SALES TAX PROJECTS 3/5 Project Number: Airport Gateway: Springhill Road and Lake Bradford Road Project Name: $58,698,138 Total Project Cost: Combined project totals: $58,698,138 Springhill Road (Beautification and Transportation Improvements) $21,426,400 Lake Bradford Gateway $37,271,738 Total Project Cost Notes Executive Project Summary: This project creates a holistic Airport Gateway project by combining Project #3 (Springhill Road) and Project #5 (Lake Bradford Road). This project spans from Stadium/Gaines Street to Capital Circle Soutwest. The improvements will create a unique, urban gateway to Tallahassee from the Airport. The Lake Bradford component of the project would extend from Gaines St. to the Orange Avenue intersection. The improvements to this portion of the project would include roundabouts, gateway streetscaping, and roadway reconstruction. The Springhill Road section of the proposed project begins the Orange Avenue intersection and extends down to Capital Circle Southwest (Project #1). The improvements to this portion of the project would include transportation improvements and right of way acquisition and beautification. Actions Taken by the Committee: March 28, 2013: Both projects moved to a second round for consideration. April 26, 2013: Project #3 (Airport Gateway: Springhill Road Gateway) Moved to Priority Level 2 and Project #5 (Lake Bradford Gateway) Moved to Priority Level 1. May 9, 2013: Staff presented the Airport Gateway project (combining Project #3 Springhill Road) and Project #5 (Lake Bradford Road). June 13, 2013: Moved the combined project to Tier 1. Themes X Regional Mobility/Transportation X Sense of Community Environmental/Water Quality X Connectivity X X Economic Vitality Ecotourism/Parks Vertical Infrastructure Gateways Detail Project Description Springhill Road improvements include: -130’ right of way -10’ sidewalk on one side and 5’ on other -Bike lanes on both sides -2 lanes (4 lane option with 22’ median) -Enhanced landscape Lake Bradford Road improvements include: -Roundabouts at key locations -Roadway reconstruction -Gateway streetscaping 12/10/2013 1

Upload: trandien

Post on 07-Jun-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

SALES TAX PROJECTS

3/5Project Number:

Airport Gateway: Springhill Road and Lake Bradford RoadProject Name:

$58,698,138Total Project Cost:

Combined project totals: $58,698,138

Springhill Road (Beautification and Transportation Improvements) $21,426,400

Lake Bradford Gateway $37,271,738

Total Project Cost Notes

Executive Project Summary:This project creates a holistic Airport Gateway project by combining Project #3 (Springhill Road) and

Project #5 (Lake Bradford Road). This project spans from Stadium/Gaines Street to Capital Circle

Soutwest. The improvements will create a unique, urban gateway to Tallahassee from the Airport.

The Lake Bradford component of the project would extend from Gaines St. to the Orange Avenue

intersection. The improvements to this portion of the project would include roundabouts, gateway

streetscaping, and roadway reconstruction.

The Springhill Road section of the proposed project begins the Orange Avenue intersection and extends

down to Capital Circle Southwest (Project #1). The improvements to this portion of the project would

include transportation improvements and right of way acquisition and beautification.

Actions Taken by the Committee:March 28, 2013: Both projects moved to a second round for consideration.

April 26, 2013: Project #3 (Airport Gateway: Springhill Road Gateway) Moved to Priority Level 2 and Project #5 (Lake Bradford

Gateway) Moved to Priority Level 1.

May 9, 2013: Staff presented the Airport Gateway project (combining Project #3 Springhill Road) and Project #5 (Lake Bradford

Road).

June 13, 2013: Moved the combined project to Tier 1.

