april 4, 2007 rolf nahnhauer1 desy-project icecube digital optical module production
Post on 23-Jan-2016
216 views
TRANSCRIPT
April 4, 2007 Rolf Nahnhauer 1
DESY-PROJECT
IceCube Digital Optical Module
Production
April 4, 2007 Rolf Nahnhauer 2
April 4, 2007 Rolf Nahnhauer 3
IceCube StatusApril 2007
April 4, 2007 Rolf Nahnhauer 4
THE ICECUBE OBSERVATORY
IceTop air shower array80 pairs of ice Cherenkov tanks
IceCube deep ice array4800 optical modules on 80 stringsinstrumented volume : 1 km3first string deployed : January 2005
~ 80.000 atm. per year
April 4, 2007 Rolf Nahnhauer 5
2005, 2006, 2007 DeploymentsAMANDA
IceCube string deployed 12/05 – 01/06
1424 DOMs deployed to date
Next year looking for 14 to 18 strings.
Want to achieve steady state of >= 14 strings / season.
21
3029
40
50
3938
49
59
4647
48
5857
6667
74
65
73
78
56
72
IceCube string deployed 01/05
IceCube string and IceTop station deployed 12/06 – 01/07
IceCube Lab commissioned
1+ 9 + 13 = 22 strings to date
April 4, 2007 Rolf Nahnhauer 6
Hotwater drilling: Trend towards increasingly stable operation continued.Experienced crew
IceCube Pole Season 2006/2007
April 4, 2007 Rolf Nahnhauer 7
•IceCube lab commissioned, •South Pole computing system (SPS), all racks and infrastructure installed,•64 bit implemented on SPS and SPTS,•About 10 racks of computers and hubs. •Working simulation, exp control, PnF
IceCube Pole Season 2006/2007
April 4, 2007 Rolf Nahnhauer 8
IceCube Events
Neutrino in IC 9 Flasher Pulse in IC 22
April 4, 2007 Rolf Nahnhauer 9
IceTop: cosmic-ray physicsIceCube: calibration, background tagging
IceTop/In-ice coincident events
April 4, 2007 Rolf Nahnhauer 10
Atmospheric neutrinos
in IC 9, 2006
John Pretz, Ph.D. thesis
Ratio of data to simulation:R=1.05 +- 0.24 (syst) +- 0.09 (stat)
given at cut strength 10156 upgoing muon eventspurity of neutrino sample > 95%
First IceCube Results
April 4, 2007 Rolf Nahnhauer 11
April 4, 2007 Rolf Nahnhauer 12
Project Year 3 4 5 6 7 8 TotalDeployment Year 04/05 05/06 06/07 07/08 08/09 09/10Drill/deploy strings 4 12 16 18 18 12 80Strings in ice 4 16 32 50 68 80 80DOMs needed 400 834 1064 1242 1182 778 5500Calendar year of prod. 2004 2005 2006 2007 2008 2009Cable systems to build 5 14 24 24 15 0 82Total DOMs: build and test 400 834 1064 0 5500DOMs: DESY 60 210 280 0 1330DOMs: Sweden 50 140 180 0 880DOMs: PSL 290 484 604 0 3290
3202
1912
780510
PRODUCTION SCHEDULE
Numbers from February 2004 slightly changing with timeBaseline change: 80 strings 70 strings + 10 strings from contingency
xxx
April 4, 2007 Rolf Nahnhauer 13
DOM Production Site Integration Status - PY5 (April, 2006 - March, 2007)
1053
939
340372
296261
0
200
400
600
800
1000
1200
Plan integration Actual Integration Plan Integration Actual Integration Plan Integration Actual Integration
Week ending 3/11/07
PSLDESY
Sweden
Site % to Weekly Plan % PY5 completed
PSL 89 84
DESY 109 100
Sweden 88 82
Site Total Plan
PSL 1125
DESY 370
Sweden 320
April 4, 2007 Rolf Nahnhauer 14
DOM Production Site Integration Status - PY6 (April, 2007 - March, 2008)
1097
0
430
0
336
00
200
400
600
800
1000
1200
Plan integration Actual Integration Plan Integration Actual Integration Plan Integration Actual Integration
Week ending 1/24/07
PSLDESY
Sweden
Site % to Weekly Plan % PY5 completed
PSL 0 0
DESY 0 0
Sweden 0 0
Site Total Plan
PSL 1097
DESY 430
Sweden 336
Do not use this chart till April, 2007 - see PY5 charts for current PY5 information
April 4, 2007 Rolf Nahnhauer 15
DOM Production DESY IntegrationStatus - PY 07 (April 2008-March 2009)
PY Year # DOMs ready
03 4/04-3/05 60
04 4/05-3/06 160
05 4/06-3/07 370
06 4/07-3/08 430
07 4/08-3/09 120-280 ?
