association of unit owners of columbia point … pt... · the terms rs means, national construction...

76
SCHWINDT & CO. RESERVE STUDY SERVICES PAGE 1 of 75 ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS MAINTENANCE PLAN UPDATE RESERVE STUDY LEVEL III: UPDATE WITH NO VISUAL SITE INSPECTION 2016 https://www.schwindtco.com/ (503) 2271165

Upload: vuonghanh

Post on 11-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 1 of 75

ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS

MAINTENANCE PLAN UPDATE

RESERVE STUDY

LEVEL III: UPDATE WITH NO VISUAL SITE INSPECTION

2016

https://www.schwindtco.com/(503) 227‐1165

Page 2: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 2 of 75

ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS

Executive Summary

Year of Report:

January 1, 2016 to December 31, 2016

Number of Units:

79 Units

Parameters:

Beginning Balance: $324,732

Year 2016 Suggested Contribution: $65,000

Year 2016 Projected Interest Earned: $261

Inflation: 2.50%

Annual Increase to Suggested Contribution: 6.25%

Lowest Cash Balance Over 30 Years (Threshold): $82,011

Average Reserve Assessment per Unit: $80.09

Prior Year’s Actual Contribution: $75,923.86

jwong
Header/Footer
Page 3: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

TABLE OF CONTENTSAssociation of Unit Owners of Columbia Point Condominiums

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 3 of 75

Disclosure Information 4 of 75

MAINTENANCE PLAN

Executive Summary of Maintenance Plan 7 of 75

Maintenance Plan 8 of 75

RESERVE STUDY

Property Description 19 of 75

Cash Flow Method - Threshold Funding Model Summary 20 of 75

Cash Flow Method - Threshold Funding Model Projection 21 of 75

Component Summary By Group 22 of 75

Component Summary By Category 24 of 75

Annual Expenditure Detail 27 of 75

Detail Report by Category 34 of 75

Additional Disclosures 73 of 75

Page 4: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 4 of 75

Association of Unit Owners of Columbia Point CondominiumsMaintenance Plan Update

Reserve Study Update – OffsiteDisclosure Information

2016

We have conducted an offsite reserve study update and maintenance plan update Association of Unit Owners of Columbia Point Condominiums for the year beginning January 1, 2016, in accordance with guidelines established by Community Associations Institute and the American Institute of Certified Public Accountants.

This reserve study and maintenance plan is in compliance with the legislative changes made in 2007 to ORS Chapters 94 and 100.

In addition to providing the reserve study and maintenance plan, we also provide tax and review/audit services to the Association.

Schwindt & Company believes that every association should have a complete building envelope inspection within 12 months of completion of all construction and again after 25 years. This inspection must be performed by a licensed building envelope inspector. Ongoing inspections of the property should be performed by a licensed inspector, with the exception of a roof inspection which may be performed by a licensed roofing contractor.

Assumptions used for inflation, interest, and other factors are detailed in page 20. Income tax factors were not considered due to the uncertainty of factors affecting net taxable income and the election of tax form to be filed.

David T. Schwindt, the representative in charge of this report, is a designated Reserve Study Specialist, Professional Reserve Analyst, and Certified Public Accountant licensed in the states of Oregon, Washington, California, and Arizona.

The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to construction industry estimating databases that are used throughout the industry to establish cost estimates and useful life estimates for common building components and products. We suggest that the Association obtain firm bids for these services.

All information regarding the useful lives and costs of reserve components were derived by the Association, vendors, MSR Services, Inc., and various construction pricing and scheduling manuals.

Please note that the Association had a complete building envelope inspection performed by MSR Services, Inc. in 2008.

Article 11, section 11.1 of the Association’s Declaration indicates that the necessary work to maintain, repair or replace the common elements shall be the responsibility of the board of directors of the Association and shall be carried out as provided in the Bylaws.

Article 7, section 7.1 of the Association’s Bylaws indicates that all maintenance of and repairs to any unit shall be made by the owner of such unit. Each unit owner shall be responsible for the maintenance, repair, or replacement of windows and doors and the forced air furnace, any plumbing or heating fixtures, telephones, water heaters, fans, lighting fixtures and lamps, fireplaces, refrigerators, dishwashers, ranges, or other appliances and accessories that may be in or connected with such owner’s unit. All maintenance, repairs, and replacements to the general and limited common elements shall be made by the Association and shall be charged to all the unit owners as a common expense. Each unit owner, however, shall keep the limited common elements which pertain to such owner’s unit in a neat, clean and sanitary condition.

jwong
Header/Footer
jwong
RS 1
jwong
RS 2
Page 5: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 5 of 75

An insurance deductible is not included in the reserve study.

We are not aware of any material issues which, if not disclosed, would cause a material distortion of this report.

Certain information, such as the beginning balance of reserve funds and other information as detailed on the component detail reports, was provided by Association representatives and is deemed to be reliable by us. This reserve study is a reflection of the information provided to us and cannot be used for the purpose of performing an audit, a quality/forensic analysis, or background checks of historical records.

Site visits should not be considered a project audit or quality inspection of the Association’s property. This site visit does not evaluate the condition of the property to determine the useful life or needed repairs. Schwindt & Company suggests that the Association perform a building envelope inspection to determine the condition, performance, and the useful life of all the components.

Certain costs outlined in the reserve study are subjective and, as a result, are for planning purposes only. The Association should obtain firm bids at the time of work. Actual costs will depend upon the scope of work as defined at the time the repair, replacement, or restoration is performed. All estimates relating to future work are good faith estimates and projections are based on the estimated inflation rate, which may or may not prove accurate. All future costs and life expectancies should be reviewed and adjusted annually.

This reserve study, unless specifically stated in the report, assumes no fungi, mold, asbestos, lead paint, urea-formaldehyde foam insulation, termite control substances, other chemicals, toxic wastes, radon gas, electro-magnetic radiation or other potentially hazardous materials (on the surface or sub-surface), or termites on the property. The existence of any of these substances may adversely affect the accuracy of this reserve study. Schwindt & Company assumes no responsibility regarding such conditions, as we are not qualified to detect substances, determine the impact, or develop remediation plans/costs.

Since destructive testing was not performed, this reserve study does not attempt to address latent and/or patent defects. Neither does it address useful life expectancies that are abnormally short due either to improper design, installation, nor to subsequent improper maintenance. This reserve study assumes all components will be reasonably maintained for the remainder of their life expectancy.

Physical Analysis:

New projects generally include information provided by developers and/or refer to drawings.

Full onsite reserve studies generally include field measurements and do not include destructive testing. Drawings are usually not available for existing projects.

Onsite updates generally include observations of physical characteristics, but do not include field measurements.

The client is considered to have deemed previously developed component quantities as accurate and reliable. The current work is reliant on the validity of prior reserve studies.

This reserve study should be reviewed carefully. It may not include all common and limited common element components that will require major maintenance, repair, or replacement in future years, and may not include regular contributions to a reserve account for the cost of such maintenance, repair, or replacement. The failure to include a component in a reserve study, or to provide contributions to a reserve account for a component, may, under some circumstances, require homeowners to pay on demand (as a special assessment) their share of common expenses for the cost of major maintenance, repair, or replacement of a reserve component.

Page 6: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 6 of 75

ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS

MAINTENANCE PLAN UPDATE

2016

Page 7: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Executive Summary of Maintenance Plan

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 7 of 75

Regular maintenance of common elements is necessary to insure the maximum useful life and optimum performance of components. Of particular concern are items that may present a safety hazard to residents or guests if they are not maintained in a timely manner and components that perform a water-proofing function.

This maintenance plan is a cyclical plan that calls for maintenance at regular intervals. The frequency of the maintenance activity and the cost of the activity at the first instance follow a short descriptive narrative. This maintenance plan should be reviewed on an annual basis when preparing the annual operating budget for the Association

Checklists, developed by Reed Construction Data, Inc., may be accessed from the RS Means website:

http://www.rsmeans.com/supplement/67346.asp

They can be used to assess and document the existing condition of an association’s common elements and to track the carrying out of planned maintenance activities.

Page 8: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 8 of 75

ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS

MAINTENANCE PLAN UPDATE

2016

Pursuant to Oregon State Statutes Chapters 94 and 100, which require a maintenance plan as an integral part of the reserve study, the maintenance procedures are as follows:

The Board of Directors should refer to this maintenance plan each year when preparing the annual operating budget for the Association to ensure that annual maintenance costs are included in the budget for the years that they are scheduled.

Property Inspection

Schwindt & Company recommends that a provision for the annual inspection of common area components be included in the maintenance plan for all associations. This valuable management tool will help to ensure that all components achieve a maximum useful life expectancy and that they function as intended throughout their lifespan.

This inspection process should include a careful visual review of the waterproofing membrane on the unit balconies.

The inspection should be performed by a qualified professional and should include a written summary of conclusions with specific recommendations for any needed repairs or maintenance.

We suggest that the Association obtain firm bids for this service.

This expense should be included in the annual operating budget for the Association.

Frequency: Annually

Roof Inspection

Schwindt & Company recommends that a provision for the periodic inspection and maintenance of roofing and related components be included in the reserve study and maintenance plan for all associations.

The frequency of this inspection will vary based on the age, condition, complexity, and remaining useful life of the roof system. As the roof components become older, the Association is well advised to consider increasing the frequency of this critical procedure.

The inspection should be performed by a qualified roofing professional and should include a written summary of conclusions with specific recommendations for any needed repairs or maintenance. Recommended maintenance should be performed promptly by a licensed roofing contractor.

We suggest that the Association obtain firm bids for this service.

Page 9: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 9 of 75

This expense is included in the reserve study for the Association.

Frequency: Every other year beginning in 2017

Lighting: Exterior & Common Area Interior – Inspection/Maintenance

Note: Replacement of flickering or burned-out bulbs or lamps should be immediate.

Lighting is a crucial element in the provision of safety and security. All lighting systems should be inspected frequently and care must be taken to identify and correct deficiencies.

Various fixture and lamp types may be used according to area needs. Lighting systems should be designed to provide maximum, appropriate illumination at minimal energy expenditures. Lighting maintenance processes should include a general awareness of factors that cause malfunctions in lighting systems, such as dirt accumulation and lumen depreciation. It is important to fully wash, rather than dry-wipe, exterior surfaces to reclaim light and prevent further deterioration.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

Repairs and inspections should be completed by a qualified professional.

This expense should be included in the annual operating budget for the Association as general property maintenance expense.

Frequency: Bi-Weekly

Clubhouse/Fitness/Recreation Areas

The clubhouse may experience heavy traffic that can have a dramatic impact on the life expectancy of the equipment. Preventive maintenance is critical. Consult the manufacturers of exercise and weight equipment for specific maintenance. The overall condition of the floors and mats should be reviewed for deficiencies such as excessive wear, stains, tears, and tripping hazards. The overall condition of the following should be reviewed: walls/ceilings, lighting fixture protection, exercise/weight equipment; location of signs and fire safety devices, fire extinguishers, and trash receptacles. Mirrors and glass should be reviewed for cracked/broken surfaces or rough edges.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the annual operating budget for the Association as general property maintenance expense.

Frequency: Monthly

Exterior Stairs, Decks, Balconies, & Patios

Individual decks and balconies should be carefully checked, particularly concrete and wood, on a

Page 10: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 10 of 75

monthly basis. Concrete should be reviewed for deficiencies such as alkali-aggregate expansion, honeycombing, chips, cracks, stains, lifted areas, tripping hazards, and/or unevenness. Railings should be reviewed for stability, hardware, and overall condition. Wood should be reviewed for deficiencies, such as dry rot, termites, instability, worn edges, cracks, holes and splintering. Footing/foundation should be reviewed for stability and overall condition deficiencies, such as cracks and broken or missing components. A safety review should include, but not be limited to, the sufficient distance maintained between flammables and other surfaces, as well as the overall condition of access points such as doors, windows, screens and thresholds.

Frequency: Monthly

Gas Connections–Review

These maintenance procedures should also be performed on the common area equipment, such as the equipment in the recreation room.

The following check should be performed monthly for all gas connections and main valves throughout the facility. (Do not open and close valves.) The gas company should be contacted if:

* There is an odor of gas anywhere at any time.

