Project: Tsolum River Spirit Park - Armoured Ford
Access type: Pedestrian, Horses and ATV's
Date: 11-Nov-04
NOTE: For preliminary planning only - Detailed field measurements are needed prior to project commencement
…………… Page one
…………… Page two
…………… Page three
…………… Page four
…………… Page five
…………… Page six
…………… Page seven
…………… Page eight
…………… Page nine
…………… Page ten
APPENDIX 2 - Stream sizing calculator …………… Page eleven
APPENDIX 3 - Example - Sediment control management at a stream crossing …………… Page eleven
…………… Page twelve
…………… Page thirteen
…………… Page fourteen
.
Copyright: 2000, 2001, 2002, 2003, 2004, 2005 - Eric L Kay
MACHINERY AND LABOUR REQUIREMENTS (continued)
APPENDIX 1 - Trucking Calculator Work-sheet
For additional information on armoured fords, see page 9
APPENDIX 4 - Ford shape and engineering guide
MOBILIZATION / DE-MOBILIZATION
BLANK
APPENDIX 5 - Ford concept drawing - 3D view
APPENDIX 6 - Ford concept drawing - Plan/Elevation View
DATA ENTRY
Armoured Ford - Construction Calculator
Utilizing Armour Rock or Flexible Concrete Revetment (Armoured Concrete Block)
BIO-ENGINEERING MATERIALS AND LABOUR REQUIREMENTS
MATERIALS CALCULATOR
I N D E X
MATERIALS LIST AND COSTS
MACHINERY AND LABOUR REQUIREMENTS
I N D E X
ARMOURED FORD using Flexible Concrete Revetment (Armoured Concrete Block)
Designed and intended to minimize environmental damage and detrimental effects to a streams ecosystem by constructing
an armoured stream crossing where one or a combination of the following conditions exists;
1) POOR AVAILABILITY OF MATERIALS
- Rock rip-rap (armour) is not readily available.
2) HIGH COST OF MATERIALS
- Cost of generating rock is costly. (eg drilling and blasting)
- Transporting rock to the site is costly. (eg long hauling distances and/or poor road conditions)
3) ACCESS TIMES COSTLY
- Access for heavy machinery to the site is costly. (eg long hauling distances and/or poor road conditions)
4) ACCESS FOR TRUCKS AND MACHINERY LIMITED or RESTRICTED
- Transporting rock to the site is not possible. (eg road condition is poor or unsafe or in the event access is restricted due to road failure or failed
bridges etc.)
- Access for heavy machinery to the site is not possible. (eg road condition is poor or unsafe or in the event access is restricted due to road failure
or failed bridges etc.)
Prepared by: Eric L Kay
Kay and Associates www.kayassociates.com
Eric L Kay Associates Ford Construction Calculator V15.xls Page 1 of 14
Page two
Ford Construction Calculator
DATA ENTRY unit
STREAM CHARACTERISTICS
Stream width (active) Bank Full Width 5 meter(s) 100 mm 1,000 mm 800 mm
Stream flank flood apron width - LEFT 5 meter(s) 100 mm 800 mm 800 mm
Stream flank flood apron width - RIGHT 5 meter(s) 100 mm 800 mm 800 mm
Stream discharge fall width 0 meter(s) 100 mm 1,000 mm 800 mm
Stream discharge energy dissipator apron width 1 meter(s) 100 mm 1,000 mm 800 mm
Stream bed slope (percent) 2 percent
Heel in width - Upstream side 0.5 meter(s) 100 mm 1,000 mm 800 mm
Heel in width - Downstream side 0.5 meter(s) 100 mm 1,000 mm 800 mm
Ditchline length to shape - LEFT
Ditchline length to shape - RIGHT
Ditchline length to armour - LEFT 0 meter(s) 100 mm 300 mm 150 mm
Ditchline length to armour - RIGHT 0 meter(s) 100 mm 300 mm 150 mm
Running surface Outlsope/Inslope - Minimum (percent) 2 percent
Running surface Outlsope/Inslope - Maximum (percent) 5 percent
ROAD CHARACTERISTICS
Road width reguirement for expected traffic 1.4 meter(s)
Road approach apron length - LEFT 2 meter(s) 100 mm 600 mm 100 mm
Road approach apron length - RIGHT 2 meter(s) 100 mm 600 mm 100 mm
Heel in width - road approach apron - LEFT 0 meter(s) 100 mm 1,000 mm 800 mm
Heel in width - road approach apron - RIGHT 0 meter(s) 100 mm 1,000 mm 800 mm
Road approach apron Left steepness (percent) 10 percent
Road approach apron Right steepness (percent) 10 percent
Road approach to ford area left steepness (percent) 6 percent
Road approach to ford area right steepness (percent) 6 percent
Approach road surface sediment cross drain - LEFT no logical Y/N (EG cross drain onto vegetated area)
Approach road surface sediment cross drain - RIGHT no logical Y/N (EG cross drain onto vegetated area)
Bedding materials required under ACB,s? yes logical Y/N (Eg. Coarse sands)
(only if leveling of native materials is impractical)
Fill materials required between ACB's? yes logical Y/N (Eg. No native coarse gravels on site)
20% void between blocks, fill with coase native gravels
`
NOTE; 'Heel-in' may also be commonly referred to as; 'rounding down', 'rolling-in' and other terms. See diagrams for
further details. Ensure that the 'heeled-in' design depth be sufficiently below the anticipated scour depth eg. Erosion
during a peak high-water event (flood) or the natural movement of stream-bed materials. A minimum depth of 1 meter is
recommended.