DOM integration at DESY will finish 7/08 to 11/08
decision how many DOMs for how many stringshave to be produced, will come in summer 2007
April 4, 2007 Rolf Nahnhauer 16
FUTURE PRODUCTION and TESTING IceCube DOM Production CY2004 - CY2008 for 80 strings installed
0
10
20
30
40
50
60
70
80
90
24.0
7.20
04
24.0
9.20
04
24.1
1.20
04
24.0
1.20
05
24.0
3.20
05
24.0
5.20
05
24.0
7.20
05
24.0
9.20
05
24.1
1.20
05
24.0
1.20
06
24.0
3.20
06
24.0
5.20
06
24.0
7.20
06
24.0
9.20
06
24.1
1.20
06
24.0
1.20
07
24.0
3.20
07
24.0
5.20
07
24.0
7.20
07
24.0
9.20
07
24.1
1.20
07
24.0
1.20
08
24.0
3.20
08
24.0
5.20
08
24.0
7.20
08
Week ending
Qu
anti
ty o
f st
rin
gs
read
y fo
r in
stal
l
Block 1
Block 2
Block 3
Final Integrated DOM PRR (early June 2006)
PMTs, spheres ordered - qty 1200
Place orders for main board, HV suite, flasher board, delay board, penetrator assembly, harness, etc - qty 1200, Block 3A
Block 3 Design freeze
qty = 1200, 3AStrings installed in ice at Pole
Known major changes between Blocks 2 and 3:1. CAEN supplied HV control board2. Toroid on HV base3. Pigtail and Harwin connector on penetrator assembly
DOM Subsystem Final Design Verification and CDR - best case: good to order 3600 units, must order 1200 min. Aug 29 - 30
qty = 2400, 3B
qty = 700, 3C to 80 strings
Block 3A readiness review, March 2006
Must order last 700 units to continue to 80 strings Feb, 2008
Must order Block 3B 2400 units to continue uninterrupted in Nov, 2006
Note: this plan reduces quantity of DOMs to ship to the Pole in CY2006 from 16+ to 14+ to accommodate later production start
April 4, 2007 Rolf Nahnhauer 17
DOM Production and Testing at DESY
April 4, 2007 Rolf Nahnhauer 18
DOM PRODUCTION at DESY
Production of up to 1300 Optical Modules until mid 2008
Production comprises:
Gel mixing, filling and potting PMTs
Collar mounting and assembly of electronics
Sealing of DOMs at low pressure
Harness DOM with suspension
Finally pack DOMs and ship them to the pole
April 4, 2007 Rolf Nahnhauer 19
PROJEKT-ABLAUF
April 4, 2007 Rolf Nahnhauer 20
Dr. H. Waldmann 100%
Dr. J. Bolmont ( postdoc) 65%
xx
S. Henze xxxJ. PieperS. Ladegast
April 4, 2007 Rolf Nahnhauer 21
OMP-Projekt Investitionen
#OM
605
620
545
2107
April 4, 2007 Rolf Nahnhauer 22
OMP-Projekt PersonalbedarfWeeks kEuro
Weeks kEuro
Produktion 07 314.8
Physiker 48 62.8Postdoc 33 33.6Ingenieure 24 26.4Techniker/Werkstaetten 96 192.0
Produktion 06 222.8
Physiker 35 38.5 Postdoc 23 24.5 Ingenieure 18 19.8 Techniker/Werkstaetten 70 140.0
April 4, 2007 Rolf Nahnhauer 23
DOM TESTINGElectronic and optical requirements
Reboot- and communication over a wide temperature range from +20°C to -45°C
Single photo electron detection
Wide dynamic signal range – capable to handle large light pulses with up to several 1000 photo electrons per microsecond
Time resolution better than 5ns for single photo electron pulses
High voltage calibration of the PMT better than 5%
Optical sensitivity within low variations for different DOMs
Dark noise rates less than 1kHz in ice
Mechanical requirements
Vibration and pressure fluctuation during transport
Rapid temperature variations from +20°C to -45°C
Very high environment pressure up to 650 bar
April 4, 2007 Rolf Nahnhauer 24
DOM FINAL ACCEPTANCE TEST
Reversed Hypothetical FAT
-60
-50
-40
-30
-20
-10
0
10
20
30
1-Jun 6-Jun 11-Jun 16-Jun 21-Jun
Time
Te
mp
erat
ure
X Y
X + Y > 180 h
A full set of different tests is performed for defined temperatures
Test of the electronics (mainly runningdiagnostic programs, checking the hardware components)
PMT high voltage calibration
Rate monitoring while DOMs are illuminated with light of different wavelength
Dark rate monitoring
Data taking with a DAQ system similar to the final low level south pole DAQ(Linearity and time resolution tests)
Timing scenario:
April 4, 2007 Rolf Nahnhauer 25
DARK FREEZER LABLarge cooling chamber (4 x 6 x 2 m)
Temperature control with coolingaggregate and heaters
