SALES TAX PROJECTS
3/5Project Number:
Airport Gateway: Springhill Road and Lake Bradford RoadProject Name:
$58,698,138Total Project Cost:
Combined project totals: $58,698,138
Springhill Road (Beautification and Transportation Improvements) $21,426,400
Lake Bradford Gateway $37,271,738
Total Project Cost Notes
Executive Project Summary:This project creates a holistic Airport Gateway project by combining Project #3 (Springhill Road) and
Project #5 (Lake Bradford Road). This project spans from Stadium/Gaines Street to Capital Circle
Soutwest. The improvements will create a unique, urban gateway to Tallahassee from the Airport.
The Lake Bradford component of the project would extend from Gaines St. to the Orange Avenue
intersection. The improvements to this portion of the project would include roundabouts, gateway
streetscaping, and roadway reconstruction.
The Springhill Road section of the proposed project begins the Orange Avenue intersection and extends
down to Capital Circle Southwest (Project #1). The improvements to this portion of the project would
include transportation improvements and right of way acquisition and beautification.
Actions Taken by the Committee:March 28, 2013: Both projects moved to a second round for consideration.
April 26, 2013: Project #3 (Airport Gateway: Springhill Road Gateway) Moved to Priority Level 2 and Project #5 (Lake Bradford
Gateway) Moved to Priority Level 1.
May 9, 2013: Staff presented the Airport Gateway project (combining Project #3 Springhill Road) and Project #5 (Lake Bradford
Road).
June 13, 2013: Moved the combined project to Tier 1.
Themes
X Regional Mobility/Transportation
X Sense of Community
Environmental/Water Quality
X Connectivity
X
X
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways
Detail Project DescriptionSpringhill Road improvements include:
-130’ right of way
-10’ sidewalk on one side and 5’ on other
-Bike lanes on both sides
-2 lanes (4 lane option with 22’ median)
-Enhanced landscape
Lake Bradford Road improvements include:
-Roundabouts at key locations
-Roadway reconstruction
-Gateway streetscaping
12/10/20131
-Bike lanes and wider sidewalks
-Enhanced landscaping and lighting
Cost By Themes
Regional Mobility/Transportation
Sense of Community
Environmental/Water Quality
Connectivity
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways
$57,698,138
$1,000,000
12/10/20132
LakeBradford
O RANGE AVE W
S M
ON
RO
E ST
S A
DA
MS
ST
SPR
ING
HILL
RD
JACKSON BLUFF RD
WO
VILL
E R
D
S A
PPL
EYA
AU
SLE
Y R
D
GAINES ST
LAK
E BR
AD
FOR
D R
D
LAKE BRADFORD
RD
S A
DA
MS
ST
S M
ON
RO
E S
T
WA
HN
ISH W
AY
O RANGE AVE W
CAPITAL CIR SW
LAK
E B
RAD
FORD R
D
SPRINGHILL R
D RIDGE RD
TH
OM
ASV
ILL E
RD
I-10
CE
NTE
RVIL
LE R
D
N M
O
NRO
E
TRA M RDBLOXHAM CUTOFF
1
23
4
Quadrants: 3 & 4Date Printed: April 8, 2013
Airport Gateway: Springhill Road Gateway& Lake Bradford Gateway
..N
E
S
W
N
E
S
W
SALES TAX PROJECTS
3Project Number:
Airport Gateway: Springhill Road GatewayProject Name:
$31,000,000Total Project Cost:
(ROW $10,800,000) (Construction $20,200,000)Total Project Cost Notes
This project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks,
bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road
into the downtown area from the Airport.
Executive Project Summary
Themes
X Regional Mobility/Transportation
X Sense of Community
Environmental/Water Quality
X Connectivity
X
X
X
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways
Detail Project DescriptionThis project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks,
bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road
into the downtown area from the Airport.