(minus)
size
block
thicknessthickness
Rock
(note: views LEFT/RIGHT are looking up the stream)
ACB;s RockMeas-
urem-
entrip-rap
Eric L Kay Associates Ford Construction Calculator V15.xls Page 2 of 14
Page three
Ford Construction Calculator
(note: views LEFT/RIGHT are looking up the stream)
MATERIALS CALCULATOR
Quantities and Volumes
Stream width (active) Bank Full Width 7 sq meters 7 sq meters 7 cu meters
Stream flank flood apron width - LEFT 7 sq meters 7 sq meters 5.6 cu meters
Stream flank flood apron width - RIGHT 7 sq meters 7 sq meters 5.6 cu meters
Stream discharge fall width 0 sq meters 0 sq meters 0 cu meters
Stream discharge energy dissipator apron width 1.4 sq meters 1.4 sq meters 1.4 cu meters
Heel in width - Upstream side 0.7 sq meters 0.7 sq meters 0.7 cu meters
Heel in width - Downstream side 0.7 sq meters 0.7 sq meters 0.7 cu meters
Ditchline length to shape - LEFT
Ditchline length to shape - RIGHT
Ditchline length to armour - LEFT 0 sq meters 0 sq meters 0 cu meters
Ditchline length to armour - RIGHT 0 sq meters 0 sq meters 0 cu meters
Road approach apron length - LEFT 2.8 sq meters 2.8 sq meters 1.68 cu meters
Road approach apron length - RIGHT 2.8 sq meters 2.8 sq meters 1.68 cu meters
Heel in width - road approach apron - LEFT 0 sq meters 0 sq meters 0 cu meters
Heel in width - road approach apron - RIGHT 0 sq meters 0 sq meters 0 cu meters
TOTAL VOLUME MATERIALS 29.4 sq meters 29.4 sq meters 24.36 cu meters
Bedding materials required under ACB,s?
(only if leveling of native materials is impractical) yes logical Y/N
Bedding material : SandDepth : 150 mm
Volume required : 4.41 cu meters
Fill materials required between ACB's?
20% void between blocks, fill with coase native gravels yes logical Y/N
Bedding material : Coarse gravel or 1" minus crushDepth : 100 mm
Volume required : 2.94 cu meters
For assistance in calculating site-specific dimensions contact Eric L Kay at [email protected]
(not required for rock)
Flexible Concrete
Revetment / Armoured
Concrete Block (ACB's)
Armour Rock (ROCK) Well-
graded material that has a specified size range
calculated with reference to expected water energy
forces. eg. 100mm-400mm
ROCK
ACB;s ROCK
ACB;s
Eric L Kay Associates Ford Construction Calculator V15.xls Page 3 of 14
Page four
Ford Construction Calculator
MATERIALS LIST AND COSTS
ACB's Cost extension
ACB;s Blocks 29.4 Sq meters 40.00$ 1,176.00$
Woven Geotextile Fabric 29.4 Sq meters 2.00$ 58.80$
Trucking - Plant to staging point 0 -$
Trucking - Staging point to jobsite 1 hours 75.00$ -$
Helicopter - Staging point to jobsite hours 1,200.00$ -$
Machine time to move blocks on site 0 hours 85.00$ -$
Bedding materials required under ACB,s? yes logical Y/N
Bedding material : Sand
Depth : 150 mm
Volume required : 4.41 cu meters 12.00$ 52.92$
Fill materials required between ACB's?