Minimal temperature for test cycle is -45°C(in the US -55°C for IceTop DOMs)
Optical fibers and mirror system installed on each test station
DOMs sit on top of cylindric cans
Cans are taped with aluminum foil todistribute the light
DOMs are covered with black plastic bags to keep them as dark as possible for the measurements
April 4, 2007 Rolf Nahnhauer 26
TEST ENVIRONMENT SETUPDark Freezer Lab (DFL) with 64 test stations
Same DAQ and wiring as for the South Pole system
Simulated cable length up to 3km
Light is distributed equally to the DOM stations via optical fibers
Time synchronization of multiple domhubs with a global GPS clock
Light system allows event simulation
Different light sources:
Laser for time calibration, pulsed LED for linearity test, DC lamp with monochromator for optical sensitivity test
April 4, 2007 Rolf Nahnhauer 27
DFL STATION CALIBRATION
Light yield differs for all stations
There is a wavelength dependence of the optical system
For studies of the optical sensitivity the stations have to be calibrated
During test runs a well characterized monitor PMT takes direct signals from the light sources
Together with the calibration information the relative optical sensitivity of the DOMs can be evaluated
April 4, 2007 Rolf Nahnhauer 28
ELECTRONIC TESTSA self test of the electronic components runs on the DOM
performed on bare mainboards before delivering
performed on integrated DOMs as functional test
Reboot tests are performed during the complete test cycleDOMs are turned on and off more than 100 times over a test runin addition tests of software uploads are performed
For the tests of the local coincidence chain the DOMs in the DFL are connected pairwise like on a real string
April 4, 2007 Rolf Nahnhauer 29
DOM CALIBRATION I
ATWD Calibration :
Reconstruction of PMT voltage waveform from ATWD data requires:
Voltage calibration of ATWD
Measurement of amplifier gain for ch0, ch1, and ch2
Frequency calibration of ATWD
Baseline measurement
Performed using theinternal pulser and oscillator
April 4, 2007 Rolf Nahnhauer 30
DOM CALIBRATION IIDark noise events are used to record the charge spectrum of single photo electron events
Calculation of the mean charge for different PMT high voltage settings reveals the gain
Finally this results in a linear fit of the gain versus high voltage relation
Working voltage yields gain = 107
Requirements:
Peak to valley ratio > 2.5
Gain > 5107 at 2000 V
overall relative error < 5%
Charge Spectrum of single photo electron events at 1400 V
Gain versus voltage[V]
April 4, 2007 Rolf Nahnhauer 31
TIME SYNCHRONIZATIONEach DOM runs with an individual clock
A global time synchronization has to be performed regularly to match the DOM-time to a global time including signal run-time
The RapCal method :
Time stamped bipolar pulses are sent from the DOR card to the DOM and vice versa
This gives a coarse time synchronization of the order of 50ns (local clock speed)
In order to improve the time synchronization accuracy the bipolar pulses are fitted at arrival, giving an exact time e.g. for zero crossing of the waveform
With that information the round trip time can be calculated and the accuracy of the time calibration is improved to better than 5ns
April 4, 2007 Rolf Nahnhauer 32
TIME RESOLUTION Pulse laser sends accurate signals (~75ps wide) to the DOMs
A bare mainboard records the absolute pulse time (sync pulse)
Analyze the distribution of time differences of DOM’s and sync pulse
The width of the distribution gives an upper limit for the DOM time resolution
Fraction of late pulses identify noise and time calibration problems
An overall comparison of the signal time offsets of all DOMs give information about the time resolution stability
Light and signal travel time
April 4, 2007 Rolf Nahnhauer 33
LINEARITY
DOMs are illuminated with different light intensities using a pulsed LED with different power settings
Different filters are brought into the light path to attenuate the amount of light
