ausrock2014 - 5/6th november coalmine pillar design and ... · 6 ecl sarpi joy r -vii 4.0 5.5 120...
TRANSCRIPT
Coalmine Pillar Design and Performance
During Mechanised Pillar Extraction in
India
AusRock2014 - 5/6th November
Keith MacAndrew
Alex Garcia
Ian Gregson
5
8
12
15
6m
17
16
14
13 6
7
10
9
11
5
5 8
5 12
15 1
3
26
m
2
4
SPLIT AND FENDER
15
32m pillar centres
(26 m pillars)
32 m
Indian Coal Background
November 14, 2014 2
India is the 3rd largest coal producer in the World (530mt/annum).
India has the 4th largest coal reserves in the World (approx. 277bt).
Almost 90% of India’s coal production is accounted for by surface
operations. Underground mining is now being expanded due to near surface
deposits and environmental restrictions (afforestation).
India imports over 200mt of coal per annum.
India has the 2nd largest population in the World after China (1.25 billion).
It is expected to increase its current annual consumption of coal from 770mt
to 1.5bt per annum by 2030 (with 400mt/annum imported). This will require
India to at least double its annual production in the next 20 years. To meet
this projected coal demand, India is looking to highly mechanised
underground mining.
Golder in India
November 14, 2014 3
Rock Mechanics Technology (RMT - now Golder) was formed following the
privatisation of the Rock Mechanics Department of British Coal in 1994 and
were instrumental in the successful introduction of rockbolting in to the UK
coal mining industry, to replace standing steel support (At the time, this
method of support was outside of the current legislation and was closely
supervised by the UK Mines Inspectorate).
The Indian Mines Inspectorate, DGMS, recognised Golder (formally RMT -
1997) as having the appropriate technology and expertise to introduce
improved support and mining methods that would enable the introduction of
mechanised mining in a safe and controlled manner.
With this recognition by the DGMS, Joy Mining Machinery (UK) identified
RMT (now Golder) as the facilitator to open up the vast potential market for
their high performance continuous miners in India.
Golder Projects in India
November 14, 2014 4
Golder currently have 5 projects with JMS
(Joy Machinery).
Plus 2 similar projects with Tractor India
(Caterpillar Equipment).
Two of the World’s largest equipment
suppliers.
Many more projects in the pipeline.
These projects were originally with Joy
Mining and Caterpillar equipment.
Joy and Caterpillar wanted to reduce their
risk and supply equipment only.
Both Joy and Caterpillar have transferred
their contract mining services to JMSL and
Tractor India Private Limited respectively.
Golder Projects in India
November 14, 2014 5
SITE AREA Mine CM Operator Seam Thickness
(m) Depth
(m)
Entr
y W
idth
(m
)
Entr
y H
eig
ht
(m)
Pill
ar C
en
tre
s (m
)
Bo
lt L
en
gth
(m
)
Bo
lt D
en
sity
(b
/m2 )
De
velo
p-m
en
t
Re
-De
velo
pm
en
t
Pill
ar E
xtra
ctio
n
Me
tho
d
De
gre
e o
f C
ave
abili
ty
1 SECL NCPH (2) JOY No.5 3.3.3.8 80 - 150 5.8 3.3 - 3.8
35 1.8 0.46 YES NO Split and Fender
Moderate to Difficult
2 WCL Tandsi II
Declines 3/4 JOY No.3 3 - 4.5 190 - 370 4.8 4 - 3.5 40 2.4 2.1 YES NO
Split and Fender
Easy
3 SCCL **VK7 JOY King 6.0 - 7.0 330 - 410 6 4.6 45 1.5 0.56 YES YES 1/3 Split and
Fender
Difficult to
Moderate
4 SCCL GDK 11 CATERPILLAR No.1 4.5 - 6.3 250 - 350 6 3.6 47 1.8 0.46 YES YES Double Split and Fender
Moderate to Difficult
5 ECL Jhanjra I JOY R-VI 4.0 - 4.5 110 - 140 6 4 - 4.3 32 1.5 0.56 YES NO Split and Fender
Difficult to
Moderate
6 ECL Sarpi JOY R-VII 4.0 - 5.5 120 - 210 6 4 - 4.5 34 1.8 0.56 YES NO * Split and
Fender Easy to
Moderate
7 SECL Sheetaldhara JOY No.3 ( C ) 3.5 - 4.5 160 - 190 6 3.5 35 1.5 0.66 YES YES Split and Fender
Easy
8 SECL ****Pinoura CATERPILLAR LB-1 3.5-4.5 65-135 6.5 3 21 - 26 1.8 0.89 YES YES Herring
Bone/Fish Tail
Easy
9 ECL ***Jhanjra II CATERPILLAR R-VI 2.5 - 3.5 130 - 310 6 3 - 3.5 30 to
38 2.1 0.56 YES NO
Split and Fender
Difficult to
Moderate
** VK7 - Due to caving issues an alternative Yield Pillar pillar extraction method was adopted but has recently been replaced by the 1/3 split and fender method.
