assuring sterility – a cmos approach
TRANSCRIPT
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 1/57
A3P 16th Annual conference
November 2012
Assuring sterility – A CMO’s approach
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 2/57
2 Confidential
Introduction
Patheon Inc. is a leading global provider of contract development andmanufacturing services to the global pharmaceutical industry.
We provide products and services to approximately 300 of the world's leadingpharmaceutical and biotechnology companies.
Our services range from preclinical development through commercial
manufacturing of a full array of solid and sterile dosage forms, includingsoftgels.
As the site Microbiologist at Patheon UK, (based in Swindon) I amresponsible for the Microbiology and sterility assurance functions at two sites,
serving a total of 10 sterile filling lines and 3 non sterile filling lines for bothcommercial and pre-clinical development batches.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 3/57
3 Confidential
Assuring sterility – Introduction
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 4/57
4 Confidential
Assuring sterility – A CMO’s approach
Our goal in the production process is to assure the absence of microorganisms from every container. However, what available means do wehave to demonstrate such an absolute negative?
• Sterility testing - is severely limited statistically (20 containers tested perbatch)
• Media fills (process simulations) - are point in time assessments of thecapabilities of an aseptic process and even then only support a maximumcontamination rate, not a level of sterility assurance.
• Environmental monitoring - can only recover a small percentage of themicroorganisms present. (contact plates recover an average of 29% of S.
epidermidis from a stainless steel surface)
Absence of growth does not mean the absence of microorganisms!
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 5/57
5 Confidential
Assuring sterility – A CMO’s approach
SterileContainer
Sterile
Closure
SterileExcipient
Sterilefinal
product Aseptic
processing
Drugproduct
Container
Closure
Excipient
Sterilisation
Sterilisation
Sterilisation
Sterilisation
Steriledrug
product
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 6/57
6 Confidential
Assuring sterility – A CMO’s approach
The essence of aseptic processing is the assembly of previously sterilised
materials into a sealed container using procedures, controls and equipment that preserves their most
critical attribute - sterility
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 7/577 Confidential
Assuring sterility – A CMO’s approach
Six blind men and an elephant!
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 8/578 Confidential
Assuring sterility – A CMO’s approach
The six pillars of a robust aseptic process:
–Facilities design
–HVAC validation –Material / component transfer
–Process simulation (media fills)
–Personnel training & monitoring
–Environmental monitoring
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 9/579 Confidential
Assuring sterility – A CMO’s approach
Like the elephant, theaseptic process must
be considered
holistically
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 10/5710 Confidential
Assuring sterility – Facility and design
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 11/5711 Confidential
Assuring sterility – Facility and design
In terms of the general design of cleanrooms, it is imperative that:
• They are built of an airtight structure
• As a minimum it should be an ISO 5 / Grade A environment
• The internal surfaces should be smooth and suitable for cleaning
•
The internal surface finish should be sufficiently resilient to resist chippingor powdering
• The surfaces should be resistant to the cleaning agent used.
The designs for manned cleanrooms have undergone constant revisions with
many of these designed to increase the separation between the operator andthe aseptic portions of the process.
The culmination of this progression is the closed isolator which affords thehighest degree of physical separation from the operator.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 12/5712 Confidential
“Open” Gowned Operator Access
Increasing confidence in sterility assurance
Reducing
probabilityof unitsbeingcontaminated
The Aseptic Processing Spectrum
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 13/5713 Confidential
Assuring sterility – Facility and design
RABS = R estricted Access Barrier System
Process improvements like RABS are aimed at
separating people from the process.
If successful the risk posed by people
contaminating the area will be greatly reduced
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 14/5714 Confidential
Assuring sterility – Facility and designPatheon RABS approach
Filling Line
HEPA
Grade AFixed BarriersGlove ports
Overspill of Grade A Air below thecritical zone of operation
HEPA
HEPA HEPA HEPA HEPA
“Open operation” Doors can be opened butonly for predefined / risk
assessed activities
Grade Btraditional cleanroom
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 15/5715 Confidential
Assuring sterility – HVAC
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 16/5716 Confidential
Assuring sterility – HVAC
The HVAC (Heating, Ventilation and Air Conditioning) system controls the roomparameters including temperature and humidity.
This is important not only for operator comfort but also for minimising microbialcontamination.
– High temperatures can lead to excessive perspiration which can reduce the efficiencyof the cleanroom suit and result in the increase of shedding of micro-organisms
– Certain mould species cannot grow in areas of low humidity, therefore keeping theroom humidity low will ensure that contamination will be kept to a minimum.
