LAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on TLAS TGC installation and commissionin Collaboration of • ICEPP-Tokyo • Kobe • Shinshu • KEK • Nagoya • TMU • …… • Weizmann • Tel Aviv • Technion On • Detector • Electronics • Online • Offline • …… JP IL

Upload: brice-morgan

Post on 01-Jan-2016

223 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS muon endcap

• 1 layer of tracking chambers (MDT)• 3 layers of trigger chambers (TGC)

which we are working on

ATLAS TGC installation and commissioning

Collaboration of• ICEPP-Tokyo• Kobe• Shinshu• KEK• Nagoya• TMU• ……• Weizmann• Tel Aviv• Technion

On • Detector• Electronics• Online• Offline• ……

JP

IL

Page 2: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS TGC installation and commissioning

Assembly of sectors• 72 sectors in total• 29 sectors completed, 43 sectors to go in next < 9 months

Tests of electronics / tests using electronics / DAQ ref: Sakamoto’s talk

Page 3: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

(Mechanically) completed 1st wheel. Commissioning starting

Page 4: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS TGC installation and commissioning• Tests of electronics / tests using electronics• Chamber operation / make it to work• Performance checks

• sector level• wheel level• complete system, using cosmic rays, then with beams

• Think, develop, design, build whatever needed to make the detector working

2006 2007 2008

LHC commissioning

0.45TeV 7 TeV

fore

ver

sectors assembly

wheels installation (-z)

wheels installation (+z)

commissioning

commissioning

Complete system

Detector performance, physics

Page 5: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS upgrade studies

“forever” (in the previous page) may not be that long

• Discussion and studies of possible LHC upgrade ~ 2016 Luminosity upgrade : nominal 1034 --> 1035 cm-2s-1

• In several years of LHC operation,• some parts of LHC• some parts of ATLAS/CMS

will be degraded and need replacement anyway

• Extending ATLAS physics potential:• Reach to higher energy scale (why ?)• access to rare processes

• ATLAS upgrade is required ( beyond the original design )• Increased collision rate • Radiation tolerance• detector occupancy / data size

Page 6: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS upgrade studies

What about the muon endcap detector ?

Seems OK in general, but ….

• Worry about chamber lifetime (radiation damage)• Electronics requires (modest ?) upgrade to cope with increased rate• Worry about performance at the region close to beams (high rate)• Kind of worry depends also on precise scenario of LHC upgrade (eg. bunch interval, …)

Studies would include

• Further study of radiation performance of chambers• Studies of electronics upgrade (including detector simulation studies)• Developments of possible new detector (to add or partial replacement) (faster and radiation stronger detector for trigger)• Studies for wider scope would also be worthwhile (eg. Tracking, …)

Page 7: ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning

ATLAS upgrade studies

Possible example: