application manual reu611 voltage protection and control · 2019-05-16 · the protection and...
TRANSCRIPT
![Page 1: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/1.jpg)
—RELION® 611 SERIES
Voltage Protection and ControlREU611Application Manual
![Page 2: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/2.jpg)
![Page 3: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/3.jpg)
Document ID: 1MRS758335Issued: 2019-04-10
Revision: DProduct version: 2.0
© Copyright 2019 ABB. All rights reserved
![Page 4: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/4.jpg)
Copyright
This document and parts thereof must not be reproduced or copied without writtenpermission from ABB, and the contents thereof must not be imparted to a third party,nor used for any unauthorized purpose.
The software or hardware described in this document is furnished under a license andmay be used, copied, or disclosed only in accordance with the terms of such license.
TrademarksABB and Relion are registered trademarks of the ABB Group. All other brand orproduct names mentioned in this document may be trademarks or registeredtrademarks of their respective holders.
WarrantyPlease inquire about the terms of warranty from your nearest ABB representative.
www.abb.com/relion
![Page 5: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/5.jpg)
Disclaimer
The data, examples and diagrams in this manual are included solely for the concept orproduct description and are not to be deemed as a statement of guaranteed properties.All persons responsible for applying the equipment addressed in this manual mustsatisfy themselves that each intended application is suitable and acceptable, includingthat any applicable safety or other operational requirements are complied with. Inparticular, any risks in applications where a system failure and/or product failurewould create a risk for harm to property or persons (including but not limited topersonal injuries or death) shall be the sole responsibility of the person or entityapplying the equipment, and those so responsible are hereby requested to ensure thatall measures are taken to exclude or mitigate such risks.
This product has been designed to be connected and communicate data andinformation via a network interface which should be connected to a secure network.It is the sole responsibility of the person or entity responsible for networkadministration to ensure a secure connection to the network and to take the necessarymeasures (such as, but not limited to, installation of firewalls, application ofauthentication measures, encryption of data, installation of anti virus programs, etc.)to protect the product and the network, its system and interface included, against anykind of security breaches, unauthorized access, interference, intrusion, leakage and/ortheft of data or information. ABB is not liable for any such damages and/or losses.
This document has been carefully checked by ABB but deviations cannot becompletely ruled out. In case any errors are detected, the reader is kindly requested tonotify the manufacturer. Other than under explicit contractual commitments, in noevent shall ABB be responsible or liable for any loss or damage resulting from the useof this manual or the application of the equipment.
![Page 6: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/6.jpg)
Conformity
This product complies with the directive of the Council of the European Communitieson the approximation of the laws of the Member States relating to electromagneticcompatibility (EMC Directive 2014/30/EU) and concerning electrical equipment foruse within specified voltage limits (Low-voltage directive 2014/35/EU). Thisconformity is the result of tests conducted by ABB in accordance with the productstandard EN 60255-26 for the EMC directive, and with the product standards EN60255-1 and EN 60255-27 for the low voltage directive. The product is designed inaccordance with the international standards of the IEC 60255 series.
![Page 7: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/7.jpg)
Table of contents
Section 1 Introduction.......................................................................3This manual........................................................................................ 3Intended audience.............................................................................. 3Product documentation.......................................................................4
Product documentation set............................................................4Document revision history............................................................. 4Related documentation..................................................................5
Symbols and conventions...................................................................5Symbols.........................................................................................5Document conventions..................................................................6Functions, codes and symbols...................................................... 6
Section 2 REU611 overview.............................................................9Overview.............................................................................................9
Product version history..................................................................9PCM600 and relay connectivity package version..........................9
Operation functionality......................................................................10Optional functions........................................................................10
Physical hardware............................................................................ 10Local HMI......................................................................................... 11
Display.........................................................................................12LEDs............................................................................................13Keypad........................................................................................ 13
Web HMI...........................................................................................14Command buttons....................................................................... 15
Authorization.....................................................................................16Audit trail......................................................................................17
Communication.................................................................................19Self-healing Ethernet ring............................................................20Ethernet redundancy................................................................... 21Secure communication................................................................23
Section 3 REU611 standardized configuration ............................. 25Standardized configuration...............................................................25Switch groups................................................................................... 26
Input switch group ISWGAPC..................................................... 26Output switch group OSWGAPC.................................................27Selector switch group SELGAPC................................................ 27
Connection diagrams........................................................................29Configuration A.................................................................................31
Table of contents
REU611 1Application Manual
![Page 8: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/8.jpg)
Applications................................................................................. 31Functions.....................................................................................32
Default I/O connections.......................................................... 32Predefined disturbance recorder connections........................33
Functional diagrams ................................................................... 33Functional diagrams for protection......................................... 34Functional diagrams for disturbance recorder and tripcircuit supervision ..................................................................39Functional diagrams for control ............................................. 41
Switch groups .............................................................................43Binary inputs ..........................................................................44Internal signal ........................................................................ 48Binary outputs and LEDs .......................................................49GOOSE.................................................................................. 67
Section 4 Protection relay's physical connections..........................69Inputs................................................................................................69
Energizing inputs.........................................................................69Phase voltage.........................................................................69Residual voltage.....................................................................69
Auxiliary supply voltage input...................................................... 69Binary inputs................................................................................70
Outputs............................................................................................. 70Outputs for tripping and controlling..............................................70Outputs for signalling...................................................................71IRF...............................................................................................71
Section 5 Glossary......................................................................... 73
Table of contents
2 REU611Application Manual
![Page 9: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/9.jpg)
Section 1 Introduction
1.1 This manual
The application manual contains application descriptions and setting guidelinessorted per function. The manual can be used to find out when and for what purpose atypical protection function can be used. The manual can also be used when calculatingsettings.
1.2 Intended audience
This manual addresses the protection and control engineer responsible for planning,pre-engineering and engineering.
The protection and control engineer must be experienced in electrical powerengineering and have knowledge of related technology, such as protection schemesand principles.
1MRS758335 D Section 1Introduction
REU611 3Application Manual
![Page 10: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/10.jpg)
1.3 Product documentation
1.3.1 Product documentation set
Pla
nnin
g &
pu
rcha
se
Eng
inee
ring
Inst
alla
tion
Com
mis
sion
ing
Ope
ratio
n
Mai
nten
ance
Dec
omm
issi
onin
g,
dein
stal
latio
n &
dis
posa
l
Quick start guideQuick installation guideBrochureProduct guideOperation manualInstallation manualConnection diagramEngineering manualTechnical manualApplication manualCommunication protocol manualIEC 61850 engineering guidePoint list manualCyber security deployment guideline
GUID-0777AFDA-CADF-4AA9-946E-F6A856BDF75E V1 EN
Figure 1: The intended use of manuals in different lifecycles
Product series- and product-specific manuals can be downloadedfrom the ABB Web site http://www.abb.com/relion.
1.3.2 Document revision historyDocument revision/date Product version HistoryA/2016-02-22 2.0 First release
B/2016-10-11 2.0 Content updated
C/2017-10-31 2.0 Content updated
D/2019-04-10 2.0 Content updated
Download the latest documents from the ABB Web sitehttp://www.abb.com/substationautomation.
Section 1 1MRS758335 DIntroduction
4 REU611Application Manual
![Page 11: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/11.jpg)
1.3.3 Related documentationName of the document Document IDModbus Communication Protocol Manual 1MRS757461
IEC 61850 Engineering Guide 1MRS757465
Engineering Manual 1MRS241255
Installation Manual 1MRS757452
Operation Manual 1MRS757453
Technical Manual 1MRS757454
Cyber Security Deployment Guideline 1MRS758337
1.4 Symbols and conventions
1.4.1 Symbols
The electrical warning icon indicates the presence of a hazard whichcould result in electrical shock.
The warning icon indicates the presence of a hazard which couldresult in personal injury.
The caution icon indicates important information or warning relatedto the concept discussed in the text. It might indicate the presence ofa hazard which could result in corruption of software or damage toequipment or property.
The information icon alerts the reader of important facts andconditions.
The tip icon indicates advice on, for example, how to design yourproject or how to use a certain function.
Although warning hazards are related to personal injury, it is necessary to understandthat under certain operational conditions, operation of damaged equipment may resultin degraded process performance leading to personal injury or death. Therefore,comply fully with all warning and caution notices.
1MRS758335 D Section 1Introduction
REU611 5Application Manual
![Page 12: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/12.jpg)
1.4.2 Document conventions
A particular convention may not be used in this manual.
• Abbreviations and acronyms are spelled out in the glossary. The glossary alsocontains definitions of important terms.
• Push button navigation in the LHMI menu structure is presented by using thepush button icons.To navigate between the options, use and .
• Menu paths are presented in bold.Select Main menu/Settings.
• LHMI messages are shown in Courier font.To save the changes in nonvolatile memory, select Yes and press .
• Parameter names are shown in italics.The function can be enabled and disabled with the Operation setting.
• Parameter values are indicated with quotation marks.The corresponding parameter values are "On" and "Off".
• Input/output messages and monitored data names are shown in Courier font.When the function starts, the START output is set to TRUE.
• This document assumes that the parameter setting visibility is "Advanced".
1.4.3 Functions, codes and symbolsTable 1: Functions included in the relay
Function IEC 61850 IEC 60617 IEC-ANSIProtection
Residual overvoltage protection,instance 1 ROVPTOV1 Uo> (1) 59G (1)
Residual overvoltage protection,instance 2 ROVPTOV2 Uo> (2) 59G (2)
Residual overvoltage protection,instance 3 ROVPTOV3 Uo> (3) 59G (3)
Three-phase undervoltage protection,instance 1 PHPTUV1 3U< (1) 27(1)
Three-phase undervoltage protection,instance 2 PHPTUV2 3U< (2) 27(2)
Three-phase undervoltage protection,instance 3 PHPTUV3 3U< (3) 27(3)
Three-phase overvoltage protection,instance 1 PHPTOV1 3U> (1) 59(1)
Three-phase overvoltage protection,instance 2 PHPTOV2 3U> (2) 59(2)
Three-phase overvoltage protection,instance 3 PHPTOV3 3U> (3) 59(3)
Positive-sequence undervoltageprotection, instance 1 PSPTUV1 U1< (1) 47U+(1)
Table continues on next page
Section 1 1MRS758335 DIntroduction
6 REU611Application Manual
![Page 13: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/13.jpg)
Function IEC 61850 IEC 60617 IEC-ANSIPositive-sequence undervoltageprotection, instance 2 PSPTUV2 U1< (2) 47U+(2)
Negative-sequence overvoltageprotection, instance 1 NSPTOV1 U2> (1) 47O-(1)
Negative-sequence overvoltageprotection, instance 2 NSPTOV2 U2> (2) 47O-(2)
Frequency protection, instance 1 FRPFRQ1 f>/f<,df/dt (1) 81(1)
Frequency protection, instance 2 FRPFRQ2 f>/f<,df/dt (2) 81(2)
Master trip, instance 1 TRPPTRC1 Master Trip (1) 94/86 (1)
Master trip, instance 2 TRPPTRC2 Master Trip (2) 94/86 (2)
Other
Input switch group1) ISWGAPC ISWGAPC ISWGAPC
Output switch group2) OSWGAPC OSWGAPC OSWGAPC
Selector3) SELGAPC SELGAPC SELGAPC
Minimum pulse timer (2 pcs)4) TPGAPC TP TP
Move (8 pcs), instance 1 MVGAPC MV (1) MV (1)
Control
Circuit-breaker control CBXCBR1 I <-> O CB I <-> O CB
Condition monitoring and supervision
Trip circuit supervision, instance 1 TCSSCBR1 TCS (1) TCM (1)
Trip circuit supervision, instance 2 TCSSCBR2 TCS (2) TCM (2)
Logging
Disturbance recorder RDRE1 DR (1) DFR(1)
Fault recorder FLTRFRC1 - FR
Measurement
Three-phase voltage measurement,instance 1 VMMXU1 3U 3U
Three-phase voltage measurement,instance 2 VMMXU2 3U(B) 3U(B)
Sequence voltage measurement,instance 1 VSMSQI1 U1, U2, U0 U1, U2, U0
Residual voltage measurement RESVMMXU1 Uo Vn
Frequency measurement, instance 1 FMMXU1 f f
1) 10 instances2) 20 instances3) 6 instances4) 10 instances
1MRS758335 D Section 1Introduction
REU611 7Application Manual
![Page 14: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/14.jpg)
8
![Page 15: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/15.jpg)
Section 2 REU611 overview
2.1 Overview
REU611 is a voltage protection relay preconfigured for voltage and frequency-basedprotection in utility substations and industrial power systems. The relay is used for awide variety of applications, including busbar, power transformer, motor andcapacitor bank applications.
