approach (connection) oslo s · allows for both conventional drilling and blasting and the use of a...

10
Approach (connection) Oslo S Description The project planning assignment in connection with “Approach Oslo S” will be geographically delimited as follows: In the west with full connection of the new Follo Line and rebuilt Østfold Line to the track area at Oslo S. In the east at the transition to mountain tunnel and - for rebuilt outgoing Østfold Line - in the transition to existing track arrangement at Loenga. The assignment includes, in addition to the two new tracks for the new Follo Line, a full rebuild of the existing Østfold Lines approach to and exit from Oslo S. Running four new tracks into Oslo S is demanding. Also, the line will go through a densely built-up area with cultural heritage sites and various technical constructions. All work in the construction phase will have simultaneous traffic diversion and there will be considerable require- ments for flexibility and robustness in the phase plans during the construction period. The construction will have a high degree of complexity with many interfaces between trades and good coordination between the different trade areas is decisive. The approach for the new Follo Line will mean changing the present track arrangement at Oslo S. In the main plan- ning work, JBV has arrived at fixed routes, with the exception of the outbound Follo Line where there are two alterna- tive routes, one that affects Gamlebyen graveyard and one that goes to the west of it. The outbound Østfold Line will have a new route out of Oslo S where it goes through Klypen before being joined to the old route. The inbound Østfold Line will branch off its original route at Sydhavna and go into a short stretch of tunnel, before continuing under Loenga and through Klypen into Oslo S. The inbound Follo Line will, on the approach to Oslo S, lie on the same route as the new inbound Østfold Line, through Klypen and into Oslo S. The outbound Follo Line will use the present route for the Østfold Line out of Oslo S and continue n a new route either east or west of Gamlebyen graveyard, depending on the preferred option, and onward through Ekebergåsen. The assignment includes many challenges in which many general objectives, guidelines and sector interests shall be coordinated and safeguarded. Planning in the area must therefore be done as an interdisciplinary collaboration be- tween many different interests. Some of the most important stakeholders in the area are the City of Oslo, the Director- ate for Cultural Heritage and affected parties along the line of the new route.

Upload: vantuong

Post on 03-Mar-2019

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Approach (connection) Oslo S

Description

The project planning assignment in connection with “Approach Oslo S” will be geographically delimited as follows:• InthewestwithfullconnectionofthenewFolloLineandrebuiltØstfoldLinetothetrackareaatOsloS.• Intheeastatthetransitiontomountaintunneland-forrebuiltoutgoingØstfoldLine-inthetransitiontoexistingtrackarrangementatLoenga.

Theassignmentincludes,inadditiontothetwonewtracksforthenewFolloLine,afullrebuildoftheexistingØstfoldLinesapproachtoandexitfromOsloS.

RunningfournewtracksintoOsloSisdemanding.Also,thelinewillgothroughadenselybuilt-upareawithculturalheritagesitesandvarioustechnicalconstructions.

Allworkintheconstructionphasewillhavesimultaneoustrafficdiversionandtherewillbeconsiderablerequire-mentsforflexibilityandrobustnessinthephaseplansduringtheconstructionperiod.Theconstructionwillhaveahigh degree of complexity with many interfaces between trades and good coordination between the different trade areasisdecisive.

TheapproachforthenewFolloLinewillmeanchangingthepresenttrackarrangementatOsloS.Inthemainplan-ningwork,JBVhasarrivedatfixedroutes,withtheexceptionoftheoutboundFolloLinewheretherearetwoalterna-tiveroutes,onethataffectsGamlebyengraveyardandonethatgoestothewestofit.

TheoutboundØstfoldLinewillhaveanewrouteoutofOsloSwhereitgoesthroughKlypenbeforebeingjoinedtotheoldroute.TheinboundØstfoldLinewillbranchoffitsoriginalrouteatSydhavnaandgointoashortstretchoftunnel,beforecontinuingunderLoengaandthroughKlypenintoOsloS.

