back energisation of main transformer - a. k. m

Upload: zillur-rahman

Post on 07-Mar-2016

219 views

Category:

Documents


0 download

DESCRIPTION

n mmmmmmm

TRANSCRIPT

  • DearMr.Angel1)Asyourequested,PGCBpeoplecameat9:00amtodaybutthetestsstartedataround11:00am.Aertoday'sworkthefollowingPGCBrequiredtestsaresllpending:

    PowerGridSide:I.Closecircuitcheck(Remoteclosecmd.)II.HarmonicsblockingcouldnotbetestedIII.BreakerFailureRemotetripS/StoP/PIV.BreakerFailureRemoteTripP/PtoS/SV.IBF/CloseblockfromGCP(From50BFrelay,G60A,M3425VI.DCearthfaultofS/SVII.GSUTshortcircuittestPleaseletusknowwhenyouwillcompletethetests.2)Aspercontract,EPCshouldnofy&inviteforwalkdownjointly(EGCB/OE&EPC)aermechanicalcompleonofanysubsystem.However,wedidnotgetanyinvitaonforwitnessingthefollowingtests:

    PowerPlantside:a.Fullfunconaltestsofallrelays(ExceptL90,L30)b.TramsformerselfproteconTest(GSUT,UAT)c.TransformerTest(GSUT,UAT)i)Shortcircuitii)Opencircuitiii)Magnecbalanceiv)Vectorgroupv)Windingresistancevi)Raotestvii)Insulaonresistanceviii)BDVofoilix)Tan&test(fullandbushing)d.TripMatrixTests

    Back Energisation of Main Transformer - A. K. M. Zillur Rahman https://mail.egcb.com.bd/owa/#viewmodel=ReadMessageItem&ItemI...

    1 of 2 2/21/2016 7:48 PM

  • Pleaseletusknowwhenyouwillcompletethetests.3)Thescheduleforbackchargingthetransformeris23rdFebruary2016.Butthetestsmenonedinitem1&2notyetcompleted.Pleasereviewtheschedule&confirmthedateofbackenergizaon.RegardsMd.NazmulAlam

    Back Energisation of Main Transformer - A. K. M. Zillur Rahman https://mail.egcb.com.bd/owa/#viewmodel=ReadMessageItem&ItemI...

    2 of 2 2/21/2016 7:48 PM