but is not inside the Designated Park Land boundary based on the exhibit DPR provided. 

Drop me a line and let me know your thoughts.  We can chat on the phone if that is easier. 

Thanks. 

Chris Vogelsang, PE 

Page 34: APPENDIX I NEXT STEPS STUDY · 2 way cycle track begins 2 stage bike boxes installed Existing median to be removed ... the entrance to the station parking garage and creates a

2

OV Consulting 1200 Bannock St Denver, CO 80204 303‐898‐8042 [email protected]