TheinboundFolloLinewill,ontheapproachtoOsloS,lieonthesamerouteasthenewinboundØstfoldLine,throughKlypenandintoOsloS.

TheoutboundFolloLinewillusethepresentroutefortheØstfoldLineoutofOsloSandcontinuenanewrouteeithereastorwestofGamlebyengraveyard,dependingonthepreferredoption,andonwardthroughEkebergåsen.

Theassignmentincludesmanychallengesinwhichmanygeneralobjectives,guidelinesandsectorinterestsshallbecoordinatedandsafeguarded.Planningintheareamustthereforebedoneasaninterdisciplinarycollaborationbe-tweenmanydifferentinterests.SomeofthemostimportantstakeholdersintheareaaretheCityofOslo,theDirector-ateforCulturalHeritageandaffectedpartiesalongthelineofthenewroute.

Page 2: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Quantities and progress

Progress and phase schedule:

Phase00 PreparatoryworkPhase10 ConstructionsinKlypenandLoengaPhase20 BuildinginboundØstfoldandFolloLinesPhase30 ConstructionspermanentØstfoldLinePhase40 TracklayingpermanentØstfoldLinePhase50 BuildingoutboundØstfoldLinePhase60 Completionofconstruction

Concretequantities:Approx.50,000m3

Sheetpilingquantity:Approx.40,000m2

Reinforcement:8,000tonnes

Jetpiling:Approx.8,000m3

Lime/cementcolumns:Approx.70,000m3

Metresoftrack:Approx.7,000m

Excavatedmass:Approx.200,000m3

Back-filledmass:Approx.80,000m3

All quantities are stipulated in accordance with provisional Main Plan.

Contact

Projectmanager:PerIversenPhone: +4791655954Email: [email protected]

Page 3: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Tunnelen

ConceptAnew19kmtunnelisplannedforthenewdoubletrackOslo-Ski.Basedonsafetyanalyses,RAManalysesandcapacityassessments,ithasbeendecidedtobuildtwosingletracktunnelswithacrosspassageevery500m.Thisallowsforbothconventionaldrillingandblastingandtheuseofatunnelboringmachine(TBM).Thechoiceofmethodwillbemadeinthedetailplanningphase.

Tunnel cross sectionThesizeofcrosssectionwilldependondesignspeed.Themainplanincludesdrawingsforboth200kphand250kph.Theprovisionallychosennetcrosssectionfor250kphis60m2.InaccordancewithGermanguidelines,thisisapprovedforspeedsof250-300kph.Blastingcrosssectionwouldthusbeabout87m2,andfortheTBMsolutionabout10.6mboreddiameter.Includingadittunnels,crosspassagesetc.,thiswillgiveabout4mill.m3oftunnelspoil.

Bedrock geologyThebedrockintheprojectareaconsistsprimarilyofPrecambriangneisstypesandsomeamphibolite.InadditionthereareanumberoferuptivedikesfromthePermianperiod,mostaroundametrethickbutafewgreaterthan10m.Sedimentaryshaletypesoccurinaveryshortstretchtothenorth,intowardsOsloS.

TherocksarehardwithUCS(uniaxialcompressivestrength)around100-200MPaforgneissandupto270foram-phibolite.Quartzcontentvariesbetweenthedifferentgneisstypesbetween25%and40%.ThebedrockisrelativelylittlebrokenupandhastwomainfracturesetsorientedE-WandSE-NWwithasteepdrop.ThebedrockstructureintheprojectareastretchesN-StoNW-SE,apartfrominthefarsouthwherethedirectionisE-W.

Injection, sealing strategy and watertightness requirementsAreaswithpossiblesubsidence-sensitivesoilandvaluablenaturalhabitatsonpartsofthetunnelsectionhavebeenidentified.Theterrainoverthetunnelislargelybelowthemarinelimitandincertainareastherearesubstantialclayandsiltdeposits.Watertightnessrequirementsforthetunnelwillthereforebedefined,butnotallareasalongtherouteareequallysensitivetogroundwaterlowering.

