april 21, 2014 dar es salaam, tanzania richard hosier ...€¦ · 1. to build an efficient and...
TRANSCRIPT
April 21, 2014 Dar es Salaam, Tanzania
Richard Hosier World Bank
To provide an update on efforts to move the RERE project toward implementation ◦ As RERE builds upon the foundation of TEDAP, provide
update on TEDAP off-grid component
Apprise EDP’s group about challenges, both intellectual and operational to moving this forward—to share ideas and to get feedback
To share ideas & obtain guidance with respect to both: ◦ Building upon the Prospectus moving forward ◦ Solving the intellectual & operational challenges being in
remote, off-grid rural electrification
Approved as part of Tanzania SREP Investment Plan by SREP Investment Committee in September 2013
Objectives: 1. To build an efficient and responsive development infrastructure for RE-
based rural electrification 2. To demonstrate its effectiveness by supporting a time-slice of private-
sector investments in off-grid electricity enterprises
To utilize three approaches to electrification in off-grid areas: 1. Mini grids of several hundred kilowatts and up to 10 MW serving a
group of villages, as well as larger customers 2. Micro grids powered by a small, centralised PV array and battery bank,
biomass gasifier, biogas, or other renewable technology 3. Sustainable Solar Market Packages (SSMPs) supplying electricity services
to essential public-service and community facilities (e.g. schools and health clinics), plus sale to private customers using stand-alone solar PV systems
Financial Proposal: SREP $25m; IDA $50m: Other DP’s $46m; Private Sector $58 m; TOTAL: ~$180m
Processing Timing: ◦ To SREP Committee for Decision-meeting review May 2014 (not met) ◦ To WB Board after July 2014 (will be met)
TEDAP began in 2008: Development Objectives 1. On-Grid: To improve the quality and efficiency of the electricity
service provision in the three main growth centers of DSM, Arusha, Kilimanjaro and
2. Off-Grid: To establish a sustainable basis for energy access expansion [and renewable energy development in Tanzania.]*
Total Value> $50m, including ◦ GEF grant ◦ IDA initial financing ◦ IDA additional financing (Credit Line) ◦ Co-financing contributions
SIDA support Russian (ESME TF) Support Carbon Finance Support
*added with Additional Financing in 2010, which also changed the name of the component to Small Power Project Component
Selected indicators
Target Progress to date
% of Target
Standardized Power Purchase Agreements Signed (MW)
20 50.3 252%
Number of Participating Financial Institutions’ loans approved for rural/RE subprojects
4 3 75%
Total installed RE capacity (MW) 25 25.4 102%
Pipeline of new rural household connections 50,000 80,673 161%
Direct beneficiaries, of which number of women (52%)
114,000, of whom 57,000 are women
177,039, of whom 92,060 are women
155%
Number of community (public facilities) connections
1,200 702 59%
Number of (subproject) transactions completed by REA
10 40 400%
First Question: SPP Sector appears to have been jump-started
◦ Allowing for growth pains and lumpy nature of investments, SPP sector has taken off
◦ To date, 25.4 MW are in operation ◦ Another 25 MW of SPPA’s have been signed with developers by
TANESCO; 40 MW of SPPA LoIs also signed ◦ As many as 32 SPP projects under development/preparation ◦ At present, 3 project totaling 27 MW are near to financial closure When they move ahead, they will exhaust existing SPP Credit Line Risk is that break in support to sector will undermine growth Luckily, some EDP’s have expressed interest in providing further CL
support necessary to ensure continuity of support ◦ Uganda Analogue: Uganda, at end of ERT I (2008), 16 MW were financially closed, but not
generating Under ERT II, total SPPs has reached >80 MW
◦ We believe that there exists further depth in the SPP market
Second Question: Answer is SSMP ◦ MEM is implementing as legacy ◦ Contractor has under-performed, not met
obligations, misrepresented products, and not made any effort for private sales
Is this a contractor problem or a systematic problem with SSMP approach? ◦ No clear answer yet but ◦ SSMP seems to be a compromise approach that
serve neither public (clinic, schools) or private (households, businesses) well
◦ Whole may equal less than sum of parts….
1) Evaluation of SSMP to consider what has happened—recently initiated
◦ Examination of SSMP experience in Tanzania compared to other countries (Philippines, Zambia, Honduras, Nicaragua)
Are both public & private markets served well?
Is there a missing element? (micro-finance?)
How does technological advance such as LED’s (Lighting Africa) shape present and future support to PV?
Is SSMP worth continuing or should it be abandoned leading to separate public vs private approaches?
Nature of SPP sector and role of grant instruments to accelerate growth of sector ◦ Matching Grants for Feasibility Studies ◦ Performance Grants for Connection subsidies ◦ Green Generation Performance Grants to front-end load
carbon payments at financial closing ◦ Credit Line support to increase liquidity and therefore
willingness of local private banks to extend loans for SPP’s from 5 to 15 years
Need to assess depth, breadth of SPP sector in TZ ◦ Initial pipeline built around small hydro ◦ Some biomass projects were shovel-ready, regulations
pushed them over the top ◦ How can experience with SPPs inform future work with mini
and micro grids?