Cost By Themes
Regional Mobility/Transportation
Sense of Community
Environmental/Water Quality
Connectivity
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways$31,000,000
4/18/20131
LakeBradford
HAS TIE RD
BLOSSO
M CIR
TANNER DR
KISSIMMEE ST
PO
PPY
FLIP
PER
SA T UR
DA
Y RD
REDBARBER
PO
TT
SDAMER ST
DA
IS
CAMPBELL
G
FA
HA
HO
TU
HAWKIN
PASCO
LENNOXDR G
LYNW
OO
D D
R
PALM
HIL
LSB
OR
WA
RW
IC
P R
D
MOONSTONE
WA
KU
LLA
ST
WA
LNU
T ST
HUTCHINSON AVE
PALM BEACH ST
STH
OLM
ES
CATHEDRAL DR
JEWELL DR
GERALD DR
RONELLIS DR
SEUM RD
EN
TREPO
T BLVD
SEASONS LN
F L ASTACOWO R
DLONG
LEAF CT
TYSON RD
PA
UL
DI R
AC
DR
LAKEVIEW DR
PHILBRICK ST
AUTUMN LN
SH
ADOWWO
ODWINDY PINE WAY
PINEKNOTT
CT
WINDY
AVIA
TIO
N AV
E
AIR
POR
T C
OM
MER
CE
F RAZIERAVE
SUNNYSIDE DR
SILV E RRIDGE DR
SYKES DR
SAYERS D R
BOB WHITE DREAGLE RD
TOU
CA
N D
R
LOR
O L
N
L AR
KW
AYST
SEA
SO
NS
BARON LN
ESTATE RD
SPRI
NIL R
D
SUMMER
ENTREPOT
WH
EATL
EY R
D
SPR
INIL
RD
CRE
E K RD
BLUE
JAY
DR
AU
TUM
N C
T
CT
CTAS
SEM
BLY
TANGELODR
TOP
CT
CT
SAPL
INTA
LLSOLE
DR
LONG PINE DR
BIG
PIN
E D
R
PARTRIDGE DR
RO
BIN
RD
BLU
E B
IRD
RD
RAINBOW RDCROWN RIDGE RD
GU
NN
ST
RO
SS LN
CALLEN ST
RED BARBER
WAY
PLZ
PEN N ELL C
IR
KE
NN
EDY
DR
WEA
VER
DR
CAT
HE R
INE
TAYLOR ST
TUCKER ST
CARVER ST
SAXO
N S
T
HO
LTO
N S
T
ST M
AR
KS
ST
OLI
VER
ST
CLA
RA
ST
WIES ST
STAFFORD
BR
OO
KR
IDGE DR
RA
CK
LEY
DR
GA
LIM
OR
E D
R
PASC
O S
T
MAUDE ST
WA
LCO
TT ST
CALLEN ST
MIL
L ST
LAK
E
SAWMILL RDJOES RD
SPRINGSAX RD
NO
TRE
DA
ME
ST
BET
HU
NE
ST
N R
IDG
E R
D
CYP
RES
S
MCPHERSON DR
VICTORIA ST
BR
UC
E LNDANIELS ST
JAM
ES
ST
SIR W
ILLIAM
S ST
LI ND
SEY C
T
LAK
E S
T
HEN
RIE
TTA
ST
LAK
E
KEI
TH
ST
ST
LN
WOODLAND DR
TALL TOP DR
MANUFACTURER CT PINE CT
CT
PRODUCTIONCT
CT
WA
XWO
OD
BA
RK
DR
W
BUNC
HE A
VE
SAN
D P
INE
DR
BRECK DRSUCCESS
R R
D MOA
N D
RBALBOA DR
WAY
FAMU FS
U W
HA
ST I
ER
D
F RD
GE
OR
GE
MA
RIS
EST
CYPRESSHAWK LN
ST
LAK
E P
ALM
MU
NS
ON
ST
LAK
E M
AR
YST
KINGFO RD AV E
MEDICAL COMMONSCT
SHALOM
JOH
N C
OX
DR
DR
BRAGG DR
AR
RO
WW
OOD LNPIN
ENO
L L DR
BLV
D
OP
E R
D
LAKE BRADFORD RD
CIR SW
LAK
E BR
ADFO
RD RD
SPRINGHILL RD
RIDGE RD
SPRI
NGHI
LL R
D
ORANGE AVE W
TH
OM
ASV
ILL
E R
D
I-10
CENTERV
ILLE
RD
N M
O
NRO
E
TR AM R DBLOXHAM CUTOFF
1
23
4
Quadrant: 3Date Printed: April 8, 2013
Project #3
Airport Gateway: Springhill Road Gateway
..N
E
S
W
N
E
S
W
Previous Project Information for:
Project #3 Airport Gateway: Springhill Road Gateway Note: Based on direction from the Committee at the March 28, 2013 Sales Tax Committee meeting, below is a list of previous project(s) that were merged or modified to create a holistic project for the Committee’s consideration. Project Name: Springhill Road to Indianhead Acres: Right of Way,
Construction, Stormwater Improvements, Greenway and Trail Developments (Previously Project #11)
Blueprint 2000 Proposed Sales Tax Projects
Project Name: Springhill Road to Indianhead Acres: Right of Way, Construction, Stormwater Improvements; Greenway and Trail Developments (Blueprint 2000 Map 2C) Project Themes:
Project Description: This project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks, bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road into the downtown area from the Airport. Water quality enhancement is to be accomplished via improved management of Munson Slough and the impacts to stormwater through roadway widening. Additionally, this project includes acquisition of active, developed properties in the surrounding floodplain areas. A joint stormwater treatment pond is proposed along the East Branch (Indianhead, Paul Russell, and Pine Ridge) to control flooding and improve water quality. Project Map:
