C O M M U N I T Y B O N D O V E R S I G H T C O M M I T T E E
Meeting Reference Material Meeting Date: August 14, 2018
A U S T I N I N D E P E N D E N T S C H O O L D I S T R I C T
Welcome
COMMITTEE MEMBERS
Cheryl Bradley Scott Norman
Jennifer Carson Julian Rivera
Dr. T. Jaime Chahin Cindy Schaufenbuel
Darrell Crayton Rocio Villalobos
Mark Grayson Dale Sump (Committee Co-Chair)
Lawrence Huang Anna Valdez
Maria Jimenez Alex Winslow
Lori Moya (Committee Co-Chair) Peck Young
Hatem Natsheh Vacant
2 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
AISD Community Bond Oversight Committee Charge 1. Providing a report and any recommendations for corrective actions to the Board on the overall
implementation of the bond programs. The report is presented orally and/or in writing twice each year and provides feedback and issues related to staff's presentation to the CBOC on the following topics:
a) Overall budget status
b) Oversight of quality and schedule
c) Contingency
d) Stakeholder satisfaction
e) HUB utilization
f) Any proposed substantive changes
g) Issues and risks
h) Communication strategies and methods
2. Utilizing the report to provide perspective on key decisions and actions that have been taken by staff and the Board since the last report submitted to the Board.
3. Maintaining a record of work and findings to inform the Board should another bond election be undertaken.
4. Reviewing information from staff on all projects and expenditures of bond funds and on the timelines and progress of the bond programs.
5. Working with staff in assessing the levels of satisfaction of key campus stakeholders with the quality of work and rating of customer service.
6. Reviewing and evaluating the survey results provided by staff.
7. Evaluating any proposed changes to the individual scope of work to the voter-approved bond programs and communicating any noted concerns to the Board.
3 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Table of Contents
Executive Summary .......................................................................................................................... 5
Project Update Report ...................................................................................................................... 7
Project Budgets, Commitments & Actuals ..................................................................................... 12
HUB Utilization ................................................................................................................................ 19
Communication Strategies & Methods ............................................................................................ 27
Glossary of Terms .......................................................................................................................... 34
Appendix A: Murchison MS Masterplan Presentation .....................................................................39
Appendix B: Construction Contract Auditing Presentation ..............................................................63
Community Bond Oversight Committee Meeting
August 14, 2018 // 6:00 pm
4 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I T Y B O N D O V E R S I G H T C O M M I T T E E C H A R G E
Executive Summary
EXECUTIVE SUMMARY
5 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
E X E C U T I V E S U M M A R Y
Executive Summary
Work on the 2017 Bond projects continues at a rapid pace. At the end of July, Menchaca and Govalle elementary schools are close to finalizing Design Development, the final design phase. During this phase designs are finalized, prior to the development of architectural drawings. Doss, Brown, and New Southwest elementary schools are close to finalizing the Schematic Design phase and New Blazier Relief School has started the Schematic Design phase which includes efforts to refine site plans and floor plans based on agreed upon space programming. The schools have worked through the design phases in collaboration with the associated communities and stakeholders.
The modernized Eastside Memorial ECHS and International HS at the Original Anderson campus, the Ann Richards School for Young Women Leaders, Murchison Middle School and Bowie High School are currently in the Masterplanning phase which includes programming efforts, conceptual development and interactive collaboration with the associated communities and Austin ISD key stakeholders. The Norman‐Sims Campus Architectural Team (CAT) has held its first four meetings and the modernization of the Norman campus is in Pre‐Design, which includes discussion of space programming and room adjacencies.
Critical Deficiency Projects for roofing at Cook Elementary School, Houston Elementary School, Lamar Middle School, Odom Elementary School, Palm Elementary School, Pillow Elementary School, Reilly Elementary School, Travis ECHS, Walnut Creek Elementary School, Baranoff Elementary School, Cowan Elementary School, Crockett ECHS, Fulmore Middle School, Graham Elementary School, Martin Middle School, Pecan Springs Elementary School, Ridgetop Elementary School, Akins High School, Anderson High School, Wooten Elementary School, Dawson Elementary School, Joslin Elementary School, and Sadler Means YWLA are in the bid and award phase and work begins this summer. Other Critical Deficiency Projects will be addressed throughout the bond program.
Two bond newsletters have been distributed electronically, with the next scheduled bond newsletter to be released in the fall of 2018. The 2017 Bond Program Information letters to parents and guardians have been distributed at all schools in the district. Site dedications and groundbreaking are being planned and scheduled, as part of a coordinated media strategy and community engagement strategy. Functionality of the bond program’s website AISDFuture.org was improved by increasing speed the site. The website features event, key dates, an interactive bond map, and a frequently asked questions section.
The 2013 Bond Program is in its final phase. AISD’s project managers are working with principals and other staff to complete summer projects prior to the beginning of school. The summer work schedule includes 50 construction projects, some at multiple campuses.
6 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
E X E C U T I V E S U M M A R Y
Project Update Report
PROJECT UPDATE REPORT
7 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
School or FacilityArchitect/Engineer
Contractor
Ann Richards School for Young Women Leaders
Architect/Engineer, O’Connell Robertson
General Contractor, Rogers-O’Brien
Eastside Memorial Early College High School & International High School at the Original L.C. Anderson Campus
Architect/Engineer, Perkins & Will
General Contractor, Cadence McShane
Bowie High School
Architect/Engineer, Page Architects
General Contractor, JE Dunn
Murchison Middle School
Design-Build: Team Bartlett Cocke/Stantec
Brown Elementary School
Design-Build: Rogers O’Brien/ERO
Menchaca Elementary School
Design-Build: Joeris/LPA
New Southwest Elementary School
Architect/Engineer BGKA Architects
General Contractor, Flintco
Doss Elementary School
Design-Build: Bartlett Cocke/Stantec
Govalle Elementary School
Design-Build: Balfour Beatty/PBK
New Blazier Relief School
Architect/Engineer BLGY
General Contractor, American
Norman Modernization
Architect/Engineer, Kirksey (Approved by Board of Trustees, in negotiation)
General Contractor, TBD
Metz, Sanchez, and Zavala Project
N/A
Rosedale
Architect/Engineer for Bridging Documents: DLR
Roofing at Cook Elementary School, Houston Elementary School, Lamar Middle School, Odom Elementary School, Palm Elementary School, Pillow Elementary School, Reilly Elementary School, Travis ECHS, Walnut Creek Elementary School, Baranoff Elementary School, Cowan Elementary School, Crockett ECHS, Fulmore Middle School, Graham Elementary School, Martin Middle School, Pecan Springs Elementary School, Ridgetop Elementary School, Akins High School, Anderson High School, Wooten Elementary School, Dawson Elementary School, Joslin Elementary School, and Sadler Means YWLA.
Work included within the Critical Facilities Deficiencies at schools throughout the district includes improvements to electrical, plumbing, HVAC systems, improvements to seal building envelope, site drainage improvements, structural improvements, architectural and interior renovations.
2017 Bond Program ‐ Active Projects
August Update
Project Phase Project Description Status
Masterplanning
Full modernization of the existing facility to a state-of-the-art campus at the current site. Demolition and new construction of athletics, fine arts, cafeteria and kitchen, media center with portion of CTE and high school academic wing. Light renovation of existing facility to become temporary MS academic wing and CTE. New athletic fields and additional parking. Technology: computer lab improvements, student mobile computers & teacher computers.
On schedule
Masterplanning
Design and construct modernized new high school for Eastside Memorial Early College High School and International High School at the original L.C. Anderson Campus. Project will include new multi-purpose, dual-use community rooms and gallery area to celebrate and honor the original L.C. Anderson legacy. Restoration of the 900 Thompson Street address location and façade. Technology: computer lab improvements, student mobile computers & teacher computers.
Project schedule under review due to community and historical considerations. Project budget under review due to historical preservation elements and site constraints.
Masterplanning
State of the art modernization of the existing facility. Additions and renovations to include athletics, fine arts and increased capacity. New parking structure, heating & air conditioning improvements, plumbing improvements. Technology: computer lab improvements, presentation systems, student mobile, teacher computers.
