CABUYAO ASRS SAFETY/Reliability REVIEWNovember 19, 2012
Mar Medina – MDO HS&E
William Marino – Technical Team Leader
Ron Alim – CDC HS&E Leader
DHL Technical TeamDHL Safety Team
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 2/22
Agenda
• ASRS Class 3 Multi Cause Findings
• ASRS Call to Action
• ASRS Safety and Reliability Improvement (Ph1)• Behaviour Based Safety Program
• PMPI Improvement Project
• ASRS Safety and Reliability Improvement (Ph2)• Next Steps and Help Needed
2
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 3/22
ASRS Class 3 Incident3
Immediate Cause:
• Unsafe Behaviour –
Not following LO/TO
Basic Causes: • Failure to follow Operating Procedures• Untimely/in-sufficient feedback .
Recommendations
• Step Change Safety Culture and Capability in DHL team.• Enforce operating procedures and reinforce safety expectations.•
Develop program to strengthen feedback system for both Team andLeadership• Improve reliability (PMPI). Less interventions ~ Less touches~ less safety
risk
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 4/22
Answer to CDC ASRS Call to Action:
1. PMPI Improvement Project (Oct 2011)
2. Behaviour Based Safety Program (July 2011)
4
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 5/22
5
PMPI Improvement Project Phase 1
Benchmarking was done in NA sites
Consultation with ASRS/ACTIV Sites Network(Led By Kim Escott/ Kim Oliver/Andrew
Gash)
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 6/22
6
Findings:
1. Top 10 interventions was due to poor
maintenance.
2. Equipment was not in basic condition.
3. In-adequate staffing and with low
capability
Interventions:
1. Restore equipment to basic condition thru
AM/PM program (via GBU Resource)
2. Overhaul Maintenance Program via re-application
of LIMA’s program (usage based)
3. Increased staffing. New Maintenance Planner
(Learning’s from NA sites)
PMPI Improvement Project Phase 1
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 7/22
7
PMPI Improvement Project Phase 1
> Restore Process/Equipment Condition
> DHL TechTeam capability building - AM/PM/PLC/SAP
Maintenance training
> Bring back ASRS to basic condition (AM)
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 8/22
DHL Staffing OLD
Corestaff
Cortez, John PeterC.
MHE/ Technical Services Senior Supervisor
Technical Services (FGW-ASRS) Table of Organization as of Sept. 2012
Total of 35 slotCorestaff Corestaff
RicGaurano
HydraHandler
Decena, Jayson M. Brabo, Argel
Hydra Handler Hydra Handler
Hydra Handler Hydra Handler
Corestaff Corestaff
DHL DHL Corestaff Corestaff
Regio, Enrique J. Babala, Noel G.
Maintenance Services
Associate
Maintenance
TechnicianHydra Handler Hydra Handler
DHL DHL DHL DHL
Tobias, Joseph R. Capuso, Dario V. Ballon, Danilo V. Caralipio, Ding L.
Technical Services
Associate
Technical Services
Associate
Technical Services
Associate
Technical Services
Associate
C am be l , E dm ar k E. I dr a, A rj ay D . Alumaga, Djan Karlo B. Artagame, Darwin S.
Senior Technical
Services Associate
SeniorTechnical
Services Associate
SeniorTechnical
Services Associate
SeniorTe chnical
Services Associate
DHL DHL DHL DHL
DHL DHL DHL DHL DHL
D oy ac , R io N il o M. B el oi ra , A lb in P. G al la no , C ar lo R. C ay , J ef fr ey I .
P ug uo n, St al i n A . O rt i ll an o, Ed ma r P. M ol i na , J e ri me E. G ar le j o, Fr an k li n S . L um ba , N at ha ni e l G .
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical Services
SPECIALIST
Technical Services
SPECIALIST
Technical Services
SPECIALIST
Technical Services
SPECIALIST
DHL DHL DHL DHL
Technical Suport SupervisorTechnical Services Maintenance
PlannerSupervisorMHE&BuildingFacilities Supervisor
Abalos Jr., Francisco B. Santiago, Rolando L. Payumo,Ferdi nand C. Magbanua, Rowel B.
Oblepias, Darwin B. Loma, Gary O. Diamante, Ronald L.
DHL Staffing NEW
Dedicated Maintenance Group in placed.
Complete roster of DHL staff includes new 8 Engineers.
Two Technicians manning ASRS instead of 1
Corestaff
Oblepias, Darwin B.
Technical Suport Supervisor
Cortez, John Peter C.
MHE / Technical Services Sen ior Supervisor
Total of 35 slotCorestaff Corestaff
Ric Gaurano
Hydra Handler
Technical Services (FGW-ASRS) Table of Organization 2011
Decena, Jayson M. Brabo, Argel
Hydra Handler Hydra Handler
Hydra Handler Hydra Handler
Corestaff Corestaff
DHL Corestaff Corestaff
Regio, Enrique J. Babala, Noel G.
Maintenance
TechnicianHydra Handler Hydra Handler
DHL DHL DHL DHL
Capuso, Dario V. Ballon, Danilo V. Caralipio, Ding L.
Technical Services
Associate
Technical Services
Associate
Technical Services
Associate
Technical Services
Associate
C am be l, E dm ar k E. I dr a, A rj ay D. Alumaga, Djan Karlo B. Artagame, Darwin S.
Senior Technical
Services Associate
Senior Technical
Services Associate
Senior Technical
Services Associate
Senior Technical
Services Associate
DHL DHL DHL DHL
DHL DHL DHL DHL
D oy ac , R io N il o M. B el oi ra , A lb in P. G al la no , C ar lo R . C ay , J ef fr ey I .
