GLOBAL SOLUTIONS STORAGE TANKAGE EQUIPMENT Ateco Tank Technology Company Presented by: Brian Quinn B.Sc. C.Eng. – Director International Operations - Ateco UK Ltd.

Upload: brian-quinn

Post on 12-Jul-2015

217 views

Category:

Engineering


4 download

TRANSCRIPT

Page 1: Ateco dome  power point presentation   master

GLOBAL

SOLUTIONS

STORAGE

TANKAGE

EQUIPMENT

Ateco Tank Technology Company

Presented by: Brian Quinn B.Sc. C.Eng. – Director International Operations - Ateco UK Ltd.

Page 2: Ateco dome  power point presentation   master

Ateco Tank Technology Company

Introduction to ATECO

Page 3: Ateco dome  power point presentation   master

• Ateco specialise in the Design and Manufacture of Storage Tankage

Equipment.

• we have been in business for more than 30 years.

• we manufacture all our Storage Tankage Products at our modern

fully automated facilities in Turkey

• we are the supplier of choice for most of the international operating

companies

• we do not outsource manufacturing and seek to source all material

from within Europe.

• we also have an office in the UK – Ateco UK Ltd.

• we are the only company of its type in the world that can claim to

manufacture all the standard equipment on an above ground

hydrocarbon liquid storage tank

Ateco Tank Technology Company

Page 4: Ateco dome  power point presentation   master

Ateco Tank Technology Company

• Ateco employs over 100 people at our Head Office and

Manufacturing Plants in Turkey and UK including a

worldwide network of agents and distributors who

provide expert knowledge and customer support

• Ateco limit our scope of supply to the “first flange “on

the tank, therefore, if the equipment is on the tank then

it is within our normal scope of supply – we are a supply

only company and do not take on site installation work.

• Ateco operate within the quality guidelines of ISO 9001

• Ateco Design and Manufacture storage tank equipment

to most internationally recognised codes, e.g. API, BS,

ISO, ASTM, ASME, NFPA11, AWWA and the various

Certification Engineer requirements such as Lloyds,

SGS, DNV, etc.

Page 5: Ateco dome  power point presentation   master

Ateco Tank Technology CompanyAteco design and supply a complete range of storage tankage products and services: including:

aluminum internal floating roofs – pontoon and full contact

primary and secondary seal systems for internal and external floating roof tanks

roof drain systems for external floating roof tanks

floating suction units for fixed roof tanks

flame and vapour control instrumentation

emission control solutions

firefighting equipment for storage tanks

Page 6: Ateco dome  power point presentation   master

Ateco Aluminum Geodesic Dome Roof

Page 7: Ateco dome  power point presentation   master

• the Ateco Dome Roof is manufactured from aluminum

which is one of the world’s most commonly used

metals

• its lightness, coupled with its strength and excellent

corrosion resistance are the main reasons for it being

used in the design of the Ateco Dome Roof

• there are three main component parts in any Dome –

Extruded Profiles, Nodes Points and Panel Sheets

• the Ateco Dome Roof can be used on tanks used to

store most products

Aluminium Geodesic Dome Roof

Page 8: Ateco dome  power point presentation   master

• the Ateco Dome Roof is a system of triangular,

lightweight Extruded Profiles - each and every profile

acts in either in compressive and tensile mode to resist

loading

• the profiles are connected through Node Points

transmitting loads laterally to the Integral Tension ring

and then through Supports to the tank shell and tank

foundation

• the framework is covered with minimum 1.2 mm thick

aluminum alloy Panel Sheets

• each of the extruded profiles and therefore each of the

triangles can be of different lengths

Page 9: Ateco dome  power point presentation   master

SLIDING SUPPORT – Free Vented SLIDING SUPPORT –Vapour Tight

FIXED SUPPORT – Free Vented FIXED SUPPORT –Vapour Tight

Page 10: Ateco dome  power point presentation   master

• the Ateco Dome Roof is an all bolted structure and no welding is required at site for its

assembly and erection

• the Ateco Dome Roof fully complies with the requirements of API 650 Appendix G

• any equipment that you have on a conventional steel tank roof can be fitted on the Ateco

Dome Roof

• The applied loads (up to 500 lbs/sqft) and taken into consideration in the design of the

Ateco Dome Roof consist of: live load, dead load, wind load (up to 175 mph) and seismic

factors

• The Ateco Dome Roof is normally fitted on a “free vented” tank however if required we

can fit a vapour tight dome roof

Page 11: Ateco dome  power point presentation   master

The Ateco Dome Roof standard design is offered with the

following features:

Gauge Hatch Assembly

Access/Manway Assembly

Centre Free Vent

Skylight Assembly

Free Vented Design with Sliding Supports & Bird Screen

Page 12: Ateco dome  power point presentation   master

• The Ateco Dome Roof can be

designed to support an aluminum

internal floating roof – suspended

IFR.