BUT, TEDAP includes no explicit support to mini or micro-grids—rather focus is on SPPs—for SPPs, it is a bottom-up approach focusing on low-hanging fruit initiated by private sector
◦ Link to m-grids (mini or micro) requires an understanding of nature of SPP sector
◦ Growth has included 3 types of SPPs 1. SPPs generating for sale to TANESCO only (main or
isolated grid--small IPPs) (example: EA Power, Ngombeni) and perhaps own use (Tanwat or TPC)
2. SPP/SPDs generating for sale to TANESCO as anchor customer and connecting to households in immediate vicinity (eg., Mwenga, Tulila)
3. SPP/SPDs generating for sale to only households/businesses in immediate vicinity (Mawengi)
Experience to date provides some insight into mini or micro grids
◦ Do have experience with one isolated mini-grid selling only to customers and not to TANESCO
◦ Have more experience with mixed mini-grids, selling both to TANESCO as off-taker and to customers
Experience to date includes only small hydro and biomass projects ◦ Both are resource-based…can take place only where resources
are plentiful, at sites on rivers or at biomass processing facilities
◦ This does not correspond to model of mini-grid which is focused on population centers of a given size
◦ Shift from resource-focused SPPs maybe with SPD qualities to population-focused SPPs using a more “footloose” technology mix
Q: What are the 3 delivery mechanisms under RERE? 1. Mini-grids
2. Micro-grids
3. SSMP
Q: So, what is the basis for building upon TEDAP? At Core, building out from the success of the SPP sector
Continuing to support SPPs through financial closure, including Credit Line
Maybe tweaking support to give some advantage to those which are more population-based and less-resource based
Begin to expand for more “footloose” technologies (solar, wind, etc.)
Q: What about SSMP or stand-alone solar? ◦ Current SSMP challenges have drawn attention from positive
case for public PV provision Case for continued support to institutional PV electrification is strong (clinics,
schools)
Number of different configurations depending specific needs (different sizes, levels of clinic) and technology use (lantern library, ICT connection)
◦ Enormous challenge is to find appropriate business model or approach for private sales of PV Performance grants for met business plan targets
Supporting only Lighting Africa certified plug ‘n play
Want to move household PV’s for being a “project” to a “product”
Without micro-financing link, consumer ability to pay is limited
Without trade finance & working capital, growing small, locally-based supply networks is extremely difficult
Any public subsidy could be justified on grounds of getting products up-country to jump-start market
How to stimulate growth in this particular market segment?
Distinction between two are not clear ◦ How to distinguish?
◦ UNF Micro-Grid report not terribly helpful (capacity < 500 kW)
Characteristic Mini-Grid Micro-Grid
Capacity MW (>1MW) kW (< 500 kW)
Nature of Grid Network
Built to standard; “Public Good”, assumable asset
Not necessarily built to standard; may not be assumable asset
Number of connections
Thousands Hundreds
Good being sold
kWh, AC only Tier or “bundle”, AC or DC
Micro-grid
Mini-grid
Willingness to Pay & Consumer Surplus in Electrification
Only existing mini-grids are those owned by TANESCO: Can SREP support the survivors (not incorporated immediately into grid?) ◦ Very costly to operate
◦ Relatively little info
◦ From EWURA’s files, cost of service > $0.487/kWh
◦ Opportunity to examine potential hybridization with PV & batteries (which is more useful?)
◦ Any work done with isolated mini-grids must include focus on energy efficiency improvement and load mgt
Micro-grids in TZ still at pilot stage—can count on one hand
Mini-grids: TANESCO units might be packaged for concession agreements
to large industrial player (Caterpillar, Cummins, GE, etc.)
Or TANESCO, with support, could improve thru useful lifetimes until grid-connected
Any mini-grid work must include EE & Load Mgt
New mini-grids, if population centers identified, could be bid out en masse In region X, identify 20 population centers > 500 hh, need to bid out
for M-grid to serve
Might include public payment for grid (public good); support for pre-payment meters; and public leverage for hybrid generation
Approach makes sense for a grid that is assumable when main grid reaches
Need to know honest length of time until grid reaches
BOT or BOO concession
Micro-grids that have “assumable” asset of network can be treated as mini-grids
Micro-grids with “non-assumable” networks (not built to standards) will require different approach ◦ Perhaps “bottom-up” driven by opportunistic
selection of locations by private sector
◦ Possibly bid out concessions by district or region requiring village coverage with W<population < Y
◦ Still need for population threshold & location
Not necessarily a “Master Plan” (avoid dusty volume production)—action focus
Need to start being concrete, focusing on regions/districts not universal (resource constraints)
Need to use GIS (Prospectus), particularly if we are to design bids targeting specific electrification instruments and needs
Build off of experience with SPPs to develop mini-grids/micro-grids are more population focus
If we are really pushing for scale, need to ◦ Plan realistically for what can be done using all tools ◦ Avoid “magical thinking” ◦ M-grids bring no new analytical or economic tools ◦ Cannot wave a wand and have them appear to supply power
to those without at costs competitive to grid prices
Build from SPP success in resource-focused to population-based SSPs and SPP-m-grids
Utilize range of mini, micro, stand-alone PV, pico-PV and SPPs to increase access
EWURA remains strong asset from regulatory perspective
REA has taken on off-grid responsibilities and executed TEDAP well
First-cut RERE proposal will take serious intellectual and operational work
Need to solve business & delivery model questions…interest & resources to solve in TZ
Thanks for your attention and guidance
Look forward to working with you and keeping you informed
Richard Hosier
World Bank