* Valves cannot be turned off or appear to be rusted or damaged.

* Minor repairs are needed and maintenance personnel do not have adequate training or tools.

When gas is detected by odor, building occupants should immediately evacuate. The gas company and fire department should be contacted.

Possible undetected leakage should be visually checked (do not open and close valves) by performing a bubble test with soap and water, or by using a handheld combustible gas detector of professional quality.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the annual operating budget for the Association.

Frequency: Monthly

Hot Water Heater –Common Area Only – Inspection/Maintenance

Maintenance of the hot water heater includes regularly scheduled inspections and maintenance.

The water heater and related components should be checked for water leaks and fuel supply leaks. The water heater and related components should also be checked for proper operation and settings. Filters should be changed and all components serviced as required. The surrounding area should be cleaned at the time of servicing.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted

Page 11: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 11 of 75

by the maintenance contractor and/or association representatives.

Inspections and maintenance should be performed by a qualified, licensed service provider.

We understand that this expense should be included in the annual operating budget for the Association.

Frequency: Monthly to Annually

Property Entrance - Review

The property entrance is a significant reflection on the development as a whole and is often the first stop in the development for residents, prospective residents or buyers, and visitors. The area should be consistently clean, functional, and accessible. In addition to serving as a point of initial access, the main entry may feature mailboxes, which should be secure and operational.

Mailboxes: Review overall condition and function of locks; proper lubrication of working parts; cleanliness of face plates; security of housing, in compliance with current postal regulations; accuracy and visibility of signage/accessibility of tactile lettering, where required; condition and function of slots and depositories for outgoing mail and packages.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the annual operating budget for the Association as general property maintenance expense.

Frequency: Monthly

Swimming Pool & Spa

Swimming pool maintenance should be performed in conjunction with a service contractor. Preventive maintenance in this area consists of validating all equipment is present and functional on a monthly basis. Only certified professionals should complete repairs or maintenance procedures more advanced than manufacturer’s prescribed chemical treatments and cleaning. Maintenance staff should accompany the certified professional during statutory inspections and maintenance to ensure that the physical work complies with contract and manufacturer’s specifications.

Preventive maintenance includes, but is not limited to, the review of the following: automatic fill device function; electrical component condition; pump/filter/chlorination function; thermostat; and heater function.

Whirlpools should be reviewed for the function of the timer, drainage, and emergency switch.

Deck surface condition should be reviewed for deficiencies such as rough areas and tripping and slippage hazards. Fence and gates should be reviewed for the function of the anchors, latches and the overall condition. Handrails and ladders should be reviewed for stability, hardware and overall condition. Steps and treads should be reviewed for security and tread condition.

Page 12: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 12 of 75

Safety equipment should be reviewed for its condition and function including, but not limited to, the following: the location and condition of the life ring; emergency telephone equipment; compliance of signage with codes and standards; visibility and overall condition of the signage; and fire extinguishers tag currency, placement, housing, hose, and overall condition.

Note: Any and all electrical outlets near water should be serviced by a ground-fault circuit-interrupter (GFI) to protect users from electrical shock.

Water condition and cleanliness should be reviewed and must comply with local health standards. The County Health Department or local water management authority determines health standards in most communities. Standards must be posted within the pool area.

Pool tile/plaster should be reviewed for its overall condition.

During the off-season when the pool is covered, check the security of the fastening system monthly to make sure it hasn’t been tampered with.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the annual operating budget for the Association.

Frequency: Monthly

Windows & Doors

The performance of and payment for the maintenance and repairs of windows and doors is solely the responsibility of the owners. Owners should be made aware of the consequence of not maintaining their property. A method should be adopted for owners to report problems.

These maintenance procedures should also be performed on the common area buildings including the recreation room. This expense for the common buildings should be included in the Association’s operating budget and may be considered part of the annual property inspection.

Exterior window and door casings, sashes, and frames should be inspected annually for twisting, cracking, deterioration, or other signs of distress. Hardware and weather stripping should be checked for proper operation and fit. Gaskets and seals should be reviewed for signs of moisture intrusion. Weep holes should be cleaned. These building envelope components should be repaired and replaced as necessary.

Frequency: Monthly

Gutters & Downspouts

Schwindt & Company recommends that all gutters and downspouts be cleaned, visually inspected, and

Page 13: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 13 of 75

repaired as required every six months in the spring and fall.

This important maintenance procedure will help to ensure that the gutters and downspouts are free-flowing at all times, thus preventing the backup of water within the drainage system. Such backup can lead to water ingress issues along the roof edges, around scuppers or other roof penetrations, and at sheet metal flashing or transition points that rely on quick and continuous discharge of water from surrounding roof surfaces to maintain a watertight building exterior.

This expense should be included in the annual operating budget for the Association.

Frequency: Semiannually, more often if necessary

Bridge Maintenance

Regular maintenance of the wooden foot bridge should include regular inspections, repairs, and replacements of boards, fasteners and railings. Fasteners and railings should be kept secure to ensure safety.

This cost is an estimated amount. We suggest that the Association obtain firm bids for this service.

This expense should be included in the Association’s operating budget.

Frequency: Annually

Exterior Walls

The siding, trim, and other wood building components should be inspected for loose, missing, cracked or otherwise damaged components. Sealant joints should be checked for missing or cracked sealant.

Painted surfaces should be checked for paint deterioration, bubbling, or other signs of deterioration.

Dryer vents should be checked twice a year and cleared of lint. Also check operation of exhaust baffles to make sure they are present and that they move freely. Exhaust ducts should be cleared of debris every 3 years.

Any penetrations of the building envelope such as utility lines and light fixtures should be checked annually for signs of water intrusion. Hose bibs should be checked for leaks and other failures. Each hose bib should be shut off and drained during the winter to prevent damage from freezing.

Annual inspections to check for signs of water intrusion should be made of the building envelope interfaces such as where the windows intersect with the walls and where the walls intersect with the roof.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

Inspections should be made by a qualified professional.

Page 14: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 14 of 75

This expense should be included in the annual operating budget for the Association.

Frequency: Annually

Fence – Swimming Pool - Inspection

Metal fences require regular inspection of paint condition, rust and other corrosion, and vegetation and trash buildup. The overall condition of the fence should be reviewed for deficiencies such as vegetation encroachment, debris buildup, holes, sagging areas, missing segments, rust, and/or vandalism.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the Association’s operating budget and may be considered part of the annual property inspection.

Frequency: Annually

Fire Extinguishers – Common Areas Only

The following annual preventive maintenance checklist is for the fire extinguishers located in the common areas, such as the recreation room. This inspection and certification must be conducted by a licensed specialty contractor and should be scheduled in advance to ensure that the date on extinguishers will not expire. Monthly inspections of fire extinguishers’ general condition, housing, and locations per code should be conducted as part of preventive maintenance procedures in areas that include restrooms, fitness/recreation areas, and swimming pool areas. In addition to the annual preventive maintenance tasks outlined below, check the pressure and weight of each extinguisher in the facility every 6 months, according to its manufacturer’s label. If the pressure is below the recommended minimum or if the extinguisher has been used, it should be recharged. Consult the National Fire Protect Association’s (NFPA) Standard 10 for the specific requirements regarding the proper locations of fire extinguishers and signage.

Annual preventive maintenance checklist consists of the following: certification; housing condition; hose condition; proper location per code; count per code; and overall condition.

This expense should be included in the annual operating budget for the Association.

Frequency: Annually

Trees - Maintenance

The Association will be responsible for trimming trees in the common area throughout the property. Trees and shrubs should be kept clear of the building components.

We suggest that the Association obtain firm bids for this service.

This expense should be included in the Association’s operating budget.

Page 15: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 15 of 75

Frequency: Annually

Landscape Maintenance

The Association will be responsible for maintenance and upkeep of common area landscape throughout the property. This may include mowing lawn, removal of weeds, and dead-heading of flowers. Landscape techniques vary depending on the foliage and season.

We suggest that the Association obtain firm bids for this service.

This expense should be included in the Association’s operating budget.

Frequency: Annually

Lawn Irrigation System

Periodic maintenance to the lawn irrigation system should be anticipated with this type of component. These maintenance procedures will include replacement of the control mechanism, replacement of damaged piping, upgrading of sprinkler heads and valve components, and any other work that is advised by repair professionals.

In recent years, improvements have been made to this type of system which has increased the efficiency of the water distribution process. Such improvements can be expected to continue to be made and the owners of such systems are well advised to plan on periodic upgrades to maintain the efficiency of their systems.

Lawn irrigation systems also require periodic testing to ensure proper operation. Sometimes this testing is mandated by ordinance or building codes. All work on lawn irrigation systems must be performed by licensed contractors who specialize in this type of work.

This expense should be included in the annual operating budget for the Association.

Frequency: Annually

Storm Drains

Storm drains or sewers are underground systems used to collect and dispose of surface water. They carry large quantities of water away from paved surface areas, and should be kept clean to prevent the accumulation of dirt and debris. They should be cleaned and flushed annually to ensure blockages are removed and piping is functional. If drains tend to become clogged frequently, they should be inspected and cleaned more often.

Deficiencies, required maintenance, and required repairs after completion of the review should be noted by the maintenance contractor and/or association representatives.

This expense should be included in the annual operating budget for the Association as a general property maintenance expense.

Page 16: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 16 of 75

Frequency: Annually

Exterior Siding Maintenance – Painting

Maintenance of the exterior siding includes regularly scheduled cleaning and inspection of the surface areas for cracks, peeling paint or other sealants, deterioration of the base material, and failure of caulking or other sealant materials that serve a waterproofing function.

This maintenance provision is for the periodic painting of the exterior siding. The siding should be cleaned, repaired as required, and primed and painted with premium quality exterior house paint in accordance with the siding manufacturer’s specifications. The work should be performed by a qualified, licensed painting contractor.

This expense is included in the reserve study for the Association.

Frequency: Every 5 years, beginning in 2018 and 2019

Asphalt – Seal Coating

Maintenance of asphalt paving includes the periodic application of an asphalt emulsion sealer or “seal coat”. This procedure is typically performed every 4 to 7 years, depending on a variety of factors that can affect the useful life of the sealer.

This maintenance procedure involves thoroughly cleaning all pavements, filling of any surface cracks and patching of any locally damaged pavement surfaces. The emulsion sealer is then applied.

This work should be performed by a licensed paving contractor.

This expense is included in the reserve study for the Association.

Frequency: Every 4 years, beginning in 2017

Handrails –- Paint

Periodic maintenance of the handrails should include cleaning, prepping and painting.

Handrails are an essential function of safety in the pool and spa area. Handrails should be regularly inspected in order to assure their safety, including the tightening and/or replacement of the mechanical fasteners as required.

This expense is included in the reserve study for the Association.

Frequency: Every 6 years, beginning in 2016

Recreation Room - Interior Paint

The interior painted surfaces of the recreation room should be cleaned, repaired as required, primed and painted with premium quality interior house paint in accordance with the manufacturer’s specifications.

Page 17: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 17 of 75

The work should be performed by a qualified, licensed painting contractor.

This expense is included in the reserve study for the Association.

Frequency: Every 10 years, beginning in 2026

Elastomeric Deck Maintenance

Maintenance of the decks includes cleaning, repairing, and applying a top coat to the exposed surfaces with appropriate sealer. Drains should be cleaned and checked for free flow. Flashings, grout and other water resistive details should be renewed as needed to ensure that the tiled surface areas on the decks remain water-tight.

This work should be performed by a licensed contractor.

This expense is included in the reserve study for the Association.

Frequency: Every 5 years beginning in 2019

Concrete Pavement

Maintenance of the concrete pavement should include cleaning the surface areas with pressure washing equipment. The pavement should also be visually reviewed for signs of undue stress and cracking. Noticeable cracks should be filled with a suitable concrete crack filler to prevent penetration of moisture below the concrete surface which will undermine the integrity of the base material over time.

This expense is included in the reserve study for the Association.

Frequency: Every 5 years beginning in 2016

This maintenance plan is designed to preserve and extend the useful life of assets and is dependent upon proper inspection and follow up procedures.