On schedule
Masterplanning
Modernization phase 1: 6th grade addition, library and administration relocation, annex roofing and bus loop addition. Courtyard improvements, heating and air conditioning improvements, wall & ceiling improvements, site drainage improvements. Technology: computer lab improvements, student mobile computers, teacher computers.
On schedule
Schematic DesignDesign and construction of a new campus on existing site. Technology: computer lab improvements, teacher computers.
On schedule
On schedule
Design Development Design and construction of a new campus on existing site. Site circulation improvements to accommodate the major adjacent road expansions. Technology: computer lab improvements, teacher computers.
On schedule
Schematic Design Design and construction of a new state-of-the-art facility with increased capacity. Technology: computer lab improvements, teacher computers.
On schedule
Critical Deficiency Projects Bid & Award On schedule
Modernization of elementary school to serve the Norman and Sims communities to support
21st century learning spaces, state-of-the-art technology and community spaces. On schedule
Bridging DocumentDesign and construction of a new state-of-the-art facility at the Read Pre-K campus. Technology: Computer lab improvements, student mobile computers, teacher computers.
On schedule
High Schools
Middle Schools
Targeted Schools
Elementary Schools
Pre-Design
Design and construction of a new state-of-the-art facility that will increase capacity. Located on the existing southeast middle school site adjacent to Blazier Elementary School to initially relieve Blazier Elementary School with grades 4-6 and future to be grade 6-8. Technology: Computer lab improvements, student mobile computers, teacher computers.
Planning PhaseModernization of elementary school to serve Zavala, Metz and Sanchez communities to support 21st century learning spaces, state-of-the art technology and community spaces.
Recommendation from community to the Superintendent expected August 9.
Schematic Design On schedule
Schematic Design Full modernization and expansion. Concept to be refined as community input is gathered during the design process. Site work to include adjustments to site circulation and additional on-site parking. Technology: computer lab improvements, teacher’s computers.
On schedule
Design Development Full modernization creating a new state-of-the-art facility. Design and construction to replace structurally compromised building areas and improve academic and support areas. Technology: Network system improvements, presentation systems, teacher computers.
P R O J E C T U P D A T E R E P O R T
8 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Location Project Name Work DescriptionPhase ‐ %
Complete
Substantial Completion Date
for Construction On Schedule Schedule Comments
Cook ESRoof Repair Preplacement
at Cook ESRoof replacement in all areas of the building. 75 8/10/2018 Yes
Reilly ESPartial Roof Replacement at
Reilly ES.Roof replacement in all areas of the buildings. 80 8/20/2018 Yes
Ridgetop ESPartial Roof Replacement at
Ridgetop ES.Roof replacement in all areas of the buildings. 30 10/1/2018 Yes
Various
Roofing replacement in
selected areas at Crockett
ECHS, Travis ECHS, and
Pillow ES
Roof replacement in all areas of the buildings. 90 8/20/2018 Yes
Akins HS Renovations at Akins HS
Renovations to convert CTE Family and Consumer
Technology Lab classroom to Special Ed Life Skills
classroom, pedestrian paving upgrades, install roof
ladders with cages, install basketball goal safety cables,
non‐destructive investigation of moisture intrusion at
two art classrooms, upgrade exterior lighting, modify
bus loop, replace floor covering in one classroom,
replace selected RTUs serving cafeteria and kitchen.
60 8/15/2018 Yes
Allison ES Renovations at Allison ES
Classroom wings 100, 200, 300 renovations, 5 ADA RR
upgrades, misc. finish replacement, kitchen HVAC
replacement, stage lift.
50 8/5/2018 Yes
Anderson HS Renovations at Anderson HSChange order safety work associated with the stair
wells.95 8/6/2018 Yes
Austin HS
Replace (2) Elevators, New
Doors, Accessible Route at
Austin HS
Replace (2) Elevators, New Doors, Accessible Route at
Austin HS45 8/15/2018 No
Determining the new
completion date to
accommodate change
order requests.
Baranoff ES Renovations at Baranoff ES
Baranoff ES: Additional Parking; Design a Replacement
Canopy at Main Entry, Correct Drainage in and around
the Canopy to Stop Flooding in the Administration Area.
60 8/17/2018 No
The canopy delivery will be
August 14, which will delay
the completion date.
Blanton ES Renovations at Blanton ES
Replace exterior lighting; replace 300 wing air handler
and resolve distribution issue; replace the kitchen,
admin and library ac units; replace the 200 wing heat
pumps; ADA improvements in area 3; ADA
improvements to restrooms; replace plumbing fixtures
in restrooms; replace SS lines; replace domestic water
heater.
80 8/6/2018 Yes
Boone ESReplacement Retainer
Panels at Boone ES
Connect Roof Downspouts to Storm Sewer.
Replace/repair Perimeter Foundation Retaining Wall.
Replace Sidewalks.
50 8/13/2018 Yes
Boone ES Renovations at Boone ES
Replace circulation desk in library. Paint library walls.
Add lighting to library entrance. Replace hvac system
for MDF room. Renovate classroom A7 & A8's
restrooms for accessibility. Replace ceiling and lighting
in kitchen. Replace sanitary sewer in kitchen. Replace
sump pumps in crawl space. Make miscellaneous
plumbing repairs.
70 8/13/2018 Yes
Bowie HS Renovations at Bowie HSHVAC & ELECTRICAL RENOVATIONS: Replacement of
hydronic piping in crawlspace of buildings A and B.50 8/6/2018 No
Determining new
completion date to
accommodate delay in
issuance of contract to
contractor.
Burger
Athletic
Complex
Renovations at Burger
Athletic Complex
Concession & Restroom/ Locker room renovations.
Security updates / Stadium RR ADA / finish upgrades,
misc. finishes and lighting upgrades, CCTV @ stadium.
60 8/5/2018 Yes
Burnet MS Renovations at Burnet MSChange order work on mechanical items in order to
complete the controls and commissioning. 95 8/6/2018 Yes
Campbell ESRenovations at Campbell ES
Twelve new RTUs to be installed during summer 2018. 85 8/6/2018 Yes
AUGUST CONSTRUCTION PROJECT UPDATE
2017 Bond Program Projects
2013 Bond Program Projects
P R O J E C T U P D A T E R E P O R T
9 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Location Project Name Work DescriptionPhase ‐ %
Complete
Substantial Completion Date
for Construction On Schedule Schedule Comments
Clayton ES Renovations at Clayton ES
Plant grass in SW play area, new canopy, insulate the
supply and return cooling water lines in building, replace
roof access ladder with security ladder and lockable
cage.
55 8/13/2018 Yes
Covington
MS
Renovations at Covington
MS
Replace kitchen ceiling; replace six CW and HW pumps;
replace 66 water source heat pumps; do ADA upgrades
in bldgs A and B; do CTE upgrades in shop in bldg C;
replace part of the roof; add a new walk in freezer; add
safety cables to bball goal; install new ice machines;
repair underpinning.
85 8/6/2018 Yes
Davis ES Renovations at Davis ES
Replace ceiling grids in MDF and adjacent corridors;
replace DDC controls; replace kitchen grease trap;
replace walk‐in freezer/cooler; bring kitchen up to code
for health permit; provide roof access between building
roof levels at Main Building and from ground level to
roof at annex building B.
65 8/13/2018 Yes
Dobie MSAddition/Renovations at
Dobie MS
Food Lab Kitchen addition and renovation. Plus admin,
Skills for Living Module labs, replace certain HVAC air
stations & duct work for central air.
45 8/10/2018 Yes
Harris ES Renovations at Harris ESReplacing 28 ground source heat pumps and their
associated heat transfer system.85 8/6/2018 Yes
Houston ES Renovations at Houston ES Final project work related to boiler replacement. 99 9/28/2018 Yes
Joslin ES Renovations at Joslin ESReplace HVAC equipment. Replace ceilings. Replace
exterior sanitary sewer. Improve ADA accessibility.75 8/13/2018 Yes
Kiker ES Renovations at Kiker ES
Install zone controls, replace heat pumps, new
underground drainage connected to existing
downspouts, classroom renovations.
65 8/3/2018 Yes
LBJ ECHSTEA Innovative Academies
at LBJTEA Innovative Academies at LBJ ‐‐Phase 2 60 8/10/2018 Yes
Lee ESAddition/Renovations at Lee
ES
Addition/Renovations Auditorium improvement, HVAC
improvements, administration expansion / renovation,
replace select floor finishes.