REU611 is a member of ABB’s Relion® product family and part of the 611 protectionand control product series. The 611 series relays are characterized by theircompactness and withdrawable-unit design.
The 611 series offers simplified yet powerful functionality for most applications.Once the application-specific parameter set has been entered, the installed protectionrelay is ready to be put into service. The further addition of communicationfunctionality and interoperability between substation automation devices offered bythe IEC 61850 standard adds flexibility and value to end users as well as electricalsystem manufacturers.
The 611 series relays fully support the IEC 61850 standard for communication andinteroperability of substation automation devices, including fast GOOSE (GenericObject Oriented Substation Event) messaging, and can now also benefit from theextended interoperability provided by Edition 2 of the standard. The relays furthersupport the parallel redundancy protocol (PRP) and the high-availability seamlessredundancy (HSR) protocol. The 611 series relays are able to use IEC 61850 andModbus® communication protocols simultaneously.
2.1.1 Product version historyProduct version Product history2.0 Product released
2.1.2 PCM600 and relay connectivity package version
• Protection and Control IED Manager PCM600 Ver.2.7 or later• REU611 Connectivity Package Ver.2.0 or later
• Communication Management• Configuration Wizard• Disturbance Handling• Event Viewer• Fault Record tool
1MRS758335 D Section 2REU611 overview
REU611 9Application Manual
![Page 16: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/16.jpg)
• Firmware Update• HMI Event Filtering• IEC 61850 Configuration• IED Compare• IED Configuration Migration• IED User Management• Label Printing• Lifecycle Traceability• Parameter Setting• Signal Matrix• Signal Monitoring
Download connectivity packages from the ABB Web sitehttp://www.abb.com/substationautomation or directly with UpdateManager in PCM600.
2.2 Operation functionality
2.2.1 Optional functions
• IEEE 1588 time v2 synchronization• High-availability seamless redundancy protocol (HSR)• Parallel redundancy protocol (PRP)
2.3 Physical hardware
The protection relay consists of two main parts: plug-in unit and case. The contentdepends on the ordered functionality.
Section 2 1MRS758335 DREU611 overview
10 REU611Application Manual
![Page 17: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/17.jpg)
Table 2: Plug-in unit and case
Main unit Slot ID Content optionsPlug-in
unit- HMI Small (4 lines, 16 characters)
X100 Auxiliarypower/BO module
48...250 V DC/100...240 V AC; or 24...60 V DC2 normally-open PO contacts1 change-over SO contact1 normally-open SO contact2 double-pole PO contacts with TCS1 dedicated internal fault output contact
Case X130 AI/BI module 3 phase voltage inputs (60...210 V)1 residual voltage input (60...210 V)1 voltage measurement input (60...210 V)4 binary inputs
X000 Optionalcommunicationmodule
See technical manual for details about different type ofcommunication modules.
Rated values of the current and voltage inputs are basic setting parameters of theprotection relay. The binary input thresholds are selectable within the range 16…176V DC by adjusting the binary input setting parameters.
See the installation manual for more information about the case andthe plug-in unit.
The connection diagrams of different hardware modules are presented in this manual.
Table 3: Number of physical connections in configuration
Conf. Analog channels Binary channels CT VT BI BO
A - 5 4 6
2.4 Local HMI
The LHMI is used for setting, monitoring and controlling the protection relay. TheLHMI comprises the display, buttons, LED indicators and communication port.
1MRS758335 D Section 2REU611 overview
REU611 11Application Manual
![Page 18: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/18.jpg)
REF611
Overcurrent
Earth-fault
Phase unbalance
Thermal overload
AR sequence in progress
Disturb.rec.trigged
Trip circuit failure
Breaker failure
GUID-E15422BF-B3E6-4D02-8D43-D912D5EF0360 V1 EN
Figure 2: Example of the LHMI
2.4.1 Display
The LHMI includes a graphical display that supports two character sizes. Thecharacter size depends on the selected language. The amount of characters and rowsfitting the view depends on the character size.
Table 4: Small display
Character size1) Rows in the view Characters per row
Small, mono-spaced (6 × 12 pixels) 5 20
Large, variable width (13 × 14 pixels) 3 8 or more
1) Depending on the selected language
The display view is divided into four basic areas.
Section 2 1MRS758335 DREU611 overview
12 REU611Application Manual
![Page 19: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/19.jpg)
1
3 4
2
GUID-24ADB995-439A-4563-AACE-1FAA193A8EF9 V1 EN
Figure 3: Display layout
1 Header
2 Icon
3 Content
4 Scroll bar (displayed when needed)
2.4.2 LEDs
The LHMI includes three protection indicators above the display: Ready, Start andTrip.
There are also 8 programmable LEDs on front of the LHMI. The LEDs can beconfigured with the LHMI, WHMI or PCM600.
2.4.3 Keypad
The LHMI keypad contains push buttons which are used to navigate in different viewsor menus. With the push buttons you can give open or close commands to one objectin the primary circuit, for example, a circuit breaker, a contactor or a disconnector. Thepush buttons are also used to acknowledge alarms, reset indications, provide help andswitch between local and remote control mode.
1MRS758335 D Section 2REU611 overview
REU611 13Application Manual
![Page 20: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/20.jpg)
GUID-B681763E-EC56-4515-AC57-1FD5349715F7 V1 EN
Figure 4: LHMI keypad with object control, navigation and command pushbuttons and RJ-45 communication port
2.5 Web HMI
The WHMI allows secure access to the protection relay via a Web browser. When theSecure Communication parameter in the protection relay is activated, the Web serveris forced to take a secured (HTTPS) connection to WHMI using TLS encryption.TheWHMI is verified with Internet Explorer 8.0, 9.0, 10.0 and 11.0.
WHMI is enabled by default.
WHMI offers several functions.
• Programmable LEDs and event lists• System supervision• Parameter settings• Measurement display• Disturbance records• Fault records• Phasor diagram• Signal configuration• Importing/Exporting parameters• Report summary
The menu tree structure on the WHMI is almost identical to the one on the LHMI.
Section 2 1MRS758335 DREU611 overview
14 REU611Application Manual
![Page 21: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/21.jpg)
GUID-CD531B61-6866-44E9-B0C1-925B48140F3F V2 EN
Figure 5: Example view of the WHMI
The WHMI can be accessed locally and remotely.
• Locally by connecting the laptop to the protection relay via the frontcommunication port.
• Remotely over LAN/WAN.
2.5.1 Command buttons
Command buttons can be used to edit parameters and control information via theWHMI.
Table 5: Command buttons
Name DescriptionEnabling parameter editing
Disabling parameter editing
Writing parameters to the protection relay
Refreshing parameter values
Printing out parameters
Committing changes to protection relay's nonvolatile flash memory
Table continues on next page
1MRS758335 D Section 2REU611 overview
REU611 15Application Manual
![Page 22: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/22.jpg)
Name DescriptionRejecting changes
Showing context sensitive help messages
Error icon
Clearing events
Triggering the disturbance recorder manually
Saving values to TXT or CSV file format
Freezing the values so that updates are not displayed
Receiving continuous updates to the monitoring view
Deleting the disturbance record
Deleting all disturbance records
Saving the disturbance record files
Viewing all fault records
Clearing all fault records
Importing settings
Exporting settings
Selecting all
Clearing all selections
Refreshing the parameter list view
2.6 Authorization
Four user categories have been predefined for the LHMI and the WHMI, each withdifferent rights and default passwords.
The default passwords in the protection relay delivered from the factory can bechanged with Administrator user rights.
User authorization is disabled by default for LHMI but WHMI alwaysuses authorization.
Section 2 1MRS758335 DREU611 overview
16 REU611Application Manual
![Page 23: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/23.jpg)
Table 6: Predefined user categories
Username User rightsVIEWER Read only access
OPERATOR • Selecting remote or local state with (only locally)• Changing setting groups• Controlling• Clearing indications
ENGINEER • Changing settings• Clearing event list• Clearing disturbance records• Changing system settings such as IP address, serial baud rate or
disturbance recorder settings• Setting the protection relay to test mode• Selecting language
ADMINISTRATOR • All listed above• Changing password• Factory default activation
For user authorization for PCM600, see PCM600 documentation.
2.6.1 Audit trail
The protection relay offers a large set of event-logging functions. Critical system andprotection relay security-related events are logged to a separate nonvolatile audit trailfor the administrator.
Audit trail is a chronological record of system activities that allows the reconstructionand examination of the sequence of system and security-related events and changes inthe protection relay. Both audit trail events and process related events can beexamined and analyzed in a consistent method with the help of Event List in LHMIand WHMI and Event Viewer in PCM600.
The protection relay stores 2048 audit trail events to the nonvolatile audit trail.Additionally, 1024 process events are stored in a nonvolatile event list. Both the audittrail and event list work according to the FIFO principle. Nonvolatile memory is basedon a memory type which does not need battery backup nor regular component changeto maintain the memory storage.
Audit trail events related to user authorization (login, logout, violation remote andviolation local) are defined according to the selected set of requirements from IEEE1686. The logging is based on predefined user names or user categories. The user audittrail events are accessible with IEC 61850-8-1, PCM600, LHMI and WHMI.
1MRS758335 D Section 2REU611 overview
REU611 17Application Manual
![Page 24: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/24.jpg)
Table 7: Audit trail events
Audit trail event DescriptionConfiguration change Configuration files changed
Firmware change Firmware changed
Firmware change fail Firmware change failed
Attached to retrofit test case Unit has been attached to retrofit case
Removed from retrofit test case Removed from retrofit test case
Setting group remote User changed setting group remotely
Setting group local User changed setting group locally
Control remote DPC object control remote
Control local DPC object control local
Test on Test mode on
Test off Test mode off
Reset trips Reset latched trips (TRPPTRC*)
Setting commit Settings have been changed
Time change Time changed directly by the user. Note that this is not usedwhen the protection relay is synchronised properly by theappropriate protocol (SNTP, IRIG-B, IEEE 1588 v2).
View audit log Administrator accessed audit trail
Login Successful login from IEC 61850-8-1 (MMS), WHMI, FTP orLHMI.
Logout Successful logout from IEC 61850-8-1 (MMS), WHMI, FTP orLHMI.