Themes

X Regional Mobility/Transportation

X Sense of Community

Environmental/Water Quality

X Connectivity

X

X

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways

Detail Project DescriptionSpringhill Road improvements include:

-130’ right of way

-10’ sidewalk on one side and 5’ on other

-Bike lanes on both sides

-2 lanes (4 lane option with 22’ median)

-Enhanced landscape

Lake Bradford Road improvements include:

-Roundabouts at key locations

-Roadway reconstruction

-Gateway streetscaping

12/10/20131

-Bike lanes and wider sidewalks

-Enhanced landscaping and lighting

Cost By Themes

Regional Mobility/Transportation

Sense of Community

Environmental/Water Quality

Connectivity

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways

$57,698,138

$1,000,000

12/10/20132

LakeBradford

O RANGE AVE W

S M

ON

RO

E ST

S A

DA

MS

ST

SPR

ING

HILL

RD

JACKSON BLUFF RD

WO

VILL

E R

D

S A

PPL

EYA

AU

SLE

Y R

D

GAINES ST

LAK

E BR

AD

FOR

D R

D

LAKE BRADFORD

RD

S A

DA

MS

ST

S M

ON

RO

E S

T

WA

HN

ISH W

AY

O RANGE AVE W

CAPITAL CIR SW

LAK

E B

RAD

FORD R

D

SPRINGHILL R

D RIDGE RD

TH

OM

ASV

ILL E

RD

I-10

CE

NTE

RVIL

LE R

D

N M

O

NRO

E

TRA M RDBLOXHAM CUTOFF

1

23

4

Quadrants: 3 & 4Date Printed: April 8, 2013

Airport Gateway: Springhill Road Gateway& Lake Bradford Gateway

..N

E

S

W

N

E

S

W

SALES TAX PROJECTS

3Project Number:

Airport Gateway: Springhill Road GatewayProject Name:

$31,000,000Total Project Cost:

(ROW $10,800,000) (Construction $20,200,000)Total Project Cost Notes

This project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks,

bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road

into the downtown area from the Airport.

Executive Project Summary

Themes

X Regional Mobility/Transportation

X Sense of Community

Environmental/Water Quality

X Connectivity

X

X

X

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways

Detail Project DescriptionThis project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks,

bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road

into the downtown area from the Airport.