Guidance would suggest that the temperature should be maintained at 18oC ±
2oC and humidity at 45% ± 15
We use a building management system to control these parameters constantlyto show that the room is in control
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 17/57
17 Confidential
Assuring sterility - HVAC
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 18/57
18 Confidential
Assuring sterility – Material and Component transfer
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 19/57
19 Confidential
Assuring sterility – Material and Component transfer
Materials and components should wherever possible enter your cleanroom as
sterile, in order to achieve this they can go via a hierarchy of controls whichaims to eradicate the microbial contamination.
– Autoclaving – usually at 121oC for a minimum of 15 minutes (validated bydemonstration of a 106 log reduction of a biological indicator)
– De-pyrogenation – (validated by demonstration of a reduction of endotoxin level)
–
Gamma irradiation – usually 25kGy (validated by dose mapping) – Ethylene Oxide - (validated by demonstration of a 106 log reduction of a biological
indicator)
• Whatever method you use you must ensure that all sterilisation andsanitisation processes are properly validated
• Recognise that premium equipment, package components and materialsshould offer enhanced reliability over lesser quality items.
• Aim to reduce the assembly time required for all sterilised materialsthrough pre-fabrication or use of disposable assemblies.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 20/57
20 Confidential
Assuring sterility – Material and Component transfer
How the material has been sterilised will determine how it enters thecleanroom:
• In the ideal situation some components will be steam sterilized directly intothe Grade B cleanroom (the problem here will be how to get it to the Grade
A environment (we use Grade A mobile LAF carts)).
• Many others arrive pre-sterilized (irradiation or EtO) and enter the via aseries of airlocks.
Patheon procedure requests that components arrive sealed inside 3 PE bags.
This allows us to operate an effective decontamination process that controlsthe risks posed by the outer surfaces of these items.
– Eg. Post sterilization the components usually arrive inside a cardboard box;cardboard can get damp during transport and can allow proliferation of moulds.
– Moulds are a risk to our processes.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 21/57
21 Confidential
Assuring sterility – Material and Component transfer
Support Area
Grade C Grade BGrade A
(eg RABS)
1 2
Remove Cardboard Box Vacuum clean if dust presentDisinfect Bag
Remove Outer Bag ANDDisinfect Inner Bag
Remove Outer BagOrDisinfect Outer Bag
Contaminationon outersurface
Nocontamination
Process for transfer of pre-sterilised components:
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 22/57
22 Confidential
Assuring sterility – Material and Component transferComponent Chute
FILLINGLINE
HEPA HEPA
Overspill of Air
Component chute pivots toopen & close
Positioned relatively high toprevent operator leaning in
Components opened in
“outer A” and poured downthe chute. Chute closesimmediately
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 23/57
23 Confidential
Assuring sterility – Media fill simulations
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 24/57
24 Confidential
Assuring sterility – Media fill simulations
The main contamination risk evaluation tool capable of including all thedifferent aspects and variables of the aseptic process is a process simulation (ormedia fill).
The design of a media fill simulation should consider the following factors:
• Media selection
• Frequency and number of runs
• Size and duration of runs
• Line speed, container size, closure type and fill volume
• Process/line configuration set up• Number of persons, activities and interventions (including line clearance)
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 25/57
25 Confidential
Assuring sterility – Media fill simulations
Choosing the media
The media fill should mimic as closely as possible your production of product.
If you have a powder filling process you should use a sterile placebo (we usePEG, polyethylene glycol)
As most clean room contaminants are strict or facultative aerobes any step inthe process where oxygen content is kept low could cause a potential growthinhibition and could mask contamination routes. (ie by the use of Nitrogen).If your process does use Nitrogen then this should be substituted during themedia fill with compressed air.
If this is not possible then evidence that growth of typical processcontaminants is not affected by this step should be considered.
If on the other hand your manufacturing process is a totally anaerobicprocess then you should consider the use of an anaerobic media such as Alternative Fluid Thioglycollate medium
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 26/57
26 Confidential
Assuring sterility – Media fill simulations
Frequency and number of runs
At least three consecutive separate successful runs are necessary for:
• Initial line qualification
• Revalidation following major changes to the equipment and/or process• Whenever there are doubts about the ability of the aseptic process toexclude contamination (extended shutdowns, trends in environmentalmonitoring, sterility test failures etc)
For routine re-qualification, one run per line with a semi-annual frequency (ortwice a year, as reported in the Annex 1) is recommended.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 27/57
27 Confidential
Assuring sterility – Media fill simulations
Size and duration of runs
Ideally, the most accurate simulation would be to mimic exactly the commercialprocess in terms of batch size and total duration. In practice, provided that theyaddress all the potential risks of contamination occurring during commercialproduction a different model can be used.
