arterial street rehabilitation for riverside drive 24 th street to 35 th street
DESCRIPTION
Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street. Public Informational Meeting July 22, 2014. Introductions. Doug Helt , P.E. City of Tulsa Transportation Lead Brooke Caviness, P.E. City of Tulsa Senior Engineer / Project Manager Tim Morgan, P.E. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/1.jpg)
Arterial Street Rehabilitation for Riverside Drive24th Street to 35th Street
Public Informational MeetingJuly 22, 2014
![Page 2: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/2.jpg)
Introductions
• Doug Helt, P.E. City of TulsaTransportation Lead
• Brooke Caviness, P.E.City of TulsaSenior Engineer / Project Manager
• Tim Morgan, P.E.HNTB CorporationProject Manager
![Page 3: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/3.jpg)
Project Location Map
![Page 4: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/4.jpg)
Overview
• Roadway Improvements
• Stormwater Improvements
• Water Main Improvements
• Sanitary Sewer Improvements
• Anticipated Project Schedule
• Questions
![Page 5: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/5.jpg)
Roadway Improvements
Roadway Geometry Improved = Safer Drive
![Page 6: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/6.jpg)
Roadway Improvements
• 35 mph Speed Limit
• Median Separation Through Park
• Lane Widths Increased
• New Lighting (LED)
![Page 7: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/7.jpg)
Roadway Improvements
![Page 8: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/8.jpg)
Stormwater Improvements
• Travis Park RCB System
• Swan Creek RCB System
• Crow Creek Bridge Replaced
• Riverside Drive Storm System Upgraded
![Page 9: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/9.jpg)
Stormwater Improvements
Pre-Project Storm Conveyance System
![Page 10: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/10.jpg)
Stormwater Improvements
Post-Project Storm Conveyance System
![Page 11: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/11.jpg)
Water Main Improvements
• Riverside Drive 12” Water Main
• Gathering Place 8” Water Main
• Creating Looped Water Main Systems
• Improved Function and Flow in Neighborhoods
![Page 12: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/12.jpg)
Water Main Improvements
Pre Project Water Main Network
![Page 13: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/13.jpg)
Water Main Improvements
Post Project Water Main Network
![Page 14: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/14.jpg)
Sanitary Sewer Improvements
• Existing Systems are 60-100 years old
• Reconstruction of Major Sanitary Mains
• High Strength Fiberglass for New Systems
• No Impact to Users
![Page 15: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/15.jpg)
Sanitary Sewer Improvements
Pre-Project Sanitary Sewer Network
![Page 16: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/16.jpg)
Sanitary Sewer Improvements
Sanitary Sewer Replacements
![Page 17: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/17.jpg)
Anticipated Project Schedule
• Fall 2014 - Construction Contract Award
• Winter 2014/2015 - Construction Begins
• Spring 2015 - Riverside Drive Closure
• 2016 - Riverside Drive Pavement Construction
• 2017 - Project Completed
![Page 18: Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street](https://reader035.vdocument.in/reader035/viewer/2022062811/56816257550346895dd2a705/html5/thumbnails/18.jpg)
Questions?