Puguon, St al i n A . O rt il l ano, Edmar P. M ol i na , Je ri me E. Gar l ejo, F rank l in S .
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical ServicesENGINEER
Technical Services
SPECIALIST
Technical Services
SPECIALIST
Technical Services
SPECIALIST
Technical Services
SPECIALIST
DHL DHL DHL DHL
Abalos Jr., Francisco B. Santiago, Rolando L. Payumo,Ferdinand C. Magbanua, Rowel B.
PMPI Improvement Project Phase 1
> DHL TechTeam manpower staffing improvement
Re-applicationfrom NA sites
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 9/22
-
2,000.00
4,000.00
6,000.00
8,000.00
10,000.00
12,000.00
E
r r o r c o u n t
Error count reduction
9
PMPI Improvement Project Phase 1
> Equipment ownership program / focus on Top contributors of intervention
> Error count reduced by 78.6 % from Nov.2011 to date
> Enabling each team member toown and improve equipment
Re-application
from PAPERGBU
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 10/22
10
PMPI Improvement Project Phase 1
> Result tracking..
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 11/22
Safety Result
• ZERO TIR since May 2012
• 2 Class 3 incidents occurred for the last 8 years and attributed to not
following SOP.
FY0405 FY0506 FY0607 FY0708 FY0809 FY0910 FY1011 FY1112
CDC TIR 0 0.18 0 0 0 0 0.12 0
ASRS TIR 0 4.30 0 0 0 0 4.72 0
TIR
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 12/22
12
SAFETY Improvement Program
DHL corporate launched BBS (Behavioural Based Safety) program across the
sites to address the behaviour culture of not following SOP’s (Short cuts).
Revisit & revise the SWP’s making the maintenance process in easier way but
still in a safe manner.
DHL corporate launched Town hall meeting conducted by country managerto all sites with support of DHL sector head
Develop safety spot check walkthrough to enhance the P&G & DHL
Leadership commitment in thorough BOS, feedback system and walkthroughs.
Safety controls implemented in the site by posting of safety Do’s & Don’ts,
Installation of interlocks and additional fencing at entry points.
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 13/22
13
SAFETY Program Improvements
> Behaviour Based Safety (BBS) LAUNCHING
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 14/22
14
SAFETY Program Improvements
14
Training pictures Family pictures/tarpaulin/board
LEADERSHIP SAFETY SPOT CHECK WALKTHROUGHS
STANDARDIZE QUALIFICATION PROCESS OF MHE OPERATORS
REVIEW AND UPDATING OF SWP & JSA
SAFETY MOMENTS IN MEETINGS
ADDITIONAL SAFETY DO’S & DON’TS IN THE WAREHOUSE
INVOLVE SUPPORTS IN IDENTIFYING & CONFRONTING UNSAFE ACTS
BOFS TRAINING FAMILY PICS
OTHER INITIATIVES SAFETY TOWN HALL @ DOCK
> BEHAVIOR BASED SAFETY EVENTS
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 15/22
15
ASRS SAFETY Features
> Access door interlock system > Safety pull cord around ASRS
> Strategically located push button E-Stop
> Safety
beacon light
> Fall prevetion safety Pin
16
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 16/22
16
ASRS Safety Feature
> Module split system
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 17/22
ASRS Key Measures
47 5787 101 124
327
615 624 635 629 637 643
0
100
200
300
400
500
600
700
800
900
PMPI Performance(Nov. 2011 – Oct. 30 2012)
PMPI Target Glide Path
12 X
improvementfrom baseline
• Cabuyao ASRS is at 70,088 Safe Effort hours,
with Zero TIR•Cabuyao ASRS reliability from 47 PMPI to 643PMPI to date
18
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 18/22
PMPI Improvement Project Phase 2
18
47 5787 101
124
327
615 624 635 629 637 643
0
100
200
300
400
500
600
700
800
900
PMPI Performance(Nov. 2011 – Oct. 30 2012)
PMPI Target Glide Path
> 800 PMPI by end of FY1213
19
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 19/22
PMPI Improvement Project Phase 2
19
Focus Improvement;
Error Code 94017
(DLT/CAT Move Failed)
0
500
1000
1500
6/1/2012 7/1/2012 8/1/2012 9/1/2012 10/1/2012
E r r o r c o u n t
Top ten error types for the last 5months
94017
94118
94002
94264
94018
94019
OLD model existing at CDC Re-application from Lima DC
In-lane tensioning (NA Sites)
20
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 20/22
20
PMPI Improvement Project Phase 2
Next Steps/Help Needed:- Top contributors of errors analysis (Monthly)
- Focused Improvement
- Dedicated P&G/DHL Supervisor to focus on ASRSreliability improvement (Nov 2012)
- In-lane tensioning (requires capital budget)- Augusta Benchmarking to re-apply/localize equipment
improvements (JFM13)
- ASRS racks assessment from ASRS vendor (JFM13)
- Inlane Tensioning Execution ( AMJ13)
21
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 21/22
• Remote Lock-out
(AMEC/Underdog)
($2MM)
21
PMPI Improvement Project Phase 3
300
800
1000
0
200
400600
800
1000
1200
FY1112 FY1213 FY1314
PMPI Run to target performance(FY1112 to Oct. 2012)
PMPITarget
> 3rd miles stone target: 1000PMPI by end of FY1314
> ASRS Safety Feature Upgrade (Re application from NA site)
22
7/29/2019 ASRS PMPI Improvement Final
http://slidepdf.com/reader/full/asrs-pmpi-improvement-final 22/22
Thank You !