· pdf fileconstituents are requested to bring/ give full particulars for the tripping ......
TRANSCRIPT
![Page 1: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/1.jpg)
![Page 2: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/2.jpg)
![Page 3: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/3.jpg)
![Page 4: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/4.jpg)
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
Agenda for the 47
th Meeting of Protection Coordination Sub-Committee of
SRPC to be held on 15.09.2015 (Tuesday)
1. Introduction
2. Confirmation of Minutes of last PCSC meeting
Confirmation of minutes of 46th
Protection Coordination Sub-Committee meeting
held on 30.07.2015.
3. Grid Occurrences (w.r.t. SRLDC)
3.1 Grid Disturbance (GD), Grid Incidences (GI), and trippings due to failure of Auto-
reclosing (A/R), and Mal-operation of PLCC equipment that occurred during the
last one-month period (July - August, 2015) would be discussed in the PCSC meeting [Annexure-I].
Constituents are requested to furnish the following information in respect of the
above grid occurrences to have fruitful discussions in the PCSC forum.
(a) Single line diagram of the station with switching devices, CT, PT and relay
details
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
Constituents are requested to bring/ give full particulars for the tripping events
incident to their system.
3.2 In compliance of Regulations 5.2 (r) of IEGC – as per the provisions under clause
1.5 of IEGC 2010, the Constituents are requested to furnish the following information in respect of Grid Occurrences (Annexure-II) latest by 10.09.2015:
(a) First Information Report (FIR)
(b) Event Logger (EL) output
(c) Disturbance Recorder (DR) output
(d) Trip event analysis report (with pre and post fault system conditions)
Non-furnishing of Tripping details including Disturbance Recorder/Sequential
Event logger output would be discussed in the meeting.
4. Submission of reports/compliance by Constituents
4.1 Status of pending Protection Coordination Sub-Committee (PCSC)
Recommendations
Status of the pending PCSC recommendations (from 30th
PCSC to 45th
PCSC) given at Annexure-III may please be sent latest by 10.09.2015.
4.2 Remedial measures for "Transmission Line under Forced Outage"
The constituents are requested to send the remedial measures/ actions taken by them for the tripping events as circulated vide our emails. (Annexure-IV)
![Page 5: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/5.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 2
The trip events are based on the daily reports at SRLDC website
http://srldc.in/DailyReport.aspx under the menu: Reports->Daily-> "TL under
Forced Outage")
4.3 Certificate for Healthiness of Batteries
As per the MoP direction given in pursuant to recommendations of the
Enquiry Committee (NEW grid disturbance on 30th
& 31st July, 2012), RPC’s
are required to obtain from their respective Constituents the monthly
certificate for healthiness of batteries, installed at 220 KV and above voltage
level Substations (for power supply to Relays, RTUs and PLCC equipment)
and furnish the same to CEA/ MoP.
With reference to above, the Constituents are requested to submit the
certificate on healthiness of batteries on monthly basis (i.e. on 7th
day of the
month) to SRPC.
The sought status for the month of July, 2015 is still awaited from the
following SR-Constituents:
APGENCO (Thermal), APTRANSCO, TSGENCO (Hydro), KPTCL,
TANGEDCO, KSEB, PGCIL (SR-I&II), NTPC (Ramagundam,
Kayamkulam), NPCIL (Kudankulam), NTPL, CEL, CEPL & TPCIL.
5. Reviewing of Zone-3 Philosophy of transmission lines protection
The general philosophy to be followed for Zone-3 settings in SR had been discussed in
the Sub Group meeting of PCSC held on 20-11-2013 and finalized during PCSC-26 held on 21.11.2013 (Annexure-V). However, as it was noticed that there exist minor
differences in the Impedance settings adopted for Zone-3 by the SR –Constituents vis-à-
vis the Rama Krishna Committee’s (Task Force on the Power System Analysis under
Contingencies) guidelines w.r.t. Zone-3, it is proposed to hold a discussion in this regard
to elicit the views of SR-Constituents.
Relevant extracts from the Appendix - 9.1 of Report of the Task Force on Power System
Analysis under Contingencies brought out in August, 2013 (available at
http://www.cea.nic.in/reports/articles/god/report_power_system_analysis.pdf): 3. ZONE-3 REACH SETTING
Zone-3 distance protection can offer time-delayed remote back-up protection for an adjacent transmission circuit. To achieve this, Zone-3 distance elements must be set according to the following criteria where possible. Zone-3 should overreach the remote terminal of the longest adjacent line by an acceptable margin (typically 20% of highest impedance seen) for all fault conditions. Set KN as (Z0 – Z1) / 3Z1.
However, in such case where Zone-3 reach is set to enter into next lower voltage level, Zone-3 timing shall be coordinated with the back-up protection (Directional over current and earth fault relay) of power transformer. Where such coordination cannot be realized, it is recommended to carry out simulation studies for relay reach & time coordination and suitable solution may be devised. Some of the typical solution can be like application of back up distance protection for power transformer, duplicated protection for downstream 220kV feeders or special protection scheme logic. Similar issues, if encountered for Zone-2 reach setting, should also be addressed in the above manner.”
![Page 6: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/6.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 3
6. ZONE-3 TIMER SETTING Zone-3 timer should be set so as to provide discrimination with the operating time of relays provided in subsequent sections with which Zone-3 reach of relay being set, overlaps. Typical recommended Zone-3 time is 0.8 to 1.0 second. For Special cases, where co-ordination between long and short lines is required, following formula would be the basis for determining the minimum acceptable Zone-3 time setting:
tZ3 > tMA + tCB + tZ3reset + tS
Where: tZ3 = Required Zone-3 time delay tMA = Operating time of slowest adjacent circuit local back-up protection tCB = Associated adjacent circuit breaker clearance time tZ3reset = Resetting time of Zone-3 impedance element with load current present tS = Safety margin for tolerance (e.g. 50 to 100milliseconds)
7. LOAD IMPEDANCE ENCROACHMENT With the extended Zone-3 reach settings, that may be required to address the many under reaching factors already considered, load impedance encroachment is a significant risk to long lines of an interconnected power system. Not only the minimum load impedance under expected modes of system operation be considered in risk assessment, but also the minimum impedance that might be sustained for seconds or minutes during abnormal or emergency system conditions. Failure to do so could jeopardize power system security. Ideal solution to tackle load encroachment may be based on the use of blinders or by suitably setting the resistive reach of specially shaped impedance elements or by use of polygon type impedance elements. It is recommended that all the distance relays should have quadrilateral / polygon characteristic. For relays having Mho characteristics, it is desirable to have load encroachment prevention characteristics or a blinder. In the absence of credible data regarding minimum voltage and maximum load expected for a feeder during emergency system condition, following criteria may be considered for deciding resistive reach / blinder setting to prevent load point encroachment:
Maximum load current (Imax) may be considered as 1.5 times the thermal rating of the line or 1.5 times the associated bay equipment current rating ( the minimum of the bay equipment individual rating) whichever is lower. (Caution: The rating considered is approximately 15 minutes rating of the transmission facility).
Minimum voltage (Vmin) to be considered as 0.85pu (85%).
For setting angle for load blinder, a value of 30 degree may be adequate in most cases.
For high resistive earth fault where impedance locus lies in the Blinder zone, fault clearance shall be provided by the back-up directional earth fault relay.
6. Grid Study Committee (GSC): Data Inputs for Task-2
For facilitating the audit-check of the 15 Stations in SR by the Consultant under Task-2,
respective Constituents have been provided with (i) a Check-list for Data Collection
(CHECK-LIST), and (ii) Details pertaining to Bus Bar protection and Breaker Failure
Protection (BBP-BFP), and requested to kindly furnish the duly filled CHECK-LIST and
BBP-BFP details for the Stations under their control area latest by 31.08.2015 to SRPC
![Page 7: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/7.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 4
([email protected]) so that the same can be forwarded to the Consultant. As
the data in this regard is yet to be received from majority of the concerned Constituents,
they are requested to expedite the same.
7. Network Configuration changes
As per the information furnished by SR-Constituents to the OCC forum in their 109th
Meeting held on 08.07.2015 (Minutes circulated on 27.07.2015), the following network
configuration changes (additions/ deletions/ modifications of transmission elements) took
place in the southern grid during the month of June-July, 2015.
COD of NTPL U-I (500 MW) had been declared from 18th June 2015.
COD of NLC II Expn U- I (250MW) had been declared from 05th July 2015.
400kV Karaikudi - Pugalur D/C line was charged first time on 06th July 2015 by
TANTRANSCO
11.35 MW Wind Generation capacity was added in Tamil Nadu during the month of
June, 2015.
10 MW Solar Generation capacity at Sivasamudram was added in Karnataka by
KPCL on 16.06.2015.
8. Protection Logic checking of Critical Substations
Logic checking of following Critical Substations in the Southern Region had been
approved in the SRPC meeting held on 18.05.2013 at Bangalore.
(i) 400 kV Guttur (vi) 400 kV Kurnool
(ii) 400 kV Ramagundam (vii) 400 kV Almatti
(iii) 400 kV Kalpaka (viii) 220 kV Edamon
(iv) 400 kV Nelamangala (ix) 400 kV VTS
(v) 400 kV Hoody (x) 400 kV Vemagiri
9. Compliance of Hon’ble CERC Orders.
9.1 Petition No. 146/MP/2013 with I.A. 36/2013: Order dated 20.02.2014
Compliance of Regulations 5.2 (r) of the Grid Code: Issue regarding non-
furnishing of FIR / Trip Analysis Report, EL, DR, etc. was also
highlighted. It is pointed out that the above reports are to be submitted /
uploaded on SRLDC web application within 24 hours as mandated under
IEGC / CEA Regulations.
Implementation of Phase-I and Phase-II of Protection Audit
Recommendations: All the constituents are requested to submit the updated
status of the compliance (those who have not completed recommendations
mentioned in the Phase I and Phase II) to SRPC Secretariat at the earliest.
Compliance of Regulations 5.2 (e) & 5.2 (l) of the Grid Code and Regulation
3(1)(e) of CEA Grid Standards: The constituents are requested to strictly
comply with these provisions by ensuring standard protections systems having
the reliability, selectivity, speed and sensitivity to isolate the faulty equipment
and protect all components from any type of faults, within the specified fault
clearance time and providing protection coordination
Ensuring proper maintenance of transmission lines and adopting best O&M
practices: The constituents are requested to conduct line patrolling regularly
![Page 8: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/8.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 5
as per the SRPC transmission line patrolling guidelines (available under the
menu item "All Uploads Operation Miscellaneous Transmission Line
Patrolling Protocol / Guidelines for Southern Region" on SRPC website).
(http://www.srpc.kar.nic.in/website/2014/operation/patrolling.pdf).
9.2 Petition No. 167/Suo- Motu/2012: Order dated 22.02.2014
The Constituents are requested to follow approved protection philosophy
ISTS licensees are requested to submit details of updated distance protection relay
setting of all inter-regional lines to POSOCO & RPCs.
All SLDCs are requested to install/activate sound recording system in their control
rooms within three months from the date of issue of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
9.3 Petition No. 263/MP/2012: Order dated 19.12.2013
Constituents are requested to implement the quantum of relief by AUFR and df/dt
relays by identifying additional feeders and keep them functional within one month
of issuing this order.
SLDCs are also requested to map these relays on their respective SCADA
system within three months of issuance of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
9.4 APTRANSCO’s Petition No.95/MP/2015: Date of hearing 09-04-2015
It was noted in the Analysis and Decision part of the Order that:
“8. Noting the submissions of the petitioner, SRPC and SRLDC and activities
initiated by the petitioner for procurement of materials required for
implementation of the remarks of protecting audit, we allow time to the
petitioner till 31.12.2015 for completion of our directions in Order dated
19.12.2013 in Petition No. 146/MP/2013.”
“9. SRPC is directed to monitor the status of completion of works relating to
protection audit remarks in respect of 7 nos 400 kV sub-stations and 11 nos
220 kV sub-stations of APTRANSCO, protection audit remarks in Protection
Coordination Sub-Committee (PCSC) meetings and coordinate the periodic
protection audit to be carried out in Southern Region after deliberation in
SRPC and submit bi-monthly report to the Commission.”
9.5 TSTRANSCO’s Petition No.83/MP/2015: Order dated 14-05-2015
It was noted in the Order that:
“12. Noting the submission of the petitioner, SRLDC and SRPC and
considering the actions already initiated by the petitioner for implementation
of works relating to protection audit, we allow time till 31.10.2015 and
31.8.2016 for implementation of Phase-I and Phase -II works respectively.
The petitioner is directed to submit affidavit confirming the completion of
Phase I of protection audit remarks by 31.10.2015 and Phase-II of protection
audit remarks by 31.8.2016.
13. SRPC is directed to monitor the status of completion of remarks in these
substations vis-à-vis protection audit remarks in Protection Coordination Sub
Committee (PCSC) meetings. SRPC is further directed to coordinate the
![Page 9: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/9.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 6
periodic protection audit to be carried out in Southern Region after
deliberation in SRPC.”
9.6 Order in Petition No. 86/MP/2014 and 374/MP/2014: Order dated 18-08-2015
A copy of the above Order dated 18.08.2015 is given at Annexure-VI. The time-
lines given to the various SR-Constituents for completion of Phase-I and Phase-II
activities of Protection Audit Recommendations are given below:
(A) KSEBL:
18. Noting the submission of KSEBL, SRLDC and SRPC and considering the actions
already initiated by KSEBL for implementation of remarks of protection audit, we
allow time till 31.12.2015 and 31.3.2016 for implementation of Phase-II works
and R&M works at Idduki HEP respectively.
(B) TANTRANSCO: 21. After considering the submissions of TANTRANSCO, SRLDC and SRPC, it is noted
that TANTRANSCO`s request for time till 31.5.2015 for implementation of Phase–I
activities of providing numerical relays for feeder protection and Auto transformer
protection is already over. We allow time till 30.6.2016 for other Phase-I activities
such as provision of line VT, 5 core CT, Time synchronizing with GPS, Disturbance
recorder & event logger and Phase-II activities. According to SRLDC, total
implementation period is 15 to 16 months for items which involve major
procurement, design changes with major site modification/civil activities.
Accordingly, we allow 16 months time i.e up to 30.11.2016, for Renovation and
Modernization of Singarpet, Singaperumalkoil, Salem and Tondiarpet 230 kV sub-
stations from the issue of the order.
(C) NLC:
22. NLC has sought time upto 31.12.2014 and 31.3.2015 for completion of Phase-I work
of Numerical Relay Retrofitting and for Phase-II works of providing second battery
bank of PLCC respectively. It is noted that the completion dates for Phase-I and
Phase-II of protection audit remarks as requested by NLC are already over.
Therefore, no direction is required in this regard. However, we direct NLC to file a
confirmation report regarding completion of protection audit works for Phase-I and
Phase-II.
(D) KPTCL:
23. …
…
Considering the submission of KPTCL and SRLDC, we allow time to KPTCL time till
15.01.2016 for completion of Phase-I and Phase-II of protection audit remarks. No
further extension shall be granted in this regard.
(E) KPCL:
24. …
… Considering the submission of KPCL and SRLDC, we allow time to KPCL till
31.10.2015 and 31.12.2015 for completion of Phase-I for Phase-II of protection
audit remarks respectively. No further extension shall be granted in this regard.
26. We direct SRPC to (a) submit status of protection audit remarks in respect of
APGENCO, NTPC (SR), Talcher, Puducherry, PGCIL (SRTS I & II), MAPS and
![Page 10: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/10.jpg)
Agenda for the 47th Protection Coordination Sub Committee Meeting to be held on 15-09-2015 Page 7
TANGEDCO, (b) monitor the status of completion of remarks of protection audit in
respect of all constituents of Southern Region in Protection Coordination Sub-
Committee (PCSC) meetings, and (c) to coordinate periodic protection audit to be
carried out in Southern Region after deliberation in SRPC. All the constituents of
Southern Region are directed to file their status with SRPC on regular basis to
facilitate proper monitoring in PCSC meetings. SRPC is directed to submit bi-
annually status report to the Commission confirming the completion of Phase-I,
Phase-II and R&M works of protection audit remarks of the constituents of Southern
Region.
In compliance of above Order, APGENCO, NTPC (SR), Talcher, Puducherry,
PGCIL (SRTS-I)& PGCIL (SRTS-II), MAPS and TANGEDCO are requested to
furnish the recent status of protection audit remarks (both Phase-I & Phase-II) by
15.09.2015 for submitting a proper reply to the Hon’ble Commission.
10. Other Protection Issues, if any, with the permission of the Chair
11. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC
meetings on monthly basis. It is requested that Agenda Items for the PCSC meetings,
if any, may please be sent latest by 5th
working day of the month to SRPC Secretariat
to compile and circulate the same so as to have fruitful discussions in the PCSC
meetings.
12. Date of next PCSC meeting
The 48th
PCSC meeting would be conducted on 29.10.2015 (Thursday) at SRPC,
Bangalore.
*******
![Page 11: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/11.jpg)
Annexure- I
Page 1 of 5
Grid Occurences
1. ग्रिडडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid Disturbances:
Sr. No.
क्र.सं. घटनाकावििरण /
Details of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Tripping at
Srisailam left bank
power station
18-08-2015
at 15:25 hrs
400kV Srisailam-Mamidapalli
line-2, 400kV Srisailam-
Satenapalli line-2 and 400 kV
Srisailam-Kurnool line tripped
during multiple tripping at
Srisailam power station. 400kV
Srisailam-Mamidapalli-1 and
400kv Srisailam-Satenapalli-1
was kept out of service due over-
voltage conditions. There was no
generation at Srisailam left bank
power station. Triggering
incident was failure of CT in
400kV Srisailam-Satenapalli
line-2 at Srisailam end.
GD-1
![Page 12: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/12.jpg)
Annexure- I
Page 2 of 5
2. ग्रिडडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid incidents:
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Tripping of HVDC Bhadrawati pole-1& 2
14-017-2015 at 11:01 hrs
HVDC pole -1&2 tripped due to failure of auxiliary supply
GI-2
2
Tripping of 400kV
Gajwel-Hyderabad
line at 18-07-2015
at 2:16 hrs
Line tripped ay Hyderabad end on
mal-operation of reactor
protection at Hyderanbad end and
direct trip was sent to Gajwel.
However line was holding from
Gajwelend .
3
Tripping of 400/220kV ICT-5 at Ramagundam
22-05-2015 at 1:30 hrs ICT-5 tripped on PRD operation.
4
Tripping of 400kV
Udumalpet-
Tirunelveli line-2 28-07-2015
at 16:48 hrs
B-phase to earth fault had
occurred in line. It was observed
that 270ms aftr occurrence of
fault, over voltage stage-2
operated at Trirunelveli and
udumalpet ends which resulted in
tripping of line.
5 Tripping of 400kV
Guttur-Hiryur line-1 29-07-2015
at 11:08 hrs
line tripped at Guttur end due to
PT fuse failure during PT supply
change over. Direct trip was
received at Hiryur end. Similar
tripping had occurred at 17:54 hrs
on 18-05-2015.