Regional Mobility/Transportation Economic Vitality Sense of Community Ecotourism/Parks Water Quality Vertical Infrastructure Connectivity Gateways
Previously Project #11 Page 1 of 1
SALES TAX PROJECTS
5Project Number:
Lake Bradford RoadProject Name:
$37,271,738Total Project Cost:
Conceptual Estimate of Probable Costs
• Lake Bradford Road From Gamble To Csx R/R Overpass (Includes roundabout at Gamble): 0.1 miles,
$1,253,525
• Lake Bradford Road From CSX R/R Overpass To Eppes Drive (Includes roundabout at Eppes): 0.2 miles,
$2,446,300
• Lake Bradford Road From Eppes Drive To Stadium/Gaines (Includes roundabout at Stadium & Airport):
0.37 miles, $6,273,593
• Eppes Drive From Jackson Bluff Road To Lake Bradford Road: 0.43 miles, $2,997,195
• Eppes (Hendry) Drive From Stadium Drive To Jackson Bluff Road: 0.14, $178,985
• Airport Drive From Eppes Drive To Lake Bradford Road: 0.14 miles $650,610
• Jackson Bluff Road From Eppes Drive To Lake Bradford Road (includes pavement removal): 0.32 miles,
$556,680
• Gaines Street From Stadium To Woodward (includes roundabout at Woodward): 0.52 miles, $5,794,850
• Lake Bradford Road From Orange Avenue To Gamble Street: 0.47 miles, $17,120,000
Total Project Cost Notes
This Gateway project would be a continuation of the investment and redevelopment spurred by the first two
phases of the Gaines Street improvements. At present, three major projects, Gaines Street, Lake Bradford
Gateway and FAMU Way, are converging in this area. With additional improvements along the Lake
Bradford corridor, we can further set the stage for redevelopment and reinvestment in this area as well and
provide and an attractive entrance into the City from the Airport.
The purpose of the Gateway is to:
• Create a unique urban gateway to Tallahassee from the Airport
• Allow more organized and consolidated development with installation of stormwater improvements
• Better traffic circulation in and around the Stadium, FSU and the future FAMU Way
Executive Project Summary
Themes
Regional Mobility/Transportation
X Sense of Community
Environmental/Water Quality
X Connectivity
X
X
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways
Detail Project DescriptionThe gateway streetscaping improvements would include roadway reconstruction to allow for bicycle
4/18/20131
facilities and wider sidewalks, roundabouts, and other pedestrian safety enhancements. It would also
include aesthetic elements such as landscaping and lighting.
Cost By Themes
Regional Mobility/Transportation
Sense of Community
Environmental/Water Quality
Connectivity
Economic Vitality
Ecotourism/Parks
Vertical Infrastructure
Gateways$37,271,738
4/18/20132
GAMBLE ST
W HARRISON STGLE NDA DR
LIBERTY ST
MANATEE ST
NASSAU ST
OKALOOSA ST
MIL
L S T
GAMBLE ST
KEI
TH S
T
KISSIMMEE ST
PERR Y S T
HO
LTO
N S
TPO
PPY
ST SA
XON
ST
FLIP
PER
ST
REDBARBER
OVER-
ST AUGUS-
D
PAU
LS
DR
CA
RD
I NA
LC
T
OC
ALA
MU
RAT
ST
ESSE
XW MADISON ST
W BLOXHAM ST
GAY
ST
W MADISON ST
W ST AU G USTINE ST
W LAFAYETTE ST
STLO
REN
RIV
OLI
MAYO
S T
HAY
DE N
RD
PRINCE ST
STAD
IUM
DR W
S M
AC
OM
B
STREETST G
RA ST
LIN
E LN
ESS
EX
DR
CA
RO
LPL
PEPPER DR
ROBERTS ST
MALCOLM JOHNSON RD
W P
AUL
DIRAC D R
E PAUL DIRAC DR
POT
T
S DAMER ST
LEIS
UR
E LN
KAREN LN
TYNDALL DR
KYL
E
VR
OG
Y C
T
TOMAHAWK TRLMELANIE DR
J AC
QU
E-
MA
RI-
LYN
CT
VAN NESS CT
CT
EVEL
YN
ST
LIPONA R
D
AIRPORT DR
MAYHEW ST
HERNANDO DRELBERTA DR
MOSLEY ST
STE
AR
NS S
T
CO
NK
LIN
ST
INDUSTRIAL
DR
MCD O NNELL DR
EUG
ENIA ST
DIS
STO
N S
T
RU
SSE
LL S
T ARDELI A