20% void between blocks, fill with coase native gravels yes logical Y/N
Bedding material : Coarse gravel or 1" minus crush
Depth : 100 mm
Volume required : 2.94 cu meters 16.00$ 47.04$
Trucking for bedding & fill materials 1 hr Round trip
Truck capacity : 11 cu meters
Trucking hours required : 1.0 hours 55.00$ 55.00$
ACB's COSTS 1,389.76$
ROCK (volume required) 24.36 cu meters
From existing Rock Quarry
Drilling and blasting costs cu meters 4.00$ -$
Machine time to sort and load hrs excavator 135.00$ -$ Mob and demob for drill and blasting -$
Mob and demob for loading excavator -$
Purchased from a Rock Quarry cu meter
Large Rip-Rap 0 20.00$ -$
Sorted and graded 54 cu meters 25.00$ 1,350.00$ Other
Trucking of rock
Round trip time : 5 hr Round trip
Truck capacity : 9 cu meters
Trucking hours required : 15.0 hours 75.00$ 1,125.00$
ROCK COSTS 2,475.00$
For costs on Articulated Concrete Blocks, contact your local supplier
Note: Trilock block cost below is an
approximation only.
Please see your local distributor for
pricing for your particular job.
Eric L Kay Associates Ford Construction Calculator V15.xls Page 4 of 14
Page five
Ford Construction Calculator (continiued on page 6)
(hours) (24" 300lb)
Vibratory
Flatdeck plate
Excavator with Hiab compactor
Shape Stream width (active) Bank Full Width 1.0 hr
Shape Stream flank flood apron width - LEFT .5 hr
Shape Stream flank flood apron width - RIGHT .5 hr
Shape Stream discharge fall width .1 hr
Shape Stream discharge energy dissipator apron width .1 hr
Excavate Heel in width - Upstream side .5 hr
Excavate Heel in width - Downstream side .5 hr
Shape Road approach apron length - LEFT .5 hr
Shape Road approach apron length - RIGHT .1 hr
Excavate Heel in width - road approach apron - LEFT .1 hr
Excavate Heel in width - road approach apron - RIGHT .1 hr
Shape Approach road surface sediment cross drain - LEFT .0 hr
Shape Approach road surface sediment cross drain - RIGHT .0 hr
Place Bedding material for ACB;s blocks 1.0 hr
Shape Ditchlines 1.0 hr
Place Geotextile fabric (Non-woven) for rock installation
Place Geotextile fabric (woven) for ACB;s installationPlace ACB;s blocks
Backfill "Heel-in" areas of ACB;s installation 1.0 hr
Compact "Heel-in" areas of ACB;s installation 4.0 hr
Fill in ACB;s Interspace areas 1.0 hr
labour Spreading and leveling sand baselabour Keep ground moisture content correct for compacting
labour Operating vibrator compactor - base preparation 8.0 hr
labour Operating vibrator compactor - 'heel-in' areasLabour/Excavator Install and monitor water diversion channel
labour Stream damming for pumping around
labour Install pumps for pumping around
labour Monitor and keep pumps operating
Excavator Spreading and placing of gravel fill (voids in between ACB's 4.0 hrExcavator Placing of rock armour (large rip-rap) .0 hr 10.0 hr
(hours) (24" 300lb)
Vibratory
Flatdeck plate
Excavator with Hiab compactor
TOTALS: 12 0 22
Hourly RATE: 125.00$ 85.00$ 12.00$
Extension: 1,500.00 - 264.00
For assistance in estimating labour and machine times, contact your local Articulated Concrete Block Supplier or Eric L
Kay at [email protected]
Action wo
MACHINERY AND LABOUR REQUIREMENTS
Average of 6.25sq m per man
per hour to lay fabric and
place trilock blocks.