5,000 to 10,000 units is a generally acceptable starting point for run size (FDA guidance), however, for commercial products with batch sizes much bigger than10,000 units it could be difficult to justify that a simulation run smaller than10,000 units is considered representative of the actual process.
The run size must be big enough to allow all of the manipulations andinterventions occurring during the commercial process to be captured.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 28/57
28 Confidential
Assuring sterility – Media fill simulations
Size and duration of runs
From a practical point of view the problem is how to combine a duration equalor longer than the longest commercial process with a media fill run size that ismuch smaller than the product batch size.
At Patheon we perform the process simulation running the line intermittentlytaking care to include line set up, all the planned interventions and maximumoperator levels.
Interventions
Interventions are generally divided into two main categories:
• Intrinsic to the process (normal interventions)
• Extrinsic to the process (non-routine interventions)
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 29/57
29 Confidential
Assuring sterility – Media fill simulations
Routine Interventions
These include all the interventions that are necessary for running the processas it is designed.
• Line set up
•
Aseptic connection(s)• Container/Closure feeding
• Product sampling
• Weight checks
• Environmental monitoring
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 30/57
30 Confidential
Assuring sterility – Media fill simulations
Non routine interventions
These include all the other interventions that are not strictly necessary forrunning the process, but that can occur due to expected or unexpectedproblems during the operation.
• Removal of jammed containers/closures
• Removal of broken containers/product residues
• Replacement of a dosing device
• Adjustment to the line set-up (guides, star wheels etc)
• Breakdowns (sensors, switches, belts etc)
The ‘perfect’ intervention is one that doesn’t exist
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 31/57
31 Confidential
Assuring sterility – Media fill simulationsInterventions into the RABS
A standard list of pre assessed interventions is published for each RABS
Each new intervention must be risk assessed prior to being performed. A. Amount of microbial contamination on source; 0-2 (eg a sterilized tool or a person’s hand)
B. Risk of dispersion, 0-2 (vigorous movements required. Working above the product or product handling?)
C. Proximity to product, 0-2 (distant from the product or close by?)
D. Effectiveness of control measures, 0-2 (localised clean, discard of exposed product & components)
A x B x C
A x B x C x D
Risk posed by intervention
Residual risk after controlmeasures taken
Defines controlsrequired e.g.•Terminate the batch•Localised clean
H, M, L or NDefines the EMRequired e.g.•Take fingerdabs•Take extrasterility samples
Duration defined
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 32/57
32 Confidential
Assuring sterility – Media fill simulations
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 33/57
33 Confidential
Assuring sterility – Facility and designExample of an intervention
M 302M 303
L 304N 305
H 301Codes are located oneach door of the RABS
These are the onlyroutine interventionsthat the operator canperform.
The number and typesof interventions arecompared during batch
release to those thathave been performedduring a Media Fill
Colour indicatesRisk and indicateshow to perform theintervention
Letters indicatesthe residual risk after the correctiveactions are takenand specifies whatEM is required
Numbers are linkedto a writtendescription of the interventionwithin the SOP andthe batch record
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 34/57
34 Confidential
Assuring sterility – Facility and designIntervention Matrix
Colour = Risk BlueDo not record
GreenRecord in BMR
OrangeRecord in BMR
RedRecord in BMR
Sanitise HandsUse glove ports
Use tools
Sanitise HandsUse glove ports
or hatchUse tools
Sanitise HandsOpen door or use
hatchUse tools
Sanitise HandsOpen door or use
hatchUse hands
Also how it isdone
Code = Risk remaining afterthe intervention
Code specifies
the EM andsamples required
N = negligible
No EM or Samples
L = Low
No EM or Samples
M = Medium
Finger-dabs
H = HighFinger-dabs,
sterility test samples
Maximumallowed time is
specified
Duration Exceeded
No action required
Duration Exceeded
BNF
Duration Exceeded
BNF
Duration Exceeded
BNF + Risk Assessment
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 35/57
35 Confidential
Media fill
Intervention
checklist
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 36/57
36 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 37/57
37 Confidential
Assuring sterility – Training of personnel
The biggest source of contamination in a cleanroom is people, and levels of contamination will be highest when their training is poor.