Cost By Themes

Regional Mobility/Transportation

Sense of Community

Environmental/Water Quality

Connectivity

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways$31,000,000

4/18/20131

LakeBradford

HAS TIE RD

BLOSSO

M CIR

TANNER DR

KISSIMMEE ST

PO

PPY

FLIP

PER

SA T UR

DA

Y RD

REDBARBER

PO

TT

SDAMER ST

DA

IS

CAMPBELL

G

FA

HA

HO

TU

HAWKIN

PASCO

LENNOXDR G

LYNW

OO

D D

R

PALM

HIL

LSB

OR

WA

RW

IC

P R

D

MOONSTONE

WA

KU

LLA

ST

WA

LNU

T ST

HUTCHINSON AVE

PALM BEACH ST

STH

OLM

ES

CATHEDRAL DR

JEWELL DR

GERALD DR

RONELLIS DR

SEUM RD

EN

TREPO

T BLVD

SEASONS LN

F L ASTACOWO R

DLONG

LEAF CT

TYSON RD

PA

UL

DI R

AC

DR

LAKEVIEW DR

PHILBRICK ST

AUTUMN LN

SH

ADOWWO

ODWINDY PINE WAY

PINEKNOTT

CT

WINDY

AVIA

TIO

N AV

E

AIR

POR

T C

OM

MER

CE

F RAZIERAVE

SUNNYSIDE DR

SILV E RRIDGE DR

SYKES DR

SAYERS D R

BOB WHITE DREAGLE RD

TOU

CA

N D

R

LOR

O L

N

L AR

KW

AYST

SEA

SO

NS

BARON LN

ESTATE RD

SPRI

NIL R

D

SUMMER

ENTREPOT

WH

EATL

EY R

D

SPR

INIL

RD

CRE

E K RD

BLUE

JAY

DR

AU

TUM

N C

T

CT

CTAS

SEM

BLY

TANGELODR

TOP

CT

CT

SAPL

INTA

LLSOLE

DR

LONG PINE DR

BIG

PIN

E D

R

PARTRIDGE DR

RO

BIN

RD

BLU

E B

IRD

RD

RAINBOW RDCROWN RIDGE RD

GU

NN

ST

RO

SS LN

CALLEN ST

RED BARBER

WAY

PLZ

PEN N ELL C

IR

KE

NN

EDY

DR

WEA

VER

DR

CAT

HE R

INE

TAYLOR ST

TUCKER ST

CARVER ST

SAXO

N S

T

HO

LTO

N S

T

ST M

AR

KS

ST

OLI

VER

ST

CLA

RA

ST

WIES ST

STAFFORD

BR

OO

KR

IDGE DR

RA

CK

LEY

DR

GA

LIM

OR

E D

R

PASC

O S

T

MAUDE ST

WA

LCO

TT ST

CALLEN ST

MIL

L ST

LAK

E

SAWMILL RDJOES RD

SPRINGSAX RD

NO

TRE

DA

ME

ST

BET

HU

NE

ST

N R

IDG

E R

D

CYP

RES

S

MCPHERSON DR

VICTORIA ST

BR

UC

E LNDANIELS ST

JAM

ES

ST

SIR W

ILLIAM

S ST

LI ND

SEY C

T

LAK

E S

T

HEN

RIE

TTA

ST

LAK

E

KEI

TH

ST

ST

LN

WOODLAND DR

TALL TOP DR

MANUFACTURER CT PINE CT

CT

PRODUCTIONCT

CT

WA

XWO

OD

BA

RK

DR

W

BUNC

HE A

VE

SAN

D P

INE

DR

BRECK DRSUCCESS

R R

D MOA

N D

RBALBOA DR

WAY

FAMU FS

U W

HA

ST I

ER

D

F RD

GE

OR

GE

MA

RIS

EST

CYPRESSHAWK LN

ST

LAK

E P

ALM

MU

NS

ON

ST

LAK

E M

AR

YST

KINGFO RD AV E

MEDICAL COMMONSCT

SHALOM

JOH

N C

OX

DR

DR

BRAGG DR

AR

RO

WW

OOD LNPIN

ENO

L L DR

BLV

D

OP

E R

D

LAKE BRADFORD RD

CIR SW

LAK

E BR

ADFO

RD RD

SPRINGHILL RD

RIDGE RD

SPRI

NGHI

LL R

D

ORANGE AVE W

TH

OM

ASV

ILL

E R

D

I-10

CENTERV

ILLE

RD

N M

O

NRO

E

TR AM R DBLOXHAM CUTOFF

1

23

4

Quadrant: 3Date Printed: April 8, 2013

Project #3

Airport Gateway: Springhill Road Gateway

..N

E

S

W

N

E

S

W

Previous Project Information for:

Project #3 Airport Gateway: Springhill Road Gateway Note: Based on direction from the Committee at the March 28, 2013 Sales Tax Committee meeting, below is a list of previous project(s) that were merged or modified to create a holistic project for the Committee’s consideration. Project Name: Springhill Road to Indianhead Acres: Right of Way,

Construction, Stormwater Improvements, Greenway and Trail Developments (Previously Project #11)

Blueprint 2000 Proposed Sales Tax Projects

Project Name: Springhill Road to Indianhead Acres: Right of Way, Construction, Stormwater Improvements; Greenway and Trail Developments (Blueprint 2000 Map 2C) Project Themes:

Project Description: This project proposes to widen Springhill Road to four lanes, provide roadway beautification, sidewalks, bike lanes, and screening of lands adjacent to roadway. Springhill Road is envisioned as a “gateway” road into the downtown area from the Airport. Water quality enhancement is to be accomplished via improved management of Munson Slough and the impacts to stormwater through roadway widening. Additionally, this project includes acquisition of active, developed properties in the surrounding floodplain areas. A joint stormwater treatment pond is proposed along the East Branch (Indianhead, Paul Russell, and Pine Ridge) to control flooding and improve water quality. Project Map:

Regional Mobility/Transportation Economic Vitality Sense of Community Ecotourism/Parks Water Quality Vertical Infrastructure Connectivity Gateways

Previously Project #11 Page 1 of 1

SALES TAX PROJECTS

5Project Number:

Lake Bradford RoadProject Name:

$37,271,738Total Project Cost:

Conceptual Estimate of Probable Costs

• Lake Bradford Road From Gamble To Csx R/R Overpass (Includes roundabout at Gamble): 0.1 miles,

$1,253,525

• Lake Bradford Road From CSX R/R Overpass To Eppes Drive (Includes roundabout at Eppes): 0.2 miles,