70 8/3/2018 Yes
Mills ESAddition/Renovations at
Mills ES
Multi‐purpose classroom addition (2 classrooms);
replace mechanical duct work at workroom; install
louvers to rooftop units
15 2/15/2019 No
Construction is on hold.
Working with CoA for
approval to move an
existing wall to align with
fire wall.
Oak Spring ESCorrective TDLR paving and
ramp items
Final project work related to corrective TDLR paving and
ramp items. This impacts parking lots and sidewalk. 99 8/15/2018 Yes
Odom ESAddition/Renovations at
Odom ES
Construct two new multi‐purpose classrooms and
outdoor classroom; Replace HVAC equipment at various
locations in existing building; Install Stage Lift; Install
TAS compliant drinking fountain at cafeteria; Install
Roof Access Ladder; Replace portions of existing
sidewalk.
40 12/14/2018 Yes
Ortega ES Renovations at Ortega ESKitchen renovations, Library renovations, Parking lot
resurfacing.50 8/13/2018 Yes
Pecan
Springs ES
Renovations at Pecan
Springs ES
Replace Electrical Distribution Panels. Repair wall
damage in custodial closet. Replace Condensing unit at
the listed rooms. Construct ADA ramp in cafeteria.
Expand and Renovate Administration Area and
Cafeteria, including RRs. Provide recycling container on
grounds. Replace built‐in cabinets and countertops in
selected areas.
40 8/3/2018 No
The steel delivery will be
August 8, which will delay
the completion date.
Determining the new date.
Pickle ESAddition/Renovations at
Pickle ES
Two multi‐purpose classroom addition. Relocated
portables as required for addition.15 12/14/2018 Yes
Pickle ESNew Cooling Tower at Pickle
ESReplace cooling tower at Pickle ES 15 12/7/2018 Yes
Rodriquez ESAddition/Renovations at
Rodriguez ES
Adding two classrooms at end of one of the corridors.
Install louvers to all rooftop package units.35 12/15/2018 Yes
Saegert Bus
Terminal
Renovations at Saegert Bus
Terminal
Overhead doors, restroom partitions, replace radiant
heating system, 110v receptacles with 110v GFCI,
building exhaust fans.
45 8/10/2018 Yes
Various
Add Fire Suppression
Systems in the Data Centers
at CRCKT and REAGN
Add fire suppression to Reagan and Crockett data
centers50 12/15/2018 No
Unforeseen conditions
have been identified, which
will delay the completion
date. This is not critcal for
school startup as it is not
related; it only pertains to
the IT MDF rooms.
10 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Location Project Name Work DescriptionPhase ‐ %
Complete
Substantial Completion Date
for Construction On Schedule Schedule Comments
Various
Installation of solar arrays at
Paredes MS, Galindo ES,
Kocurek ES and Boone ES.
Installation of solar arrays at Paredes MS, Galindo ES,
Kocurek ES and Boone ES.70 8/31/2018 No
Substantial Completion
date will be revised based
on available dates to
perform power outage at
each school. Power
shutdown is required for
interconnection of the
solar arrays.
VariousDevelop Prototype Athletic
Restroom
Construct athletic restroom and storage at Akins,
Crockett, Eastside and Travis. Final work being done at
Akins (utility connections). All other sites are complete.
99 8/6/2018 Yes
VariousResurface Running Tracks at
BURNT, MURCH, PARED
Final project work at Paredes. Change order work on
sidewalk & guardrail.95 10/15/2018 Yes
Various
Repair and Replacement of
Floor Coverings at Various
Locations
Installations at Allison, Austin, Casey, Bryker Woods,
Summitt, McCallum and Boone. 60 8/18/2018 Yes
VariousRepair Detention Ponds at
Overton, Garcia & Delco.
Pond repair work at Garcia, Delco and Overton. Rebuild
the road and sidewalks at the property entrance of the
Overton campus.
70 9/3/2018 Yes
Various
Urgent
Roofing/Waterproofing
Repairs at Various AISD
Campuses
Work is ongoing as needed at various campuses. 70 1/15/2019 Yes
VariousPortable Roof Repair and
ReplaceWork is ongoing as needed at various campuses. 75 1/15/2019 Yes
VariousPartitions at Clayton and
Boone Elementary Schools
Replacing folding walls between gym and cafeteria at
both sites. 55 8/17/2018 Yes
Widen ES Renovations at Widen ES
Misc. renovations including HVAC and walk‐in
refrigerant insulation replacement. Stage lift, 4 ADA RR
upgrades, misc. finishes, HVAC grilles, and hardware.
60 8/5/2018 Yes
Williams ES Renovations at Williams ESRemodeling the restrooms by the cafeteria, the music
room and the stage (with a new chair lift).50 8/6/2018 Yes
Winn ESInstall 5‐12 playscape at
Winn ES.Install 5‐12 playscape at Winn ES. 95 8/3/2018 Yes
Wooten ES Renovations at Wooten ESFinal project work involving additional scope related to
wastewater pipe as required by CoA.99 8/3/2018 Yes
Zavala ES Renovations at Zavala ES
Replacement of windows in kitchen and other selected
areas, repairs of exterior walls & sidewalks, replacement
of selected exterior and interior doors, replacement of
marble restroom partitions, ceiling repairs, replacement
of HVAC along with piping and condensing lines and
units, ADA improvements and renovation of selected
classrooms.
60 8/14/2018 Yes
11 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
P R O J E C T U P D A T E R E P O R T
Project Budgets, Commitments & Actuals
PROJECT BUDGETS, COMMITMENTS & ACTUALS
12 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Project Budgets, Commitments & Actuals
Data extracted from Austin ISD Audited Financial System of Record (BOLT).
**Includes amounts for Modernization of elementary campuses within the vertical team or Fine Arts Reinvention.
School/Facility (per 2017 Bond Book)2017 Bond
Book AmountProject Budget*
Actuals Encumbrances Commitments Project Balance
Legend A B C D E F =B-C-D-E
High Schools
Akins HS 13,196,000 9,447,698 - - - 9,447,698 Anderson HS 11,163,000 7,878,000 - - - 7,878,000 Ann Richards School YWL 70,416,000 61,113,000 221,859 47,389 - 60,843,751 Austin HS 30,198,000 24,539,162 - - - 24,539,162 Bowie HS 91,030,000 78,153,410 43,009 89,978 - 78,020,422 Crockett ECHS 15,095,000 11,529,477 - - - 11,529,477 Eastside Memorial ECHS 80,699,000 69,843,000 121,135 63,152 3,875,733 65,782,980 Garza Independence HS 544,000 283,065 - - - 283,065 Lanier ECHS 7,172,000 4,739,055 - - - 4,739,055 LASA 10,380,000 7,455,938 - - - 7,455,938 LBJ ECHS 25,575,000 42,777,127 - - - 42,777,127 McCallum HS 8,455,000 5,912,824 - - - 5,912,824 Reagan ECHS 6,703,000 4,599,428 - - - 4,599,428 Travis ECHS 9,528,000 6,864,090 - - - 6,864,090
Middle Schools
Bailey MS 6,196,000 4,596,168 - - - 4,596,168 Bedichek MS 5,293,000 3,872,775 - - - 3,872,775 Burnet MS 3,425,000 2,177,819 - - - 2,177,819 Covington MS 6,190,000 4,615,594 - - - 4,615,594 Dobie MS 3,267,000 2,223,620 - - - 2,223,620 Fulmore MS 5,472,000 3,892,719 - - - 3,892,719 Garcia YMLA 4,325,000 3,104,497 - - - 3,104,497 Gorzycki MS 2,057,000 824,579 - - - 824,579 Kealing MS 3,719,000 2,208,076 - - - 2,208,076 Lamar MS 14,882,000 12,156,145 54,800 38,100 - 12,063,245 Martin MS 4,715,000 3,597,682 - - - 3,597,682 Mendez MS 2,668,000 1,539,251 - - - 1,539,251 Murchison MS 25,308,000 22,379,961 118,230 1,252,468 - 21,009,263 New Northeast MS 60,958,000 53,219,000 3,710 - - 53,215,290 O. Henry MS 3,135,000 2,045,387 - - 148,349 1,897,038 Paredes MS 3,157,000 1,947,660 - - - 1,947,660 Sadler Means YWLA 3,112,000 2,161,327 - - - 2,161,327 Small MS 1,225,000 171,320 - - - 171,320 Webb MS 3,181,000 2,156,999 - - - 2,156,999
*Difference between 2017 Bond Book Amount and Project Budget is reserved for work in later phases, program-wide bond services, technology, administration and contingency.