6
Tripping of 400kV
Khammam-KTPS
line-2
30-07-2015
at 6:08 hrs
Y-phase to earth fault had
occurred in line. From Khammam
end DR it was observed that the
relay after dead time tried for
auto-reclose. The fault was
persisting and relay gave a single
phase trip instead of a 3 phase trip
after 1.25 sec. R& B pole voltage
dip after 2 sec possibly due to
operation of pole discrepancy.
Auto-reclose close command
observed after 2.5 seconds and all
poles got closed.
7
Tripping of 220kV
Kadra-Karwar line-
1&2 and 220kV
Kaiga-Kadra line
31-07-2015
at 11:44 hrs
220kV KAdra-Karwar lines-1&2
tripped on earth fault in B-phase
in zone-2. Kaiga-Kadra line
tripped at Kaiga end only on
operation of directional eath fault
![Page 13: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/13.jpg)
Annexure- I
Page 3 of 5
protection.
8
Tripping of HVDC
Bhadrawati Pole-2
03-08-2015
at 02:01 hrs
Pole-2 tripped on “VCC2.MAIN
CIRCUIT FULL FLOW - V-
LOW” alarm. Heavy leakage of
Demineralised (DM) water
occurred in the Valve Cooling
System.
9
Tripping of 400kV
Coastal-NTPL line
and running units at
NTPL
03-08-2015
at 15:43 hrs
R-phase to earth fault had
occurred in 400kV Coastal NTPL
line. Line auto-reclosed at NTPL
end and failed to reclose at Coatal
end. Auto reclose block was
persisting due to PLCC channel
fail. Also running Units-1&2 at
NTPL tripped on operation of GT
differential protection.
10
Tripping of 400/220
kV ICT-2 at
Gazuwaka
(Vishakapatnam)
04-08-2015
at 12:49 hrs
ICT-2 tripped on operation of
220kV Bus bar protection of
220kV Bus bar-2 at 220kV VSS
station of APTRANSCO.
11
Tripping of HVDC
Bhadrawati Pole-1
05-08-2015
at 10:53 hrs
Main pump-2 of valve cooling got
tripped during dip in 33kV
auxiliary bus voltage. Valve
cooling flow got reduced due to
tripping of pump and resulting in
tripping of pole-1
12
Tripping of 400kV
VTPS-Satenapalli
line-1
05-08-2015
at 23:48 hrs
Line tripped on direct trip receive
at Satenapalli end.
13
Tripping of Unit-
1&2 along with
400/220kV ICT-2 at
Raichur TPS
06-08-2015
at 4:51 hrs
220kV RTPS-Lingasugur line-2
tripped at TPS end on operation of
distance protection zone-1.
400/220kV ICT-2 got tripped on
operation of earth fault protection.
220kV RTPS-Lingasugur line-
1&3 tripped on distance
protection zone-2 and zone-3
respectively. Due to tripping of
ICT-2, the running units got
overloaded and it was mentioned
that under frequency occurred as
units are on load control. The
Units got tripped on under
frequency. D
14
Tripping of 400kV
Talaguppa-
Neelamangala line
13-08-2015
at 12:57 hrs
and 19-08-
2015 at 19:30
hrs
Reason for tripping needs to be
furnished. FIR, DR/ EL not
provided
![Page 14: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/14.jpg)
Annexure- I
Page 4 of 5
15
Tripping of 400kV
Hassan-UPCL line-2
17 Aug 2015
at 22:53 hrs
and
16thAugust
2015 at 3:01
and 23:59 hrs
Line tripped on operation of over-
voltage protection at UPCL end
on both days. However D.R / EL
of Hassan station was not
furnished to validate the same.
16
Tripping of 765kV
Kurnool-NPS line-1
19-08-2015
at 13:43 hrs
line tripped on operation of line
reactor R –phase WTI at Kurnool
end and direct trip was received at
NPS end.
3. Failure or non-operation of Auto reclose during transient fault
Sr. No.
Element Date & Time
Reason
1
Tripping of 400kV Khammam-
Kalpakka line-1
13-07-2015 at
12:12 hrs
Y-phase to earth fault occurred in
line. Line auto-reclosed at
Kalpakka end and failed to auto-
reclose at Khammam end
2
Tripping of 400kV Vemagiri-
GVK line-2 16-07-2015 at
17:02 hrs R-phase to earth fault had
occurred in line. Line auto
reclosed at Vemagiri end and
failed to reclose at GVK end
Tripping of 220kV Chikodi-
Mudshingi line
17-07-2015 at 5:01
hrs
line tripped on a R-phase to earth
fault and line tripped from both
ends. line did not auto-reclose
3
Tripping of 400kV Chikodi-
Talandage line 21-07-2015 at
17:15 hrs line tripped on R-phase to earth
fault and line tripped at both ends.
line did not auto-reclose
4 Tripping of 220kV Sedam-
Tandur line
23-07-2015 at 11:30 hrs
Line tripped on earth fault. Line
did not auto-reclose
5
Tripping of 400kV Pugalur-
Karaikudi line
at 18:40 hrs on 23-
07-2015
Line tripped on a B-phase to earth
fault. Line tripped due 2nd fault
in B-phase within reclaim time.
At karaikudi Main CB did not
reclose during 1st fault and tripped
on PD.
6
Tripping of 400kV Kayatahr-
Karaikudi line
26-07-2015 at
18:26 hrs
Y-phase to earth fault had
occurred in line. Line auto-
reclosed at Karaikudi end and did
not reclose at Kayathar .
7
Tripping of 220kV Ambewadi-
Ponda line-2
02-08-2015 at
13:20 hrs
Line tripped on a transient fault in
B-phase. There is no provision
for auto reclose.
8
Tripping of 400kV Kaiga-
Guttur line-1
07-08-2015 at
11:19 hrs
Line tripped on a B-phase to earth
fault. Line tripped as there is no
provision for auto-reclose
9 Tripping of 220kV Ambewadi-
Ponda line-1
08-08-2015 at
10:51 hrs and 09-
Line tripped on a B-phase to earth
fault. Line tripped as there is no
![Page 15: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/15.jpg)
Annexure- I
Page 5 of 5
08-2015 at 11:15
hrs
provision for auto-reclose
10
Tripping of 400kV
Vijayawada-Nellore(AP) line-3
15-08-2015 at
14:04hrs and 15:40
hrs
Line tripped on a B-phase to earth
fault. Line did not attempt for
auto-reclose at Vijayawada
11
Tripping of 220kV Ambewadi-
Ponda line-1
17-08-2015 at
13:20 hrs
Line tripped on a transient fault .
There is no provision for auto
reclose.
12
Tripping of 400kV
Vijayawada-Nellore line-2
20-08-2015 at
20:53 hrs
Line tripped on a B-phase to earth
fault. Line auto-reclosed at
Vijayawada end and line did not
reclose at Nellore end.
13
Tripping of 220kV Sabarigi-
Theni line
16-08-2015 at
12:15 hrs and 17-
08-2015 at
10:02hrs
Line tripped o earth faults.
Attempt for Auto reclose could
not be established
4. Lines tripping due to tripping at one end/PLCC mal-operation
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Tripping of 400kV
Kayathar-Karaikudi
line-2 26-07-2015
at 23:03 hrs
Line tripped on operation of
overvoltage protection at
Karaikudi end. Over voltage
protection was found to be in
order. However voltage was
continuously observed in D.R of
Karaikudi station.
2 Tripping of 400kV
RTPS-YTPS line
20-08-2015
at 00:14 hrs
Line tripped at RTPS end only
![Page 16: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/16.jpg)
Annexure- II
1 / 18
![Page 17: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/17.jpg)
Annexure- II
2 / 18
![Page 18: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/18.jpg)
Annexure- II
3 / 18
![Page 19: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/19.jpg)
Annexure- II
4 / 18
![Page 20: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/20.jpg)
Annexure- II
5 / 18
![Page 21: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/21.jpg)
Annexure- II
6 / 18
![Page 22: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/22.jpg)
Annexure- II
7 / 18
![Page 23: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/23.jpg)
Annexure- II
8 / 18
![Page 24: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/24.jpg)
Annexure- II
9 / 18
![Page 25: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/25.jpg)
Annexure- II
10 / 18
![Page 26: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/26.jpg)
Annexure- II
11 / 18
![Page 27: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/27.jpg)
Annexure- II
12 / 18
![Page 28: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/28.jpg)
Annexure- II
13 / 18
![Page 29: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/29.jpg)
Annexure- II
14 / 18
![Page 30: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/30.jpg)
Annexure- II
15 / 18
![Page 31: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/31.jpg)
Annexure- II
16 / 18
![Page 32: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/32.jpg)
Annexure- II
17 / 18
![Page 33: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/33.jpg)
Annexure- II
18 / 18
![Page 34: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/34.jpg)
Meeting
No /
Index
Details of
Event
Date Reason PCSC Recommendations Utility
Responsib
le for
implemen
tation
Status of Recommendations
as on 04.08.2015
Remarks
45/II/14 Tripping
of
400/220
kV ICT-
1&2 at
Gooty
substation
31-05-2015at
06:37 hrs
As per FIR, ICT-1&2
tripped on operation of
directional overcurrent
and earth fault
protection. It was
reported that there was
fault in 220kV
APTRANSCO system
1. APTRANSCO to check resistive reach of the
distance relays on 220 kV Gooty SS – Gooty RS
line
2. APTRANSCO to check time coordination of
distance relay on Gooty SS – Gooty RS line at
Gooty SS with Gooty ICT’s (1 & 2) back-up
protection.
APTRAN
SCO
Yet to be informed Pending
44/III/2 Tripping
of 400kV
Ghanapur-
Mamidap
alli
line
15-04-2015
at 2:03 hrs
Line tripped at
Mamidapalli end only
and was holding at
Ghanapur. Overvoltage
protection had operated
at Mamidapalli
TSTRANSCO to make DR
functional at Mamidipalli
TSTRAN
SCO
TSTRANSCO informed vide their mail dated 24.06.15 that the
existing relays would be replaced with numerical relays in DPR
works.
Pending
Pending Implementation of PCSC Recommendations (30th to 45th)
Andhra Pradesh
Telangana
Karnataka
42/II/3 Outage at
Regulapa
du
station of
APTRAN
SCO
21-02-2015
at
00:49 hrs
Y-Ph Metering PT
failed at 220KV
Ragulapadu Substation.
Fault got cleared
by tripping of lines from
remote ends.
APTRANSCO to furnish the remedial
measures taken in consequent to the tripping
incident along with the status of bus bar
protection and bus coupler at Regulapadu S/s.
A/R feature to be enabled on Regulapadu –
Alipuira 220 kV inter-state line.
APTRAN
SCO
Mail received on 27-05-2015:
1)Failed metering PT was replaced with new PT.
2) 220kV Ragulapadu is a single bus system. Hence there is no
provision for bus coupler at Ragulapadu SS.
Mail received on 24-06-2015:
APTRANSCO Vide Ltr. Dt. 23/06/2015, requested KPTCL to
furnish the details of available tele protection equipments and
details of the equipments going to be procure for enabling the
carrier aided protection on 220KV Ragulapadu-Alipura line. Based
on the KPTCL information we will take further necessary action.
Mail recieved on 22-08-2015:
APTRANSCOhas planned to commission ABB make ETL-41 type
PLCC terminal along with NSD-50 type protection coupler at
Ragulapadu end towards Alipura. vide our Ltr Dt 23-07-2015, it is
requested KPTCL to arrange ABB make ETL-41 cabinet with
NSD-50 type protection coupler for establishing PLC
communication between Alipura- Ragulapadu.
Pending
Annexure- III
1 / 20
![Page 35: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/35.jpg)
A fault had occurred in
220 kV Kadra and
Kodasalli. As A result,
de-energization of
220kV bus occurred at
Kadra and
Kodasalli.
13-11-2014
at 19:31hrs
GD-1 at
Kadra and
Kodasalli
hydro
power
station
38/GD/3
.5
1. A/R for 220kV lines enabled already.
2. Shut down of lines availed to commission the auto reclosing
schme for 400 kV line at BTPS.
Mail recieved on 28-05-2015:
P.O. placed for procurement of timers for A/R function. Work
shall be completed by July 2015.
Mail recieved on 07-07-2015:
P.O. placed for procurement of timers for A/R function. Work
shall be completed by August 2015.
A/R at BTPS end to be made operational
within one month
KPCLTransient fault in R-
phase.
Line did not auto
reclose
26-06-2014 Pending400kV
Raichur-
BTPS line
34/III/1
Mail recieved on 28-05-2015:
1) e-NIT floated on 28.07.2014 for procurement of Numerical
distance relays & GPS. As there is change in scope of work and
quantity of relays by more than 25%, which is not permitted as per
KTPP act. Hence, tender cancelled and refloated on 05.05.2015
with revised scope of work and revised PQR.
2. However, as per the recommendations of PSAG, Relays
were temporarily rearranged, replaced and wired up. testing &
commissioning shall be completed with the assistance of KPTCL.
Mail recieved on 07-07-2015:
1. Cover -1 of the bid is scheduled for open eing on 25.06.2015.
2. As per the recommendations of PSAG, Relays were temporarily
rearranged. testing & commissioning completed with the assistance
of KPTCL.
PendingKPCL1. The PCSC forum requested KPCL to speed
up the installation of Numerical Distance
Protection relay in Kadra –Kaiga and
Kodasalli –Kaiga.
2. The PCSC forum requested KPCL to submit
the implementation status of PSAG-10
recommendations within a week’s time.
Mail recieved on 28-05-2015:
1. e- Tender folated for the retrofit of existing static relays with
Numerical version for lines M.nagar,M.bad,ICT-1 & 2 -Technical
Bid & Price bid opened . Bid evaluation and approval to place
P.O. is in progress.
2. Retrofit of existing bus bar (CAG-34) with numerical version -
Budgetetory offers obtained and is in process.
3. Order placed on M/s Siemens to replace relays. The work will
be Completed by May - 2015.
Mail recieved on 07-07-2015:
1. Retrofit of existing static relays with Numerical version for lines
M.nagar, M.bad and ICT- 1 & 2 -- Inspection of the Numerical
relays at M/s Siemens works completed on 11-06-2015 and
Dispatch clearance has been issued. Materials received.
2. Retrofit of existing bus bar (CAG-34) with numerical version –
Budgetary offers obtained and is under process.
KPCLThe PCSC forum recommended for
replacement of existing electromechanical
relays with Numerical relays.
Spl meeting held at
RTPS on 13th
and 14th
March 2014
Mar-14RTPS
Tripping
incidents
and the
Spl
meeting
held at
RTPS on
13th and
14th
March
2014
30/I/A Pending
Annexure- III
2 / 20
![Page 36: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/36.jpg)
Circuit breaker of
400kV Guttur-Hiriyur
line-1 failed at Guttur
end while availing
shutdown for
replacement of CVT.
The
failure of breaker
caused bus fault at
Guttur.
KPTCL was requested to expedite the early
implementation of pending recommendations
of:
1. Protection Audit (Phase-I & Phase-II)
2. PSAG-4, PSAG-5, and PSAG-8
KPTCL Mail received on 27-05-2015 & 29-07-2015:
Latest satus of implementatin of Phase-1 &2 recommendations,
PSAG 4,5 and 8 is being obtained from field. The Status will be
updated witin a weeks time.
Pending05-11-2014
at 11:42 hrs
GD-1 at
Guttur
Substation
of KPTCL
38/GD/3
.2
38/GD/3
.1
GD-1 at
Mahaling
apura
Substation
of KPTCL
25-10-2014 Fault had occurred in
220kV
Mahalingapura-
Narendra line-2. Due to
the
failure of relay
operation at
Mahalingapura,
breakers at remote end
tripped which
resulted in bus dead
condition.
1. PCSC forum recommended KPTCL to
replace the old static distance protection
relays with numerical relays.
2. PCSC forum also requested KPTCL to
provide a broken conductor alarm indication in
Control Room.
3. Standing instruction needed to be given to the
all substation personnel for not changing the
relay settings without approval of RT/MRT
wing.
KPTCL Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
1.Existing Back up relays will be replaced by numerical type
distance relays.Procurement is in tendering stage. Remaining
observations were attended.
Pending
34/I/6 400/220
kV ICT-1
& 2 at
MUNIR
ABAD
16-07-2014 As reported directional
over current relay of
ICT’s operated due to
snapping of line
jumper in 220kV
Lingapur line.
1. Bus bar protection shall be provided by
asset owner ( i.e KPTCL).
2. Settings for main distance protection &
Overcurrent protection shall be examined and
reviewed.
3. Time synchronization of the Substation
shall be ensured.
4. Correct DR shall be submitted to the SRLDC
for trip analysis.
KPTCL Mail recieved on 27-05-2015 (KPTCL):
1. KPTCL has taken action to provide bus bar protection to 220kV
buses.
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
Mail received on 29-07-2015 (KPTCL):
Initial Tendering stage
A fault had occurred in
220 kV Kadra and
Kodasalli. As A result,
de-energization of
220kV bus occurred at
Kadra and
Kodasalli.
13-11-2014
at 19:31hrs
GD-1 at
Kadra and
Kodasalli
hydro
power
station
38/GD/3
.5
Pending
Mail recieved on 28-05-2015:
1) e-NIT floated on 28.07.2014 for procurement of Numerical
distance relays & GPS. As there is change in scope of work and
quantity of relays by more than 25%, which is not permitted as per
KTPP act. Hence, tender cancelled and refloated on 05.05.2015
with revised scope of work and revised PQR.
2. However, as per the recommendations of PSAG, Relays
were temporarily rearranged, replaced and wired up. testing &
commissioning shall be completed with the assistance of KPTCL.
Mail recieved on 07-07-2015:
1. Cover -1 of the bid is scheduled for open eing on 25.06.2015.
2. As per the recommendations of PSAG, Relays were temporarily
rearranged. testing & commissioning completed with the assistance
of KPTCL.
PendingKPCL1. The PCSC forum requested KPCL to speed
up the installation of Numerical Distance
Protection relay in Kadra –Kaiga and
Kodasalli –Kaiga.
2. The PCSC forum requested KPCL to submit
the implementation status of PSAG-10
recommendations within a week’s time.Annexure- III
3 / 20
![Page 37: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/37.jpg)
39/I/5 Tripping
of
400/220k
V
ICT-2 at
Hoody
substation
of KPTCL
01-12-2014 Suspected mal-
operation of 220kV side
Rphase
over current relay
1. PCSC forum recommended KPTCL to
replace the relay with a different make.
2. KPTCL was also requested to train the O&M
personnel adequately before performing any
maintenance works to avoid such unwanted
trippings.
KPTCL Mail received on 27-05-2015 & 29-07-2015:
C&R panels of 500MVA ICT 1&2 will be replaced under
scheduled R&M works. O&M personnel are instructed to take
sufficient care in order to avoid unwarrented trippings.