Bothsubsidence-sensitivebuilt-upareasandnaturalareashavebeenassessedandpreliminaryrequirementsforsealinghavebeengivenforthedifferentsubsections.Thewatertightnessrequirementswillbeadjustedasmoresur-veysaremadeandmoreinformationisavailableaboutgroundconditions.Provisionallythefollowingwatertightnessrequirementshavebeenset:

Page 4: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

NordstrandplateauandfromSofiemyrtotheopeningtowardsSki:4-8l/min/100mUpperparts:10-12l/min/100m

Inareaswherethereareparticularlystringenttargetsforleakage,orwheresatisfactorysealingcannotbeachievedwithpre-injection,temporarywaterinfiltration,post-injectionandpossiblyalsowaterproofconcretecastingwillberelevant.

Thesealingstrategyforblastedtunnelsisbasedonpre-injection.Fortunnelscutwithtunnelboringmachines(TBMs),awatertightconcreteliningcomposedofsegmentswithwatertightcaulkingbetweenthesegmentsisrelevant.Dur-ingtheconstructionphase,waterinfiltrationfromthesurfacemaybenecessary.HowthetunnelistobesealedwhenusingTBMswillbestudiedmorecloselyinthedetailplanningphase.

ImplementationThechoiceoftunnellingmethodisthefactorofmostsignificanceforimplementation.Withconventionaloperations,therewillbemanyadits,withrigareastobesitedinadenselybuilt-upareaandtransportofspoiloveralreadystronglyimpactedroads,partlythroughbuilt-upareas.Itisprovisionallyestimatedthat7-8aditswillberequiredtoachieveanacceptableconstructiontime.Strictrequirementsforthetunnel’swatertightnessmeanreducedprogressinthoseareasthatarevulnerabletoleakage.IftunnellingbyTBMischosen,therewillonlybeaneedfortwoorthreeaditsandsolessimpactonthesurroundings.WiththeTBMalternative,operationisplannedfromanaditapproximatelyinthemiddle,tunnellingusingtwoma-chinesnorthwardsandtwosouthwards-thatistosay4tunnelboringmachinesinall.Thecrosspassagesbetweenthetunnelsevery500metrescanbeblastedatthesametimetunnelboringisproceeding.

Variousmachinetypeshavebeenconsidered,bothopenandshielded.Ifanopenmachineisused,injectionandsecuringworkmustbeperformedaswithconventionaltunnelling.Muchofthetimewillbetakenupinwaterproofing,withlesstimefortunnelboring.ThismeansthatwewouldnotbeabletousethefullpotentialofthehighborespeedsthataTBMcannormallyachieve.Neitherbyusingsuchamachinewouldwehaveanybenefitinrelationtoconven-tionaltunnelling,takingrocksecuringandwaterandfrostprotectionintoaccount.

Contact

Projectmanager:LiseBackerPhone: +4790554403Email: [email protected]

Page 5: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Open section north of Ski station (Langhus – Ski)

Present situationTheareawheretheexistingØstfoldLineistodayispartofaculturallandscapeofnationalandarchaeologicalvalue.Therehasbeenhumansettlementinthislandscapesinceancienttimesandautomaticallyprotectedculturalheritagesiteshavebeenrecordedinseveralplaceswithintheareaofoperations.Existingrailtrackrunspartlythroughcuttingsandpartlyonembankments,ontheinterfacebetweenforestandculti-vatedland.TherearelevelcrossingstothefarmsofEndsjøandRoås.

Superstructure/RouteTheopensectionincludesgroundworkbothinconnectionwiththenewFolloLineandfortherebuildingoftheexist-ingØstfoldLine.ThesectionstretchesfromthetunnelopeninginthenorthtotheareasouthofKapelldammenfortheFolloLineandfromRoåsfarmtothesameareasouthofKapelldammenfortheØstfoldLine.Intotalthisrepresentsabout1,200metresofnewFolloLineandabout2,000metresofnew/rebuiltØstfoldLine.1,000metresofnewpassingsidingforgoodstrainswillalsobebuiltinthissector.ThepassingsidingforgoodstrainsbranchesoffoftheoutboundØstfoldLinebyRoåsfarmandjoinstheoutboundFolloLinesouthofEndsjøfarm.Togivetheoptionofbetterlandusageinthefuture,partoftheØstfoldLinewillberebuiltandrunparallelwiththeFolloLine.