P R O J E C T B U D G E T S , C OMM I T M E N T S & A C T U A L S
13 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
School/Facility (per 2017 Bond Book)2017 Bond
Book AmountProject Budget*
Actuals Encumbrances Commitments Project Balance
Legend A B C D E F =B-C-D-E
Elementary Schools
Allison ES 1,140,000 798,612 - - - 798,612 Andrews ES 496,000 245,720 - - - 245,720 Baldwin ES 631,000 282,068 - - - 282,068 Baranoff ES 3,038,000 2,383,735 - - - 2,383,735 Barrington ES 1,585,000 1,128,273 - - - 1,128,273 Barton Hills ES 349,000 185,166 - - - 185,166 Becker ES 1,467,000 1,086,732 - - - 1,086,732 Blackshear ES 1,715,000 1,268,429 - - - 1,268,429 Blanton ES 773,000 450,782 - - - 450,782 Blazier ES 395,000 89,980 - - - 89,980 Boone ES 2,503,000 1,940,726 - - - 1,940,726 Brentwood ES 35,817,000 31,223,000 - - - 31,223,000 Brooke ES 251,000 57,100 - - - 57,100 Brown ES 30,842,000 26,887,000 128,232 1,389,456 - 25,369,312 Bryker Woods ES 381,000 214,584 - - - 214,584 Campbell ES 968,000 654,380 - - - 654,380 Casey ES 1,176,000 768,332 - - - 768,332 Casis ES 35,216,000 30,687,000 - - - 30,687,000 Clayton ES 1,158,000 691,338 - - - 691,338 Cook ES 2,435,000 1,901,809 - - - 1,901,809 Cowan ES 4,928,000 4,049,327 - - - 4,049,327 Cunningham ES 1,647,000 1,237,287 - - - 1,237,287 Davis ES 1,238,000 850,522 - - - 850,522 Dawson ES 1,841,000 1,424,191 - - - 1,424,191 Dobie Pre-K 54,000 - Doss ES 43,052,000 37,541,000 513,007 2,459,827 - 34,568,162 Galindo ES 1,252,000 823,712 - - - 823,712 Govalle ES 32,565,000 28,373,000 313,417 1,619,315 - 26,440,267 Graham ES 2,352,000 1,819,592 - - - 1,819,592 Guerrero Thompson ES 970,000 532,978 - - - 532,978 Gullett ES 542,000 346,090 - - - 346,090 Harris ES 1,965,000 1,519,099 - - - 1,519,099 Hart ES 2,371,000 1,804,893 - - - 1,804,893 Highland Park ES 2,017,000 1,566,947 - - - 1,566,947 Hill ES 17,783,000 15,468,438 - - - 15,468,438 Houston ES 3,299,000 2,607,839 - - - 2,607,839 Jordan ES 1,319,000 912,839 - - - 912,839 Joslin ES 2,235,000 1,793,641 - - - 1,793,641 Kiker ES 1,109,000 729,401 - - - 729,401 Kocurek ES 1,482,000 1,042,619 - - - 1,042,619 Langford ES 645,000 315,808 - - - 315,808 Lee ES 984,000 708,635 - - - 708,635 Linder ES 2,284,000 1,764,223 - - - 1,764,223 Maplewood ES 902,000 642,002 - - - 642,002 Mathews ES 1,089,000 813,325 - - - 813,325 McBee ES 1,456,000 1,047,797 - - - 1,047,797 Menchaca ES 33,351,000 29,072,000 76,907 7,770 - 28,987,323 Metz ES 297,000 67,480 - - - 67,480 Mills ES 1,160,000 756,215 - - - 756,215 New Blazier Relief School 50,487,000 43,652,000 104,590 96,192 - 43,451,218 New Southwest ES 36,227,000 29,230,617 192,598 2,034,983 - 27,003,035 Norman ES 280,000 - - - - - Norman-Sims Modernization 25,000,000 21,695,020 - - - 21,695,020 Oak Hill ES 1,161,000 773,530 - - - 773,530 Oak Springs ES 316,000 128,924 - - - 128,924 Odom ES 4,110,000 3,370,119 13,537 66,864 - 3,289,717 Ortega ES 1,488,000 1,142,991 - - - 1,142,991 Overton ES 1,224,000 805,536 - - - 805,536 Padron ES 1,321,000 664,494 - - - 664,494 Palm ES 1,656,000 1,192,309 - - - 1,192,309
14 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
School/Facility (per 2017 Bond Book)2017 Bond
Book AmountProject Budget*
Actuals Encumbrances Commitments Project Balance
Legend A B C D E F =B-C-D-EPatton ES 1,701,000 1,239,033 - - - 1,239,033 Pease ES 638,000 443,018 - - - 443,018 Pecan Springs ES 3,790,000 3,104,500 - - - 3,104,500 Perez ES 1,003,000 617,780 - - - 617,780 Pickle ES 2,218,000 1,551,379 - - - 1,551,379 Pillow ES 2,669,000 2,142,336 - - - 2,142,336 Pleasant Hill ES 2,749,000 2,179,558 - - - 2,179,558 Read Pre-K 17,000 - - Reilly ES 3,060,000 2,519,587 - - - 2,519,587 Ridgetop ES 2,166,000 1,766,843 - - - 1,766,843 Rodriguez ES 1,371,000 942,242 - - - 942,242 Sanchez ES 372,000 83,930 - - - 83,930 Sims ES 213,000 48,440 - - - 48,440 St. Elmo ES 495,000 278,615 - - - 278,615 Summitt ES 1,095,000 716,422 - - - 716,422 Sunset Valley ES 2,384,000 1,860,279 - - - 1,860,279 Travis Heights ES 1,253,000 901,569 - - - 901,569 Uphaus Early Childhood Center 425,000 142,752 - - - 142,752 Walnut Creek ES 2,962,000 2,321,449 - - - 2,321,449 Webb Primary 106,000 - Widen ES 1,700,000 1,244,227 - - - 1,244,227 Williams ES 741,000 443,882 - - - 443,882 Winn ES 1,615,000 1,207,006 - - - 1,207,006 Wooldridge ES 895,000 559,795 - - - 559,795 Wooten ES 2,737,000 2,204,634 - - - 2,204,634 Zavala ES 332,000 75,270 - - - 75,270 Zilker ES 1,230,000 908,502 - - - 908,502 Eastside Vertical Team Elementary Modernization 25,000,000 - - - - -
Other Facilities
Alternative Learning Center 88,000 - - Burger Athletic Complex 1,721,000 1,289,213 - - - 1,289,213 Central Warehouse 295,000 126,340 - - - 126,340 Clifton Center 606,000 366,867 - - - 366,867 Delco Activity Center 570,000 426,558 - - - 426,558 House Park Athletic Facility 6,000,000 5,191,000 - - - 5,191,000 Nelson Field Bus Terminal 507,000 486,253 - - - 486,253 Nelson Field 151,000 - - Noack Sports Complex 10,000 4,320 - - - 4,320 Performing Arts Center 171,000 81,325 - - - 81,325 Pleasant Hill Annex 135,000 116,809 - - - 116,809 Rosedale School 40,092,000 34,921,000 - - - 34,921,000 Saegert Bus Terminal 433,000 353,030 - - - 353,030 Service Center 137,000 58,830 - - - 58,830 Southeast Bus Terminal 118,000 73,565 - - - 73,565
15 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
School/Facility (per 2017 Bond Book)2017 Bond
Book AmountProject Budget*
Actuals Encumbrances Commitments Project Balance
Legend A B C D E F =B-C-D-E
Districtwide
Master Planning for Athletics, CTE and Fine Arts 273,000 273,000 - - - 273,000 Police 7,508,000 9,008,000 779,083 - - 8,228,917 Life Safety (Special Education Security Camera Installation)
349,000 - - - - -
Furniture (Purchasing Department) 5,000,000 - - - - - Transportation 21,400,000 19,900,000 1,233,025 4,186,107 - 14,480,867 Bond Carry Costs 30,000,000 30,000,000 8,602,045 37,320,754 - (15,922,799)
Technology
Technology ($55,000,000 distributed across all campuses, included in Schools/Facilities)
- 9,660,125 1,012,926 8,666,518 - (19,319)
ContingencyContingency 73,821,000 73,821,000 Program AdministrationProgram Management 59,811,783 156,003 117,728 - 59,538,052
Program Subtotals 1,134,735,000 1,084,729,125 13,688,113 59,456,600 4,024,082 1,007,560,316 Less Estimated Land Sales (40,000,000)
Less Previous Bond Contingency (43,751,000)Total Bond Cost 1,050,984,000
Note: Contingency funds to be prioritized for overcrowding relief for the Northwest, Blazier, Cowan and Baranoff communities.
