aries-at maintenance system definition and...

68
ARIES-CS Maintenance System Final Report Waganer, 02/26/22, 12:02 AM ARIES-CS Maintenance System Definition and Analysis By Lester M. Waganer and Richard J. Peipert-Jr The Boeing Company, Xueren R. Wang and Siegfried Malang, University of California, San Diego and The ARIES Team Corresponding Author Lester M. Waganer The Boeing Company Mail Code S270-3760 PO Box 516 St. Louis, MO 63166 Phone: 314-233-8617 Fax: 314-233-7338 [email protected] Key Words: ARIES, fusion, stellarator, maintenance, availability, power core Page 1

Upload: vuminh

Post on 26-Aug-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

ARIES-CS Maintenance System Definition and AnalysisBy

Lester M. Waganer and Richard J. Peipert-Jr The Boeing Company,

Xueren R. Wang and Siegfried Malang, University of California, San Diego

andThe ARIES Team

Corresponding Author

Lester M. WaganerThe Boeing CompanyMail Code S270-3760

PO Box 516St. Louis, MO 63166Phone: 314-233-8617

Fax: 314-233-7338

[email protected] Words:

ARIES, fusion, stellarator, maintenance, availability, power core

Number of pages: xx pages

Number of tables: 4 tables

Number of figures: 19 figures

Page 1

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

ARIES-CS Maintenance System Definition and AnalysisBy

Lester M. Waganer The Boeing Company

andThe ARIES Team

AbstractThe goal of the ARIES-Compact Stellarator is to define and assess a stellarator-based fusion

power plant to provide electrical power as competitively as possible by balancing performance,

cost, and plant availability. The traditional stellarator concepts are made as compact as possible

to reduce the plant capital costs, which are driven by the power core volume, weight, and

specific cost. Different coil configurations are defined and assessed trading plasma performance,

power core design, access between the coils, and overall capital cost. Maintenance options are

assessed and the port maintenance of first wall/blanket and divertor modules is selected as the

most feasible approach. Access through the coils is very important because the plasma facing

components have a limited lifetime. The available port access areas between the coils determine

the maximum module envelope. With the maintenance approach selected, the frequency of

maintenance determined, and module size defined, features of the maintenance approach are

developed to maximize the power plant availability. After the preliminary maintenance

approach details for the power core components and facilities are finalized, a maintenance

assessment is developed by analyzing the nominal times to conduct the maintenance actions. It

is estimated that the ARIES-CS plant availability could reasonably be in the range of 85%.

Page 2

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

IntroductionThe ARIES studies, sponsored by DOE and led by UCSD, have explored, developed, and

examined numerous magnetic and inertially confined conceptual commercial electric power

plants. The ARIES-Compact Stellarator (ARIES_CS) power plant1 is the current fusion power

plant study. The goals of this study is to capture the very attractive operational features of a

stellarator while packaging it very compactly to bring the capital cost closer to the tokamak and

without impacting the usability of the device. A measure of the usability is the plant availability

that directly influences the busbar cost of electricity (COE), just as does the plant performance

(gross electrical power), net plant efficiency, and annual operational costs.

This chapter will specifically examine the how the compactness of the stellarator impacts the

maintenance approach and the design of the maintenance facilities and hardware. Moreover, the

approach and maintenance equipment and facilities will be used to analyze the scheduled power

core maintenance actions and the overall plant availability factor. Other ARIES-CS chapters will

address the overall power core design and discuss how the physics and coil definition determine

and influence the power core elements. Especially important to the maintenance approach is the

geometry definition of the toroidal coils, which directly determines the location and size of the

available maintenance ports.

The power core is defined to be the innermost subsystems that produce and contain the

plasma and convert the fusion power into thermal power. The power core consists of the first

wall, blanket, shield, divertor, in-vessel shielding, internal structure, modular TF and PF coils,

vacuum vessel, cryostat, and plasma heating for startup. No current drive systems are required

for a stellarator device. The power core systems are a part of the Reactor Plant Equipment that is

uniquely configured to the particular magnetic confinement concept.

Page 3

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Power Core Maintenance PhilosophyTwo of the primary guiding principles, or goals, for the overall fusion power plant continue

to significantly influence the design and operation of its maintenance system — the plant must

be safe and economical.

The plant must be safe both to the general population and to the plant workers, including the

maintenance workers. A fusion power plant is a nuclear device that emits high-energy neutrons

during operation. During operation, sufficient shielding within the power core and the biological

shield (bioshield) is provided for the plant operational personnel. These personnel are not

allowed inside the bioshield during operation. During shutdown periods, secondary reactions

from the highly irradiated power core materials continue to produce beta and gamma radiation

inside the power core at a lower rate as compared to the dose rate during operation. The power

core materials are chosen to minimize these secondary radiation levels and long-lived radioactive

waste products. After a 24-hour cooling off period, the radiation level within the power core will

decrease by roughly two orders of magnitude to a level suitable for remote access with radiation-

hardened maintenance equipment, as documented in ARIES-RS2. It is anticipated that the

governing regulations for allowable radiation levels for nuclear plant workers will continue to be

upgraded to assure no hazardous exposure. This assumption would effectively mandate that all

maintenance and refurbishment of power core replaceable components would be accomplished

entirely by robotic equipment, both within the power core, during transit to the Hot Cell, and any

disposal or refurbishment in the Hot Cell. No hands-on maintenance of the power core

components is allowed or required.

For the power plant to be as economical as possible, the plant availability must be as high as

possible. Current power plants annual availability experience is in the mid 80% range, with

Page 4

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

some instances in the 90% range. Thus an availability goal or at least 85% is the nominal goal

for potential fusion power plants.

The definition of Availability is the amount of time the plant is available for power

production divided by the total time, which is the sum of the operational time and the down time.

For a base-loaded plant, it is assumed that all downtime is associated exclusively with either

scheduled or unscheduled maintenance.

Operational Time is the power production time over a set period of time. Scheduled Down

Time is the sum of regularly scheduled maintenance periods for the power core, other reactor

plant equipment, and balance of plant equipment. The Unscheduled Down Time is the

summation of maintenance times to repair operation failures that cause the plant to cease power

production. Failures that do not cause a power interruption are not considered.

The primary interest for this aspect of the study is the influence of the power core

components on the plant availability. The maintenance actions for both the scheduled and

unscheduled actions are generally related for the components with a limited lifetime. All other

plant items can also fail and must be replaced with a very low probability of failure. Thus, they

will not be addressed herein except that they must be designed such that they are repairable or

replaceable.

The maintenance of the internal power core components must be efficient and expedient to

keep the maintenance downtimes as short as possible. It is assumed that aggressive maintenance

research and development programs will be implemented to accomplish an automated robotic

maintenance system that can quickly and efficiently inspect, diagnose, repair, remove, replace,

Page 5

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

and inspect all components of the power core. The degree of automation and autonomy is

unknown at this point, but the trend is toward a higher degree of autonomy, that is, self

determination of the actions to be accomplished. Since this power plant design is based on a

tenth of a kind plant, all design definition and maintenance actions would have been fully vetted

and a highly efficient maintenance operation is likely. The use of expert systems will be

expanded to help develop and enhance experience databases for maintenance systems. Fuzzy

logic will be applied to help analyze new variations on maintenance situations. Vision, position,

and feedback control will be enhanced to provide precise position and motion control that would

compensate for unexpected position and loading conditions. Optimization programs will refine

the maintenance procedures to speed the overall process. The ability to predict component wear-

out and incipient failures will continue to be improved.

Maintenance Impact of a Compact Stellarator DesignThe overall goal of the ARIES-CS study was to investigate the inherent advantages and

issues that would arise in adopting a very compact stellarator design. The initial step was to

investigate and define the potential modular toroidal field coil sets that would offer a stable, high

beta plasma with attractive engineering features. These engineering features would include

reasonable coil bend radii, moderate out of plane excursions for the coils, sufficient access

between coils, and adequate space for access (maintenance, support, heat transport plumbing,

vacuum ducts, and plasma startup heating).

Selection of a Coil Configuration - Several classes of coils were assessed3, including two that

were more intensively examined, namely the quasi-axisymmetric stability derivative of the

NCSX (National Compact Stellarator)4 three-field period configuration designated as ARE and a

MHH2 two-field period configuration. These are shown below in Figure 1. A greater physics

Page 6

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

basis and design experience from NCSX led to an earlier and more extensive examination of the

ARE case, which was adopted for the baseline ARIES coil configuration. A more in-depth

assessment is provided in Reference 3.

Figure 1. ARIES-CS ARE and MHH2 Plasma and Coil Configurations

Selection of a Maintenance Scheme - In concert with the coil/plasma selection and the

definition of the internal power core components, the maintenance approach was evaluated and

defined. One approach was to remove and replace individual coil structures and all related

internal power core components as complete assemblies through individual large access ports.

This would be very difficult to implement as the coils are very convoluted and would require

similarly convoluted poloidal segmentation of all internal components with very difficult

plumbing of all power core components. This approach of coil segmentation was not pursued

beyond the initial evaluation.

Page 7

ARE Three Field Period MHH2 Two Field Period

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

The second maintenance approach was to remove complete field period sectors. After the

field period sectors are translated radially outward a short distance (implying a much larger

enclosing bioshield), the blanket and divertor modules would be removed toroidally in sequential

order. The convoluted geometry of the first wall and blanket required a 3-D analysis to

determine if the blanket modules could be extracted toroidally inside the convoluted hot shield.

