Atelier 4Innovations maritimes : les nouveaux navires
The Seven Borealis, a World-Class Strategic Enabler
Frédéric BOST, Vessel Support Team, Deputy Director Pipelay and Heavy Lift,
SUBSEA 7 Corporate
12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
2Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
1. Introduction : Seven Borealis key notes
• Subsea 7’s state-of-the-art world-class strategic enabler
• New pipelay & heavy lift DP vessel
• Designed to meet the exacting requirements of today’s
and tomorrow’s ultra-deep and deepwater challenges, in
the world’s harshest conditions
3Page12th of October 2011
the world’s harshest conditions
• Acquired in December 2009 and scheduled for delivery in
early 2012, developed to precise Subsea 7 specification
• Brings unprecedented deepwater pipelay and
riser/subsea construction capabilities
• Represent a significant leap forward to the offshore
industry
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
4Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
5Page12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Key abstracts:
Biggest multi-roles capability vessel in the industry:
Pipelay: Two rigid pipelay systems up to 1,000mT capacity:
• 600mT S-lay Single or Double joint, piggy back,
• 1000mT DJ J-lay, (2000mT capacity foundation).
Flexlay: Facility for 500mT flexible lay tower and space for multiple reels or carousels
6Page12th of October 2011
and space for multiple reels or carousels
Subsea construction. Flexibility with:
• Large multipurpose crane,
• Multiple subsea winches systems onboard,
• Foundation for hang-off (1no 1000mT & 1no 1200mT)
Heavy lift construction:
• 5000mT main crane,
ROVs: Top-end ROV systems for subsea intervention
Seven Borealis, Subsea 7 World-Class Strategic Enabler
7Page12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Borealis – Marine support details
DP Class 3 DnV Class plus NMD Letter
of Compliance for worldwide operations
Principal Particulars
Length 182.2 m
Breadth 46.2 m
Depth 16.1 m
Draught 7 – 11.35 m
Speed 14 kts max, 12.5 kts transit
Behaviour
Passive flume tank roll damping
system
8Page12th of October 2011
Speed 14 kts max, 12.5 kts transit
POB 220 (NMD) – 399
Machinery & Propulsion
Installed power 34.6 MW
Thrusters:
- 2 x fixed azimuth each 5500 kw aft
- 4 x retractable azimuth each 3200 kw
in hull
- 1 x 2790 kw in tunnel
system
Helideck
Approved for up to Sikorsky S61N
ROV Systems
2 ultra deep water units with
cyber technology and full survey
package.
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Model testing campaign
Model tank testing
9Page12th of October 2011
Wind tunnel testing
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Borealis – ROV, Survey & additional capabilities
ROV Systems2 ultra deep water units with cyber technology and full surveypackage.
Survey
• Survey enhancements HP500 & HP100 plus gate valves forSonadyne LBL and NASNET.
10Page12th of October 2011
Capabilities
• Designed as mothership to carry fuel and potable / technical freshwater available for others.
• An onboard monitoring, decision and prediction system for weather sensitive operations.(vessel behaviour modelling and performance software using live weather forecasts to predict vessel operability and optimise heading, including deep water load behaviour).
Seven Borealis, Subsea 7 World-Class Strategic Enabler
ROV Equipment (FAT Phase)
11Page12th of October 2011
Cyber Chairs
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Seven Borealis, in a few numbers
• 70.000 tons deadweight (7 Eiffel towers)
• More than 500 kms of electrical cables
• Main crane boom weight: 1200 tons, length 120m
• Stinger 100m, 1100 tons
• Weight of main hook: 150 tons
• Bridge 56m large
12Page12th of October 2011
• Bridge 56m large
• Fresh water production to military standard & increased
storage capacity
• Equipped with one sauna
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Some History of the Build
13Page12th of October 2011
Launch Nantong, October 2009
Accommodation block removed, extended
and re-installed April – July 2010
1st dry-dock – February 2010
Seven Borealis, Subsea 7 World-Class Strategic Enabler
General DataMain Crane (Huisman) J-Lay tower
• Pipe from 4” to 36” (outside dia.)
• Double joint & double working stations
• Friction clamp + travelling block system
14Page12th of October 2011
Pipe storage area
Stinger A-frame
Deepsea S-Lay stinger
3 off 40 t deck cranes
Hang offs foundation 1000 tDeck prepared for a 500 t
flexible lay tower (stbd)
Accommodation
for 399 people
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
15Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Borealis – Main crane rating
Main Crane (heavy-lift mode)
• Main crane capacity: 5000 t (tested at 5500t),
• Revolving capacity: 4000 t,
• Main blocks splitable in two blocks to allow jacket upending,
Main Crane – Auxiliary / subsea hook (Deep Water Lowering System)• Heave compensated.
16Page12th of October 2011
• Heave compensated.
• Subsea capacity: 1200 t.
• Max water depth: 6000 m.