Eric L Kay Associates Ford Construction Calculator V15.xls Page 5 of 14
Page six MACHINERY AND LABOUR REQUIREMENTS (continued)
(contiued from page 6)
Pump for Dewatering Sandbags 4 man
maintaining Pump for stream crew
dampness for (state size diversion Hand Rock/gravel
compaction and quantity) labour truck
.0 hr
4.7 hr.0 hr
4.0 hr1.0 hr
2.0 hr
2.0 hr2.0 hr
1.0 hr
1.0 hr
1.0 hr
4.0 hr
Pump for Dewatering Sandbags 4
maintaining Pump for stream man crew
dampness for (state size diversion Hand Rock/gravel
compaction and quantity) 0 labour truck
0 0 0 26.7 0
10.00$ 12.00$ 35.00$ 125.00$
- - - 3,738.56 -
For assistance in estimating labour and machine times, contact your local Articulated Concrete Block Supplier or Eric L
Kay at [email protected]
work times per machine / unit / man
Eric L Kay Associates Ford Construction Calculator V15.xls Page 6 of 14
Page seven
Ford Construction Calculator
Area to treat with bio-engineering and treatment types
(sq meter) Extension
sq meters Grass seeding, dry -$ -$
sq meters Fertilizer -$ -$
sq meters Grass seeding, Hydroseed -$ -$
sq meters Grass seeding, Bonded Fibre Matrix -$ -$
sq meters Grass sod -$ -$
sq meters other -$ -$
sq meters Live staking with Willow Whips -$ -$
sq meters Contour wattling -$ -$
sq meters Planting of live plugs -$ -$
sq meters other -$ -$
sq meters other -$ -$
sq meters other -$ -$
TOTALS: -$
For assistance in estimating Boi-engineering requirements, contact Eric L Kay at [email protected] (For a
description and how-to of Bio-engineering, Eric also has a handbook availble, contact him for a complimentary copy)
Cost
Bioengineering typeArea
Please refer to "Boi-engineering Calculator" spreadsheet for calcualtions for area's to be treated and for
details of treatments. (For a copy of the spreadsheet send an email to [email protected])
BIO-ENGINEERING MATERIALS AND LABOUR REQUIREMENTS
Eric L Kay Associates Ford Construction Calculator V15.xls Page 7 of 14
Page eight
Ford Construction Calculator
Mobilization Demobilization Total hours cost extension
Excavator Lowbed 3 3 6 75.00$ 450.00$
Walking time 2 2 4 125.00$ 500.00$
Gravel trucks Travel time 5 5 10 75.00$ 750.00$
Rock Drill Lowbed time 3 3 6 75.00$ 450.00$
Travel time 2 2 4 75.00$ 300.00$
trucking time cost extension
ACB's transported to site from staging area eg flatdeck with hiab 5 60.00$ 300.00$
travel time cost extension
Machine to move stuff around on site eg bobcat or backhoe 5 55.00$ 275.00$
TOTAL of Mobilization / De-mobilization costs : 3,025.00$
MOBILIZATION / DE-MOBILIZATION
Eric L Kay Associates Ford Construction Calculator V15.xls Page 8 of 14
Page nine
Ford Construction Calculator
For further information on armoured fords, see Powerpoint presentation at www.kayassociates.com/powerpoint/ford.htm,
and a reprint of the magazine article on Fords at www.kayassociates.com/articles/ford.htm or send an email to:
BLANK
Eric L Kay Associates Ford Construction Calculator V15.xls Page 9 of 14
Page ten For use in assistance in appoximating
times and costs. NOTE: Does not take into
account mobilization and demobilization or
standby time or minimum billing hours or that
there may be delays for traffic or other factors.
Project: Date: 28-Jul-04
INSTRUCTIONS Spreading equipment
Enter your data into the bright YELLOW boxes Equipment type
Machine used for loading the trucks Rate
Loader type Ex 200 Excavator Road Grading
Loader hourly rate 88.32$ Grader type
Truck Type Capacity Rate
Truck type T/A Truck 12 Cubic yards Km of road graded per DAY 12
Truck Rate 65.00$ Km of road graded per HOUR 1.2
Materials Road width (m) Material depth (mm) Road length (m) Volume
Volume Calculation 7.0 600 40 168.0 Cubic Meters
23.6 inches 219.7 Cubic Yards
2.0 Lineal meters Total number
6.4 Lineal feet of truckloads 20.0
Trucking time calculator Loading Trucks time calculator
Truck capacity 12 Cu Yards Bucket Capacity (yards) 1
Truck capacity 9.2 Cu Meters Bucket Capacity (meters) 0.8
% of full capacity 90% Seconds per cycle 20
Actual truck load 8.3 Cu Meters Minutes per cycle 0.33
Trucking distance 9 Km (one way) Cycles per minute 3.0Trucking distance 18 Km (round trip) Buckets per truckload 10.8
Truck Travel Speed 40 Km/hr (average) Rounded UP buckets 11.0
Truck travel time 27 Minutes Minutes to load truck 3.7
Loading time/truck 4.0 Minutes (rounded up) Minutes to load truck (rounded up) 4.0
Dumping time/truck 2 Minutes
Truck cycle time 33 Minutes
