bacnet spec - jci sales
TRANSCRIPT
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-1 Project Title Revised January 18, 2016 A-xxxxxx
1. Part 1 – General
Table of Contents
Part 1 – General 1.1 Related Documents 1.2 Definitions 1.3 BACS System Description 1.4 References 1.5 Work By Others 1.6 Submittals 1.7 Record Documentation 1.8 Warranty Part 2 – Products 2.1 System Architecture 2.2 Operator Workstation 2.3 Operator Interface 2.4 Application Nodes 2.5 Application Software 2.6 Field Devices 2.7 Specialty Items Part 3 – Execution 3.1 Installation Practices 3.2 Training 3.3 Commissioning Requirements 3.4 Coordination 3.5 Sequences 3.6 Point Lists
1.1 Related Documents
A. All work of this Division shall be coordinated and provided by a single Building Automation Controls System (BACSBACS) Contractor, approved contractor shall be Johnson Controls, Inc. (JCI Factory Office) or Automated Logic installed by Control Service Company Inc. (CSCI). Pricing shall be based on the current State of Kansas contract. JCI or CSCI will subcontract to the Mechanical Contractor, unless otherwise directed by the DCM Project Manager.
B. The work of this Division shall be scheduled, coordinated, and interfaced with the associated work of other trades.
C. The work of this Division shall be as required by the Specifications, Point Schedules and Drawings.
D. If the BACS Contractor believes there are conflicts or missing information in the project documents, the Contractor shall promptly request clarification and instruction from the design team.
1.2 Definitions
A. Analog: A continuously variable system or value not having discrete levels. Typically exists within a defined range of limiting values.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-2 Project Title Revised January 18, 2016 A-xxxxxx
B. Binary: A two-state system where an “ON” condition is represented by one discrete signal level and an “OFF” condition is represented by a second discrete signal level.
C. Building Automation Controls System (BACS): The total integrated system of fully operational and functional elements, including equipment, software, programming, and associated materials, to be provided by this Division BACS Contractor and to be interfaced to the associated work of other related trades.
D. BACS Contractor: The single Contractor to provide the work of this Division. This Contractor shall be the primary manufacturer, installer, commissioner and ongoing service provider for the BACS work.
E. Control Sequence: An BACS pre-programmed arrangement of software algorithms, logical computation, target values and limits as required to attain the defined operational control objectives.
F. Direct Digital Control: The digital algorithms and pre-defined arrangements included in the BACS software to provide direct closed-loop control for the designated equipment and controlled variables. Inclusive of Proportional, Derivative and Integral control algorithms together with target values, limits, logical functions, arithmetic functions, constant values, timing considerations and the like.
G. BACS Network: The total digital on-line real-time interconnected configuration of BACS digital processing units, workstations, panels, sub-panels, controllers, devices and associated elements individually known as network nodes. May exist as one or more fully interfaced and integrated sub-networks, LAN, WAN or the like.
H. Node: A digitally programmable entity existing on the BACS network. I. BACS Integration: The complete functional and operational interconnection and
interfacing of all BACS work elements and nodes in compliance with all applicable codes, standards and ordinances so as to provide a single coherent BACS as required by this Division.
J. Provide: The term “Provide” and its derivatives when used in this Division shall mean to furnish, install in place, connect, calibrate, test, commission, warrant, document and supply the associated required services ready for operation.
K. PC: IBM-compatible Personal Computer from a recognized major manufacturer L. Furnish: The term “Furnish” and its derivatives when used in this Division shall mean
supply at the BACS Contractor’s cost to the designated third party trade contractor for installation. BACS Contractor shall connect furnished items to the BACS, calibrate, test, commission, warrant and document.
M. Wiring: The term “Wiring” and its derivatives when used in this Division shall mean provide the BACS wiring and terminations.
N. Install: The term “Install” and its derivatives when used in this Division shall mean receive at the jobsite and mount.
O. Protocol: The term “protocol” and its derivatives when used in this Division shall mean a defined set of rules and standards governing the on-line exchange of data between BACS network nodes.
