ATLAS closing scenario Where we are What is still be done before closing (ADO-PO suppo Closing scenario / Procedure / Schedule Prepared by Michel RAYMOND ADO-PO section meeting ADO-PO section meeting March 12th, 2009 March 12th, 2009

Upload: jenis

Post on 14-Jan-2016

24 views

Category:

Documents


1 download

DESCRIPTION

ADO-PO section meeting March 12th, 2009. ATLAS closing scenario. Where we are What is still be done before closing (ADO-PO support) Closing scenario / Procedure / Schedule. Prepared by Michel RAYMOND. Side C. Side A. Side C. Side A. Where we are. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ATLAS closing scenario

ATLAS closing scenario

Where we are What is still be done before closing (ADO-PO support) Closing scenario / Procedure / Schedule

Prepared by Michel RAYMOND

ADO-PO section meetingADO-PO section meeting March 12th, 2009March 12th, 2009

Page 2: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20092

Where we are

Side ASide C Side ASide C

Atlas is in standard opening configurationNominal gaps are granted except at a very few locations (Tile Extended Barrel) Access exist and are evolving depending on systems requests

Most of them complies with expectations (2 sectors not reachable on BEE C side)No particular complain caused by the new layout of the Round scaffoldingCurrent situation should be the baseline for future, including necessary improvements

Page 3: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 200933

Just to remind where the ADO-PO operation team is involved

What is to be done before closing

EEL muon chambers installation in sector 5 Ring segments modification on JD Shielding of LVPS on End Cap calorimeters BOL6A11 and BOL6C15 repairs Magnet preparation

Only the main tasks that have to be done before the closing are mentioned

To check all functionalities of the movement system A few improvements are on going (Traction control, Air distribution) Spare components have been ordered but will be partially here only, because of very long delivery time

Done

Done

Done

On going

On going

On going

Page 4: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20094

Closing scenario : overview

It will be the reverse scenario compare to the opening

1. Closing of side A2. In parallel, fiber replacement on Big Wheels MDT chambers side A

+ closing of C side

Octagonal shielding will be installed for the 1st time

5 weeks

5 weeks

Dismounting of platformRemoving of BT Vacuum pump Chamber installationBT vacuum pump backModification (?) and platforms back

Page 5: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20095

Team activity

All Barrel scaffoldings

All Barrel scaffoldings

G.AkhperjanianI. KrasinS.StudenovS.Yukhimchuk

MagnetsP. BenoitM. Jeckel

MagnetsP. BenoitM. Jeckel

BW movement + maintenanceR. VuillermetW. Andreazza

C. LeboubeV. DurastantiA. Yandyan

BW movement + maintenanceR. VuillermetW. Andreazza

C. LeboubeV. DurastantiA. Yandyan

Movement systemM. Raymond

D. BertetF. RossetA. Popov

Movement systemM. Raymond

D. BertetF. RossetA. Popov

L. Rose-Dulcina

Supervision/operations M. Raymond

P. Petit

Supervision/operations M. Raymond

P. Petit

Barrel chambers + EEG. Spigo

C. LeboubeV. Durastanti

A. PopovA.Yandyan

Barrel chambers + EEG. Spigo

C. LeboubeV. Durastanti

A. PopovA.Yandyan

General support(team)

General support(team)

This is the main idea : detail will be decided according real time activity

Follow up – ALARAO.Beltramello

F. PedrosaR. Vuillermet

Follow up – ALARAO.Beltramello

F. PedrosaR. Vuillermet

Page 6: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20096

Side ASide C Side ASide C

Closing Side A (1)

EBA closed

16/04/2009

Scaffoldings removal (JD, EB, then Barrel)Hydraulics connectionsEBA movementEIL4A11 replacementAir pads + hydraulics JD-A movementFixed point on VA - Removing of temporary support of VT Installation of JD locking devices

30/03/200907/04/2009

JD-A closed09/04/2009

Page 7: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20097

Side ASide C Side ASide C

Closing Side A (2)

ECT-A closed

22/04/2009

ECT X-brackets removingHydraulics connectionsECT-A movementSupport of VT-AAFT lockingHydraulics connection and truck movementLight truck to surfaceA-frame installation

15/04/200917/04/2009

Truck to surface21/04/2009

Page 8: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20098

Side ASide C Side ASide C

Closing Side A (3)