Page 18: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 18 of 75

ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT CONDOMINIUMS

RESERVE STUDY

LEVEL III: UPDATE WITH NO VISUAL SITE INSPECTION

2016

Page 19: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Property Description

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 19 of 75

Association of Unit Owners of Columbia Point Condominiums consists of 5 buildings with 79 units plus a pool and two story parking area, located in Portland, Oregon. The property was converted in 1999; and was originally built in 1983. The Association shall provide exterior maintenance upon each unit, such as paint, maintenance, repair and replacement of roofs, gutters, downspouts, rain drains, and exterior building surfaces. The individual homeowners are responsible for all maintenance and repair of the interior of their home.

A site visit was performed by Schwindt & Company in 2012. Schwindt & Co did not investigate components for defects, materials, design or workmanship. This would ordinarily be considered in a complete building envelope inspection. Our condition assessment considers if the component is wearing as intended. All components are considered to be in fair condition and appear to be wearing as intended unless noted otherwise in the component detail.

Funds are being accumulated in the replacement fund based on estimates of future need for repairs and replacement of common property components. Actual expenditures, investment income and provisions for income taxes however, may vary from estimated amounts and the variations may be material. Therefore, amounts accumulated in the replacement fund may not be adequate to meet future funding needs.

If additional funds are needed, the Association has the right, subject to member approval, to increase regular assessments, and levy special assessments; otherwise the Association may delay repairs or replacements until funds are available.

Page 20: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Cash Flow Method - Threshold Funding Model Summary

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 20 of 75

Report Date February 02, 2016Account Number 2colpo

Budget Year Beginning January 01, 2016Budget Year Ending December 31, 2016

Total Units 79

Report Parameters

Inflation 2.50%Annual Assessment Increase 6.25%Interest Rate on Reserve Deposit 0.10%

2016 Beginning Balance $324,732.00

Threshold Funding Fully Reserved Model Summary

This study utilizes the cash flow method and the threshold funding model, which establishes a reserve funding goal that keeps the reserve balance above a specified dollar or percent funded amount. The threshold method assumes that the threshold method is funded with a positive threshold balance, therefore, "fully reserved".

The following items were not included in the analysis because they have useful lives greater than 30 years: grading/drainage; foundation/footings; storm drains; telephone, cable, and internet lines.

This funding scenario begins with a contribution of $65,000 in 2016 and increases 6.25% each year for the remaining years of the study. A minimum balance of $82,011 is maintained.

The reserve study cash flow model includes an annual increase in the required contribution over the 30 year period. Since the current Board and membership only has the authority to obligate the Association for the current budget year, the cash flow model relies on the actions of future Boards to adhere to the required increase in the annual reserve contribution. Because of the possibility that future Boards, due to budgetary constraints, are not able to increase the reserve contribution to the required amount to provide for adequate funding, the Association may be at risk in the future of special assessing the members to fund needed expenditures.

The purpose of this study is to insure that adequate replacement funds are available when components reach the end of their useful life. Components will be replaced as required, not necessarily in their expected replacement year. This analysis should be updated annually.

Cash Flow Method - Threshold Funding Model Summary of Calculations

Required Month Contribution $5,416.67$68.57 per unit monthly

Average Net Month Interest Earned $21.74Total Month Allocation to Reserves $5,438.41

$68.84 per unit monthly

Page 21: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Cash Flow Method - Threshold Funding Model Projection

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 21 of 75

Beginning Balance: $324,732Projected

Annual Annual Annual EndingYear Contribution Interest Expenditures Reserves

2016 65,000 261 99,151 290,8422017 69,062 292 36,808 323,3882018 73,379 303 60,173 336,8972019 77,965 272 107,186 307,9482020 82,838 336 17,149 373,9732021 88,015 416 5,378 457,0272022 93,516 473 34,553 516,4642023 99,361 456 114,489 501,7922024 105,571 307 252,022 355,6482025 112,169 378 38,524 429,6722026 119,180 482 12,801 536,5322027 126,629 587 18,548 645,1992028 134,543 601 117,097 663,2472029 142,952 630 110,574 696,2552030 151,886 749 29,817 819,0732031 161,379 865 41,528 939,7902032 171,465 1,001 32,139 1,080,1182033 182,182 272 906,460 356,1122034 193,568 467,669 82,0112035 205,666 182 11,478 276,3822036 218,520 374 20,451 474,8272037 232,178 459 141,738 565,7262038 246,689 529 170,895 642,0492039 262,107 388 395,872 508,6732040 278,489 606 53,891 733,8772041 295,894 872 22,902 1,007,7412042 314,388 1,179 1,323,3072043 334,037 1,341 164,266 1,494,4182044 354,914 1,546 141,715 1,709,1632045 377,097 1,905 9,727 2,078,437

Page 22: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Component Summary By Group

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 22 of 75

Serv

ice

Dat

e in

Year

Repla

cem

ent

Use

ful

Adj

ustm

ent

Remai

ning

Uni

ts

Cost

Uni

t

Cost

Curre

nt

Description

CapitalCanvas Canopy 2014 2020 7 -1 4 1 Total 3,000.00 3,000Composition Roof - Replacement 2008 2033 25 0 17 1 Total 496,068.00 496,068Concrete Curbing & Wheel-stops 2007 2033 25 1 17 1 Total 4,514.21 4,514Concrete Parking Garage - Repairs 2009 2016 1 1 0 1 Total 3,069.41 3,069Concrete Paving - Driveways & Parking G.. 2009 2034 25 0 18 3,557 SF 15.51 55,180Exterior Lighting - Replacement 2007 2017 10 0 1 23 Each 372.04 8,557Exterior Siding - Replacement Phase (I) 2014 2019 5 0 3 1 Total 35,000.00 17,500Exterior Siding - Replacement Phase (II) 2013 2018 5 0 2 1 Total 35,000.00 17,500Exterior Stairs- Replacement 2016 2015 2016 1 0 0 1 Total 25,000.00 25,000Exterior Stairs- Replacement 2017 2017 2017 1 0 1 1 Total 18,000.00 18,000Front Entry Decks - Repair 2009 2034 25 0 18 22 Total 7,441.02 163,702Irrigation Project - Pump System UnfundedKey Card System - Add 2013 2038 25 0 22 1 Total 11,018.75 11,019Landscape/Irrigation - Repair 1999 2016 10 0 0 1 Total 10,000.00 10,000Mailboxes - Replacement 2007 2033 25 1 17 1 Total 3,720.51 3,721Parking Garage - Restripe 2010 2016 7 -1 0 1 Total 2,500.00 2,500Photovoltaic Electric Project UnfundedPool - Cover Replacement 2009 2019 10 0 3 1 Total 3,305.62 3,306Pool - Equipment - Filter/Chlorinator 2007 2018 10 1 2 1 Total 1,612.22 1,612Pool - Equipment - Heater 2006 2017 6 5 1 1 Total 4,600.00 4,600Pool - Equipment - Pump 2006 2019 6 7 3 1 Total 2,500.00 2,500Pool - Liner Replacement 2009 2019 10 0 3 1 Total 11,608.25 11,608Rear Deck Membrane - Replacement 2009 2024 15 0 8 48 Each 3,305.62 158,670Recreation Center - Bathrooms UnfundedRecreation Center - Equipment Renewal 2013 2018 5 0 2 1 Total 6,448.89 6,449Recreation Center - Garden Style Window 2013 2063 25 25 47 1 Total 3,720.51 3,721Recreation Center - Renovation 1983 2016 30 0 0 1 Total 27,546.87 27,547Recreation Center - Spa & Sauna UnfundedRoofing - Preformed Metal 2007 2023 15 1 7 2,500 SF 12.39 30,975Signs UnfundedSwimming Pool - Solar Panels UnfundedTrees: Replace/Remediate 2015 2016 1 0 0 1 Total 1,240.17 1,240 Capital - Total $1,091,557

Non-CapitalAsphalt Walking Path - Repairs 2007 2020 12 1 4 5,055 SF 2.48 12,536Asphalt Walking Path - Seal Coat 2007 2017 4 6 1 5,055 SF 0.43 2,174Bridge: Walking Path & Railings - Repairs 2009 2030 20 1 14 2 Total 9,301.28 18,603Concrete Pavement - Power Wash & Seal .. 2013 2016 3 0 0 42,898 SF 0.55 23,594Concrete Walkways - Repair 2007 2032 25 0 16 587 SF 15.51 9,113Exterior Siding - Painting (I) 2014 2019 5 0 3 1 Total 30,676.20 30,676Exterior Siding - Painting (II) 2013 2018 5 0 2 1 Total 31,711.96 31,712

Page 23: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Component Summary By Group

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 23 of 75

Serv

ice

Dat

e in

Year

Repla

cem

ent

Use

ful

Adj

ustm

ent

Remai

ning

Uni

ts

Cost

Uni

t

Cost

Curre

nt

Description

Non-Capital continued...Front Entry Decks - Re-Coat (I) 2009 2019 10 0 3 784 SF 9.91 7,769Front Entry Decks - Re-Coat (II) 2009 2044 10 25 28 784 SF 9.91 7,769Gutters & Downspouts - Repair 2008 2033 25 0 17 1 Total 31,004.25 31,004Handrails & Guardrails - Paint 2010 2016 6 0 0 1 Total 6,200.85 6,201Handrails & Guardrails - Repair 2007 2037 30 0 21 1 Total 37,205.09 37,205Pool Deck, Concrete - Repairs 2007 2037 30 0 21 340 SF 15.51 5,280Recreation Center - Interior Painting 2013 2036 10 13 20 1 Total 2,480.35 2,480Roofing - Inspection (I) 2015 2017 2 0 1 1 Total 2,579.56 2,580 Non-Capital - Total $228,696

Total Asset Summary $1,320,254

Page 24: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Component Summary By Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 24 of 75

Serv

ice

Dat

e in

Year

Repla

cem

ent

Use

ful

Adj

ustm

ent

Remai

ning

Uni

ts

Cost

Uni

t

Cost

Curre

nt

Description

RoofingComposition Roof - Replacement 2008 2033 25 0 17 1 Total 496,068.00 496,068Roofing - Inspection (I) 2015 2017 2 0 1 1 Total 2,579.56 2,580Roofing - Preformed Metal 2007 2023 15 1 7 2,500 SF 12.39 30,975 Roofing - Total $529,623

DecksRear Deck Membrane - Replacement 2009 2024 15 0 8 48 Each 3,305.62 158,670 Decks - Total $158,670

LightingExterior Lighting - Replacement 2007 2017 10 0 1 23 Each 372.04 8,557 Lighting - Total $8,557

EquipmentCanvas Canopy 2014 2020 7 -1 4 1 Total 3,000.00 3,000Key Card System - Add 2013 2038 25 0 22 1 Total 11,018.75 11,019Recreation Center - Equipment Renewal 2013 2018 5 0 2 1 Total 6,448.89 6,449 Equipment - Total $20,468

Building ComponentExterior Siding - Replacement Phase (I) 2014 2019 5 0 3 1 Total 35,000.00 17,500Exterior Siding - Replacement Phase (II) 2013 2018 5 0 2 1 Total 35,000.00 17,500Exterior Stairs- Replacement 2016 2015 2016 1 0 0 1 Total 25,000.00 25,000Exterior Stairs- Replacement 2017 2017 2017 1 0 1 1 Total 18,000.00 18,000Front Entry Decks - Re-Coat (I) 2009 2019 10 0 3 784 SF 9.91 7,769Front Entry Decks - Re-Coat (II) 2009 2044 10 25 28 784 SF 9.91 7,769Front Entry Decks - Repair 2009 2034 25 0 18 22 Total 7,441.02 163,702Handrails & Guardrails - Repair 2007 2037 30 0 21 1 Total 37,205.09 37,205Recreation Center - Bathrooms Unfunded Building Component - Total $294,446