16 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Project Budgets, Commitments & Actuals
Data extracted from Austin ISD Audited Financial System of Record (BOLT).
Actuals 13,688,113$ Encumbrances 59,456,600$ Commitments 4,024,082$ Balance (budget not yet committed, encumbered or spent)
1,007,560,316$
Funds not yet entered/programmed into Bolt 50,005,875$ Program Total 1,134,735,000$
Actuals$13,688,113
1%
Encumbrances$59,456,600
5%
Commitments$4,024,082
0%
Balance (Budget lessActuals, Encumbrancesand Commitments)1,007,560,316
89%
Funds not yet entered/programmed
into Bolt$50,005,875
4%
2017 Bond Budget Chart
Actuals Encumbrances
Commitments Balance (budget not yet committed, encumbered or spent)
Funds not yet entered/programmed into Bolt
P R O J E C T B U D G E T S , C OMM I T M E N T S & A C T U A L S
17 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Project Budget 951,096,342$ Project Savings* -
Program Administration** 59,811,783$ Funds not yet entered/programmed into Bolt 50,005,875$
Contingency 73,821,000$
Program Total 1,134,735,000$
* As projects near completion, project savings are identified for re-distribution to complete remaining voter-approved projects or board-approved ** Includes cost for permits & fees, copying & printing, legal services, misc. services - construction inspection, newspaper advertisement, safety
Project Budget$951,096,342
84%
Program Administration**
$59,811,783 5% Funds not yet
entered/programmed into Bolt
$50,005,8754%
Contingency$73,821,000
7%
2017 Bond Contingency Chart
Project Budget Project Savings*
Program Administration** Funds not yet entered/programmed into Bolt
Contingency
Project Savings*‐0%
P R O J E C T B U D G E T S , C O M M I T M E N T S & A C T U A L S
18 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
HUB Utilization
HUB UTILIZATION
19 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Created July 26, 2018
August CBOC Update HUB Participation A/E and Construction reports for the 2013 & 2017 Bond Programs are attached for review. Ongoing meetings are being conducted with the Office of Management Systems (IT), Finance, Contract & Procurement and HUB Program Departments. Efforts are being made to integrate the B2GNOW software reporting system with the BOLT financial system. Office of Management Systems (IT) staff is taking the lead on integrating the systems. The original forecasted date was end of July 2018, however, due to additional mapping requirements, the date has been pushed out until more substantial information (financial data and system connectivity) is obtained. HUB Staff continues training on the B2GNOW software capabilities and a new contract is being finalized. On June 18, 2018, the Board of Trustees approved HUB Program and Procurementrecommended policy revisions.
Recommended revisions to existing District policies (CV, CH and CHE) were for the followingreasons to:
• Provide for the expansion to administer Program Guidelines for District-wide procurements that will now include commodities/supplies and other services valued at $50,000 or more.
• Ensure uniform administration and compliance with program policy and regulations. • Create enforceable policy by relocating key requirements to local policy from the
existing Guidelines that will ensure strict scrutiny program administration. • Provide greater awareness of the Program, and improve understanding of requirements
by internal and external stakeholders. • Ensure equitable opportunity for all interested proposers.
The Districtwide HUB Program for procurement is forecasted to begin September 1, 2018. Internal and external training will be upcoming in August. Additionally, an Outreach Event will be held on August 22, 2018, Austin High School, to inform the community stakeholders of this new Districtwide HUB Program procurement expansion. HUB staff member Cecilia Allen, resigned July 30, 2018. The position was posted and an offer has been extended for a new Contract Relations Coordinator to begin on August 20, 2018. This new staff will be assigned to the Commodities and Non-Professional services for the program.
20 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Category Contracted Amount Paid Amount Paid Participation Goal Variance
African American 330,813$ 301,336$ 1.4% 1.9% ‐0.5%
Asian/Native American 3,548,337$ 3,317,857$ 14.9% 7.4% 7.5%
Hispanic 2,730,470$ 2,289,627$ 10.3% 9.4% 0.9%
Women‐Owned 3,952,825$ 3,348,716$ 15.1% 9.8% 5.3%
HUB Total 10,562,445$ 9,257,536$ 41.6% 28.5% 13.1%
Non‐HUB 13,794,099$ 12,976,700$ 58.4% ‐ ‐
Total 24,356,543$ 22,234,236$ 100.0% ‐ ‐
Historically Underutilized Business (HUB) Participation Report2013 Bond Program
THROUGH THE END OF JUNE 2018
Architect/Engineering
Non‐HUB 58.4%
Women‐Owned 15.1%
Hispanic10.3%
African American1.4%
Asian/ Native American14.9%
21 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Category Contracted Amount Paid Amount Paid Participation Goal Variance
African American 4,382,191$ 3,506,433$ 1.9% 1.7% 0.2%
Asian/Native American 1,943,135$ 1,750,383$ 0.9% 1.9% ‐1.0%
Hispanic 18,673,237$ 16,065,121$ 8.7% 8.1% 0.6%
Women‐Owned 25,165,920$ 22,942,813$ 12.4% 10.2% 2.2%
HUB Total 50,164,483$ 44,264,751$ 23.8% 21.9% 1.9%
Non‐HUB 158,397,528$ 141,360,516$ 76.2% ‐ ‐
Total 208,562,011$ 185,625,267$ 100.0% ‐ ‐
Historically Underutilized Business (HUB) Participation Report2013 Bond Program
THROUGH THE END OF JUNE 2018
Construction
Non‐HUB 76.2%
Women‐Owned 12.4%
Hispanic8.7%
African American1.9%
Asian/ Native American0.9%
22 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Category Contracted Amount Paid Amount Paid Participation Goal Variance
African American 556,009$ 99,008$ 18.1% 1.9% 16.2%
Asian/Native American 275,630$ 19,576$ 3.6% 7.4% ‐3.8%
Hispanic 2,487,168$ 186,758$ 34.1% 9.4% 24.7%
Women‐Owned 424,729$ 77,829$ 14.2% 9.8% 4.4%
HUB Total 3,743,536$ 383,171$ 70.0% 28.5% 41.5%
Non‐HUB 4,500,166$ 164,553$ 30.0% ‐ ‐
Total 8,243,702$ 547,723$ 100.0% ‐ ‐
Forecasted Budget Contracted % Contracted % Paid
62,434,000$ 8,243,702$ 13.2% 0.9%
Historically Underutilized Business (HUB) Participation Report2017 Bond Program
THROUGH THE END OF JUNE 2018
Architect/Engineering
Non‐HUB 30.0%
Women‐Owned 14.2%Hispanic
34.1%
African American18.1%
Asian/ Native American3.6%
23 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Category Contracted Amount Paid Amount Paid Participation Goal Variance
African American ‐$ ‐$ 0.0% 1.7% ‐1.7%
Asian/Native American 105,600$ ‐$ 0.0% 1.9% ‐1.9%
Hispanic 627,026$ 363,375$ 60.9% 8.1% 52.8%
Women‐Owned 36,625$ 755$ 0.1% 10.2% ‐10.1%
HUB Total 769,251$ 364,130$ 61.1% 21.9% 39.2%
Non‐HUB 1,913,072$ 232,223$ 38.9% ‐ ‐
Total 2,682,323$ 596,353$ 100.0% ‐ ‐
Forecasted Budget Contracted % Contracted % Paid
880,078,000$ 2,682,323$ 0.3% 0.1%
Historically Underutilized Business (HUB) Participation Report2017 Bond Program
THROUGH THE END OF JUNE 2018
Construction
Non‐HUB 38.9%
Women‐Owned 0.1%
Hispanic60.9%
African American0.0%
Asian/ Native American0.0%
24 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Advancing Equity in Contracting…
2018 HUB Outreach Events 1. GAHCC Annual Meeting and Installation Luncheon – January 4, 2018
3 HUB Staff attended in a networking capacity.
2. AISD HUB CBS Austin TV – February 19, 2018 Director and HUB Coordinator on air for “We Are Austin” segment promoting AISD HUB Program and 02/21/18 Outreach Event.