$2,446,300

• Lake Bradford Road From Eppes Drive To Stadium/Gaines (Includes roundabout at Stadium & Airport):

0.37 miles, $6,273,593

• Eppes Drive From Jackson Bluff Road To Lake Bradford Road: 0.43 miles, $2,997,195

• Eppes (Hendry) Drive From Stadium Drive To Jackson Bluff Road: 0.14, $178,985

• Airport Drive From Eppes Drive To Lake Bradford Road: 0.14 miles $650,610

• Jackson Bluff Road From Eppes Drive To Lake Bradford Road (includes pavement removal): 0.32 miles,

$556,680

• Gaines Street From Stadium To Woodward (includes roundabout at Woodward): 0.52 miles, $5,794,850

• Lake Bradford Road From Orange Avenue To Gamble Street: 0.47 miles, $17,120,000

Total Project Cost Notes

This Gateway project would be a continuation of the investment and redevelopment spurred by the first two

phases of the Gaines Street improvements. At present, three major projects, Gaines Street, Lake Bradford

Gateway and FAMU Way, are converging in this area. With additional improvements along the Lake

Bradford corridor, we can further set the stage for redevelopment and reinvestment in this area as well and

provide and an attractive entrance into the City from the Airport.

The purpose of the Gateway is to:

• Create a unique urban gateway to Tallahassee from the Airport

• Allow more organized and consolidated development with installation of stormwater improvements

• Better traffic circulation in and around the Stadium, FSU and the future FAMU Way

Executive Project Summary

Themes

Regional Mobility/Transportation

X Sense of Community

Environmental/Water Quality

X Connectivity

X

X

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways

Detail Project DescriptionThe gateway streetscaping improvements would include roadway reconstruction to allow for bicycle

4/18/20131

facilities and wider sidewalks, roundabouts, and other pedestrian safety enhancements. It would also

include aesthetic elements such as landscaping and lighting.