Password change Password changed
Firmware reset Reset issued by user or tool
Audit overflow Too many audit events in the time period
Violation remote Unsuccessful login attempt from IEC 61850-8-1 (MMS),WHMI, FTP or LHMI.
Violation local Unsuccessful login attempt from IEC 61850-8-1 (MMS),WHMI, FTP or LHMI.
PCM600 Event Viewer can be used to view the audit trail events and process relatedevents. Audit trail events are visible through dedicated Security events view. Sinceonly the administrator has the right to read audit trail, authorization must be used inPCM600. The audit trail cannot be reset, but PCM600 Event Viewer can filter data.Audit trail events can be configured to be visible also in LHMI/WHMI Event listtogether with process related events.
To expose the audit trail events through Event list, define theAuthority logging level parameter via Configuration/Authorization/Security. This exposes audit trail events to all users.
Section 2 1MRS758335 DREU611 overview
18 REU611Application Manual
![Page 25: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/25.jpg)
Table 8: Comparison of authority logging levels
Audit trail event Authority logging level
NoneConfiguration change
Settinggroup
Settinggroup,control
Settingsedit
All
Configuration change ● ● ● ● ●
Firmware change ● ● ● ● ●
Firmware change fail ● ● ● ● ●
Attached to retrofit testcase
● ● ● ● ●
Removed from retrofittest case
● ● ● ● ●
Setting group remote ● ● ● ●
Setting group local ● ● ● ●
Control remote ● ● ●
Control local ● ● ●
Test on ● ● ●
Test off ● ● ●
Reset trips ● ● ●
Setting commit ● ●
Time change ●
View audit log ●
Login ●
Logout ●
Password change ●
Firmware reset ●
Violation local ●
Violation remote ●
2.7 Communication
The protection relay supports a range of communication protocols including IEC61850 and Modbus®. Operational information and controls are available throughthese protocols. However, some communication functionality, for example,horizontal communication between the protection relays, is only enabled by the IEC61850 communication protocol.
The IEC 61850 communication implementation supports all monitoring and controlfunctions. Additionally, parameter settings, disturbance recordings and fault recordscan be accessed using the IEC 61850 protocol. Disturbance recordings are availableto any Ethernet-based application in the IEC 60255-24 standard COMTRADE fileformat. The protection relay can send and receive binary signals from other devices(so-called horizontal communication) using the IEC 61850-8-1 GOOSE profile,
1MRS758335 D Section 2REU611 overview
REU611 19Application Manual
![Page 26: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/26.jpg)
where the highest performance class with a total transmission time of 3 ms issupported. The protection relay meets the GOOSE performance requirements fortripping applications in distribution substations, as defined by the IEC 61850standard.
The protection relay can support five simultaneous clients. If PCM600 reserves oneclient connection, only four client connections are left, for example, for IEC 61850and Modbus.
All communication connectors, except for the front port connector, are placed onintegrated optional communication modules. The protection relay can be connected toEthernet-based communication systems via the RJ-45 connector (100Base-TX) or thefiber-optic LC connector (100Base-FX). An optional serial interface is available forRS-485 communication.
2.7.1 Self-healing Ethernet ring
For the correct operation of self-healing loop topology, it is essential that the externalswitches in the network support the RSTP protocol and that it is enabled in theswitches. Otherwise, connecting the loop topology can cause problems to thenetwork. The protection relay itself does not support link-down detection or RSTP.The ring recovery process is based on the aging of the MAC addresses, and the link-up/link-down events can cause temporary breaks in communication. For a betterperformance of the self-healing loop, it is recommended that the external switchfurthest from the protection relay loop is assigned as the root switch (bridge priority= 0) and the bridge priority increases towards the protection relay loop. The end linksof the protection relay loop can be attached to the same external switch or to twoadjacent external switches. A self-healing Ethernet ring requires a communicationmodule with at least two Ethernet interfaces for all protection relays.
Section 2 1MRS758335 DREU611 overview
20 REU611Application Manual
![Page 27: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/27.jpg)
Managed Ethernet switch
with RSTP support
Managed Ethernet switch
with RSTP support
Client A Client B
Network
Network
GUID-A19C6CFB-EEFD-4FB2-9671-E4C4137550A1 V2 EN
Figure 6: Self-healing Ethernet ring solution
The Ethernet ring solution supports the connection of up to 30protection relays. If more than 30 protection relays are to beconnected, it is recommended that the network is split into severalrings with no more than 30 protection relays per ring. Each protectionrelay has a 50-μs store-and-forward delay, and to fulfil theperformance requirements for fast horizontal communication, thering size is limited to 30 protection relays.
2.7.2 Ethernet redundancy
IEC 61850 specifies a network redundancy scheme that improves the systemavailability for substation communication. It is based on two complementaryprotocols defined in the IEC 62439-3:2012 standard: parallel redundancy protocolPRP and high-availability seamless redundancy HSR protocol. Both protocols rely onthe duplication of all transmitted information via two Ethernet ports for one logicalnetwork connection. Therefore, both are able to overcome the failure of a link orswitch with a zero-switchover time, thus fulfilling the stringent real-timerequirements for the substation automation horizontal communication and timesynchronization.
PRP specifies that each device is connected in parallel to two local area networks.HSR applies the PRP principle to rings and to the rings of rings to achieve cost-effective redundancy. Thus, each device incorporates a switch element that forwardsframes from port to port. The HSR/PRP option is available for all 611 series protectionrelays.
1MRS758335 D Section 2REU611 overview
REU611 21Application Manual
![Page 28: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/28.jpg)
IEC 62439-3:2012 cancels and replaces the first edition published in2010. These standard versions are also referred to as IEC 62439-3Edition 1 and IEC 62439-3 Edition 2. The protection relay supportsIEC 62439-3:2012 and it is not compatible with IEC 62439-3:2010.
PRPEach PRP node, called a double attached node with PRP (DAN), is attached to twoindependent LANs operated in parallel. These parallel networks in PRP are calledLAN A and LAN B. The networks are completely separated to ensure failureindependence, and they can have different topologies. Both networks operate inparallel, thus providing zero-time recovery and continuous checking of redundancy toavoid communication failures. Non-PRP nodes, called single attached nodes (SANs),are either attached to one network only (and can therefore communicate only withDANs and SANs attached to the same network), or are attached through a redundancybox, a device that behaves like a DAN.
Managed Ethernet switch
IEC 61850 PRP Managed
Ethernet switch
GUID-AA005F1B-A30B-48F6-84F4-A108F58615A2 V1 EN
Figure 7: PRP solution
In case a laptop or a PC workstation is connected as a non-PRP node to one of the PRPnetworks, LAN A or LAN B, it is recommended to use a redundancy box device or anEthernet switch with similar functionality between the PRP network and SAN toremove additional PRP information from the Ethernet frames. In some cases, defaultPC workstation adapters are not able to handle the maximum-length Ethernet frameswith the PRP trailer.
There are different alternative ways to connect a laptop or a workstation as SAN to aPRP network.
Section 2 1MRS758335 DREU611 overview
22 REU611Application Manual
![Page 29: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/29.jpg)
• Via an external redundancy box (RedBox) or a switch capable of connecting toPRP and normal networks
• By connecting the node directly to LAN A or LAN B as SAN• By connecting the node to the protection relay's interlink port
HSRHSR applies the PRP principle of parallel operation to a single ring, treating the twodirections as two virtual LANs. For each frame sent, a node, DAN, sends two frames,one over each port. Both frames circulate in opposite directions over the ring and eachnode forwards the frames it receives, from one port to the other. When the originatingnode receives a frame sent to itself, it discards that to avoid loops; therefore, no ringprotocol is needed. Individually attached nodes, SANs, such as laptops and printers,must be attached through a “redundancy box” that acts as a ring element. For example,a 615 or 620 series protection relay with HSR support can be used as a redundancybox.
IEC 61850 HSR
Ethernet switch
Redundancy box
Redundancy box
Redundancy box
XX
Unicast traffic
Message is recognized as a duplicate and is
immediately forwarded
X Sending device removes the message from the ring
Devices not supporting HSR
Sen
der
Receiver
GUID-B24F8609-0E74-4318-8168-A6E7FCD0B313 V1 EN
Figure 8: HSR solution
2.7.3 Secure communication
The protection relay supports secure communication for WHMI and file transferprotocol. If the Secure Communication parameter is activated, protocols require TLSbased encryption method support from the clients. In this case WHMI must beconnected from a Web browser using the HTTPS protocol and in case of file transferthe client must use FTPS.
As a factory default, Secure Communication is “ON”.
1MRS758335 D Section 2REU611 overview
REU611 23Application Manual
![Page 30: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/30.jpg)
24
![Page 31: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/31.jpg)
Section 3 REU611 standardized configuration
3.1 Standardized configuration
REU611 is available in one configuration.
To increase the user-friendliness of the configuration and to emphasize the simplicityof usage of the relay, only the application-specific parameters need setting within therelay's intended area of application.
The standard signal configuration can be altered by local HMI, Web HMI or optionalapplication functionality of Protection and Control IED Manager PCM600.
Table 9: Standardized configuration
Description Conf.Voltage and frequency protection A
Table 10: Supported functions
Function IEC 61850 AProtection
Residual overvoltage protection ROVPTOV 3
Three-phase undervoltage protection PHPTUV 3
Three-phase overvoltage protection PHPTOV 3
Positive-sequence undervoltage protection PSPTUV 2
Negative-sequence overvoltage protection NSPTOV 2
Frequency protection FRPFRQ 2
Master trip TRPPTRC 2
Control
Circuit-breaker control CBXCBR 1
Condition monitoring and supervision
Trip circuit supervision TCSSCBR 2
Logging
Disturbance recorder RDRE 1
Fault recorder FLTRFRC 1
Measurement
Three-phase voltage measurement VMMXU 2
Sequence voltage measurement VSMSQI 1
Residual voltage measurement RESVMMXU 1
Table continues on next page
1MRS758335 D Section 3REU611 standardized configuration
REU611 25Application Manual
![Page 32: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/32.jpg)
Function IEC 61850 AFrequency measurement FMMXU 1
Other
Input switch group ISWGAPC 10
Output switch group OSWGAPC 20
Selector SELGAPC 6
Minimum pulse timer (2 pcs) TPGAPC 10
Move (8 pcs) MVGAPC 1
1, 2, ... = Number of included instances. The instances of a protection function represent the number ofidentical protection function blocks available in the standardized configuration.() = optional
3.2 Switch groups
The default application configurations cover the most common application cases,however, changes can be made according to specific needs through LHMI, WHMIand PCM600.
Programming is easily implemented with three switch group functions including inputswitch group ISWGAPC, output switch group OSWGAPC and selector switch groupSELGAPC. Each switch group has several instances.
Connections of binary inputs to functions, GOOSE signals to functions, functions tofunctions, functions to binary outputs and functions to LEDs have been preconnectedthrough corresponding switch groups.
The real connection logic and the application configuration can be modified bychanging the parameter values of the switch groups. It is also possible to modify thereal connection logic and the application configuration through the matrix view in thesignal configuration menu in the WHMI.
3.2.1 Input switch group ISWGAPC
The input switch group ISWGAPC has one input and a number of outputs. Every inputand output has a read-only description. ISWGAPC is used for connecting the inputsignal to one or several outputs of the switch group. Each output can be set to beconnected or not connected with the input separately via the “OUT_x connection”setting.