Pending
40/IV/1 220kV
Sedam-
Tandur
line
20-12-2014
at 22:20 hrs
Line tripped on Yphase
to earth fault from both
the ends
KPTCL was requested to explore the possibility
of providing A/R feature to this line and
submit the remedial measures to the PCSC
forum.
KPTCL Mail recieved on 29-07-2015:
Carrier protection is being restored for 220kV Sedam-Tandoor line
at Sedam end. After restoring the carrier protection , AR will be
enabled.
Pending
41/I/1 GD-1 at
220kV
Kadra
power
Station of
KPCL
16-02-2015
at 12:56 hrs
Triggering incident was
B-phase to earth fault
had occurred in 220kV
Kadra-Kodasalli line.
Line tripped from
Kodasalli end only.
220kV Kaiga-Kadra
tripped in Zone-3 from
Kaiga end. Tripping of
evacuating lines caused
bus shut down at Kadra
hydro station.
1. KPCL to make functional the Main2
(EPAC) relay with the help of KPTCL at the
earliest.
2. KPCL to investigate the reason for DC
fuse fail during transient fault in 220kV Kadra-
Kodasalli line including the testing/ checking of
DC supply cables, breaker control cables, and
trip coils.
3. KPCL to ensure supply for Main-1& Main-
2 protections, Trip Coils (TC1, TC2) from
separate battery banks.
KPCL Mail received on 28-05-2015:
1. Main-2 relays already installed and commissioned.
2. DC fuses are intact. Till date no such incidence occurred.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC
will be reviewed.
Mail received on 07-07-2015:
1. Completed.
2. Completed.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC
will be reviewed.
Mail received on 28-04-2015:
1. In view of operating 220kV Ambewadi SS in split bus mode,
action is being taken up by KPTCL . Problem in the 220kV bus
coupler breaker is attended and isolator overhauling work is
under progress. Spilt bus operation at Ambewadi will be made
possible at the earliest.
2. ICT protection system at Ambewadi and trippings occured at
Supa GS during the instance is checked up and remedial measures
already furnished in this regard.
Mail recieved on 29-07-2015:
Action is being taken by KPTCL for operating Ambewadi in split
bus mode. Problem in bus coupler breaker is attended.Isolator
overhaulling work is completed.PTs are already provided to
220kV Bus-II. After commissioning of Bus-II PTs, Ambewadi
can be operated in split bus mode. Pending works will be
completed within a months time.
KPTCL1. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation
at Ambewadi and submit the details of the
same to PCSC forum.
2. KPTCL shall provide the details of the
tripping of Supa hydro station connected
downstream from 110 kV bus.
Triggering incident was
B-phase to earth fault in
220kV Ambewadi-
Nagzari line-1. B-pole
of breaker did not open
at Ambewadi end. LBB
protection not available
at Ambewadi end. All
elements tripped on
Zone-2 from remote
ends.
22-12-2014
at 21:22 hrs
GD-1 at
220kV
Ambewad
i Station
of KPTCL
40/I/1 Pending
Pending
Annexure- III
4 / 20
![Page 38: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/38.jpg)
42/I/2
(GD)
Complete
outage of
220kV
Ambewad
i
substation
of KPTCL
12-03-2015
at 7:51 hrs
Fault in 220kV
Ambewadi-Nagjheri
line-2
1. KPTCL shall provide A/R feature on
Ambewadi – Ponda 220 kV D/C inter-state line.
2. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation at
Ambewadi and submit the details of the
same to PCSC forum.
KPTCL Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of
PLCC.
Pending
Mail received on 27-05-2015: 1. Bus Bar protection will be
provded under R&U.
2. A/R yet to be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of
PLCC.
KPTCL1. KPTCL to provide Bus Bar protection and
LBB protection at Sedam S/s and furnish
the status of their implementation to PCSC
forum.
2. KPTCL to implement A/R feature on 220 kV
Sedam-Tandur inter-state line.
Fault occurred in 220kV
Sedam-Shahpur line
15-02-2015
at 14:24 hrs
Complete
outage of
220kV
Sedam
substation
of KPTCL
42/I/1
(GD)
Pending
Mail received on 28-04-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage. 2. Action is being taken to restore the carrier
protection for 220kV Sedam-Tandoor line. AR will be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for
220kV Sedam-Tandoor line. AR will be enabled after
restoration of PLCC.
KPTCL 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
R-Phase to ground fault
occurred on 220kV
Sedam-Shahpur line.
Fault not cleared from
Sedam end due to stuck-
breaker condition.
While the Sedam-
Sahapur line tripped
from Shahapur end in
Zone-1, the other 220
kv lines from Sedam
tripped at remote ends
in Zone-2. This caused
complete outage of
220kV Sedam
substation.
27-01-2015
at 8.00 hrs
Complete
outage at
220kV
Sedam
Substation
of KPTCL
(GD-1)
41/I/4 Pending
Mail received on 27-05-2015:
Carrier protection is put in to service. AR will be enabled at the
earliest.
Mail received on 29-07-2015:
Action is taken for enabling AR for Mudashinge and Talandage
lines. Work is scheduled during first week of August 2015.
KPTCL1. KPTCL to provide A/R feature on the 220
kV Chikkodi – Talandage, and 220 kV
Chikkodi –Mudashinge inter-state lines.
2. KPTCL to carry out E/F relay coordination
for Chikkodi - Talandage and Chikkodi –
Mudashinge lines in coordination with
Maharashtra.
Lines tripped during test
charging 220kV
Chikodi-Belgaum line-2
from Chikodi
end.
20-02-2015
at
06:40 hrs
Tripping
of 220kV
Chikodi-
Talandage
and
220kV
Chikodi-
Mudshing
i line
42/II/2 Pending
Annexure- III
5 / 20
![Page 39: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/39.jpg)
43/II/14 Tripping
of
400/220k
V ICT-1
at
BTPS
14-01-2015
at 1:09
hrs
ICT tripped due to
operation of Over
current and Earth fault
relay
KPCL to check the possibility of providing line
differential protection between RTPS and
Yermarus stations.
KPCL KPCL vide their mail dated 07.07.2015 informed that revised relay
settings would be incorporated in co-ordination with KPTCL.
Pending
44/II/10 Tripping
of 400kV
Raichur-
RTPS line-
2
26-04-2015
at 18:01
hrs
Line tripped on
operation of overvoltage
protection at RTPS.
Line was
holding from Raichur
(PG)
KPCL to check the drop off to pick up ratio of
the OV relay at RTPS end.
KPCL Mail received on 07.07.2015:
Same will be checked during next shutdown.
Pending
220kV Kodasalli-
Nagjheri line-1 tripped
from Kodasalli end on
operation of
distance protection,
zone-2.
220kV Kodasalli-
Nagjheri line-1&2 is
kept opened from
Nagjheri end, hence
fault
could not be cleared
with carrier aided
protection. Backup
earth fault relay at
Kaiga end got operated
during the event and
resulted in tripping of
220kV Kaiga-
Kodasalli line from
Kaiga end.
22-04-2015
at
20:28 hrs
Tripping
of 220kV
Kaiga-
Kodasalli
and
220kV
Kodasalli-
Nagjheri
line- 1
44/II/3 1. KPCL to check the possibility of
implementing Permissive Over Reach (POR)
with Echo feature at Kodasally end.
2. If the above is not possible, KPCL shall
check the possibility of keeping the 220kV
Kodasalli-Nagjheri lines OPEN at Kodasalli
end and idle-charged at Nagjheri end, and
implement the same.
KPCL Mail received on 07.07.2015:
The matter had been discussed with KPTCL. KPTCL
recommended to keep Zone-2 time lever to zero. If this is
acceptable, then the same shall be incorporated immediately.
Pending
Annexure- III
6 / 20
![Page 40: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/40.jpg)
45/II/13 Tripping
of
400/220k
V ICT-2
Raichur
TPS
30-05-2015at
21:59 hrs
ICT-2 tripped due to
operation of group-2
master trip relay.
KPCL to wire/ connect a spare contact of static
relay to DR unit to capture operation of Group-
2 master trip relay as a temporary arrangement.
KPCL Yet to be informed Pending
45/III/12 Tripping
of 400kV
Raichur-
BTPS line
01-06-2015
at 01:02 hrs
line tripped on R-phase
to earth fault. Line did
not auto-reclose
KPCL to make A/R operational on 400 kV
RTPS – BTPS S/C line at both ends.
KPCL Yet to be informed Pending
Tamil Nadu
44/I/3
(GD)
Outage of
Tiruvalam
substation
24-05-2015
at 19:13 hrs
Failure of Y-phase CT 1. TANTRANSCO to remove the intentional
time delay of 200ms given for STUB protection
as
it is an instantaneous protection.
2. TANTRANSCO to carry out Dissolved Gas
Analysis (DGA) to monitor the healthiness of
all CT’s of similar make.
3. TANTRANSCO to submit the CT failure
report to CEA with a copy to SRPC.
TANTRA
NSCO
TANTRANSCO vide their mail dated 24.06.15 informed that Oil
samples collected and test results awaited. CT failure report sent to
CEA on 20.06.2015.
Mail received on 14.07.2015:
1. STUB protection settings will be revised to 2 In / Inst.
2. DGA test conducted in similar make CTs and the test results are
found normal. (Completed).
3. Completed.
Mail recieved on 24-07-2015:
1. STUB protection settings will be revised to 2 In / Inst.
2. DGA test conducted in similar make CTs and the test results are
found normal.
Line-2 tripped on R-
phase to earth fault.
Line autoreclosed at
SVChatram end and
failed to reclose at
Alamathy end. Bphase
to earth fault in line-1.
Line tried for A/r but
due to permanent fault
line did not reclose. ICT
tripped on operation of
over flux protection.
29-03-2015
at
15:29 hrs
Tripping
of 400kV
Alamathy-
SVChatra
m line-
1&2
and
400/230k
V ICT
at
S.V.Chatr
am
43/II/5 TANTRANSCO was requested to swap the
relays between two stations, so that
Main-1 and Main-2 will be of different make at
each station.
TANTRA
NSCO
TANTRANSCO vide their mail dated 24.06.15 informed that
different relays in Main-I & Main-II would be ensured at the
earliest.
Mail recieved on 24-07-2015:
Different relays in Main-I & Main-II will be ensured.
Pending
Pending
Annexure- III
7 / 20
![Page 41: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/41.jpg)
Mail received on dated 24.06.15:
2. Zero sequence compensation enabled in the relay on 19.06.2015.
(Completed)
Mail received on dated 14.07.15:
1.No other Feeder / ICT trippings recorded at the time of tripping
of ICT at Thiruvalam.
2. Completed.
Mail recieved on 24-07-2015:
No other Feeder / ICT trippings recorded at the time of tripping of
ICT at Thiruvalam. Zero sequence filter enabled in the relay on
19.06.2015.
TANTRA
NSCO
1. TANTRANSCO to take up with OEM for
ensuring stability of the differential relay for
thorough fault and other non-transformer fault
conditions.
2. TANTRANSCO to enable zero sequence
compensation for both the ICTs to avoid
tripping for through fault condition.
ICT-1 tripped on
operation
of differential
protection.
17-04-2015
at
20:15 hrs
Tripping
of
400/230k
V ICT-1
at
Tiruvalam
Substation
44/II/1 Pending
Kerala220 kV breaker of unit-
3 at Idukki Power
house flashed and bus
differential protection
acted. All Generators
(6Nos.) along with all
220 kV feeders tripped
during the incident.
28-04-2015
at 12:30 Hrs
Complete
outage of
Idukki
Hydro
Power
Station
(GD-1)
44/I/1
(GD)
Pending
As per FIR, failure of R-
phase CT of 230kV
Alamathy-Manali feeder
occurred at Alamathy
end. Hence 230KV Bus
bar protection Zone 1 &
2 Operated at Alamathy
substation. All the
230KV feeders, 230KV
Bus Coupler, ICT-3, 4
& 5 LV breakers got
tripped.
TANTRANSCO to furnish a detailed tripping
report including reasons for delayed clearance
of fault at Almathy.
TANTRA
NSCO
Yet to be informed Pending25-05-2015at
09:08hrs
Multiple
tripping at
400/230k
V
Alamathy
substation
45/II/12
Mail received on 31-07-2015:
1. Reducing the sensitivity of REF protection of Unit # 4, 5, 6 at
Idukki PH: - Generation wing is planning to purchase new
transformer management relays with low impedance REF
protection. Purchase procedures initiated.
2. The replacement/ repair of faulty breakers are under the
consideration of Generation wing. Breakers will be replaced /
repaired in a phased manner. Unit #3 breaker was replaced with
available breaker from the 220kV IDMD feeder. The 220kV CBs
of unit #2 and unit #3 will be replaced with in two months.
3. No abnormalities were noticed in the PLCC equipment at New
Pallom station. It is kept under observation.
KSEB1. KSEB to reduce sensitivity of REF protection
appropriately at Idukki PH.
2. KSEB to replace/ repair the faulty breaker.
3. KSEB to check the PLCC equipment at New
Pallam and inform the remedial measures taken
to PCSC forum.
Annexure- III
8 / 20
![Page 42: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/42.jpg)
41/II/6 Tripping
of 400kV
Coastal
Energen
(CEPL)---
NTPL line
07-02-2015
at 01:07 hrs
and at
00:08hrs on
08-02-2015
B-phase to earth fault
had occurred in Line
during both instants. As
seen from D.R of
Coastal Energen
distance relay sensed
fault in zone-2 and earth
fault protection had
operated.
PGCIL to carry out hot-line washing
regularly as NTPL is in highly polluted
location.
PGCIL Yet to be informed Pending
41/II/8 Tripping
of HVDC
Talcher-
Kolar pole-
2
10-02-2015
at 7:37 hrs
Pole-2 tripped due to
ESOF from Talcher end
PGCIL to test the pumps at Talcher HVDC
during pole shut-down and submit the report
to PCSC forum.
PGCIL Yet to be informed Pending
PGCIL34/I/7 HVDC
BHADR
AVATHI
POLE 2
18-07-2014 As reported pole-2
tripped due on 5th
harmonic alarm.
1. Complete analysis of the faults and
rectification/remedial action taken to avert
similar occurrence in the HVDC Back to Back
station shall be submitted.
2. The PCSC forum recommended PGCIL,
SRTS-I take up the issue with WRTS to submit
the report as per IEGC guidelines.
3. SRLDC is also requested to send a letter to
WRLDC to submit the reports to SR also.
4. Based on the SRTS/SRLDC
correspondences, SRPC would take it up with
WR and PGCIL if the issue is not getting
resolved.
PGCIL Reply received during 46th PCSC meeting:
Being pursued with POWERGRID, WR-1
Pending
Mail received on 31-07-2015:
1. All quadramo relays in Madakkathara is working in good
condition. Replacement of the same with numerical one will be
carried out in a phased manner.
2. The SPS settings were revised after this disturbance and the
revised logic is already forwarded to that office vide reference (2)
above. Copy of the same is attached
KSEB1. KSEB to replace Quadramo relay (static)
with numerical one at Madakkathara station.
2. After finalizing the SPS, KSEB shall share
the details of the revised SPS logic for the
North Kerala system to PCSC forum.
Blackout had occurred
in North kerala i.e.,
Complete outage of
220kV Mylatty, 220kV
Taliparamba, 220kV
Kanhirode, 220kV
Vadakara and Shoranur
substations occurred
due
to tripping of 220kV
Thrissur-Areacode and
220kV Thrissur-
Shoranur feeders.
09-05-2015
at 11:18hrs
Disturban
ce in
North
Kerala
system
(GD-1)
44/I/2
(GD)
Pending
Annexure- III
9 / 20
![Page 43: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/43.jpg)
41/II/16 Tripping
of 400 kV
NEYVEL
I TS 2 -
PUGALU
R
15-02-2015
at 18:38 hrs
Line tripped at pugalur
end due to direct trip
receive
PGCIL to check the protection coupler of
PLCC system at Pugalur end.
PGCIL Yet to be informed Pending
41/III/2 Tripping
of 400kV
Udumalpe
t-Palakad
line-1&
400
Udumalpe
t-Arasur
line-2
09-02-2015
at 9:50hrs
PLCC of Udumalpet-
Arasur-2 mal-operated
• PGCIL to furnish remedial measures taken.
• PGCIL to properly tune PLCC panels.
PGCIL Yet to be informed Pending
42/II/8 Tripping
of HVDC
Talcher-
Kolar pole-
1
23-02-2015
at 15:37
hrs
Pole 1 of Talcher-Kolar
HVDC
Transmission system
tripped on receipt
of ESOF (Emergency
Switch-off) from
Talcher
PGCIL (SR-II) to submit a report on the reasons
for operation of filter protection at
Talcher, and subsequent receipt of ESOF at
Kolar.
PGCIL Yet to be informed Pending
Tripping
of 400kV
Jeypore-
Gazuwaka
line-
1&2 and
tripping
of
HVDC
back to
back pole-
1&2 at
Gazuwaka
23-02-2015
at
13:34 hrs
HVDC pole-1 got
tripped due to failure
of 4 no. power supply
card. HVDC
pole-2 tripped on DC
low voltage trip.
400kV Jeypore-
Gazuwaka line-1&2
tripped due to
operation of Over
voltage
protection at Gazuwaka
end.
PGCIL (SR-II) to submit the report of M/s
ABB’s on preventing supply card failures.
PGCIL Yet to be informed Pending42/II/7
Annexure- III
10 / 20
![Page 44: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/44.jpg)
42/II/13 Tripping
of 400kV
Neelaman
gala-
Mysore
Line-1
02-03-2015
at 23:30
hrs
Line tripped on
operation of over
voltage protection at
Neelamangala end.
PGCIL (SR-II) to check OVR operation at
Nelamangala.
PGCIL Yet to be informed Pending
42/II/23 Tripping
of HVDC
Bhadravat
hi Pole-1
18-03-2015
at
13:55 hrs
Pole tripped due to
failure of auxiliary
supply
PGCIL (SR-I) to submit the compliance report
on PSAG-11 recommendations to PCSC
forum.
PGCIL Reply received during 46th PCSC meeting:
Tertiary Transformer charged and auxiliary power for HVDC is
being availed from tertiary widings of ICT.
Pending
43/II/2 PGCIL (SR-II) to check the possibility of
providing re-trip feature in LBB relay.
PGCIL Yet to be informed Pending
Pending
230kV Bus-2 at Hosur
(PG) got
tripped as spurious
initiation got
extended to LBB relay
of 230kV
Hosur-Hosur(PG) line
at Hosur(PG)
end due to shorting of
contacts in
lockout relay.
