  • 7/28/2019 B Questionnaire Fujita

    1/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    1 Tender Offer Price(s)

    As this is a lump sum contract, your offer price shall be deemed to

    have been priced in the Bills of Quantities that you have entered in the

    Form of Tender(s). Please confirm.

    2 Time for Completion

    Please confirm that you will be able to complete the Whole Works of

    the Construction Project within the period listed in your submitted

    Schedule.

    3 Tender Documentsa) Please confirm that you will comply fully to 'Instruction to

    Tenderers' and follow all updates in addenda

    b) For the design, please confirm that you followed design standards

    listed in the scopes of works and load capacity in the Tendering

    drawings and addenda

    4 Litigation Please confirm your current litigation information

    5 Organization

    Please confirm that you will provide key staff follow closely with your

    organization chart and manpower allocation, it is our requirement that

    your PM must be fulltime at site and Head of Design Leader must be

    full time at least during the design period

    6 Master Construction Schedulea) Please confirm and show on Master Schedule the milestone for

    provisional sum and out of scope items if requested by Employer

    b) Tentative commencement of work shall be 1st December, 2012

    7 Commence of Work Please confirm that you will commence work within 7 days upon the

    Employer's official notification to take possesion of the Site

    8 Personnel DataPlease confirm that your personnels are capable of communicate in

    English, both speaking and writing

    VKS Expansion

  • 7/28/2019 B Questionnaire Fujita

    2/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    9 Specificationa) Pls change PHC500 plie to square 400x400. We do not permit

    spun pile.

    b) Made in China steel structures including bolts are not acceptable,

    please confirm

    10 Temporary Plans a) Your temporary plan is insufficient

    b) Please confirm that at least 4 guard posts at Employers designated

    locations together with guardhouse to be included on your temporary

    plans and active throughout duration of the project.

    11 Bills of Quantities General Conditions & Preliminary

    a) Please confirm your design and management fee in general

    conditions and preliminary is adequate to cover all necessary costs,

    please clearly clarify contents of the preliminary such as housing,

    manpower, temporary facilities etc.

    General Questionsa) Please confirm you have excluded the costs of jack roof in Melt

    Shop, refer to addendum #3.

    b) There shall be 2 weighing bridges, their total cost of 70,000,000

    VND shall be tentative only, after confirmation of specification we shall

    finalize this Cost

    c) Please confirm crane girder and crane rails already included in your

    cost.

    d) In ceiling finishes, please include items insulation panel 100mm thk

    and ceiling steel frame support in your BOQ

  • 7/28/2019 B Questionnaire Fujita

    3/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    e) In the Rolling Mills, please include 7m raised floor in your BOQ.

    f) Please confirm there are steel louvers in Rolling Mills.

    g) Please confirm there is no bird net

    h) Please confirm we use 0.48mm thick APT

    i) Except Rolling Mills, Please check your quantities of excavation and

    backfilling based on what method of works

    j) Metal roof sheet shall be using Klip-Lock system

    k) Please confirm that there are two types of steel purlin in Melt Shop

    and Rolling Mills: Z200x60x65x20x2,0mm and

    Z200x60x65x20x1,50mm

    l) In External work, electric room for fes, rolling mill water treatment,

    and melt shop water treatment from BOQ because they are out of

    scopes of works. Please confirm.

    m) Please check your quantities of excavation and backfilling and

    confirm what method of works had been used

    n) Your steel total quantity is too low, Please confirm

    o) Your provisional sum cost is incorrect, please follow cost mentioned

    in addendum #4.

    10a Civil Works Melt Shop

  • 7/28/2019 B Questionnaire Fujita

    4/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    a) Please check your quantities of Structural Steel Works: item Supply