*** Jhanjra II project is due to start production in the spring of 2014.
**** Pinoura Mine - Golder have had no involvement at this site.
Golder Projects in India
November 14, 2014 6
SITE AREA MineCM
OperatorSeam
Thickness
(m)
Depth
(m)
En
try
Wid
th (
m)
En
try
He
igh
t (m
)
Pil
lar
Ce
ntr
es
(m)
Bo
lt L
en
gth
(m
)
Bo
lt D
en
sity
(b/m
2)
De
ve
lop
me
nt
Re
-
De
ve
lop
me
nt
Pil
lar
Ex
tra
ctio
n
Me
tho
d
De
gre
e o
f
Ca
ve
ab
ilit
y
Op
era
tio
na
l
Sta
tus
Anjan Hill Zero 3.5 - 4.5 5 - 150 5.2 3 - 4.5 35 2.4 0.51 YES NOSplit and
Fender
Easy to
Moderat
e
Exhausted
NCPH No.5 3.3 - 3.8 80 - 150 5.8 3.3 - 3.8 35 1.8 0.46 YES NO No
Moderat
e to
Difficult
Exhausted
R6 No.3 6.5 30 - 80 5.5
4m + 1m
bottom
coaling
22 1.8 0.49 YES NOModified
NEVID
Difficult
to
Moderat
e
Exhausted
NCPH (2) No.5 3.3.3.8 80 - 150 5.8 3.3 - 3.8 35 1.8 0.46 YES NOSplit and
Fender
Moderat
e to
Difficult
Working
*Kapildhara No.3 3.0 - 4.5 20 - 50 6 3.5 20 2.4 0.56 NO YES NEVID
Easy to
Moderat
e
Replacement
Section
Example of the Versatility of the Continuous Miner Operating at Chirimiri (SECL)
1 SECL JOY
An example of the versatility of the Continuous Miner operating at
Chirimiri (SECL).
Golder Projects in India
November 14, 2014 7
Working Range of CMs to date in India
Mining Depth 10 m to 410 m
Pillar Centres 20 m to 47 m
Entry Heights 3.0 m to 5.8 m
Entry Widths 4.8 m to 6.5 m
Design Approach
November 14, 2014 9
Use best practice and proven experience
for initial design.
Measure to confirm that expected
behaviour is taking place to confirm
design assumptions:
Behaviour of roof, ribs, floor and pillars.
Progress in stages - prove each stage
before changing.
Understand roof failure mechanisms.
Use an effective rockbolt system.
Design by measurement.
Monitor the system.
Use real data to validate computer
models.
Golder Design Process
November 14, 2014 10
Geotechnical
Assessment
Geotechnical
Report
Initial Support
System
Support Rules
Support
Implementation
Support
Verification
Routine
Monitoring
Support
Modified
Local area
unstable
Unstable
Local area stable
Stable
Support Verification
Process on
Development
Geotechnical
Assessment
Geotechnical
Report
Initial Pillar
Extraction
Method and
Support
Implementation
of Extraction Plan
Monitored
Verification
Routine
Monitoring
Modify Extraction
Method
Local area unstable
Stop Slicing move
to next Fender/Pillar
Unstable
Local area stable
continue slicing
Stable Continued
Rapid
Instability
Review Method
Verification Process
for Pillar Extraction
Method
November 14, 2014 12
Pillar Extraction
Currently two high production mechanised coal mining methods are
used in India: Retreat longwall and room and pillar.