Substructure/Ground conditionsThegroundconditionsinthesectorvaryfromexposedrockinthenorthtosoilover50metresthickwestofKapell-dammen.OutofSkistation,theroutecutsthroughaterminalmoraineridge.FurthernorthpastKapelldammentherearemarineandfjorddepositsofgreatthickness.Endsjøfarmliesonaterminalmoraineandfurthernorththerouteliesinthetransitionbetweeninshoredepositsandmarineandfjorddepositsbeforeenteringareasofexposedrock.

Existing railway embankments towards KapelldammenThepresentrailwayembankmentdoesnothavesatisfactoryestimatedstabilityinrelationtocurrentsafetyprinciples.NewrailwayconstructionwillnotinvolveexcavatingtheexistingembankmenttowardsKapelldammen.Stabilisingmeasuresfortheembankmentwillbecarriedoutusinggroundreinforcement,possiblesupportingembankmentandpossiblyincombinationwithloweringtheterrainpastKapelldammen.

Page 6: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Emergency evacuation area and access for operationsAnareaforemergencyevacuationoftrainsinthetunnelwillbeestablished.Accesstotherailloopsandaserviceroadalongthetrackwillalsobeestablished.

Constructions:• Access to Roås farmTheconstructioncrossestheaccessroadtoRoåsfarminthatexcavationandblastingforthepassingsidingforgoodstrainsaffectsthefoundationfortheexistingbridgeovertheØstfoldLine.Anewunstressedreinforcedoverpasswillbeestablished.• Tunnel portals for the Follo LineConcreteculvertswillbeestablishedintheextensionofthemountaintunnelsfortheFolloLine• Crossing RoåsbekkenThestreamcurrentlycrossesbelowthepresentØstfoldLineandwillalsocrossthenewtracks.Thestreammustbeloweredabout10metresinordertorunbelowthefutureFolloLine.• Retaining wall between the tracks Becauseoftheheightdifferencebetweenthetracks,retainingwallsmustbeestablished,includingbetweentheØst-foldLineandthepassingsidingforgoodstrainsandbetweentheFolloLineandtheØstfoldLine.• Access to Endsjø farmOntheeasternsideofEndsjøfarm,therailwayconstructionliesinadeepcuttingandcreatesabarrierbetweenthefarmandtheareastotheeast.Inordertoreducethewidthofthecutting,retainingwallswillbebuiltthroughthecut-ting.Ontopoftheseitwillbeoverbuilt,withabridgetoconnectthefarmtotheareastotheeast.• Noise screeningTheareashallhavenoisescreening;noisescreenswillbebuilttotheextentnecessary.

Contact

Projectmanager:SverreLerbakPhone: +4740433348Email: [email protected]

Page 7: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Ås passing track

IntroductionÅspassingsidingislocatedsouthofSkistationonthewesttrackoftheØstfoldLineinÅsmunicipality/Akershuscounty.ThemeasureisincludedinProjectOslo-Skiasasub-project.Doublepassingsidingswillbebuilt,withonenewsidingineachdirection.The establishment of the passing siding is based on the following three elements:

1. Capacity-GoodstrainsontheMoss-OsloSsectionhaveconsiderablylowerspeedsthanpassengertrains. Thefunctionofthepassingsidingistooffsetspeeddifferencesbetweendifferenttraintypes,sothatpassen gertrainscanfollowrigidtimetableswithoutbeingaffectedbygoodstrains.2. RobustnessoftrafficsituationandenablingrebuildingofSkistation–TherebuildingofSkistationandde molitionoftrack4mustbecompensatedbyatrackofatleast600metres.Establishingapassingsiding meetsthisneed.3. EnablesrebuildingofSkistation–WiththerebuildingofSkistation(phase30)theavailabilityoftheopera tionalareawillbeconsiderablyreduced.Duringthisperiodthepassingsidingcanbeusedasaturningtrack for passenger trains