Section 3 1MRS758335 DREU611 standardized configuration
26 REU611Application Manual
![Page 33: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/33.jpg)
GUID-2D549B56-6CF7-4DCB-ACDE-E9EF601868A8 V1 EN
Figure 9: Input switch group ISWGAPC
3.2.2 Output switch group OSWGAPC
The output switch group OSWGAPC has a number of inputs and one output. Everyinput and output has a read-only description. OSWGAPC is used for connecting oneor several inputs to the output of the switch group via OR logic. Each input can be setto be connected or not connected with the OR logic via the “IN_x connection”settings. The output of OR logic is routed to switch group output.
GUID-1EFA82D5-F9E7-4322-87C2-CDADD29823BD V1 EN
Figure 10: Output switch group OSWGAPC
3.2.3 Selector switch group SELGAPC
The selector switch group SELGAPC has a number of inputs and outputs. Every inputand output has a read-only description. Each output can be set to be connected withone of the inputs via the OUT_x connection setting. An output can also be set to be notconnected with any of the inputs. In SELGAPC, one output signal can only beconnected to one input signal but the same input signal can be routed to several outputsignals.
1MRS758335 D Section 3REU611 standardized configuration
REU611 27Application Manual
![Page 34: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/34.jpg)
GUID-E3AEC7AB-2978-402D-8A80-C5DE9FED67DF V1 EN
Figure 11: Selector switch group SELGAPC
Section 3 1MRS758335 DREU611 standardized configuration
28 REU611Application Manual
![Page 35: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/35.jpg)
3.3 Connection diagrams
REU611
16
17
1918
X100
67
89
10
111213
15
14
2
1
3
45
22
212324
SO2
TCS2
PO4
SO1
TCS1
PO3
PO2
PO1
IRF
+
-Uaux
20
L1L2L3
da dn
a
nN
A
A N n a
X13012
34
56
BI 4
BI 3
BI 2
BI 1
87
9101112
U12B
1314
U1
1516
U2
1718
U3
UoN
N
N
N
60 -
N
210V
60 -210V
60 -210V
60 -210V
60 -210V
GUID-45AA211F-CF77-4974-BBF6-4FC34B46EF3B V1 EN
Figure 12: Connection diagram for configuration A (voltage protection withphase-to-phase voltage measurement)
1MRS758335 D Section 3REU611 standardized configuration
REU611 29Application Manual
![Page 36: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/36.jpg)
REU611
L1L2L3
da dn
a
nN
A
A N n a
X13012
34
56
BI 4
BI 3
BI 2
BI 1
87
9101112
U12B
1314
U1
1516
U2
1718
U3
UoN
N
N
N
60 -
N
210V
60 -210V
60 -210V
60 -210V
60 -210V
GUID-90BD624C-28F1-4B93-8A2B-708E480A07A8 V1 EN
Figure 13: Connection diagram for configuration A (voltage protection withphase-to-earth voltage measurement)
Section 3 1MRS758335 DREU611 standardized configuration
30 REU611Application Manual
![Page 37: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/37.jpg)
3.4 Configuration A
3.4.1 Applications
Configuration A for voltage and frequency-based protection is mainly intended forutility and industrial power systems and distribution systems including networks withdistributed power generation. The configuration handles fault conditions originatingfrom abnormal voltages in the power system.
The protection relay with a standardized configuration is delivered from the factorywith default settings and parameters. The end-user flexibility for incoming, outgoingand internal signal designation within the protection relay enables this configurationto be further adapted to different primary circuit layouts and the related functionalityneeds by modifying the internal functionality using PCM600.
1MRS758335 D Section 3REU611 standardized configuration
REU611 31Application Manual
![Page 38: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/38.jpg)
3.4.2 Functions
UL1
UL2
UL3
UL1UL2UL3
3U<27
3U>59
U2>47O-
U1<47U+
Uo>59G
f>/f<,df/dt81
REMARKS
Optionalfunction
No. ofinstances
Alternative function to be defined when ordering
OR3×
Io/Uo
Calculatedvalue
CONDITION MONITORING AND SUPERVISION
CONTROL AND INDICATION 1) MEASUREMENT
- U, Uo, f- Limit value supervision- Symmetrical components
VOLTAGE PROTECTION RELAY STANDARD CONFIGURATION
LOCAL HMI
A
COMMUNICATION
Protocols: IEC 61850-8-1 Modbus®
Interfaces: Ethernet: TX (RJ-45), FX (LC) Serial: RS-485
Redundant protocols: HSR PRP RSTP
-
5
Analog interface types 1)
Current transformer
Voltage transformer1) Conventional transformer inputs
Object Ctrl 2) Ind 3)
CB
DC
ES
1 -
- -
- -1) Check availability of binary inputs/outputs from technical documentation2) Control and indication function for primary object3) Status indication function for primary object
Master TripLockout relay
94/86
PROTECTION
Uo
Uo
ALSO AVAILABLE
- Disturbance and fault recorders- Event log and recorded data- Local/Remote push button on LHMI- Self-supervision- Time synchronization: IEEE 1588 v2, SNTP, IRIG-B- User management- Web-HMI
2×
2×
TCSTCM
2×
3× 2× 3×
3× 2×
REU611
RL
ESCI
O
AControlEventsMeasurementsDisturbance records
U12
GUID-188F04CC-D6B0-4AB5-BDAB-BE4B993A605C V1 EN
Figure 14: Functionality overview for configuration A
3.4.2.1 Default I/O connections
Table 11: Default connections for binary inputs
Binary input Description Connector pinsX130-BI1 Blocking of overvoltage protection X130:1-2
X130-BI2 Circuit breaker closed position indication X130:3-4
X130-BI3 Circuit breaker open position indication X130:5-6
X130-BI4 Bus voltage transformer MCB open X130:7-8
Section 3 1MRS758335 DREU611 standardized configuration
32 REU611Application Manual
![Page 39: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/39.jpg)
Table 12: Default connections for binary outputs
Binary input Description Connector pinsX100-PO1 Close circuit breaker X100:6-7
X100-PO2 General start indication X100:8-9
X100-SO1 Overvoltage operate indication X100:10-12
X100-SO2 Undervoltage operate indication X100:13-14
X100-PO3 Open circuit breaker/trip coil 1 X100:15-19
X100-PO4 Open trip coil 2 X100:20-24
Table 13: Default connections for LEDs
LED Description1 Overvoltage protection operated
2 Undervoltage protection operated
3 Residual voltage protection operated
4 Sequence protection operated
5 Frequency protection operated
6 Disturbance recorder triggered
7 Trip circuit supervision alarm
8 Bus VT MCB failure
3.4.2.2 Predefined disturbance recorder connections
Table 14: Predefined analog channel setup
Channel Description1 Uo
2 U1
3 U2
4 U3
5 U1B
Additionally, all the digital inputs that are connected by default are also enabled withthe setting. Default triggering settings are selected depending on the connected inputsignal type. Typically all protection START signals are selected to trigger thedisturbance recorded by default.
3.4.3 Functional diagrams
The functional diagrams describe the default input, output, programmable LED,switch group and function-to-function connections. The default connections can beviewed and changed with switch groups in PCM600, LHMI and WHMI according tothe application requirements.
1MRS758335 D Section 3REU611 standardized configuration
REU611 33Application Manual
![Page 40: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/40.jpg)
The analog channels have fixed connections towards the different function blocksinside the protection relay’s configuration. Exceptions to this rule are the 12 analogchannels available for the disturbance recorder function. These channels are freelyselectable and a part of the disturbance recorder’s parameter settings.
The line and bus voltages to the protection relay are fed from voltage transformer. Theresidual voltage to the protection relay is fed from either residual connected VTs, anopen delta connected VT or internally calculated.
3.4.3.1 Functional diagrams for protection
The functional diagrams describe the protection functionality of the protection relayin detail and picture the factory default connections.
LED 1
SELGAPC4
OUT_1IN_8
OSWGAPC7
OROUT
IN_1
IN_2
IN_3
OVERVOLTAGE PROTECTION INDICATION
PHPTOV13U>(1)
59(1)
BLOCK START
OPERATE3U
PHPTOV23U>(2)59(2)
BLOCK START
OPERATE3U
PHPTOV33U>(3)
59(3)
BLOCK START
OPERATE3U
GUID-A6031EA6-2B8B-41D9-BCA8-5EB5446B9594 V1 EN
Figure 15: Overvoltage protection
Three overvoltage protection stages PHPTOV1...3 offer protection againstovervoltage conditions. All operate signals are connected to the master trip and toalarm LED 1.
Section 3 1MRS758335 DREU611 standardized configuration
34 REU611Application Manual
![Page 41: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/41.jpg)
LED 2
SELGAPC4
OUT_2IN_9
OSWGAPC8
OROUT
IN_4
IN_5
IN_6
UNDERVOLTAGE PROTECTION INDICATION
PHPTUV13U<(1)
27(1)
BLOCK START
OPERATE3U
PHPTUV23U<(2)
27(2)
BLOCK START
OPERATE3U
PHPTUV33U<(3)
27(3)
BLOCK START
OPERATE3U
GUID-0E0A1B18-45A8-4FDB-BCFB-9FFC175CD53B V1 EN
Figure 16: Undervoltage protection
Three undervoltage protection stages PHPTUV1...3 offer protection againstundervoltage conditions. All operate signals are connected to the master trip and toalarm LED 2.
1MRS758335 D Section 3REU611 standardized configuration
REU611 35Application Manual
![Page 42: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/42.jpg)
LED 3
RESIDUAL OVERVOLTAGE PROTECTION
ROVPTOV1U0>(1)
59G(1)
BLOCK START
OPERATEU0
ROVPTOV2U0>(2)
59G(2)
BLOCK START
OPERATEU0
ROVPTOV3U0>(3)
59G(3)
BLOCK START
OPERATEU0
OSWGAPC9
OROUT
IN_7
IN_8
IN_9
SELGAPC4
OUT_3IN_10
GUID-77BDA0D6-968E-4EF0-84E0-ED91580217A7 V1 EN
Figure 17: Residual overvoltage protection
The residual overvoltage protection ROVPTOV provides earth-fault protection bydetecting abnormal level of residual voltage. It can be used, for example, as anonselective backup protection for the selective directional earth-fault functionality.
All operate signals of these residual overvoltage protections are connected to themaster trip and to alarm LED 3.
Section 3 1MRS758335 DREU611 standardized configuration
36 REU611Application Manual
![Page 43: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/43.jpg)
LED 4
SELGAPC4
OUT_4IN_11
OSWGAPC10
OROUT
IN_12
IN_13
IN_14
IN_15
POSITIVE AND NEGATIVE SEQUENCE PROTECTION INDICATION
PSPTUV1U1<(1)
47U+(1)
BLOCK START
OPERATE3I
PSPTUV2U1<(2)
47U+(2)
BLOCK START
OPERATE3I
NSPTOV1U2>(1)
47O-(1)
BLOCK START
OPERATE3I
NSPTOV2U2>(2)
47O-(2)
BLOCK START
OPERATE3I
GUID-1D8D400A-3ED1-4C24-BE3D-A93EB046013D V1 EN
Figure 18: Unbalance protection
Four unbalance voltage protection functions are available, two stages of positive-sequence undervoltage protection PSPTUV and two stages of negative-sequenceovervoltage protection NSPTOV.
The operate signals of these unbalance voltage protections are connected to the mastertrip and to alarm LED 4.