Grounds ComponentAsphalt Walking Path - Repairs 2007 2020 12 1 4 5,055 SF 2.48 12,536Bridge: Walking Path & Railings - Repairs 2009 2030 20 1 14 2 Total 9,301.28 18,603Concrete Curbing & Wheel-stops 2007 2033 25 1 17 1 Total 4,514.21 4,514Concrete Parking Garage - Repairs 2009 2016 1 1 0 1 Total 3,069.41 3,069Concrete Pavement - Power Wash & Seal .. 2013 2016 3 0 0 42,898 SF 0.55 23,594Concrete Paving - Driveways & Parking G.. 2009 2034 25 0 18 3,557 SF 15.51 55,180Concrete Walkways - Repair 2007 2032 25 0 16 587 SF 15.51 9,113Landscape/Irrigation - Repair 1999 2016 10 0 0 1 Total 10,000.00 10,000Parking Garage - Restripe 2010 2016 7 -1 0 1 Total 2,500.00 2,500

Page 25: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Component Summary By Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 25 of 75

Serv

ice

Dat

e in

Year

Repla

cem

ent

Use

ful

Adj

ustm

ent

Remai

ning

Uni

ts

Cost

Uni

t

Cost

Curre

nt

Description

Grounds Component continued...Trees: Replace/Remediate 2015 2016 1 0 0 1 Total 1,240.17 1,240 Grounds Component - Total $140,349

Streets/AsphaltAsphalt Walking Path - Seal Coat 2007 2017 4 6 1 5,055 SF 0.43 2,174 Streets/Asphalt - Total $2,174

Pool/SpaPool - Cover Replacement 2009 2019 10 0 3 1 Total 3,305.62 3,306Pool - Equipment - Filter/Chlorinator 2007 2018 10 1 2 1 Total 1,612.22 1,612Pool - Equipment - Heater 2006 2017 6 5 1 1 Total 4,600.00 4,600Pool - Equipment - Pump 2006 2019 6 7 3 1 Total 2,500.00 2,500Pool - Liner Replacement 2009 2019 10 0 3 1 Total 11,608.25 11,608Pool Deck, Concrete - Repairs 2007 2037 30 0 21 340 SF 15.51 5,280Recreation Center - Spa & Sauna Unfunded Pool/Spa - Total $28,906

Interior FurnishingsRecreation Center - Renovation 1983 2016 30 0 0 1 Total 27,546.87 27,547 Interior Furnishings - Total $27,547

MailboxesMailboxes - Replacement 2007 2033 25 1 17 1 Total 3,720.51 3,721 Mailboxes - Total $3,721

EquipmentIrrigation Project - Pump System UnfundedPhotovoltaic Electric Project UnfundedSwimming Pool - Solar Panels Unfunded

PaintExterior Siding - Painting (I) 2014 2019 5 0 3 1 Total 30,676.20 30,676Exterior Siding - Painting (II) 2013 2018 5 0 2 1 Total 31,711.96 31,712Handrails & Guardrails - Paint 2010 2016 6 0 0 1 Total 6,200.85 6,201Recreation Center - Interior Painting 2013 2036 10 13 20 1 Total 2,480.35 2,480 Paint - Total $71,069

WindowRecreation Center - Garden Style Window 2013 2063 25 25 47 1 Total 3,720.51 3,721 Window - Total $3,721

Page 26: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Component Summary By Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 26 of 75

Serv

ice

Dat

e in

Year

Repla

cem

ent

Use

ful

Adj

ustm

ent

Remai

ning

Uni

ts

Cost

Uni

t

Cost

Curre

nt

Description

Gutters & DownspoutsGutters & Downspouts - Repair 2008 2033 25 0 17 1 Total 31,004.25 31,004 Gutters & Downspouts - Total $31,004

SignsSigns Unfunded

Total Asset Summary $1,320,254

Page 27: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 27 of 75

Description Expenditures

Replacement Year 2016Concrete Parking Garage - Repairs 3,069Concrete Pavement - Power Wash & Seal (I) 23,594Exterior Stairs- Replacement 2016 25,000Handrails & Guardrails - Paint 6,201Landscape/Irrigation - Repair 10,000Parking Garage - Restripe 2,500Recreation Center - Renovation 27,547Trees: Replace/Remediate 1,240

Total for 2016 $99,151

Replacement Year 2017Asphalt Walking Path - Seal Coat 2,228Exterior Lighting - Replacement 8,771Exterior Stairs- Replacement 2017 18,450Pool - Equipment - Heater 4,715Roofing - Inspection (I) 2,644

Total for 2017 $36,808

Replacement Year 2018Exterior Siding - Painting (II) 33,317Exterior Siding - Replacement Phase (II) 18,386Pool - Equipment - Filter/Chlorinator 1,694Recreation Center - Equipment Renewal 6,775

Total for 2018 $60,173

Replacement Year 2019Concrete Pavement - Power Wash & Seal (I) 25,408Exterior Siding - Painting (I) 33,035Exterior Siding - Replacement Phase (I) 18,846Front Entry Decks - Re-Coat (I) 8,367Pool - Cover Replacement 3,560Pool - Equipment - Pump 2,692Pool - Liner Replacement 12,501Roofing - Inspection (I) 2,778

Total for 2019 $107,186

Page 28: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 28 of 75

Description Expenditures

Replacement Year 2020Asphalt Walking Path - Repairs 13,838Canvas Canopy 3,311

Total for 2020 $17,149

Replacement Year 2021Asphalt Walking Path - Seal Coat 2,459Roofing - Inspection (I) 2,919

Total for 2021 $5,378

Replacement Year 2022Concrete Pavement - Power Wash & Seal (I) 27,362Handrails & Guardrails - Paint 7,191

Total for 2022 $34,553

Replacement Year 2023Exterior Siding - Painting (II) 37,696Exterior Siding - Replacement Phase (II) 20,802Parking Garage - Restripe 2,972Pool - Equipment - Heater 5,468Recreation Center - Equipment Renewal 7,666Roofing - Inspection (I) 3,066Roofing - Preformed Metal 36,820

Total for 2023 $114,489

Replacement Year 2024Exterior Siding - Painting (I) 37,376Exterior Siding - Replacement Phase (I) 21,322Rear Deck Membrane - Replacement 193,324

Total for 2024 $252,022

Replacement Year 2025Asphalt Walking Path - Seal Coat 2,715Concrete Pavement - Power Wash & Seal (I) 29,466

Page 29: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 29 of 75

Description Expenditures

Replacement Year 2025 continued...Pool - Equipment - Pump 3,122Roofing - Inspection (I) 3,222

Total for 2025 $38,524

Replacement Year 2026Landscape/Irrigation - Repair 12,801

Total for 2026 $12,801

Replacement Year 2027Canvas Canopy 3,936Exterior Lighting - Replacement 11,227Roofing - Inspection (I) 3,385

Total for 2027 $18,548

Replacement Year 2028Concrete Pavement - Power Wash & Seal (I) 31,731Exterior Siding - Painting (II) 42,649Exterior Siding - Replacement Phase (II) 23,536Handrails & Guardrails - Paint 8,339Pool - Equipment - Filter/Chlorinator 2,168Recreation Center - Equipment Renewal 8,673

Total for 2028 $117,097

Replacement Year 2029Asphalt Walking Path - Seal Coat 2,996Exterior Siding - Painting (I) 42,287Exterior Siding - Replacement Phase (I) 24,124Front Entry Decks - Re-Coat (I) 10,710Pool - Cover Replacement 4,557Pool - Equipment - Heater 6,341Pool - Liner Replacement 16,002Roofing - Inspection (I) 3,556

Total for 2029 $110,574

Page 30: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 30 of 75

Description Expenditures

Replacement Year 2030Bridge: Walking Path & Railings - Repairs 26,285Parking Garage - Restripe 3,532

Total for 2030 $29,817

Replacement Year 2031Concrete Pavement - Power Wash & Seal (I) 34,171Pool - Equipment - Pump 3,621Roofing - Inspection (I) 3,736

Total for 2031 $41,528

Replacement Year 2032Asphalt Walking Path - Repairs 18,610Concrete Walkways - Repair 13,528

Total for 2032 $32,139

Replacement Year 2033Asphalt Walking Path - Seal Coat 3,307Composition Roof - Replacement 754,826Concrete Curbing & Wheel-stops 6,869Exterior Siding - Painting (II) 48,253Exterior Siding - Replacement Phase (II) 26,628Gutters & Downspouts - Repair 47,177Mailboxes - Replacement 5,661Recreation Center - Equipment Renewal 9,813Roofing - Inspection (I) 3,925

Total for 2033 $906,460

Replacement Year 2034Canvas Canopy 4,679Concrete Pavement - Power Wash & Seal (I) 36,798Concrete Paving - Driveways & Parking Garage 86,062Exterior Siding - Painting (I) 47,844Exterior Siding - Replacement Phase (I) 27,294

Page 31: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 31 of 75

Description Expenditures

Replacement Year 2034 continued...Front Entry Decks - Repair 255,320Handrails & Guardrails - Paint 9,671

Total for 2034 $467,669

Replacement Year 2035Pool - Equipment - Heater 7,354Roofing - Inspection (I) 4,124

Total for 2035 $11,478

Replacement Year 2036Landscape/Irrigation - Repair 16,386Recreation Center - Interior Painting 4,064

Total for 2036 $20,451

Replacement Year 2037Asphalt Walking Path - Seal Coat 3,651Concrete Pavement - Power Wash & Seal (I) 39,628Exterior Lighting - Replacement 14,372Handrails & Guardrails - Repair 62,489Parking Garage - Restripe 4,199Pool - Equipment - Pump 4,199Pool Deck, Concrete - Repairs 8,868Roofing - Inspection (I) 4,333

Total for 2037 $141,738

Replacement Year 2038Exterior Siding - Painting (II) 54,594Exterior Siding - Replacement Phase (II) 30,127Key Card System - Add 18,970Pool - Equipment - Filter/Chlorinator 2,776Recreation Center - Equipment Renewal 11,102Roofing - Preformed Metal 53,326

Total for 2038 $170,895

Page 32: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 32 of 75

Description Expenditures

Replacement Year 2039Exterior Siding - Painting (I) 54,132Exterior Siding - Replacement Phase (I) 30,881Pool - Cover Replacement 5,833Pool - Liner Replacement 20,484Rear Deck Membrane - Replacement 279,990Roofing - Inspection (I) 4,552

Total for 2039 $395,872

Replacement Year 2040Concrete Pavement - Power Wash & Seal (I) 42,675Handrails & Guardrails - Paint 11,216

Total for 2040 $53,891

Replacement Year 2041Asphalt Walking Path - Seal Coat 4,030Canvas Canopy 5,562Pool - Equipment - Heater 8,528Roofing - Inspection (I) 4,782

Total for 2041 $22,902

No Replacement in 2042

Replacement Year 2043Concrete Pavement - Power Wash & Seal (I) 45,956Exterior Siding - Painting (II) 61,769Exterior Siding - Replacement Phase (II) 34,086Pool - Equipment - Pump 4,869Recreation Center - Equipment Renewal 12,561Roofing - Inspection (I) 5,024

Total for 2043 $164,266

Replacement Year 2044Asphalt Walking Path - Repairs 25,029

Page 33: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Annual Expenditure Detail

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 33 of 75

Description Expenditures

Replacement Year 2044 continued...Exterior Siding - Painting (I) 61,245Exterior Siding - Replacement Phase (I) 34,939Front Entry Decks - Re-Coat (II) 15,512Parking Garage - Restripe 4,991

Total for 2044 $141,715

Replacement Year 2045Asphalt Walking Path - Seal Coat 4,448Roofing - Inspection (I) 5,279

Total for 2045 $9,727

Page 34: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 34 of 75

Composition Roof - ReplacementAsset ID 1001

CapitalRoofing

Placed in Service November 2008Useful Life 25

Replacement Year 2033Remaining Life 17

1 Total @ $496,068.00Asset Cost $496,068.00

Percent Replacement 100%Future Cost $754,826.13

This provision funds for the composition roof, which is currently being installed in 2008 to replace the concrete tile roof on all five buildings.

According to the Association, there are approximately 46,581 square feet of the concrete tile roof.

MSR Services, Inc. performed an inspection on the roof, and indicated that the roof is concrete tiles over wood battens which are mechanically fastened through asphalt saturated felt into a plywood roof substrate. During the inspection, MSR provided the following information:

While the concrete tile might be sustaining its longevity as installed, the underlying system of battens and felt have run their life cycle.

