  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Part Design and Construction of Viaduct of Length 6.583 Km from Noida cityPart Design and Construction of Viaduct of Length 6.583 Km from Noida city130.03w 10-Aug-15 05-Feb-18 -0.03wAWARD OF THE WORKAWARD OF THE WORK 0.00w 10-Aug-15 10-Aug-15 130.00w

    Commencement DateCommencement Date 0.00w 10-Aug-15 10-Aug-15 -0.03wA1000 Date of commencement 0.00w 10-Aug-15 10-Aug-15 -0.03w

    Area Handover by ClientsArea Handover by Clients 0.00w 10-Aug-15 10-Aug-15 130.00wAH1010 Handing over of area for preliminary activities for Viaduct 0.00w 10-Aug-15 10-Aug-15 -0.03wAH1020 Handing over of area for preliminary activities for Stations 0.00w 10-Aug-15 10-Aug-15 130.00wAH1030 Handing over of area for Casting yard 0.00w 10-Aug-15 10-Aug-15 130.00wAH1040 Handing over of test pile location - Viaduct 0.00w 10-Aug-15 10-Aug-15 -0.03wAH1050 Handing over of test pile location - Station 0.00w 10-Aug-15 10-Aug-15 0.00wAH1060 Handing over of hindrance free area for construction for Phase 1 0.00w 10-Aug-15 10-Aug-15 130.00wAH1070 Handing over of hindrance free area for construction for Phase 2 0.00w 10-Aug-15 10-Aug-15 130.00wAH1080 Handing over of hindrance free area for construction for Phase 3 0.00w 10-Aug-15 10-Aug-15 130.00w

    INITIAL ACTIVITIESINITIAL ACTIVITIES 20.50w 10-Aug-15 31-Dec-15 109.50wSurveyingSurveying 6.00w 10-Aug-15 20-Sep-15 122.60w

    S1010 Initial survey of the Alignment 6.00w 10-Aug-15 20-Sep-15 122.60wGeo Technical InvestgationGeo Technical Investgation 7.40w 10-Aug-15 30-Sep-15 122.60w

    GT1010 Geo-Technical Investigation 7.40w 10-Aug-15 30-Sep-15 122.60wUtilities & TreesUtilities & Trees 15.50w 10-Aug-15 26-Nov-15 114.50w

    UT1010 Trees identification 7.40w 10-Aug-15 30-Sep-15 77.10wUT1040 Approval of tree cutting and (or) transplantation (Arranged by DMRC) 6.00w 24-Aug-15 04-Oct-15 114.50wUT1050 Tree cutting and (or) transplantation 7.50w 05-Oct-15 26-Nov-15 114.50w

    Initial Pile Load TestInitial Pile Load Test 15.50w 14-Sep-15 31-Dec-15 -0.03wIP1010 Test Pile - Viauduct 6.80w 14-Sep-15 30-Oct-15 -0.03wIP1020 Test Pile - Station 5.90w 19-Sep-15 30-Oct-15 0.00wIP1030 Initial pile load test - Viaduct 11.50w 12-Oct-15 31-Dec-15 -0.03wIP1040 Initial pile load test - Station 10.50w 17-Oct-15 30-Dec-15 0.00w

    ENGINEERINGENGINEERING 52.90w 10-Aug-15 13-Aug-16 77.10wDesign & DrawingDesign & Drawing 52.90w 10-Aug-15 13-Aug-16 77.10w

    ViaductViaduct 52.90w 10-Aug-15 13-Aug-16 77.10wSubmission of Design & DrawingsSubmission of Design & Drawings 51.90w 10-Aug-15 06-Aug-16 78.10w

    S.D.1010 Submission of Span Configuration pier location 0.30w 14-Sep-15 15-Sep-15 77.10wS.D.1020 Submission of Span Configuration pier location with vertical alignment 2.10w 15-Sep-15 30-Sep-15 121.70wS.D.1030 Submission of design, drawing for foundation 18.00w 26-Oct-15 28-Feb-16 1.97wS.D.1040 Submission of design, drawing for Sub-Structure 40.00w 31-Oct-15 06-Aug-16 77.10wS.D.1050 Release of design, drawing for Segment casting 5.20w 10-Aug-15 15-Sep-15 124.80w

