Page 1: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

AZ Presentation5 March 2019

Construction A to Z

1

Page 2: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

2

Outlook

Page 3: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

3

Outlook

Page 4: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Structure & Management

CAZ (Thailand) PLC

EPC service for customer in energy business

JKEC Co., Ltd.

Civil Construction service

Takuni (Thailand) Co., Ltd.

LPG system construction

36.6% 27.3% 38.1%

73.2%

4

Strategic Shareholders

(Management)

Company Structure

Minor Shareholders

(CAZ staffs 8%)

Page 5: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

IntroductionBackground and Vision

VisionA most competitive construction contractor who

creates sustainable prosperity in Thailand.

Mission- Excellent construction capability, competitive

fabricator.

- Set engineering capability, entered into oversea

market.

- Strong EPC player in Asia Pacific Region.Projects

As of February 2014, CAZ has established from executives

and managerial staffs who has extensive experiences and

has completed numerous project as a well recognized EPC

contractor in Oil & Gas, Petrochemical, Chemical, Energy,

Power plants segments.

CAZ‘s major business range is Construction Total Service &

Management System (Procurement, Construction, and Shop

Fabrication) to provide clients with the best possible service

in all phases of project from A to Z including Civil &

Architectural, Structural, Tank & Vessel, and Heaters

Fabrication work, Piping & Mechanical erection, Electrical,

Instrument work regardless of project amount.

On - going

15Finished

40

5

Backlog

2,516As of 28 February 2019

Page 6: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

IntroductionMilestone

2014

Established in

February- Paid up capital 23 MB

- Integrated Production

Control System

program to improve

project cost

management

2015

Strong Partnership- Partnering with TAKUNI,

listed company in MAI stock

market

- Paid up capital 54.5 MB

- Our first EPC project, PTT

ASAHI SAR

- Integrated Welding Control

System & Spool Tracking

Management System to

improve our quality

2016

New office and

Workshop - Paid up capital 58.5

MB

- Acquired 51% of JKEC

Co., Ltd as subsidiary

- Purchase 108 Rai of

Land and Factory

- Thailand’s biggest

Spherical Tank project,

PTT Tank’s Propylene

tank, 332 MB as EPC

2018

Solid Growth - Paid up capital 100 MB

- PTT LNG Cold Water

Project, 643 MB as EPC

project

- Certified ASME Stamp

for Pressure Vessel, Tank

Fabrication

2017Sustainability - Additionally acquired

JKEC to be 73% of total

shares

- Highest Backlog of 2,816

MB

- Awarded Bangchak

Enclosure Ground Flare

Project, 272 MB as EPC

project

- Awarded PTT GC ORP

SMP Project 1,570 MB

and PTT GC PO Civil Project

451 MB

6

Page 7: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

7

Outlook

Page 8: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

E

P C

• P&ID

• 3D Modeling

• Detail DWG

• Buying

• Expediting & Inspection

• Logistics

Engineering

Procurement

Execution

• Civil & Arch

• STR Fab. / Equip. Erection / Piping

• Electrical & Instrument

• Scaffolding / Painting

• Pre-commissioning / Commissioning

Construction

Scope of Services

EPC Work

PTT Tank Terminal4,000 Tons Spherical Tank, Transfer

Pump, Ground Flare & Etc.Contract Amount : 345 MB

December 2016 – October 2018

BCP EGFEnclosed Ground FlareContract Amount : 272 MB

April 2018 – June 2019

-8-

EPC

Engineering

Procurement

Construction

40.7%

PTT LNG Cold WaterNG Vaporizer, NG Heater, Tanks, Pumps

& etc.Contract Amount : 733 MB

July 2017– July 2018

Page 9: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Scope of Services

SMP / E&I

PTT Midline Compressor Station800 tons for Equip, Compressor 4 setsContract Amount : 508 MB

April 2016 – April 2017

PTT LPG Terminal

Khao Bo Ya PJT E&I WorkE&I : 310,000 MContract Amount : 200 MB

September 2014 – January 2016

PTT LNG Receiving Terminal Expansion Process Structure. Equip. Foundation, Pipe Rack

Pre-castingContract Amount : 382 MB

November 2014 – March 2016 -9-

SMP / E&I

Steel Structure

Mechanical

Piping

Electrical & Instrument • Cable Tray & Conduit, Cabling, Electric Equipment Install. SWGR/MCC

• Instrument Calibration, Loop Test and Function Test

• Platform & Ladder • Shelter

• Equipment Erection for Compressor, Pump, Column, Vessel, etc.