Ventilation is non-existent at the structural members (cavity or interstitial space below deck) from the exterior wall to the peak. Ventilation appears to be challenged in that it does not meet one square foot in 150 square feet of attic/above ceiling air space.

Penetrating items through the roof deck do not appear to be detailed to a standard that resists the infiltration of water. Penetrating items through the roof assembly include plumbing vent pipes, exhaust vents for air transfer and exhaust vents for furnace, stove and other energized gases.

Walls between second floor decks (pony wall assembly) are capped with tile but in a manner such that there may be infiltration through fasteners. Also, transition points at the top and the bottom of these walls details appear to allow for the infiltration of water.

According to Scott Rich with MSR Services, Inc., the concrete tile roof is currently to be replaced with composition shingle roof. This roof replacement is currently in progress for 2008. A cost of $400,000 was provided by Scott for the replacement of concrete tile roof to composition roof.

According to the Association, the roof was completed in 2009.

Page 35: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 35 of 75

Composition Roof - Replacement continued...

Useful life estimates were provided by Board.

Roofing - Inspection (I)Asset ID 1026

Non-CapitalRoofing

Placed in Service January 2015Useful Life 2

Replacement Year 2017Remaining Life 1

1 Total @ $2,579.56Asset Cost $2,579.56

Percent Replacement 100%Future Cost $2,644.05

This provision funds for periodic inspection of the roofing, flashing, and related surfaces. This visual inspection is necessary to maintain the integrity of the roof and to insure against water penetration.

According to Scott Rich with MSR Services, Inc., the concrete tile roof is being replaced with composition shingle roof. This roof replacement is currently in progress in 2008.

According to the Association, roof replacements will not be complete until 2009; therefore, they would like roofing inspection to begin in 2012.

Roofing - Preformed MetalAsset ID 1002

CapitalRoofing

Placed in Service January 2007Useful Life 15Adjustment 1

Replacement Year 2023Remaining Life 7

5,000 SF @ $12.39Asset Cost $30,975.00

Percent Replacement 50%Future Cost $36,819.54

This provision funds for ongoing repairs to the preformed metal roofing as needed.

According to the Association, there are approximately 50 squares of the metal roofing or 5,000 square feet.

According to Micheline with Tt & L Sheet Metal Roofing (503-641-0552), the cost to replace

Page 36: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 36 of 75

Roofing - Preformed Metal continued...

the metal roofing is $8 to $10 per square foot.

According to Scott Rich with MSR Services, Inc., the preformed metal roof is in good condition, and will not be replaced during the replacement of the concrete tile roof. Scott recommended a useful life of every 15 years to do repairs and/or replacement if needed.

This work should be performed by a qualified roofing contractor.

Roofing - Total Current Cost $529,623

Page 37: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 37 of 75

Rear Deck Membrane - ReplacementAsset ID 1066

CapitalDecks

Placed in Service January 2009Useful Life 15

Replacement Year 2024Remaining Life 8

48 Each @ $3,305.62Asset Cost $158,669.76

Percent Replacement 100%Future Cost $193,323.70

This is a provision to fund for the rear decks at the second floor living units.

The association indicated that there are 48 decks on the second floor.

Schwindt and Company estimated the decks to measure 130 square feet each.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator.

The Association should obtain a bid to confirm this estimate.

Decks - Total Current Cost $158,670

Page 38: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 38 of 75

Exterior Lighting - ReplacementAsset ID 1019

CapitalLighting

Placed in Service January 2007Useful Life 10

Replacement Year 2017Remaining Life 1

23 Each @ $372.04Asset Cost $8,556.92

Percent Replacement 100%Future Cost $8,770.84

This is a provision to fund for the exterior lighting fixtures if needed.

According to the Association, there are 14 path lights, five parking lights at the garage; and four lights underneath the pedestrian deck; a total of 23 exterior lights..

Cost and useful life is based on estimates established on RS Means and/or the National Estimator.

Note: This provision is for an anticipated expense. If the cost to maintain the exterior lighting is determined to be different than the amount listed here, this study should be updated accordingly.

Lighting - Total Current Cost $8,557

Page 39: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 39 of 75

Canvas CanopyAsset ID 1035

CapitalEquipment

Placed in Service January 2014Useful Life 7Adjustment -1

Replacement Year 2020Remaining Life 4

1 Total @ $3,000.00Asset Cost $3,000.00

Percent Replacement 100%Future Cost $3,311.44

This is a provision to fund for the canvas canopy at the mailboxes.

According to Judy Saleg, the canvas has a useful life of five to seven year. According to the Association, this was replaced in 2014 for $2,880

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator. The Association should obtain a bid to confirm this estimate.

According to the Association, the canvas canopy was replaced in 2004.

Key Card System - AddAsset ID 1064

CapitalEquipment

Placed in Service January 2013Useful Life 25

Replacement Year 2038Remaining Life 22

1 Total @ $11,018.75Asset Cost $11,018.75

Percent Replacement 100%Future Cost $18,969.56

This provision is for the addition of a keycard entry system to the common recreation areas.

The Association should obtain a bid for this item.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator. The Association should obtain a bid to confirm this estimate.

Note: This is a provision for an anticipated expense. Should the Association find that the cost of this item is greater than or less than the amount provided for herein, this study should be updated to reflect the actual component cost.

Page 40: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 40 of 75

Recreation Center - Equipment RenewalAsset ID 1025

CapitalEquipment

Placed in Service January 2013Useful Life 5

Replacement Year 2018Remaining Life 2

1 Total @ $6,448.89Asset Cost $6,448.89

Percent Replacement 100%Future Cost $6,775.36

This provision creates a funding cycle to be used for renewal and/or replacement of exercise equipment in the recreation center if needed.

Useful life is based on estimates established on RS Means and/or the National Estimator.

Equipment - Total Current Cost $20,468

Page 41: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 41 of 75

Exterior Siding - Replacement Phase (I)Asset ID 1004

CapitalBuilding Component

Placed in Service January 2014Useful Life 5

Replacement Year 2019Remaining Life 3

1 Total @ $35,000.00Asset Cost $17,500.00

Percent Replacement 50%Future Cost $18,845.59

This is a provision to fund for the exterior cedar siding.

According to the Association, there is approximately 45,949 square feet of cedar siding at the buildings. There is a total of 11,350 square feet of the second floor deck siding (walls). There is a total of 1,130 square feet of the pool wall siding. There is a total of 479 square feet of the pool house siding. There is a total of 58,908 square feet of the cedar siding.

MSR Services, Inc. performed an inspection on sidings around the window areas and found potentials for water infiltration. MSR did not perform extensive evaluation or destructive testing on the cladding. A variety of locations throughout the structures show the wood siding has absorbed moisture to the point of the formation of rot. Gaps at the trim to fenestration have allowed for the infiltration of moisture.

MSR Services, Inc. indicated that the parapet wall assemblies between the second floor decks over living space have been aggressively strained with the addition of a roof diverter above the deck at a third-floor window. This diverter is intended to direct water to each end thus keeping it from proceeding over the third story window, landing upon the metal roof structure. This has loaded the parapet's protective cap. The parapet wall is roofed with tile, metal, and a barrier underneath. Those walls which have been reviewed by this Inspector have allowed for the infiltration of moisture underneath. A review of previous work orders clearly show that many challenges experienced within units located at the first or even second level occur at this juncture. With the volume of roof above and its water load being directed towards this wall assembly, MSR recommends a waterproof barrier system be designed to handle this extreme volume of water.

During Schwindt & Company's site visit, Scott Rich with MSR Services, Inc. indicated that the cedar siding has run its life cycle. There are holes in some of the siding. Scott provided an estimated replacement cost of $300,000 to $400,000 for the replacement of the siding within the next few years. Scott indicated that the cost includes $4,000 to $5,000 for design work.

Scott recommend replacing the siding in 2010.

Page 42: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 42 of 75

Exterior Siding - Replacement Phase (I) continued...

The Association has decided to do repairs as the siding is painted. The Association has approved $31,000 of repairs in 2012 and 2013.

The useful life estimates of this component are based on accepted industry estimates as established by the National Construction Estimator.

Exterior Siding - Replacement Phase (II)Asset ID 1052

CapitalBuilding Component

Placed in Service January 2013Useful Life 5

Replacement Year 2018Remaining Life 2

1 Total @ $35,000.00Asset Cost $17,500.00

Percent Replacement 50%Future Cost $18,385.94

This is a provision to fund for the exterior cedar siding.

According to the Association, there is approximately 45,949 square feet of cedar siding at the buildings. There is a total of 11,350 square feet of the second floor deck siding (walls). There is a total of 1,130 square feet of the pool wall siding. There is a total of 479 square feet of the pool house siding. There is a total of 58,908 square feet of the cedar siding.

MSR Services, Inc. performed an inspection on sidings around the window areas and found potentials for water infiltration. MSR did not perform extensive evaluation or destructive testing on the cladding. A variety of locations throughout the structures shows the wood siding has absorbed moisture to the point of the formation of rot. Gaps at the trim to fenestration have allowed for the infiltrations of moisture.

MSR Services, Inc. indicated that the parapet wall assemblies between the second floor decks over living space have been aggressively strained with the addition of a roof diverter above the deck at a third-floor window. This diverter is intended to direct water to each end thus keeping it from proceeding over the third story window, landing upon the metal roof structure. This has loaded the parapet's protective cap. The parapet wall is roofed with tile, metal, and a barrier underneath. Those walls that have been reviewed by this Inspector have allowed for the infiltration of moisture underneath. A review of previous work orders clearly show that many challenges experienced within units located at the first or even second level occur at this juncture. With the volume of roof above and its water load being directed towards this wall assembly, MSR recommends a waterproof barrier system be designed to handle this extreme volume of water.

Page 43: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 43 of 75

Exterior Siding - Replacement Phase (II) continued...

During Schwindt & Company's site visit, Scott Rich with MSR Services, Inc. indicated that the cedar siding have run its life cycle. There are holes in some of the siding. Scott provided an estimated replacement cost of $300,000 to $400,000 for the replacement of the sidings within the next few years. Scott indicated that the cost includes $4,000 to $5,000 for designs.

Scott recommend replacing the sidings in 2010.

The Association has decided to do repairs as the siding is painted. The Association has approved $31,000 of repairs in 2012 and 2013.

Useful life estimates of this component are based on accepted industry estimates as established by the National Construction Estimator.

Exterior Stairs- Replacement 2016Asset ID 1068

CapitalBuilding Component

Placed in Service January 2015Useful Life 1

Replacement Year 2016Remaining Life 0

1 Total @ $25,000.00Asset Cost $25,000.00

Percent Replacement 100%Future Cost $25,000.00

This is a provision to fund for the exterior stairs in 2016.

Exterior Stairs- Replacement 2017Asset ID 1069

CapitalBuilding Component

Placed in Service January 2017Useful Life 1

Replacement Year 2017Remaining Life 1

1 Total @ $18,000.00Asset Cost $18,000.00

Percent Replacement 100%Future Cost $18,450.00

This is a provision to fund for the exterior stairs in 2017.

Page 44: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 44 of 75

Front Entry Decks - Re-Coat (I)Asset ID 1028

Non-CapitalBuilding Component

Placed in Service January 2009Useful Life 10

Replacement Year 2019Remaining Life 3

784 SF @ $9.91Asset Cost $7,769.44

Percent Replacement 100%Future Cost $8,366.84

This component provides funding for re-coating the front entry decks.

The Association indicated that there is 784 square feet of the concrete pedestrian decks on the second floor.

According to Scott Rich, an additional coat of liquid membrane should be applied to the front entry decks every 10 years, after the replacement in 2009. Scott provided a cost of $5-$8 per square feet to re-coat the decks.

Front Entry Decks - Re-Coat (II)Asset ID 1039

Non-CapitalBuilding Component

Placed in Service January 2009Useful Life 10Adjustment 25

Replacement Year 2044Remaining Life 28

784 SF @ $9.91Asset Cost $7,769.44

Percent Replacement 100%Future Cost $15,511.65

This component provides funding for re-coating the front entry decks.

