asta accelerator directorate review project plan and es&h carsten hast may 20, 2014
DESCRIPTION
ASTA Project Milestones Beam line components -Overall beam line layout done Ready to order bellows this week (eta mid July) -Designed sample chamber (going to purchasing this week, installation ~ Aug. 4 th ) Motorized stages to be ordered this week (eta mid July) -Designing diagnostics chamber (no long lead items) -Designing detector chambers (no long lead items) Screens and reflecting mirrors, Faraday cup etc. available -Various support stages are in fabrication (T-1 and various supports) (June-July) -Ion pumps and controllers are available: surplus from NLCTA -Turbo pump(s) need to be ordered soon Laser parts -Ready to order, details in Ryan’s talk Modulator stabilization available in July (Minh’s talk) 3TRANSCRIPT
UED @ ASTAAccelerator Directorate ReviewProject Plan and ES&HCarsten HastMay 20, 2014
UED @ ASTA Project Milestones
• Overall Schedule- Started April 2014
- Ends September 30th 2014 with results
• ASTA Infrastructure- General layout and consensus what to do agreed upon in late April
• New optical tables, mini girders, new gun location, support stages, various chambers, etc.
• New AC design and installation for laser room
• Relocate some LCW feeds, 110V outlets
• Improve ventilation in ASTA
- Moved X-band devices (Done)
- AC project is in purchasing (eta mid August)
- Mini girders (June 13th)
- Optical benches (June 13th )
2
UED @ ASTA Project Milestones
• Beam line components- Overall beam line layout done
• Ready to order bellows this week (eta mid July)
- Designed sample chamber (going to purchasing this week, installation ~ Aug. 4th)
• Motorized stages to be ordered this week (eta mid July)
- Designing diagnostics chamber (no long lead items)
- Designing detector chambers (no long lead items)
• Screens and reflecting mirrors, Faraday cup etc. available
- Various support stages are in fabrication (T-1 and various supports) (June-July)
- Ion pumps and controllers are available: surplus from NLCTA
- Turbo pump(s) need to be ordered soon
• Laser parts- Ready to order, details in Ryan’s talk
• Modulator stabilization available in July (Minh’s talk)
3
UED @ ASTA Installation Schedule
• Infrastructure work June 16th - June 27th - During night and weekend will operate X-band (most of the time)
- Remove old laser optics infrastructure
- Move gun
- Move LCW
- Install mini girders
- Install new optical tables (maybe a shelve over one)
- Provide plenty of 110V outlets
- Improve ventilation in ASTA
- Additional penetration
- Pull additional cables
- More Ethernet
4
UED @ ASTA Installation Schedule
• Cathode laser work 2 weeks in July- During night and weekend will operate X-band (most of the time)
- First round of controls work for motors, cameras, etc.
- Install existing GTL detector chamber for testing beam line
- Test the new stable modulator voltage with beam (Minh’s talk)
• Turn on new AC (August 18)
• Experiment laser work 2 weeks in August- During night and weekend will operate X-band (most of the time)
- Install all new chambers and complete beam line
- Finish controls work for motors, cameras, etc.
• Commissioning starts September 1st (latest)
5
UED @ ASTAWhat’s Missing?
• Controls Work- In June: Need to layout what we need, want and how to do it
- Preliminary work in July
- Commissioning in August
• RF / Laser Timing - Need a schedule (Joe F.)
• Better M&S estimate, both what else we need and overall costs
• Better labor estimate, both what else we need and overall costs
6
UED @ ASTA ES&H
• ASTA is really small- Egress issues were discussed and agreed upon with Fire Marshall
- Ergonomics
• LCW and electricity will be relocated to maximize space around laser tables
• X-Band table was raised to allow some room under it for the detectors
• Cryo-stand was moved to increase walking space
• Unnecessary equipment was and will be removed
• Cables and hoses were and will be rerouted to minimize obstruction in bunker
• New lights were installed
• BIO Reviews• X-Band table (done)
• AC Project (partly done)
• Optical tables and mini girder (needs to start soon)
• Location of PPS devices review late June
• Laser SOP update in July
• Radiological Review has started- Results June 16th
• Safety Assessment Document Review has started - Signatures by July 14th
7
UED @ ASTA Project Plan and ES&H Summary
• Most critical items have been/will be ordered this week
• Installation will allow existing programs to continue
• Schedule has not much float
Let’s all work together for:
Want UED? Come to SLAC!
8
UED @ ASTA Layout
9