1MRS758335 D Section 3REU611 standardized configuration
REU611 37Application Manual
![Page 44: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/44.jpg)
LED 5
FREQUENCY PROTECTION INDICATION
OSWGAPC16
OUTIN_12
SELGAPC4
OUT_5IN_17OR
FRPFRQ1f>/f<,df/dt (1)
81(1)
BLOCK START
OPERATE3U
FRPFRQ2f>/f<,df/dt (2)
81(2)
BLOCK START
OPERATE3U
GUID-8E6B38BF-E8C6-4346-9EA4-F6A3DB231343 V1 EN
Figure 19: Frequency protection
The selectable underfrequency or overfrequency protection FRPFRQ preventsdamage to network components under unwanted frequency conditions. The functionalso contains a selectable rate of change of the frequency (gradient) protection todetect an increase or decrease in the rapid changing power system frequency at anearly stage. This can be used as an early indication of a disturbance in the system.
The operate signals of these frequency protections are connected to the master trip andto alarm LED 5.
Section 3 1MRS758335 DREU611 standardized configuration
38 REU611Application Manual
![Page 45: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/45.jpg)
3.4.3.2 Functional diagrams for disturbance recorder and trip circuitsupervision
RDRE1
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
C12
C13
C14
C15
C16
C17
C18
C19
C20
C21
C22
C23
C24
C25
C26
C27
C28
C29
C30
C31
OR
OR
OR
OR
TRIGGERED LED 6
DISTURBANCE RECORDER
PSPTUV1_OPERATE
PSPTUV2_OPERATE
NSPTOV1_OPERATE
NSPTOV2_OPERATE
PHPTUV2_OPERATE
PHPTUV1_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
OSWGAPC11
OUTIN_1
SELGAPC4
OUT_6IN_12
PHPTOV3_START
PHPTOV2_START
PHPTOV1_START
PHPTUV1_START
PHPTUV3_START
PSPTUV2_START
SEL1_Blocking 1
SEL1_CB Closed
SEL1_CB_Open
PHPTUV2_START
SEL1_External_Trip
SG_1_ACT
SG_2_ACT
SG_3_ACT
SG_4_ACT
SG_5_ACT
SG_6_ACT
ORPHPTOV2_OPERATE
PHPTOV1_OPERATE
PHPTOV3_OPERATE
PSPTUV1_START
NSPTOV1_START
NSPTOV2_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
FRPFRQ1_START
FRPFRQ2_START
BUS_VT_MCB_OPEN
GUID-E2B78222-723F-42A9-9F6C-1AE1E3BCDF9F V1 EN
Figure 20: Disturbance recorder
All start and operate signals from the protection stages are routed to trigger thedisturbance recorder or alternatively only to be recorded by the disturbance recorderdepending on the parameter settings. The active setting group is also to be recorded viaSG_1_ACT to SG_6_ACT. The disturbance recorder triggered signal indication isconnected to LED 6.
Table 15: Disturbance recorder binary channel default value
Channel number Channel ID text Level trigger modeBinary channel 1 PHPTOV1_START 1=positive or rising
Binary channel 2 PHPTOV2_START 1=positive or rising
Binary channel 3 PHPTOV3_START 1=positive or rising
Binary channel 4 PHPTUV1_START 1=positive or rising
Binary channel 5 PHPTUV2_START 1=positive or rising
Binary channel 6 PHPTUV3_START 1=positive or rising
Binary channel 7 PSPTUV1_START 1=positive or rising
Binary channel 8 PSPTUV2_START 1=positive or rising
Binary channel 9 NSPTOV1_START 1=positive or rising
Binary channel 10 NSPTOV2_START 1=positive or rising
Binary channel 11 ROVPTOV1_START 1=positive or rising
Binary channel 12 ROVPTOV2_START 1=positive or rising
Table continues on next page
1MRS758335 D Section 3REU611 standardized configuration
REU611 39Application Manual
![Page 46: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/46.jpg)
Channel number Channel ID text Level trigger modeBinary channel 13 ROVPTOV3_START 1=positive or rising
Binary channel 14 FRPFRQ1_START 1=positive or rising
Binary channel 15 FRPFRQ2_START 1=positive or rising
Binary channel 16 PHPTOV_OPERATE 1=positive or rising
Binary channel 17 PHPTUV_OPERATE 1=positive or rising
Binary channel 18 ROVPTOV_OPERATE 1=positive or rising
Binary channel 19 PSPTUV/NSPTOV_OPERATE 1=positive or rising
Binary channel 20 FRPFRQ_OPERATE 1=positive or rising
Binary channel 21 SELGAPC1_Blocking 1 1=positive or rising
Binary channel 22 SELGAPC1_CB_Closed 1=positive or rising
Binary channel 23 SELGAPC1_CB_Open 1=positive or rising
Binary channel 24 SELGAPC1_External Trip 1=positive or rising
Binary channel 25 SG_1_ACT 1=positive or rising
Binary channel 26 SG_2_ACT 1=positive or rising
Binary channel 27 SG_3_ACT 1=positive or rising
Binary channel 28 SG_4_ACT 1=positive or rising
Binary channel 29 SG_5_ACT 1=positive or rising
Binary channel 30 SG_6_ACT 1=positive or rising
Binary channel 31 BUS_VT_MCB_OPEN 1=positive or rising
X120-BI3
OR
LED 7
TRIP CIRCUIT SUPERVISION
SELGAPC1
OUT_3IN_3
TRPPTRC1_TRIP
TRPPTRC2_TRIP
TCSSCBR1
BLOCK ALARM
TCSSCBR2
BLOCK ALARM
SELGAPC4
OUT_7IN_13
OSWGAPC12
OROUT
IN_2
IN_3
SELGAPC2
OUT_1
IN_2 OUT_2CB Open Position
GUID-EC303A9E-DD21-4501-A0C9-82EBC49AA114 V1 EN
Figure 21: Trip circuit supervision
Two separate trip circuit supervision functions are included, TCSSCBR1 for PO3(X100:15-19) and TCSSCBR2 for PO4 (X100:20-24). Both functions are blocked bythe master trip (TRPPTRC1 and TRPPTRC2) and the circuit breaker open position.The TCS alarm indication is connected to LED 7.
Section 3 1MRS758335 DREU611 standardized configuration
40 REU611Application Manual
![Page 47: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/47.jpg)
3.4.3.3 Functional diagrams for control
OR X100 PO3
OSWGAPC1
OR
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
OUT
IN_12
IN_13
IN_15
IN_14
X100 PO4
MASTER TRIP #1
MASTER TRIP #2
OR
OR
SELGAPC3OUT_6IN_2
SELGAPC3OUT_5IN_1
TRIP
CL_LKOUT
BLOCK
RST_LKOUT
TRPPTRC1
OPERATE
TRIP
CL_LKOUT
BLOCK
RST_LKOUT
TRPPTRC2
OPERATE
SELGAPC1_RST_LKOUT
CBXCBR1_EXE_OP
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERTAE
NSPTOV2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
FRPFRQ1_OPERTAE
FRPFRQ2_OPERTAE
PHPTUV2_OPETATE
NSPTOV1_OPERATE
SELGAPC1_RST_LKOUT
OSWGAPC2
OR
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
OUT
IN_12
IN_13
IN_15
IN_14
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERTAE
NSPTOV2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
FRPFRQ1_OPERTAE
FRPFRQ2_OPERTAE
PHPTUV2_OPETATE
NSPTOV1_OPERATE
SELGAPC1_External Trip
Q1
Q2
Q3
IN1
IN2
IN3
MVGAPC1
ORGOOSERCV_BIN 2_OUT
GOOSERCV_BIN 3_OUT
BUS_VT_MCB_OPEN
SELGAPC1_External Trip
Q1
Q2
Q3
IN1
IN2
IN3
MVGAPC1
ORGOOSERCV_BIN 2_OUT
GOOSERCV_BIN 3_OUT
BUS_VT_MCB_OPEN
GUID-FBD41DB4-5D20-46F7-9D09-04318A7EE553 V3 EN
Figure 22: Master trip
The operate signals from the protections and an external trip are connected to the twotrip output contacts PO3 (X100:15-19) and PO4 (X100:20-24) via the correspondingmaster trips TRPPTRC1 and TRPPTRC2. Open control commands to the circuit
1MRS758335 D Section 3REU611 standardized configuration
REU611 41Application Manual
![Page 48: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/48.jpg)
breaker from local or remote CBXCBR1_EXE_OP is connected directly to the outputcontact PO3 (X100:15-19).
TRPPTRC1 and TRPPTRC2 provide the lockout/latching function, event generationand the trip signal duration setting. One binary input through SELGAPC1 can beconnected to the RST_LKOUT input of the master trip. If the lockout operation modeis selected, it is used to enable external reset.
X120-BI2
X120-BI3
ANDTRPPTRC1_TRIP
TRPPTRC2_TRIP
CBXCBR1_EXE_OP
X100 PO1
CIRCUIT BREAKER CONTROL
Always True SELGAPC3
OUT_1IN_3
SELGAPC1
OUT_2
IN_3
IN_2
OUT_3
IN_5 OUT_5
CB Closed Position
CB Open Position
CBXCBR1
ENA_OPEN
SELECTED
EXE_OP
EXE_CL
ENA_CLOSE
BLK_OPEN
BLK_CLOSE
AU_OPEN
AU_CLOSE
POSOPEN
POSCLOSE
OPENPOS
CLOSEPOS
OKPOS
OPEN_ENAD
CLOSE_ENAD
TRIP
SYNC_ITL_BYP
OP_REQ
CL_REQ
SYNC_OK
GUID-798F8D1E-A9AA-47A1-8A27-EAB36E989637 V2 EN
Figure 23: Circuit breaker control
The ENA_CLOSE input, which enables the closing of the circuit breaker, isinterlocked by two master trip signals. Any trip blocks the breaker from closing. Analways true signal is also connected to ENA_CLOSE via SELGAPC1 by default. Theopen operation is always enabled.
Section 3 1MRS758335 DREU611 standardized configuration
42 REU611Application Manual
![Page 49: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/49.jpg)
X100 PO2
X100 SO1
COMMON ALARM INDICATION 1 & 2
OSWGAPC3
OROUT
OSWGAPC7
OROUT
SELGAPC3OUT_2IN_4
OUT_3IN_8
TPGAPC1IN1 OUT1
TPGAPC3IN1 OUT1
PHPTOV1_START
PHPTOV2_START
PHPTOV3_START
PHPTUV1_START
PHPTUV3_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
NSPTOV2_START
PSPTUV1_START
PSPTUV2_START
FRPFRQ1_START
FRPFRQ2_START
PHPTUV2_START
NSPTOV1_START
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
IN_15
IN_14
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
IN_1
IN_2
IN_3
GUID-ABBA0E88-9D42-4D61-A3E9-DC321BA760B4 V2 EN
Figure 24: Common alarm indication
The signal outputs from the protection relay are connected to give dedicatedinformation.
• Start of any protection function PO2 (X100:8-9)• Operation (trip) of overvoltage protection function SO1 (X100:10-12)
TPGAPC functions are timers and they are used for setting the minimum pulse lengthfor the outputs. There are seven generic timers (TPGAPC1…7) available in theprotection relay.
3.4.4 Switch groups
In configuration A, the switch group function blocks are organized in four groups:binary inputs, internal signal, GOOSE and binary outputs and LEDs.