Pillar extraction with continuous miners in room and pillar mines has
so far been the most productive method of the two.
First applied to Anjan hill in 2002, eight more have been established
since, breaking local and national production records.
Can be applied to existing room and pillar mines by reworking
reserves left in pillars and new developments.
Pillars have been extracted using modern methods such as remote
controlled continuous miners and shuttle cars.
Substantial unworked coal deposits at shallow depth are also
potentially suitable for mechanised room and pillar mining
(Estimated at 2 – 3 Bt).
Seen by the Indian authorities as the key to increasing production.
November 14, 2014 13
Pillar Design
Golder uses established pillar design methods such as Salamon
and Munro (1967) for pillar sizing.
Initial pillars are given a high SoF of 2.0 to ensure stability during
pillar extraction.
The choice of pillar extraction pattern and sequence depend on site
conditions, such as overlying strata cavability.
Where the risk of difficult caving presents, yield pillar systems can
be employed.
Golder believes an adequate remnant pillar (snook), should be left
to support intersections (around 10% of initial pillar size).
Mark and Zelanko (2001) reported during pillar extraction over a six
year period, 30% of fatalities in the US were due to insufficient
snook sizing or attempts to extract the snook.
November 14, 2014 14
Snook Design
The smaller the snook is, the junction ‘stand-up’ time will be less.
These are snook parameters for CM5 at NCPH Old mine.
November 14, 2014 15
Snook Design
Relationship between snook size and caving delay in four-way
junctions for CM5 at NCPH Old Mine.
November 14, 2014 16
Pillar Design
To minimise ground control risks during pillar extraction:
Appropriately size pillars on development
Implement a suitable extraction sequence
Size remnant pillars to suit mine conditions
Install load cells and monitoring systems to confirm
early designs
Mechanised Pillar Extraction Methods
November 14, 2014 17
MODIFIED NEVID SYSTEM
5m 16
19
21
1
2
3
4
5
11
12
13
14
6
7
8
9
10
15
16
17
8
19
20
21
22
23
24
25
18
26
27
28
29 S1 S2
S3 S4
S5 S6
1 2
3 4
5 6
7
8 9
11
10
14
12
13
16
17
18
22
19
20
21
S1
S2
S3
15
3
4a 4a 4
1
5 2
3
DOUBLE SPLIT AND FENDER
1/3 SPLIT AND FENDER
47m pillar centres
(41 m pillars)
47m pillar centres
(41 m pillars)
22m pillar centres
(16 m pillars)
5
8
12
15
6m
17
16
14
13 6
7
10
9
11
5
5 8
5 12
15 1
3
26
m
2
4
SPLIT AND FENDER
15
32m pillar centres
(26 m pillars)
32 m
22 m
47 m
Design Monitoring Instrumentation
November 14, 2014 19
More accurate instruments
Comprehensive set of data on rock and support behaviour
Instruments verify pillar design by installing instruments into pillars
All instrumentation is remote reading
Also used to validate numerical models (FLAC, FLAC3D and MAP3D)
Roof and Rib Extensometers
Roof/Rib Strain Gauged Bolts
Design Monitoring Instrumentation (cont.)
November 14, 2014 20
Strain Gauged Rock Bolts
Fully encapsulated rockbolts develop a
load profile along their length
depending on rock properties and
stresses around the tunnel.
It is important to be able to measure
this profile.
We glue 9 pairs of resistance strain
gauges in opposed machined grooves
along the bolt.
Vibrating Wire Stress Cells (Pillar Loading)
November 14, 2014 23
Section through a vibrating
wire stress cell
Vibrating Wire
Platen
Proving Ring
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 26
Seam No.3 extracted 40m above Seam No.5.
Remnant pillars left in Seam No.3 shown in GREY.
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 27
1st two pillar rows extracted
(Pillars 1 – 10)
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 28
1st two pillars extracted in 3rd row
(Pillars 11 – 12)
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 29
Pillars 13 & 14 split, and Fender A of Pillar 13 taken.