In a few instances, the hot shield was slightly modified to allow additional space. A field period

sector of the power core is a very large and massive component to be moved (approximately 4 M

kg), the superconducting coils have to be de-energized and warmed, and all lifetime components

have to be disconnected and realigned upon reinsertion. This approach was evaluated in some

detail, but is not recommended as the baseline maintenance approach.

The third maintenance approach is to leave all lifetime components (hot shield, coolant

manifold/hot structure, vacuum vessel, and coils/coil structure) in place and only remove the life-

limited components (first wall, blanket, divertor, and a few elements of the shield). These

replaceable components would be removed through the main ports. The size of the main

maintenance ports determines the blanket and divertor module sizes and geometries. This is the

adopted approach. A more detailed assessment of the maintenance approaches is discussed in

the ARIES-CS Power Core chapter5.

Selection of Coil Structural Approach - The usual design approach for the stellarator coil

structural support in existing experiments is to create a coil structure for each coil. Then the

conducting cables would be wound onto individual structures. In turn, the structures would be

joined to each other to form a field period and then field periods would be joined. Usually for

the larger radii stellarators, the coil interconnecting structures are a rather open lattice structures

with much open space between individual coil structures. In the case of more compact NCSX

Page 8

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

experiment, each individual coil structure has integral bridging structure including bolted flanges

for connection to the adjacent coil structures.

For ARIES-CS, the adopted approach5,6 was to adopt a single monolithic field period coil

structure that contains internal grooves for the superconducting coils, thicker side and outside

(away from plasma) structural support for the coil EM forces, and a thinner connecting structure

in regions further away from the coils. This monolithic structure will be operated at cryogenic

temperatures and accommodate all penetrations for maintenance, vacuum pumping, heat

transport plumbing, and plasma startup heating systems. A single field period, without and with

coils are shown in Figure 2.

Figure 2. Coil structure without and with coils in the internal grooves

Selection of Port Locations - The coil configurations were carefully examined for locations

to maximize the necessary penetration envelopes, allow adequate functionality of the penetrating

component, and still have sufficient structural strength and minimal deflection under design

loading conditions. Table 1 is a tabular listing of the ports provided through the coil structure.

For maintenance, three large ports are located outboard on the 0°, 120°, and 240° planes and

centered on the horizontal midplane.

Page 9

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Number of the openings

Opening in the vacuum vessel

Opening in the coil structure tube (VV wall ~0.1 m;

insulation ~0.02 m)

Maintenance port

3 1.85 m (tor.) x 3.85 m (pol.)

2.09 m (tor.) x 4.09 m (pol.)

ECH/Auxiliary port

3 1.52 m (tor.) x 1.54 m (pol.)

(waveguide: 0.24 m x 0.54 m)

1.76 m (tor.) x 1.78 m (pol.)

Diverter access pipe

24 D=0.6 m D=0.64 m

Vacuum pumping duct

12 1.0 m (tor.) x 1.25 m (pol.)

1.24 m (tor.) x 1.49 m (pol.)

He/PbLi pipe connecting

to HXs

6+6 D=0.74 m D=0.78 m

Hot supporting leg

9 D=1.0 m D=1.04 m

Cold supporting leg

9 D=0.75 m D=0.79 m

Table 1. Port openings through the coil support structure with the ARE baseline coil set

Impact of Radial Build - Moving the coils inward to be as compact as possible also has a

profound impact on the power core components internal to the coils, namely the first wall,

blanket, divertor, shielding and internal supporting structures. The intent is to maximize the

content of the lifetime components while minimizing the replaceable components. L. El-

Guebaly7 documents this approach to create an optimized radial build for all regions of the

compact stellarator. A further refinement is to create a specialized tapered blanket/shielding

region that is radially much more compact that allows further minimizing the radial thickness of

the stellarator configuration in the critical areas.

Page 10

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Feasibility Groundrule - One other study premise has a profound effect on the maintenance

approach and analysis for ARIES-CS. The ARIES project has a ground-rule that any design

approach must be demonstrated or deemed feasible based upon today’s technology and not rely

on a completely unproven future development to achieve a viable solution. For the maintenance

approach, the current approach is to connect all high temperature heat transfer fluid piping with

welded joints and disconnect/reconnect these joints by grinding, cutting, and re-welding the

pipes. Thus all blanket heat transfer fluid piping must use the cutting and welding approach. An

advanced connection approach that would allow a much faster blanket replacement was

proposed, but is considered only as an advanced maintenance option.

The design approaches and guidelines outlined above are the basis for the development of the

maintenance approach for the ARIES-Compact Stellarator.

Design Approach for Maintenance Equipment and Maintenance FacilitiesMaintenance Port Definition - With the study goals and the basic design precepts in place,

the design approach for the maintenance equipment could be developed. The port maintenance

is the baseline approach with all blanket and divertor modules passing through large maintenance

ports. As noted in Table 1, there is only room for a single large maintenance port per field

period that is located outboard at the 0º poloidal position on the horizontal midplane. This

maintenance port envelope is 4.0 meters high and 1.8 meters wide. Slightly larger dimensions is

possible with some corners clipped to clear the close TF modular coils, but this is deemed to be

1

2

Page 11

Figure 3. Operational view of power core

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

an undesirable envelope and not pursued. Likewise, a slightly larger envelope was possible if

the envelope is tilted, however, this idea is also rejected.

Maintenance Port Access Provisions - Figure 3 shows an operational power core cross-

section view at the 0º poloidal position, with the plasma shown in the interior of the power core.

To gain access to the power core vacuum vessel maintenance port, a section of the bioshield is

removable. This sizable bioshield door is on hinges or rollers that will allow it to be withdrawn

and stored to the side. This allows access to the vacuum vessel main maintenance port. The 4-

meter high and 1.8-m wide opening is the inside dimensions of the vacuum vessel port extension.

Since both the vacuum vessel and the coil structure have openings in their structure, an

equivalent shielding component is provided in

the port vacuum duct area. There is a

removable shield element (Port Shielding)

inside the vacuum vessel port duct. Due the

nuclear heating in this region, this removable

component must be cooled. This element will

also be removed and placed outside the power

core. Removal of these elements allows access

to the internals of the power core.

These design parameters are used to develop an approach for port maintenance equipment

and maintenance facilities. The design approach described is not unique, but it would be

representative of a reasonable means to accomplish the desired maintenance.

Transfer Chamber Approach and Definition - Figure 4 shows the operational power core

view with a permanently attached transfer chamber. The ARIES-RS8 and ARIES- AT9

Page 12

Figure 4. Operational power core with attached transfer chamber

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

maintenance approaches used a maintenance corridor directly outside the bioshield to dock large

mobile transporters for the removed power core sections. In the ARIES-RS and ARIES-AT

design approaches, the time to transport the few large components was short in comparison to the

other maintenance actions. But with the

ARIES-CS design, there are a total of 198

blanket modules and 24 divertor modules to be

removed. The adopted approach is to use a

fixed transfer chamber permanently attached to

the bioshield, as shown in Figure 4. The size

of the internal transfer chamber is not defined

other than it should be large enough to

accommodate the maintenance equipment and

removed and stored power core components. The transfer chamber has airlocks that allows

ingress and egress of mobile extractor machines to remove the blanket and divertor modules and

place them into smaller mobile transporters. These mobile transporters dock to the transfer

chamber, accept the used modules, and transfer them quickly to the hot cell for refurbishment or

disposal. New modules are brought to the transfer chamber and subsequently installed into the

power core. On the far side of the transfer chamber, as shown in Figure 4, the transfer airlock

door is shown, which prevents any connection between the plasma chamber and building

atmosphere during maintenance.

This transfer chamber approach allows the extractor equipment to work at maximum

efficiency by disconnecting the power core modules, removing them from the core, bringing

them inside the transfer chamber, and transferring them into the awaiting mobile transfer

Page 13

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

modules for transit to the Hot Cell. Then, the transfer modules independently transfer the

removed components back to the Hot Cell. Thus, the interior power core operations and the

external operations are accomplished in parallel except for common operations at the transfer

airlock door. This concept of the fixed transfer chamber has a safety advantage as providing a

more secure containment barrier, as discussed in Reference 10.

Initial Maintenance Actions for Access to Power Core Interior - For both scheduled and

unscheduled maintenance actions, the power core must be powered down with plasma

extinguishment. The coils will be de-energized, but will remain in at cryogenic temperatures.

The heat transfer fluids and coolants continue to be circulated to remove the stored energy and

decay heat. This is accomplished over a 24-hour deactivation and cooling-down period. During

this time, the power core maintenance equipment, the Extractor, is readied and positioned for

entry into the power core, as shown in Figure 5. Just outside the bioshield is a lower region of

the Transfer Chamber that allows the bioshield door to be removed and translated to the side as

shown in Figure 6. The vacuum vessel door is then removed and set aside. After this vacuum

door is in the storage position, the floor is raised or a platform is installed at floor level for the

remainder of the maintenance actions at this port.

Page 14

Figure 6. Extractor removing Bioshield door

Figure 7. Removal of the vacuum vessel main port shield plug

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

The next component in the vacuum port duct

for removal is the removable shield plug, see

Figure 7, that supplies a shielding equivalent for

the vacuum vessel and coil structure. This plug

structure is designed to closely fit to the vacuum

port walls to minimize neutron leakage around the

periphery of the shield plug. This component

receives some nuclear heating that requires active

cooling. Plumbing connections are not defined at

present.