The Association indicated that there are 784 square feet of the concrete pedestrian decks on the second floor.

According to Scott Rich, an additional coat of liquid membrane should be applied to the front entry decks every 10 years, after the replacement in 2009. Scott provided a cost of $5-$8 per square feet to re-coat the decks.

Page 45: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 45 of 75

Front Entry Decks - RepairAsset ID 1007

CapitalBuilding Component

Placed in Service January 2009Useful Life 25

Replacement Year 2034Remaining Life 18

22 Total @ $7,441.02Asset Cost $163,702.44

Percent Replacement 100%Future Cost $255,319.94

This component provides funding for renewal of the concrete front entry decks, which is known as pedestrian decks in MSR Services, Inc.'s report.

According to Scott Rich, the pedestrian decks will be replaced in 2009, a cost of $5,000 plus $1,000 additional for rot repairs, per pedestrian deck, for a total cost of $6,000 per pedestrian deck.

According to Allen Zachary with Case Forensics, there are a total of 22 front entry decks.

MSR Services, Inc. performed an inspection to the pedestrian decks at the second level. MSR recommends protecting the decks leading to the entry of the second floor units in a similar fashion to those decks leading from the parking structure. In doing this, the system would need to be modified such that the structural metal would not be encapsulated unless all the oxidation has been terminated.

MSR Services, Inc. indicated that the concrete pedestrian decks leading from the parking structure to the respective units at the second floor entrances are not protected at this time. There are areas where the concrete intersects with a dissimilar material, which is allowing for the intrusion of water. Corrosion was observed at the metal surfaces along with intrusion through the concrete, as presented by staining on the underside of the pedestrian decking. Also, there appears to be ponding water at the concrete to steel juncture. Drainage and proper slope is questionable and to be determined. Transition from threshold to wall may be inadequately flashed to prevent the intrusion of water.

MSR Services, Inc. suggests that once the evaluation of the reinforcement is completed, and any repairs are completed, the concrete pedestrian deck should be coated with either an elastomeric pedestrian-grade material or polymer-modified reinforced cement-based slurry. This coating should prevent the infiltration of water by protecting the horizontal exposure of the decking. Also, this coating should provide a tread-surface with safety traction in its application.

Page 46: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 46 of 75

Handrails & Guardrails - RepairAsset ID 1011

Non-CapitalBuilding Component

Placed in Service January 2007Useful Life 30

Replacement Year 2037Remaining Life 21

1 Total @ $37,205.09Asset Cost $37,205.09

Percent Replacement 100%Future Cost $62,488.99

This provision is to repair all the exposed metal exterior handrails and guardrails at all common areas.

According to the Association, the guardrails at Building C and D are approximately 297 linear feet, the guardrail at the terrace of Building A and B is approximately 840 linear feet, the guardrails and handrails on the bridge and on top of the stairs are approximately 209 linear feet, the handrails on the stairs are approximately 676 linear feet, and the guard rail at the garage and upper decks is approximately 530 linear feet. There is a total estimated length of 2,552 linear feet of the handrails and guardrails.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator. The Association should obtain a bid to confirm this estimate.

Note: This is a provision for an anticipated expense. Should the Association find that the cost of this item is greater than or less than the amount provided for herein, this study should be updated to reflect the actual component cost.

Recreation Center - BathroomsAsset ID 1034

CapitalBuilding Component

Placed in Service January 2010Useful Life 15

Replacement Year 2025Remaining Life 9

1 Total @ $6,200.85Asset Cost $6,200.85

Percent Replacement 100%Future Cost $7,744.01

This is a provision to fund for the bathrooms in the recreation room.

During Schwindt & Company's site visit, there are two bathrooms in the recreation room.

According to the Association, one bathroom was renovated in 2010. The other will be

Page 47: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 47 of 75

Recreation Center - Bathrooms continued...

renovated in the 2013 planned renovation.

Useful life estimates are established on Fannie Mae Expected Useful Life Tables and Forms.

Building Component - Total Current Cost $294,446

Page 48: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 48 of 75

Asphalt Walking Path - RepairsAsset ID 1048

Non-CapitalGrounds Component

Placed in Service January 2007Useful Life 12Adjustment 1

Replacement Year 2020Remaining Life 4

5,055 SF @ $2.48Asset Cost $12,536.40

Percent Replacement 100%Future Cost $13,837.84

This is a provision to fund for major repairs to the asphalt walking path.

Cost is based on A per square foot estimate provided by Bob Knott (503-783-4308) with Kodiak Pacific Construction.

Useful Life estimates are established on RS Means and/or the National Estimator.

Bridge: Walking Path & Railings - Repairs

Asset ID 1059Non-Capital

Grounds ComponentPlaced in Service January 2009

Useful Life 20Adjustment 1

Replacement Year 2030Remaining Life 14

2 Total @ $9,301.28Asset Cost $18,602.56

Percent Replacement 100%Future Cost $26,284.93

This is a provision to repair the two bridges and railings at the walking path.

According to the Association, there are two bridges at the walking path. A repair cost of $7,500 per bridge; a total of $15,000 was to occur in 2009.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator. The Association should obtain a bid to confirm this estimate.

Page 49: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 49 of 75

Concrete Curbing & Wheel-stopsAsset ID 1014

CapitalGrounds Component

Placed in Service January 2007Useful Life 25Adjustment 1

Replacement Year 2033Remaining Life 17

1 Total @ $4,514.21Asset Cost $4,514.21

Percent Replacement 100%Future Cost $6,868.90

This provision is to repair or replace the continuous curb with an estimated length of 564 linear feet, and 118 wheel-stops per the Association.

The cost for this component assumes that half of the concrete wheel stops, and approximately 10% of the concrete curbing will require replacement in twenty-five years.

Concrete Parking Garage - RepairsAsset ID 1058

CapitalGrounds Component

Placed in Service January 2009Useful Life 1Adjustment 1

Replacement Year 2016Remaining Life 0

1 Total @ $3,069.41Asset Cost $3,069.41

Percent Replacement 100%Future Cost $3,069.41

This provision funds for the repair of the parking garage.

According to the Association, there is approximately 24,228 square feet of the parking garage, and 11,349 square feet of the parking area at each building; a total of 35,577 square feet of the concrete area.

According to Scott Rich with MSR Services, Inc., the concrete garage has cracks, and will be repaired. A proposal was provided by D&R Masonry Restoration, Inc. for repairs to the concrete garage. An estimated cost of $2,475 was provided by Dan Elkins with D&R Masonry Restoration, Inc. This repair will occur in 2009.

The cost estimate includes the following scope of work:

D&R will remove the existing spall as per conversation in two locations

Page 50: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 50 of 75

Concrete Parking Garage - Repairs continued...

Prep the rebar and treat it with a rust inhibitor to prevent further rusting of the steal.

D&R will install a patching mortar to the area and shape to match the existing surface.

The product that will be used for this repair is called Thorite by Thoro products.

Note: This repair is scheduled to occur once. The next repair is included in the Concrete Paving - Driveways & Parking Garage component.

Concrete Pavement - Power Wash & Seal (I)

Asset ID 1027Non-Capital

Grounds ComponentPlaced in Service January 2013

Useful Life 3Replacement Year 2016

Remaining Life 0

42,898 SF @ $0.55Asset Cost $23,593.90

Percent Replacement 100%Future Cost $23,593.90

This provision funds for periodic power-washing and sealing of the concrete driving and parking surfaces, the concrete pool deck area, and concrete walkway to remove grease stains and debris build-up as needed.

According to the Association, there is approximately 24,228 square feet of the parking garage; 11,349 square feet of the parking area at each building; 3,404 square feet of the pool deck concrete area; and 3,917 square feet of the concrete walkway; for a total of 42,898 square feet of the concrete area. Concrete pavement power washing was done in 2003 by an HOA volunteer.

The Association would like this component to occur every five years per Board meeting.

Cost is based on a per square foot estimate provided by Ken Verhaalen with Verhaalen Painting, Inc.

Page 51: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 51 of 75

Concrete Paving - Driveways & Parking Garage

Asset ID 1012Capital

Grounds ComponentPlaced in Service January 2009

Useful Life 25Replacement Year 2034

Remaining Life 18

35,577 SF @ $15.51Asset Cost $55,179.93

Percent Replacement 10%Future Cost $86,061.85

This provision funds for the partial replacement and/or repair of the common area driveways and the parking garage. Since the expected useful life of a typical concrete driveway and parking installation is greater than 30 years, this provision only funds for the replacement of a percentage of the total driveways and parking.

Routine maintenance and repair should occur on an ongoing basis throughout the life of the component.

According to the Association, there is approximately 24,228 square feet of the parking garage, and 11,349 square feet of the parking area at each building; a total of 35,577 square feet of the concrete area.

According to Scott Rich with MSR Services, Inc., the concrete garage has cracks, and will be repaired. A proposal was provided by D&R Masonry Restoration, Inc. for repairs to the concrete garage. An estimated cost of $2,475 was provided by Dan Elkins with D&R Masonry Restoration, Inc. The cost estimate include the following scope of work:

D&R will remove the existing spall as per conversation in two locations

Prep the rebar and treat it with a rust inhibitor to prevent further rusting of the steal.

D&R will install a patching mortar to the area and shape to match the existing.

The product that will be used for this repair is called Thorite by Thoro products.

Cost is based on a per square foot estimates provided by Kal's Paving.

The cost of $2,475 provided by D&R Masonry Restoration, Inc. is only for the repairs of the parking garage that will occur in 2009. Therefore, Kal's Paving cost is used in the study to budget for the repairs of the driveways along with the parking garage.

Page 52: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 52 of 75

Concrete Paving - Driveways & Parking Garage continued...

Useful life is based on estimates provided by RS Means and/or the National Estimator.

Concrete Walkways - RepairAsset ID 1013

Non-CapitalGrounds Component

Placed in Service January 2007Useful Life 25

Replacement Year 2032Remaining Life 16

3,917 SF @ $15.51Asset Cost $9,112.90

Percent Replacement 15%Future Cost $13,528.15

This provision funds for partial repairs and/or replace to the common area walkways. Since the expected useful life of a typical concrete walkway installation is greater than 30 years, this provision only funds for the replacement of a percentage of the total walkway.

According to the Association, there are approximately 3,917 square feet of the concrete walkway area.

Foundations around the trees are cracking, and will be repaired and/or remediated in 2010 per the Board.

During Schwindt & Company's site visit, Scott Rich with MSR Services, Inc. indicated that overgrown tree roots are causing damage to the concrete walkways. Scott suggests removing the trees.

Routine maintenance and repair should occur on an ongoing basis throughout the life of the component.

Cost is based on a per square foot estimate provided by Kal's Paving.

Useful life is based on estimates established on RS Means and/or the National Estimator.

Page 53: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 53 of 75

Landscape/Irrigation - RepairAsset ID 1063

CapitalGrounds Component

Placed in Service January 1999Useful Life 10

Replacement Year 2016Remaining Life 0

1 Total @ $10,000.00Asset Cost $10,000.00

Percent Replacement 100%Future Cost $10,000.00

This provision is for the renovation of the landscaping or repair of the irrigation system.

The Association plans to budget $10,000 every 10 years for this work.

Parking Garage - RestripeAsset ID 1046

CapitalGrounds Component

Placed in Service January 2010Useful Life 7Adjustment -1

Replacement Year 2016Remaining Life 0

1 Total @ $2,500.00Asset Cost $2,500.00

Percent Replacement 100%Future Cost $2,500.00

This is a provision to fund for the re-striping of the parking garage.

The Board would like this component to begin in 2009, and every seven years thereafter. The Board provided a cost of $2,500 for this work.

According to the Association, this was done in 2010.

Trees: Replace/RemediateAsset ID 1060

CapitalGrounds Component

Placed in Service January 2015Useful Life 1

Replacement Year 2016Remaining Life 0

1 Total @ $1,240.17Asset Cost $1,240.17

Percent Replacement 100%Future Cost $1,240.17

This is a provision to replace or remediate trees that are cracking the foundations, per Board

Page 54: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 54 of 75

Trees: Replace/Remediate continued...

meeting. The Board provided a cost of $1,000 for 2010.