JFC1 installed

07/05/2009

Lowering of Compressed truckLowering of JF tableHydraulics connection Lowering of JFC1JFC1 positioningBeam pipe + LucidTruck movement + liftingJFC2 installation + survey

23/04/200927/04/2009

JFC2 installed06/05/2009

Page 9: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 20099

Fiber replacement – SIDE A

Installation of JFC3 is delayed to give access to LUCID

BW-A opening and decoupling – planned 4 days Tilt + 3 meters movementColumns installationMDT–TGC2 disconnectionLoad transfer to static columnsMovement 1.5 meter toward IP

Optical fibers replacement maintenance operationsUsing 1 lifting platform + 1 basket lifted by the crane

Planned 6 days

IP face openingMovement of chariotLoad transferConnection TGC2-MDTMovement to IPDisconnection MDT-TGC1Load transferMovement 1.5 meter

Planned 3 days

Optical fibers replacement + maintenance operationsUsing 1 lifting platform + 1 basket lifted by the crane

Planned 6 days

BW-A at closed positionClosing the wheelLoad transferConnection TGC1-MDTTilt

Planned 1.5 day

07/05/2009

10/06/2009

15/05/2009

26/05/2009

29/05/2009

09/06/2009

Page 10: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 200910

Side ASide C

Closing Side C

06/05/2009 Scaffoldings removal (JD, EB, then Barrel)Hydraulics connectionsEBC movementAir pads + hydraulics JD-C movementFixed point on VA - Removing of temporary support of VT Installation of JD locking devices

EBC closed19/05/2009

JD-C closed22/05/2005

ECT X-brackets removingHydraulics connectionsECT-C movementSupport of VT-CAFT lockingHydraulics connection and truck movementLight truck to surfaceA-frame installation

ECT-C closed28/05/2009

Truck to surface02/06/2009

25/05/2009

Lowering of Compressed truckLowering of JF tableHydraulics connection Lowering of JFC1JFC1 positioningBeam pipe + LucidTruck movement + liftingJFC2 installation + survey

JFC1 installed08/06/2009

JFC2 installed11/06/2009

04/06/2009

11/06/2009

Page 11: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 200911

Last activities

11/06/2009

24/06/2009

27/07/2009

06/08/2009

Magnetic test

15/07/2009

22/07/2009

EE side AEE side C

Octagonal shielding side A Work on VJ beam pipe & LUCID

Install JFC3 + plugRails set upLower compressed truck + JF tableTruck positioning - hydraulic connectionLowering of JFS3 bottom partJFS3 bottom part positioningAir pads removalJFS3 top part installation - TAS survey

Octagonal shielding side C

Removing of all equipment and material from UX15Shafts closing

Activity in parallel on both sides need a very sharp organization

Page 12: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 200912

Improvement foreseen on closing/opening movement

Improvements about the procedure close collaboration between Operation team and Safety team Follow up of the procedure and task durations Analysis of the procedure + Go to more details when necessary Add to the procedure the clear information on which material is removed and when Addition in the procedure of RPE intervention.

Technical improvements on movement system Air flow panels have been lowered from top of the truck to the floor of the trench

To monitor air will need one tech. instead of two Tech. will stand much further from activated area

Many components duplicated to save not only time but also handling and access close to activated area Connection between Bcam and movement HMI is being developed

will reduce the need of survey and make us more confident during movement

Page 13: ATLAS closing scenario

M. Raymond ADO-PO meeting – March 12th, 200913

Plans for detectors positioning

End Cap calorimeters

Overall policy = do the same than during 1st closing in 2008

Method and tooling is kept unchanged1.Checking of the distances between Tile fingers and ITC2.Adjustment of stoppers and electrical switches3.To perform the movement until stoppers are touching

What is our goal : nominal position or “previous run” position ? To be confirmed

JD + Small wheels 1. Tilt back the JD to the nominal angle 2. Adjust the new ring segments accordingly

Goal : be as close as possible from nominal position

End Cap Toroid

Big wheels

So far, no change in requirements no change in the procedure

Goal : be as close as possible from “previous run” position ? To be confirmed

Measurement done on C side after fibers replacement shows no relative movement between wheels.Last positioning will be reproduced

Shielding Goal : place the various parts as they were,Final survey needed (for magnetic reason)