Whip hook
• 110t
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Some History of the Build
17Page12th of October 2011
Crane loadout, China – February 2011
Crane installation – March 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
5,000 t Crane Reeved
18Page12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
5500mT crane test: New Scale of Equipment
1500 mT1250 mT
900 mT
700 mT
Test lift padeyes - 120mm plate
19Page12th of October 2011
Slings
~280 mm Ø
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Test of intermediate Hoist @ 350 tons
20Page12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
21Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Borealis – 600t S-Lay spreadPipelay Steep-S single or double joint pipelay system.
Variable layout
22Page12th of October 2011
• Single or double joint pipelay system for pipe from 4.5” to 46” (outside diameter).
• 3 x 200 t tensioners.
• Two A&R systems.
• Steep-S 92m , 3 sections stinger, 90° departure angle.
• Three auxiliary cranes (general supply & pipe loading).
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Steep-S stinger
Stinger Section 3 Stinger Section 2
23Page12th of October 2011
Stinger Tip
Stinger Section 1
Attachment to ShipTackle attachment Structure
Stinger Fabrication
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Some History of the Build
24Page12th of October 2011
Pipe conveyor equipment
Main Firing Line Beadstall area
600 t A&R winch system
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Miscenaleous ship equipments
25Page12th of October 2011
Seven Borealis, Subsea 7 World-Class Strategic Enabler
S-Lay – Firing Line EquipmentAssembly of the 200t Tensioner is currently ongoing at the Huisman facilities
in Schiedam and Czech.
26Page12th of October 2011
Assembly of the Upper Track
Assembly of the Main Frame
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
27Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Travelling Friction Clamp
Draw works
Travelling Block
Work Station 1 (Welding)
Gimballing
Borealis – J-Lay spread
J-lay tower:
• Gimballing J-lay tower over the side
• Double joint, two stations
• 4” up to 36”
• 1 000 t maximum capacity
28Page12th of October 2011
Borealis HULL
PLET Handling System
Hang off
Work Station 2(AUT + FJC)
Gimballing
Ring
StingerStructure
• PLET handling system up to 100 t
• Travelling block / friction clamp system.
• The gimball system allows pipelayin operational / weather preferred headings, as well as PLET installations, etc.
• 7’B is capable of self installation & removal of the J-lay tower.
Seven Borealis, Subsea 7 World-Class Strategic Enabler
J-lay tower - PLET handling system• 100t capacity.
• Safe handling of PLET/ILT in control manner.
Example: Pazflor triple in-line tee(two vertical & one horizontal connectors)
29Page12th of October 2011
(two vertical & one horizontal connectors)
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
30Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Programme to Completion• Ongoing yard commissioning and completion programme :
� Basin trials thrusters - ongoing
� Electrical system hook-up and commissioning - ongoing
� Crane load test (5,500 t) – October 2011
� Sea trials – November 2011
• Seven Borealis will depart Singapore December / January 2012, as a heavy
lift ship.
31Page12th of October 2011
lift ship.
• Pipelay equipment will be commissioning in the Netherlands.
• J-Lay tower stored in Flushing (The Netherlands).
• January / February 2012 Borealis in Rotterdam – load and installation J-Lay
system.
• 4 months at Huisman for S-Lay spread installation, integration and
commissioning (tensioners, SHF, stinger, pipe handling, winches, etc).
• Perform offshore trials – Mid 2012.
• Ready for operations end Mid 2012.
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Agenda:
1. Introduction
2. Vessel overview
3. Crane and deployment spread
4. S-lay pipelaying spread
32Page12th of October 2011
4. S-lay pipelaying spread
5. J-lay pipelaying spread
6. Build status
7. First project
Seven Borealis, Subsea 7 World-Class Strategic Enabler
CLOV – Borealis scope of workClient: TOTAL E&P Angola, Location: Angola, Block 17, Water depth: 1000 to 1400m
Pipelay: 22 flowlines 10 & 12”, inc 11 pipe in pipe, 110 km in J-lay, 19km in S-lay, 51 FLET & ILT.
Structure deployment: 14 foundations (90 to 220mT) & 28 structures (90 to 210mT)
Riser installation: 1 x Gas Export SHR (Including Flexible Jumper connection)
Rigid spools: 8 nos at bottom of riser towers ( 3D, ~110mT).
33Page12th of October 2011
Q4 - 2012 Q1 - 2013 Q2 - 2013
J-lay J-lay S-lay
Structures Structures Spools
SHR
Q4 - 2012 Q1 - 2013 Q2 - 2013
J-lay J-lay S-lay
Structures Structures Spools
SHR
Q4 - 2012 Q1 - 2013 Q2 - 2013
J-lay J-lay S-lay
Structures Structures Spools
SHR
Q4 - 2012 Q1 - 2013 Q2 - 2013
J-lay J-lay S-lay
Structures Structures Spools
SHR
Seven Borealis, Subsea 7 World-Class Strategic Enabler
Questions ?
As of 28/09/2011
34Page12th of October 2011