APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL UPDATE BART STEPP, PUBLIC WORKS DIRECTOR PROJECTS COMPLETED LAST MONTH 1. Horseshoe Lake Park Shelter Renovations – Rollup doors at the entrance ways and concession window and covers on the wall openings have been completed. 2. Annual Traffic Impact Fee Analysis – Attached is the annual analysis of traffic impact fees. Based on the analysis the Traffic Impact Fee base rate of $838 should remain the same. PROJECTS IN PROGRESS 3. Waste Control Contract – The City’s existing contract with Waste Control for solid waste services expires on 12/31/15. City Council has in the past asked about providing 35 gallon container service in addition to the 60 gallon and 90 gallon containers currently provided. This would require additional costs by Waste Control for new carts and to retrofit equipment. Attached is a proposal by Waste Control. In exchange for extending the contract another 10 years they would provide 35 gallon carts at no extra charge. Costs for a 35 gallon and 60 gallon customer would be the same. Joe Willis with Waste Control will be at workshop to discuss the proposal with you. 4. Scott Reconnection Study Project – Received letter from WSDOT on 4/20 stating they will not review project or reimburse expenses after 4/29 (letter attached). BergerABAM was notified and will shut down the project. Jilma Jimenez of BergerABAM will be at workshop to discuss options with Council. 5. Large Water Meter Repair – Staff in process of replacing all old water meters 1” or larger in town. All meters larger than 1-1/2” have been replaced. Staff goal is to complete replacement of 1-1/2” meters by June 2015. 6. South Woodland Safe Walking Route Project (SRTS) – WSDOT approved design deviation to allow for keeping a utility pole in place by narrowing sidewalk for a short section. Final plans submitted to WSDOT for review on March 27 th . Hope to go out to bid in May with construction occurring this summer. Work will also include some adjusting of the right-of-way in front of the Gardens. The right-of-way adjustments will need to be approved by City Council prior to construction. 7. General Sewer Plan –Gray & Osborne has submitted draft plan to Ecology for comments. 8. 2015 Comprehensive Park Plan –A draft plan was reviewed by the Park Board on 4/15/15. Park Board will make final recommendation at May meeting. The Park Plan will then be reviewed by the Planning Commission and the City will have an open house on the Park Plan to receive feedback. Current schedule is to get a plan to the City Council for review and approval this summer or early fall. 9. WWTP Maintenance Building Roof – Contractor has been given notice to proceed, system submittal was approved, and building permit application for new roof was submitted to building official. 10. 2014 CDBG Project (Old Town Connections) – Notice to proceed was given to River Country Construction on April 17. Work will occur in May and June. 11. 300 E. Scott Fire Station Project – Cowlitz PUD removed electrical services, area lights, and some poles. Frontier removed phone services. Building official issued demolition permit. Columbia Pacific Construction has cleaned out some material and has had an asbestos inspection completed which identified two different areas with asbestos. Demolition can’t begin until asbestos demolition permit is received from the Southwest Clean Air Agency. 12. SR 503/E Scott Intersection Project – City Council awarded construction contract to Tapani, Inc. and construction management services contract to SCJ Alliance on April 20 th . City signed the last right-of-way purchase needed on April 22 nd . Actual construction is expected to start in Mid-May. 13. Ranney Well Pump #3 – The third Ranney Well Pump will be rehabilitated in May. In 2013 and 2014 we rehabilitated pumps 1 and 2, this year it is 3. This is part of the water system maintenance budget.

Upload: others

Post on 15-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL UPDATE BART STEPP, PUBLIC WORKS DIRECTOR

PROJECTS COMPLETED LAST MONTH 1. Horseshoe Lake Park Shelter Renovations – Rollup doors at the entrance ways and concession window and

covers on the wall openings have been completed.

2. Annual Traffic Impact Fee Analysis – Attached is the annual analysis of traffic impact fees. Based on the analysis

the Traffic Impact Fee base rate of $838 should remain the same.

PROJECTS IN PROGRESS

3. Waste Control Contract – The City’s existing contract with Waste Control for solid waste services expires on

12/31/15. City Council has in the past asked about providing 35 gallon container service in addition to the 60

gallon and 90 gallon containers currently provided. This would require additional costs by Waste Control for new

carts and to retrofit equipment. Attached is a proposal by Waste Control. In exchange for extending the contract

another 10 years they would provide 35 gallon carts at no extra charge. Costs for a 35 gallon and 60 gallon

customer would be the same. Joe Willis with Waste Control will be at workshop to discuss the proposal with you.