• The Ateco Dome Roof is normally

designed with a maximum radius

equal to 1.2 times the tank diameter

and the minimum is 0.7 times the

tank diameter, this equates to the

ratio of dome height to tank

diameter of about 1:6

• 30,000 mm diameter tank – dome

height is approximately 5,000 mm

Page 13: Ateco dome  power point presentation   master

The Ateco Dome Roof can be assembled inside the tank and lifted into its final position

using either a crane or a system of pulley blocks

Ateco can supply all the necessary assembly and erection equipment and tools or provide

details if customer wishes to source locally

If using the “jacking method” to erect the tank, the Ateco Dome Roof is fitted on the top

course and jacked up with the shell

Page 14: Ateco dome  power point presentation   master
Page 15: Ateco dome  power point presentation   master

MAIN ADVANTAGES OF ATECO ALUMINUM GEODESIC DOME

ROOF

• Ateco Dome Roof is a self-supporting structure - internal roof supports are not required

• Ateco Dome Roof lightweight construction means that when fitting on an existing external

floating roof tank - it is not necessary to reinforce the tank shell

• Ateco Dome Roof is fitted with an Integral Tension Ring to avoid any additional stiffening

requirement of the tank shell

• Ateco Dome Roof does not require painting, EVER - in this respect it can be considered

as maintenance free for the entire lifetime of the tank

Page 16: Ateco dome  power point presentation   master

Inspection and Supervision Services

Ateco has qualified and experience engineers who can support the installation of all Ateco

tank equipment on site, we also offer Inspection Services to give advice on the operation,

suitability, maintenance, repair or replacement of all Ateco supplied tank equipment.

Page 17: Ateco dome  power point presentation   master

Ateco Dome Roof Quotation

The Ateco Dome Roof is normally supplied on the basis of the

Ateco Standard Terms and Conditions for the Preparation of a Quotation

for Goods.

The Ateco Dome Roof is supplied to ex works Turkey and

packed in sea going containers.

Typically Delivery to ex works for an Ateco Dome Roof; 30,000

mm (100 ft.) nominal diameter tank is in the order of 14 weeks.

A breakdown of the Delivery is as follows:

Prepare Detail Engineering Drawings: 5 weeks

Manufacture : 7 weeks

Final Inspection and Packing: 2 weeks

Total: 14 weeks to ex works from acceptance of Purchase

Order.

A 30,000 mm (100 ft.) Ateco Dome Roof with standard

accessories should be shipped in 1 No x 40 ft. container

Page 18: Ateco dome  power point presentation   master

Ateco Dome Roof Quotation

Technical Details:

Typically 30,000 mm (100 ft) Ateco Dome Roof, with standard accessories has an installed weight of

9,500 kg (approx. 10 Tons)

The Number of Sliding Supports would be 28 No.

Load transferred through each Sliding Support (Dead Load + Live Load) to tank shell is 28.3 kN

Assembly and Erection:

5 skilled skilled labour x 10 hours per day x 6 days a week x 4 weeks: approximately 1200 Man-hours.

Ateco recommend complete assembly and installation by a competent tank contractor and if not

familiar with the Ateco Dome Roof they should retain the services of an Ateco Supervisor.

Page 19: Ateco dome  power point presentation   master

Aluminum Dome Roofs

South Pole Research Station

Mr Buckminister Fuller from USA developed

the principal of the geodesic dome in the

1940’s primarily for social housing

Grain Storage Hanger “Spruce Goose” Airplane

“Astrodome” Football Stadium

DISCLAIMERAteco does not claim or seek to claim

that the domes in these photographs

are Ateco Domes.

Geodesic – means the shortest line between two

points on a curved surface.

The complex design of the dome structure is carried

out using the latest finite element method (FEM). The

propriety software used by Ateco enables us to

maximize the domes structural strength, minimize

the number of different beam lengths and by

optimizing the panel size Ateco has developed a

dome with the minimum number of rings

The Astrodome in Houston is 200 meters

diameter. Diameter is no limitation– design

proposals already developed to cover

Downtown Houston, Texas with an

aluminum geodesic dome roof

Page 20: Ateco dome  power point presentation   master

Ateco Tank Technology Company

Yazlık Yeni Mah. Başöğretmen Cad.

No:46 Gölcük - KOCAELI -

TURKEY

PO Box 41650

Phone: + + 90 262 335 15 98

Fax: + + 90 262 335 15 67

E-mail: [email protected]

Website: www.atecotank.com

Ateco UK Ltd

Phone: + + 44 (0) 1899 830542

Mobile: + + 44 (0) 7789 690039

E-mail: [email protected]

Ateco Tank Technology Company

Page 21: Ateco dome  power point presentation   master

Ateco Tank Technology Company

No Date Item No: Qty. Properti

es

Size Buyer End User Country

1 2013 J.100.00

1

1 19.5 MT. GALANA PETROLEUM GALANA TERMINAIS

MOZAMBIQUE

MOZAMBIQU

E

2 2014 J.100.00

2

1 30 MT. AGDECOL BIOENERGY S.A /

ECOPETROL

COLOMBIA

3 2014 J.100.00

3

1 29.5 MT. ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

4 2014 J.100.00

4

1 29.5 MT ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

5 2014 J.100.00

5

1 29.5 MT. ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

6 2014 J.100.00

6

1 15.5 MT. ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

7 2014 J.100.00

7

1 15.5 MT ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

8 2014 J.100.00

8

1 13.5 MT. ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

9 2014 J.100.00

9

1 13.5 MT. ENOC / CYLINGAS (ONGOING) ECOMAR PROJECT UAE

Ateco Aluminum Dome Reference 2013/2014

Page 22: Ateco dome  power point presentation   master

Ateco Tank Technology Company - Photo Gallery