General conditionsTheØstfoldLinecurrentlyhasdoubletrackonthesectionOslo–Ski–Sandbukta.BetweenÅsandSkistations,therailwayroutewaschangedbyrebuildingattheendofthe1990s.JustsouthofSkistation,theØstfoldLinerunspartlyintheopenandpartlyintunnels(2).Thelineisintheopenfromkm26.850toÅsstationkm31.000.ThelinegoesbybridgeacrossBølstadbekkenkm27.950–28.233andoveralocalroadatÅsstation.ThesectionbetweenÅsandSkistationsisabout4kmandcurrentspeedvariesbetween100and160kph.Allcross-ingsaregradeseparated.Thepresentdoubletrackhasswitches/pointsatÅsmåsan,km30.172–30.379.Theexistingpointsaresomewhatwornasaresultofrepeatedsubsidence.Thecurrentswitchonthesitecanbemovedandlocationmustbefixedinanewtrackplan.Keytechnicalassumptions/conditionsfortheproject:• Speedforpassengertrainsupto160kphsouthofSkistationwithpresenttechnicalsolutions.• Passingsidingsshallsatisfyfunctionalrequirementsforgoodstrafficin/outofcountrywithtrainlengthupto 750m.• RealisationmustbeseeninrelationtorebuildingofSkistation(phaseplans)

Page 8: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

ScopeThetrackarrangementisassumedtofollowthisprinciple:

Withadditionforaccessroadonbothsides,constructionwidthmustbeatleast40m.Withtheadditionoftemporarywalkingpathandsafetymeasures,thisincreasesto45-50mduringtheconstructionperiod.Noisescreening,powerleadsystemetcwillgobeyondthat.Thepermanentsolutionstillassumesaserviceroad/walkingpathwestofthetrack,i.e.thepresentserviceroadmustbemovedsidewaystoallowroomforoneextratrack.The following general elements will be realised:• Passingsidingwitheffectivelengthofminimum750m• DoubleswitchintheNorth(towardsSki)• Neworrelocationofexistingdoubleswitchinthesouth(towardsÅs)• Pointsheatingforatotalof12points• Extendingexistingcatenarysystem(system-20)• Establishingnewsubstructurewithassociatedfoundation,cablechannelsetc.• Dependingonlocation-associatedconstructions• Dependingonlocation-solutionforstabilisingground• Temporaryrig,securing,phasedconnectionetc.

Progress scheduleItisassumedthatgeneralplanningconditionsareclearedoutsidethesub-project.ThisincludesapprovalofplansandfundingfortheFolloLineandSkistation,aswellaschoiceofsafetysystem.Thesub-projectsaremutuallydepen-dent.Forexample,SkistationcannotberebuiltuntilthefinalconstructionofÅspassingsidingstarts.Thefollowingroughprogressscheduleisforguidance:

Activity DeadlineDetailandzoningplanready Summer2012.Constructionplan Autumn2013Contracting Spring2014Contractstartup Autumn2014Completion Autumn2015Commissioning January2016

Passing siding

Passing sidingOutbound Østfold line

Inbound Østfold line

Oslo Ås

Contact

Projectmanager:TrulsAndersenPhone: +4791656352Email: [email protected]

Page 9: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Railway technology

Track

Oslo central stationAtOsloStherearetwotracksfortheFollolineandtwotracksfortheexistingØstfoldlinethatarebeingremodelledandwillbecome8tracks,soastogivefullflexibilityforchoiceoftrackatOsloS.Here8kmoftrackisbeingremovedand7kmbeinginstalled,and38pointsarebeingremovedand19pointsfitted.