According to the Association, trees will be replaced in 2012.

Grounds Component - Total Current Cost $140,349

Page 55: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 55 of 75

Asphalt Walking Path - Seal CoatAsset ID 1017

Non-CapitalStreets/Asphalt

Placed in Service January 2007Useful Life 4Adjustment 6

Replacement Year 2017Remaining Life 1

5,055 SF @ $0.43Asset Cost $2,173.65

Percent Replacement 100%Future Cost $2,227.99

This provision is to seal coat the asphalt walking path.

Maintenance of asphalt paving includes the periodic application of an asphalt emulsion sealer or "seal coat". This work should be performed by a licensed paving contractor.

Estimated area is per the Association.

Cost is based on a per square foot estimate provided by Bob Knott (503-783-4308) with Kodiak Pacific Construction.

Useful life is based on estimates established on RS Means and/or the National Estimator.

Streets/Asphalt - Total Current Cost $2,174

Page 56: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 56 of 75

Pool - Cover ReplacementAsset ID 1021

CapitalPool/Spa

Placed in Service January 2009Useful Life 10

Replacement Year 2019Remaining Life 3

1 Total @ $3,305.62Asset Cost $3,305.62

Percent Replacement 100%Future Cost $3,559.79

This provision funds for replacement of the swimming pool cover every ten years.

Per the Association, the cover was purchased in 2009.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator.

The Association should obtain a bid to confirm this estimate.

Note: This is a provision for an anticipated expense. Should the Association find that the cost of this item is greater than or less than the amount provided for herein, this study should be updated to reflect the actual component cost.

Pool - Equipment - Filter/ChlorinatorAsset ID 1022

CapitalPool/Spa

Placed in Service January 2007Useful Life 10Adjustment 1

Replacement Year 2018Remaining Life 2

1 Total @ $1,612.22Asset Cost $1,612.22

Percent Replacement 100%Future Cost $1,693.84

This provision funds for replacement of the swimming pool filter and chlorinator every five years.

According to Judy Saleg, the pool filter/chlorinator was replaced in 2007, and should last until 2017.

Page 57: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 57 of 75

Pool - Equipment - HeaterAsset ID 1067

CapitalPool/Spa

Placed in Service January 2006Useful Life 6Adjustment 5

Replacement Year 2017Remaining Life 1

1 Total @ $4,600.00Asset Cost $4,600.00

Percent Replacement 100%Future Cost $4,715.00

This provision funds for replacement of the swimming pool heater.

According to Judy Saleg, the pool heater and pump were replaced in 2006, and have a life of five to six years. The Association suggests scheduling this component to occur in 2017.

Pool - Equipment - PumpAsset ID 1023

CapitalPool/Spa

Placed in Service January 2006Useful Life 6Adjustment 7

Replacement Year 2019Remaining Life 3

1 Total @ $2,500.00Asset Cost $2,500.00

Percent Replacement 100%Future Cost $2,692.23

This provision funds for replacement of the swimming pool circulation pump.

According to Judy Saleg, the pool heater and pump were replaced in 2006, and have a life of five to six years. The Association suggests scheduling this component to occur in 2017.

Pool - Liner ReplacementAsset ID 1065

CapitalPool/Spa

Placed in Service January 2009Useful Life 10

Replacement Year 2019Remaining Life 3

1 Total @ $11,608.25Asset Cost $11,608.25

Percent Replacement 100%Future Cost $12,500.82

This provision funds for replacement of the swimming pool liner every ten years.

Page 58: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 58 of 75

Pool - Liner Replacement continued...

Per the Association, the liner was replaced in 2009.

The cost and useful life assumptions are based on accepted industry estimates as established by RS Means and/or The National Construction Estimator.

The Association should obtain a bid to confirm this estimate.

Note: This is a provision for an anticipated expense. Should the Association find that the cost of this item is greater than or less than the amount provided for herein, this study should be updated to reflect the actual component cost.

Pool Deck, Concrete - RepairsAsset ID 1030

Non-CapitalPool/Spa

Placed in Service January 2007Useful Life 30

Replacement Year 2037Remaining Life 21

3,404 SF @ $15.51Asset Cost $5,279.60

Percent Replacement 10%Future Cost $8,867.53

This is a provision to fund for partial repairs to the concrete pool deck.

According to the Association, there is approximately 3,404 square feet of the concrete pool deck.

Per Board meeting, the pool deck will be repaired in 2012.

Useful life is based on estimates established on RS Means and/or the National Estimator.

Cost is based on a per square foot estimate provided by Kal's Paving.

Recreation Center - Spa & SaunaAsset ID 1015

CapitalPool/Spa

Placed in Service January 2007Useful Life 5

Replacement Year 2016Remaining Life 0

1 Total @ $18,602.55Asset Cost $18,602.55

Percent Replacement 100%Future Cost $18,602.55

At the time of this report, the spa is closed. The Association is considering removing the

Page 59: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 59 of 75

Recreation Center - Spa & Sauna continued...

sauna and spa.

This provision is included to provide funding for major repair to the spa and sauna.

Per Board meeting, major repairs to the spa and sauna will occur in 2011, a cost of $15,000. This cost includes the repairs and/or replacements to the garden style window.

Pool/Spa - Total Current Cost $28,906

Page 60: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 60 of 75

Recreation Center - RenovationAsset ID 1062

CapitalInterior Furnishings

Placed in Service January 1983Useful Life 30

Replacement Year 2016Remaining Life 0

1 Total @ $27,546.87Asset Cost $27,546.87

Percent Replacement 100%Future Cost $27,546.87

This provision is for the renovation of the recreation center.

The Association plans to spend $25,000 in 2013.

Interior Furnishings - Total Current Cost $27,547

Page 61: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 61 of 75

Mailboxes - ReplacementAsset ID 1033

CapitalMailboxes

Placed in Service January 2007Useful Life 25Adjustment 1

Replacement Year 2033Remaining Life 17

1 Total @ $3,720.51Asset Cost $3,720.51

Percent Replacement 100%Future Cost $5,661.19

This is a provision to fund for the replacement of the mailboxes if needed.

Useful life and cost estimates are established on RS Means and/or the National Estimator.

Mailboxes - Total Current Cost $3,721

Page 62: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 62 of 75

Irrigation Project - Pump SystemAsset ID 1045

CapitalEquipment

Placed in Service December 2008No Useful Life

1 Total @ $49,606.80Asset Cost

Future Cost

Memo Only Per Board Meeting

This is a provision to fund for the pump system per Board.

According to the Association, the pump system is to pump water from the Columbia River to water plants. This is a three year process, and will cost $40,000. This component will need to be reviewed and updated when information becomes available.

Photovoltaic Electric ProjectAsset ID 1044

CapitalEquipment

Placed in Service December 2008No Useful Life

1 Total @ $62,008.50Asset Cost

Future Cost

Memo Only Per Board Meeting

This is a provision to fund for the photovoltaic electric project. The Association is planning to have a major electric system built. Cost of $50,000 was provided by the Board.

Swimming Pool - Solar PanelsAsset ID 1049

CapitalEquipment

Placed in Service December 2008No Useful Life

Asset Cost

Future Cost

Per Board meeting, the Association may invest in solar panels to heat the swimming pool. The Association will fund for the acquisition of this component. This component will need to be reviewed and updated when information becomes available.

Page 63: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 63 of 75

Equipment - Total Current Cost $0

Page 64: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 64 of 75

Exterior Siding - Painting (I)Asset ID 1006

Non-CapitalPaint

Placed in Service January 2014Useful Life 5

Replacement Year 2019Remaining Life 3

1 Total @ $30,676.20Asset Cost $30,676.20

Percent Replacement 100%Future Cost $33,034.91

This provision funds for the periodic painting of the exterior wood siding and related building components. The siding is a bevel cedar siding. This will include painting all exterior trim, doors, and any exposed wood structure, as well as renewal of all exterior caulking and sealants.

According to the Association, there is approximately 45,949 square feet of cedar siding at the five buildings. There is a total of 11,350 square feet of the second floor deck siding (walls). There is a total of 1,130 square feet of the pool wall siding. There is a total of 479 square feet of the pool house siding. There is a total of 58,908 square feet of the cedar siding.

According to the Association, the buildings will be painted over 2 years.

The cost is based on and estimate received by the Association from Jon Bake Painting.

Exterior Siding - Painting (II)Asset ID 1061

Non-CapitalPaint

Placed in Service January 2013Useful Life 5

Replacement Year 2018Remaining Life 2

1 Total @ $31,711.96Asset Cost $31,711.96

Percent Replacement 100%Future Cost $33,317.38

This provision funds for the periodic painting of the exterior wood siding and related building components. The siding is a bevel cedar siding. This will include painting all exterior trim, doors, and any exposed wood structure, as well as renewal of all exterior caulking and sealants.

According to the Association, there is approximately 45,949 square feet of cedar siding at the five buildings. There is a total of 11,350 square feet of the second floor deck siding (walls). There is a total of 1,130 square feet of the pool wall siding. There is a total of 479 square feet

Page 65: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 65 of 75

Exterior Siding - Painting (II) continued...

of the pool house siding. There is a total of 58,908 square feet of the cedar siding.

According to the Association, the buildings will be painted over 2 years.

The cost is based on and estimate received by the Association from Jon Bake Painting.

Handrails & Guardrails - PaintAsset ID 1029

Non-CapitalPaint

Placed in Service January 2010Useful Life 6

Replacement Year 2016Remaining Life 0

1 Total @ $6,200.85Asset Cost $6,200.85

Percent Replacement 100%Future Cost $6,200.85

This provision is to paint all the exposed metal exterior handrails and guardrails at all common areas. This procedure follows the same schedule as other exterior painting procedures.

According to the Association, the guardrails at Building C and D are approximately 297 linear feet, the guardrail at the terrace of Building A and B is approximately 840 linear feet, the guardrails and handrails on the bridge and on top of the stairs are approximately 209 linear feet, the handrails on the stairs are approximately 676 linear feet, and the guard rail at the garage and upper decks is approximately 530 linear feet. There is a total estimated length of 2,552 linear feet of the handrails and guardrails.

Per Board meeting, handrails and guardrails will be replacing with anodized painting surfaces, which only need touch up paint. A cost of $5,000 was provided by Board.

According to the Association, the railings on the stairways and by the pool were painted in 2010.

Useful life estimates are established on RS Means and/or the National Estimator.

Page 66: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 66 of 75

Recreation Center - Interior PaintingAsset ID

Non-CapitalPaint

Placed in Service January 2013Useful Life 10Adjustment 13

Replacement Year 2036Remaining Life 20

1 Total @ $2,480.35Asset Cost $2,480.35

Percent Replacement 100%Future Cost $4,064.34

This provision is for painting all the interior surfaces in the recreation center.

This assumes the recreation center is painted in the planned 2013 renovation.

A cost of $2,000 was provided by the Board.

Useful life is based on estimates established on RS Means and/or the National Estimator.

Paint - Total Current Cost $71,069

Page 67: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 67 of 75

Recreation Center - Garden Style Window

Asset ID 1037Capital

WindowPlaced in Service January 2013

Useful Life 25Adjustment 25

Replacement Year 2063Remaining Life 47

1 Total @ $3,720.51Asset Cost $3,720.51

Percent Replacement 100%Future Cost $11,874.74

This is a provision to fund for the garden style window at the recreation room. This assumes the windows are repaired in the 2013 renovation.

The useful life is based on estimates established on RS Means and/or the National Estimator.

Window - Total Current Cost $3,721

Page 68: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 68 of 75

Gutters & Downspouts - RepairAsset ID 1003

Non-CapitalGutters & Downspouts

Placed in Service November 2008Useful Life 25

Replacement Year 2033Remaining Life 17

1 Total @ $31,004.25Asset Cost $31,004.25

Percent Replacement 100%Future Cost $47,176.63

This component provides funding for the replacement of the gutters and downspouts.

All ongoing expenses for cleaning, maintenance and minor repairs should be included in the annual operating budget for the association.

According to the Association, there is approximately 1,889 linear feet of the gutter, and 519 linear feet of the downspouts.