400/230kV ICT-2, ICT-
3, 230kV Hosur-
Vinnamangalam,
230kV Hosur(PG)-
Hosur which were
connected to Bus-2 got
tripped along
with bus coupler
breaker
26-03-2015
at 15:40 hrs
Multiple
tripping
at
400/230k
V
Hosur
substation
of
Powergrid
Reply received during 46th PCSC meeting:
Operation is in-order as per OEM manual (ABB HVDC)
42/II/22 Tripping
of
HVDC
pole-1&2
at
Gazuwaka
and
400kV
400kV
Jeypore
Gajuwaka
line -1
14-03-2015
at
17:12 hrs
HVDC Pole-1 at
Gazuwaka tripped due
to
tripping of filter banks
and Pole-2 tripped
due to operation of
differential protection.
400kV Jeypore-
Gazuwaka line-1
tripped
on over-voltage from
Gazuwaka end.
PGCIL (SR-I) to furnish the reasons for
Converter Transformer differential protection
operation for Pole-2 along with the remedial
measures taken.
PGCIL
Annexure- III
11 / 20
![Page 45: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/45.jpg)
44/I/3
(GD)
HVDC
Talcher-
Kolar pole
1 & 2 at
Kolar
24-05-2015
at 19:18 hrs
Due to valve cooling
problem
PGCIL to check the possibility of providing
manual reset of the valve cooling panels of both
the poles in the control room at Talcher and
Kolar end, and implement the same.
PGCIL Yet to be informed Pending
44/I/3
(GD)
765 kV
Raichur-
Sholapur
line 1 &
2 tripped
24-05-2015
at 19:19 hrs
Tripped on Overload. 1. PGCIL to provide the status of healthiness of
SPS contact logic in SRLDC’s SCADA.
2. PGCIL to furnish the details of the
implemented SPS-7 scheme including logic
diagram to PCSC forum.
PGCIL Yet to be informed Pending
400kV Vemagiri-
Vijayawada line-1&3,
400kV Vemagiri-
Goutami line-2, 400kV
Vemagiri-Konaseema
line-2 and 400/220kV
ICT-2 at Vemagiri
tripped
during the incident.
Triggering incident
was failure of B-phase
L.A in 400kV
Vijayawada-Vemagiri
line-1 at
Vemagiri end.
25-04-2015
at 10:04
hrs
Multiple
tripping at
Vemagiri
substation
of
APTRAN
SCO
44/II/6 1. PGCIL (SR-I) to enable Auto reclosure
feature at Vijayawada end.
2. PGCIL (SR-I) to check distance relay settings
for Vijayawada – Vemagiri line 3, and
furnish a compliance report to PCSC forum.
PGCIL Yet to be informed Pending
43/II/2 PGCIL (SR-II) to check the possibility of
providing re-trip feature in LBB relay.
PGCIL Yet to be informed Pending
Tripping
of 400kV
Ramagun
dam-
Hyderaba
d line-3,
400kV
Hyderaba
d-
Malkaram
line-1 and
400kV
Bus-1
at
Hyderaba
d
23-04-2015
at
15:11 hrs
400kV Ramagundam-
Hyderabad line-3 at
ramagundam end only
due to DT receive.
400kV Hyderabad-
Malkaram line-1
tripped at Hyderbad end
only and was
holding from Malkaram
end. 400kV Bus-1 at
Hyderabad due to
operation of bus
bar protection.
PGCIL (SR-I) to check healthiness of PLCC
panels at Hyderabad SS, and repair/ replace
them, if necessary.
PGCIL Yet to be informed Pending44/II/4
230kV Bus-2 at Hosur
(PG) got
tripped as spurious
initiation got
extended to LBB relay
of 230kV
Hosur-Hosur(PG) line
at Hosur(PG)
end due to shorting of
contacts in
lockout relay.
400/230kV ICT-2, ICT-
3, 230kV Hosur-
Vinnamangalam,
230kV Hosur(PG)-
Hosur which were
connected to Bus-2 got
tripped along
with bus coupler
breaker
26-03-2015
at 15:40 hrs
Multiple
tripping
at
400/230k
V
Hosur
substation
of
Powergrid
Annexure- III
12 / 20
![Page 46: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/46.jpg)
44/II/7 Tripping
of 765kV
Kurnool-
Tiruvalam
line-1
and
765kV
Kurnool-
NPS-1
25-04-2015
at
18:10 hrs
REF protection of Line
reactor of
Nellore-1&2 and
Tiruvalam line-1
maloperated
due to DC earth fault
1. PGCIL (SR-I) to submit the action taken
report on the measures suggested by their OEM.
2. PGCIL (SR-I) to check for the availability of
Chatter Disable feature in P141 and
configure it appropriately to block operation of
REF protection on DC fluctuations.
PGCIL Yet to be informed Pending
44/II/8 Tripping
of 400kV
Gooty-
NPS line-
2
26-04-2015
at 13:16
hrs
R-phase to earth fault
had occurred in
line. Lines auto-reclosed
at gooty end
and later tripped due to
DT receive from
NPS end.
PGCIL (SR-I) to coordinate STUB protection
settings with the distance protection time
settings at NPS.
PGCIL Yet to be informed Pending
45/II/21 Tripping
of
400/220k
V ICT-1
at Gooty
Substation
03-06-2015
at 12:30 hrs
ICT tripped due to mal-
operation of differential
relay
1. PGCIL to follow IS and CEA regulations
while carrying out maintenance work.
2. PGCIL to furnish a report on what caused
the ICT-1 tripping including remedial measures.
PGCIL Yet to be informed Pending
400kV Vemagiri-
Vijayawada line-1&3,
400kV Vemagiri-
Goutami line-2, 400kV
Vemagiri-Konaseema
line-2 and 400/220kV
ICT-2 at Vemagiri
tripped
during the incident.
Triggering incident
was failure of B-phase
L.A in 400kV
Vijayawada-Vemagiri
line-1 at
Vemagiri end.
25-04-2015
at 10:04
hrs
Multiple
tripping at
Vemagiri
substation
of
APTRAN
SCO
44/II/6 1. PGCIL (SR-I) to enable Auto reclosure
feature at Vijayawada end.
2. PGCIL (SR-I) to check distance relay settings
for Vijayawada – Vemagiri line 3, and
furnish a compliance report to PCSC forum.
PGCIL Yet to be informed Pending
To avoid tripping of transmission lines on
transient faults, PGCIL is recommended to carry
out periodic patrolling of lines, and ensure their
proper maintenance by carrying out jungle/
bushing clearance and trimming of tree
branches within the RoW of transmission lines
as per the SRPC transmission line patrolling
guidelines (available under the menu item "All
Uploads Operation Miscellaneous
Transmission Line Patrolling Protocol /
Guidelines for Southern Region" on SRPC
website).
Lines tripped on
transient fault. Auto
reclose was un-
successful. SR &NEW
grid separated due to
tripping of 765kV lines
03-05-2015
at 4:13 hrs
Tripping
of 765kV
Raichur-
Solapur
line-1&2
45/II/15 PGCIL Yet to be informed Pending
Annexure- III
13 / 20
![Page 47: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/47.jpg)
41/II/10 Tripping
of Hassan-
UPCL
line-2
12-02-2015
at 15:57 hrs
Line tripped due to high
resistance fault in B-
phase. DEF picked up at
hassan end and DT was
sent to UPCL. DEF
protection did not pick
up at UPCL
UPCL to revise their DEF relay settings. UPCL Mail recieved on 28-04-2015: Revised settings issued to
UPCL on 27-04-2015 for implementation.
Mail received on 27-05-2015: Revised settings have to be
implemented by UPCL
Pending
with
UPCL
41/II/12 Tripping
of 400KV
Coastal-
NTPL line
13-02-2015
at 22:54 hrs
Line tripped B-phase to
earth fault and later
tripped on R-Y phase
fault. From Coastal end
D.R, Y & B poles of
breaker opened first and
R-pole appears to be
opened on Pole
discrepancy.
CEPL to check A/R scheme at their end. CEPL Yet to be informed Pending
To avoid tripping due to transient faults, PGCIL
(SR-I) is recommended to carry out periodic
patrolling of lines, and ensure proper
maintenance of transmission lines by carrying
out jungle/ bushing clearance and trimming of
tree branches within the RoW of transmission
lines as per the ‘SRPC transmission line
patrolling guidelines’ (available under the menu
item "All Uploads Operation Miscellaneous
Transmission Line Patrolling Protocol /
Guidelines for Southern Region" on SRPC
website).
DC line fault26-05-2015
at 17.55 hrs
Tripping
of HVDC
Talcher-
Kolar
Pole-2.
45/II/29 PGCIL Yet to be informed Pending
Others37/I/9 Tripping
of
400/220k
V ICT-
1&2 at
UPCL
04-10-2014 ICT-1&2 tripped during
transient fault in R-
phase in 400kV Hassan-
UPCL line-1
To avoid tripping of ICTs for line fault, UPCL
is requested to review the settings of ICT’s
SEF relay and consider IDMT setting instead
of existing Definite Time setting.
UPCL It has been reported by UPCL that, the work of review of relay
coordination and setings for the entire plant is given to M//s
Alstom for entire plant. UPCL has furnished the settings given by
M/s Alstom for verification. Revised settings will be issued this
week for implementation
Mail recieved on 28-04-2015: Revised settings issued to
UPCL on 27-04-2015 for implementation.
Mail received on 27-05-2015: Revised settings have to be
implemented by UPCL
Pending
with
UPCL
Annexure- III
14 / 20
![Page 48: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/48.jpg)
41/IV/2 400kV
Tuticorin
PS-NTPL
line
09-02-2015
at 03:17 hrs
Y-phase to earth fault
had occurred in line.
Line auto reclosed at
Tuticorin PS end and
failed to reclose at
NTPL end.
NTPL to check A/R scheme at their end. NTPL Yet to be informed Pending
42/II/16 Tripping
of UNIT-
3
& 5 at
Jindal
power
station
08-03-2015
19:41hrs
Units tripped due to
tripping of SUT.
JSWEL to enable DEF feature in the numerical
relay for the 220 kV Jindal – Lingapur lines
at Jindal end.
JSWEL Mail received on 27-05-2015(KPTCL): Settings issued to M/s
Jindal for implementation.
Pending
with
JSWEL.
44/III/4 Tripping
of 400kV
Coastal
(CEPL)-
Tuticorin
pooling
station
20-04-2015
at 12:35 hrs
Line tripped at Coastal
energen end only and
was holding from
TTRNPS
CEPL to furnish a detailed report on this trip
event to PCSC forum.
CEPL Yet to be informed Pending
44/IV/8 Tripping
of 400kV
Hassan-
UPCL
line-2
06-05-2015
at
15:37 hrs
Y-phase to earth fault in
line. Line auto reclosed
at
Hassan end and did not
reclose at UPCL
UPCL to check A/R relay operation at their end. UPCL Yet to be informed Pending
36/II/8 400kV
Raichur-
Muniraba
d line
07-09-2014 B-phase to earth fault
had occurred in line.
Line auto reclosed at
Munirabad end and
failed to reclose at
Raichur end.
KPTCL:
PD (pole discrepancy) time delay would be
changed.
PGCIL /
KPTCL
Yet to be informed Pending
Miscellaneous
Annexure- III
15 / 20
![Page 49: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/49.jpg)
38/II/5 400kV
Ramagun
dam-
Hyderaba
d line-4
27-10-2014 Line tripped on
Bphase
to earth fault.
Line did not auto
reclose at Hyderabad
end due to
PLCCmal-operation.
Planned to replace the PLCC system within a
week's time at both the ends during the
shutdown.
NTPC/
PGCIL
Yet to be informed. Pending
Pending
with
UPCL.
39/I/2 Tripping
of
400Kv
Ghanapur-
Mamidipa
lly
line
22-12-14
at 10:52 hrs,
24-12-14 at
11:32
hrs,
24-12-14 at
16:16 hrs
Due to PLCC Mal-
operation at HYD S/S
end, DT received at
MMPLY end and line
got tripped.
PGCIL is requested check up with the
manufacturer to resolve the issue and submit
remedial measures to PCSC forum.
PGCIL/
TSTRAN
SCO
Mail received on 26-05-2015 from TSTRANSCO:
On 27-12-2014 PGCIL requested to arrange services of
OEM(Manufacturer)for identifying the problem. TSTRANSCO
arranged the same on 06-01-2015 and the manufacturer testing and
concluded that the problem in not in the newly erected digital
protection coupler at both ends and the issue is related to relay
panel at Ghanapur. [OEM minutes enclosed]
Pending
37/I/6 Tripping
of 400KV
Hassan-
UPCL
line-2
25-09-2014 High resistance fault as
the fault ampere was
very less i.e., 0.6kA at
Hassan end and nearly
0.9kA at UPCL end.
Back up earth fault
protection had operated
at Hassan.
At UPCL end the high
resistance fault got
converted into a R ph-B-
ph fault which resulted
in operation of distance
protection Zone-1.
The reason for non-
picking up of Back up
earth fault at UPCL
needs investigation.
1. At UPCL end, unused zones of distance
protection (probably zone 5 to 8) shall be
disabled.
2. At UPCL end, time synchronization
between main-1 and main-2 relays shall be
ensured.
3. UPCL shall ensure time synchronization
with Hassan substation.
4. Reasons for non operation of back up
protection at UPCL for high resistance fault
is to be submitted.
5. Reasons for not sending DT to UPCL by
Hassan end is to be submitted.
6. Settings of UPCL are to be reviewed and
informed to PCSC forum.
UPCL /
KPTCL
It has been reported by UPCL that, the work of review of relay
coordination and setings for the entire plant is given to M//s
Alstom for entire plant. UPCL has furnished the settings given by
M/s Alstom for verification. Revised settings will be issued this
week for implementation.
Mail recieved on 28-04-2015:
Revised settings issued to UPCL on 27-04-2015 for
implementation.
Mail received on 27-05-2015 (KPTCL):
Revised settings have to be implemented by UPCL
Annexure- III
16 / 20
![Page 50: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/50.jpg)
Tripping
of 400kV
NTPL-
Tuticorin
pooling
station
13-02-2015
at 23:12 hrs
Line tripped on R-phase
to earth fault at 22:53
hrs. Line auto reclosed
at Tuticorin pooling end
and holding. At 23:12
line tripped on B-phase
to earth fault in zone-2
time.
Tripping
of 400kV
NTPL-
Tuticorin
pooling
station
14-02-2014
at 1:41 hrs
B-phase to earth fault
had occurred and line
auto reclosed at 01.09
Hrs and holding from
Tuticorin PS end and
line was and up hand
tripping at 01.44.
1. PED to investigate the cause of non-
operation of ICT’s protection system
(differential protection, back-up protection)
and review the relay settings suitably.
2. PGCIL to check the settings of distance
relay and back-up relays for correctness of
operation.
Bus fault occurred in
110kV bus at
230/110kV Bahoor
substation due to failure
of Y-phase main bus
strain insulator. 220kV
lines connected to
Bahoor (viz., Bahoor-
NLC TPS II and Bahoor
– Pondy) tripped from
remote end on operation
of back up protection.
15-02-2015
at 11:20 hrs
Complete
outage at
220kV
Bahoor
Substation
of
Pondicher
ry (GD-1)
41/I/2 PED/PGC
IL
Yet to be informed Pending
41/II/13,
41/II/14,
41/II/15
PGCIL to carry out hot-line washing
regularly as NTPL is in highly polluted
location.
NTPL to review A/R scheme at their end.
PGCIL/N
TPL
Yet to be informed Pending
On account of R-phase
to earth fault, line
tripped at Hassan end
due to operation of
distance Zone-2 and non-
receipt of
carrier. From D.R of
Talaguppa end it is
observed that fault had
occurred in Yphase.
1. PGCIL and KPTCL to ascertain the reason
for the phase discrepancy in the relay
operation and take suitable remedial measures.
2. KPTCL to check the PLCC operation at
Talaguppa end and submit the report to the
PCSC forum.
PGCIL/
KPTCL
Mail recieved on 28-04-2015: End to end testing of PLCC
has been done and problem in the PLCC is atttended.
Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
End to end testing of PLCC has been done and problem in the
PLCC is atttended. Phase
discripancy in the relay operation is to be checked jointly.
Pending01-01-2015
at
13:38 hrs
Tripping
of 400
kV
TALAGU
PPA
–
HASSAN
line
40/II/3
Annexure- III
17 / 20
![Page 51: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/51.jpg)
Tripping
of 400kV
NTPL-
Tuticorin
pooling
station
14-02-2014
at 6:55 hrs
Line tripped on B-phase
to earth fault. Line did
not reclose at NTPL end
Line tripped at Coastal
end only
due to suspected PLCC
maloperation
and was holding from
Tuticorin PS end.
Running Unit at
Coastal energen also got
tripped
during the event.
PLCC end-to-end testing shall be carried out by
CEPL and Tuticorin PS (PGCIL-SR II) by
06.04.2015.
CEPL/
PGCIL(SR-
II)
Yet to be informed Pending19-02-2015
at
16:37 hrs
Tripping
of 400kV
Coastal-
Tuticorin
PS line
42/II/1
Mail received on 26-05-2015 from TSTRANSCO:
It is found that the main-2 ABB make REL316 type distance
relay was defective and same was replaced with MICOM P444 by
M/s.PGCIL on 23.04-2015. After replacement of main-II, DR can
be extracted from this relay. For EL in to service, some field
winding is pending which is being taken up in this month.
Pending42/II/18 Multiple
tripping at
Raichur
thermal
power
station of
KPCL
09-03-2015
at
06:36 hrs
400kV Raichur TPS-
Raichur(PG) line-
1&2, 400kV Raichur-
Mahboobnagar,
Unit#7 and ICT-2 at
RTPS tripped
during the incident. B
phase to earth
fault had occurred in
400kV Raichur
TPS-Raichur line-1
1. KPCL to review REF setting (DMT or
IDMTL) for unit-7 by first week of April, 2015
and
inform the same to PCSC forum.
2. TSTRANSCO to furnish Mehaboobnagar’s
DR and EL and the reasons for distance relay
operation at their end within a week’s time.
3. PGCIL (SR-I) to rectify the issues relating to
A/R operation, relay reach (Z2), reverse reach
(Z4) and SOTF auxiliary contacts within a
week’s time, and submit the actions taken to
PCSC forum.
KPCL/TS
TRANSC
O/PGCIL
(SR-I)
400kV Raichur(PG)-
Gooty line-2,
400kV Raichur TPS-
Raichur(PG)
line-1&2, 400kV
Raichur-
Mahboobnagar, Unit#5
at RTPS
tripped during the
incident
KPCL, KPTCL and PGCIL (SR-I) to furnish the
action taken report on the
recommendations given by PSAG members held
at Raichur on 22-04-2015 and
23-04-2015.
KPCL/KP
TCL/
PGCIL(SR-
I)
Yet to be informed Pending11-04-2015at
18:04 hrs
Multiple
tripping at
400kV
Raichur(P
G)
and
Raichur
thermal
power
station of
KPCL
43/II/12
41/II/13,
41/II/14,
41/II/15
PGCIL to carry out hot-line washing
regularly as NTPL is in highly polluted
location.
NTPL to review A/R scheme at their end.