Removal Procedure for the Main Port

Blanket/Shield/Manifold Assembly - The removal

of most of the blanket modules requires

disconnection of their plumbing and the

Page 15

Figure 7. Removal of the vacuum vessel main port shield plug

Figure 8. Removal of the port blanket, shield, and manifold/structure with Extractor

Figure 5. Quiescent power core with Extractor maintenance equipment inside transfer chamber

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

mechanical fasteners from the underlying shield. However at the main ports, all these

components of blanket, shield, and manifold / structure must be removed to gain access to the

interior. It is possible to sequentially disconnect and remove each component in the port region,

but it is more convenient to remove the entire assembly as a single unit, as shown in Figure 8.

Structural and plumbing connections to the adjacent coolant manifold and structure are

disconnected by removing access covers. This level of detail is not defined at this conceptual

design. The Extractor maintenance machine secures and holds this assembly while the

connections are disconnected. Following the disconnection of the plumbing and structural

connections, this port assembly is removed through the vacuum vessel port, as shown in Figure

8. This assembly is as large as possible while still fitting through the port area.

Blanket Module Maintenance Provisions - The removal of the vacuum vessel port shielding

plug opens up the main maintenance vacuum port and provides access to the power core

elements for removal and replacement. All life-limited first wall/blanket modules are

mechanically attached to hot shield throughout the power core, as explained in Reference 5. In

turn, the hot shield is structurally attached to the hot coolant manifold / structure, which, in turn,

is supported by the vacuum vessel and power core structure. The physical attachment of the

blanket modules to the hot shield is tentatively defined as four mechanical fasteners accessed

from the face of the first wall. These fasteners are located deep in the

blanket, close to the shield, to minimize the radiation damage. In

addition to the physical connection, there are fluid connections at the

back of the blanket that are disconnected before blanket module

removal. The connection is at the back of the blanket module and is

completely inaccessible from the front as shown in Figure 9. Access

Page 16

Figure 9. Back of Blanket module showing two coaxial heat transfer fluid pipes

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

to the coolant connections is provided by removing shielding blocks behind an adjacent module,

previously removed, and around the pipe connections as shown in Figure 10. Shielding block #1

is accessible and removable after its overlaying blanket module is removed. Then the

semicircular shielding block #2 is translated from behind the blanket module and removed. Then

the semi-circular shielding ring (shielding block #3) is then rotated 180° and removed. This

provides a small annular access area around each tube.

A cutting machine is inserted into the annular ring area

to disconnect the outer heat transfer pipe. The inner

pipe has a slip joint in this area that does not require

cutting the pipe. This subject is discussed in detail in

Reference 5.

Divertor Module Maintenance Provisions - The

other type of module to be removed from inside the power

core is the divertor module. The divertor modules (shown

in Figures 5, 6, and 7) are only located near the

pointed sections of the plasma and only in certain

poloidal regions. There are 24 individual divertor

modules. The divertor modules are not anchored on

the structural manifold; rather they are structurally

attached to the vacuum vessel via their coolant

piping. Figure 11 shows that structural and

plumbing arrangement. The internal shielding inside

the pipe is designed to reduce the neutron streaming

Page 17

Figure 10. Exploded view of removed shielding blocks and rings for access to heat transfer pipes

Figure 11. Divertor Structural and Plumbing Arrangement

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

down the pipe to acceptable levels and protect the manifold regions to achieve life-of-plant

lifetimes.

Technique for Disconnecting Divertor Module Plumbing - The initial step of the divertor

module replacement is to open access ports in the divertor plumbing near the center of the power

core outside the vacuum vessel and coil structure. This allows the central maintenance machine

to reach in and remove the inner pipe and internal pipe shielding. Further explanation of the

central maintenance machine is provided in a later section. Removing the inner pipe and

shielding is possible because the inner pipe connection is designed to be a slip joint near the back

of the divertor. Once the inner pipe assembly is removed, there is sufficient access inside the

pipe to bring in a cutting machine to cut the smaller diameter section of the outer pipe close to

the divertor back surface. The cut has to be close to the divertor because cutting the larger

diameter pipe would trap the divertor pipe behind blanket. During the cutting operation, the

articulated arm of the extractor machine inside the power core is supporting the divertor module.

Once the outer pipe cut is accomplished, the maintenance extractor removes the divertor module

and takes it out the main port. Because the first pipe cut was made close to the plasma, the

remaining pipe will have been sufficiently damaged by neutrons so that it cannot be re-welded.

Thus, a second cut is done further away from the plasma, perhaps near the vacuum vessel or coil

structure in a region where re-welding is possible. During this second cut, the articulated arm of

the extractor machine holds the larger divertor coolant pipe while the pipe is being cut. Then the

second section of pipe is removed by the interior articulated maintenance arm. These

maintenance actions are explained in more detail in subsequent sections that discuss the

maintenance equipment.

Page 18

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Technique for Removing Hot Shield Blocks for Blanket Plumbing Access - In a prior

paragraph, the approach of removing shield blocks to gain access to cut the heat transfer fluid

plumbing lines is discussed, as shown in the exploded view of Figure 10. Now we will discuss

how these shielding blocks are planned to be removed. One option is that the main extractor

maintenance machine, shown in Figure 8, is used to bring in end effectors to translate, rotate, and

remove the shielding blocks and take them back into the transfer chamber for removal. Then a

cutting machine is brought in and cut the two outer coolant pipes. These operations are either

done by the main articulated boom or by one or more smaller auxiliary booms from the main

port. Then the main boom engages the main mounting fasteners from the front of the blanket

module, disconnects the fasteners, and removes the module out to the transfer chamber. This

option is comprised of all serial operations that can only be done through the main port, which is

very time extensive. Due to the long duration of the serial operations, this is not the chosen

approach.

A more time efficient approach is to remove the shielding blocks and cut the pipe in parallel

while the main port extractor machine is removing a disengaged blanket module. This requires

another auxiliary maintenance port in this field period. There is a requirement to have ECH for

heating the plasma during startup. The size of the port is approximately a square meter in size,

which is an appropriate size for use as an auxiliary maintenance port. A region was found5,6 at a

toroidal angle of 35° slightly above the horizontal midplane with low stresses in the coil structure

that accommodates a port of 1 m2. One ECH port per field period is required and this is in

agreement with the use of the port for supporting maintenance actions.

Definition of ECH Launcher Assembly - The ECH system requires a waveguide launcher

that extends from the first wall surface back through the shield, vacuum vessel, and coil support.

Page 19

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

The design approach for the ECH launcher is shown in Figure 12. The ECH gyrotrons are

located outside the bioshield and will be inside a controlled environment. Right angle turns in

the launcher tube help attenuate the neutron flux down the tube. Supplemental shielding at the

ends of the tube help capture the neutrons. In addition to the right angle bends shown in Figure

12, there are two more horizontal right angle bends just outside the coil structure. The wave

guide launcher tube, bends, blanket, and shielding around the wave guide form a complete

assembly that can be removed for refurbishment of the innermost portion of the launcher tube.

The blanket modules surrounding the launcher tube are a part of the ECH. Since the assembly in

place during operation, there is no requirement for a bioshield door.

Page 20

Figure 12. ECH Launcher Assembly that extends through the bioshield, into the interior of the power core

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Provisions for ECH Assembly Removal – The ECH launcher assembly is designed to be a

self-contained unit of launcher, blanket, and shielding that is separately cooled and removed as a

single unit. Figure 13 shows the ECH assembly after removal from the power core and in the

ECH and auxiliary maintenance transfer chamber. A section of the ECH launcher tube is

removed and set aside to allow the assembly to be translated into the transfer chamber. An

adjustable floor is adjustable in height to accommodate both the ECH assembly and the auxiliary

maintenance equipment. The ECH/auxiliary maintenance transfer chamber is very compact, so a

special extraction mechanism might be employed to withdraw the assembly into the chamber.

Figure 13. Withdrawal of ECH Assembly into the ECH and Aux Maintenance Transfer Chamber

The next step transfers the ECH assembly from the transfer chamber into a smaller transporter

for transit to the Hot Cell for refurbishment. This sequence is shown in Figure 14.

Page 21

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Figure 14. ECH module transfer into the mobile ECH assembly

Auxiliary Maintenance Operations Conducted Through ECH Port – After the removal of the

ECH assembly, the auxiliary maintenance equipment is brought into the transfer chamber and

power core interior to assist in the disassembly of the blanket modules from the underlying

shielding. This is shown in Figure 15. This auxiliary maintenance equipment specializes in

removing the access shielding around the blanket piping allows the main port maintenance

equipment to operate at a higher degree of efficiency removing the divertor and blanket modules.

It is envisioned that one or more specialized end effectors is used to remove the shielding pieces.

As they

Figure 15. Insertion of the Auxiliary Maintenance Module operating in the ECH port with several articulated booms disconnecting shielding blocks to access blanket coolant

are removed, another arm will collect them in a basket or container for retrieval. After all the

shielding blocks are removed for access to the piping for a particular blanket, a specialized pipe

Page 22

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

cutting machine is positioned around the pipe in the annular opening inside the power core.

These cutting machines currently exist to access the pipe in the envelope defined. These cutting

machines also collect all debris from the cutting action. There are welding units of a similar size

are used for the reassembly of the blanket piping.

