ADO-PO section meeting March 12th, 2009. ATLAS closing scenario. Where we are What is still be done before closing (ADO-PO support) Closing scenario / Procedure / Schedule. Prepared by Michel RAYMOND. Side C. Side A. Side C. Side A. Where we are. - PowerPoint PPT PresentationTRANSCRIPT
ATLAS closing scenario
Where we are What is still be done before closing (ADO-PO support) Closing scenario / Procedure / Schedule
Prepared by Michel RAYMOND
ADO-PO section meetingADO-PO section meeting March 12th, 2009March 12th, 2009
M. Raymond ADO-PO meeting – March 12th, 20092
Where we are
Side ASide C Side ASide C
Atlas is in standard opening configurationNominal gaps are granted except at a very few locations (Tile Extended Barrel) Access exist and are evolving depending on systems requests
Most of them complies with expectations (2 sectors not reachable on BEE C side)No particular complain caused by the new layout of the Round scaffoldingCurrent situation should be the baseline for future, including necessary improvements
M. Raymond ADO-PO meeting – March 12th, 200933
Just to remind where the ADO-PO operation team is involved
What is to be done before closing
EEL muon chambers installation in sector 5 Ring segments modification on JD Shielding of LVPS on End Cap calorimeters BOL6A11 and BOL6C15 repairs Magnet preparation
Only the main tasks that have to be done before the closing are mentioned
To check all functionalities of the movement system A few improvements are on going (Traction control, Air distribution) Spare components have been ordered but will be partially here only, because of very long delivery time
Done
Done
Done
On going
On going
On going
M. Raymond ADO-PO meeting – March 12th, 20094
Closing scenario : overview
It will be the reverse scenario compare to the opening
1. Closing of side A2. In parallel, fiber replacement on Big Wheels MDT chambers side A
+ closing of C side
Octagonal shielding will be installed for the 1st time
5 weeks
5 weeks
Dismounting of platformRemoving of BT Vacuum pump Chamber installationBT vacuum pump backModification (?) and platforms back
M. Raymond ADO-PO meeting – March 12th, 20095
Team activity
All Barrel scaffoldings
All Barrel scaffoldings
G.AkhperjanianI. KrasinS.StudenovS.Yukhimchuk
MagnetsP. BenoitM. Jeckel
MagnetsP. BenoitM. Jeckel
BW movement + maintenanceR. VuillermetW. Andreazza
C. LeboubeV. DurastantiA. Yandyan
BW movement + maintenanceR. VuillermetW. Andreazza
C. LeboubeV. DurastantiA. Yandyan
Movement systemM. Raymond
D. BertetF. RossetA. Popov
Movement systemM. Raymond
D. BertetF. RossetA. Popov
L. Rose-Dulcina
Supervision/operations M. Raymond
P. Petit
Supervision/operations M. Raymond
P. Petit
Barrel chambers + EEG. Spigo
C. LeboubeV. Durastanti
A. PopovA.Yandyan
Barrel chambers + EEG. Spigo
C. LeboubeV. Durastanti
A. PopovA.Yandyan
General support(team)
General support(team)
This is the main idea : detail will be decided according real time activity
Follow up – ALARAO.Beltramello
F. PedrosaR. Vuillermet
Follow up – ALARAO.Beltramello
F. PedrosaR. Vuillermet
M. Raymond ADO-PO meeting – March 12th, 20096
Side ASide C Side ASide C
Closing Side A (1)
EBA closed
16/04/2009
Scaffoldings removal (JD, EB, then Barrel)Hydraulics connectionsEBA movementEIL4A11 replacementAir pads + hydraulics JD-A movementFixed point on VA - Removing of temporary support of VT Installation of JD locking devices
30/03/200907/04/2009
JD-A closed09/04/2009
M. Raymond ADO-PO meeting – March 12th, 20097
Side ASide C Side ASide C
Closing Side A (2)
ECT-A closed
22/04/2009
ECT X-brackets removingHydraulics connectionsECT-A movementSupport of VT-AAFT lockingHydraulics connection and truck movementLight truck to surfaceA-frame installation
15/04/200917/04/2009
Truck to surface21/04/2009
M. Raymond ADO-PO meeting – March 12th, 20098
Side ASide C Side ASide C
Closing Side A (3)
JFC1 installed
07/05/2009
Lowering of Compressed truckLowering of JF tableHydraulics connection Lowering of JFC1JFC1 positioningBeam pipe + LucidTruck movement + liftingJFC2 installation + survey
23/04/200927/04/2009
JFC2 installed06/05/2009