During Schwindt & Company's site visit, Scott Rich with MSR Services, Inc. indicated that the gutters and downspouts will be replaced in 2008 during the roof replacement. Scott provided an estimated cost of $22,000 to $25,000 for the gutters and downspout replacement.

Useful life estimates coincides with the roofing replacement.

Gutters & Downspouts - Total Current Cost $31,004

Page 69: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point CondominiumsPortland, Oregon

Detail Report by Category

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 69 of 75

SignsAsset ID 1051

CapitalSigns

Placed in Service December 2008No Useful Life

Asset Cost

Future Cost

Memo Only per Board Meeting

This is a provision to fund for signage around the buildings, and a sign map. This component is unfunded at this time. This component will need to be reviewed and updated when information becomes available.

Signs - Total Current Cost $0

Page 70: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Category Detail Index

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 70 of 75

Asset IDDescription Replacement Page

Roofing1001 Composition Roof - Replacement 2033 34 of 751026 Roofing - Inspection (I) 2017 35 of 751002 Roofing - Preformed Metal 2023 35 of 75

Decks1066 Rear Deck Membrane - Replacement 2024 37 of 75

Lighting1019 Exterior Lighting - Replacement 2017 38 of 75

Equipment1035 Canvas Canopy 2020 39 of 751064 Key Card System - Add 2038 39 of 751025 Recreation Center - Equipment Renewal 2018 40 of 75

Building Component1004 Exterior Siding - Replacement Phase (I) 2019 41 of 751052 Exterior Siding - Replacement Phase (II) 2018 42 of 751068 Exterior Stairs- Replacement 2016 2016 43 of 751069 Exterior Stairs- Replacement 2017 2017 43 of 751028 Front Entry Decks - Re-Coat (I) 2019 44 of 751039 Front Entry Decks - Re-Coat (II) 2044 44 of 751007 Front Entry Decks - Repair 2034 45 of 751011 Handrails & Guardrails - Repair 2037 46 of 751034 Recreation Center - Bathrooms Unfunded 46 of 75

Grounds Component1048 Asphalt Walking Path - Repairs 2020 48 of 751059 Bridge: Walking Path & Railings - Repairs 2030 48 of 751014 Concrete Curbing & Wheel-stops 2033 49 of 751058 Concrete Parking Garage - Repairs 2016 49 of 751027 Concrete Pavement - Power Wash & Seal (I) 2016 50 of 751012 Concrete Paving - Driveways & Parking Garage 2034 51 of 751013 Concrete Walkways - Repair 2032 52 of 751063 Landscape/Irrigation - Repair 2016 53 of 75

Page 71: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Category Detail Index

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 71 of 75

Asset IDDescription Replacement Page

Grounds Component Continued...1046 Parking Garage - Restripe 2016 53 of 751060 Trees: Replace/Remediate 2016 53 of 75

Streets/Asphalt1017 Asphalt Walking Path - Seal Coat 2017 55 of 75

Pool/Spa1021 Pool - Cover Replacement 2019 56 of 751022 Pool - Equipment - Filter/Chlorinator 2018 56 of 751067 Pool - Equipment - Heater 2017 57 of 751023 Pool - Equipment - Pump 2019 57 of 751065 Pool - Liner Replacement 2019 57 of 751030 Pool Deck, Concrete - Repairs 2037 58 of 751015 Recreation Center - Spa & Sauna Unfunded 58 of 75

Interior Furnishings1062 Recreation Center - Renovation 2016 60 of 75

Mailboxes1033 Mailboxes - Replacement 2033 61 of 75

Equipment1045 Irrigation Project - Pump System Unfunded 62 of 751044 Photovoltaic Electric Project Unfunded 62 of 751049 Swimming Pool - Solar Panels Unfunded 62 of 75

Paint1006 Exterior Siding - Painting (I) 2019 64 of 751061 Exterior Siding - Painting (II) 2018 64 of 751029 Handrails & Guardrails - Paint 2016 65 of 75

Recreation Center - Interior Painting 2036 66 of 75

Window1037 Recreation Center - Garden Style Window 2063 67 of 75

Page 72: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

Association of Unit Owners of Columbia Point Condominiums Category Detail Index

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 72 of 75

Asset IDDescription Replacement Page

Gutters & Downspouts1003 Gutters & Downspouts - Repair 2033 68 of 75

Signs1051 Signs Unfunded 69 of 75

Total Funded Assets 41Total Unfunded Assets 6Total Assets 47

Page 73: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 73 of 75

Additional DisclosuresLevels of Service

The following three categories describe the various types of Reserve Studies from exhaustive to minimal.

I. Full: A Reserve Study in which the following five Reserve Study tasks are performed: ■ Component Inventory ■ Condition Assessment (based upon on-site visual observations) ■ Life and Valuation Estimates ■ Fund Status ■ Funding Plan

II. Update, With Site Visit/On-Site Review: A Reserve Study update in which the following five Reserve Study tasks are performed:

■ Component Inventory (verification only, not quantification) ■ Condition Assessment (based on on-site visual observations) ■ Life and Valuation Estimates ■ Fund Status ■ Funding Plan

III. Update, No Site Visit/Off Site Review: A Reserve Study update with no on-site visual observations in which the following three Reserve Study tasks are performed:

■ Life and Valuation Estimates ■ Fund Status ■ Funding Plan

Terms and Definitions

CASH FLOW METHOD: A method of developing a reserve Funding Plan where contributions to the reserve fund are designed to offset the variable annual expenditures from the reserve fund. Different reserve Funding Plans are tested against the anticipated schedule of reserve expenses until the desired Funding Goal is achieved.

COMPONENT: The individual line items in the Reserve Study developed or updated in the Physical Analysis. These elements form the building blocks for the Reserve Study. Components typically are: 1) association responsibility; 2) with limited Useful Life expectancies; 3) predictable Remaining Useful Life expectancies; 4) above a minimum threshold cost; and 5) as required by local codes.

COMPONENT INVENTORY: The task of selecting and quantifying reserve Components. This task can be accomplished through on-site visual observations, review of association design and organizational documents, a review of established association precedents, and discussion with appropriate association representative(s) of the Association or cooperative.

COMPONENT METHOD: A method of developing a reserve Funding Plan where the total contribution is based

Page 74: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 74 of 75

on the sum of contributions for individual Components. See Cash Flow Method.

CONDITION ASSESSMENT: The task of evaluating the current condition of the Component based on observed or reported characteristics.

CURRENT REPLACEMENT COST: See Replacement Cost.

DEFICIT: An actual or projected Reserve Balance that is less than the Fully Funded Balance. The opposite would be a Surplus.

EFFECTIVE AGE: The difference between Useful Life and Remaining Useful Life. Not always equivalent to chronological age since some Components age irregularly. Used primarily in computations.

FINANCIAL ANALYSIS: The portion of a Reserve Study where current status of the reserves (measured as cash or Percent Funded) and a recommended reserve contribution rate (reserve Funding Plan) are derived, and the projected reserve income and expense over time is presented. The Financial Analysis is one of the two parts of a Reserve Study.

FULLY FUNDED: 100% Funded. When the actual or projected Reserve Balance is equal to the Fully Funded Balance.

FULLY FUNDED BALANCE (FFB): Total accrued depreciation, an indicator against which actual or projected Reserve Balance can be compared. The Reserve Balance that is in direct proportion to the fraction of life “used up” of the current repair or Replacement Cost. This number is calculated for each Component, then added together for an association total. Two formulas can be utilized, depending on the provider’s sensitivity to interest and inflation effects. Note: Both yield identical results when interest and inflation are equivalent.

FFB = Current Cost X Effective Age / Useful Life

or

FFB = (Current Cost X Effective Age / Useful Life) + [(Current Cost X Effective Age /

Useful Life) / (1 + Interest Rate) ^ Remaining Life] - [(Current Cost X Effective Age / Useful Life)

/ (1 + Inflation Rate) ^ Remaining Life]

FUND STATUS: The status of the reserve fund as compared to an established benchmark such as percent funding. The Association appears to be adequately funded as the threshold method.

FUNDING GOALS: Independent of methodology utilized, the following represent the basic categories of Funding Plan goals:

■ Baseline Funding: Establishing a reserve funding goal of keeping the reserve cash balance above zero.

■ Full Funding: Setting a reserve funding goal of attaining and maintaining reserves at or near 100% funded.

Page 75: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 75 of 75

■ Statutory Funding: Establishing a reserve funding goal of setting aside the specific minimum amount of reserves required by local statues.

■ Threshold Funding: Establishing a reserve funding goal of keeping the Reserve Balance above a specified dollar or Percent Funded amount. Depending on the threshold, this may be more or less conservative than fully funding.

FUNDING PLAN: An association’s plan to provide income to a reserve fund to offset anticipated expenditures from that fund.

FUNDING PRINCIPLES: ■ Sufficient Funds When Required ■ Stable Contribution Rate over the Years ■ Evenly Distributed Contributions over the Years ■ Fiscally Responsible

LIFE AND VALUATION ESTIMATES: The task of estimating Useful Life, Remaining Useful Life, and repair or Replacement Costs for the reserve Components.

PERCENT FUNDED: The ratio at a particular point of time (typically the beginning of the Fiscal Year) of the actual or projected Reserve Balance to the Fully Funded Balance, expressed as a percentage.

PHYSICAL ANALYSIS: The portion of the Reserve Study where the Component Inventory, Condition Assessment, and Life and Valuation Estimate tasks are performed. This represents one of the two parts of the Reserve Study.

REMAINING USEFUL LIFE (RUL): Also referred to as “Remaining Life” (RL). The estimated time, in years, that a reserve Component can be expected to continue to serve its intended function. Projects anticipated to occur in the initial year have “zero” Remaining Useful Life.

REPLACEMENT COST: The cost of replacing, repairing, or restoring a reserve Component to its original functional condition. The Current Replacement Cost would be the cost to replace, repair, or restore the Component during that particular year.

RESERVE BALANCE: Actual or projected funds as of a particular point in time that the Association has identified for use to defray the future repair or replacement of those major Components which the Association is obligated to maintain. Also known as reserves, reserve accounts, or cash reserves. Based upon information provided and not audited.

RESERVE PROVIDER: An individual that prepares Reserve Studies.

RESERVE STUDY: A budget planning tool which identifies the current status of the reserve fund and a stable and equitable Funding Plan to offset the anticipated future major common area expenditures. The Reserve Study

Page 76: ASSOCIATION OF UNIT OWNERS OF COLUMBIA POINT … Pt... · The terms RS Means, National Construction Estimator, and Fannie Mae Expected Useful Life Tables and Forms refer to

SCHWINDT & CO. RESERVE STUDY SERVICES

PAGE 76 of 75

consists of two parts: the Physical Analysis and the Financial Analysis.

RESPONSIBLE CHARGE: A reserve specialist in Responsible Charge of a Reserve Study shall render regular and effective supervision to those individuals performing services which directly and materially affect the quality and competence rendered by the reserve specialist. A reserve specialist shall maintain such records as are reasonably necessary to establish that the reserve specialist exercised regular and effective supervision of a Reserve Study of which he was in Responsible Charge. A reserve specialist engaged in any of the following acts or practices shall be deemed not to have rendered the regular and effective supervision required herein:

■ The regular and continuous absence from principal office premises from which professional services are rendered, except for performance of field work or presence in a field office maintained exclusively for a specific project;

■ The failure to personally inspect or review the work of subordinates where necessary and appropriate;

■ The rendering of a limited, cursory, or perfunctory review of plans or projects in lieu of an appropriate detailed review;

■ The failure to personally be available on a reasonable basis or with adequate advance notice for consultation and inspection where circumstances require personal availability.

SPECIAL ASSESSMENT: An assessment levied on the members of an association in addition to regular assessments. Special Assessments are often regulated by governing documents or local statutes.

SURPLUS: An actual or projected Reserve Balance greater than the Fully Funded Balance.The opposite would be a Deficit.

USEFUL LIFE (UL): Total Useful Life or depreciable life. The estimated time, in years, that a Reserve Component can be expected to serve its intended function if properly constructed in its present application or installation.