Cell 1 Extracted
(Lost)
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 30
Cell 2 Cell 3
1st three pillar rows extracted
(Pillars 1 – 15)
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 31
Cell 2 Cell 3
Pillars 16/17 Extracted in 4th Row
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 32
Cell 2 Cell 3
4th Row of Pillars Extracted
Pillar No.21/22 started to be split
21
2
2
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 33
Cell 2 Cell 3
Extraction of Fender A,
Pillar 23 Starts
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 34
Cell 2 Cell 3
Extraction of
Fender A, Pillar 23
Completed
Extraction of
Fender B, Pillar 23
Starts
Roof Fall Over
No.21 Area
Adjacent to Stress Cell
Cell No.2 Extracted
(Lost)
Monitoring Stress Change in Pillars During
Depillaring, CM5, NCPH, SECL
November 14, 2014 35
Cell 2 Cell 3
Yield Pillar Partial Extraction Method
Indicating Fender Slicing Sequence
45m pillar centres
25.5m pillar core
19m max span
after slicing
(Final span will
be determined by
actual pillar size)
19m max span
after slicing
Snook width
>2 x height
min 9m
Breaker line
3 rows
7 x 2.4m bolts
@ 0.8m centres
Entries
4.6m x 6.5m
after
Bottom Coaling
No Bottom Coaling
adjacent to Barrier Pillars
To maintain FoS >2
November 14, 2014 37
Mining Method
Secondary Extraction by widening, bottom coaling
and partial extraction
The final remnant pillars are designed to yield in a
slow and controlled fashion
November 14, 2014 38
Key Elements for the Design of Yield Pillars
Remnant pillars left behind
Width/height ratio high enough to prevent
uncontrolled collapse
Span between pillars sufficiently small to prevent
most roof falls
Some small falls may occur as the pillars yield and
the roof moves
Barrier pillars to isolate panels
November 14, 2014 39
Key Elements of Proposed Design of Yield Pillars
40
The method relies on the pillars that are left behind
failing slowly
The mode of pillar failure is controlled by their width to
height ratio
And the stiffness of the loading system
November 14, 2014 40
Depth 410m
Pillar width 45m
Pillar height 2.5 to 4.6m
Entry width 3.5 to 6.5m
AVERAGE PILLAR STRESSES
0
4
8
12
16
20
24
28
32
36
40
1st
development
Road
widening
Bottom
coaling
First side Second side
Str
ess, M
Pa
November 14, 2014 41
Pre-
mining
Calculated Average Pillar Stresses During Mining
Depth 410m
Pillar width 45m
Pillar height 2.5 to 4.6m
Entry width 3.5 to 6.5m
PILLAR SAFETY FACTORS
0
0.25
0.5
1.0
1.25
1.5
1.74
2.0
2.25
2.5
1st
development
Road
widening
Bottom coal first side second side
Safe
ty f
acto
r
Pillar Safety factors during extraction
0.75
November 14, 2014 42
Calculated Pillar Safety Factors
Stresses – before secondary partial extraction
VIRGIN PILLAR
Virgin stress
=10.25Mpa
Pillar stress
=14.4Mpa (stress
concentration 1.4)
Pillar FoS > 2
w/h ratio > 9
November 14, 2014 43
Stresses – after 1st pillar slice taken
1st side extracted
Pillar stress
=21.5Mpa (stress
concentration 2.1)
Pillar FoS < 1
November 14, 2014 44
Stresses – after 2nd pillar slice taken
2nd Side extracted
Pillar stress
=31.8Mpa (stress
concentration 3.1)
Assume snook
failure
Pillar SoF < 0.5
w/h ratio > 5
November 14, 2014 45
November 14, 2014 50
15 m
10 m
Pillar No.9
All cells lost at this point
Example of Pillar Loading in Pillar No. 11
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Ab
so
lute
An
ch
or
Dis
pla
cem
en
t (m
m)
Date
31R(77L-78L) 4-way Roof Exto Ch. 37,36
Anchor 1 1.5(m) Anchor 2 5(m) Anchor 3 10(m) Anchor 4 15(m)
Pillar 6 Completed
Exto in Waste Area
6 7 8 9 10 12 13 14 16
19 18 17 20
11
15
VK7, SCL. 31R (77L-78L) 4 Way roof Exto ch.37,36
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Ab
so
lute
An
ch
or
Dis
pla
cem
en
t (m
