ATN Subnetwork Implementation: VDL Mode 2/Controller Pilot Data Link Communications (CPDLC) Presentation ATN 3-4 by R. Oishi, ARINC ICAO Regional ATN Seminar 6-7 May 2002. Aviation Communications. Aeronautical Operational Control (AOC) Dispatcher - Pilot Communications - PowerPoint PPT PresentationTRANSCRIPT
A1
ATN Subnetwork Implementation:ATN Subnetwork Implementation:VDL Mode 2/Controller Pilot Data Link VDL Mode 2/Controller Pilot Data Link
Communications (CPDLC)Communications (CPDLC)
Presentation ATN 3-4 by R. Oishi, ARINCICAO Regional ATN Seminar
6-7 May 2002
A2
Aviation Communications
Aeronautical Operational Control (AOC)• Dispatcher - Pilot Communications• Operational Information• Flight Information Services
Air Traffic Services (ATS)• Controller - Pilot Communications• Flight Information Services
A3
VDL Mode 2 Subnetwork
FMSor ATSU
VDLRadio
CMU
ATN Aircraft
FMSor ATSU
MU or CMU
VDLRadio
VDL Mode 2Subnetwork
GroundStation
AOC G/G Network
ATN G/G Network
ATNRouter
ATN ATCEnd System
ACARS Aircraft
Air/GroundRouter
AOCEnd System
MessageProcessor
ATN Messages
ACARS Messages
A4
VDL Mode 2 Ground Station Status
US• 40+ AOA stations operational
…and approaching 50+ stations quickly over 90 stations deployed by end of CY 2002
• 9 aircraft using AOA operationally and number of aircraft growing (revenue flights)
Europe• 3 AOA stations being installed to support Airbus
Toulouse is operational Lyon and Nice are installed; waiting for frequency
license
A5
ARINC VDL Coverage Available/Near-Term
A6
EUROCONTROL PETAL II
PETAL II in operational environment at Maastricht Upper Air Control Centre• With line ATC controllers • Revenue and non-revenue flights of American Airlines 767-
300ERs• Also conducted test flights with Qinetiq BAC1-11 in a test
sector configuration • Flight operations completed September 01
PETAL II was a Success• Demonstrated viability/suitability of CPDLC over
VDLM2/ATN• Worked out many technical and ops issues for CPDLC over
VDLM2/ATN in a trials environment• Basis for US-based CPDLC program and Link 2000+
A7
CPDLC Partnership
A
A8
FAA CPDLC Build 1
CPDLC Build 1 partners, in a consensus decision, replanned CPDLC Build 1• Technical validation and operational evaluation conducted• Operational service begins Sep 02 and lasts until Build 1A
(Dec 05)
ARINC has installed the US ATN/VDLM2 ground network • 4 stations in FL operational (MCO, RSW, GNV, MIA)• Provides partial coverage of the Miami ARTCC airspace to
support testing pre-operational testing • 5 additional stations (9 total) to be operational by Sep 02
FAA flight tests with Rockwell Collins• In the Miami ARTCC• Three successful flights on 22, 24 January 02
A9
CPDLC Build I Coverage Map
A10
Summary ARINC VDL Mode 2 and CPDLC
AOA and ATN capability using VDL Mode 2 is now available
Customers are using VDL Mode 2 operationally today
Coverage is being expanded as customer aircraft are equipped
CPDLC activities are proceeding• PETAL II was a success• CPDLC Build 1 is in flight tests