M. Raymond ADO-PO meeting – March 12th, 20099
Fiber replacement – SIDE A
Installation of JFC3 is delayed to give access to LUCID
BW-A opening and decoupling – planned 4 days Tilt + 3 meters movementColumns installationMDT–TGC2 disconnectionLoad transfer to static columnsMovement 1.5 meter toward IP
Optical fibers replacement maintenance operationsUsing 1 lifting platform + 1 basket lifted by the crane
Planned 6 days
IP face openingMovement of chariotLoad transferConnection TGC2-MDTMovement to IPDisconnection MDT-TGC1Load transferMovement 1.5 meter
Planned 3 days
Optical fibers replacement + maintenance operationsUsing 1 lifting platform + 1 basket lifted by the crane
Planned 6 days
BW-A at closed positionClosing the wheelLoad transferConnection TGC1-MDTTilt
Planned 1.5 day
07/05/2009
10/06/2009
15/05/2009
26/05/2009
29/05/2009
09/06/2009
M. Raymond ADO-PO meeting – March 12th, 200910
Side ASide C
Closing Side C
06/05/2009 Scaffoldings removal (JD, EB, then Barrel)Hydraulics connectionsEBC movementAir pads + hydraulics JD-C movementFixed point on VA - Removing of temporary support of VT Installation of JD locking devices
EBC closed19/05/2009
JD-C closed22/05/2005
ECT X-brackets removingHydraulics connectionsECT-C movementSupport of VT-CAFT lockingHydraulics connection and truck movementLight truck to surfaceA-frame installation
ECT-C closed28/05/2009
Truck to surface02/06/2009
25/05/2009
Lowering of Compressed truckLowering of JF tableHydraulics connection Lowering of JFC1JFC1 positioningBeam pipe + LucidTruck movement + liftingJFC2 installation + survey
JFC1 installed08/06/2009
JFC2 installed11/06/2009
04/06/2009
11/06/2009
M. Raymond ADO-PO meeting – March 12th, 200911
Last activities
11/06/2009
24/06/2009
27/07/2009
06/08/2009
Magnetic test
15/07/2009
22/07/2009
EE side AEE side C
Octagonal shielding side A Work on VJ beam pipe & LUCID
Install JFC3 + plugRails set upLower compressed truck + JF tableTruck positioning - hydraulic connectionLowering of JFS3 bottom partJFS3 bottom part positioningAir pads removalJFS3 top part installation - TAS survey
Octagonal shielding side C
Removing of all equipment and material from UX15Shafts closing
Activity in parallel on both sides need a very sharp organization
M. Raymond ADO-PO meeting – March 12th, 200912
Improvement foreseen on closing/opening movement
Improvements about the procedure close collaboration between Operation team and Safety team Follow up of the procedure and task durations Analysis of the procedure + Go to more details when necessary Add to the procedure the clear information on which material is removed and when Addition in the procedure of RPE intervention.
Technical improvements on movement system Air flow panels have been lowered from top of the truck to the floor of the trench
To monitor air will need one tech. instead of two Tech. will stand much further from activated area
Many components duplicated to save not only time but also handling and access close to activated area Connection between Bcam and movement HMI is being developed
will reduce the need of survey and make us more confident during movement
M. Raymond ADO-PO meeting – March 12th, 200913
Plans for detectors positioning
End Cap calorimeters
Overall policy = do the same than during 1st closing in 2008
Method and tooling is kept unchanged1.Checking of the distances between Tile fingers and ITC2.Adjustment of stoppers and electrical switches3.To perform the movement until stoppers are touching
What is our goal : nominal position or “previous run” position ? To be confirmed
JD + Small wheels 1. Tilt back the JD to the nominal angle 2. Adjust the new ring segments accordingly
Goal : be as close as possible from nominal position
End Cap Toroid
Big wheels
So far, no change in requirements no change in the procedure
Goal : be as close as possible from “previous run” position ? To be confirmed
Measurement done on C side after fibers replacement shows no relative movement between wheels.Last positioning will be reproduced
Shielding Goal : place the various parts as they were,Final survey needed (for magnetic reason)