Page 23

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Equipment and Procedures for Divertor Module Removal – Before the remaining blanket

modules are replaced, the divertor modules are

removed as they overlay the blanket modules. As

stated previously, the divertor modules are supported

from the coil structure with the divertor piping. The

technique of cutting the supporting outer coolant

piping was discussed earlier. This section will

discuss the maintenance equipment to accomplish

the blanket removal. First, the inner divertor coolant

pipe and shielding is removed from the outside of the

coil structure and vacuum vessel. Figure 16 shows the

two sets of central maintenance equipment that

removes the inner first divertor coolant piping at the

inner, upper, and lower regions of the power core for

24 locations total. There are two maintenance

machines located outside the coil structure that are

located on the power core central vertical axis (upper

and lower). These maintenance machines have

multiple articulated arms to gain access to the

divertor plumbing access ports. A retrieval end

effector removes access panels and the inner divertor pipe and shielding assemblies. After

removal, robot cutter and cleanup end effectors cut and cleanup the outer divertor pipe. During

the latter operation, the divertor module is supported by the main port articulated boom (also

Page 24

Figure 16. Removal of Divertor inner pipe and shielding to allow entry of cutting and cleanup robots inside outer diameter divertor tube

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

shown in Figure 16) as the supporting divertor pipe is being cut. Following the cutting of the

supporting pipe, the divertor module is removed from the power core with the main articulated

boom and moved to the transfer chamber through the main port opening, as shown in Figure 17.

Page 25

Figure 17. Main articulated boom can now remove and transport divertor plate modules to transfer chamber

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Equipment and Procedures for Blanket Module Removal – Now that the overlying divertor

modules are removed, the blanket module removal commences. As shown previously in Figure

15, the auxiliary articulated arms in the ECH port are removing the shielding blocks and severing

the blanket coolant pipes. Following the final cutting operation on the blanket coolant tubes, the

auxiliary articulated arms commence operations on the next available blanket module shielding

blocks. Once the blanket coolant pipes are severed and debris removed, the main port articulated

arm begins actions to remove the blanket modules.

Figure 18 shows the main port articulated arm

attached to a blanket module near the blanket port.

It inserts special tools deep into the face the blanket

module. The end effectors expand against the side

walls of the holes with sufficient force to engage the

fasteners. The four fasteners to the underlying

shield are then disengaged. The end effectors

continue to grip the holes, allowing the blanket

module removal for transit to the hot cells, as

shown in Figure 19. The same sequence of

removing the shielding blocks, cutting the blanket

cooling tubes by the auxiliary articulated arms, and

removal of the overlying blanket modules is

continued for the remainder of the blanket modules

Page 26

Figure 19. Transfer of Blanket Module #4 into Transfer Chamber

Figure 18. Main articulated boom removing a Blanket Module #4 near main maintenance port

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

in the field period. As mentioned previously, these maintenance actions are being conducted in

parallel in all three field periods.

Inspection and Refurbishment of Power Core Interior – After the removal of all the divertor

and blanket modules, the entire surface of the shield is exposed. At this time, inspection end

effectors is placed on the auxiliary maintenance articulated arms to inspect and survey the entire

shield surface for a field period. The inspection is to detect surface damage that would warrant

further investigation of local areas for repair and/or replacement. The inspection also surveys all

the fiducial datums on the shield to determine if any distortions occurred on the lifetime

components. This data are used to make adjustments for the attachment of the replacement

divertor and blanket modules. Time is allotted for these actions.

Reassembly of the Power Core – The reverse sequence of operations is required for

reassembly of the power core modules. Additional time is required for joining the coolant

connections, cleaning up the weld residue, inspecting for leaks, and securing mechanical

connections. This is the sequence of operations for the initial build of the power core.

Cleaning, Bakeout, Power Up, and Systems Checkout – To bring the power core back to an

operational state, the new divertor modules, new blanket modules, and refurbished ECH

assemblies are cleaned, baked out, powered up, and checked out prior to commencing full power

operation.

Assessment of Scheduled Power Core Maintenance Scheduling Options

The prior discussions focused on how the power core is maintained and refurbished. This

section addresses scheduling of maintenance and duration of each operation. Each field period is

identical in its makeup of modules and ancillary equipment. Thus scheduled maintenance is

Page 27

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

conducted simultaneously at all three ports at the end of the current blanket and divertor lifetime

of 3.0 FPY. This provides the shortest maintenance time, but requires three complete sets of

maintenance equipment plus any required spares.

A second option is to only replace only half the divertor and blanket modules in all three

field periods, alternating the right and left half of each field period every 1.5 FPY. Since the

blanket modules cannot be individually removed, they have to be removed in a certain sequence,

starting from the main port opening. Therefore, the right and left replacement scheme always

has to remove those blankets in the port sector each time. They cannot be re-welded due to

radiation damage to their piping, thus they have to be replaced every 1.5 FPY. Therefore there is

additional cost and time associated with the right/left replacement scheme. It still requires three

full sets of maintenance equipment.

Another option is to replace only on one field period at a time, once every three years. There

is no extra replacement hardware required for this option. And it only uses one set of

maintenance equipment, but that set of maintenance equipment is used three times as often. The

downside is that the downtime for cooldown, access to the machine, inspection, checkout, and

startup are duplicated three times every 3.0 full power years as opposed to once for the first

option and twice for the second option.

The decision which of the three options is the most suitable also depends on the frequency

and duration of general plant maintenance. The down time needed for scheduled maintenance of

the entire plant can be used for the parallel replacement of power core components. If, for

example, the plant is shut down for two weeks once every year, this time could be used for the

replacement of a part of the blanket modules, reducing in this way the impact of power core

replacement on total availability. This method is employed in fission power plants where, for

Page 28

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

example, every year a third of the fuel elements is replaced during the scheduled maintenance of

the entire plant. This corresponds with the option three described above with either the

replacement of all blanket modules in one field period, or the replacement of half the modules in

two field periods. However, there is strong incentive to push for the option with the highest

availability and extend the all of the plant scheduled maintenance periods to match that of the

power core.

Since it was not possible in the frame of this study to get sufficient information on the

required maintenance of the entire plant, the first option of maintaining all three field periods

simultaneously is selected as the baseline maintenance approach. There is a trade off between

option 1 and 3 depending on the times and the cost of maintenance equipment that may need to

be revisited in the future when more detail is known.

The technology of forecasting failures in the blanket modules will be a necessary research

and development effort because the financial impact of having a large base-loaded plant out of

service is significant. Unscheduled downtimes can have a more profound impact on availability

as compared to scheduled downtimes. So it is anticipated that a predicted impending failure

might be capable of being forecast in the time frame of this plant. The decision to remove

enough divertor and blanket modules to replace the faulty one or replace all the modules in a

field period will have to be made based on the remaining core lifetime. The geometry constraint

of the Compact Stellarator blanket modules is such that, on average, many modules may have to

be removed in sequence to obtain access to the faulty module.

Page 29

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Maintenance and Availability AnalysisThe maintenance approach is defined and supported with selected maintenance equipment

and facilities. The following sections analyzes the maintenance actions and durations necessary

to remove and replace the life-limited power core parts.

Maintenance Analysis Basis – The maintenance actions are defined to be those necessary to

gain access to, remove, and replace all life-limited components inside the power core. Those

components are the divertor modules, blanket modules and parts of the ECH launcher assembly.

All these components are designed to have the same operational lifetime of 3.0 full power years

(FPY). The chosen maintenance scenario replaces all components at one time. Since there is a

varying neutron wall load on the first wall surface, one or more blanket modules will be at its

end of life, while others in a lower NWL region are replaced before their actual end of life. But

the cost of blanket modules is small compared to those costs associated with plant downtime.

Each maintenance action is identified and an estimate of the time to complete the action is

defined. The basis for this conceptual design is that it is representative of a tenth of a kind plant.

There will also be a demonstration plant and a prototype plant that will precede the commercial

plants. Further, it is assumed that the maintenance facilities, equipment, procedures, and

timelines have been defined, developed and refined to achieve a mature process at the 10th of a

kind plant.

The maintenance equipment is remotely operated and nuclear hardened due to the radiation

hazard. Also the equipment is highly autonomous with known actions predetermined. The

degree of human intervention is anticipated to be minimal except for abnormal situations. The

paths of the articulated arms is fully defined in advance and optimized for step duration,

Page 30

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

component safety, maintenance equipment load, and arm deflection. The duration estimates are

based upon these assumptions.

Maintenance Timelines – All the steps in the shutdown period, removal operations,

inspection and repair, reassembly, and startup are estimated. These time steps are summarized at

a high level in Table 2. Each time step was analyzed for the distance traveled, mass and shape of

the object transported, and the path and constraints observed. Appendix A contains the detail

time steps for all the actions shown in the summary chart. For example, there are 48 steps in the

Removal of the Main Port Opening to remove the main port bio shield door, remove the vacuum

vessel main port shielding assembly, and remove the main port blanket/shield/coolant manifold

assembly, which takes about 10 hours to complete. Table 2 shows all the governing steps along

with the other operations that are conducted in parallel with the governing operations. The

Shutdown and Preparation for Maintenance and removal of the Main Port Opening are singular

tasks that must be done each time interior power core maintenance is performed. Likewise, there

are similar operations on closing the power core and startup sequences. After access is provided

to the interior of the power core, the repetitive tasks commence, such as removal of the divertor

plates or modules and the blanket modules. The data shown in Table 2 is just summary times for

the sets of operations. Full detail of the sequence and durations of maintenance actions are

reported in the Appendix A.