PGCIL/N
TPL
Yet to be informed Pending
Annexure- III
18 / 20
![Page 52: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/52.jpg)
43/III/1 400kV
Guttur-
Narendra
line-1
11-03-2015
at 17:16 hrs
Line tripped at
Narendra end only
on direct trip receive
and line was holding
from Guttur
End to end testing shall be
conducted on 6.5.2015.
KPTCL/
PGCIL(SR-
II)
Mail received on 29-07-2015:
End to end testing is yet to be conducted
Pending
Tripping
of Unit 1
at NCTPS
24-05-2015
at 19:13 hrs
ID Fan trip
Tripping
of Unit 1
at MEPL
24-05-2015
at 19:13 hrs
Coal Mill tripped
Tripping
of Unit 1
at
Krishnapa
tnam
24-05-2015
at 19:17 hrs
Generator Protection
operated
Tripping
of Unit-8
at RTPS
24-05-2015
at 19:19 hrs
Tripped on Overvoltage.
1. MEPL to ensure healthiness of all CT’s by
carrying out Tan Delta and DGA tests wherever
necessary.
2. MEPL to take suitable action to correct the
operation of tie-CB Bay Control Unit that
caused LBB/ BBP operation.
3. PGCIL (SR-1) to carry out end-to-end
PLCC testing in coordination with MEPL and
ensure that carrier-aided protection on MEPL –
NPS line is in healthy condition.
4. SEL to properly time-coordinate their Over
Current phase and Earth fault relays in
consultation with MEPL.
Y phase CT failure at
MEPL led to tripping of
400kV NPS-MEPL,
400kV SEPL-MEPL
line and Unit-2 at
MEPL. Uni-1 was not in
service at the time of
tripping
20-05-2015
at 20:38 hrs
Complete
outage of
MEPL
power
station
45/I/2
(GD)
MEPL/
PGCIL(SR-
I)/ SEL
Yet to be informed Pending
44/I/3
(GD)
1. All Tripped units, viz., Krishnapatinam,
MEPL, Raichur, NCTPS to submit a detailed
report on this event including the remedial
measures taken to PCSC forum.
2. KPCL to check the excitation system of Unit
8 of RTPS, and submit the remedial measures
taken to PCSC forum.
KPCL/
MEPL/
APGENC
O/ TNEB
TANGEDCO vide their mail dated 07.07.2015 informed that as
per the discussion and recommendation of 44th meeting of PCSC
held on 28.05.2015, a time delay of 2 Sec had been introduced for
the above tripping for all the ID fans at NCTPS-II.
Pending
Annexure- III
19 / 20
![Page 53: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/53.jpg)
1. MEPL to ensure healthiness of all CT’s by
carrying out Tan Delta and DGA tests wherever
necessary.
2. MEPL to take suitable action to correct the
operation of tie-CB Bay Control Unit that
caused LBB/ BBP operation.
3. PGCIL (SR-1) to carry out end-to-end
PLCC testing in coordination with MEPL and
ensure that carrier-aided protection on MEPL –
NPS line is in healthy condition.
4. SEL to properly time-coordinate their Over
Current phase and Earth fault relays in
consultation with MEPL.
Y phase CT failure at
MEPL led to tripping of
400kV NPS-MEPL,
400kV SEPL-MEPL
line and Unit-2 at
MEPL. Uni-1 was not in
service at the time of
tripping
20-05-2015
at 20:38 hrs
Complete
outage of
MEPL
power
station
45/I/2
(GD)
MEPL/
PGCIL(SR-
I)/ SEL
Yet to be informed Pending
Annexure- III
20 / 20
![Page 54: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/54.jpg)
Sl.No. Element NameOutage
date/time
Revival
date/time
Reason for
OutageSender/ Receiver
Remedial Measures/ Actions
taken
1 220 kV AMBEWADI - PONDA 123-06-
2015/11:39:00
EARTH
FAULT
RELAY
OPERATED
KPTCL/ GOA To-be-discussed
2400 kV KHAMMAM - KALPAKKA
1
13-07-
2015/12:12:00
13-07-
2015/12:22:00Y - N FAULT PGCIL(SR-I)/ APTRANSCO
APTRANSCO: Auto reclose
attempted and successful for Y-
N, Zone-1 momentary fault.
Hence Line is in service from
Kalpaka End.
PGCIL(SR-II):
3 400 Kv NAGAPATNAM-TIRCHY14-07-
2015/10:57:00
14-07-
2015/11:01:00
DT
RECEIVED
AT TRICHY
PGCIL(SR-II) To-be-discussed
4 220 Kv CHIKKODI - MUDUSHINGI17-07-
2015/05:01:00
17-07-
2015/05:33:00
TRANSIENT
FAULTKPTCL To-be-discussed
5 400 kV GAJWEL - HYDERABAD18-07-
2015/02:16:00
18-07-
2015/03:28:00
MALOPERAT
ION OF
REACTOR
PROTN
TSTRANSCO/ PGCIL(SR-I) To-be-discussed
Pending Remedial Measures/ Actions taken
for the Critical Tripping Incidents (as on 01.09.2015)
Annexure-IV
1
![Page 55: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/55.jpg)
6400 Kv KRISHNAPATNAM -
NELLORE
20-07-
2015/11:27:00
20-07-
2015/12:00:00
BUS -1
TRIPPED :
REASON
AWAITED
APGENCO/ APTRANSCO
APGENCO: BUS-1 was tripped
at Power Grid Sub-
Station(PGCIL), Nellore during
the operation of the Isolators,
which is not pertaining to
APGENCO.
APTRANSCO: Line tripped at
Krishnapatnam end only.Line is
in service from Nellore-AP.
PGCIL (SR-I):
7 220 Kv CHIKKODI - TALANDGE21-07-
2015/17:15:00
21-07-
2015/20:16:00
R-PHASE TO
GROUND
FAULT
KPTCL To-be-discussed
8 400/220 kV ICT-5 AT RSTPS22-07-
2015/01:30:00
PRD
OPERATEDNTPC To-be-discussed
9 220 kV SEDAM - TANDUR23-07-
2015/11:30:00
23-07-
2015/12:11:00
EARTH
FAULTKPTCL/ TSTRANSCO To-be-discussed
10 400 Kv PUGALUR - KARAIKUDI 223-07-
2015/18:40:00
23-07-
2015/19:30:00
TRIPPED ON
B-PH FAULTPGCIL(SR-II) To-be-discussed
11400 Kv KAYATHAR - KARAIKUDI
1
26-07-
2015/18:26:00
26-07-
2015/19:31:00Y - N FAULT
TANTRANSCO/ PGCIL(SR-
II)
TANTRANSCO: Temporary
fault. Feeder normalised at
19:33 hrs. Voltage continuously
observed in D.R at Kayathar
was due to the presence of Line
Reactor.
12 400 kV VIJAYAWADA - VTPS IV 126-07-
2015/00:05:00
TRIPPED
DUE TO B-
PHASE CT
BLAST
PGCIL(SR-I)/ APGENCO
APGENCO: This issue pertains
to PGCIL.
PGCIL(SR-I):
Annexure-IV
2
![Page 56: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/56.jpg)
13 400 Kv KLVDPT - VALLUR 227-07-
2015/16:56:00
27-07-
2015/18:00:00Y - N FAULT PGCIL (SR-II)/ NTECL
NTECL: Kalivanthapattu Line 2
Y phase tripped on Y phase
earth fault at
16:56:15:688 hrs. Line got auto-
reclosed succesfully at
16:56:16:711 hrs. Then, the
line tripped again on Y to B
phase fault at 16:56:19:516.
The fault occurred due to arcing
in the newly replaced composite
long rod polymer insulator in
PGCIL tower during strong
wind. No remedial action
required at NTECL end.
14 400 Kv HASSAN - UPCL 128-07-
2015/15:35:00
28-07-
2015/16:05:00
DPR
OPERATEDPGCIL (SR-II)/ UPCL To-be-discussed
15400 kV UDUMALPET -
TIRUNELVELI 2
28-07-
2015/16:48:00
28-07-
2015/17:10:00B-N FAULT PGCIL (SR-II) To-be-discussed
16400 kV HASSAN -
NEELAMANGALA 1
29-07-
2015/19:09:00B-N FAULT PGCIL (SR-II)/ KPTCL To-be-discussed
17 400 kV GUTTUR - HIRIYUR 129-07-
2015/11:08:00
29-07-
2015/11:33:00
DT
RECEIVED
AT HYR END
KPTCL/ PGCIL (SR-II) To-be-discussed
18 400 kV KHAMMAM - KTPS 230-07-
2015/06:08:00
30-07-
2015/06:58:00
TRIPPED ON
B-PH FAULTPGCIL (SR-I)/ APGENCO To-be-discussed
19 400 kV KAIGA - NARENDRA 230-07-
2015/03:50:00
30-07-
2015/04:41:00
TRIPPED
WHILE GT
ISOLATION
AT KAIGA
END
KAPS/ PGCIL(SR-II) To-be-discussed
Annexure-IV
3
![Page 57: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/57.jpg)
20 400 Kv HASSAN - UPCL 201-08-
2015/09:18:00
01-08-
2015/10:02:00Y-N FAULT PGCIL (SR-II)/ UPCL To-be-discussed
21 400 Kv HASSAN - UPCL 201-08-
2015/15:20:00
01-08-
2015/15:41:00
TRIPPED ON
B-PH FAULTPGCIL (SR-II)/ UPCL To-be-discussed
22 400 Kv HASSAN - UPCL 201-08-
2015/22:32:00
01-08-
2015/23:13:00
DISTANCE
PROTECTIO
N
OPERATED
PGCIL (SR-II)/ UPCL To-be-discussed
23 GOOTY-NELAMANGALA02-08-
2015/09:18:00
02-08-
2015/10:57:00
TRIPPED AT
SHOLAPUR
END ONLY.
KPTCL To-be-discussed
24 220 kV AMBEWADI - PONDA 202-08-
2015/13:20:00
02-08-
2015/18:48:00
TRIPPED ON
B-PH FAULTKPTCL/ GOA To-be-discussed
25 HVDC BHADRAVATHI POLE 203-08-
2015/02:01:00
BLOCKED
DUE TO VCC-
2 MAIN CKT
FULL FLOW
VERY LOW
PGCIL (SR- I) To-be-discussed
26 400 Kv COASTAL - NTPL03-08-
2015/15:43:00
03-08-
2015/16:11:00R - N FAULT CEPL/ NTPL To-be-discussed
27400/220 kV ICT-2 AT
VISAKHAPATNAM
04-08-
2015/12:49:00
04-08-
2015/13:31:00
DUE TO BUS
BAR
PROTECTIO
N ACTED ON
220KV SIDE
PGCIL (SR- I) To-be-discussed
Annexure-IV
4
![Page 58: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/58.jpg)
28 400/220 kV ICT-1 AT KAIGA04-08-
2015/21:56:00
Y-PH LA
FAILUREKAPS To-be-discussed
29 HVDC BHADRAVATHI POLE 105-08-
2015/10:53:00
05-08-
2015/11:23:00
AUX.
SUPPLY
FAILURE
PGCIL (SR- I) To-be-discussed
30 400/220 kV ICT-2 AT RAICHUR06-08-
2015/04:52:00
REASON
AWAITEDKPTCL To-be-discussed
31 400 kV KAIGA - GUTTUR 107-08-
2015/11:19:00
07-08-
2015/12:33:00
DISTANCE
PROTECTIO
N
KAPS/ KPTCL To-be-discussed
32 220 kV AMBEWADI - PONDA 108-08-
2015/10:51:00
08-08-
2015/11:19:00
DISTANCE
PROTECTIO
N
KPTCL/ GOA To-be-discussed
33 220 kV AMBEWADI - PONDA 109-08-
2015/11:15:00
09-08-
2015/11:37:00R G FAULT KPTCL/ GOA To-be-discussed
34 400 kV KAIGA - GUTTUR 113-08-
2015/09:27:00
13-08-
2015/10:10:00B - N FAULT KAPS / KPTCL To-be-discussed
35400 Kv VIJAYAWADA - NELLORE
- AP - 3
15-08-
2015/14:04:00
15-08-
2015/14:52:00B-N FAULT PGCIL (SR-I) / APTRANSCO To-be-discussed
36400 Kv VIJAYAWADA - NELLORE
- AP - 3
15-08-
2015/15:40:00
15-08-
2015/20:40:00B-N FAULT PGCIL (SR-I) / APTRANSCO To-be-discussed
37 220 kV SABARGIRI - THENI16-08-
2015/12:15:00
16-08-
2015/12:45:00
SINGLE
PHASE
FAULT
KSEB / TNEB To-be-discussed
38 400 Kv NCTPS - SVCTM-II16-08-
2015/00:46:00
TRIPPED ON
B-N FAULTTNEB To-be-discussed
Annexure-IV
5
![Page 59: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/59.jpg)
39 220 kV SABARGIRI - THENI17-08-
2015/10:02:00
17-08-
2015/15:42:00Y-N FAULT KSEB / TNEB To-be-discussed
40220 kV YERANDAHALLY -
HOSUR
17-08-
2015/12:50:00B-N FAULT KPTCL / TNEB To-be-discussed
41 220 kV AMBEWADI - PONDA 117-08-
2015/13:20:00
17-08-
2015/15:28:00
DECLARED
FAULTYKPTCL / GOA To-be-discussed
42220 kV KUNDRA -
KAYAMKULAM
18-08-
2015/16:32:00
TRIPPED ON
Y-PH FAULTKSEB / NTPC To-be-discussed
43400 Kv SATTENAPALLI -
SRISAILAM 2
18-08-
2015/15:25:00
BUS BAR
ACTED ON B-
PH FAULT
APTRANSCO / TSGENCO To-be-discussed
44400 kV SRISAILAM-
MAMIDIPALLI 2
18-08-
2015/15:25:00
BUS BAR
ACTED ON B-
PH FAULT
TSGENCO / TSTRANSCO To-be-discussed
45 220 kV EDAMON - EDAPPON18-08-
2015/16:32:00
18-08-
2015/17:01:00
TRIPPED ON
Y-PH FAULTKSEB To-be-discussed
46 765 KV KURNOOL - NPS 119-08-
2015/13:43:00
19-08-
2015/15:45:00
TRIPPED
DUE TO
LINE
REACTOR W
T I HIGH
PGCIL (SR-I) To-be-discussed
47 400 Kv BTPS - YTPS20-08-
2015/00:14:00
20-08-
2015/01:05:00
RELAY MAL
OPERATIONKPCL To-be-discussed
48 400 kV KAIGA - GUTTUR 121-08-
2015/10:28:00
21-08-
2015/11:06:00B - N FAULT KAPS/ KPTCL To-be-discussed
Annexure-IV
6
![Page 60: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/60.jpg)
49 400 kV KAIGA - GUTTUR 221-08-
2015/12:32:00
21-08-
2015/12:55:00B - N FAULT KAPS/ KPTCL To-be-discussed
50 220 kV AMBEWADI - PONDA 121-08-
2015/13:00:00
21-08-
2015/13:10:00B - N FAULT KPTCL/ GOA To-be-discussed
51 400 kV KAIGA - GUTTUR 222-08-
2015/15:02:00
22-08-
2015/15:58:00B-N FAULT KAPS/ KPTCL To-be-discussed
52 400 kV GUTTUR - HIRIYUR 123-08-
2015/10:01:00
23-08-
2015/13:12:00
BUS BAR
CONNECTIO
N
KPTCL/ PGCIL(SR-II) To-be-discussed
53 400 kV KAIGA - GUTTUR 125-08-
2015/11:35:00
25-08-
2015/12:36:00B-N FAULT KAPS/ KPTCL To-be-discussed
54 400 kV KAIGA - GUTTUR 225-08-
2015/12:37:00
25-08-
2015/20:13:00B-N FAULT KAPS/ KPTCL To-be-discussed
55 400 kV NEYVELI TS 2 - PUGALUR25-08-
2015/16:09:00
25-08-
2015/17:50:00
TRIPPED
DUE TO
ARCHING
ON BUS-1
ISOLATOR
AT NLC
NLC/ PGCIL(SR-II) To-be-discussed
56 220 Kv CHIKKODI - MUDUSHINGI26-08-
2015/10:15:00
26-08-
2015/14:19:00
DISTANCE
PROTECTIO
N ACTED
KPTCL To-be-discussed
57400 kV SRISAILAM-
MAMIDIPALLI 2
26-08-
2015/15:40:00
26-08-
2015/18:40:00JUMPER CUT TSGENCO/ TSTRANSCO To-be-discussed
Annexure-IV
7
![Page 61: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/61.jpg)
58 400/110 kV ICT-4 AT S'PUDUR26-08-
2015/15:26:00
26-08-
2015/18:18:00
TRIPPED
DUE TO
BREAKER
OIL
LEAKAGE
TNEB To-be-discussed
59 220 kV AMBEWADI - PONDA 126-08-
2015/21:44:00
EARTH
FAULTKPTCL/ GOA To-be-discussed
60 400 kV KAIGA - GUTTUR 228-08-
2015/15:17:00
28-08-
2015/16:18:00B - N FAULT KAPS/ KPTCL To-be-discussed
61 220 kV AMBEWADI - PONDA 229-08-
2015/15:54:00
29-08-
2015/16:30:00
DISTANCE
PROTECTIO
N
KPTCL/ GOA To-be-discussed
62 400/230 kV ICT-2 AT SALEM30-08-
2015/03:49:00
30-08-
2015/04:34:00
BUS BAR
ACTED ON
220KV SIDE
DUE TO CT
BLAST
PGCIL (SR-II) To-be-discussed
63 400/230 kV ICT-1 AT SALEM30-08-
2015/03:49:00
30-08-
2015/04:18:00
BUS BAR
ACTED ON
220KV SIDE
DUE TO CT
BLAST
TNEB To-be-discussed
Annexure-IV
8
![Page 62: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/62.jpg)
Page 1 of 1
Annexure-V (Zone-3 philosophy)
The general philosophy to be followed for Zone-3 settings in SR had been discussed in the Sub
Group meeting of PCSC held on 20-11-2013 and finalized during PCSC-26 held on 21.11.2013.
These are as given below:
1. Load encroachment feature would be enabled on all 400 kV lines and also on 220/230 KV lines
where Numerical relays are installed.
2. Load angle shall be kept below 30 degree and if possible it should be set at 26 degree. Resistive
reach of the relay should be more than sum of line resistance, Arc resistance and Tower foot
resistance.
3. Resistive reach of the relay should be less than minimum load resistance of the system ideally, and if
possible should be kept at 60% of minimum Load resistance. This percentage is only an indicative
figure, places where high resistance fault have occurred should analysis previous fault data for setting
resistive reach.