TunnelTheFolloline’stunnelsconsistoftwoboreswithonetrackineachbore.Eitherslabtrackorballastedtrackwillbeestablished.Itwillbedecidedwhetherthetunnelsaretobedesignedfor200kph,250kphor300kph.IfitisdecidedtoestablishfreighttracksfromtheFollolinetunneltoAlnabrugoodsterminal,therewillbeaneedforpointsdesignedforabranchingspeedof110kphandapassingspeedofupto250kph.IfitisdecidedtocreatealinktoafuturehighspeedlinenorthofSkiStation,therewillbeaneedforpointsthatallowtraffictobranchtoandfromSkistationinsidethetunnel.Thesepointswouldneedtoallowspeedsof250–300kphforpassingtrafficandspeedsof200–250kphfortrafficto/fromSkistation.TherewillbenolinksbetweentheFollolinetracksinsidethetunnel.

Open section Ski and Ski station5kmoftrackwillberemovedand10.1kmoftrackestablished,and2pointsarebeingremovedandxpointsfittedintheopen-airsection.TherewillbesomechangesatSkistationaheadoftheactivitiesontheSkiopen-airsectionthatwillmeanestablishingsidings.Also,alltracksandplatformsatthestationwillberebuilt.Thisinvolvesremoving4kmoftrackandestablishing7km,andremoving20pointsandestablishing29points.

Ås overtaking trackItisplannedtoestablish2parallelovertakingtracksofabout1kilometrewithpointsandflyoverloopsateachendanddoublecrossoverbetweenthemaindoubletrack.

GeneralAllpointswillhavedrivedevicesandheatingelementsthatareremotecontrolled.RailsofqualityclassDandsleep-ersoftypeNSB95arethesolutionsweareconsidering.

Signals

Approach Oslo SHereitisplannedtoextendtheexistingsystem,whichisarelaycontrolledGSsystem.

Tunnel, Ski open-air section, Ski station and Ås overtaking track.ThissectionwillhaveanF-ATCsystemthatisconvertibletoERTMSlevel2,ERTMSwithexteriorsignalsoranERTMSlevel2system.ThewillbelocatedatSkistationwithaCTCunitforremotecontrolofOsloS.

Page 10: Approach (connection) Oslo S · allows for both conventional drilling and blasting and the use of a tunnel boring machine (TBM). The choice of method will be made in the detail planning

Electric power

Electric power supply to permanent installationsA22kV/50Hzpowersupplywillbeestablishedtotransformersthatsupplypowertovarioususersalongtheline.Therewillbeaneedfor8-10transformersinthetunneland15transformersaltogether.Therewillbeaneedforcapacityof7,7MVAatnormalloadincluding20%margin.Transformerswillbeofstandarddesignwith100-500kVAcapacity.

Electric power supply to rolling stockA15kV/162/3Hzpowersupplywillbeestablishedtothecatenarysystem,usingautotransformerssupplying±15kV,together30kVpotentialdifference.Aseparateprojectwillsupplyanewconverterstationof100MVA,whichwillprobablybelocatedundergroundinconnectionwiththeFollolinetunnel.Someofthetransformersmayneedtobeestablishedinconnectionwiththis.

Earthing conceptLongitudinalearthleadswillbeestablished.

Catenary system

Approach to Oslo S, Ski open section and Ski stationSystem20andtransitionzonestosystem25willbeestablishedonthesesections.

TunnelTwosystemsarebeingconsideredforthetunnel.TheseareSystem25,whichissimilartotheGermanRe250,andSystemRe330. Telecom

Connection to Oslo S and Ski open-air sectionAAfibreoptictransmissionnetworkwillbeestablished.FortheOsloSareaandtheski-openairsection,aradiomastforthetunnelwillbestablished.

TunnelItisplannedtoequipthetunnelwithredundantradiosystemsforGSM-R,whicharecompatiblewithERTMS,surveillancecameraateachtunnelentrance,multispectrecamerathroughthetunnelforevacuationaidandforpublicGSMandWiFi.

Ski stationSkistationwillbeequippedwithPIAsystem,camerasurveillancesystemandfibreoptictransmissionnetwork.

Contact

Projectmanager:TrulsAndersenPhone: +4791656352Email: [email protected]