The total disassembly time is 475 hours and the reassembly time is 753 hours. The time

difference is due to a slower movements and installation procedures. There is additional time for

inspection and checkout of components and systems. The total downtime is estimated to be 1230

hours every 3.0 full power years. This equates to an inherent availability of 95.5% for the power

core replaceable items.

Page 31

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Shutdown And Preparation For Maintenance. 30.00 7.40Removal Maintenance TasksRemoval of Main Port Opening 10.20Removal of ECH/ AUX. Port Opening 8.40Removal of Diverter Plate Inner Coolant Tubes 9.40Removal of Diverter Plates 20.40 6.40Blanket Shielding Blocks and Module Removal 240.50 39.00Shield Ring and Coolant Tube Removal 139.75Diverter Outer Coolant Tube Section Removal 8.80Shield and Support System Inspection and Repair 26.00 36.00TOTAL DISASSEMBLY TIME 475.65 106.60

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksDiverter Outer Coolant Tube Section Installation 14.40Shielding Ring and Coolant Tube Installation 230.75Blanket Shielding Blocks and Module Installation 429.00 39.00Replace of Diverter Plates 26.40 8.00NDI of Diverter Plates Welds 2.80Chamber Inspection 2.00 2.00NDI Robot Secured 0.55Main Port Closure 13.40Closure of ECH/AUX. Port Opening 10.00Replacement of Diverter Plate Inner Coolant Tubes 9.60Inspection, Diagnostics and Preparation for Operations 38.00 13.10TOTAL ASSEMBLY TIME 753.95 85.05

TOTAL DISASSEMBLY TIME 475.65 106.60TOTAL ASSEMBLY TIME 753.95 85.05TOTAL TIME 1,229.60 191.65

Full power years 3.00Number of Available Days 1,095.75

Number of Available Hours 26,298.00Nominal hours to replace three field periods 1,229.60

Inherent Availability 95.5%

ARIES Estimated Maintenance Times

KEYSOperational Tasks

Parallel/Simultaneous Tasks

Table 2. Summary of Scheduled Power Core Maintenance Times

The main time advantage of the maintenance scheme proposed in this approach is that there

are many simultaneous parallel operations. Table 3 shows a summary of the maintenance

actions that are being conducted in the main port, auxiliary port and the central bio chamber

manipulators. The shaded cells indicate which operations are governing and which are being

conducted in parallel or setting idle. The table illustrates that removing the shielding blocks to

gain access to the blanket coolant tubes and cutting the tubes is the most time consuming

operation. This is also true for the reconnection of the blanket coolant pipes and replacing the

Page 32

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

shielding blocks. The overall maintenance operation could significantly improve if the method

of blanket plumbing disconnection and reconnections were simpler and more accessible.

Table 3. Summary of maintenance actions with three types of maintenance equipment

Availability Analysis – With these durations of the scheduled maintenance periods for the

major scheduled actions for the power core, the plant availability is computed. With a total

scheduled time of 1229.6 hours or 51.12 days occurring every 3 FPY, this translates into an

annual maintenance time of 17.08 days/FPY or an inherent availability of 95.5%. To be

comparable with the ARIES-AT9 maintenance results, the maintenance estimates for the minor

scheduled power core, unscheduled power core, scheduled and unscheduled reactor plant

equipment, and scheduled and unscheduled balance of plant are adopted as shown in Table 4.

The resultant total power plant availability is 84.6%. This value of plant availability will be used

in the ARIES-CS Systems Assessment11. This is consistent with the experience of existing power

plants for the reactor plant and balance of plant inherent availabilities. This trend is expected to

Page 33

Main Port Shutdown Port Opening

Diverter Plates

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Diverter Outer

Coolant Tube

Shield & Support System

Insp.

Diverter Outer

Coolant Tube

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Diverter Plates

Chamber Inspection

Port Installation Start-Up

TaskShutdown &

Prep for Maint.

Open Three Main Maint.

Ports

Twenty-four Diverter

Plates (8 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Diverter Outer Coolant Tube (8x3 Sectors)

Inspect, Clean &

Vacuum - Inspect Repairs

Diverter Outer Coolant Tube (8x3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Twenty-four Diverter

Plates (8 x 3 Sectors)

Inspect Chamber

After Build-Up

Close Three Main Maint.

Ports

Inspect, Diagnostics &

Prep for Operation

Time (Hrs) 30.00 10.20 20.40 240.50 139.75 8.80 26.00 14.40 230.75 429.00 26.40 2.00 13.40 38.00

ECH/Aux Port Shutdown ECH Assembly

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Diverter Outer

Coolant Tube

Shield & Support System

Insp.

Diverter Outer

Coolant Tube

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Chamber Inspection

ECH Installation Start-Up

TaskShutdown &

Prep for Maint.

Remove Three ECH Assemblies

Shielding Blocks & Cut Weld (65x 6 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Diverter Outer Coolant Tube (8x3 Sectors)

Make Any Needed Repairs

Diverter Outer Coolant Tube (8x3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Shielding Blocks &

Welds (65x 6 x 3 Sectors)

Inspect Chamber

After Build-Up

Install Three ECH

Assemblies

Time (Hrs) 30.00 8.40 240.50 139.75 8.80 24.00 14.40 230.75 429.00 2.00 9.60 38.00

BIO-Chamber ShutdownDiverter Coolant Tubes

Diverter Plates

Shield & Support System

Insp.

Diverter Plates NDI Welds

Coolant Tubes

InstallationStart-Up

TaskShutdown &

Prep for Maint.

Twenty-four Coolant

Tubes (8 x 3 Sectors)

Cut Plates Coolant Tube Weld (8 x 3

Sectors)

Inspect Outside for Damage &

Repair

Weld Plates Coolant Tube

(8 x 3 Sectors)

Complete Coolant Tube Weld Inspect.

Twenty-four Coolant

Tubes (8 x 3 Sectors)

Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00Total Time (Hrs) Total Time (Hrs)

ECH

/Aux

iliar

y Po

rtM

ain

Port

Bio

-Cha

mbe

r

KEYSOperational Tasks

Parallel/Simultaneous Tasks

ARIES MAINTENANCE TASKS

Disassembly 475.65 Hrs. Replacement 753.95 Hrs.Total Maintenance Time 1,229.6 Hrs. Inherent Availability 95.5%

Removal Tasks Replacement Tasks

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

continue in this future time period. The scheduled minor power core maintenance will likely be

a fraction of the major scheduled maintenance times as much of the repair of these minor

components can be done off line. The most difficult issue is the prediction of unscheduled major

power core maintenance. A time of 20 days per year has been allocated for this purpose. If it is

assumed that on average, an unscheduled failure would require, on average, removal of one

fourth of the modules in a field period (one side of the main port and half of the modules on that

side would be replaced), the unscheduled time might be on the order of 16 days (accounting for

ingress and egress and half of component removal) per failure. Therefore the allocation of 20.56

days/FPY would be sufficient for a major failure each FPY with some additional time left over

for minor leaks that would be repairable in-situ.

Summary of Maintenance Actions Maintenance Days, Total

Maintenance Days/FPY

Availability

Scheduled Power Core, Major 51.23 17.08 95.5

Scheduled Power Core, Minor (ref ARIES-AT9) 6.05 98.4

Unscheduled Power Core (ref ARIES-AT9) 20.56 94.7

Reactor Plant Equipment, Scheduled + Unscheduled

(ref ARIES-AT9) 9.37 97.5

Balance of Plant, Scheduled + Unscheduled

(ref ARIES-AT9) 9.37 97.5

Total 84.6

Table 4. Summary of maintenance durations and inherent availability

Summary and Conclusions

Page 34

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

A conceptual design approach for the maintenance approach for the ARIES-Compact

Stellarator is defined to include the techniques to maintain the power core, the required

maintenance equipment, and associated maintenance facilities. Maintenance procedures to

remove, inspect, and replace life-limited power core components down to individual

maintenance actions are defined and estimates of action durations are estimated. These

procedures are analyzed for parallel and sequential operations to estimate the scheduled

maintenance times for power core refurbishment. These scheduled actions are combined with

representative maintenance times for unscheduled power core and total maintenance durations

for reactor plant equipment and balance of plant equipment as used in the ARIES-AT study to

determine the estimated plant availability for the ARIES-CS power plant. With the utilization of

the postulated maintenance approaches and procedures, it is predicted ARIES-CS could achieve

a plant availability of 85% with only one third of the unavailability caused by scheduled power

core maintenance. This availability would be in line with other competing base load power

generation capabilities and would help fusion power plants be economically competitive.

Page 35

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

References

. F. Najmabadi, et al, “Overview of ARIES-Compact Stellarator Power Plant Study”, to be published in this issue of Fusion Science and Technology Journal, 2007.

2. L.A. El-Guebaly, “Overview of ARIES-RS neutronics and radiation shielding: key issues and main conclusions,” Fus. Eng. and Des., 38 (1997) 139-158.

3. L. P. Ku, et al., “Physics Design of ARIES-CS”, to be published in this issue of Fusion Science and Technology Journal, 2007.

4. G. H. Neilson, M.C. Zarnstorff, L. P. Ku, et al., “Physics Considerations in the Design of NCSX,” 19th IAEA Fusion Energy Conference, Lyon, France, 14-19, October 2002

5. R. Raffray, et. al, “Engineering Design and Analysis of the ARIES-CS Power Core,” to be published in this issue of Fusion Science and Technology Journal, 2007.

6. X. R. Wang, S. Malang, et al., “ARIES-CS Magnet Conductor and Structure Evaluation,” to be published in this issue of Fusion Science and Technology Journal, 2007.