4. Out of Step Settings to be enabled in Critical lines after due analysis of PMU data.
5. Timing for Zone-3 action is as follows:
a. 400 kV lines – 1 sec.
b. Interstate lines – 1 sec
c. For Zone 4/5/Rev Zone : Zone 3 time + 100 msec
![Page 63: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/63.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 1 of 18
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI
Coram: Shri Gireesh B. Pradhan, Chairperson
Shri A.K Singhal, Member Shri A.S.Bakshi, Member
Date of Order : 18.8.2015
Petition No. 86/MP/2014 In the matter of
Petition under Section 94 (f) of the Electricity Act, 2003 seeking time extension for implementing the Commission‟s order dated 20.2.2014 in Petition No. 146/MP/2013 with I.A. 36/2013, in the matter of providing protection systems having reliability, selectivity, speed and sensitivity and keeping them functional in terms of Regulation 5.2 (i) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) (First Amendment) Regulations, 2012 read along with Regulation 3 (e) of Central Electricity Authority (Grid Standards) Regulations, 2010 and following best practice of O&M of transmission elements for ensuring security of the Southern Regional grid as well as the inter-connected Indian grid.
And In the matter of Kerala State Electricity Board Limited Vyduthi Bhavanam, Pattom, Thiruvananthapuram-695 004 ….. Petitioner
Vs.
1. Southern Regional Load Despatch Centre 29, Race Course Cross Road, Bangalore-110 016. 2. Southern Regional Power Committee 29, Race Course Cross Road, Bangalore-110 016 ....Respondents
Annexure- VI
1 / 18
![Page 64: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/64.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 2 of 18
Petition No. 374/MP/2014
In the matter of
Petition under Section 94 (f) of the Electricity Act, 2003 seeking extension of time in implementing the Commission‟s order dated 20.2.2014 in Petition No. 146/MP/2013 and I.A. 36/2013 of SRLDC for providing protection systems having reliability, selectivity, speed and sensitivity and keeping them functional in terms of Regulation 5.2 (i) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) (First Amendment),Regulations, 2012 read along with Regulation 3 (e) of Central Electricity Authority (Grid Standards) Regulations, 2010 and following best practices of O&M of transmission elements for ensuring security of the Southern Regional grid as well as the interconnected Indian Grid. And In the matter of Tamil Nadu Transmission Corporation Limited (TANTRANSCO) Protection and Communication, 1st Floor, 5B Block, 144, Anna Salai, Chennai-600 002 Petitioner Vs
Southern Regional Load Despatch Centre 29, Race Course Cross Road, Bangalore-110 016. Respondent Following were present: Shri George V.James, KSEB Shri S. Vallinayagam, Advocate, TANTRANSCO Shri J. Rexline Terse, TANTRANSCO Shri V.Suresh, SRLDC Ms. Jyoti Prasad, POSOCO Ms. Abilla Zaidi, POSOCO Ms. Jayantika Singh, SRPC and SRLDC
ORDER The petitioners, Kerala State Electricity Board Limited and Tamil Nadu
Transmission Corporation Limited, have filed the present petitions for seeking
Annexure- VI
2 / 18
![Page 65: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/65.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 3 of 18
extension of time to comply with the Commission`s direction dated 20.2.2014 in
Petition No. 146/MP/2013.
Background of the case:
2. As per the recommendations in Enquiry Committee report, a third party
protection audit in Southern Region was carried out and all constituents of Southern
Region (SR) agreed in-principle for implementation of the recommendations of the
Committee. Since a number of recommended items were not implemented by the
constituents of Southern Region, Southern Regional Load Despatch filed Petition No.
146/MP/2013 seeking directions to the constituents of SR to ensure timely
implementation of recommendations of Protection Audit. The Commission, after
hearing all the constituents of SR and SRLDC, by order dated 20.2.2014 issued the
following directions:
“27. We agree to the petitioner's contention that the linking implementation of protection audit/PCC recommendations with funding modality has resulted into implementing schedule becoming uncertain which is undesirable as the matter involves grid security. The petitioner has proposed to segregate the works of implementation in two Phases, namely Phase-I requiring immediate attention and Phase-II requiring timely implementation. Phase-I involves minor works such as revision of settings, replacement of numerical relays, implementation of bus-bar protection in critical 220 kV sub-stations etc. and Phase-II involves activities such as replacement of old breakers etc. which may require some time. Accordingly, we direct the respondents to implement the works as mentioned in Phase-I and Phase-II by 1.5.2014 and 1.9.2014 respectively. SRPC is directed to coordinate the protection setting issue and submit a report regarding implementation of Phase-I activities by 1.6.2014. SRPC is further directed to submit bimonthly status report for works mentioned in Phase-II to the Commission.
29. The petitioner has submitted that number of respondents are not complying with the provisions of Regulation 5.2 (r) of the Grid Code and the directions of the Commission. We administer a strong warning to the respondents to take all possible measures permissible under the Act and the Grid Code to provide
Annexure- VI
3 / 18
![Page 66: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/66.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 4 of 18
data /information to RLDC and RPC for maintaining reliability and security of the grid. We also make it clear that failure in this regard will amount to non-compliance of the directions of this Commission and render the constituent liable for proceedings under Section 142 of the Electricity Act, 2003 and other relevant provisions. We also direct the petitioner and SRPC to coordinate and monitor the progress and compliance of Commission's directions and ensure compliance of Regulations 5.2 (r) of the Grid Code and report instances of non-compliance to the Commission.”
Petition No. 86/MP/2014 filed by Kerala State Electricity Board Limited
3. Kerala State Electricity Board Limited (KSEBL) has filed this petition for seeking
extension of time for implementation of the Commission‟s order dated 20.2.2014 in
Petition No. 146/MP/2013. KSEBL has submitted that it is working under the
Government of Kerala and all major works, procurement, etc. are governed and
guided by the rules and regulations of Government of Kerala.
4. KSEBL has submitted that it has to comply with all the tender formalities such
as administrative sanction for procurement/work, finalization of the specifications,
inviting tenders with wide publicity, evaluation of technical tender documents, review
of pre-qualification committees, financial bid evaluation, issue of LOI, etc. The said
formalities require a minimum of six months before issuing purchase order for a
particular item. If the same is re-tendered, additional period of four months also would
be required for the whole process. In case of 220 kV Pothencode sub-station, certain
works in Phase-II can only be completed with double bus arrangement which is
included in Phase-I. KSEBL has submitted the status of phase-wise details of
protection audit remarks, action taken so far and proposed road map with time line for
implementation of remaining protection audit remarks works along with PERT chart.
Annexure- VI
4 / 18
![Page 67: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/67.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 5 of 18
5. In view of the above, KSEBL has made the following prayers:
“Considering the above submissions made by KSEB Ltd. and the difficulties faced by
KSEB Ltd. regarding the timely implementation of the Hon`ble CERC order dated 19.12.2013, in the matter of completion of Phase-I & II works of Protection Audit, it is prayed before the Hon`ble Commission that
(a) Time extension may kindly be granted for Phase-I works till 31.12.2014 and 220 kV
Pothencode sub-station date of completion of phase-I works by 31.3.2015.
(b) Time extension may kindly be granted for Phase-II works till 31.5.2016.”
6. The matter was heard on 15.7.2014. During the course of the hearing, the
representative of KSEBL submitted that Phase-I requires minor works to be completed
such as revision of settings, replacement of numerical relays, implementation of bus
bar protection in critical 220 kV sub-stations, etc. and phase-II involves activities such
as procurement of circuit breakers and current transformers. The representative of
KSEBL further submitted that certain sub-stations of KSEBL are very old and require
different equipment. At certain sub-stations, there are space constraints. The
representative of KSEBL submitted that considering all these limitations, KSEBL is
seeking time for implementation of works in Phase-I and Phase-II of the Protection
Audit till 31.12.2014 and 31.5.2016 respectively and for completion of Phase-I works
of 220 kV Pothencode sub-station till 31.3.2015.
7. The Commission directed Southern Regional Load Despatch Centre (SRLDC)
to file (i) reasonableness of time sought by KSEBL for Phase-II, (ii) position of other
constituents in regard to implementation of the Commission`s order dated 20.2.2014
in Petition No. 146/MP/2013 and (iii) status report regarding visibility of protection
system of Southern Region constituents in the SCADA system of SLDC.
Annexure- VI
5 / 18
![Page 68: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/68.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 6 of 18
8. SRLDC, vide its affidavit dated 1.9.2014, has submitted as under:
(a) As far as time scale for attending protection audit remarks is concerned,
the maximum time required for any item which requires procurement action
would be about 10 months as under:
Activity Months
Finalization of Specification 0.5
Estimate preparation 0.5
Initiating proposal 0.5
Approval of Proposal 1
Calling tender 0.5
Processing Tenders 2
Discussion &Issue of LoA 1
Supply of Materials 3
Erection,Testing &Commissioning 1
Total Period 10
(b) For CT/CVT circuit breakers, the supply and erection period may be 8 to
10 months in place of 3 to 4 months shown in table above. Thus, maximum time
schedule for any item even if it is commenced only now, shall be 15 to 16 months.
During the special meeting on 19.8.2014, SRPC also opined that time scale
computed above is practical and reasonable.
(c) The rational time schedule of individual milestone for implementation of
all the recommendations could be as under:
S.No Major Milestone Description Practically possible time schedule
1 Technical and Administrative approval including finalization, finance concurrence, start-up of tendering process.
2 to 3 months for all the items as multiple proposals are to be processed
2 Tendering process including calling of tenders, pre/post bid
3 to 4 months for all the items as multiple proposals are to be
Annexure- VI
6 / 18
![Page 69: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/69.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 7 of 18
discussion, placement of LOA processed
3 Supply of materials including FAT etc.
8 to 10 months for items like CT,CVT, Breaker etc., while about 3 months for other items
4 Installation, testing and commissioning including SAT, etc.
3 to 4 months for all the items as the construction activities like foundation, structural erection etc,. could be done as a parallel activity during supply period.
5 Total implementation period 3 months for items that involves relays/meter and minor procurement.
12 months for items that involve major procurement, design changes with major site modification/civil activities.
(d) According to KSEBL, works such as arrangement for earth resistance
measurement, etc. mentioned at Iddukki HEP would be done as a part of
Renovation and Modernization (R & M). In the 220/230 kV sub-stations, major
changes and multiple works are required for implementation of the
recommendations of protection audit due to space constraints in the very hilly
terrain old sub-station. Iddukki HEP is critical generating station of KSEBL and
number of times partial grid disturbances had occurred in the generating station.
The works at Idukki HEP requires special attention of KSEBL and shall not be
treated as regular R&M works. Considering the same, KSEBL is required to make
all possible efforts to complete the entire work recommended at Iddukki HEP by
December 2015/March 2016.
(e) During deliberation at SRPC on 19.8.2014, KSEBL confirmed that „it would be
completing all the Phase-I items by December 2014, Bus-bar protection works
identified for Kanaiyampetta sub-station by March 2015 and all other items of the
Annexure- VI
7 / 18
![Page 70: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/70.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 8 of 18
Phase-II activities by December 2015 except at Iddukki HEP, which is clubbed with
R&M proposal,. This appears practically reasonable considering the fact that
actions were effectively commenced by KSEBL in the recent past. However, the
R&M proposals need to be expedited‟.
9. Neyveli Lignite Corporate Limited (NLC), which is not a party in the present
petition, vide its affidavit dated 11.9.2014 has filed status of implementation of
protection audit remarks. NLC has further submitted that during the hearing of the
petition, the Commission, vide RoP dated 15.7.2014, directed SRLDC to file the status
of the constituents of Southern Region in regard to the implementation of the
Commission‟s order dated 20.2.2014. Accordingly, SRPC requested the constituents
of Southern Region to submit affidavit directly to the Commission as per the decision
of the Protection Coordination Sub-Committee (PCSC) meeting held on 31.7.2014.
NLC has submitted that based on the direction of SRPC, it has filed the present
affidavit containing the status of compliance of the recommendations of protection
audit with respect to NLC generating stations. NLC has submitted that SRPC has
issued 25 guidelines for NLC generating stations. Out of these, 7 guidelines are to be
completed in Phase-I and the remaining 18 are to be completed in Phase-II. NLC has
stated that 22 guidelines are complied with and only 3 guidelines, namely replacement
of existing micro mho distant protection (main-I) relays in TPS-I expansion with
numerical relay (Phase-I), providing 2nd bank of 48 V battery for PLCC in TPS-I
Expansion and TPS-II Expansion (Phase-II) are to be complied with by NLC which
would be completed by 31.12.2014 and 31.3.2015 respectively.
Annexure- VI
8 / 18
![Page 71: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/71.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 9 of 18
Petition No. 374/MP/2014 filed by Tamil Nadu Transmission Corporation Limited (TANTRANSCO) 10. Tamil Nadu Transmission Corporation Limited has filed this petition for seeking
extension of time for implementation of remarks of protection audit. TANTRASCO has
submitted as under:
(a) Protection Audit for the 33 nos. of sub-stations of TANTRANSCO has
been completed. Minor issues recommended by the Audit Team under Phase- I
and Phase-II activities have been resolved and in this regard, report and
pending activities with regard to Phase-I and Phase-II works have already been
submitted to SRPC. Procurement action for materials is being carried out in
phased manner which involves a minimum time frame of 6 months for
processing the tender.
(b) All possible steps are being taken by TANTRANSCO, namely purchase
orders have been placed for supply of distance relays for feeder protection,
differential relays for auto transformer protection and carrier sets with coupler
for providing carrier inter-trip and redundant channels to comply with the
directions of the Commission. However, despite sincere efforts made by
TANTRANSCO, the works of Phase- I and Phase- II activities could not be
completed within the prescribed time specified in the order dated 20.2.2014 in
146/MP/2013.
Annexure- VI
9 / 18
![Page 72: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/72.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 10 of 18
(c) As per the recommendations of SRPC, different make of relays for Main
1 and Main 2 protection as well as separate DC source for different protection
schemes are being adopted in the new sub-stations to ensure grid security.
The new stations are equipped with sub-station Automation System which
involves GPS, Disturbance Recorder and Event Logger.
(d) In the existing generating stations, for synchronization of all relays with
GPS could be enabled only after replacing the static relays with numerical
relays. This process involves procurement of new relays and replacing them in
place of old ones.
(e) Provision of bus section breaker for sectionalizing the bus to avert total
sub-station outage involves procurement of breaker, erection and modification
of bus bar Protection Scheme and the requirement is covered in DPR. This
process involves space constraints in some places, bay shifting works and
procurement through tender which requires considerable time.
(f) The existing protection scheme in TANTRANSCO ensures stable
operation. TANTRANSCO is taking all steps to prevent/minimize system
outage. During July 2014 to February 2015, total 583 trippings have occurred in
Southern Region. Out of this, 28 trippings occurred in TANTRANSCO which is
4.80% of total trippings in Southern Region. From this, it is evident that the
trippings are not due to failure of protection schemes. Trippings are always
reviewed by SRLDC and SRPC. The recommendations of Protection Co-
Annexure- VI
10 / 18
![Page 73: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/73.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 11 of 18
ordination Sub-Committee of SRPC are being complied with by
TANTRANSCO.
11. In view of the above, TANTRANSCO has made the following prayers:
“(a) Time extension upto 31.3.2015 for completing the Phase-I activities of providing numerical relays for feeder protection and auto transformer protection;
(b) Time extension upto 30.6.2016 for other Phase-I activities such as provision of line VT, 5 core CT, Time synchronizing with GPS, DR and EL and Phase-II activities;
(c) Time extension upto 30.6.2017 for Renovation & Modernization of Singarpet, Singaperumalkoil and Tondiarpoet 230 KV Substations; and (d) Such other order or orders as this Hon`ble Commission may deem fit and proper in the facts and circumstances of the case.”
12. The matter was heard on 15.1.2015. During the course of hearing, learned
counsel for TANTRANSCO submitted that due to financial and time constraints,
TANTRANSCO could not implement the recommendations of protection audit.
Learned counsel further submitted that there are 6 to 7, 230 kV sub-stations which are
very old and require additional land and entire civil work has to be done for installation
of new equipment. The representative of SRPC and SRLDC submitted that SRPC and
SRLDC convened a meeting of all the constituents of Southern Region wherein
detailed inputs were given to each constituent regarding improvement of the State
system. The representative of SRLDC submitted that SRPC and SRLDC have made
efforts on their own to take feedback on the status of implementation from the
individual constituents of the Southern Region. The Commission directed the other
constituents of the Southern Region to submit the status of implementation of
protection system in their respective States.
Annexure- VI
11 / 18
![Page 74: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/74.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 12 of 18
13. TANTRANSCO, vide its affidavit dated 28.3.2015, has submitted that in
compliance with the Commission`s directions, purchase orders have already been
placed for supply of distance relays for feeder protection, differential relays for auto
transformer protection and carriers sets with coupler for providing carrier inter-trip and
redundant channels. TANTRANSCO has further submitted that availing „Line Clear‟ is
one of the major difficulties due to operational constraints. TANTRANSCO has
submitted the details of remedial measures for the trippings in its affidavit dated
28.3.2015.
14. Karnataka Power Transmission Corporation Limited (KPTCL) vide its affidavit
dated 31.3.2015 has submitted that all the constituents of Southern Region were
directed vide order dated 20.2.2014 to complete the implementation of activities
covered under Phase-I and Phase-II of protection audit observations by 1.5.2014 and
1.9.2014 respectively. Since implementation of Phase-I and Phase-II works involve
tendering, procurement and execution of works based on availability of shutdowns,
the Commission`s directions dated 20.2.2014 could not be timely complied with.
Accordingly, KPTCL vide its affidavit dated 27.8.2014 (filed on 1.9.2014) requested
the Commission to grant time upto 15.1.2016 for completion of protection audit
remarks. KPTCL has submitted that tender was floated for the subject work, however,
considering the different variety of works involved at various sub-stations spread
across vast geographical area, the bidders requested time extension for preparing
their offers and up-loading their bid documents. The technical bid was opened on
20.2.2015. Since the amount put to tender is ` 77.46 crore, the same was required to
Annexure- VI
12 / 18
![Page 75: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/75.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 13 of 18
be placed before the Board of Director`s meeting. KPTCL has submitted that after
resolution in the Board, LoI would be issued. However, successful bidder would be
given a month`s time to accept LOI and entered into an agreement with KPTCL.
KPTCL has requested to grant extension of time by 15.1.2016 for completion of
Phase-I and Phase-II activities.
15. Karnataka Power Corporation Limited (KPCL) in its affidavit dated 28.3.2015 has
submitted that KPCL, vide its affidavit dated 25.8.2014 had requested for grant of
additional time to comply with the directions in order dated 20.2.2014 in Petition No.
146/MP/2013. KPCL has filed the status of implementation of recommendations of
Third Party Protection Audit Committee pursuant to the Commission`s direction dated
15.1.2015. KPCL has stated that out of 33 observations of Third Party Protection Audit
in Phase-I activities, 13 observations have been complied with and out of 21
observations for Phase-2 activities, 6 observations have been complied with.