    Approval of Design & DrawingsApproval of Design & Drawings 47.60w 15-Sep-15 13-Aug-16 77.10wA.D.1060 Approval of Span Configuration pier location 2.10w 15-Sep-15 30-Sep-15 122.60wA.D.1070 Approval of Span Configuration pier location with vertical alignment 2.00w 22-Sep-15 06-Oct-15 121.70wA.D.1080 Approval of design, drawing for foundation 18.00w 02-Nov-15 06-Mar-16 100.00wA.D.1090 Approval of design, drawing for Sub-Structure 40.00w 07-Nov-15 13-Aug-16 77.10w

    For Station by ClientFor Station by Client 13.50w 02-Sep-15 05-Dec-15 113.10wA.D.1110 Release of details/drawings for foundations -Station 4.00w 31-Oct-15 28-Nov-15 1.00wA.D.1120 Release of details/drawings for Substructure -Station 4.00w 07-Nov-15 05-Dec-15 113.10wA.D.1130 Release of details/drawings for Superstructure -Station 2.00w 02-Sep-15 16-Sep-15 124.60w

    MOBILIZATIONMOBILIZATION 26.00w 10-Aug-15 07-Feb-16 104.00wInstallationsInstallations 17.10w 10-Aug-15 07-Dec-15 112.90w

    IS.1120 Precasting Yard Installation 16.00w 10-Aug-15 29-Nov-15 114.00wIS.1130 First batching plant mobilization/installation 10.00w 10-Aug-15 19-Oct-15 112.90wIS.1140 Second batching plant mobilization/installation 10.00w 28-Sep-15 07-Dec-15 112.90wKD.V. 010 KEY DATE 1 : SUBMISSION OF CONSTRUTION PROGRAMME, ESTABLISHING SITE OFFICE0.00w 13-Sep-15 125.00wKD.V. 020 KEY DATE 2 : COMMISIONING OF 1ST BATCHING PLANT 0.00w 19-Oct-15 119.90wKD.V. 040 KEY DATE 4 : COMMISIONING OF 2ND BATCHING PLANT 0.00w 07-Dec-15 112.90w

    Enabling WorksEnabling Works 24.00w 24-Aug-15 07-Feb-16 32.00wE.W.1150 Fabrication of shuttering sets (Pile cap/Pier/Pier Cap) 24.00w 24-Aug-15 07-Feb-16 32.00wE.W.1160 Fabrication of shuttering sets (Segment casting) 12.00w 24-Aug-15 15-Nov-15 40.00wKD.V. 030 KEY DATE 3: COMPLETION FO 1ST FORMAWORK OF BOX GIRDER PRODUCTION LINE FOR ENGINEER'S APPROVAL0.00w 22-Nov-15 41.00w

    CONSTRUCTIONCONSTRUCTION 116.10w 14-Nov-15 04-Feb-18 0.00wPrecasting WorksPrecasting Works 78.00w 28-Dec-15 25-Jun-17 32.00w

    A1120 Segment Casting 70.00w 28-Dec-15 30-Apr-17 40.00wA1130 Parapet Casting 70.00w 22-Feb-16 25-Jun-17 32.00wKD.V. 060 KEY DATE 6 :START OF CASTING OF BOX GIRDERS/SEGMENT 0.00w 28-Dec-15 110.00w

    Elevated ViaductElevated Viaduct 103.00w 07-Dec-15 26-Nov-17 10.00wViaduct - Phase 1 ( CH: 0000 - 2100 , TOTAL 2100 M of viaduct)Viaduct - Phase 1 ( CH: 0000 - 2100 , TOTAL 2100 M of viaduct) 68.03w 07-Dec-15 27-Mar-17 44.97w