7. L. El-Guebaly, P. Wilson, and the ARIES Team, “Designing ARIES-CS Compact Radial Build and Nuclear System: Neutronics, Shielding, and Activation,” to be published in this issue of Fusion Science and Technology Journal, 2007.

8. S. Malang, F. Najmabadi, L.M. Waganer, and M.S. Tillack, “ARIES-RS Maintenance Approach for High Availability,” 4th International Symposium on Fusion Nuclear Technology, Tokyo, April 1997.

9. L. M. Waganer and the ARIES Team, “ARIES-AT Maintenance System Definitions and Analysis,” Fusion Engineering and Design Journal, 2001.

10. B. Merrill, L. El-Guebaly, C. Martin, “Safety and Environmental Assessment of the ARIES Compact Stellarator Design,” to be published in this issue of Fusion Science and Technology Journal, 2007.

11. J. F. Lyon, L-P. Ku, L. El-Guebaly, L. Bromberg, and the UCSD ARIES Team, “Determination of ARIES-CS Plasma and Device Parameters and Costing,” to be published in this issue of Fusion Science and Technology Journal, 2007.

Page 36

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Appendix A. Detailed ARIES-CS Maintenance Analysis

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Shutdown And Preparation For Maintenance.Cool down of systems, afterheat decay 24.00 De-energize coils, keep cryogenic 2.00 Pressurize power core with inert gas 2.00 Move Maint Machine(s) transport(s) to outer isolation door 1.00 Move mobile transporters to outer transfer airlock door(s) 1.00 Move ECH mobile transporters to outer transfer airlock doors. 1.00Drain Coolants, fill with inert gas 6.00 Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transfer chamber(s) 0.20 Close transfer chamber(s) outer main isolation door(s) 0.10

TOTAL 30.00 7.40

ARIES Estimated Maintenance Times

Page 37

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksRemoval of Main Port OpeningMove Maint Machine into position 0.10Move boom forward and engage bio-shield plug 0.10Remove and set aside bio-shield plug 0.50Retrieve and place bridging structure into place 0.30Move Maint Machine into position 0.10Move boom forward and engage vacuum seals on vacuum vessel door 0.10Disconnect vacuum seals around vacuum vessel door 2.00Disengage and remove vacuum vessel door 0.30Retract Maint Machine and set vacuum vessel door aside 0.20Move Maint Machine into position 0.10Move boom forward and engage post shield plug 0.10Disconnect post shield plug 0.20Remove port shield plug 0.30Retract Maint Machine set aside port shield plug(s) 0.50Move Maint Machine into position 0.10Move boom forward and engage manifold shield plug closure disk 0.10Disengage and remove removable manifold shield plug closure 0.20Retract boom with closure disk 0.10Retract Maint Machine and place close disk into transfer airlock and close airlock 0.10

Move Maint Machine into position 0.10Move boom forward and engage 1st inner coolant tube 0.10Disconnect and remove inner coolant tube via sliding joints 0.30Retract boom with inner coolant tube 0.10Retract Maint Machine and place inner coolant tube into transfer airlock and close airlock 0.10

Move Maint Machine into position 0.10Move boom forward and engage 2nd inner coolant tube 0.10Disconnect and remove inner coolant tube via sliding joints 0.30Retract boom with inner coolant tube 0.10Retract Maint Machine and place inner coolant tube into transfer airlock and close airlock 0.10

Move Maint Machine into position 0.10Move boom forward and insert cutting tool 0.10Cut assembly welds at second cut position 0.50Retract boom 0.10Move boom forward and insert cutting tool 0.10Cut assembly welds at second cut position (Second Location) 0.50Retract boom 0.10Move Maint Machine into position 0.10Move Maint Machine into port position and secure 0.10Move boom forward and position for removable manifold shield plug module removable 0.10Disengage removable manifold shield plug(s) modules 0.20Retract boom with removable manifold shield plug(s) modules 0.20Retract Maint Machine into transfer chamber with removable manifold shield plug's) modules 0.10Place removable manifold shield plug(s) modules into transfer airlock and close airlock 0.10Move Maint Machine into port position and secure 0.10Move boom forward and engage Shield and Blanket Modules 0.10Disengage Shield and Blanket Modules 0.30Retract boom with Shield and Blanket Modules 0.20Retract Maint Machine into transfer chamber with Shield and Blanket Modules 0.10

Place Shield and Blanket Modules into transfer airlock and close airlock 0.10

TOTAL 10.20

Page 38

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksRemoval of ECH/ AUX. Port Opening Move Maint Machine into position 0.10 Move boom forward and engage ECH coaxial cable 0.10 Disconnect ECH coaxial cable (two places) 0.40 Retract boom and set ECH coaxial cable aside 0.10 Move Maint Machine into position 0.10 Move boom forward and engage ECH shielding coolant tube 0.10 Disconnect ECH shielding coolant tube 0.30 Move boom and set ECH shielding coolant tube aside 0.10 Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transport(s) 0.10 Close transfer chamber(s) outer main isolation door(s) 0.10 Open transfer chamber(s) rear outer main isolation door(s) 0.10 Open ECH transporter(s) main isolation door(s) 0.10 Raise transfer chamber floor to expose ECH guide rails & conveyor 0.25

Using conveyor assembly retract ECH assembly into transfer chamber 3.00

Using conveyor assembly insert ECH assembly into ECH mobile transporter(s) 2.50 Close ECH transporter(s) main isolation door(s) 0.10 Close transfer chamber(s) rear outer main isolation door(s) 0.10 Lower transfer chamber floor to cover ECH guide rails & conveyor 0.25 Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transfer chamber(s) 0.20 Close transfer chamber(s) outer main isolation door(s) 0.10

TOTAL 8.40

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksRemoval of Diverter Plate Inner Coolant Tubes Move remote handling manipulator over coolant tube opening. 0.10 Remove locking device securing coolant tube covering. 0.20 Open coolant tube cover. 0.05 Position remote handling manipulator inside coolant tube. 0.05 Move and disengage coolant tube sliding ring. 0.10 Secure inner coolant tube turn elbow. 0.10 Disengage inner coolant tube elbow. 0.15 Remove inner coolant tube elbow from coolant tube. 0.10 Move remote handling manipulator to transfer airlock door. 0.10 Open transfer airlock door. 0.05 Place inner coolant tube elbow into airlock. 0.10 Close transfer airlock door. 0.05 Move remote handling manipulator over coolant tube opening. 0.10 Position remote handling manipulator inside coolant tube. 0.10 Secure inner coolant tube. (tube, shielding block & shielding ring) 0.10 Disengage inner coolant tube. 0.30 Remove inner coolant tube from coolant tube. 0.25 Move remote handling manipulator to transfer airlock door. 0.10 Open transfer airlock door. 0.05 Place inner coolant tube into airlock. 0.15 Close transfer airlock door. 0.05

TOTAL 2.35

Repeat above sequence of steps for 3 additional coolant tubes. Total repetitive time = 3 x 2.35 Hr. 7.05 (NOTE: There are a total of 24 coolant tubes)

TOTAL 7.05

Page 39

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksRemoval of Diverter PlatesMove remote handling manipulator to transfer airlock door. 0.10Open transfer airlock door. 0.05Secure bore tool (weld cutting) robot. 0.10Close transfer airlock door. 0.05Move remote handling manipulator over coolant tube opening. 0.10 Move Maint Machine into port position and secure 0.10Position bore tool (weld cutting) robot inside coolant tube. 0.10 Move boom forward and position over diverter plate. 0.10Move bore tool (weld cutting) robot to assembly weld of coolant tube. 0.20 Move boom forward engage and secure diverter plate. 0.10Position bore tool (weld cutting) robot and cut assembly weld. 1.25Disengage bore tool (weld cutting) robot and retract. 0.20 Retract boom with removed diverter shield 0.20Secure bore tool (weld cutting) robot. 0.10 Retract Maint Machine into transfer chamber with diverter plate. 0.10Move remote handling manipulator to transfer airlock door. 0.10 Place diverter plate into transfer airlock and close airlock 0.20Open transfer airlock door. 0.05Place bore tool (weld cutting) robot into air lock. 0.10Close transfer airlock door. 0.05

TOTAL 2.55 0.80

Repeat above sequence of steps for 7 additional diverter plates. Total repetitive time = 7 x 2.55 Hr. 17.85 5.60 (NOTE: There are a total of 24 coolant tubes)

TOTAL 17.85 5.60

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksBlanket Shielding Blocks and Module RemovalMove Maint Machine into port position and secure 0.10 Move Maint Machine into port position and secure 0.10Move boom forward and position over blanket module inside chamber 0.20 Move boom forward and position & remove shielding block #1 0.20Move boom forward and engage blanket module 0.20 Retract boom and place shielding block #1 into transfer bucket 0.10Move boom forward and position & remove shielding block #2. 0.20Retract boom and place shielding block #2 into transfer bucket 0.10Move boom forward and position & remove shielding block #3. 0.30Retract boom and place shielding block #3 into transfer bucket 0.10Move boom forward into position and cut access pipe #1 0.50Move boom forward and position & remove shielding block #1 0.20Retract boom and place shielding block #1 into transfer bucket 0.10Move boom forward and position & remove shielding block #2. 0.20Retract boom and place shielding block #2 into transfer bucket 0.10Move boom forward and position & remove shielding block #3. 0.30Retract boom and place shielding block #3 into transfer bucket 0.10Move boom forward into position and cut access pipe #2 0.50 Disengage blanket module/diverter shield to be replaced 0.20Retract boom clear of blanket module & pick up transfer bucket 0.10Retract boom with removed blanket module 0.20 Retract boom with transfer bucket 0.20Retract Maint Machine into transfer chamber with blanket module 0.10 Retract Maint Machine into transfer chamber with transfer bucket 0.10Place blanket module into transfer airlock and close airlock 0.10Place transfer bucket into transfer airlock and close airlock 0.10