1MRS758335 D Section 3REU611 standardized configuration
REU611 43Application Manual
![Page 50: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/50.jpg)
GOOSE
Binary Inputs Protection and Control
GOOSE
GOOSE
GOOSE
Binary Inputs(1..4)
Received GOOSE(0...19)
Binary Outputs and LEDs
OSWGAPC2
OSWGAPC1
OSWGAPC16
OSWGAPC15
OSWGAPC14
OSWGAPC13
OSWGAPC12
OSWGAPC11
SELGAPC4
LEDs
SELGAPC3
Binary Outputs
OSWGAPC10
OSWGAPC9
OSWGAPC8
OSWGAPC7
OSWGAPC6
OSWGAPC5
OSWGAPC4
OSWGAPC3
Binary Outputs(1...6)
LEDs(1…8)
ROVPTOV1 ROVPTOV2
ROVPTOV3 PHPTUV1
PHPTUV2 PHPTUV3
PHPTOV1
PHPTOV3
PHPTOV2
PSPTUV1
PSPTUV2 NSPTOV1
NSPTOV2 FRPFRQ1
FRPFRQ2 CBXCBR1
TCSSCBR2TCSSCBR1
Internal Signal
SELGAPC1
Binary Inputs
ISWGAPC2
ISWGAPC1
SELGAPC2
Blocking
TCS Blocking
ISWGAPC9
GOOSE Blocking
ISWGAPC10
GOOSE Block CBAlarm
Trip
Start
Master trip
GUID-DD46D20E-10C3-4190-988E-DB2C8E1E906E V1 EN
Figure 25: Configuration A switch group overview
3.4.4.1 Binary inputs
The binary inputs group includes one SELGAPC and two ISWGAPCs. SELGAPC1is used to route binary inputs to ISWGAPC or directly to protection relay functions.ISWGAPC1 and ISWGAPC2 are used to configure the signal to block the protectionfunctions.
Section 3 1MRS758335 DREU611 standardized configuration
44 REU611Application Manual
![Page 51: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/51.jpg)
SELGAPC1
ISWGAPC1Blocking 1
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
X130-BI1
X130-BI2
X130-BI3
ISWGAPC2Blocking 2
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
X130-BI4
GUID-061E1E21-E166-4597-99F7-4770E336775A V1 EN
Figure 26: Binary inputs
SELGAPC1SELGAPC1 has inputs from protection relay binary inputs. IN_1...IN_4 are binaryinputs from X130. An always true signal is connected to IN_5. SELGAPC1 outputsare used to route inputs to different functions. Binary inputs can be configured fordifferent purposes by setting SELGAPC1.
1MRS758335 D Section 3REU611 standardized configuration
REU611 45Application Manual
![Page 52: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/52.jpg)
SELGAPC1
Blocking 1
CBXCBR1_POSCLOSESELGAPC2_IN_1
CB Closed Position
CB Open Position CBXCBR1_POSOPENSELGAPC2_IN_2
TRPPTRC1/2_RST_LKOUT
CBXCBR1_ENA_CLOSECB Close Enable
External Trip
PROTECTION_BI_SG_2Setting Group 2
PROTECTION_BI_SG_3Setting Group 3
ISWGAPC1_INX130/1-2 BI1
X130/3-4 BI2
X130/5-6 BI3
X130/7-8 BI4
IN_1
IN_2
IN_3
IN_4
IN_5
TRPTTRC1_OPERATE
X130-BI1
X130-BI2
X130-BI3
X130-BI4
Always True
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
OUT_7
OUT_8
OUT_9
OUT_10
OUT_11
TRPTTRC1_RST_LKOUTTRPTTRC2_RST_LKOUT
PROTECTION_BI_SG_4Setting Group 4
Blocking 2 ISWGAPC2_IN
BUS_VT_MCB_OPEN
BUS_VT_MCB_OPEN_ALARM
GUID-80A08942-C2E5-48CB-94C3-2A803058F830 V2 EN
Figure 27: SELGAPC1
ISWGAPC1ISWGAPC1 is used to select the protection functions to be blocked by changing theISWGAPC1 parameters. ISWGAPC1 input is routed from SELGAPC1 outputOUT_1 Blocking 1. ISWGAPC1 outputs are connected to the BLOCK inputs ofthe protection functions.
Section 3 1MRS758335 DREU611 standardized configuration
46 REU611Application Manual
![Page 53: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/53.jpg)
ISWGAPC1
IN
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
OUT_7
OUT_8
OUT_9
OUT_10
OUT_11
OUT_12
OUT_13
OUT_14
OUT_15
Blocking 1
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
GUID-65F2F3B6-3D6D-4126-891E-9C7AD6122367 V1 EN
Figure 28: ISWGAPC1
ISWGAPC2ISWGAPC2 is used to select the protection functions to be blocked by changingISWGAPC2 parameters. ISWGAPC2 input is routed from SELGAPC1 outputOUT_13 Blocking 2. ISWGAPC2 outputs are connected to the BLOCK inputs ofthe protection functions.
1MRS758335 D Section 3REU611 standardized configuration
REU611 47Application Manual
![Page 54: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/54.jpg)
Blocking 2
ISWGAPC2
IN
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
OUT_7
OUT_8
OUT_9
OUT_10
OUT_11
OUT_12
OUT_13
OUT_14
OUT_15
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
GUID-21043993-1044-4B8B-81E5-BF45A21D79CB V1 EN
Figure 29: ISWGAPC2
3.4.4.2 Internal signal
The internal signal group is used to configure logic connections between functionblocks. There is one SELGAPC in the group. SELGAPC2 is used to configure TCSblocking from the circuit breaker open or close position.
SELGAPC2TCSSCBR1_BLOCK
TCSSCBR2_BLOCKSELGAPC1_OUT_3
CB Closed Position
CB Open Posit ion
SELGAPC1_OUT_2
GUID-F60A5ABF-7569-44D7-B5E4-CC60F9F87D9E V1 EN
Figure 30: Internal signal
SELGAPC2SELGAPC2 inputs represent the circuit breaker closed and open positions fromSELGACP1. SELGAPC2 outputs are routed to the BLOCK input of the trip circuitsupervision TCSSCBR1 and TCSSCBR2.
By default, X100 PO3 and PO4 are both used for opening the circuit breaker.TCSSCBR1 and TCSSCBR2 are both blocked by the circuit breaker open position. IfX100-PO3 is used for closing the circuit breaker, TCSSCBR1 needs to be blocked bycircuit breaker close position (OUT_1 connection=IN_1). If X100-PO4 is used forclosing the circuit breaker, TCSSCBR2 needs to be blocked by the circuit breakerclose position (OUT_2 connection=IN_1).
Section 3 1MRS758335 DREU611 standardized configuration
48 REU611Application Manual
![Page 55: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/55.jpg)
SELGAPC2
IN_1
IN_2
OUT_1
OUT_2
TCSSCBR1_BLOCK
TCSSCBR2_BLOCK
SELGAPC1_OUT_2
SELGAPC1_OUT_3
CB Closed Position
CB Open Posit ion
GUID-BC1E889E-D80E-4561-A70B-9986BFB374F7 V1 EN
Figure 31: SELGAPC2
3.4.4.3 Binary outputs and LEDs
In the standard configuration A, the signals are routed to binary outputs and LEDs areconfigured by OSWGAPCs. There are 16 OSWGAPC instances in total. They arecategorized in four groups, which include two master trip, four start, four trip and sixalarm signals. The OSWGAPC output is connected with binary outputs and LEDs viaSELGAPC3 and SELGAPC4.
• SELGAPC3 is used to configure OSWGAPC signals to the protection relay'sbinary outputs. SELGAPC4 is used to configure OSWGAPC signals to LEDs.
• OSWGAPC1 and OSWGAPC2 are used for the master trip. The inputs are routedfrom the protection function's operate and the circuit breaker failure's re-trip.
• OSWGAPC3 to OSWGAPC6 are used for the start signal. The inputs are startsignals routed from the protection functions.
• OSWGAPC7 to OSWGAPC10 are used for the trip signal. The inputs areoperation signals routed from the protection functions.
• OSWGAPC11 to OSWGAPC16 are used for the alarm signal. The inputs arealarm signals routed from the protection and monitoring functions.
1MRS758335 D Section 3REU611 standardized configuration
REU611 49Application Manual
![Page 56: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/56.jpg)
Master Trip 1
OSWGAPC2Master Trip 2
Trip 1
Trip 2
Trip 3
Trip 4
RDRE_TRIGGERED
TCSSCBR1_ALARM
TCSSCBR2_ALARM
SELGAPC1_EXT_Trip
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
RES_VOLTAGE_OPERATE
SEQ_VOLTAGE_OPERATE
FREQUENCY_OPERATE
OSWGAPC12 Alarm 2
OSWGAPC13 Alarm 3
OSWGAPC14 Alarm 4
OSWGAPC1
OSWGAPC3
OSWGAPC11 Alarm 1
TRPPTRC1
TRPPTRC2
TPGAPC3
TPGAPC4
TPGAPC5
TPGAPC6
SELGAPC3
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV2_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
NSPTOV1_OPERATE
NSPTOV2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
PHPTOV1_START
PHPTOV2_START
PHPTOV3_START
PHPTUV1_START
PHPTUV2_START
PHPTUV3_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
NSPTOV2_START
PSPTUV1_START
PSPTUV2_START
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV2_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
NSPTOV1_OPERATE
NSPTOV2_OPERATE
OSWGAPC8
OSWGAPC7
OSWGAPC10
OSWGAPC9
X100 PO1
X100 PO2
X100 SO1
X100 SO2
X100 PO3
X100 PO4
Start 1
Start 2
TPGAPC1
OSWGAPC4
OSWGAPC5 Start 3
Start 4
TPGAPC2
OSWGAPC6
OSWGAPC15 Alarm 5
OSWGAPC16 Alarm 6
TPGAPC7
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
IN1 OUT1
IN2 OUT2
GUID-71FC5116-1DD0-48DF-A650-2100F982CBE4 V1 EN
Figure 32: Binary outputs
Section 3 1MRS758335 DREU611 standardized configuration
50 REU611Application Manual
![Page 57: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/57.jpg)
Master Trip 1
OSWGAPC2Master Trip 2
Trip 1
Trip 2
Trip 3
Trip 4
RDRE_TRIGGERED
TCSSCBR1_ALARM
TCSSCBR2_ALARM
SELGAPC1_EXT_Trip
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
RES_VOLTAGE_OPERATE
SEQ_VOLTAGE_OPERATE
FREQUENCY_OPERATE
OSWGAPC1
OSWGAPC3
OSWGAPC11Alarm 1
TRPPTRC1
TRPPTRC2
SELGAPC4
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV2_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
NSPTOV1_OPERATE
NSPTOV2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
PHPTOV1_START
PHPTOV2_START
PHPTOV3_START
PHPTUV1_START
PHPTUV2_START
PHPTUV3_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
NSPTOV2_START
PSPTUV1_START
PSPTUV2_START
PHPTOV1_OPERATE
PHPTOV2_OPERATE
PHPTOV3_OPERATE
PHPTUV1_OPERATE
PHPTUV2_OPERATE
PHPTUV3_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
NSPTOV1_OPERATE
NSPTOV2_OPERATE
PSPTUV1_OPERATE
PSPTUV2_OPERATE
OSWGAPC8
OSWGAPC7
OSWGAPC10
OSWGAPC9
Start 1
Start 2OSWGAPC4
OSWGAPC5 Start 3
Start 4OSWGAPC6
LED1
LED2
LED3
LED4
LED5
LED6
LED7
LED8
OSWGAPC12Alarm 2
OSWGAPC13Alarm 3
OSWGAPC14Alarm 4
OSWGAPC15Alarm 5
OSWGAPC16Alarm 6
GUID-079B9E25-2261-4E6C-AF7C-DD32B3D084AD V1 EN
Figure 33: LEDs
SELGAPC3SELGAPC3 is used to configure the OSWGAPC outputs to the protection relay binaryoutputs. Master trip signals are connected to SELGAPC3 via TRPPTRC. Start, tripand alarm signals are connected to SELGAPC3 via TPGAPC. TPGAPC functions aretimers and used for setting the minimum pulse length for the outputs. SELGAPC3outputs are connected to X100 binary outputs.