4. Scott Reconnection Study Project – Received letter from WSDOT on 4/20 stating they will not review project or

reimburse expenses after 4/29 (letter attached). BergerABAM was notified and will shut down the project. Jilma

Jimenez of BergerABAM will be at workshop to discuss options with Council.

5. Large Water Meter Repair – Staff in process of replacing all old water meters 1” or larger in town. All meters

larger than 1-1/2” have been replaced. Staff goal is to complete replacement of 1-1/2” meters by June 2015.

6. South Woodland Safe Walking Route Project (SRTS) – WSDOT approved design deviation to allow for keeping a

utility pole in place by narrowing sidewalk for a short section. Final plans submitted to WSDOT for review on

March 27th. Hope to go out to bid in May with construction occurring this summer. Work will also include some

adjusting of the right-of-way in front of the Gardens. The right-of-way adjustments will need to be approved by

City Council prior to construction.

7. General Sewer Plan –Gray & Osborne has submitted draft plan to Ecology for comments.

8. 2015 Comprehensive Park Plan –A draft plan was reviewed by the Park Board on 4/15/15. Park Board will make

final recommendation at May meeting. The Park Plan will then be reviewed by the Planning Commission and the

City will have an open house on the Park Plan to receive feedback. Current schedule is to get a plan to the City

Council for review and approval this summer or early fall.

9. WWTP Maintenance Building Roof – Contractor has been given notice to proceed, system submittal was

approved, and building permit application for new roof was submitted to building official.

10. 2014 CDBG Project (Old Town Connections) – Notice to proceed was given to River Country Construction on

April 17. Work will occur in May and June.

11. 300 E. Scott Fire Station Project – Cowlitz PUD removed electrical services, area lights, and some poles. Frontier

removed phone services. Building official issued demolition permit. Columbia Pacific Construction has cleaned

out some material and has had an asbestos inspection completed which identified two different areas with

asbestos. Demolition can’t begin until asbestos demolition permit is received from the Southwest Clean Air

Agency.

12. SR 503/E Scott Intersection Project – City Council awarded construction contract to Tapani, Inc. and construction

management services contract to SCJ Alliance on April 20th. City signed the last right-of-way purchase needed on

April 22nd. Actual construction is expected to start in Mid-May.

13. Ranney Well Pump #3 – The third Ranney Well Pump will be rehabilitated in May. In 2013 and 2014 we

rehabilitated pumps 1 and 2, this year it is 3. This is part of the water system maintenance budget.

Page 2: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

14. Wastewater Plant Facility Audit and Operator Review – Veolia has completed two monthly reports (attached)

from their operator who is reviewing operations at the plant. The items raised in the monthly reports that do not

require large capital investments have been corrected or addressed. Items like the computer asset management

software and upgrades to the control (SCADA) system are significant cost items that are not budgeted for this

year. One of the identified projects in the 20 year Operations Plan approved last year by City Council was to

implement an asset management system by 2019 for all of Public Works which would include the Wastewater

Treatment Plant. The schedule in that plan was starting in 2015 staff would research asset management systems

for possible purchase of a system in 2016 or 2017. The intention is to start that work this fall. Once the software

is purchased it will take some time to insert data into the system and train staff in the use of the software. The

upgrade to the SCADA system is identified as a high priority capital improvement project in The General Sewer

Plan that is currently under review by the Department of Ecology. Once the General Sewer Plan is approved the

projects in the Capital Improvement Plan can be completed using Sewer Reserve Funds.

The Department of Ecology came and inspected the plant on March 27th at the request of WWTP Superintendent

Mark Morgan but the City has not yet received a report from that inspection. All of the site visits for the facility

audit have been completed but Veolia has not submitted the audit to the City.

PROJECTS SCHEDULED FOR AGENDA IN MAY

15. South Woodland Safe Walking Route Project (SRTS) – At May 4th meeting City Council will vote on resolution to

approve an ordinance to vacate some existing right-of-way in front of a portion of the Lilac Gardens in exchange

for dedication of some other right-of-way in front of the Gardens. This has been negotiated with the Gardens

and will allow for a more uniform right-of-way in the area. Council would vote on the ordinance to approve the

vacation at the June 4th City Council meeting. Attached are maps and legal descriptions of the areas vacated and

the area to be dedicated.