• Shop Fabrication & Field Erection for General, Dissimilar, special

Execution

• Equipment Structure24.8%

Page 10: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Scope of Services

Civil & Arch. Work

IRPC PPECivil and Electric Work Contract Amount : 83 MB

February 2016 – December 2016

Samsung TSE ATV Civil and Structure Work Contract Amount : 113 MB

February 2016 – April 2016

PTT PO CivilCivil Work & quip. FoundationContract Amount : 452 MB

January 2018 – January 2020 -10-

CCivil & Building.

Civil Piling (Bored / Driven / Non-Pollution Pile)

Tank Foundation (Concrete Type)

Pre-Casting Concrete Pipe Rack

Central Control Building

Compressor BuildingBuilding

Execution

Equipment Foundation

Tank Foundation (Earth Type)

Concrete Fire Proofing

Pelletizing Building

Sub-Station Building

24.7%

Page 11: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Scope of Services

Shop Fabrication Capability

Vessel/Heat Exchanger/SKIDTankStack/Fired Heater-11-

Shop Fabrication

Structure Fabrication

Production Capability : 1,500 Tons / Month

Pipe rack, Equipment & Shelter Structure Work

Furnace & Heater Fabrication Work

Platform & Ladder Fabrication Work

Flare Stack Fabrication Work

Tank FabricationTank Fabrication

FRT Tank

DRT / CRT Tank

Spherical Tank

Vessel Fabrication

Thickness : Max. 75 m/m

Handling Weight : Max. 120 Ton/unit

Handling Length : Max. 50 m

Max Capability : 200 Tons / Month

(Pressure Vessel)

Pressure Vessel Fabrication

9.9%

Page 12: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Office and Fabrication shops

Scope of Services

12

CAZ

MaptaphudU-Tapao

Laem Chabang

10 KM

Page 13: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

13

Outlook

Page 14: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Cost Control

CAZ Strategy

Operation Strategy

-14-

Quality of service – No subcontract

Tight control of budget by Risk Management Gate and set

procurement policy

Develop IT System and maximize automation for shop

fabrication to increase productivities

Participate the bidding with partner and/or Main

Contractor

Award project as Main Contractor

Expand new client and projects

Main Contractor

40.2

59.8Subcontractor

Customer

Relationship

Page 15: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

CAZ Strategy

Risk Management Gate

Bidding Price

Decision

Alternative

Proposal

Cost

Estimation

Risk

Analysis

6. Project

Close-out

5. Project

Execution

4. Project

Preparation

3. Contract

Negotiation

Final Decision

for Bidding

Evaluation

for Bidding or not

Project

Information

1. Project Bidding

Decision

Site

Survey

2. Proposal

Development

Review of

Contract Doc.

Result of

Negotiation

Preparation of

Negotiation

Analysis

For Bidding Result

Early

Start

Project

ITC

Project

Execution Plan

Internal Kick-off

Meeting

Project Launch

Meeting

ITC of

Changed Plan

Early

Construction

Exclusive

Contract

Request

Urgent Money

Overrun

Report

Monthly

Performance Review

Report of

Project Completion

Review

Contract Condition

Internal Kick-off

Meeting

15

6 Steps

Page 16: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

IT Management System

System is based on Bar-Code & GPS System

Structure Production Control System (SPCM) and Spool Tracking Management System(STMS)

STMS 3D Map STMS Google MapTracking by PDA with GPS

PDA

16

Page 17: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Log-In Screen Daily Welding Inspection Report

Shop & Field Welding Progress Report

Spool Fabrication Status

Report List

- Progress Report : 5

- Inspection Report : 3

- Spool Report : 3

- NDE Report : 9

- Welder Report : 5

Welding Control System (CWCS) - System is based on Web Version

IT Management System

Test Package Report

Status for Welder Efficiency

NDE Request Report

RT Shooting Status Report

17

Page 18: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Tools, Asset & Consumable Management System (TCMS)