However, the remaining activities could not be complied with till date due to (a) delay
in obtaining approvals from technical committee before issuing tender notification, (b)
clarifying the bid queries from the bidders, (c) evaluation of technical bid, (d) obtaining
approvals from Contract Management Group of KPCL, (e) opening of price bid, the
process of evaluation and (f) obtaining financial opinion from the Finance Department
of Govt. of Karnataka. KPCL has submitted that though the erection works involve
obtaining prior line clearance from the Load Despatch Centre, dismantling of existing
equipment, laying new foundation, curing time of 25 days, erection of new equipment
and commissioning, KPCL is insisting on the contractors to take up the erection works
simultaneously at different project locations and to complete the same at the earliest.
Annexure- VI
13 / 18
![Page 76: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/76.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 14 of 18
KPCL has requested to extend the date of completion of Phase-I and Phase-II works
till 31.10.2015 and 31.12.2015 respectively.
Analysis and Decision:
(A) Case of KSEBL:
16. KSEBL has initiated action to implement the suggestions of protection audit.
However, KSEBL has sought extension of time for completion of Phase-I activities till
31.12.2014, 220 kV Pothencode sub-station till 31.3.2015 and Phase-II till 31.5.2016.
The Commission vide Record of Proceedings dated 1.8.2014 had allowed time to
KSEBL till 31.12.2014 for completion of works in Phase-I of the protection audit.
17. SRLDC, vide its affidavit dated 25.8.2014, has submitted that action like
administrative approval, finalization of specification, tendering process, etc. has
already commenced in case of KSEBL and with consistent effort, it would be possible
to complete all Phase-II items by 12 months. i.e by September,2015. KSEBL has
further submitted that KSEPBL`s request for time till December, 2015 on account of
such reasons as design changes in old sub-stations, modification of bus arrangement,
simultaneous execution of multiple works, etc. appear to be reasonable. According to
SRLDC, works at Iddukki HEP should not be treated as regular R&M works as the
sub-station is very important and critical and the entire works recommended for the
sub-station should be completed by December, 2015/March, 2016. It is noted that the
KSEBL has already initiated actions to attend the protection audit remarks covered
under Phase-I and Phase-II. KSEBL has also submitted detailed time-line for
implementation of the audit remarks. It is pertinent to mention that time for completion
Annexure- VI
14 / 18
![Page 77: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/77.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 15 of 18
of Phase–I of protection audit remarks and for 220 kV Pothencode sub-station of
KSEBL is already over.
18. Noting the submission of KSEBL, SRLDC and SRPC and considering the
actions already initiated by KSEBL for implementation of remarks of protection audit,
we allow time till 31.12.2015 and 31.3.2016 for implementation of Phase-II works and
R&M works at Idduki HEP respectively.
(B) Case of TANTRANSCO:
19. TANTRANSCO has sought time (a) upto 31.5.2015 for completion of Phase-I
activities of providing numerical relays for feeder protection and auto transformer
protection; (b) up to 30.6.2016 for other Phase-I activities such as provision of line
VT, 5 core CT, Time synchronizing with GPS, Distrubance Recorder, Event Logger
and Phase II activities; and (c) up to 30.6.2017 for Renovation and Modernization of
Singarpet, Singaperumalkoil and Tondiarpet 230 kV sub-stations under Phase-III
activities.
20. TANTRANSCO has submitted that due to financial and time constraints, it
could not implement the recommendations of Protection Audit. TANTRANSCO has
further submitted that 6 to 7 Nos. of 230 kV sub-stations are very old and require
additional land and entire civil work has to be done for installation of new equipment. It
is noted that TANTRANSCO has already initiated action for attending the issues
brought in Phase-I and Phase-II of protection audit and due to certain difficulties
projected by TANTRANSCO, it could not implement the remarks of protection audit.
Annexure- VI
15 / 18
![Page 78: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/78.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 16 of 18
21. After considering the submissions of TANTRANSCO, SRLDC and SRPC, it is
noted that TANTRANSCO`s request for time till 31.5.2015 for implementation of
Phase–I activities of providing numerical relays for feeder protection and Auto
transformer protection is already over. We allow time till 30.6.2016 for other Phase-I
activities such as provision of line VT, 5 core CT, Time synchronizing with GPS,
Disturbance recorder & event logger and Phase-II activities. According to SRLDC,
total implementation period is 15 to 16 months for items which involve major
procurement, design changes with major site modification/civil activities. Accordingly,
we allow 16 months time i.e up to 30.11.2016, for Renovation and Modernization of
Singarpet, Singaperumalkoil, Salem and Tondiarpet 230 kV sub-stations from the
issue of the order.
(C) Case of NLC:
22. NLC has sought time upto 31.12.2014 and 31.3.2015 for completion of Phase-
I work of Numerical Relay Retrofitting and for Phase-II works of providing second
battery bank of PLCC respectively. It is noted that the completion dates for Phase-I
and Phase-II of protection audit remarks as requested by NLC are already over.
Therefore, no direction is required in this regard. However, we direct NLC to file a
confirmation report regarding completion of protection audit works for Phase-I and
Phase-II.
(D) Case of KPTCL
23. SRLDC has stated that KPTCL has already completed protection audit
recommendations where there are no additional financial implications. SRLDC has
Annexure- VI
16 / 18
![Page 79: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/79.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 17 of 18
further submitted that on 16.9.2014, KPTCL invited tenders for the completion of
works and LOA is under process. As per the time line given in the tender documents,
the schedule for completion of entire works of Phase-I and Phase-II is January 2016.
SRLDC has stated that to facilitate timely completion, the tender has been processed
by making four geographical packages such that different agencies may
simultaneously work at different areas of the distribution companies of Karnataka.
Considering the submission of KPTCL and SRLDC, we allow time to KPTCL time till
15.1.2016 for completion of Phase-I and Phase-II of protection audit remarks. No
further extension shall be granted in this regard.
(E) Case of KPCL
24. SRLDC has submitted that KPCL is yet to implement number of items of the
Phase-I which do not involve procurement action. However, KPCL vide its affidavit
dated 6.4.2015 has submitted that it has obtained administrative approval for
procurement of material required for protection audit remarks. KPCL has further stated
that it has already completed certain Phase-I as well as Phase-II works. KPCL has
prayed to extend the date of completion for Phase-I and Phase-II works upto
31.10.2015 and 31.12.2015 respectively. Considering the submission of KPCL and
SRLDC, we allow time to KPCL till 31.10.2015 and 31.12.2015 for completion of
Phase-I for Phase-II of protection audit remarks respectively. No further extension
shall be granted in this regard.
25. SRLDC has submitted list of items discussed in special meeting of PCSC
wherein it was proposed that PCSC forum would send the proposal for dropping
Annexure- VI
17 / 18
![Page 80: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/80.jpg)
------------------------------------------------------------------------------------------------------------------------------------ Order in Petition Nos. 86/MP/2014 and 374/MP/2014 Page 18 of 18
certain items under protection audit recommendations. In this regard, we are of the
view that the items to be included/excluded while monitoring implementation of
protection audit should be finalized at RPC level in the interest of grid security.
26. We direct SRPC to (a) submit status of protection audit remarks in respect of
APGENCO, NTPC (SR), Talcher, Puducherry, PGCIL (SRTS I & II), MAPS and
TANGEDCO, (b) monitor the status of completion of remarks of protection audit in
respect of all constituents of Southern Region in Protection Coordination Sub-
Committee (PCSC) meetings, and (c) to coordinate periodic protection audit to be
carried out in Southern Region after deliberation in SRPC. All the constituents of
Southern Region are directed to file their status with SRPC on regular basis to
facilitate proper monitoring in PCSC meetings. SRPC is directed to submit bi-annually
status report to the Commission confirming the completion of Phase-I, Phase-II and
R&M works of protection audit remarks of the constituents of Southern Region.
27. The Petition Nos. 86/MP/2014 and 374/MP/2014 are disposed of in terms of
the above.
Sd/- sd/- sd/- (A.S.Bakshi) (A. K. Singhal) (Gireesh B. Pradhan) Member Member Chairperson
Annexure- VI
18 / 18
![Page 81: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/81.jpg)
![Page 82: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/82.jpg)
![Page 83: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/83.jpg)
![Page 84: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/84.jpg)
Additional Agenda for 47th PCSC meeting Page 1
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
Additional Agenda for the 47th
meeting of Protection Coordination Sub-Committee
(PCSC-47) of SRPC to be held on 15.09.2015
1. Grid Occurrences
The additional Grid Occurrences to be discussed in the meeting are given below.
Sr.
No.
क्र.स.ं
घटना का वििरण /
Details of Event
तारीख/ Date
& समय
/Time
कारण / Reason शे्रणी/ Category
1 230 kV Bus dead
at Salem
substation
03:50 Hrs at
30-08-15
Link1 feeder Y phase CT failed and all the
feeders & ICT 1, ICT 2 and 230kV breakers
got tripped at the same time.
2 765 kV
RAICHUR -
SHOLAPUR 1
and 2
04-09-2015
at 19:25 hrs
Sholapur -1 and 2 Feeder got tripped at
Raichur end on operation of over current
protection in Main-1 distance relay and
holding from Solapur end on 04.09.2015 at
19:24:42 Hrs
3 765 KV
RAICHUR –
KURNOOL 2
04-09-2015
at 19:25 hrs
Kurnool -II Feeder got tripped on B-N fault
and holding from Kurnool end (successfully
auto-reclosed at Kurnool end) subsequently
tripped at other end on operation of Over
Voltage stg-1 protection at Raichur end on
04.09.2015 at 19:24 Hrs
2. Review of implementation of certain Protection Audit Recommendations of SR-Constituents
Based on the status updates received from APGENCO, APTRANSCO, TANGEDCO, TANTRANSCO &
PGCIL (SR-II) w.r.t. implementation of protection audit recommendations of their stations, certain recommendations, as brought out in Annexure-VII, are proposed to be reviewed for implementation.
3. Non- furnishing of Tripping Details
The members were intimated about non- furnishing of tripping details for the grid incidents that
occurred during the period 16th
- 31st Aug, 2015 vide SRPC letter dated 08.09.2015 (Annexure-
VIII). The issue would be discussed in the meeting.
4. Revision in Special Protection Scheme
Based on SRPC’s requests to review various SPS’s that have bearing on SR in view of the changed and
anticipated grid conditions, NLDC has carried out extensive load-flow studies for secure operation of All
India Grid considering the anticipated commissioning of 765 kV Kolhapur-Narendra D/C and 765 kV
![Page 85: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/85.jpg)
Additional Agenda for 47th PCSC meeting Page 2
Aurangabad – Sholapur D/C, and suggested for certain modifications in the existing SPS’s along with
installing some new SPS’s on a few transmission lines. These modifications & suggestions given at Annexure-IX are proposed to be deliberated in the meeting to ascertain the views of SR-Constituents.
*****
![Page 86: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/86.jpg)
1220 KV- Dr. NTTPS, Stage-I, 220
KV Switch yard. VTS (Phase-II)
Only 220 V DC Source with one battery set is
available for entire 220 kV SS.It is recommended
to have redundant DC source.
Redundant 220 kV DC supply is available from station
Battery Bank.
2 220KV Bommur Substation REF is not used in APTRANSCO for 220KV
Substations
Differential protection is used for Transformers in
220KV Substations.
Latest Update as on 26-08-2015:
At present differential protection is used as main
problem and O/C and E/F protection as a back up
protection for Transformers in 220KV Substations.
Requested to drop the audit vide lr. no.273 dt.5-5-2015
3 220KV Chittor SubstationAuto reclosure to be made functional for 220 kV
feeders.
On 220KV feeders Auto recloser function not used in
APTRANSCO system.
4 220KV Renigunta sub stationAuto reclosure to be made functional for 220 kV
feeders.
On 220KV feeders Auto recloser function not used in
APTRANSCO system.
5 220kV Sullurpet Substation Enabling of Auto recloser in all 220kV feeders.
On 220KV feeders Auto recloser function not used in
APTRANSCO system.
Latest Status Updated (as on 10-04-2015):
On 220KV feeders Auto recloser function not used in
APTRANSCO system and will be taken as per the
instructions of System Protection Wing.
6 400KV Chittor substationAuto reclosure to be made functional for 220 kV
feeders.
On 220KV feeders Auto recloser function not used in
APTRANSCO system.
7 230 kV Basin Bridge SubstationNo Earth fault protection on HV & LV side of
transformer. Same to be provided
E/F settings for AUTOs not being adopted in
TANTRANSCO.
8 230 kV Ennore (ETPS)
Earth fault relay to be provided on HV & LV sides of
Auto t/p # 1, 2 and TO # 3 t/f. Over fluxing relayto be
provided.
E/F settings for AUTOs not being adopted in Tantransco.
9 230 kV Korattur SubstationNo E/L relay protection on ATR 1, 2 & 3 HVs. Same to
be providedE/F settings for AUTOs not being adopted in Tantransco.
10 230 kV Mylapore SubstationNo Earth fault protection on HV & LV side. Same to be
reviewed and providedE/F settings for AUTOs not being adopted in Tantransco.
11 230 kV Tondiarpet Substation
100 MVA, 230/110 kV transformer # 1 &2, back up
O/C relays setting need review. Earth fault relays to be
provided on both HV & LV side of ICT's
Uniform setting adopted for O/C. E/F settings for AUTOs not
being adopted in Tantransco
12
400 kV Kochi SS220V Battery bank-1&2 for protection system to be
replaced with lead acid batteriesVRLA batteries are inline with the standard guidelines
Review of implementation of certain Protection Audit Recommendations of SR-Constituents
PGCIL-SRII (Phase-II)
APTRANSCO (Phase-I)
APGENCO (Phase-II)
TANGEDCO (Phase-I)
TANGEDCO (Phase-I)
Annexure-VII (PAR-Review)
![Page 87: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/87.jpg)
Annexure- VIII
1
![Page 88: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/88.jpg)
Annexure- VIII
2
![Page 89: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/89.jpg)
Annexure- VIII
3
![Page 90: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/90.jpg)
Annexure- VIII
4
![Page 91: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/91.jpg)
Annexure- VIII
5
![Page 92: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/92.jpg)
Annexure- VIII
6
![Page 93: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/93.jpg)
Annexure- VIII
7
![Page 94: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/94.jpg)
Annexure- VIII
8
![Page 95: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/95.jpg)
Annexure- VIII
9
![Page 96: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/96.jpg)
CIN No.: U40105DL2009GOI188682Annexure- IX (SPS-Revisions)
1 / 18
![Page 97: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/97.jpg)
Copy for kind information to:
1) Member (GO & D), CEA, Sewa Bhawan, R. K. Puram, New Delhi-110 066
2) Chief Operating Officer, CTU-Planning, POWERGRID, Gurgaon
3) Executive Director, SRLDC, Bangalore
4) General Manager ERLDC, Kolkata
5) General Manager, WRLDC, Mumbai
Annexure- IX (SPS-Revisions)
2 / 18
![Page 98: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/98.jpg)
1
Power System Operation Corporation Limited National Load Despatch Centre
New Delhi
07th Sep 2015
A. Assessment of WR-SR Transfer Capability considering 765kV Aurangabad-Sholapur D/C and the likely flow pattern
Assumptions in Base-case load flow study are as follows:
765kV Aurangabad-Sholapur D/C is considered.
765kV Kolhapur – Narendra (to be initially charge at 400kV) is not considered.
Power flow on Bhadrawati BTB HVDC: 1000 MW.
Power flow on Talcher-Kolar Bipole HVDC: 2000 MW.
Power flow on Gazuwaka BTB HVDC: 500 MW.
Maximum permissible loading considered for 765kV lines is 2500 MW under (n-1)
contingency.
Maximum permissible loading considered for 400 kV lines under (n-1) contingency is
thermal limit.
Thermal limit of 400kV Kolar-Hosur line is considered as 1100 MVA based on the
certification given by POWERGRID.
Based on the above assumptions, the load flow studies has been carried out and it has been
observed that WR-SR transfer capability would be in the 3500-4000 MW and the limiting
constraint would vary depending on Load-generation and network topology. The table below
gives the WR-SR corridor transfer capability with different conditions:
S. No.
Condition TTC (MW) ATC (MW) Limiting constraint
1 Assuming 765kV line limit as 2500 MW
3500 2750 (n-1) contingency of 765kV Raichur-Sholapur leads to 2500MW on other
circuit
2 If RTPS generation is full ~3600 2850 (n-1) contingency of 765kV Raichur-Kurnool leads to 874 MVA on 400kV
RTPS-Mahaboobnagar S/C
3 If RTPS generation is generating around 1100 MW
~4000 3250 (n-1) contingency of 765kV Raichur-
Kurnool leads to overloading of 2*1500 MVA ICTs at Raichur Substation
Note: TTC/ATC figures may vary depending on the network topology and Load-Generation Balance and the above figures are only representative.
Annexure- IX (SPS-Revisions)
3 / 18
![Page 99: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/99.jpg)
2
With the above TTC/ATC figures, the flow on 2*765kV Raichur-Sholapur S/C would be in the
range of 2500 MW to 3000 MW and flow on 765kV Aurangabad-Sholapur D/C would be in the
range of 3000 MW to 3500 MW. Considering the above power flows on 765kV lines, certain
modifications have to be carried out in existing SPS and new special protection schemes needs
to be installed on 765kV Aurangabad-Sholapur D/C. The table given below shows the angular
difference between 400 kV Jindal (Chhattisgarh) and 400kV Cochin (Kerala) for different
conditions:
S. No. Condition Ang. diff (deg)
1 Base case with 2500 MW limit on 2*765kV Raichur-Sholapur S/C 95.54
2 Outage of one circuit of 765kV Aurangabad-Sholapur D/C 102.14
3 Outage of one circuit of 765kV Raichur-Kurnool S/C 110.56
Single Line Diagram of the relevant portion of the All India grid indicating the power flows and voltage is enclosed at Annexe. Accordingly, the revised SPS settings are indicated in the Table below at B. No change is proposed in respect of Talcher-Kolar SPS.
Annexure- IX (SPS-Revisions)
4 / 18
![Page 100: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/100.jpg)
3
B. Modifications Suggested in the Special Protection Schemes (SPS) – NEW-SR Corridor
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
1 SPS-1
(Both
lines in
service)
765kV Sholapur-Raichur flow > 1500 MW:
Total flow on 2*765 kV Sholapur-Raichur S/C lines
crossing a pre-set value of 1500 MW in Sholapur to
Raichur direction and remains above 1500 MW for 2.5
seconds.
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
500 MW Load shedding in SR: TN – 146 MW, Kerala –
125 MW, Karnataka – 104 MW, AP – 125 MW
Note: Loads identified for shedding in SR for this SPS
action is same as the Loads identified for shedding in SR
for Trip Signal-3 of Talcher-Kolar.
Suggestion: SPS should trigger when total flow on 2*765 kV Sholapur-Raichur S/C line crosses 3500 MW and remains above 3500 MW for 5 seconds. SPS Actions:
In addition to the SPS actions already implemented, the following actions may also be taken: - Loads identified for shedding in SR
for this SPS action is same as the Loads identified for shedding in SR for Talcher-Kolar Trip Signal-3.