Gowns, masks, gloves and goggles can reduce the incidence of contaminationbut the risk remains.
The closer the people get to the product and the more they interact with theline and the product the more likely that contamination will be transferred.
It is therefore essential that adequate training is conducted before anindividual is allowed to enter the cleanroom to perform aseptic manipulations.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 38/57
38 Confidential
Assuring sterility – Training of personnel
As a minimum the training of the operator should include education in:
• GMP
• Personal hygiene
• Gowning and comportment training
• Basic Microbiology• Knowledge of how a cleanroom functions
• The impact their behaviours can have on the product
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 39/57
39 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 40/57
40 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 41/57
41 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 42/57
42 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 43/57
43 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 44/57
44 Confidential
Assuring sterility – Training of personnel
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 45/57
45 Confidential
Assuring sterility – Environmental monitoring
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 46/57
46 Confidential
Introduction
• The Patheon site at Swindon has ten Grade A (Class 100) manufacturinglines.
• Environmental monitoring is performed at defined frequencies and locationsusing Settle plates, Active air samples and contact plates.
• The locations for the EM monitoring has been defined based on risk assessment of the operation in conjunction with smoke visualisationfootage and trend data.
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 47/57
47 Confidential
Environmental monitoring - Frequency
Grade A B
Settle plates Continuous monitoring Each operational shift
Contact plates End of eachbatch/campaign
Daily
Active air sample Every shift Each operational shift
Routine Finger Dab After every exit After every exit
Intervention Finger Dab After every high andmedium risk intervention
N/A
Sleeve monitoring At the end of each entry ahigh risk intervention is
performedN/A
Gown Monitor After every exit After every exit
Swabs End of eachbatch/campaign
N/A
(An operational shift is defined as an 8 hour period)
l h h l
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 48/57
48 Confidential
Environmental monitoring – Choosing the location
EM locations are primarily selected based on an assessment of the processwith respect to risk from microbial contamination using the followingequation:
Risk from microbial contamination (Risk rating) = A x B x C x D
Where:
• A = Microbial contamination on, or in, a source.
• B = Ease of dispersion and transfer of contamination.
• C = Proximity and ease of contaminating source from the critical area.
• D = Effectiveness of contamination control method.
E i l i i Ch i h l i
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 49/57
49 Confidential
Environmental monitoring – Choosing the location
A committee should be set up to carry out the risk assessment and comprisethe following people:
– Risk management expert
– Microbiologist
–
Quality Assurance manager – Facilities manager
– Production manager
The risk scores should be assigned to hazards by an aggregation of opinion
from the committee individuals and you should all establish a method of scoring to suit your facility.
We use the scoring system 0 – 2 with
0 = nil, 0.5 = very low, 1.0 = low, 1.5 = medium and 2.0 = high
E i l i i Ch i h l i
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 50/57
50 Confidential
Environmental monitoring – Choosing the locations
Environmental monitoring is increased or decreased basedon the risk assessment score. ie Red ratings would requireenvironmental monitoring to be performed during thatactivity or intervention
E i t l it i Ch i th l ti
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 51/57
51 Confidential
Environmental monitoring – Choosing the locations
• The number of points to be sampled in a given area should be related torisk, therefore the sampling points should be concentrated in the criticalareas, and as the risk of contamination in the surrounding areas becomesless (ie corridors and other support areas) then there should be fewersampling points.
• Transfer areas may be the exception and require more sampling because of the higher risk associated with the materials and personnel that moving tothe critical area.
E i t l it i Ch i th l ti
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 52/57
52 Confidential
Environmental monitoring – Choosing the locations
E i t l it i Ch i th l ti
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 53/57
53 Confidential
Environmental monitoring – Choosing the locations
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 54/57
54 Confidential
Assuring sterility – Conclusion
A i t ilit C l i
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 55/57
55 Confidential
Assuring sterility – Conclusion
Like the elephant, theaseptic process must
be considered
holistically
Thank o fo listening!
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 56/57
56 Confidential
Thank you for listening!
References
7/29/2019 Assuring sterility – A CMOs approach
http://slidepdf.com/reader/full/assuring-sterility-a-cmos-approach 57/57
References
• Risk Management of Contamination (RMC) During Manufacturing Operations In Cleanrooms – TechnicalMonograph No. 14 by the Pharmaceutical and Healthcare sciences society (PHSS) and the Scottish society forcontamination control