    KD.V. 050 KEY DATE 5 :COMPLETION OF 1ST WORKING PILE 0.00w 07-Dec-15 113.00wKD.V. 070 KEY DATE 7 :START OF LAUNCHING OF BOX GIRDERS/SEGMENT 0.00w 28-Apr-16 92.47wKD.V. 080 KEY DATE 8 :START OF LAUNCHING OF PARAPETS 0.00w 09-Jun-16 86.47wKD.V. 090 KEY DATE 9 :PARTIAL ACCESS OF THE VIADUCT ( MINIMUM 2 KM IN ONE STRETCH) FOR LAYING TRACK0.00w 27-Mar-17 44.97wP1. 1010 Piling 20.53w 07-Dec-15 28-Apr-16 -0.03wP1. 1020 Pile Caps 23.00w 04-Jan-16 12-Jun-16 4.50wP1. 1030 Pier 27.00w 25-Jan-16 31-Jul-16 4.50wP1. 1040 Pier Caps 32.00w 22-Feb-16 02-Oct-16 4.50wP1. 1050 Segment launching 39.00w 28-Apr-16 26-Jan-17 -0.03wP1. 1060 Parapet Erection 39.00w 09-Jun-16 09-Mar-17 -0.03wP1. 1070 Miscellaneous works 25.50w 29-Sep-16 27-Mar-17 -0.03w

    Viaduct - Phase 2 (CH:2100.00- ch: 4666.611 , TOTAL 2566.71 Meter of viaduct)Viaduct - Phase 2 (CH:2100.00- ch: 4666.611 , TOTAL 2566.71 Meter of viaduct) 72.00w 14-Dec-15 30-Apr-17 40.00wP2. 1080 Piling 25.00w 14-Dec-15 05-Jun-16 10.00wP2. 1090 Pile Caps 28.00w 11-Jan-16 24-Jul-16 10.00w

    Part Design and Construction of Viaduct of Length 6.583 Km from Noida Classic WBS Layout 09-Sep-15 18:24

    Page 1 of 3 TASK filter: All Activities

    Oracle Corporation

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    P2. 1100 Pier 33.00w 08-Feb-16 25-Sep-16 10.00wP2. 1110 Pier Caps 39.00w 07-Mar-16 04-Dec-16 10.00wP2. 1120 Segment launching 38.00w 02-May-16 22-Jan-17 40.00wP2. 1130 Parapet Erection 42.00w 13-Jun-16 02-Apr-17 40.00wP2. 1140 Miscellaneous works 30.00w 03-Oct-16 30-Apr-17 40.00w

    Viaduct - Phase 3 (CH: 4666.61 - 6820.843 , TOTAL 2154.23 Meter of viaduct)Viaduct - Phase 3 (CH: 4666.61 - 6820.843 , TOTAL 2154.23 Meter of viaduct) 99.30w 01-Jan-16 26-Nov-17 10.00wKD.V. 100 KEY DATE 10 :FULL ACCESS OF THE VIADUCT INCLUDING G.I.HANGERS FOR LAYING OF TRACK AND CABLE0.00w 17-Jul-17 28.90wP3. 1080 Piling 28.00w 01-Jan-16 15-Jul-16 65.30wP3. 1090 Pile Caps 32.00w 29-Jan-16 09-Sep-16 65.30wP3. 1100 Pier 36.00w 26-Feb-16 04-Nov-16 65.30wP3. 1110 Pier Caps 42.00w 07-Mar-16 25-Dec-16 58.00wP3. 1120 Segment launching 42.00w 02-May-16 19-Feb-17 10.00wP3. 1130 Parapet Erection 48.00w 27-Jun-16 28-May-17 10.00wP3. 1140 Miscellaneous works 48.00w 26-Dec-16 26-Nov-17 10.00w

    StationsStations 116.10w 14-Nov-15 04-Feb-18 0.00wKEY DATE FOR STATIONKEY DATE FOR STATION 55.00w 15-Jan-17 04-Feb-18 0.00w

    KEY DATE 1KEY DATE 1 0.00w 15-Jan-17 15-Jan-17 55.00wKDS. 010 PARTIAL ACCESS TO E&M CONTARCTOR 0.00w 15-Jan-17 55.00w

    KEY DATE 2KEY DATE 2 10.00w 26-Feb-17 07-May-17 39.00wKDS. 02010 FOR ANY TWO STATIONS 0.00w 26-Feb-17 49.00wKDS. 02020 FOR NEXT ANY TWO STATIONS 0.00w 02-Apr-17 44.00wKDS. 02030 FOR BALANCED TWO STATIONS 0.00w 07-May-17 39.00w