Base on Bar-Code System

IT Management System

18

Page 19: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

19

Outlook

Page 20: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Financial PerformanceOverall Highlight

20

272

742651

1,019

2017201620152014 2018

1,387

Revenue(Million Baht)

2015 2016 2017

Profitability(Percentage)

2019

2018

11.18.3

53.022.9

2015 2016 2017 2018

10.11 11.55

9.98 10.52

1.12 1.69 2.24 3.81

Gross Profit Net Profit

Net Profit (Million Baht)

Page 21: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Assets

Financial Position

19.41%

Cash

13%

Account

Receivable

23%

Unbilled

Income

PPE

43%

9%

12%

Cash

3%

Account

Receivable

18%

Unbilled Income

24%

PPE

32%

Inventory

12%

Other assets

11%

729.1 MB

(Dec’17)1,149.8 MB

(Dec’18)

o Increased in Unbilled income

o Increased in equipment purchase during the

period.

o Increased in inventories for new projects

o Decreased in cash as dividend payment 34.87 Mil.

Baht

o Increased in Account Payable and Unearned Income

o Decreased in Loan from bank as repayment during the

period.

o Dividend payment in May’18

Liabilities and Equity729.1 MB

(Dec’17)

Account

Payable

24%

Unearned

Income

23%

Bank Loan

30%

Equity

19%

1,149.8 MB

(Dec’18)

Account

Payable

25%

Unearned

Income

37%

Bank Loan

21%

Equity

14%

21

Financial Performance

Page 22: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Leverage Ratio

2.59

4.73

4.15

6.11

0.64

3.48

1.58 1.52

-

2.00

4.00

6.00

8.00

FY2015 FY2016 FY2017 FY2018

Debt to Equity Interest Bearing Debt

Efficiency Ratio

14.63 12.94

19.78

35.88

7.38 6.94 7.11 8.80

-

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

FY2015 FY2016 FY2017 FY2018

Return on Equity Return on Asset

Financial PerformanceFinancial Ratio

22

* After IPO, Interest bearing debt to equity will reduce to be 0.60

Page 23: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Introduction

About Construction A to Z

Financial Performance

Scope of Services

CAZ Strategy

23

Outlook

Page 24: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Business Outlook

Eastern Economic Corridor Development

24Source: Ministry of Industry’s presentation of “Eastern Economic Corridor Development Project” Driving Forward, 15 February 2017

Page 25: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

* As PTT Group (PTT LNG, Thai Oil, PTT GC, IRPC)

invested for MEGA Project, Down Stream project

also shall be continuously invested (HMC PP,

BST, Dow Chemical & etc)

PTTGC – Award 2,021 M. Baht from

53,600 M. Baht (3.8%)

2018 Propylene Oxide Project (11,200 M.Baht)

2018 Polyols Project (20,000 M.Baht)

2018 Olefins Reconfiguration Project (22,400

M.Baht)

IRPC

2019 Paraxylene Plant Project (30,000 M.Baht)

2019 Olefins Expansion Project (20,000 M.Baht)

Business Outlook

Customer Investment

25

2018 Terminal 2 7.5 MTPA (30,000 M.Baht)

2020 EGAT 5 MTPA

2026 Terminal 3 5 MTPA

2031 Terminal 4 5 MTPA

Terminal

LNG Infrastructure

Thai Oil

2019 Clean Fuel Project (140,000 M.Baht)

2019 Improvement (4,000 M.Baht)

*Annual Maintenance (1,320 M.Baht)

BCP – Award 314 M. Baht from 8,400 M.

Baht (3.7%)

2018 Continuous Catalyst Regeneration Unit

(8,400 M.Baht)

Page 26: AZ Presentation - CAZ (Thailand) Public Company LimitedControl System program to improve project cost management 2015 Strong Partnership - Partnering with TAKUNI, listed company in

Key Success Factor

-26-

CAZ Highlight

1

25

4 3Solid backlog secured

Cost management

Experienced

management team

Good relationship with

renowned owners and

main contractors

Strong financial status