1MRS758335 D Section 3REU611 standardized configuration
REU611 51Application Manual
![Page 58: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/58.jpg)
SELGAPC3
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
IN_14
IN_15
IN_16
IN_17
X100 PO1
X100 PO2
X100 SO1
X100 SO2
X100 PO3
X100 PO4
Start 1
Start 2
Start 3
Start 4
Trip 1
Alarm 1
Trip 2
Trip 3
Trip 4
Alarm 2
Alarm 3
Alarm 4
Alarm 5
Alarm 6
CBXCBR_EXE_OP
TRPPTRC1_TRIP
CB Open 1
CB Close
CB Open 2
TPGAPC1
IN1 OUT1
IN2 OUT2
TPGAPC7
IN1 OUT1
IN2 OUT2
TPGAPC6
IN1 OUT1
IN2 OUT2
TPGAPC5
IN1 OUT1
IN2 OUT2
TPGAPC4
IN1 OUT1
IN2 OUT2
TPGAPC3
IN1 OUT1
IN2 OUT2
TPGAPC2
IN1 OUT1
IN2 OUT2
GUID-EE736EA4-3EF1-4581-BB5A-FE060E1483B9 V1 EN
Figure 34: SELGAPC3
SELGAPC4SELGAPC4 is used to configure the OSWGAPC outputs to LEDs. Master trip signalsare connected to SELGAPC4 via TRPPTRC. Start, trip and alarm signals areconnected to SELGAPC4 directly. SELGAPC4 outputs are connected toprogrammable LEDs: LED1...LED8.
Section 3 1MRS758335 DREU611 standardized configuration
52 REU611Application Manual
![Page 59: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/59.jpg)
SELGAPC4
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
OUT_7
OUT_8
IN_14
IN_15
IN_16
IN_17
LED1
LED2
LED3
LED4
LED5
LED6
LED7
LED8
Start 1
Start 2
Start 3
Start 4
Trip 1
Alarm 1
Trip 2
Trip 3
Trip 4
Alarm 2
Alarm 3
Alarm 4
Alarm 5
Alarm 6
CB Close
CB Open 1
CB Open 2
CBXCBR_EXE_OP
TRPPTRC1_TRIP
GUID-80F9A51C-77DC-4BCF-BE66-EAAD07B014BB V1 EN
Figure 35: SELGAPC4
Master trip OSWGAPCsOSWGAPC1 and OSWGAPC2 are used to route the protection function operatesignals to master trip. OSWGAPC1 and OSWGAPC2 have the same inputs from theprotection function's operate signals. The output is connected to TRPPTRC function.
1MRS758335 D Section 3REU611 standardized configuration
REU611 53Application Manual
![Page 60: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/60.jpg)
OSWGAPC1
TRPPTRC 1_OPERATEMaster trip 1
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
NSPTOV1_OPERATE
PHPTOV1_OPERATE
NSPTOV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
PSPTUV1_OPERATE
PSPTUV2_OPERATE
GUID-3808B480-39FF-4E00-8340-BBD1497AF4E2 V1 EN
Figure 36: OSWGAPC1
Section 3 1MRS758335 DREU611 standardized configuration
54 REU611Application Manual
![Page 61: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/61.jpg)
Master trip 2TRPPTRC 2_OPERATE
OSWGAPC2
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
NSPTOV1_OPERATE
PHPTOV1_OPERATE
NSPTOV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
PSPTUV1_OPERATE
PSPTUV2_OPERATE
GUID-9D1302AD-C7CF-4081-83E4-CC1BB38775AE V1 EN
Figure 37: OSWGAPC2
Start OSWGAPCsOSWGAPC instances 3...6 are used to configure the protection start signals. Thesefour OSWGAPCs have the same inputs from the protection function start signals. Theoutput is routed to SELGAPC3 via TPGAPC timer, and routed to SELGAPC4directly.
1MRS758335 D Section 3REU611 standardized configuration
REU611 55Application Manual
![Page 62: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/62.jpg)
TPGAPC1_IN1
SELGAPC4_IN_4Start 1
OSWGAPC3
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_START
PHPTUV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
PHPTOV1_START
NSPTOV2_START
PHPTUV1_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
PHPTOV3_START
PHPTOV2_START
IN_14
IN_15
PSPTUV1_START
PSPTUV2_START
GUID-1CEEF190-B5CB-40C0-8D3B-B85233DB3BDF V1 EN
Figure 38: OSWGAPC3
Section 3 1MRS758335 DREU611 standardized configuration
56 REU611Application Manual
![Page 63: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/63.jpg)
OSWGAPC4
OUT
Start 2 TPGAPC1_IN2
SELGAPC4_IN_5
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
PHPTUV2_START
PHPTUV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
PHPTOV1_START
NSPTOV2_START
PHPTUV1_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
PHPTOV3_START
PHPTOV2_START
IN_14
IN_15
PSPTUV1_START
PSPTUV2_START
GUID-BBEFEA55-AEDB-44D2-943B-C0151C9C7D3C V1 EN
Figure 39: OSWGAPC4
1MRS758335 D Section 3REU611 standardized configuration
REU611 57Application Manual
![Page 64: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/64.jpg)
Start 3 TPGAPC2_IN1
SELGAPC4_IN_6
OSWGAPC5
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
PHPTUV2_START
PHPTUV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
PHPTOV1_START
NSPTOV2_START
PHPTUV1_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
PHPTOV3_START
PHPTOV2_START
IN_14
IN_15
PSPTUV1_START
PSPTUV2_START
GUID-37731A72-0467-4010-8A5F-29834699000A V1 EN
Figure 40: OSWGAPC5
Section 3 1MRS758335 DREU611 standardized configuration
58 REU611Application Manual
![Page 65: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/65.jpg)
OSWGAPC6
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
IN_14
IN_15
Start 4 TPGAPC2_IN2
SELGAPC4_IN_7
PHPTUV2_START
PHPTUV3_START
FRPFRQ1_START
FRPFRQ2_START
NSPTOV1_START
PHPTOV1_START
NSPTOV2_START
PHPTUV1_START
ROVPTOV1_START
ROVPTOV2_START
ROVPTOV3_START
PHPTOV3_START
PHPTOV2_START
PSPTUV1_START
PSPTUV2_START
GUID-21366E41-D912-47F4-8E79-0A1897838DE8 V1 EN
Figure 41: OSWGAPC6
Trip OSWGAPCsOSWGAPC instances 7...10 are used to configure the protection operate signalswhich belong to the trip group. These four OSWGAPCs have same inputs from theoperate signals of the protection functions. The output is routed to SELGAPC3 viaTPGAPC timer, and routed to SELGAPC4 directly.
1MRS758335 D Section 3REU611 standardized configuration
REU611 59Application Manual
![Page 66: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/66.jpg)
Trip 1 TPGAPC3_IN1
SELGAPC4_IN_8
OSWGAPC7
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
PSPTUV1_OPERATE
PHPTOV1_OPERATE
PSPTUV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
NSPTOV1_OPERATE
NSPTOV2_OPERATE
GUID-4C59046E-A106-47B2-9278-872145522C9A V1 EN
Figure 42: OSWGAPC7
Section 3 1MRS758335 DREU611 standardized configuration
60 REU611Application Manual
![Page 67: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/67.jpg)
Trip 2 TPGAPC3_IN2
SELGAPC4_IN_9
OSWGAPC8
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
PSPTUV1_OPERATE
PHPTOV1_OPERATE
PSPTUV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
NSPTOV1_OPERATE
NSPTOV2_OPERATE
GUID-89D0D99C-9A90-4F63-9E25-251108BFA4B3 V1 EN
Figure 43: OSWGAPC8
1MRS758335 D Section 3REU611 standardized configuration
REU611 61Application Manual
![Page 68: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/68.jpg)
Trip 3 TPGAPC4_IN1
SELGAPC4_IN_10
OSWGAPC9
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
PSPTUV1_OPERATE
PHPTOV1_OPERATE
PSPTUV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
NSPTOV1_OPERATE
NSPTOV2_OPERATE
GUID-689B84B6-25A0-4CB7-A374-ED2E73A41A91 V1 EN
Figure 44: OSWGAPC9
Section 3 1MRS758335 DREU611 standardized configuration
62 REU611Application Manual
![Page 69: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/69.jpg)
Trip 4 TPGAPC4_IN2
SELGAPC4_IN_11
OSWGAPC10
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
IN_13
OUT
PHPTUV2_OPERATE
PHPTUV3_OPERATE
FRPFRQ1_OPERATE
FRPFRQ2_OPERATE
PSPTUV1_OPERATE
PHPTOV1_OPERATE
PSPTUV2_OPERATE
PHPTUV1_OPERATE
ROVPTOV1_OPERATE
ROVPTOV2_OPERATE
ROVPTOV3_OPERATE
PHPTOV3_OPERATE
PHPTOV2_OPERATE
IN_14
IN_15
NSPTOV1_OPERATE
NSPTOV2_OPERATE
GUID-BA32398F-8C21-4566-9C0F-A7874307413C V1 EN
Figure 45: OSWGAPC10
Alarm OSWGAPCsOSWGAPC instances 11...16 are used to configure the alarm signals which belong tothe alarm group. These six OSWGAPCs have same inputs from the alarm signals. Theoutput is routed to SELGAPC3 via TPGAPC timer, and routed to SELGAPC4directly.