MILES ST
CTCAROL
CTBELLE VUE WAY
FAIR
BA
NK
SD
R
DR
PASC
O S
T
DA
ISY
ST
OSCEOLA ST
CAMPBELL ST
GORE ST
FAMCEE AVE
HAMPTON AVE
HOWARD AVE
TUSKEGEE ST
HAWKINS ST
PASCO CT
KINGSOLOMON
DUPONT DR
N
POLK DR
YA
KESTNER
LINCOLN STPALM BEACH ST
PALMETTO ST
BARBOURVILLE DR
PE
PA
E J
E P
E
W VAN BUREN ST
HU
DS
ON
S
T
STUCKEY AVE
LAKE AVE
LEVY AVE IND
IAN
RIV
ER S
T
HO
LMES
ST
HIL
LSB
OR
OU
GH
ST
HIG
HLA
ND
ST
MCCASKILL AVE
HIL
LSB
OR
OU
GH
WA
RW
ICK
ST
WA
KU
LLA
ST
MEL
VIN
ST
ST
EPPES DR E
CRATE
DANIEL
STSHARKEY ST
WA
LNU
T ST
CLE
VEL A
ND
ST
KISSIMMEE ST
ST
ATKAMIRE DR
MIK
EST
RA
ILR
OA
D A
VE
YOUNG ST
HUTCHINSON AVE
IAM
ON
IA S
T
GEN
E ST
PALM BEACH ST
FLORAL ST
LBI DR
ST
HO
LMES
ST
R
VARS
ITY
DR
WALLIS
OW
ENS ST
BR
OA
D S
T
S M
AR
TIN
LU
THER
KIN
G J
R B
LVD
S B
RO
NO
UG
H
S
T
FAMU WAY
CT
TINE ST
GU
NN
ST
RO
SS LN
CALLEN ST
RE D BARBER
WAY
PLZ
P EN N ELL
CIR
KE
NN
EDY
DR
WE
AVER
DR
CAT
HE R
INE
TAYLOR ST
TUCKER ST
CARVER ST
SAXO
N S
T
HO
LTO
N S
T
ST M
AR
KS
ST
OLI
VER
ST
CLA
RA
ST
WIES ST
ASC
O S
T
MAUDE ST
WA
LCO
TT ST
CALLEN ST
MIL
L ST
LAK
E
SAWMILL RDJOES RD
BET
HU
NE
S
T
CYP
RE
SS
CPHERSON DR
VICTORIA ST
BR
UC
E L
N
DANIELS ST
JAM
ES S
T
SIR W
ILLIAM
S S
T
LI ND
SEY CT
LAK
E S
T
HEN
RIE
TTA
STLA
KE
KEI
TH
ST
BA
LTZELL
BLOUNT STALL SAINTS ST
ST
FAMU F
SU W
AY
LAK
E P
ALM
MU
NSO
N S
T
LAK
E M
ARY
ST
KINGF O RD AV E
MEDICAL COMMONSCT
BR
ON
OU
GH
ST
STONE VALLEY WAY
ST FRANCISST
SUM
MER
VIL
LEST
MA
IN S
T
SHALOM LN
BLACKBURN AVE
DR
DRDUPONT DR
AU
SLEY
RD
E P
GAINES ST
W PENSACOLA ST
W GAINES ST
LAK
E B
RA
DFO
RD
RD
LAKE BRADFORD RD
S A
DA
MS
S T
S M
ON
RO
E ST
ORANGE AVE W
S M
ON
RO
E ST
S A
DA
MS
ST
RD
WA
HN
ISH W
AY
ORANGE AVE W
TH
OM
ASVI
LLE
RD
I-10
CENTER
VIL
LE R
D
N MO
NRO
E
TRAM RDBLOXHAM CUTOFF
1
23
4
Quadrant: 3 and 4Date Printed: April 8, 2013
Project #5
Lake Bradford Gateway
..N
E
S
W
N
E
S
W
Previous Project Information for:
Project #5 Lake Bradford Gateway
Note: Based on direction from the Committee at the March 28, 2013 Sales Tax Committee meeting, below is a list of previous project(s) that were merged or modified to create a holistic project for the Committee’s consideration. Project Name: Building the Core: Lake Bradford Gateway (Previously Project
#18)
Florida State University – Lake Bradford Gateway Extension to Orange Avenue. (Previously Project #71)
Program Building the Core: Lake Bradford Gateway
Estimated Cost: 1c $37 million
WHAT IS IT? Combining it with other projects within this special district area of the overall Mobility District could create the opportunity for additional redevelopment of the southwestern quadrant of the urban core. This would be a continuation of the redevelopment spurred by the first two phases of the Gaines Street improvements. At present, three major projects, Gaines Street, Lake Bradford Gateway and FAMU Way, are converging in this area. With few additional improvements to the existing concepts, we can set the stage for redevelopment of the area. The project elements include:
Roundabout at Gaines Street / Stadium
Roundabout at Gamble
Landscaping
Eppes Drive and Hendry Street Connections
Major stormwater conveyance system from the Stadium to the north end of Lake Elberta
Evaluation Criteria: Benefits the Environment
Provides Regional Impact / Geographic Equity Supports Economic Development / Revitalization
Enhances Mobility On an Existing Master Plan or Blueprint List
Supports Recreation and Quality of Life Leverages Other Funds
Proposed Lake Bradford Investments
The purpose of the Gateway is to:
Create a unique urban gateway to Tallahassee from the Airport