Page 3: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

Use Type Trip Rate Units of Measure Bypass Trip % Developed Units Developed Trips Undeveloped Units Undeveloped TripsIndustrial 3.8 Acres (Total) 379.0 1440.2 596.8 2267.8Commercial 55 Acres (Total) 20 128.6 5658.4 118.5 5213.1SF Residential 1.00 Homes 1410.0 1410.0 631.0 631.0Mobile Home 0.59 Units   320.0 188.8 0.0 0.0Multi‐Family 0.62 Units  564.0 349.7 581.0 360.2Park 0.19 Acres (Total) 7.5 1.4 45.2 8.6Schools 1.20 Building Sq. Feet 242.3 290.8 149.8 179.8Trips = Trip Rate x Units x (1 ‐ Bypass Trip %) Total Dev. Trips: 9339.3 Total Undev. Trips: 8660.5

TIF Eligbile Ratio = Undeveloped Trips/ Total Trips 0.48TIF Eligible Costs = $15,100,000‐TIF Revenue Received $15,066,372TIF Eligible Funding = TIF Eligible Ratio * TIF Eligible Costs $7,249,127

PM Peak Hour TIF = TIF Eligible Funding / Undeveloped Trips $837.03

Numbers in bold are changes from the 2014 analysis.  The 2014 analysis calculated a TIF of $837.69.  The difference between 2014 and2014 is not significant enough to warrant changing the existing TIF Fee of $838 per PM Peak Hour Trip.

Changes include 18 new single family homes, 1 duplex, 36 apartment units, and the O'Reilly's store.

2015 City of Woodland Traffic Impact Fee Analysis

G:\Public works\Transportation\TrafficImpactFees(TIF)\2015 TIF Analysis.xlsx 4/22/2015

Page 4: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 5: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 6: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 7: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

March 17, 2015

To: Bart Stepp, Woodland PWD

Veolia Overview of Woodland WWTP Operations through March 10th

Veolia staff has visited the Woodland wastewater treatment plant weekly to make

observations, audit operations and maintenance practices, review record keeping and

regulatory compliance and to consider what program areas may be in need of

development. Communications and collaboration with Woodland staff have been very

positive.

The City of Woodland has a 2.0 MGD SBR WWTP plant designed by Gibbs and Olson

from Longview, WA. Current average daily flow is around 0.5 MGD and the plant is

about 13 years old. Solids are wasted into one of two aerobic digesters and about every

4-6 weeks a local hauling company transfers the sludge to area agricultural properties.

Veolia was unable find proper documentation on the hauled material volumes/pounds.

Operationally the plant performs very well; effluent quality is excellent and odors are

minimal. There is an O&M manual but it does not appear to be referenced or used.

Process control decisions are based upon MLSS concentration with summer and winter

set points. The UV disinfection system has historically not performed well and has

limited automatic controls. The system initially appears to be undersized but further

investigation is needed. Some non-functioning capacitors have randomly been

replaced. There are concerns with the low bulb intensity.

Maintenance for the Plant is provided by the Public Works Department (PWD) on an “as

needed” basis. According to staff, there are 14 pump stations and keeping up with their

ongoing maintenance is challenging. Overall implementation of the maintenance

program is simply reactionary; when equipment breaks down, the PWD staff is called

upon to fix it. Maintenance tracking and documentation need further development and

implementation. Currently, the only form of maintenance documentation is notation in

the “Operator’s Log Book”. It does not appear that the maintenance program has ever

been audited. A simple Asset Management tracking and monitoring system is needed

to better protect City assets and to extend useful life of the equipment. It appears a

form was created a while ago for City staff to document Daily, Weekly and Monthly

Preventative Maintenance (PM) but Veolia was unable to find such documentation for

Corrective Maintenance or Predictive Maintenance. These forms are completed by

Page 8: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

hand and placed in a binder; however, they were not up-to-date. There were months

where work was done but not documented. City staff is now tracking this PM

information once again. The City needs a more formal maintenance tracking program.

Documented asset management for each individual piece of equipment is the industry

standard, ensuring the appropriate tracking of work history instead of relying on staff

memory. Even at a minimum, a notebook log tracking each piece of major equipment

with its work history would be helpful to have from a historical perspective.

It did not appear equipment was labeled with an organized equipment identification

system. Inventory control, organization, monitoring and documentation is not properly

being performed or documented. Equipment and supply ordering is also not done in an

organized and reliable manner. Having a master inventory list of equipment is a critical

component of Asset Management, knowing first what you have, the specifications of

what you have, how old it is, when routine maintenance is required, and tracking what

repairs/replacements were and are being done.

City operations staff is in need of general computer skills training. Veolia recommends

staff take basic courses in Microsoft Excel and Word to help track activities and to better

manage process control. All computer-related activities appear to be performed by

Public Works office staff five miles away. Each time something office-related is needed,

staff would drive over to the Public Works office (sometimes four times a day) to have it

done. It is common industry practice to enter lab data, work, maintenance and results

into a computer system for better effective data management. Quality control of such

entries is also a minimum standard; but, neither are taking place in Woodland, which

was also a concern raised by the Department of Ecology.