1MRS758335 D Section 3REU611 standardized configuration
REU611 63Application Manual
![Page 70: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/70.jpg)
OSWGAPC11
OUT
Alarm 1 TPGAPC5_IN1
SELGAPC4_IN_12
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-53D8F638-3D65-4A83-BD3A-CCCF5C4F9CFC V1 EN
Figure 46: OSWGAPC11
Alarm 2 TPGAPC5_IN2
SELGAPC4_IN_13
OSWGAPC12
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-D3C08406-962B-44DB-B830-B53093100311 V1 EN
Figure 47: OSWGAPC12
Section 3 1MRS758335 DREU611 standardized configuration
64 REU611Application Manual
![Page 71: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/71.jpg)
Alarm 3 TPGAPC6_IN1
SELGAPC4_IN_14
OSWGAPC13
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-150A454F-3B7B-4CE0-8295-B7F038A2D45B V1 EN
Figure 48: OSWGAPC13
Alarm 4 TPGAPC6_IN2
SELGAPC4_IN_15
OSWGAPC14
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-57BA3BF3-AEFD-4BEF-9B1E-DEE4C88F635B V1 EN
Figure 49: OSWGAPC14
1MRS758335 D Section 3REU611 standardized configuration
REU611 65Application Manual
![Page 72: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/72.jpg)
Alarm 5 TPGAPC7_IN1
SELGAPC4_IN_16
OSWGAPC15
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-945CCB97-C5D5-419E-8A17-E70CF2D1AB2D V1 EN
Figure 50: OSWGAPC15
Alarm 6 TPGAPC7_IN2
SELGAPC4_IN_17
OSWGAPC16
OUT
IN_1
IN_2
IN_3
IN_4
IN_5
IN_6
IN_7
IN_8
IN_9
IN_10
IN_11
IN_12
TRPPTRC1_CL_LKOUT
TRPPTRC2_CL_LKOUT
RDRE_TRIGGERED
SELGAPC1_OUT_6
TCSSCBR2_ALARM
TCSSCBR1_ALARM
BUS_VT_MCB_OPEN
OVERVOLTAGE_OPERATE
UNDERVOLTAGE_OPERATE
External Trip
GUID-34F936D2-922C-4805-8350-25028A79223D V1 EN
Figure 51: OSWGAPC16
Section 3 1MRS758335 DREU611 standardized configuration
66 REU611Application Manual
![Page 73: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/73.jpg)
3.4.4.4 GOOSE
There are 20 GOOSERCV_BIN functions in the configuration. EachGOOSERVC_BIN function can be connected to one received binary GOOSE signal.The signal connection can be configured in PCM600.
• GOOSERCV_BIN instances 0 and 1 are used for blocking protection functions.Signals from these two GOOSERCV_BINs are connected to ISWGAPC9.ISWGAPC9 is used to configure which protection function block is blocked.
• GOOSERCV_BIN instances 2 and 3 are used for tripping from GOOSE. Signalsfrom these two GOOSERCV_BINs are connected to TRPPTRC1 andTRPPTRC2 trip.
• GOOSERCV_BIN instances 4 to 19 are used for blocking circuit breakeroperation. Signals from these 16 GOOSERCV_BINs are connected toISWGAPC10. ISWGAPC10 is used to configure the GOOSE input signal toblock the circuit breaker open or close operation.
CBXCBR1_BLK_CLOSE
CBXCBR1_BLK_OPEN
GOOSERCV_BIN:1
GOOSERCV_BIN:0
OR ISWGAPC9GOOSE Blcoking
GOOSERCV_BIN:3
GOOSERCV_BIN:2
OR
GOOSE
External Trip
GOOSERCV_BIN:5
GOOSERCV_BIN:4
GOOSERCV_BIN:19
OR ISWGAPC10GOOSE Block CB
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
GUID-4388A3EC-3534-4618-A0CD-47147FD0591E V1 EN
Figure 52: GOOSE overview
ISWGAPC9ISWGAPC9 is used to configure which protection functions can be blocked by thereceived GOOSE signals. ISWGAPC9 inputs are received GOOSE signals from
1MRS758335 D Section 3REU611 standardized configuration
REU611 67Application Manual
![Page 74: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/74.jpg)
GOOSERCV_BIN:0 and GOOSERCV_BIN:1. The outputs are connected to blockinputs of the protection functions.
ISWGAPC9
INGOOSE Blocking
OUT_1
OUT_2
OUT_3
OUT_4
OUT_5
OUT_6
OUT_7
OUT_8
OUT_9
OUT_10
OUT_11
OUT_12
OUT_13
OUT_14
OUT_15
PHPTOV1_BLOCK
PHPTOV2_BLOCK
PHPTOV3_BLOCK
PHPTUV1_BLOCK
PHPTUV2_BLOCK
PHPTUV3_BLOCK
ROVPTOV1_BLOCK
ROVPTOV2_BLOCK
ROVPTOV3_BLOCK
FRPFRQ1_BLOCK
FRPFRQ2_BLOCK
NSPTOV1_BLOCK
NSPTOV2_BLOCK
PSPTUV1_BLOCK
PSPTUV2_BLOCK
GUID-0FCCA7F3-9413-49E1-8DF9-A46703C2DBAF V1 EN
Figure 53: ISWGAPC9
ISWGAPC10ISWGAPC10 is used to block the circuit breaker operation from the received GOOSEsignals. ISWGAPC10 inputs are received GOOSE signals from GOOSERCV_BIN:4 to GOOSERCV_BIN:19. The outputs are connected to block the circuit breaker'sclose and open operation.
ISWGAPC10
INOUT_1
OUT_2
CBXCBR1_BLK_CLOSE
CBXCBR1_BLK_OPEN
GOOSE Block CB
GUID-7DC47FBA-D2C9-4696-B947-0A2C9F67C05E V1 EN
Figure 54: ISWGAPC10
Section 3 1MRS758335 DREU611 standardized configuration
68 REU611Application Manual
![Page 75: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/75.jpg)
Section 4 Protection relay's physical connections
4.1 Inputs
4.1.1 Energizing inputs
4.1.1.1 Phase voltage
Table 16: Phase voltage inputs
Terminal DescriptionX130:11-12 U1
X130:13-14 U2
X130:15-16 U3
Table 17: Reference voltage measurement
Terminal DescriptionX130:9-10 U12B
4.1.1.2 Residual voltage
Table 18: Residual voltage
Terminal DescriptionX130:17-18 Uo
4.1.2 Auxiliary supply voltage input
The auxiliary voltage of the protection relay is connected to terminals X100:1-2. AtDC supply, the positive lead is connected to terminal X100:1. The permitted auxiliaryvoltage range (AC/DC or DC) is marked on the top of the LHMI of the protectionrelay.
Table 19: Auxiliary voltage supply
Terminal DescriptionX100:1 + Input
X100:2 - Input
1MRS758335 D Section 4Protection relay's physical connections
REU611 69Application Manual
![Page 76: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/76.jpg)
4.1.3 Binary inputs
The binary inputs can be used, for example, to generate a blocking signal, to unlatchoutput contacts, to trigger the disturbance recorder or for remote control of protectionrelay settings.
Binary inputs of slot X130 are available with AIM0006 module.
Table 20: Binary input terminals X130:1-8 with AIM0006 module
Terminal DescriptionX130:1 BI1, +
X130:2 BI1, -
X130:3 BI2, +
X130:4 BI2, -
X130:5 BI3, +
X130:6 BI3, -
X130:7 BI4, +
X130:8 BI4, -
4.2 Outputs
4.2.1 Outputs for tripping and controlling
Output contacts PO1, PO2, PO3 and PO4 are heavy-duty trip contacts capable ofcontrolling most circuit breakers. In the factory default configuration, the trip signalsfrom all the protection stages are routed to PO3 and PO4.
Table 21: Output contacts
Terminal DescriptionX100:6 PO1, NO
X100:7 PO1, NO
X100:8 PO2, NO
X100:9 PO2, NO
X100:15 PO3, NO (TCS resistor)
X100:16 PO3, NO
X100:17 PO3, NO
X100:18 PO3 (TCS1 input), NO
X100:19 PO3 (TCS1 input), NO
X100:20 PO4, NO (TCS resistor)
X100:21 PO4, NO
X100:22 PO4, NO
X100:23 PO4 (TCS2 input), NO
X100:24 PO4 (TCS2 input), NO
Section 4 1MRS758335 DProtection relay's physical connections
70 REU611Application Manual
![Page 77: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/77.jpg)
4.2.2 Outputs for signalling
Output contacts SO1 and SO2 in slot X100 can be used for signalling on start andtripping of the protection relay. On delivery from the factory, the start and alarmsignals from all the protection stages are routed to signalling outputs.
Table 22: Output contacts X100:10...14
Terminal DescriptionX100:10 SO1, common
X100:11 SO1, NC
X100:12 SO1, NO
X100:13 SO2, NO
X100:14 SO2, NO
4.2.3 IRF
The IRF contact functions as an output contact for the self-supervision system of theprotection relay. Under normal operating conditions, the protection relay is energizedand the contact is closed (X100:3-5). When a fault is detected by the self-supervisionsystem or the auxiliary voltage is disconnected, the contact X100:3-5 drops off and thecontact X100:3-4 closes.
Table 23: IRF contact
Terminal DescriptionX100:3 IRF, common
X100:4 Closed; IRF, or Uaux disconnected
X100:5 Closed; no IRF, and Uaux connected
1MRS758335 D Section 4Protection relay's physical connections
REU611 71Application Manual
![Page 78: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/78.jpg)
72
![Page 79: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/79.jpg)
Section 5 Glossary
100BASE-FX A physical medium defined in the IEEE 802.3 Ethernetstandard for local area networks (LANs) that uses fiber opticcabling
100BASE-TX A physical medium defined in the IEEE 802.3 Ethernetstandard for local area networks (LANs) that uses twisted-pair cabling category 5 or higher with RJ-45 connectors
611 series Series of numerical protection and control relays for low-endprotection and supervision applications of utility substations,and industrial switchgear and equipment
CB Circuit breakerCSV Comma-separated valuesDAN Doubly attached nodeDC 1. Direct current
2. Disconnector3. Double command
DPC Double-point controlEMC Electromagnetic compatibilityEthernet A standard for connecting a family of frame-based computer
networking technologies into a LANFIFO First in, first outFTP File transfer protocolFTPS FTP SecureGOOSE Generic Object-Oriented Substation EventHSR High-availability seamless redundancyHTTPS Hypertext Transfer Protocol SecureIEC International Electrotechnical CommissionIEC 61850 International standard for substation communication and
modelingIEC 61850-8-1 A communication protocol based on the IEC 61850 standard
seriesIED Intelligent electronic deviceIEEE 1686 Standard for Substation Intelligent Electronic Devices'
(IEDs') Cyber Security Capabilities
1MRS758335 D Section 5Glossary
REU611 73Application Manual
![Page 80: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/80.jpg)
IP address A set of four numbers between 0 and 255, separated byperiods. Each server connected to the Internet is assigned aunique IP address that specifies the location for the TCP/IPprotocol.
IRIG-B Inter-Range Instrumentation Group's time code format BLAN Local area networkLC Connector type for glass fiber cable, IEC 61754-20LCD Liquid crystal displayLED Light-emitting diodeLHMI Local human-machine interfaceMAC Media access controlMCB Miniature circuit breakerMMS 1. Manufacturing message specification
2. Metering management systemModbus A serial communication protocol developed by the Modicon
company in 1979. Originally used for communication in PLCsand RTU devices.
PCM600 Protection and Control IED ManagerPO Power outputPRP Parallel redundancy protocolREU611 Voltage protection and control relayRJ-45 Galvanic connector typeRS-485 Serial link according to EIA standard RS485RSTP Rapid spanning tree protocolSAN Single attached nodeSNTP Simple Network Time ProtocolSO Signal outputWAN Wide area networkWHMI Web human-machine interface
Section 5 1MRS758335 DGlossary
74 REU611Application Manual
![Page 81: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/81.jpg)
75
![Page 82: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/82.jpg)
![Page 83: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/83.jpg)
![Page 84: Application Manual REU611 Voltage Protection and Control · 2019-05-16 · The protection and control engineer must be experienced in electrical power engineering and have knowledge](https://reader030.vdocument.in/reader030/viewer/2022040923/5e9e78ca119939727b2efeaf/html5/thumbnails/84.jpg)
ABB Distribution SolutionsDistribution AutomationP.O. Box 699FI-65101 VAASA, FinlandPhone +358 10 22 11
www.abb.com/mediumvoltagewww.abb.com/relion
—
© Copyright 2019 ABB. All rights reserved. 1MR
S75
8335
D