    and Installation Steel purlin Z200x60x65x20x2,0mm

    b) Please check your quantities of Structural Steel Works: item Supply

    and Installation Steel purlin Z250x72x78x20x2.5mm

    Scrap Yard

    a) Please checkMetal roof sheet, (external walls) quantity of

    colorbond steel cladding 0.48 mm thk

    Billet Yard

    a) Please check unit of your structural steel works: bracing cable Phi12

    b) Please check unit of your structural steel works: erection

    c) Please check quantities of s tructure steel works: item Supply and

    Installation Steel purlin Z200x60x65x20x2,0mm

    Rolling Milla) Please check quantities of ground slab: item wiremesh steel D12

    External

    a) Please check quantity unit of Curb & pavement: item concrete curb

    b) Please check quantity of grass

    M&E Works General Questions

  • 7/28/2019 B Questionnaire Fujita

    5/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    a) In general we are using GI conduit in Rolling mill to protect wires

    from high heat, however, it was substituded with PVC conduits

    10b Master Plan 30% higher than our total

    1. For Fire Alarm, the quantity of Cu/PVC/PVC/Sc Cable 12C - 1 .25

    mm2 is high. Plz recheck

    $13,000 in cost of fire alarm, HT to check again on additional

    items proposed by contractor, check why proposed items by New

    CC had not been priced

    2. For Fire Alarm, the quantity of Cu/PVC/PVC/Sc Cable 12C - 1.25

    mm2 is high. Plz recheck

    Contractor doesn't follow breakdow proposed by New CC on theplumbing works, need check carefully what included and not

    3. For Fire Alarm, the quantity of Cu/PVC/PVC/Sc Cable 2C - 1.0

    mm2 is high. Plz recheck[proposed by Contractor]

    Earthing lingting cost is double NewCC price

    4. For Fire Alarm, the quantity of Cu/PVC/PVC/Sc Cable 2C - 1.0

    mm2 is high. Plz recheck [proposed by Contractor]

    5. For FIRE FIGHTING SYSTEM, the rate of Fire Fighting Electric

    Pump 90m3/h x 8kgf/cm2 is high. Plz recheck[proposed by

    Contractor

    6. For FIRE FIGHTING SYSTEM, the rate of Control panel for system

    is high. Plz recheck [proposed by Contractor]

    Melt Shop 3% higher than our total cost

    1. For Fire fighting, the rate of 8kg ABC powder extinguisher botle is

    high. Plz recheck

    2. For Emergency/Exit lighting, the rate of Emergency Light 5W x 2 is

    high. Plz recheck

    Scrap Yard 5% higher than our total cost

    1. For Fire fighting, the rate of 8kg ABC powder extinguisher botle is

    high. Plz recheck

  • 7/28/2019 B Questionnaire Fujita

    6/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    2. For Emergency/Exit lighting, the rate of Emergency Light 5W x 2 is

    high. Plz recheck

    Billet Yard 1% higher than our total cost

    1. For Fire fighting, the rate of 8kg ABC powder extinguisher botle is

    high. Plz recheck

    2. For Emergency/Exit lighting, the rate of Emergency Light 5W x 2 is

    high. Plz recheck

    Rolling Mill 25% higher than our total cost1. For Fire fighting at Fire Alarm the rate of Combination Box

    Bell, Lamp, Push Button (Water proof) is high. Plz recheck[proposed

    by Contractor]

    Lighting and calbe ladder cost is high, recheck additional items

    proposed by contractor

    2. For Fire fighting at Fire Alarm the quantity of Excavation &

    Backfilling Fee is high. Plz recheck[proposed by Contractor]

    Fire Alarm cost is high,

    3. For Fire fighting the rate of 8kg ABC powder extinguisher botle is

    high. Plz recheck

    Emergency/Exhit lighting must be missed calculated some items,

    cost is too low.

    4. For Emergency/Exit lighting the rate of Emergency Light 5W x 2 is

    high. Plz recheck

    Utility 62% higher than our total cost1. For Lighting, Socket at Guard house the rate of Emergency Light 5W

    x 2 is high. Plz recheck

  • 7/28/2019 B Questionnaire Fujita

    7/7

    Project Name

    Closing Date Monday, Nov 5th, 2012 Before 12:00 (Noon)

    Tender Resubmission Date Friday, Nov 16th, 2012 Before 12:00 (Noon)

    Employer Vina Kyoei Steel Co., Ltd.

    Tenderer Fujita

    TENDER QUESTIONNAIRE NO. 1

    ITEM REF. / DWGS NO. Query Answer

    VKS Expansion

    Contractor's Signature & Company Stamp