m)
Date
31R(77L-78L) 4-way Roof Exto Ch. 37,36
Anchor 1 1.5(m) Anchor 2 5(m) Anchor 3 10(m) Anchor 4 15(m)
Pillar 6 Completed
Exto in Waste Area
9 10 12 13 14 16
19 18 17 20
11
15
VK7, SCL. 31R (77L-78L) 4 Way roof Exto ch.37,36
2n
d R
ow
Co
mp
lete
d
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Ab
so
lute
An
ch
or
Dis
pla
cem
en
t (m
m)
Date
31R(77L-78L) 4-way Roof Exto Ch. 37,36
Anchor 1 1.5(m) Anchor 2 5(m) Anchor 3 10(m) Anchor 4 15(m)
Pillar 6 Completed
Exto in Waste Area
13 14 16
19 18 17 20
15
VK7, SCL. 31R (77L-78L) 4 Way roof Exto ch.37,36
2n
d R
ow
Co
mp
lete
d
3n
d R
ow
Co
mp
lete
d
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Ab
so
lute
An
ch
or
Dis
pla
cem
en
t (m
m)
Date
31R(77L-78L) 4-way Roof Exto Ch. 37,36
Anchor 1 1.5(m) Anchor 2 5(m) Anchor 3 10(m) Anchor 4 15(m)
Pillar 6 Completed
Exto in Waste Area
19 18 17 20
VK7, SCL. 31R (77L-78L) 4 Way roof Exto ch.37,36
2n
d R
ow
Co
mp
lete
d
3n
d R
ow
Co
mp
lete
d
4th
R
ow
Co
mp
lete
d
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Ab
so
lute
An
ch
or
Dis
pla
cem
en
t (m
m)
Date
31R(77L-78L) 4-way Roof Exto Ch. 37,36
Anchor 1 1.5(m) Anchor 2 5(m) Anchor 3 10(m) Anchor 4 15(m)
Pillar 6 Completed
Exto in Waste Area
2n
d R
ow
Co
mp
lete
d
3n
d R
ow
Co
mp
lete
d
4th
R
ow
Co
mp
lete
d
140m in to Waste Area
5th
R
ow
Co
mp
lete
d
VK7, SCL. 31R (77L-78L) 4 Way roof Exto ch.37,36
Auto-warning Telltale
November 14, 2014 57
Golder’s intrinsically safe Auto-warning Telltale provides a
highly visible immediate warning of excessive movement,
over and above that provided by the coloured bands on
standard telltale.
These were specifically developed for the Indian coal
market to provide real-time warning to the machine
operators of the possible onset of caving in the pillar
extraction zone during mechanised pillar mining
operations.
The extraction line is the most high risk area for fatalities
and machine burial due to the unpredictable nature of
caving during pillar extraction.
These have proved to be highly effective and have now
been adopted as the standard means of monitoring in
mechanised pillar extraction panels in India.
v
v
2
7
8
1
54N
53N
52N
11E 12E 13E 14E 15E 16E
10 9 18/4/12 5:20 21/4/12 18:30
4
1/5/12 18:00
3 5
6
9/5/12 13:00
18/5/12 7:00
19/5/12 23:30
Extraction Sequence with Caving and AWTT Triggering
Times during the Extraction of Pillars 1 to 10
November 14, 2014 62
The application of mechanised room and pillar mining systems in
India for the development and the re-establishment of old
workings prior to subsequent pillar extraction has proved to be
very successful.
Pillar extraction is important to India, as vast reserves of coal still
exist underground in old mining districts as pillars.
The risk of ground control failure during pillar extraction is
relatively high, especially where overlying strata conditions are
high such as found at some India sites.
This risk has been reduced with the help of Golder, by adopting
appropriate pillar design and support, extraction sequences.
Summary
November 14, 2014 63
Remote monitoring of selected pillars during extraction with
instruments provides confirmation of behaviour and verifies
designs.
Safety procedures undertaken during pillar extraction now include
the use of Golder’s AWTT, which flash when dangerous roof
movement is detected. This is significant to operator safety during
pillar extraction. However, experiences shows their relative
effectiveness can be site specific and therefore should not be
used in isolation.
The potential for the application of mechanised room and pillar
mining with CMs in India is significant having the potential to
achieve world class productivity while maintaining safety.
Summary cont.