Cost By Themes

Regional Mobility/Transportation

Sense of Community

Environmental/Water Quality

Connectivity

Economic Vitality

Ecotourism/Parks

Vertical Infrastructure

Gateways$37,271,738

4/18/20132

GAMBLE ST

W HARRISON STGLE NDA DR

LIBERTY ST

MANATEE ST

NASSAU ST

OKALOOSA ST

MIL

L S T

GAMBLE ST

KEI

TH S

T

KISSIMMEE ST

PERR Y S T

HO

LTO

N S

TPO

PPY

ST SA

XON

ST

FLIP

PER

ST

REDBARBER

OVER-

ST AUGUS-

D

PAU

LS

DR

CA

RD

I NA

LC

T

OC

ALA

MU

RAT

ST

ESSE

XW MADISON ST

W BLOXHAM ST

GAY

ST

W MADISON ST

W ST AU G USTINE ST

W LAFAYETTE ST

STLO

REN

RIV

OLI

MAYO

S T

HAY

DE N

RD

PRINCE ST

STAD

IUM

DR W

S M

AC

OM

B

STREETST G

RA ST

LIN

E LN

ESS

EX

DR

CA

RO

LPL

PEPPER DR

ROBERTS ST

MALCOLM JOHNSON RD

W P

AUL

DIRAC D R

E PAUL DIRAC DR

POT

T

S DAMER ST

LEIS

UR

E LN

KAREN LN

TYNDALL DR

KYL

E

VR

OG

Y C

T

TOMAHAWK TRLMELANIE DR

J AC

QU

E-

MA

RI-

LYN

CT

VAN NESS CT

CT

EVEL

YN

ST

LIPONA R

D

AIRPORT DR

MAYHEW ST

HERNANDO DRELBERTA DR

MOSLEY ST

STE

AR

NS S

T

CO

NK

LIN

ST

INDUSTRIAL

DR

MCD O NNELL DR

EUG

ENIA ST

DIS

STO

N S

T

RU

SSE

LL S

T ARDELI A

MILES ST

CTCAROL

CTBELLE VUE WAY

FAIR

BA

NK

SD

R

DR

PASC

O S

T

DA

ISY

ST

OSCEOLA ST

CAMPBELL ST

GORE ST

FAMCEE AVE

HAMPTON AVE

HOWARD AVE

TUSKEGEE ST

HAWKINS ST

PASCO CT

KINGSOLOMON

DUPONT DR

N

POLK DR

YA

KESTNER

LINCOLN STPALM BEACH ST

PALMETTO ST

BARBOURVILLE DR

PE

PA

E J

E P

E

W VAN BUREN ST

HU

DS

ON

S

T

STUCKEY AVE

LAKE AVE

LEVY AVE IND

IAN

RIV

ER S

T

HO

LMES

ST

HIL

LSB

OR

OU

GH

ST

HIG

HLA

ND

ST

MCCASKILL AVE

HIL

LSB

OR

OU

GH

WA

RW

ICK

ST

WA

KU

LLA

ST

MEL

VIN

ST

ST

EPPES DR E

CRATE

DANIEL

STSHARKEY ST

WA

LNU

T ST

CLE

VEL A

ND

ST

KISSIMMEE ST

ST

ATKAMIRE DR

MIK

EST

RA

ILR

OA

D A

VE

YOUNG ST

HUTCHINSON AVE

IAM

ON

IA S

T

GEN

E ST

PALM BEACH ST

FLORAL ST

LBI DR

ST

HO

LMES

ST

R

VARS

ITY

DR

WALLIS

OW

ENS ST

BR

OA

D S

T

S M

AR

TIN

LU

THER

KIN

G J

R B

LVD

S B

RO

NO

UG

H

S

T

FAMU WAY

CT

TINE ST

GU

NN

ST

RO

SS LN

CALLEN ST

RE D BARBER

WAY

PLZ

P EN N ELL

CIR

KE

NN

EDY

DR

WE

AVER

DR

CAT

HE R

INE

TAYLOR ST

TUCKER ST

CARVER ST

SAXO

N S

T

HO

LTO

N S

T

ST M

AR

KS

ST

OLI

VER

ST

CLA

RA

ST

WIES ST

ASC

O S

T

MAUDE ST

WA

LCO

TT ST

CALLEN ST

MIL

L ST

LAK

E

SAWMILL RDJOES RD

BET

HU

NE

S

T

CYP

RE

SS

CPHERSON DR

VICTORIA ST

BR

UC

E L

N

DANIELS ST

JAM

ES S

T

SIR W

ILLIAM

S S

T

LI ND

SEY CT

LAK

E S

T

HEN

RIE

TTA

STLA

KE

KEI

TH

ST

BA

LTZELL

BLOUNT STALL SAINTS ST

ST

FAMU F

SU W

AY

LAK

E P

ALM

MU

NSO

N S

T

LAK

E M

ARY

ST

KINGF O RD AV E

MEDICAL COMMONSCT

BR

ON

OU

GH

ST

STONE VALLEY WAY

ST FRANCISST

SUM

MER

VIL

LEST

MA

IN S

T

SHALOM LN

BLACKBURN AVE

DR

DRDUPONT DR

AU

SLEY

RD

E P

GAINES ST

W PENSACOLA ST

W GAINES ST

LAK

E B

RA

DFO

RD

RD

LAKE BRADFORD RD

S A

DA

MS

S T

S M

ON

RO

E ST

ORANGE AVE W

S M

ON

RO

E ST

S A

DA

MS

ST

RD

WA

HN

ISH W

AY

ORANGE AVE W

TH

OM

ASVI

LLE

RD

I-10

CENTER

VIL

LE R

D

N MO

NRO

E

TRAM RDBLOXHAM CUTOFF

1

23

4

Quadrant: 3 and 4Date Printed: April 8, 2013

Project #5

Lake Bradford Gateway

..N

E

S

W

N

E

S

W

Previous Project Information for:

Project #5 Lake Bradford Gateway

Note: Based on direction from the Committee at the March 28, 2013 Sales Tax Committee meeting, below is a list of previous project(s) that were merged or modified to create a holistic project for the Committee’s consideration. Project Name: Building the Core: Lake Bradford Gateway (Previously Project

#18)

Florida State University – Lake Bradford Gateway Extension to Orange Avenue. (Previously Project #71)

