AGE Technologies JHB (Pty) Ltd. secured the contract to assist Arcelor Mittal’s planning department with the design, project management and commissioning of the automation system required at the Vanderbijlpark works Continuous Casting plant. Scope of work to be done Was the equipment supply and product training of Modicon Quantum PLC's and FactoryLink SCADA. However, the whole project was to be executed during a planned shutdown period and required careful planning in order to minimise disruption at the changeover. Products used The PLC was programmed in hot standby configuration and it was decided to make use of standard terminal cabling in order to facilitate a smoother transition. Duration of the project The project was five months in preparation and comprised 3 manmonths effort in execution. www.age.co.za AGE Technologies JHB 50 Charl Cilliers Ave, Alberton North, 1456 Tel: +27 11 869 3925/6/7 Fax: +27 11 869 6427

Upload: age-technologies

Post on 12-Jul-2015

32 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Arcelor Mittal

AGE Technologies JHB (Pty) Ltd. secured the contract to assist Arcelor Mittal’s planning department with the design, project management and commissioning of the automation system required at the Vanderbijlpark works Continuous Casting plant. 

Scope of work to be done Was the equipment supply and product training of Modicon Quantum PLC's and FactoryLink SCADA.  However, the whole project was to be executed during a planned shutdown period and required careful planning in order to minimise disruption at the changeover.

Products usedThe PLC was programmed in hot stand‐by configuration and it was decided to make use of standard terminal cabling in order to facilitate a smoother transition.

Duration of the projectThe project was five months in preparation and comprised 3 man‐months effort in execution. 