- Different set of loads (500 MW) shall be identified and the trip command should be given to these new identified loads only.
- Additional loads to the tune of 500–1000 MW shall be identified for load shedding in Southern Region.
Rationale: WR-SR TTC would be in the range of 3500 MW to 4000 MW, the total flow on both the circuits of 765 kV Raichur-Sholapur would be in the range of 2500-3000 MW. Higher value of line flow for SPS action (i.e., 3500 MW) is chosen so as to avoid frequent operation of SPS. This would also ensure that in the event of tripping of Bhadrawathi HVDC or Gazuwaka HVDC or Talcher-Kolar HVDC or Kudankulam Unit-1, the SPS-1 would get activated and keep the system secure.
Annexure- IX (SPS-Revisions)
5 / 18
![Page 101: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/101.jpg)
4
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
- So in total there would be a total of 1000-1500 MW load shedding in Southern Region for this SPS.
2 SPS-1
(Both
lines in
service)
765kV Sholapur-Raichur flow > 1500 MW:
Total flow on 2*765 kV Sholapur-Raichur S/C lines
crossing a pre-set value of 2000 MW in Sholapur to
Raichur direction sensed both at Sholapur and Raichur --
- Instantaneous triggering.
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
500 MW Load shedding in SR: TN – 146 MW, Kerala –
125 MW, Karnataka – 104 MW, AP – 125 MW
Suggestion: SPS should trigger when the total flow on 765 kV Sholapur-Raichur 2*S/C crosses 4000 MW and remains above 4000 MW for 2.5 seconds.
SPS Actions:
In addition to the SPS actions already implemented, the following actions may be taken: - Loads identified for shedding in SR
for this SPS action is same as the Loads identified for shedding in SR for Talcher-Kolar Trip Signal-3.
- Different set of loads (500 MW) shall be identified and the trip command should be given to these new
Rationale: As compared to proposed SPS setting at S.No-1, additional 500 MW margin has been taken for activating the SPS. Further, the time delay has been reduced to control the line loading immediately. Additional 1000 MW loads has to be identified for further load shedding.
Annexure- IX (SPS-Revisions)
6 / 18
![Page 102: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/102.jpg)
5
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
Note: Loads identified for shedding in SR for this SPS
action is same as the Loads identified for shedding in SR
for Trip Signal-3 of Talcher-Kolar.
identified loads only. - Additional loads to the tune of 500–
1000 MW shall be identified for load shedding in Southern Region.
- So in total there would be a total of 1000-1500 MW load shedding in Southern Region for this SPS.
3 SPS-1
(Only
One
line in
service)
765kV Sholapur-Raichur S/C flow > 1000 MW:
Total flow on 765 kV Sholapur-Raichur S/C lines crossing
a pre-set value of 1000 MW in Sholapur to Raichur and
remains above 1000 MW for 2.5 seconds.
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
500 MW Load shedding in SR: TN – 146 MW, Kerala –
125 MW, Karnataka – 104 MW, AP – 125 MW
Note: Loads identified for shedding in SR for this SPS
action is same as the Loads identified for shedding in SR
Suggestion: SPS should trigger when one of the two ckts of 765 kV Raichur-Sholapur is out and the flow on other 765 kV Sholapur-Raichur S/C line crosses 2000 MW and remains above 2000 MW for 2.5 seconds (i.e. SPS should act in case of outage / tripping of one circuit and flow on the other circuit greater than 2000 MW). SPS Actions:
In addition to the SPS actions already implemented, the following actions may be taken: - Loads identified for shedding in SR
for this SPS action is same as the
Rationale: Tripping of one 765kV circuit would lead to heavy flow on second circuit. Consider both Raichur-Sholapur ckts are carrying 2900 MW. Tripping of one circuit would lead to 2900 MW on second circuit. Many a times in the past, it was observed that both Raichur-Sholapur ckts have tripped leading to NEW-SR separation. Considering FRC of SR in the tune of 1500-2000MW, tripping of both Raichur-Sholapur ckts at this level of flow might lead to frequency dip of 0.7–1.2 Hz in SR. Considering frequency of 50 Hz, there will be high probability of 49.2 Hz UFR operation in SR. This means that the load shedding for SPS-1 should be such that it should not consist of loads, which are for UFR operation.
Annexure- IX (SPS-Revisions)
7 / 18
![Page 103: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/103.jpg)
6
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
for Trip Signal-3 of Talcher-Kolar. Loads identified for shedding in SR for Talcher-Kolar Trip Signal-3.
- Different set of loads (500 MW) shall be identified and the trip command should be given to these new identified loads only.
- Additional loads to the tune of 500–1000 MW shall be identified for load shedding in Southern Region.
- So in total there would be a total of 1000-1500 MW load shedding in Southern Region for this SPS.
Further, 765kV Kolhapur (New)-Narendra (New) D/C (to be initially charged at 400kV) is likely to be commissioned in the same period. Load flow studies indicate that tripping of both Raichur-Sholapur circuits carrying more than 1500 MW would cause voltages at 400kV Kolhapur, 400kV Mapusa, 400kV Narendra sub-stations to go below 370kV. This might cause grid disturbance in Kolhapur area, Goa and also in SR. In case of planned outage of one of the 765 kV Sholapur-Raichur S/C, TTC on WR-SR would reduce drastically by 2000-2500 MW; so actual flows would be much lower and this SPS would ordinarily not be required to operate unless there is a large contingency in SR.
Annexure- IX (SPS-Revisions)
8 / 18
![Page 104: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/104.jpg)
7
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
4 SPS-1
(Only
One
line in
service)
765kV Sholapur-Raichur S/C flow > 1500 MW:
Total flow on 765 kV Sholapur-Raichur S/C lines crossing
a pre-set value of 1500 MW in Sholapur to Raichur ---
Instantaneous triggering
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
500 MW Load shedding in SR: TN – 146 MW, Kerala –
125 MW, Karnataka – 104 MW, AP – 125 MW
Note: Loads identified for shedding in SR for this SPS
action is same as the Loads identified for shedding in SR
for Trip Signal-3 of Talcher-Kolar.
Suggestion: This may be blocked
S no 3 above should be ok.
Annexure- IX (SPS-Revisions)
9 / 18
![Page 105: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/105.jpg)
8
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
5 SPS-3 Loss of 765kV Sholapur-Raichur lines carrying 800 MW
towards SR:
Loss of import of SR on 765kV Sholapur-Raichur section
by more than 800 MW due to tripping of these lines.
SPS Actions:
500 MW Load shedding in SR: TN – 146 MW, Kerala –
125 MW, Karnataka – 104 MW, AP – 125 MW
Suggestion: SPS should trigger when loss of import of SR on 765kV Sholapur-Raichur section due to tripping of these lines is more than 1500 MW.
SPS Actions:
Loads identified for shedding in SR for
this SPS action is same as the Loads
identified for shedding in SR for
Talcher-Kolar Trip Signal-3.
Different set of loads (500 MW) shall be
identified and the trip command should
be given to these new identified loads
only.
Additional loads to the tune of 500–
1000 MW shall be identified for load
shedding in Southern Region.
So in total there would be a total of 1000-1500 MW load shedding in
Rationale: From the past data, it is observed that SR FRC is in the range of 1500 MW – 2500 MW. Hence, 1500 MW has been selected for SPS action. In SR, to arrest a sharp frequency fall, additional load shedding to the tune of 1000–1500 MW through SPS shall be identified.
Annexure- IX (SPS-Revisions)
10 / 18
![Page 106: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/106.jpg)
9
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
Southern Region for this SPS.
6 SPS-4 400kV Raipur – Wardha D/C:
Flow on either circuit of 400 kV Raipur – Wardha D/C
crossing 850 MW and remaining above this value for 2.5
seconds
Or
Tripping of any one circuit of 400 kV Raipur – Wardha
D/C carrying 700 MW or above
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
800 MW Load shedding in SR: TN – 290 MW, Kerala –
135 MW, Karnataka – 195 MW, AP – 230 MW
Suggestion: SPS settings may be retained.
SPS Actions:
Loads identified for shedding in SR for
this SPS action is same as the Loads
identified for shedding in SR for
Kudankulam Unit tripping.
Hence, different set of loads (500 MW) shall be identified for tripping and should be different from the loads identified from Kudankulam Unit tripping.
Loads to the tune of 200-300 shall also
be identified for tripping in Western
Rationale:
This would not be an issue after
commissioning of 765kV Raipur-Wardha
Ckt-3 & 4 which are expected by next 3-4
months.
WRPC may kindly ensure load shedding
of 200-300 MW in Western
Maharashtra.
Annexure- IX (SPS-Revisions)
11 / 18
![Page 107: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/107.jpg)
10
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
Maharashtra for shedding.
7 SPS-5 400kV Wardha - Parli D/C:
Flow on either circuit of 400 kV Wardha - Parli D/C
crossing 850 MW and remaining above this value for 2.5
seconds
Or
Tripping of any one circuit of 400 kV Wardha - Parli D/C
carrying 750 MW or above
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
800 MW Load shedding in SR: TN – 290 MW, Kerala –
135 MW, Karnataka – 195 MW, AP – 230 MW
Suggestion: SPS settings may be retained as it would help in case of tripping of 765kV Aurangabad-Sholapur D/C. SPS Actions:
Loads identified for shedding in SR for
this SPS action is same as the Loads
identified for shedding in SR for
Kudankulam Unit tripping.
Hence, different set of loads (500 MW) shall be identified for tripping and should be different from the loads identified from Kudankulam Unit
WRPC may kindly ensure load shedding
of 200-300 MW in Western
Maharashtra.
Annexure- IX (SPS-Revisions)
12 / 18
![Page 108: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/108.jpg)
11
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
tripping. Loads to the tune of 200-300 shall be
identified in Western Maharashtra for
shedding.
8 SPS-6 400kV Parli – Sholapur D/C:
Flow on either circuit of 400 kV Parli – Sholapur D/C
crossing 800 MW and remaining above this value for 2.5
seconds
Or
Tripping of any one circuit of 400 kV Parli – Sholapur
D/C carrying 700 MW or above
SPS Actions:
800MW Gen Back down in WR: JPL-150 MW, JPL extn –
150 MW, KSK – 100 MW, LANCO – 100MW, DB Power –
100 MW, KWPCL – 100 MW, BALCO – 50 MW, NSPCL –
50 MW
800 MW Load shedding in SR: TN – 290 MW, Kerala –
135 MW, Karnataka – 195 MW, AP – 230 MW
Suggestion: SPS settings may be retained as it would help in case of tripping of 765kV Aurangabad-Sholapur D/C.
SPS Actions:
Loads identified for shedding in SR for
this SPS action is same as the Loads
identified for shedding in SR for
Kudankulam Unit tripping.
Hence, different set of loads (500 MW) shall be identified for tripping and should be different from the loads identified from Kudankulam Unit tripping.
Rationale:
This SPS would act as back-up in case of failure of 765kV Aurangabad-Sholapur D/C tripping SPS. WRPC may kindly ensure load shedding of 200-300 MW in Western Maharashtra.
Annexure- IX (SPS-Revisions)
13 / 18
![Page 109: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/109.jpg)
12
S.
No
SPS
Name
Triggering criteria for SPS (implemented) Proposed revision in SPS Remarks
Loads to the tune of 200-300 shall be
identified in Western Maharashtra for
shedding.
9 SPS-7
(Only
One
line in
service)
765kV Raichur-Sholapur line current exceeding 800
Amp (1000 MW on either direction):
Total flow on 765 kV Sholapur-Raichur S/C lines crossing
a pre-set value of 1000 MW (800 Amps) in Sholapur to
Raichur and remains above 1000MW for 10 seconds ---
Trips the line
Suggestion: Line tripping to be blocked
Rationale: Tripping of line would lead to unnecessary separation of NEW grid and SR grid. Hence, tripping of line through SPS should be blocked.
Annexure- IX (SPS-Revisions)
14 / 18
![Page 110: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/110.jpg)
13
A. Proposed Special Protection Schemes (SPS)
S.
No
SPS Name Proposed Triggering criteria for SPS (implemented) SPS action required Remarks
1 SPS-8
(Both lines
in service)
765kV Aurangabad-Sholapur D/C flow > 2000 MW
Tripping of 765kV Aurangabad-Sholapur D/C carrying a pre-set value of 2000 MW
in Aurangabad to Sholapur direction.
Load shedding in SR: Quantum of load shedding for each case is indicated in the Table-1. Generation Back-down in WR: Approximately 500 - 1000 MW generation may be backed down from generators in W3 area.
Rationale:
SR load is having 80% sensitivity on 765kV Aurangabad-Sholapur line loading. In case of Outage of one circuit of 765kV Aurangabad-Sholapur D/C, the angle between 400kV Jindal and 400kV Cochin goes above 100 degrees. D/C loss should be properly detected by the SPS.
2 SPS-8
(Both lines
in service)
765kV Aurangabad-Sholapur D/C flow > 2500 MW
Tripping of 765kV Aurangabad-Sholapur D/C carrying a pre-set value of 2500 MW
in Aurangabad to Sholapur direction.
3 SPS-8
(Both lines
in service)
765kV Aurangabad-Sholapur D/C flow > 3000 MW
Tripping of 765kV Aurangabad-Sholapur D/C carrying a pre-set value of 3000 MW
in Aurangabad to Sholapur direction.
4 SPS-9 765kV Raichur - Kurnool S/C flow > 2000 MW
Tripping of 765kV Raichur - Kurnool S/C carrying a pre-set value of 2000 MW in
Raichur to Kurnool direction.
Load shedding in SR: 500 MW -1000 MW
Tripping of 765kV Raichur-Kurnool line above 2000MW would lead to overloading of 2*1500 MVA ICTs at Raichur. Hence, it would be better to
Annexure- IX (SPS-Revisions)
15 / 18
![Page 111: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/111.jpg)
14
S.
No
SPS Name Proposed Triggering criteria for SPS (implemented) SPS action required Remarks
shed the load to the tune of 500-1000 MW, so that system remains intact and secure.
Table-1: Load shedding requirement in SR and Maharashtra due to tripping of 765kV Aurangabad-Sholapur D/C
S. No.
Condition Flow on both
Circuits (A)
Flow on Sholapur-Raichur (B=
A*0.8)
Maximum Allowable flow on Sholapur-Raichur D/C without 765kV Aurangabad-Sholapur D/C
Load shedding required in SR
1 Tripping of 765kV Aurangabad-Sholapur D/C 2000 1600 1300 300
2 Tripping of 765kV Aurangabad-Sholapur D/C 2500 2000 1300 700
3 Tripping of 765kV Aurangabad-Sholapur D/C 3000 2400 1300 1100
4 Tripping of 765kV Aurangabad-Sholapur D/C 3500 2800 1300 1500
Annexure- IX (SPS-Revisions)
16 / 18
![Page 112: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/112.jpg)
15
Load Groups identified for SPS actions (Presently Implemented): S. No.
SPS Name Load Group – 875 MW
Load Group – 780 MW
Load Group – 505 MW
Load Group – 848 MW
1
Talcher-Kolar HVDC Trip Signal-1 - Loss of power flow on HVDC greater than 500 MW but less than 1000
MW (OR) - Tripping of one pole and HVDC flow prior tripping greater than 1000
MW but less than 1500 MW
√ (Kar-250, AP-230,
TN -395) - - -
2
Talcher-Kolar HVDC Trip Signal-2 - Loss of power flow on HVDC greater than 1000 MW (OR) - Tripping of one pole and HVDC flow prior tripping greater than 1500
MW
- √ (Kar-200, AP-240, TN -170, Kerala-170)
- -
3
Talcher-Kolar HVDC Trip Signal-3 - Loss of power flow on HVDC greater than 2000 MW (OR) - Tripping of one pole and HVDC flow prior tripping greater than 2000
MW
- - √ (Kar-104, AP-125, TN -146, Kerala-125)
-
4 Kudankulam Unit Tripping
- -
-
√ (Kar-193, AP-230, TN -290, Kerala-135)
5 SPS-1 (765kV Sholapur-Raichur flow > 1500 MW) - - √ -
6 SPS-3 (Loss of 765kV Sholapur-Raichur lines carrying 800 MW towards SR) - - √ -
7 SPS-4 (400kV Raipur – Wardha D/C flow > 850 MW/ckt) - - - √
8 SPS-5 (400kV Wardha - Parli D/C flow > 850 MW/ckt) - - - √
9 SPS-6 (400kV Parli – Sholapur D/C flow > 800 MW/ckt) - - - √
10 SPS-7 (765kV Raichur-Sholapur line current exceeding 800 Amp (1000 MW on either direction)
- - √ -
1. Loads identified for shedding in SR for SPS-1 & SPS-3 are same as the loads identified for load shedding in SR for Trip Signal-3 of Talcher-
Kolar HVDC. 2. Loads identified for shedding in SR for SPS-4, SPS-5 & SPS-6 are same as the loads identified for load shedding in SR for Kudankulam
unit tripping.
Annexure- IX (SPS-Revisions)
17 / 18
![Page 113: · PDF fileConstituents are requested to bring/ give full particulars for the tripping ... that may be required to address the many ... 400 kV Kalpaka (viii) 220 kV Edamon](https://reader033.vdocument.in/reader033/viewer/2022051320/5a7d778f7f8b9a49588d95a7/html5/thumbnails/113.jpg)
16
Observations based on load groups identified for SPS actions:
1. Loads identified for SPS-1, 3, 4, 5 & 6 shall be different from Talcher-Kolar HVDC SPS loads and Kudankulam SPS loads.
2. With the commissioning of 765kV Aurangabad-Sholapur D/C, 765kV and 400kV lines loadings are likely to increase drastically with
operationalization of LTA. Loads identified for SPS shall be different from the loads identified for UFR.
3. In the event of tripping of single circuit or both circuits of 765kV Raichur-Sholapur, a signal may be sent to Talcher-Kolar HVDC for
ramping up the HVDC set-point to 2500MW. This would reduce the overloading of AC lines in WR-SR corridor.
Notwithstanding the above revisions suggested, the following are also important.
Improving reliability of SPS through redundant measurements, logic and communication path and end terminals.
Use of metering core of CTs and PTs for analog measurements used in the SPS logic, particularly where the same is based on steady
state flows crossing a particular value.
Need to cover more generators in the NEW grid so that adequate relief is available as in many instances, the antecedent generation in
many of the generators selected is already very low.
Wiring of each SPS operation to the local substation Event Logger.
Triggering of each SPS action and the receipt of signal at each point to be recorded in SLDC/RLDC/NLDC SCADA
Prompt submission of data to RLDCs regarding SPS action in the prescribed format.
Each instance of inadequate relief through SPS to be thoroughly analysed and remedial actions taken so as to have increased
confidence on the SPS reliability.
Annexure- IX (SPS-Revisions)
18 / 18