Aurora Hills Community and Senior Center RefurbishmentCommunity PresentationDecember 8, 2015
Aurora Hills Community and Senior Center Refurbishment Existing Floor Plan 2
Scope of Work
Common Area / Lobby• Renovate the existing restrooms to make them ADA compliant
Senior Center• Remove the abandoned HVAC cabinets and replace with drywall• Remove the existing built-in cabinets and replace with new and add new storage cabinets• Redesign and relocate the reception desk• Construct a new office and storage room in place of the existing portable dividers• Remove the kitchen and built-in cabinets and replace with new • Provide new freestanding storage units• Provide new full length mirrors, new whiteboard and new storage in the Training Room• Provide new flooring finish and paint the Senior Center
Library• Redesign and replace the existing circulation desk • Remove the existing built-in cabinets and replace with drywall• Demo the kitchen and cabinets and replace with a new residential kitchen in the Break Room• Provide additional electrical outlets• Remove the abandoned HVAC cabinets
Construction• The Senior Center will be closed throughout the construction period• The library will remain open during construction – contractor will work after hours
3Aurora Hills Community and Senior Center Refurbishment
Proposed Floor Plan 4Aurora Hills Community and Senior Center Refurbishment
Existing Restrooms
Existing restrooms
5Aurora Hills Community and Senior Center Refurbishment
Renovated Restrooms
Renovated Restrooms will be Phased so that one restroom remains open during construction• Phase 1: Renovate Men’s Room• Phase 2: Renovate Women’s Room
5Aurora Hills Community and Senior Center Refurbishment
Senior Center Floor Plan
Note: Existing Storage will be doubled in proposed plan
7Aurora Hills Community and Senior Center Refurbishment
Reception Desk
• Refurbishment
Existing location Proposed location
8Aurora Hills Community and Senior Center Refurbishment
Reception Desk
Reception Desk Cabinets behind Desk
9Aurora Hills Community and Senior Center Refurbishment
New Office & Storage Room 10Aurora Hills Community and Senior Center Refurbishment
Multipurpose Room Storage 11
Floor Plan
Aurora Hills Community and Senior Center Refurbishment
Multipurpose Room Storage
Note: Existing Storage will be doubled in proposed plan
Freestanding Cabinets Built-in Cabinets
BUILT IN
12
Floor Plan
Aurora Hills Community and Senior Center Refurbishment
New Acoustic Wall / Cabinet Removal
Acoustic Wall Panels
Abandoned HVAC cabinets
Before After
ACOUSTIC WALL PANELS
New Acoustic Panels
13Aurora Hills Community and Senior Center Refurbishment
Training Room Upgrades 14Aurora Hills Community and Senior Center Refurbishment
Training Room Upgrades
White Board on Accent Wall Built in Cabinets
Built-in Cabinets
New white board
15Aurora Hills Community and Senior Center Refurbishment
Training Room Upgrades
• t
Floor to Ceiling Mirror on end wall
Mirrors on Wall
56” High Freestanding Cabinets
Freestanding cabinets
16Aurora Hills Community and Senior Center Refurbishment
Kitchen
KITCHEN
17
New Plan
New Cabinets & Appliances New Built –in Storage
Aurora Hills Community and Senior Center Refurbishment
Library Floor Plan 18Aurora Hills Community and Senior Center Refurbishment
Existing Circulation Desk 19Aurora Hills Community and Senior Center Refurbishment
New Circulation Desk
• Accommodates latest technology & wire management
• Better location of self check adjacent to holds
• Replace flooring around Circulation desk
• Secure book return• Better staff space to interact
with patrons
20Aurora Hills Community and Senior Center Refurbishment
Perimeter HVAC Enclosures
before after
Abandoned HVAC Cabinets
21Aurora Hills Community and Senior Center Refurbishment
Finishes 22Aurora Hills Community and Senior Center Refurbishment
Project Schedule 23Aurora Hills Community and Senior Center Refurbishment