Allow more organized and consolidated development with installation of stormwater improvements
Better traffic circulation in and around the Stadium, FSU and the future FAMU Way
Previously Project #18 Page 1 of 2
WHY IS IT IMPORTANT?
Benefits the Environment – By increasing access to the St. Marks Trail, a major recreational and commuter bike facility, and by providing safer, more convenient bicycle and pedestrian access to FSU, FAMU, Downtown and Gaines Street, this project would encourage increased use of alternative transportation modes, which results in reduction in fossil fuel use and increased air quality.
Provides Regional Impact / Geographic Equity – Since this corridor is the main entrance to town from the airport, the entire region stands to benefit from creating a positive first impression on visitors. The mobility and aesthetic enhancements also would benefit the neighborhoods and blighted properties in the area.
Enhances Mobility – The project would include bike lanes, rebuilt sidewalks, landscaping, roundabouts and signage, which would increase the safety and access for all modes. It would also allow easier movement of north/south traffic at the intersection of Gaines.
Supports Recreation and Quality of Life – Enhancements along this area would support access to the Lake Elberta Park as well as connections to the St. Marks Trail. Landscaping, lighting and transportation investments would increase the mobility and safety for residents, students, and business patrons in the area.
Supports Economic Development / Revitalization – This project would enhance private investments near the area, such as Collegetown just north, and support further high quality urban redevelopment by creating an aesthetically pleasing and safe pedestrian, bicycle and vehicular infrastructure in walking distance to FSU, FAMU, and Gaines Street.
On an Existing Master Plan or Blueprint List – This has been an identified Gateway project for the City for nearly ten years.
Leverages Other Funds – The City has earmarked approximately 3 million dollars for gateway enhancements in this area.
A roundabout at Stadium, Lake Bradford and Gaines would
provide greater traffic efficiency, shorter crossing distances for
pedestrians and cyclists, and create a monumental gateway
entrance to the Stadium and Gaines St into Downtown.
A ground level view of how Lake Bradford Road
south of Stadium would appear. The more
attractive corridor could facilitate redevelopment.
redevelopmentlong.
Previously Project #18 Page 2 of 2
Proposed Sales Tax Projects by the Community
Project Name: Florida State University – Lake Bradford Gateway Extension to Orange Avenue (Project #71) Project Themes:
Project Description: On March 14, 2013, the Florida State University presented several projects for the consideration of the Sales Tax Committee. This project is for the extension of Lake Bradford Gateway Extension to Orange Avenue. The project description for this project was developed using the materials by FSU during their presentation to the Committee. The University is requesting that the Lake Bradford Gateway project be extended to Orange Avenue. By extending this gateway to Orange Avenue, it would provide an entrance to the downtown core and the Main Campus. This would provide for enhanced signage, landscaping, and similar improvements along this gateway corridor. Project Map:
Regional Mobility/Transportation Economic Vitality Sense of Community Ecotourism/Parks Water Quality Vertical Infrastructure Connectivity Gateways
Previously Project #71 Page 1 of 1