3. AISD HUB KAZI Radio – February 19, 2018 Director and HUB Coordinator on air promoting AISD HUB Program and 02/21/18 Outreach Event.
4. AISD HUB “2017 Bond Construction” – February 21, 2018 Event promoting AISD HUB Program including networking event with 4 Design-Build firms contracted on projects from the 2017 Bond Program.
5. ABCA “Annual Black History Event” – February 22, 2018
AISD HUB Program representative in a networking capacity.
6. GAACC Connect Forum – February 28, 2018 AISD HUB Program exhibitor and networking for upcoming projects on 2017 Bond Program.
7. CTSB Coaching Series “Writing a Winning Proposal” – March 30, 2018 AISD HUB Program co-sponsor with 4 other local governmental agencies workshop series. Presentation to Primes and subconsultants/subcontractors on tips to compiling a successful proposal.
8. AISD HUB KAZI Radio “Underwriting HUB Program Segment” – began April 9, 2018 ran through July 3, 2018. AISD HUB Program announcements seeking firms for contracting on the 2017 Bond Program. Ran 20 times.
9. State HUB Vendor Fair “Marketing for Success” – April 18, 2018 AISD HUB Program speaker, exhibitor and networking for upcoming projects on 2017 Bond Program.
25 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
2018 HUB Outreach Events (continue)
10. 2018 Black Business Day at the Capital – April 20, 2018 2 HUB staff attended in a networking capacity and to obtain information on African American business future.
11. Austin Black Business Journal – April 30, 2018 Director attended in a networking capacity.
12. CTSB Annual Event - “The Bond Passed-Now What?” – May 16, 2018 AISD HUB Program co-sponsored with 4 other local governmental agencies. Program included 2017 AISD Bond Overview (Matias Segura, AISD Operations Officer); upcoming Contracting Opportunities (Veronica Harris, AECOM Deputy Program Manager & Debra Boone, AISD HUB Program Director moderator) and exhibits with AISD HUB Program Department and 5 CMR firms (Rogers O’Brien, Cadence McShane, Flintco, JE Dunn & McKissack & McKissack) to network with Primes and subs attending.
13. GAHCC – Attended 2018 HAL Program Graduation – May 16, 2018 National award-winning leadership training program that makes our community a better place to live. Felipe Romero, HUB Coordinator, graduated from this nine-month training program and received the Guillermo Calderon Award, class honor, for extraordinary leadership that inspired and impacted the community (voted on my peers).
14. GAACC Connect Forum – Quarterly Event - May 23, 2018
AISD HUB Program exhibitor and networking for upcoming projects on 2017 Bond Program
15. CAPMETRO/ACC – Small and Disadvantaged Business Networking – May 24, 2018 AISD HUB Program exhibitor and networking for upcoming projects on 2017 Bond Program
16. TEXAS STATE/TEXAS FACILITIES COMMISSION – Legacy in the Making – June 6, 2018 AISD HUB Program exhibitor and networking for upcoming projects on 2017 Bond Program.
17. City of Austin – 14th Annual Women’s Entrepreneurial Luncheon – June 22, 2018 Staff members attended and networked with WBE business owners to inform them about the newly expanded HUB Program that will include non-professional services and commodities.
18. PeopleFund - PeopleSpring ATX “Ladies, Lunch & Learn” Grow your Network – July 26, 2018. Staff members attended and networked with WBE business owners to inform them about the newly expanded HUB Program that will include non-professional services and commodities.
26 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
S T A K E H O L D E R S A T I S F A C T I O N
Communication Strategies & Methods
COMMUNICATION STRATEGIES & METHODS
27 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Communications Summary
As the 2018 summer season winds down at Austin ISD, the 2017 Bond Program continues to take shape, the communications and community engagement teams are working to ensure that campus and community stakeholders are engaged, and that the general public and taxpayers are informed of progress currently underway.
The AustinISD2017Bond.org website features real‐time construction updates and detailed information about bond activities at each campus, including public, committee and Campus Architectural Team (CAT) meetings. The Bond website, www.aisdfuture.com has been updated to be more user‐friendly and easier to navigate. It includes all the information that was hosted on the original page, but in a more concise format.
Norman Elementary and Eastside Memorial Early College High School and International High School joined other modernization projects in beginning their CAT process and have had three meetings to date. Blazier, Doss, T.A. Brown, Govalle, Menchaca, and the new Southwest elementary schools, Rosedale School, Murchison Middle, Bowie High School, and the Ann Richards School for Young Women Leaders continue outreach with their respective school communities and Campus Architectural Teams.
Govalle Elementary hosted a community meeting to showcase its progress on design development on June 18th from 6‐7 p.m. Administrators, along with PBK Architects and Balfour Beatty shared updates on the design as well as renderings of the new school. T.A. Brown Elementary School hosted a schematic design meeting with the Webb Middle School community on July 18th.
In addition to the CAT team meetings, several community‐focused events have been held including Doss Elementary’s 4th of July parade in collaboration with the Northwest Austin Civic Association. New Blazier Relief School held a teacher and parents meeting on June 18th and a Master Planning Community Meeting on June 19th.
The Metz/Sanchez/Zavala modernization continues its outreach and information gathering efforts so that an informed decision can be reached. Two planning meetings have been held, moving them closer to their decision deadline of August 9th. The Planning Team meeting on June 7th focused on the cultural and historical significance of each of the campuses, and the meeting on June 19th was a discussion on how to weigh the evaluation criteria that will be used to vote.
28 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Elementary Schools Prepare to Co‐Locate Set to undergo modernization, Norman Elementary will co‐locate at nearby Sims Elementary School beginning with the upcoming 2018‐2019 school year. Principal Wendy Mills and Adisa Communications are reaching out to Norman families before the registration deadline with a variety of communication strategies to notify parents that Norman is still open for enrollment of students. Adisa Communications and the combined Norman and Sims Elementary Schools will have a booth at AISD’s Back‐to‐School Bash on Saturday, August 4th to educate parents on the modernization and to educate them on enrollment requirements and deadlines. The school has revamped its website to reflect its co‐located status. Check it out at http://norman‐sims.austinschools.org/. The combined Sims and Norman Elementary Schools are expected to enroll approximately 400 students for the coming school year. Norman will be co‐located with Sims for two school years while the Norman campus is modernized through the 2017 Bond Program. It will re‐open in Fall 2020. Doss Elementary has also moved into the Lucy Read facility so that construction can begin on the Doss campus.
Save the Date for the Upcoming 2017 Bond Celebration Ceremonies!
T.A. Brown Elementary School Site Dedication ‐ Aug. 29 at 9:30 a.m. at the T.A. Brown site
Menchaca Elementary School Groundbreaking ‐ Aug. 30 at 10 a.m. at Menchaca
Doss Elementary School Groundbreaking ‐ Sept. 6 at 10 a.m. at the Doss site
Govalle Elementary School Groundbreaking ‐ Sept. 25 at 10 a.m. at Govalle
More details and formal invitations to follow.
Want the Big Picture on the Bond Program?
You can get the big picture on 2017 Bond Program progress at http://austinisd2017bond.org/events/ and to sign up for regular email updates, go to this link.
Social Media Coverage
There were 34 total posts (3 on Facebook and 31 on Twitter) that were tagged #AISDFuture. They focused primarily on community events, partnering programs and CAT progress at modernized campuses.
Austin ISD currently has more than 30,000 followers on Twitter and 20,000 likes on the District's Facebook page.