Plots show the charge distribution for different filter settings (low to high attenuation)
Plotting the mean charge versus light intensity gives the linearity characteristic for a DOM
April 4, 2007 Rolf Nahnhauer 34
OPTICAL SENSITIVITYSensitivity of integrated DOMs differs due to transmission characteristic of glass (sphere,PMT), gel and the PMT
quantum and collection efficiency
Do rate measurements while the DOM is illuminated with light of varying wavelength
Data has been already recorded, analysis is in preparation
Measure behaviour of subsystems: e.g. transmission of gel samples with respect to air
Allows relative comparison of different production batches
April 4, 2007 Rolf Nahnhauer 35
DARK NOISEReadout on board scaler – discriminator crossings of PMT signal
Requirements:
Mean noise rate < 3kHz No outliers within 5σ
(Noise rate in ice is much lower (~700Hz))
Search for spikes in noise ratebackground – maybe an indication for problematic PMTs or HV generators
Coincidence spikes are likely caused by some outside influences
[Hz]
Histogram of the dark noise ratesfor a single DOM
April 4, 2007 Rolf Nahnhauer 36
DOM - Passport
Decision June 2005:
use formalized DOM-passport for characterization
and qualification of DOM’s (ready early 2006)
April 4, 2007 Rolf Nahnhauer 37
DOM-Production 2004-2008
YearYear DOMs
produced
DOMs OK
finalDOMs
shipped
2004 60 45 0.75 28
2005 160 159 0.99 160
2006 257 255 0.99 224
2007 480
2008 183-343
only ~1% of DOMs are cannibalized – goal was 5% or bettergood components are used in next years production
April 4, 2007 Rolf Nahnhauer 38
2004 DOM TESTING + USAGE
time load good bad comment
FAT1 20.9.-5.10.04 25 20 5 3 gel, 1 MB, 1 HV
FAT2 4.11.-17.11.04 21 8 13 13 gel, 1 MB
FAT3 10.1.-20.1.05 20 17 3 1 MB,3 FB,1 HV
FAT4 24.2.-7.3.05 8 8 0 use 5 CAEN HV
location number
quality purpose
Pole 42 good deploy
DFL 3 good standard
Madison 8 bad Check
Dortmund
1 bad HV-tests
- 6 bad cannibalize
Production efficiency:
P2004 = 75 %
Wanted:
P = 95 %
April 4, 2007 Rolf Nahnhauer 39
2005 DOM TESTING Time load good bad FAT
FAT5 10.06.-27.06. 51 37 14 0.73
FAT6 12.07.-8.08 54 49 5 0.91
FAT7 29.08.-12.09 57 47 10 0.82
FAT8 14.9.-30.09 26 20 6 0.77
FAT9 14.11.-01.12 6 6 0 1.00
*) in all cases +3 permanent DOM’s from FAT3 for comparison
FAT 7
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 8
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 9
Passed
STF
FB
Dark Rates
Comm/other
GelFAT5
FAT6
FAT7
FAT8
FAT9
April 4, 2007 Rolf Nahnhauer 40
2006 DOM TESTINGtime load good bad FAT
FAT10 19.06- 30.06 57 46 11 0.81
FAT11 19.07-04.08 57 50 7 0.88
FAT12 09.08-25.08 57 53 4 0.93
FAT13 05.09-20.09 51 48 3 0.94
FAT14 12.10-27.10 55 49 6 0.89
FAT15 27.10-15.11 14 12 2 0.86
FAT 10
Passed
STF
FB
Dark Rates
Comm/other
Gel FAT 11
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 12
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 13
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 14
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 15
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT10
FAT11
FAT12
FAT13
FAT14
FAT15
April 4, 2007 Rolf Nahnhauer 41
2007 DOM TESTINGtime load good bad FAT
FAT16 29.01-14.02 57 50 7 0.88
FAT17 28.02-17.03 57 49 8 0.86
FAT18 22.03-xx.yy 34
FAT 16
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT 17
Passed
STF
FB
Dark Rates
Comm/other
Gel
FAT16 FAT17
No dominant error source could be identified in FATs
Different small problems appeared for all FATs
April 4, 2007 Rolf Nahnhauer 42
SummaryDOM first year mass production is running without problems
Production team well trained
Delivery of components mostly smooth
Storage space sufficient but at the limit, many transports betweenZeuthen and Wildau necessary
Many small problems contribute to test failure rate
Total failure rate after rework sufficiently small (better than expected)
DESY well prepared for continuous mass production until autumn 2008