The SCADA system is in dire need of an upgrade. When an after-hour alarm condition

is present, the alarm system calls out the alarm but it doesn’t distinguish what the

source of alarm condition is. So each time an alarm goes off the on-call or on-duty

Operator has to come onsite to find out what it is. This is extremely ineffective and

expensive. Simple programming upgrades can help identify what the alarms are and

reduce the number of required alarm responses. An upgraded SCADA system with

remote laptop access would dramatically improve Woodland’s Operations especially

considering the current staffing level.

Veolia prides itself as the industry-leader in Safety. Woodland is sincerely in need of a

formal Safety Program. Current and past safety practices are too risky for the City. We

don’t necessarily believe that it is because staff has become complacent, we believe it

is because they have not received the proper safety training. Staff does not even use

the bare minimum personal protective equipment such as hard-hats, safety glasses,

gloves, hearing protection or vests anywhere at the plant. There were several places

Page 9: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

within the plant that would be identified by OSHA as “confined space” and access

should immediately be limited. Unfortunately, it appears that no gas monitoring, fall

protection or retrieval equipment is used for confined space entries. In fact, entries are

often made with only one person. If the Public Works Sewer Collections team has the

applicable safety gear, Veolia suggests at a bare minimum that it be shared with the

WWTP staff as practicable. City risk and liability is high under current practices and

conditions; but Veolia can assist the City with such compliance with OSHA and

DOE/EPA rules.

Over the past few weeks, Veolia has seen the City address some of the Safety items as

noted in the DOE inspection report.

Hard Hats, Safety Glasses, Goggles, Gloves and other associated safety

Equipment was ordered and a “Safety Wall” was created in the Maintenance

shop. This is a noted improvement; everything is on display and easily

accessible by all staff.

A sign-in log book is provided for all non-public works visitors and is kept in

the Lab; safety glasses are required for visitor use and are also kept in the

Lab.

Staff was observed performing a blower oil change. We went through the

lock-out/tag-out (LOTO) procedure and the theory behind how it should work

and the protections it provides. The equipment was properly locked, tagged

out, documented and paperwork retained in a binder in the maintenance shop

for future reference. This meets the requirement for the LOTO program,

ready information access and records retention.

An energy management program does not exist but should be developed to reduce

energy consumption. By working through Cowlitz PUD's Industrial Energy Efficiency

Program it is possible to participate in the Northwest Regional Industrial Training Project

for energy efficiency, perform an energy efficiency audit and possibly receive financial

incentives to install more efficient lighting, HVAC equipment, green motor rewinding and

implement industrial custom energy projects which could substantially save the City

much needed funds.

Staffing considerations: with one seasoned operator and an inexperienced newly

transferred City staff member there needs to be better organization, prioritization,

distribution, implementation and documentation of tasks for O&M to be effective.

SCADA and automation improvements would certainly increase effectiveness and

reliability and longevity. Veolia has assisted the new operator in acquiring State DOE

certification documents to become an Operator-in-Training designation. We have also

shared training resources for the operators. Until this new operator is trained up and

Page 10: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

becomes experienced enough to operate the facilities alone, the seasoned operator or

other qualified designee needs to make all the process decision-making responsibilities,

key O&M duties and emergency responses. The seasoned operator needs to develop

a close collaborative working relationship with the new operator and translate as much

knowledge and experience as quickly as practicable. Operators need to better

document, record, track, monitor and trend O&M activities.

Note that during the week of February 23rd Flyer Automation Inc. was called in

(Industrial Controls & Automation Solutions) to make some alarm changes to reduce

and eliminate the late night callouts that have plagued the plant over the years. Most of

these were unnecessary alarms and resulted in the compensation for simply coming in

after hours and acknowledging nuisance alarms. Upgrades will be needed in the future

to make the plant more automated and the SCADA system more functional, helping to

reduce wasted staff call-outs.