29 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Campus Community Meetings T.A. Brown Elementary
Date Group/ Location Time/ Meeting Type
6/21/18 T.A. Brown Elementary School
400 Cooper Dr., Austin TX 78752 9‐10:30 a.m. CAT Meeting
7/18/18 T.A. Brown Schematic Design Community Meeting 400 Cooper Dr., Austin TX 78752
5:30 p.m. Parent and Teacher Meeting
Blazier Relief
Date Group/ Location Time/ Meeting Type
6/12/18 New Blazier Relief
8601 Vortez Blvd, Austin, TX 78744 2‐4:00 p.m. CAT Meeting
6/18/18 New Blazier Relief Teacher and Parent Meeting 8601 Vortez Blvd, Austin, TX 78744
4‐5:30 p.m. Parent and Teacher Meeting
6/19/19 New Blazier Relief: Master Planning Community Meeting
8601 Vortez Blvd, Austin, TX 78744 5‐6:30 p.m. Community Meeting
6/26/18 New Blazier Relief
8601 Vortez Blvd, Austin, TX 78744 2‐4:00 p.m. CAT Meeting
7/17/18 New Blazier Relief
8601 Vortez Blvd, Austin, TX 78744 2‐4:00 p.m. CAT Meeting
7/31/18 New Blazier Relief
8601 Vortez Blvd, Austin, TX 78744 2‐4:00 p.m. CAT Meeting
Doss Elementary
Date Group/ Location Time/ Meeting Type
6/12/18 Doss Elementary
2608 Richcreek Rd., Austin TX 78757 3:15‐4:45 p.m. CAT Meeting at Lucy Read Pre‐K
7/04/18 Doss Elementary School and Murchison Community Meeting at NWACA 4th of July Parade 7005 Northledge Dr, Austin, TX 78731
6‐7:30 p.m. Community Meeting
30 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Date Group/ Location Time/ Meeting Type
7/10/18 Doss Elementary School
2608 Richcreek Rd., Austin TX 78757 3:15‐4:45 p.m. CAT Meeting at Lucy Read Pre‐K
Govalle Elementary School
Date Group/ Location Time/ Meeting Type
6/18/18 Govalle Elementary School 3601 Govalle Ave, Austin, TX 78702
6‐7:00 p.m. Community Meeting
7/18/18 Govalle Elementary School
3601 Govalle Ave, Austin, TX 78702 4‐6:00 p.m. CAT Meeting
Metz, Sanchez and Zavala
Date Group/ Location Time/ Meeting Type
6/07/18 Sanchez Elementary School 73 San Marcos St, Austin, TX 78702
6‐7:30 p.m. Planning Team Meeting
6/19/18 Metz Elementary School 84 Robert T. Martinez Jr. St. Austin, TX 78702
6‐7:30 p.m. Planning Team Meeting
6/19/18 Sanchez Elementary School 73 San Marcos St. Austin, TX 78702
6‐7:30 p.m. Planning Team Meeting
6/19/18 Zavala Elementary School 310 Robert T. Martinez Jr. St. Austin, TX 78702
6‐7:30 p.m. Planning Team Meeting
7/19/18 Metz, Sanchez and Zavala Community Engagement Meeting 1601 Haskell St. Austin, TX 78702
6‐7:30 p.m. Community Engagement at Martin Middle School
Norman Elementary School
Date Group/ Location Time/ Meeting Type
6/05/18 Norman Elementary 4001 Tannehill Ln, Austin TX 78721
4:30‐6:00 p.m. CAT Meeting
7/18/18 Norman Elementary 4:30‐6:00 p.m.
31 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Date Group/ Location Time/ Meeting Type
4001 Tannehill Ln, Austin TX 78721 CAT Meeting
7/27/18 Norman Elementary
1203 Springdale Rd, Austin TX 78721 5:30‐6:45 p.m. CAT Meeting
Murchison Middle School
Date Group/ Location Time/ Meeting Type
6/01/18 Murchison Middle School 3700 N Hills Dr, Austin, TX 78731
8:30‐10:30 a.m. CAT Meeting
6/22/18 Murchison Middle School
3700 N Hills Dr, Austin, TX 78731 10:00‐ noon CAT Meeting
7/17/18 Murchison Middle School
3700 N Hills Dr, Austin, TX 78731 1‐3:00 p.m. CAT meeting
7/31/18 Murchison Middle School
3700 N Hills Dr, Austin, TX 78731 4‐6:00 p.m. CAT Meeting
Ann Richards School for Young Women Leaders
Date Group/ Location Time/ Meeting Type
6/04/18 Schematic Design Community Meeting
2206 Prather Lane, Austin, TX 78704 5‐6:30 p.m. Community Engagement
New Southwest Elementary School
Date Group/ Location Time/ Meeting Type
7/09/18
SW ES Schematic Design Community Meeting at
Circle C Community Center
7817 La Cross Ave, Austin, TX 78739
RESCHEDULED FOR AUGUST 10 6‐7:00 p.m.
7/31/18 SW ES Schematic Design Community Meeting
7817 La Cross Ave, Austin, TX 78739 6‐7:00 p.m. SD Community Meeting
32 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Bowie High School
Date Group/ Location Time/ Meeting Type
6/5/18 Bowie High School at Page Architects
400 W. Cesar Chavez St., Austin TX 78701 1‐3:00 p.m. CAT Meeting
6/20/18 Bowie High School at Page Architects
400 W. Cesar Chavez St., Austin TX 78701 12:30‐2:30 p.m. CAT Meeting
7/11/18 Bowie High School at Page Architects
400 W. Cesar Chavez St., Austin TX 78701 12:30‐2:30 p.m. CAT Meeting
7/18/18 Bowie High School at Page Architects
400 W. Cesar Chavez St., Austin TX 78701 12:30‐2:30 p.m. CAT Meeting
Eastside Memorial Early College High School and International High School
Date Group/ Location Time/ Meeting Type
6/19/18 Eastside Memorial ECHS and IHS Kickoff Meeting
1012 Arthur Styles Rd., Austin TX 78721 9‐10:30 a.m. CAT Meeting
7/31/18 Eastside Memorial ECHS and IHS
1012 Arthur Styles Rd., Austin TX 78721 6‐7:00 p.m. CAT Meeting
Rosedale School
Date Group/ Location Time/ Meeting Type
7/16/18 Rosedale CAT Kickoff and Ed. Spec Orientation
2117 W. 49th St., Austin TX 78756 3‐3:30 p.m. CAT Meeting
33 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
C O M M U N I C A T I O N S T R A T E G I E S & M E T H O D S
Glossary of Terms
GLOSSARY OF TERMS
34 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Glossary of Terms BAS Building Automation System (HVAC and lighting controls)
The automatic centralized control of a building's heating, ventilation and air conditioning, lighting and other systems through a building management system.
Change Order
A modification to the original construction contract authorizing a change in the work or an adjustment in the amount of the contract or the contract time.
Commissioning Agent
An independent party, unaffiliated with the design team or contractors, that takes charge of the construction commissioning process.
Competitive Bidding
A procurement method by which a governmental entity contracts with a contractor for the construction, alteration, rehabilitation, or repair of a facility by awarding the contract to the lowest responsible bidder.
Competitive Sealed Proposal (CSP)
A procurement method by which a governmental entity may request proposals and pricing information based on the scope of work provided, rank the offers, negotiate a contract, and then award the project to the contractor that offers the best value to the entity.
Concept Design
An early phase of the design process, in which the broad outlines of function and form of something are articulated. It includes the design of adjacencies, interactions, circulation, experiences, processes and strategies.
Construction Commissioning
A collaborative process whose purpose is to ensure that buildings and systems perform according to contract.
Construction Documents
Extremely detailed drawings and specifications showing and describing all the details required to construct the building.
Construction Manager at Risk (CMAR)
A construction delivery method by which a governmental entity contracts with an architect or engineer for design and construction phase services and contracts separately with a construction manager-at-risk to serve as the general contractor and to provide consultation during the design and construction, rehabilitation, alteration, or repair of a facility. A CMAR is selected based upon qualifications and price proposal that would provide the best value for the governmental entity.
35 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Construction Phase
Prior to the start of construction, the community will be invited to meet a final time to discuss construction schedule, receive the plan for housing students in an alternative location (if needed), and provide contact information for the community should issue arise during construction.
Contingency
An amount of money reserved by the owner to pay for unforeseen changes in the work.
Daylighting
A planned energy conservation strategy that utilizes illumination from sunlight.