    KEY DATE 3KEY DATE 3 6.00w 18-Jun-17 30-Jul-17 27.00wKDS. 3010 FOR ANY TWO STATIONS 0.00w 18-Jun-17 33.00wKDS. 3020 FOR NEXT ANY TWO STATIONS 0.00w 25-Jun-17 32.00wKDS. 3030 FOR BALANCED TWO STATIONS 0.00w 30-Jul-17 27.00w

    KEY DATE 4KEY DATE 4 3.00w 18-Jun-17 09-Jul-17 30.00wKDS. 4010 FOR ANY TWO STATIONS 0.00w 18-Jun-17 33.00wKDS. 4020 FOR NEXT ANY TWO STATIONS 0.00w 25-Jun-17 32.00wKDS. 4030 FOR BALANCED TWO STATIONS 0.00w 09-Jul-17 30.00w

    KEY DATE 5KEY DATE 5 3.00w 14-May-17 04-Jun-17 35.00wKDS. 5010 FOR ANY TWO STATIONS 0.00w 14-May-17 38.00wKDS. 5020 FOR NEXT ANY TWO STATIONS 0.06w 29-May-17 29-May-17 35.94wKDS. 5030 FOR BALANCED TWO STATIONS 0.00w 04-Jun-17 35.00w

    KEY DATE 6KEY DATE 6 11.00w 05-Mar-17 21-May-17 37.00wKDS. 6010 FOR ANY TWO STATIONS 0.00w 05-Mar-17 48.00wKDS. 6020 FOR NEXT ANY TWO STATIONS 0.00w 09-Apr-17 43.00wKDS.6030 FOR BALANCED TWO STATIONS 0.00w 21-May-17 37.00w

    KEY DATE 7KEY DATE 7 0.00w 04-Feb-18 04-Feb-18 0.00wA1170 KD3: COMPLETION OF ENTIRE WORK AS PER CONTRACT 0.00w 04-Feb-18 0.00w

    Station - 34Station - 34 59.00w 14-Nov-15 31-Dec-16 0.00wP1. 1080 Piling 12.00w 14-Nov-15 06-Feb-16 0.00wP1. 1090 Pile Caps 13.00w 12-Dec-15 12-Mar-16 0.00wP1. 1100 Pier 13.00w 09-Jan-16 09-Apr-16 0.00wP1. 1110 Arm at consourse slab 32.00w 06-Feb-16 17-Sep-16 0.00wP1. 1120 Concourse Slab 32.00w 06-Feb-16 17-Sep-16 0.00wP1. 1130 Arm at Track Slab 32.00w 02-Apr-16 12-Nov-16 0.00wP1. 1140 Track Slab 32.00w 02-Apr-16 12-Nov-16 0.00wP1. 1150 Platform slab & Misc Struture 32.00w 02-Apr-16 12-Nov-16 0.00wP1. 1160 Finishing Work 39.00w 02-Apr-16 31-Dec-16 0.00w

    Station - 52Station - 52 59.00w 28-Nov-15 14-Jan-17 55.10wP1. 1980 Piling 12.00w 28-Nov-15 20-Feb-16 14.10wP1. 1990 Pile Caps 13.00w 26-Dec-15 26-Mar-16 23.10wP1. 2000 Pier 13.00w 23-Jan-16 23-Apr-16 23.10wP1. 2010 Arm at consourse slab 32.00w 20-Feb-16 01-Oct-16 23.10wP1. 2020 Concourse Slab 32.00w 20-Feb-16 01-Oct-16 23.10wP1. 2030 Arm at Track Slab 32.00w 16-Apr-16 26-Nov-16 30.10wP1. 2040 Track Slab 32.00w 16-Apr-16 26-Nov-16 55.10wP1. 2050 Platform slab & Misc Struture 32.00w 16-Apr-16 26-Nov-16 55.10wP1. 2060 Finishing Work 39.00w 16-Apr-16 14-Jan-17 55.10w

    Station - 62Station - 62 62.00w 12-Dec-15 18-Feb-17 50.10wP1. 2070 Piling 12.00w 12-Dec-15 05-Mar-16 14.10wP1. 2080 Pile Caps 13.00w 09-Jan-16 09-Apr-16 14.10wP1. 2090 Pier 13.00w 06-Feb-16 07-May-16 14.10wP1. 2100 Arm at consourse slab 32.00w 05-Mar-16 15-Oct-16 14.10wP1. 2110 Concourse Slab 32.00w 05-Mar-16 15-Oct-16 14.10wP1. 2120 Arm at Track Slab 32.00w 30-Apr-16 10-Dec-16 28.10wP1. 2130 Track Slab 32.00w 30-Apr-16 10-Dec-16 28.10wP1. 2140 Platform slab & Misc Struture 32.00w 30-Apr-16 10-Dec-16 50.10wP1. 2150 Finishing Work 42.00w 30-Apr-16 18-Feb-17 50.10w

