CONSTRUCTION
MANAGEMENT
Master of ARCHITECTURE
Instituto Superior Técnico, DECivil e
Arquitectura
Tel: 218 418 355
Construction Management: It is an investment control process
and ressources utilization, (labour, material and equipment) that is
to perform work Construction
The building owner or investor can be:
Public, Privat or Privat with public suport.
Types of Construction:
Residential housing construction;
Institutional and commercial buildings;
Specialized Industrial Construction;
Infrastructure and heavy construction
Project
Efficiency in resource use
Return oninvestment
PrivateCompanies
PublicCompanies
Public supportfor PrivateCompanies
The Main features of Construction Projects are:
(1) Are temporary they have a begining and na end defined;
(2) Must be planned, executed and controlled;
(3) Performing products, services or exclusive results;
(4) Developed by stages and continue with a
progressive development;
(5) Performed by persons and use resources and time
Life Cycle of a Project
CONCEPTION and START PROCESS – It is an importante process.
Must define the issues in general of the construction, the purposes,
must agree budgets and get the approval of the preliminary
program;
PLANNING PROCESS – Formed the design team that thoroughly
analyzes the needs of users and owner. This work is logged in a
document called: Specifying Conditions. Running up previus study
and work plans;
EXECUTION or CONSTRUCTION PROCESS – Coordinating people and
others resources to carry out the plan.
The execution is the period which the idea becomes a reality, the
product (building) is born;
Life Cycle of a Project
CONTROL AND MONITORING – To assure the
purposes of the project are being met, through the
monotoring and regular measurement of work
progress, to check inventory changes relative to
planned;
CLOSURE and EXPLORATION PROCESS – At this
stage draws up a final report and drawings, where
they finalize the costs of the project and is made the
Certicate of Provisional Acceptance
GESTÃO E FISCALIZAÇÃO DE OBRAS
Os grupos de processos de gestão de projetos não são discretos, nem um evento único, são um conjunto de atividades que ocorrem em diferentes níveis de
intensidade ao longo das fases do projecto.
Grupos de Processos
Tempo
Nív
el d
e at
ivid
ade
Fase inicial Fase final
Processosde arranque
Processosde planeamento
Processosde controlo
Processosde execução
Processosde fecho
Life Cycle of a Project
- The end of the phase is marked by a revision of products and
project performance to date;
- The costs increases as the stage progresses;
- The risks decreases as the stage progresses;
- The possibility of the parties involved (architect, engº) to do
amendments of each stage is decreased as the stage
progresses;
- Each speciality enters the work in a given period but is not
independente of the others speciality ( masonery, electicity, etc
Project Manager
Is responsible for the Construction Project Management
Should: To promote the release of building contest,
consideration of applications, contract negociation and his
implemementation. He has to take decisions about:
• Technical Decisions;
Decide how yo use the material that allows the realization of the
dimensional project:
Register Book, Drawings, Bill of Quantities
•Commercial Decisions;
Making and analyses the quantification of the labor costs
The documents used as a basis for implementing
Financial schedule
Lists of unit prices.
Decision Administrative and Planning;
Scope:
Ensure the quality of the project;
Ensure implementation in accordance with the contract
documents.
Project Manager
Project Manager
Financial Decisions;
Measurements and Invoicing. To ensure thebudget is not passed
Human Resource Decisions;
To keep the team well informed
To keep the team well informed and dynamics
Entities involved on Management
• Owner of the workHe has the money to pay all the resources used in the building
• Project ManagerHe is responsible the choice of general contractor and for the success of theinvestment
• FiscalizationThe supervisor work in the interests of the owner of the enterprise. Fulfill
the contarct is the fundamental work of supervision , which passes through
amendments to the project, analysis of these changes and conditions of
reception.
The fiscalization has three simultaneous functions: cost control, quality
control and monitoring of deadlines
• Authors of ProjectsTo do technical assistance , give informations about all the projectsand ask questions
• Director of workHired by the general contractor , will be responsible for , monitor andcoordinate the preparation of budgets and work plans. Is responsiblefor Construction.
• General ContractorHe made the construction contract with the owner of work. It has theresources to do the work
Entities involved on Management
Entities involved on Management
• ProvidersProvide the necessary ressurces for the work, material, labour, equipment, etc
• Safety EngineerResponsible for safety on the site and make the safety and health plan
• Official EntityResponsible for lifetime license of work. . Entity approving the projects
Surveillance director’s ( Fiscalization) responsabilities
He is representing the owner of work. Should ensure the proper execution of the work according to construction projects.Until provisional acceptance has to ensure the quality and safety of workThe main duties are:
• Control or supervision of the execution of works ; • Quality Control of Work;• Environmental Monitoring ; • Security Assurance Execution of Work; • Quantity and Cost Control ; • Planning Control
BIBLIOGRAPHY
[1] Anthony Walker – “Project Management in Construction” – Blackwell publishing,
fifth edition, 2007.
[2] Shohet, Igal M.; Frydman Shay – “Communication Patterns in Construction at
Construction Manager Level” – Journal of Construction Engineering and
Management, ASCE – September/October 2003, pp 570-577.
[3] William R. Duncan – “A Guide to the Project Management Body of Knowledge” –
PMI Standards Committee, PMBOK Guide, 2004.
[4] Curso FUNDEC sobre “Gestão e controlo de custos em obra” – Coordenação Prof.
Pedro Gameiro Henriques (IST). Fevereiro 2008.