Design Development
Process in which schematic design drawings are further developed to include more detail, including: detailed site plan; room layouts; door and window types; interior and exterior elevations; reflected ceiling plans; plumbing, mechanical, structural, and electrical drawings; and kitchen layouts.
Design Development Phase
The purpose is to inform stakeholder on the interior organization of the building, exterior appearance, and parking, etc.
Design Team
A group of professionals from architectural and engineering firms that is engaged to design a facility.
Educational Specifications
A document that details the number of rooms required, the size of each room, how those rooms should relate to each other (adjacencies), and the elements (sinks, electrical outlets, markerboards, cabinets, etc.) that should be included in each room. District-wide Educational Specifications will be adapted for the specific needs of the campus.
FF&E
Furniture, Fixtures, and Equipment. This describes all contents that are not a permanent part of the structure.
Hard Costs
Expenses associated with direct construction of a project.- Includes labor and material.
Historically Underutilized Business Program (HUB)
Austin ISD promotes and strongly encourages the involvement and participation of Historically Underutilized Businesses (HUBs) in its construction projects. The District is committed to providing opportunities to small minority- and women-owned firms in the Construction Management Bond Program for a diverse array of contractors and service providers. The Board of Trustees adopted the formal HUB program in August 2016. More information is available at www.austinisd.org/hub
36 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
HVAC
Heating, ventilation, and air-conditioning
Job Order Contract (JOC)
A procurement method used for maintenance, repair, alteration, renovation, remediation, or minor construction of a facility when the work is of a recurring nature, but the delivery times, type, and quantities of work required are indefinite.
Leadership in Energy and Environmental Design (LEED)
A building certification process developed by the U.S. Green Building Council (USGBC) to enhance environmental awareness among architects and building contractors and to encourage the design and construction of energy-efficient, water-conserving buildings that use sustainable or green resources and materials.
MEP
Mechanical/Electrical and Plumbing systems.
Program or Concept Design
Single-line drawings that illustrate room adjacencies and scale
Schematic Design
The schematic design submission typically includes a simple site plan, floor plans (simple scale drawings that show room sizes, relationships, doors, and windows), simple building cross sections, an outline specification with general information about building systems, a table comparing required square footages from the educational specifications with actual square footages shown on the drawings, a preliminary estimate of cost options, and possibly 3-dimensional depictions of the exterior of the building. Typically includes a simple site plan, floor plans, simple building cross-sections, an outline specification with general information about building systems, a table comparing required square footages from the educational specifications with actual square footages shown on the drawings, a preliminary estimate of cost options, and three-dimensional depictions of the exterior of the building.
Schematic Design Phase
The purpose is for stakeholders to receive information and provide feedback about the project parameters, how the building relates to the site, anticipated traffic flow, and building orientation, etc.
Soft Costs
A construction industry term, but more specifically a contractor accounting term for an expense item that is not considered direct construction cost. Soft costs include architectural, engineering, financing, legal fees, and other pre- and post-construction expenses.
Swing Space
A school building or a portion of an existing school building or other facility that will house the student population and its teachers and staff during the school-construction process.
37 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
APPENDIX
38 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
APPENDIX A:MURCHISON MS MASTERPLAN PRESENTATION
39 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Austin ISD
Murchison Middle School
MASTER PLAN
8/14/2018
40 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
CONTEXT
• Current Enrollment
• 1500 (Y 2018)
• Future Capacity:
• 1700 (Y 2025)
• Current Area :
• 169,430 S.F.
• 16 Portables House the
6th Grade
41 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
EXISTING BUILDING ANALYSIS
• Current Middle School
Master Schedule
• COA Population
Projections, 2010-2030
• 2016 AISD Demographic
Study
• City of Austin Code -
Tree Regulations
• Kleinfelder Geotechnical
Engineering Site Survey
42 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
EXISTING CONDITION
2 0 1 5 F A C I L I T Y C O N D I T I O N I N D E X
All Priorities
FCA 60 Poor
Summary of Critical
Deficiency Projects - Phase 1
Projects Numb
er
ProjectBudget
HVAC Replacement and Energy
Management
Controls System
1 $488,000
Site Drainage 1 $304,000
CourtyardImprovements
1 $78,000
Architectural + InteriorRenovations
1 $95,000
GrandTotal 4 $965,000
43 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
TRAFFIC CONDITIONS
44 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
MASTER PLAN SITE PLAN
45 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
EXISTING CLASSROOM ASSIGNMENT
LEGEND
BUSINESS - 90 PEOPLE
EDUCATIONAL - 1142 PEOPLE
FINE ARTS - 606 PEOPLE
MEDIA - 74 PEOPLE
ASSEMBLY A-4 - 393 PEOPLE
ASSEMBLY A-4 - 735 PEOPLE
46 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
UTILIZATION
47 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
PROGRAM
SUMMARY
48 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
MASTER PLAN CONCEPT
• Move Administration to the front of the building
• Locate the Library in the center of the building
• New Academic Addition
• Consolidate Fine Arts East and expanding northwest
• Build out remaining academic spaces
• Athletic additions, cafeteria, and kitchenexpansion
PHASE 1 AND FUTURE PHASE CONSIDERATIONS
49 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 1 MASTER PLAN
50 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 1 AXON
51 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 2 MASTER PLAN
52 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 2 AXON
53 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 3 MASTER PLAN
54 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
LEVEL 3 AXON
55 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
PHASE 1 CONCEPT
• Alleviate Bond Program buildingdeficiencies
• Alleviate as many portable buildings aspossible
• Permanently house the 6th grade
• Provide a safe environment for learning
• Locate Library in center of the building
• Relocate Administration at South creating new building entrance
• Locate Academic addition Northwest
• Consolidate / reconfigure existing building only as necessary
• Change how teachers own a classroomto achieve higher utilization (88%) ofclassrooms to better accommodate thegrowing population.
PRIORITIES
56 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
PHASE 1 SITE PLAN
57 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
PHASE 1- OPTION B••••
Move Administration to front of school Move Media Center to Central Commons Academic Addition (6th Grade Center)Renovate old Admin/Classrooms/Library to CTE
3,200 sf10,000 sf36,000 sf14,000 sf
58 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
OPTION 1-B – LEVEL 1
59 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
OPTION 1-B – LEVEL 2
60 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
SCHEDULE
61 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
62 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
APPENDIX B:CONSTRUCTION CONTRACT AUDITING PRESENTATION
63 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
CONSTRUCTION CONTRACT AUDITING
DEBBIE TOWNSEND
R. L. TOWNSEND & ASSOCIATES, LLC
(972) 403‐1829
WWW.RLTOWNSEND.COM
64 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
Founder – Rich Townsend (CPA, CIA, CCA) President – Debbie Townsend (CPA, CIA, CCA, CFE) Small Business since 1984 - 21 employees Focus on construction contract compliance for owners
WHO IS R. L. TOWNSEND & ASSOCIATES, LLC?
65 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
ISD EXPERIENCE
66 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
WHY ARE CONSTRUCTION AUDITS A GOOD IDEA?
Independent review of
large financial
expenditures
Hard Dollar Recoveries
Cost Avoidance
Dollars
Improves controls for
future projects
67 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
BASIC SERVICES
Inclusions:
Lifecycle Auditing
Assist with Management in Resolving Audit Issues
Meetings and Reports as Requested
Presentations as Requested
Exclusions:
Fraud Investigations
68 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
WHAT DOES THE AUDITOR LOOK FOR?
Financial Contract Terms vs. Billings
True up of Costs Based on a %
Review of Subcontracts & Payments
Reconcile Final Cost to Amount Billed
Change Orders (Owner & Subcontract)
Applicability of Sales Tax
Prevailing Wage Rates 69 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALS
AUGUST UPDATE
2017 BOND - $1.1MM
• Design Build (DB) • Construction Manager at Risk (CMR)
Townsend & Associates:
• Competitive Sealed Proposal (CSP) • Other (JOC, POs, etc.) Internal Audit:
70 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
AISD INTERNAL AUDIT
Max Marchlewski -
Director
Jerry Hopkins – Construction
Auditor
71 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE
QUESTIONS
72 of 72 COMMUNITY BOND OVERSIGHT COMMITTEE MEETING RFERENCE MATERIALSAUGUST UPDATE