TOTAL 3.70 0.60

Repeat above sequence of steps for 64 blanket modules Total repetitive time = 64 x 3.70 Hr. 236.80

TOTAL 236.80 38.40

Page 40

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksShield Ring and Coolant Tube RemovalMaint Machine secures Shielding Rings transfer bucket 0.10Move Maint Machine into port position and secure 0.10Move boom forward and place bucket inside chamber 0.20Move boom forward and position over 1st inner coolant tube 0.10Move boom forward and engage inner coolant tube 0.10Disengage inner coolant tube 0.10Retract boom and place inner coolant tube into transfer bucket 0.10Move boom forward into position over shielding ring 0.10Insert cutting tool and make second cut of shielding ring 0.50Retract cutting tool and engage shielding ring 0.10Move boom and place shielding ring into transfer bucket 0.10Move boom into position over removed shielding ring 0.10Insert tool to clean and inspect area 0.30Retract tool 0.10Move boom forward and position over 2nd inner coolant tube 0.10Move boom forward and engage inner coolant tube 0.10Disengage inner coolant tube 0.10Retract boom and place inner coolant tube into transfer bucket 0.10Move boom forward into position over shielding ring 0.10Insert cutting tool and make second cut of shielding ring 0.50Retract cutting tool and engage shielding ring 0.10Move boom and place shielding ring into transfer bucket 0.10Move boom into position over removed shielding ring 0.10Insert tool to clean and inspect area 0.30Retract tool 0.10Move boom engage and secure transfer bucket 0.10Retract boom with transfer bucket 0.20Retract Maint Machine into transfer chamber with transfer bucket 0.10Place transfer bucket into transfer airlock and close airlock 0.10

TOTAL 4.30

Repeat above sequence of steps for 31.5 sets Total repetitive time = 31.5 x 4.30 Hr. 135.45

TOTAL 135.45

Page 41

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Removal Maintenance TasksDiverter Outer Coolant Tube Section RemovalMaint Machine secures Diverter Outer Coolant Tube transfer bucket 0.10Move Maint Machine into port position and secure 0.10Move boom forward and place bucket inside chamber 0.20Move boom forward into position over Diverter Outer Coolant Tube 0.10Insert cutting tool and make second cut of Diverter Outer Coolant Tube 0.50Retract cutting tool and engage Diverter Outer Coolant Tube 0.10Move boom and place Tube Section into transfer bucket 0.10Move boom into position over removed Diverter Outer Coolant Tube 0.10Insert tool to clean and inspect area 0.30Retract tool 0.10Move boom engage and secure transfer bucket 0.10Retract boom with transfer bucket 0.20Retract Maint Machine into transfer chamber with transfer bucket 0.10Place transfer bucket into transfer airlock and close airlock 0.10

TOTAL 2.20

Repeat above sequence of steps for 3 additional coolant tubes. Total repetitive time = 3 x 2.20 Hr. 6.60

TOTAL 6.60

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Shield and Support System Inspection and RepairInspection of shield for damage and displacement, record data 12.00 Inspection of outside for damage and displacement, record data 12.00 Allocate time for potential repair of fasteners, alignment features, 24.00 and plumbing connections.Clean and/or vacuum interior of reactor from teardown of interior 12.00Repair Inspection 2.00

TOTAL 26.00 36.00

TOTAL DISASSEMBLY TIME 475.65 106.60

Page 42

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksDiverter Outer Coolant Tube Section InstallationRetrieve transfer bucket from transfer airlock and close airlock 0.10Move Maint Machine into port position and secure 0.10Move boom forward and place bucket inside chamber 0.20Move boom and secure diverter outer coolant tube section 0.10Move boom forward and place diverter outer coolant tube into opening 0.10Move boom to ensure tube section is fully and properly seated 0.10Holding tube section in place using boom tack weld in place 0.20Retract boom and insert welding tool 0.10Weld diverter outer tube section into position at second cut position 0.75Retract welding tool and allow weld to cool 0.20Inset inspection/NDI tool 0.10Inspect shielding ring weld 0.25Remove inspection/NDI tool 0.10Insert grinding tool and clean up weld as required 0.20Remove grinding tool 0.10Move boom forward to inspect and clean area 0.20Retract boom 0.10Retract boom 0.10Retrieve and secure transfer bucket 0.10Retract boom with transfer bucket 0.20Retract Maint Machine into transfer chamber with transfer bucket 0.10Place transfer bucket into airlock and close airlock 0.10

TOTAL 3.60

Repeat above sequence of steps for 3 additional coolant tubes. Total repetitive time = 3 x 3.610 Hr. 10.80

TOTAL 10.80

Page 43

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksShielding Ring and Coolant Tube InstallationRetrieve transfer bucket from transfer airlock and close airlock 0.10Move Maint Machine into port position and secure 0.10Move boom forward and place bucket inside chamber 0.20Move boom and secure shielding ring 0.10Move boom forward and place shielding ring into 1st opening 0.10Move boom to ensure shielding ring is fully and properly seated 0.10Holding shielding ring in place using boom tack weld in place 0.20Retract boom and insert welding tool 0.10Weld shielding ring into position at second cut position 0.75Retract welding tool and allow weld to cool 0.20Inset inspection/NDI tool 0.10Inspect shielding ring weld 0.25Remove inspection/NDI tool 0.10Insert grinding tool and clean up weld as required 0.20Remove grinding tool 0.10Move boom forward to inspect and clean area 0.20Retract boom 0.10Retrieve inner coolant tube from transfer bucket 0.10Move boom forward and install coolant tube into position 0.20Move boom to ensure coolant tube is fully and properly seated 0.10Retract boom 0.10Retrieve and secure 2nd shielding ring 0.10Move boom forward and place shielding ring into 2nd opening 0.10Move boom to ensure shielding ring is fully and properly seated 0.10Holding shielding ring in place using boom tack weld in place 0.20Retract boom and insert welding tool 0.10Weld shielding ring into position at second cut position 0.75Retract welding tool and allow weld to cool 0.20Inset inspection/NDI tool 0.10Inspect shielding ring weld 0.25Remove inspection/NDI tool 0.10Insert grinding tool and clean up weld as required 0.20Remove grinding tool 0.10Move boom forward to inspect and clean area 0.20Retract boom 0.10Retrieve inner coolant tube from transfer bucket 0.10Move boom forward and install coolant tube into position 0.20Move boom to ensure coolant tube is fully and properly seated 0.10Retract boom 0.10Retrieve and secure transfer bucket 0.10Retract boom with transfer bucket 0.20Retract Maint Machine into transfer chamber with transfer bucket 0.10Place transfer bucket into airlock and close airlock 0.10

TOTAL 7.10

Repeat above sequence of steps for 31.5 sets Total repetitive time = 31.5 x 7.10 Hr. 223.65

TOTAL 223.65

Page 44

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksBlanket Shielding Blocks and Module InstallationRetrieve new blanket module from transfer chamber and close airlock 0.10 Retrieve shielding blocks transfer bucket from transfer chamber and close air lock 0.10Move Maint Machine into port position and secure 0.10 Move Maint Machine into port position and secure 0.10Move boom forward and position blanket module inside chamber 0.20 Move boom forward and place transfer bucket inside chamber 0.20Engage and secure new blanket module. 0.20Move boom forward and position welding tool at 1st cut position 0.20Weld blanket module to shielding ring 0.75Retract welding tool 0.10Move boom forward and position welding tool at 1st cut position 0.20Weld blanket module to shielding ring 0.75Retract welding tool 0.10Move boom forward and insert inspection/NDI tool (1st Weld) 0.10Inspect first weld 0.25Remove Inspection/NDI tool 0.10Move boom forward and insert inspection/NDI tool (2nd Weld) 0.10Inspect first weld 0.25Remove Inspection/NDI tool 0.10Retract boom 0.10Move boom forward and retrieve shielding block #3 0.10Move boom forward and position shielding block #3 at opening 0.10Insert shielding block #3 into position 0.25Retract boom 0.10Move boom forward and retrieve shielding block #2 0.10Move boom forward and position shielding block #2 at opening 0.10Insert shielding block #2 into position 0.10Retract boom 0.10Move boom forward and retrieve shielding block #1 0.10Move boom forward and position shielding block #1 at opening 0.10Insert shielding block #1 into position 0.10Retract boom 0.10Move boom forward and retrieve shielding block #3 0.10Move boom forward and position shielding block #3 at opening 0.10Insert shielding block #3 into position 0.25Retract boom 0.10Move boom forward and retrieve shielding block #2 0.10Move boom forward and position shielding block #2 at opening 0.10Insert shielding block #2 into position 0.10Retract boom 0.10Move boom forward and retrieve shielding block #1 0.10Move boom forward and position shielding block #1 at opening 0.10Insert shielding block #1 into position 0.10Retract boom 0.10Disengage boom from blanket module 0.10 Move boom forward and retrieve transfer bucket 0.10Retract boom 0.10 Retract boom 0.10