Program Building the Core: Lake Bradford Gateway

Estimated Cost: 1c $37 million

WHAT IS IT? Combining it with other projects within this special district area of the overall Mobility District could create the opportunity for additional redevelopment of the southwestern quadrant of the urban core. This would be a continuation of the redevelopment spurred by the first two phases of the Gaines Street improvements. At present, three major projects, Gaines Street, Lake Bradford Gateway and FAMU Way, are converging in this area. With few additional improvements to the existing concepts, we can set the stage for redevelopment of the area. The project elements include:

Roundabout at Gaines Street / Stadium

Roundabout at Gamble

Landscaping

Eppes Drive and Hendry Street Connections

Major stormwater conveyance system from the Stadium to the north end of Lake Elberta

Evaluation Criteria: Benefits the Environment

Provides Regional Impact / Geographic Equity Supports Economic Development / Revitalization

Enhances Mobility On an Existing Master Plan or Blueprint List

Supports Recreation and Quality of Life Leverages Other Funds

Proposed Lake Bradford Investments

The purpose of the Gateway is to:

Create a unique urban gateway to Tallahassee from the Airport

Allow more organized and consolidated development with installation of stormwater improvements

Better traffic circulation in and around the Stadium, FSU and the future FAMU Way

Previously Project #18 Page 1 of 2

WHY IS IT IMPORTANT?

Benefits the Environment – By increasing access to the St. Marks Trail, a major recreational and commuter bike facility, and by providing safer, more convenient bicycle and pedestrian access to FSU, FAMU, Downtown and Gaines Street, this project would encourage increased use of alternative transportation modes, which results in reduction in fossil fuel use and increased air quality.

Provides Regional Impact / Geographic Equity – Since this corridor is the main entrance to town from the airport, the entire region stands to benefit from creating a positive first impression on visitors. The mobility and aesthetic enhancements also would benefit the neighborhoods and blighted properties in the area.

Enhances Mobility – The project would include bike lanes, rebuilt sidewalks, landscaping, roundabouts and signage, which would increase the safety and access for all modes. It would also allow easier movement of north/south traffic at the intersection of Gaines.

Supports Recreation and Quality of Life – Enhancements along this area would support access to the Lake Elberta Park as well as connections to the St. Marks Trail. Landscaping, lighting and transportation investments would increase the mobility and safety for residents, students, and business patrons in the area.

Supports Economic Development / Revitalization – This project would enhance private investments near the area, such as Collegetown just north, and support further high quality urban redevelopment by creating an aesthetically pleasing and safe pedestrian, bicycle and vehicular infrastructure in walking distance to FSU, FAMU, and Gaines Street.

On an Existing Master Plan or Blueprint List – This has been an identified Gateway project for the City for nearly ten years.

Leverages Other Funds – The City has earmarked approximately 3 million dollars for gateway enhancements in this area.

A roundabout at Stadium, Lake Bradford and Gaines would

provide greater traffic efficiency, shorter crossing distances for

pedestrians and cyclists, and create a monumental gateway

entrance to the Stadium and Gaines St into Downtown.

A ground level view of how Lake Bradford Road

south of Stadium would appear. The more

attractive corridor could facilitate redevelopment.

redevelopmentlong.

Previously Project #18 Page 2 of 2

Proposed Sales Tax Projects by the Community

Project Name: Florida State University – Lake Bradford Gateway Extension to Orange Avenue (Project #71) Project Themes:

Project Description: On March 14, 2013, the Florida State University presented several projects for the consideration of the Sales Tax Committee. This project is for the extension of Lake Bradford Gateway Extension to Orange Avenue. The project description for this project was developed using the materials by FSU during their presentation to the Committee. The University is requesting that the Lake Bradford Gateway project be extended to Orange Avenue. By extending this gateway to Orange Avenue, it would provide an entrance to the downtown core and the Main Campus. This would provide for enhanced signage, landscaping, and similar improvements along this gateway corridor. Project Map:

Regional Mobility/Transportation Economic Vitality Sense of Community Ecotourism/Parks Water Quality Vertical Infrastructure Connectivity Gateways

Previously Project #71 Page 1 of 1