    Station - 59Station - 59 76.00w 13-Feb-16 29-Jul-17 27.10w

    P1. 2160 Piling 12.00w 13-Feb-16 07-May-16 44.10wP1. 2170 Pile Caps 13.00w 19-Mar-16 18-Jun-16 43.10wP1. 2180 Pier 13.00w 16-Apr-16 16-Jul-16 43.10wP1. 2190 Arm at consourse slab 32.00w 03-Sep-16 15-Apr-17 27.10wP1. 2200 Concourse Slab 32.00w 03-Sep-16 15-Apr-17 27.10wP1. 2210 Arm at Track Slab 32.00w 29-Oct-16 10-Jun-17 27.10wP1. 2220 Track Slab 32.00w 29-Oct-16 10-Jun-17 27.10wP1. 2230 Platform slab & Misc Struture 32.00w 29-Oct-16 10-Jun-17 27.10w

    Part Design and Construction of Viaduct of Length 6.583 Km from Noida Classic WBS Layout 09-Sep-15 18:24

    Page 2 of 3 TASK filter: All Activities

    Oracle Corporation

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    P1. 2240 Finishing Work 39.00w 29-Oct-16 29-Jul-17 27.10wStation - 61Station - 61 78.00w 27-Feb-16 26-Aug-17 23.10w

    S62. 1610 Piling 12.00w 27-Feb-16 21-May-16 36.10wS62. 1620 Pile Caps 13.00w 02-Apr-16 02-Jul-16 35.10wS62. 1630 Pier 13.00w 30-Apr-16 30-Jul-16 35.10wS62. 1640 Arm at consourse slab 34.00w 17-Sep-16 13-May-17 23.10wS62. 1650 Concourse Slab 34.00w 17-Sep-16 13-May-17 23.10wS62. 1660 Arm at track slab 34.00w 12-Nov-16 08-Jul-17 30.10wS62. 1670 Track Slab 34.00w 12-Nov-16 08-Jul-17 30.10wS62. 1680 Platform slab & Misc Struture 34.00w 12-Nov-16 08-Jul-17 30.10wS62. 1690 FInishing Work 39.00w 26-Nov-16 26-Aug-17 23.10w

    Station - Electronic CityStation - Electronic City 85.00w 12-Mar-16 28-Oct-17 14.10wP1. 1710 Piling 12.00w 12-Mar-16 04-Jun-16 27.10wP1. 1720 Pile Caps 13.00w 16-Apr-16 16-Jul-16 26.10wP1. 1730 Pier 13.00w 14-May-16 13-Aug-16 26.10wP1. 1740 Arm at consourse slab 34.00w 01-Oct-16 27-May-17 14.10wP1. 1750 Concourse Slab 34.00w 01-Oct-16 27-May-17 14.10wP1. 1760 Arm at Track Slab 34.00w 26-Nov-16 22-Jul-17 28.10wP1. 1770 Track Slab 34.00w 26-Nov-16 22-Jul-17 28.10wP1. 1780 Platform slab & Misc Struture 34.00w 26-Nov-16 22-Jul-17 28.10wP1. 1790 Finishing Work 42.00w 07-Jan-17 28-Oct-17 14.10w

    HANDING OVERHANDING OVER 53.13w 28-Jan-17 05-Feb-18 -0.03wA1140 Handing over of viaduct 44.00w 03-Apr-17 05-Feb-18 -0.03w

    A1150 Handing over of station 53.10w 28-Jan-17 04-Feb-18 0.00wKD.S.070 KEY DATE 7 : STATION: COMPLETON OF ENTIRE WORK AS PER CONTRACT.0.00w 04-Feb-18 0.00wKD.V.110 KEY DATE 11: VIADUT: COMPLETION OF ENTIRE WORK AS PER CONTRACT0.00w 05-Feb-18 -0.03w