Page 11: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

April 3, 2015

To: Bart Stepp, Woodland PWD

Veolia Overview of Woodland WWTP Operations between March 10th and 24th

March 17th

Veolia operations staff visited the Woodland WWTP and was updated on a process

performance issue with the UV disinfection system which was operating at maximum

output. The UV systems unsatisfactory performance is causing ineffective disinfection

which can lead to poor, high or even false effluent Fecal Coliform (FC) test results. City

staff was concerned with having a high FC permit violation. The WWTP superintendent

did a good job researching and troubleshooting the UV performance issue and

identifying possible solutions. Research suggested that the bulbs purchased from UV

Doctor were bad, possibly due to mercury contamination or poor manufacturer quality

control. City staff requested that UV Doctor send the City new lamps from a different

batch (not from the last batch or lot). WWTP staff will install them as one unit then will

compare any differences. Staff also contacted Aquionics, the original equipment

manufacturer of the UV system to supply some bulbs and quartz sleeves. They of

course stated that the City would see improved performance and better longevity if City

used their products rather than aftermarket. When staff was in the process of making

this change to the other unit, Aquionics notified him they sent the wrong model sleeves

and would expedite the correct ones the next day. Superintendent’s plan was to operate

each unit independently and perform tests on each to compare performance. Lab

results indicate that the two units with the new bulbs from different suppliers operate

similarly and the FC results are within permit limits. Problem was successfully corrected.

Veolia was informed by superintendent that over the weekend a small blower failed.

Two City employees spent much of the day working on the UV system and changing out

the failed blower with a new one. Using this repair as an example, Veolia operations

staff raised concern again regarding the methodology or lack thereof of maintenance

documentation. City staff needs to better record operational changes, corrective

maintenance and preventative maintenance activities that take place at the WWTP. This

still does not appear to be taking place. If not recorded properly and soon, such

historical institutional repair/replacement task information is quickly lost. More

Page 12: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

importantly, performing the manufacturers’ recommended maintenance on equipment

does not appear to be taking place. It may be taking place, but if it is, it’s not being

recorded as Veolia would do so.

Safety issues are still a concern; all of the requisite PPE equipment is now available for

staff but they do not appear to be using it. No steel toed shoes, safety glasses or hard

hats have been worn during our onsite presence. A City employee was observed today

by the Veolia operator going up to the SBR to add a bag of HTH (powdered 65%

Chlorine) to control a filamentous organism problem he felt he had and the employee

wore no safety equipment at all. The wind was blowing as is common and HTH could

easily have contacted the skin, entered the eyes or inhaled. The Veolia employee

maintained a safe distance from this activity while it took place. Veolia would strongly

recommend the City have applicable WWTP and any other City staff (i.e. Public Works

staff) that performs work at the WWTP to complete a certified safety training program.

This program should be implemented with the understanding that compliance with all

standard safety practices is mandatory at all times. The City should also develop or

have developed an updated general safety plan with clearly defined Standard Operating

Procedures.

March 24th

This visit focused on plant maintenance management. Currently routine Planned

Maintenance (PM) activities (greasing, oil changes etc.) are performed by staff and are

logged in a hardcopy notebook by organized by month. The more technical and larger

maintenance activities (motor, blower, pump replacements etc.) are not documented.

There is no Computerized Maintenance Management System (CMMS) to properly

manage and document assets and maintenance activities. CMMS is critical not only to

maintaining and protecting the City’s assets, but also to help extend the useful life of the

equipment.

Veolia staff created a maintenance tracking form in Microsoft Excel for each major

equipment category (SBR Blower, PAD Blower and UV system). A City employee went

back a few months and entered all repairs that could be documented and recalled. If

properly utilized, this will be a good start for the City WWTP staff to document all

maintenance activities going forward. It should also meet the minimum requirement

from the DOE on record keeping as well.

Veolia EHS&S Manager visited the facilities this week along with a Veolia Operator to

do a walk through and safety review and visit. A comprehensive inspection was

conducted. Safety issues were documented and a task list created for City staff. This

included the Safety Manual and MSDS notebook. The MSDS notebook was not

Page 13: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …

inclusive of all chemicals on site and was made current that day with Veolia’s

assistance. An EHS&S report was drafted.

David Knight, WA DOE, made a visit to the WWTP on Friday March 27th to do a follow

up audit. Post audit communication with City staff that day was to the effect that Dave

Knight was satisfied with what he saw and that he found no issues and did not

recommend any further changes. Mr. Knight was satisfied with the Lab area, QA/QC

and the Lockout/Tagout and Maintenance Tracking programs that were implemented.

The City staff member said he would forward the DOE audit report to Veolia as soon as

it is received.

March 31st

Site visit focused on addressing Veolia EHS&S Manager safety inspection findings from

last week’s visit. The fuel safety cabinet was moved to the UV building and grounded.

All safety chains were adjusted to the legal heights and barricades were put in place.

An outside receptacle cover was put back onto the outdoor plug-in; it had fallen off. Low

lying trip hazards were painted yellow or yellow safety tape was placed over them. All

hoses were coiled up. It was again noted that the safety manual is outdated and needs

to be updated.

Page 14: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 15: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 16: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …
Page 17: APRIL 27, 2015 PUBLIC WORKS DEPARTMENT CITY COUNCIL …