Maryland Avenue at Payne Avenue
April 18, 2013
Luke Lortie, EIT651.266.7123
Jerry Auge, PE651.266.7117
![Page 2: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/2.jpg)
Purpose of Project Schedule Funding Proposed Improvements Questions
Meeting Agenda
![Page 3: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/3.jpg)
Improve Safety ◦ Provide Designated Left Turn Lanes◦ Upgrade Signal System◦ Improve Pedestrian Facilities◦ Increase Lane Widths
Purpose of Project
![Page 4: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/4.jpg)
Maryland Avenue ADT:19,800
Payne Avenue ADT: 9,000
130 Crashes at the Inters. (2007-2012)◦ Average of 26 Crashes per Year◦ 53% of Crashes Involve Left Turning Vehicles◦ 25% of Crashes involve Sideswipe or Rear-Ends◦ 22% Pedestrian, Right Turns
Project Background
![Page 5: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/5.jpg)
Crash DataCollision Diagrams provided by the Minnesota
Department of Transportation
![Page 6: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/6.jpg)
Top 50 IntersectionsNumber of Accidents
June 2007 – June 2012
Maryland & Payne #11
![Page 7: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/7.jpg)
40 foot Roadway Width 4 Lanes 10 foot Lane Width No Left Turn Lanes 30 mph Speed Limit Split Phase West Bound
Existing Maryland Avenue
![Page 8: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/8.jpg)
44 Foot Roadway Width (55 Feet at Intersection)
4 Lanes 11 Foot Lane Width Left Turn Lanes on Maryland Avenue 30 mph Speed Limit
Proposed Maryland Avenue
![Page 9: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/9.jpg)
Appraisals/Offers Aug/Sept 2013
Property Acquisition February 2014 Project Approval March 2014 Bid Project April 2014 Bid Award June 2014 Start Construction July 2014 End Construction Sept 2014
Proposed Schedule
![Page 10: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/10.jpg)
Federal $1,498,000County State Aid Highway $1,600,000Municipal State Aid $1,580,000
Total $4,688,000
Estimated Project Funding
![Page 11: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/11.jpg)
Alignment Options: ◦ North ◦ Center ◦ South Alignment
Payne/Maryland Community Center Project South Option Minimizes Impacts to
Residential Houses (Northeast Quadrant)
Maryland Ave. Alignment
![Page 12: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/12.jpg)
Project Layout
![Page 13: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/13.jpg)
Typical Section
![Page 14: April 18, 2013 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117](https://reader035.vdocument.in/reader035/viewer/2022070412/5697bf6f1a28abf838c7d2b0/html5/thumbnails/14.jpg)
Metro Transit Impacts
•Impacts to Bus Route 64 at Payne Ave and Greenbrier St