ARRA Project Summary Information

Division of Construction Management

ARRA Program Update

(As of February 23, 2010)ODOT Let

• 129 Projects let in 2009• 14 Projects let in 2010• 143 Total ARRA Projects let to date• 59 projects remain to be let in 2010

2010 Conaway Conference 2

2010 Conaway Conference 3

ARRA Program Update

Local Let Projects (LPA)

• 66 Projects Let to date• 90 Remain to be let in 2010

2010 Conaway Conference 4

ARRA Program Update

(As of February 23, 2010)ODOT Let

• 50 projects completed in 2009• 78 projects will continue into 2010

season

2010 Conaway Conference 5

2010 Conaway Conference 6

ARRA Program Update

Local Let Projects (LPA)

• 34 have construction start dates• 18 are completed

2010 Conaway Conference 7

ARRA Program Update(As of February 23, 2010)

ODOT Let

$436,591,978.56 Total Original Contract Amt.

$352,647,970.02 ARRA Funding

2010 Conaway Conference 8

2010 Conaway Conference 9

ARRA Program Update

Local Let (LPA)• $333.33 M local program• $93.8 M has been awarded to date• $18 M has been paid to date

2010 Conaway Conference 10

ARRA Program Update(As of February 23, 2010)

ODOT Let

$436,591,978.56 Total Original Contract Amt.

$119,329,262.55Total Paid to Date

2010 Conaway Conference 11

2010 Conaway Conference 12

ARRA Program Update(As of February 23, 2010)

ODOT Let

Change Orders Processed$165,460.41

Or0.14% of Paid to Date

2010 Conaway Conference 13

2010 Conaway Conference 14

ARRA Program Update

Of the 143 Contracts (ODOT) Let to date:

57 Different Contractors37 Contractors have a single contract9 Contractors have 2 contracts3 Contractors have 3 contracts2 Contractors have 4 contracts

2010 Conaway Conference 15

ARRA Program Update

1 Contractor has 5 contracts1 Contractor has 8 contracts1 Contractor has 9 contracts1 Contractor has 12 contracts1 Contractor has 14 contracts1 Contractor has 23 contracts

2010 Conaway Conference 16

2010 Conaway Conference 17

ARRA Projects (ODOT) - Types

Bridge Deck Replacement 4 projectsBridge Maintenance 2 projectsBridge Painting 3 projectsBridge Repair 7 projectsBridge Replacement 17 projectsCulvert Constr./Reconstr./ 5 projects

RepairBRIDGE RELATED 38 projects

2010 Conaway Conference 18

ARRA Projects (ODOT) - Types

Mill & Fill 11 projectsPave Gnrl System 23 projectsPave Prmy System 9 projectsResurfacing Undivided 29 projectsResurfacing Divided 3 projectsResurfacing Safety 1 projectPAVING RELATED 76 projects

2010 Conaway Conference 19

ARRA Projects (ODOT) - TypesInterchange Reconstruction2 projectsIntersection Improvement 1 projectMajor Rehab 1 projectMajor Widening 3 projectsMinor Widening 1 projectsWidening 1 projectNew Construction 2 projectsRelocation 2 projects

2010 Conaway Conference 20

ARRA Projects (ODOT) - Types

Add Sidewalks 1 projectDrainage Improvement 1 projectEarthwork/Slide Repair 2 projectGR Maintenance (NEW) 2

projectsParks 1 projectPreventive Maintenance 5

projects

2010 Conaway Conference 21

ARRA Projects (ODOT) - Types

Section Improvement 1 projectSignals 1 projectSpot Safety 1 projectTraffic Management System 1

project

2010 Conaway Conference 22

Questions?