Optimum number of Trucks 7.3 (Assuming there is adequate passingRounded down number of trucks 7.0 places for the trucks on the road)
7.0
Trucking/Loading Truck (trucking) Loader (loading) NOTE:Cost calcuator Time (HRS) Cost Time (HRS) Cost Equipment times
Calculated values 11.0 715.00$ 2.0 176.64$ are rounded up
User entered values 12.0 780.00$ 2.0 176.64$
Spreading equipment Road Grading
Cost calcuator Time (HRS) Cost Cost calcuator Time (HRS) Cost
Calculated values 2.0 -$ Calculated values 1.0 -$ User entered values -$ User entered values -$
S U M M A R Y Calculated values User entered values
Truck Loader Time Cost 176.64$ 176.64$ Ex 200 Excavator
Trucking Time Cost 715.00$ 780.00$ T/A Truck
Spreading equipment Time Cost -$ -$ 0Road Grading Time Cost -$ -$ 0
891.64$ 956.64$
Calculated values User entered values
TOTAL COSTS
For latest version of the Trucking estimating guide contact [email protected]
Ford Construction Calculator
Material depth (inches)
Use this guide to assist in calculating trucking times for Rock,
Gravels or Sand
Trucking Calculator
Ver 1.6
User entered number of trucks
APPENDIX 1 - Trucking Calculator Work-sheet
Distance covered with one truckload
Distance covered with one truckload
Eric L Kay Associates Ford Construction Calculator V15.xls Page 10 of 14
Page eleven
Ford Construction Calculator
ESTIMATE Q100 - using Forest Road Engineering Method
Where Q = Flood return interval of appoximately xx years eg. Q 2 = 2 years and Q 100 = 100 years
3.70
2.40
0.30
0.92
2.75
British Columbia Ministry of Forests
APPENDIX 3 - Example - Sediment control management at a stream crossing
Wbf (width bank full)W2 (Width, stream bed)
Dbf (Depth, banf full)
Q 2 area (Bankfull area)
meters
meters
meters
Q 100 area (Bankfull area x 3)
Square meters
APPENDIX 2 - Stream sizing calculator
Square meters
Wbf (width, bank full)
Dbf (Depth, bankfull)
W2 (Width, stream bed)
Eric L Kay Associates Ford Construction Calculator V15.xls Page 11 of 14
Page twelve
Ford Construction Calculator
Vehicle Dimension Summary Table BC Ministry of Forests - Kamloops Forest Region
Vehicle Center Angle Minimum Minimum Max ht of Minimumclassification clear of sag crest crest curve in water crossing
height departure curve curve 4m horiz distance width
mm % mm mm mm mmTwo Compact Pick-up 270 50% 4400 3000 750 700
wheel Full size Pick-up 270 45% 5400 3800 570 900
drive Extended cab Pick-up 300 43% 6300 4850 430 1000
trucks Crew cab Pick-up 300 39% 7100 7000 280 1000
Max : 300 50% 7100 7000 750 1000
Min : 270 39% 4400 3000 280 700Four Compact Pick-up 370 61% 4200 3100 730 600
wheel Full size Pick-up 300 45% 5800 4200 510 900
drive Extended cab Pick-up 350 50% 5400 4040 530 800
trucks Crew cab Pick-up 340 46% 6900 6200 330 1000
Compact Sport Utility 300 55% 4000 2680 910 600Full size Sport Utility 310 38% 6100 3300 670 900
Max : 370 61% 6900 6200 910 1000
Min : 300 38% 4000 2650 330 600
Special fire protection vehicle 430 32% 9300 3350 680 1300
Sub-classification
APPENDIX 4 - Ford shape and engineering guide
Angle of entry Angle of departurecenter clear height
Minium sag curve
Minium crest curve
Stream bed)
Approach ramp
armoured prevent
tracking of sediment
and vehicle damageWidth equal to
stream bed width
Stream bed is level but with
depression to maintain fish passage in
low flows
15% gradient
Maximum gradients
dependant on vehicle type
15% gradient
Width and depth of armoured channel equal to Q100
Approach ramp
armoured prevent
tracking of sediment and
vehicle damage
Suggested approach gradients
Two wheel drive - 15% max
Four wheel drive - 20% max
Width equal to
stream bed width
Existing road
Eric L Kay Associates Ford Construction Calculator V15.xls Page 12 of 14
Page thirteen
Ford Construction Calculator
For full-size drawings (.jpg or .dwg or other format) send an email request to [email protected]
For full-size paper copies or electronic copies of these drawings (available in different file formats) , please Email
[email protected] or call Eric at 1-250-337-5096
APPENDIX 5 - Ford concept drawing - 3D view
Eric L Kay Associates Ford Construction Calculator V15.xls Page 13 of 14
Page fourteen
Ford Construction Calculator
For full-size drawings (.jpg or .dwg or other format) send an email request to [email protected]
For full-size paper copies or electronic copies of these drawings (available in different file formats) , please Email
[email protected] or call Eric at 1-250-337-5096