TOTAL 6.60 0.60

Repeat above sequence of steps for 64 blanket modules Total repetitive time = 64 x 6.60 Hr. 422.40

TOTAL 422.40 38.40

Page 45

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksReplace of Diverter PlatesMove remote handling manipulator to transfer airlock door. 0.10 Move Maint Machine in front of airlock 0.10Open transfer airlock door. 0.05 Open transfer airlock 0.10Secure bore tool (welding & NDI) robots. 0.10 Secure diverter plate 0.10Close transfer airlock door. 0.05 Close transfer airlock 0.10Move remote handling manipulator over coolant tube opening. 0.10 Move Maint Machine into port position and secure 0.10Position bore tool (welding) robot inside coolant tube. 0.10 Move boom forward and position diverter plate. 0.10Move bore tool (welding) robot to assembly weld of coolant tube. 0.20 Move boom forward set diverter plate in place. 0.10Position bore tool (welding) robot and make assembly weld. 2.30Disengage bore tool (welding) robot and retract. 0.20 Disengage and retract boom 0.20Secure bore tool (welding) robot. 0.10 Retract Maint Machine into transfer chamber 0.10

TOTAL 3.30 1.00

Repeat above sequence of steps for 7 additional diverter plates. Total repetitive time = 7 x 3.30 Hr. (NOTE: There are a total of 24 coolant tubes)

TOTAL 23.10 7.00

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksNDI of Diverter Plates WeldsMove remote handling manipulator over coolant tube opening. 0.10Position bore tool (NDI) robot inside coolant tube. 0.10Move bore tool (NDI) robot to assembly weld of coolant tube. 0.20Position bore tool (NDI) robot and make assembly weld. 0.10Position bore tool (NDI) robot and inspect assembly weld. 2.00Disengage bore tool (NDI) robot and retract. 0.20Secure bore tool (NDI) robot. 0.10

TOTAL 2.80

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksChamber InspectionAfter Maintenance Inspection of chamber 2.00 After Maintenance Clean-Up & Repair (If Required) 2.00

TOTAL 2.00 2.00

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksNDI Robot SecuredMove remote handling manipulator over coolant tube opening. 0.10Secure bore tool (NDI) robot. 0.10 Move remote handling manipulator to transfer airlock door. 0.10 Open transfer airlock door. 0.05 Place inner coolant tube into airlock. 0.15 Close transfer airlock door. 0.05

TOTAL 0.55

Page 46

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksMain Port Closure

Retrieve Shield & Blanket Modules from transfer airlock and close airlock 0.10

Move Maint Machine into port position and secure 0.10Move boom forward and position Shield & Blanket Module 0.20Engage and secure Shield & Blanket Module 0.30Disengage and retract boom 0.10Retract Maint Machine into transfer chamber 0.10Retrieve removable manifold shield plug module from transfer airlock and close airlock 0.10

Move Maint Machine into port position and secure 0.10Move boom forward and position removable manifold shield plug 0.30Engage and secure removable manifold shield plug 0.20Disengage and retract boom 0.10Insert welding tool into removable manifold shield closure disk opening 0.10Weld 1st removable shield ring to coolant manifold 0.75Retract welding tool 0.10Insert welding tool into removable manifold shield closure disk opening 0.10Weld 2nd removable shield ring to coolant manifold 0.75Retract welding tool 0.10Insert inspection/NDI tool into removable manifold shield closure disk opening 0.10

Inspect first weld assembly 0.25Retract inspection/NDI tool 0.10Insert inspection/NDI tool into removable manifold shield closure disk opening 0.10

Inspect second weld assembly 0.25Retract inspection/NDI tool 0.10Retract Maint Machine into transfer chamber 0.10Retrieve 1st inner coolant tubes from transfer airlock and close airlock 0.10Move Maint Machine into port position and secure 0.10Move boom forward and position inner coolant tube 0.20Engage and secure inner coolant tube via sliding joint 0.30Retract boom 0.10Retract Maint Machine into transfer chamber 0.10Retrieve 2nd inner coolant tubes from transfer airlock and close airlock 0.10Move Maint Machine into port position and secure 0.10Move boom forward and position inner coolant tube 0.20Engage and secure inner coolant tube via sliding joint 0.30Retract boom 0.10Retract Maint Machine into transfer chamber 0.10Retrieve removable manifold shield plug closure disk from transfer airlock and close airlock 0.10

Move Maint Machine into port position and secure 0.10Move boom forward and position closure disk 0.20Engage and secure closure disk 0.20Disengage and retract boom 0.10Retract Maint Machine into transfer chamber 0.10Retrieve port shield plug 0.10Move Maint Machine into position and insert port shield plug 0.20Engage and secure port shield plug into position 0.40Retract Maint Machine into transfer chamber 0.10Retract Maint Machine into transfer chamber 0.10Retrieve Vacuum Vessel Door 0.10Move Maint Machine into position and insert vacuum vessel door 0.20Engage and secure vacuum vessel door 0.40Disengage and retract boom 0.10Connect and secure vacuum seals around vacuum vessel door 3.00Retract boom 0.10Retract Maint Machine into transfer chamber 0.10Retrieve and place bridging structure inside transfer chamber 0.30Retrieve and place bio-shield plug into position 0.50Disengage and secure boom 0.10Open transfer chamber(s) outer main isolation door(s) 0.10Move Maint Machine(s) into transporter(s) 0.20Close transfer chamber(s) outer main isolation door(s) 0.10

TOTAL 13.40

Page 47

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksClosure of ECH/AUX. Port Opening Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transporter(s) 0.20 Close transfer chamber(s) outer main isolation door(s) 0.10 Raise transfer chamber floor to expose ECH guide rails & conveyor 0.25 Open transfer chamber(s) rear outer main isolation door(s) 0.10 Open ECH transporter(s) main isolation door(s) 0.10

Using conveyor assembly retract ECH assembly from ECH mobile Transporter(s) into transfer chamber

2.50

Using conveyor assembly insert ECH assembly into ECH opening 4.00 Close ECH transporter(s) main isolation door(s) 0.10 Close transfer chamber(s) rear outer main isolation door(s) 0.10 Lower transfer chamber floor to cover ECH guide rails & conveyor 0.25 Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transfer chamber(s) 0.20 Close transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine into position 0.10 Move boom forward engage & secure ECH coaxial cable 0.10 Move boom forward and position ECH coaxial cable 0.10 Connect ECH coaxial cable (two places) 0.40 Disengage & retract boom. 0.10 Move Maint Machine into position 0.10 Move boom forward engage & secure ECH shielding coolant tube 0.10 Move boom forward and position ECH shielding coolant tube 0.10 Connect ECH shielding coolant tube 0.30 Disengage & retract boom. 0.10 Open transfer chamber(s) outer main isolation door(s) 0.10 Move Maint Machine(s) into transport(s) 0.10 Close transfer chamber(s) outer main isolation door(s) 0.10

TOTAL 10.00

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Replacement Maintenance TasksReplacement of Diverter Plate Inner Coolant Tubes Move remote handling manipulator to transfer airlock door. 0.10 Open transfer airlock door 0.05 Secure inner coolant tube (tube, shielding block & shielding ring). 0.15 Close transfer airlock 0.05 Move remote handling manipulator over coolant tube opening. 0.10 Position inner coolant tube inside coolant tube. 0.25 Move remote handling manipulator forward & secure inner coolant tube. 0.35 Disengage and retract remote handling manipulator 0.10 Move remote handling manipulator to transfer airlock door. 0.10 Secure inner coolant tube turn elbow. 0.10 Move remote handling manipulator over coolant tube opening. 0.10 Position inner coolant tube turn elbow inside coolant tube. 0.10 Secure inner coolant tube turn elbow to inner coolant tube. 0.20 Release inner coolant tube turn elbow 0.10 Move and engage inner coolant tube sliding ring. 0.10 Retract remote handling manipulator 0.10 Move remote handling manipulator over coolant tube opening. 0.10 Close coolant tube cover. 0.05 Securing coolant tube cover locking device. 0.20

TOTAL 2.40

Repeat above sequence of steps for 3 additional coolant tubes. Total repetitive time = 3 x 2.40 Hr. (NOTE: There are a total of 24 coolant tubes)

TOTAL 7.20

Page 48

ARIES-CS Maintenance System Final ReportWaganer, 05/10/23, 3:07 PM

Duration of Serial Subtotal for Set Duration of ParallelMaintenance Task(s) Operations, Hours of Operations, Hours Operations, Hours

Inspection, Diagnostics and Preparation for OperationsPressurize coolant systems and test with test gas for leaks 4.00Evacuate power core interior 10.00 Initiate trace or helium heating 10.00 Pick up VV door, move into position, and secure 0.30 Reestablish vacuum door seal 2.00 Acquire port bio shield door, align, and move into position 0.50 Remove maintenance machine from transfer chamber 0.20 Close transfer chamber outer main isolation door 0.10Fill power core coolants 8.00Bake out (clean) power core chamber 12.00Check out and power up systems 4.00

TOTAL 38.00 13.10

TOTAL ASSEMBLY TIME 753.95 85.05

TOTAL DISASSEMBLY TIME 475.65 106.60TOTAL ASSEMBLY TIME 753.95 85.05TOTAL TIME 1,229.60 191.65

Full power years 3.00Number of Available Days 1,095.75

Number of Available Hours 26,298.00Nominal hours to replace three field periods 1,229.60

Inherent Availability 95.5%

Page 49