P. Software: The term “software” and its derivatives when used in this Division shall mean all of programmed digital processor software, preprogrammed firmware and project specific digital process programming and database entries and definitions as generally understood in the BACS industry for real-time, on-line, integrated BACS configurations.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-3 Project Title Revised January 18, 2016 A-xxxxxx
Q. The use of words in the singular in these Division documents shall not be considered as limiting when other indications in these documents denote that more than one such item is being referenced.
R. Headings, paragraph numbers, titles, shading, bolding, underscores, clouds and other symbolic interpretation aids included in the Division documents are for general information only and are to assist in the reading and interpretation of these Documents.
S. The following abbreviations and acronyms may be used in describing the work of this Division: ADC - Analog to Digital Converter AI - Analog Input AN - Application Node ANSI - American National Standards Institute AO - Analog Output ASCII - American Standard Code for Information
Interchange ASHRAE American Society of Heating, Refrigeration and Air
Conditioning Engineers AWG - American Wire Gauge CPU - Central Processing Unit CRT - Cathode Ray Tube DAC - Digital to Analog Converter DDC - Direct Digital Control DI - Digital Input DO - Digital Output EEPROM - Electronically Erasable Programmable Read Only Memory EMI - Electromagnetic Interference FAS - Fire Alarm Detection and Annunciation System GUI - Graphical User Interface HOA - Hand-Off-Auto ID - Identification IEEE - Institute of Electrical and Electronics Engineers I/O - Input/Output LAN - Local Area Network LCD - Liquid Crystal Display LED - Light Emitting Diode MCC - Motor Control Center NC - Normally Closed NIC - Not In Contract NO - Normally Open OWS - Operator Workstation OAT - Outdoor Air Temperature PC - Personal Computer RAM - Random Access Memory RF - Radio Frequency RFI - Radio Frequency Interference RH - Relative Humidity ROM - Read Only Memory RTD - Resistance Temperature Device SPDT - Single Pole Double Throw
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-4 Project Title Revised January 18, 2016 A-xxxxxx
SPST - Single Pole Single Throw XVGA - Extended Video Graphics Adapter TBA - To Be Advised TCP/IP - Transmission Control Protocol/Internet Protocol TTD - Thermistor Temperature Device UPS - Uninterruptible Power Supply VAC - Volts, Alternating Current VAV - Variable Air Volume VDC - Volts, Direct Current WAN - Wide Area Network
1.3 BACS Description
A. The Building Automation Controls System (BACS) shall be a complete system designed for use with the enterprise IT systems. This functionality shall extend into the equipment rooms. Devices residing on the automation network located in equipment rooms and similar shall be fully IT compatible devices that mount and communicate directly on the IT infrastructure in the facility. Contractor shall be responsible for coordination with the owner’s IT staff to ensure that the BACS will perform in the owner’s environment without disruption to any of the other activities taking place on that LAN.
B. All points of user interface shall be on standard PCs that do not require the purchase of any special software from the BACS manufacturer for use as a building operations terminal. The primary point of interface on these PCs will be a standard Web Browser.
C. All work on this project shall be loaded onto either the existing Johnson Controls or Automated Logic server located in the Computer Services Facility. Database will be updated to reflect all new systems resulting from the execution of this project for consistent user interface and data archiving across the JCI BACS or ALC network.
D. The work of the single BACS Contractor shall be as defined individually and collectively in all Sections of this Division specifications together with the associated Point Sheets and Drawings and the associated interfacing work as referenced in the related documents.
E. The BACS work shall consist of the provision of all labor, materials, tools, equipment, software, software licenses, software configurations and database entries, interfaces, wiring, tubing, installation, labeling, engineering, calibration, documentation, samples, submittals, testing, commissioning, training services, permits and licenses, transportation, shipping, handling, administration, supervision, management, insurance, temporary protection, cleaning, cutting and patching, warranties, services, and items, even though these may not be specifically mentioned in these Division documents which are required for the complete, fully functional and commissioned BACS.
F. Provide a complete, neat and workmanlike installation. Use only manufacturer employees who are skilled, experienced, trained, and familiar with the specific equipment, software, standards and configurations to be provided for this Project.
G. Manage and coordinate the BACS work in a timely manner in consideration of the Project schedules. Coordinate with the associated work of other trades so as to not impede or delay the work of associated trades.
H. The BACS as provided shall incorporate, at minimum, the following integrated features, functions and services: 1. Operator information, alarm management and control functions. 2. Enterprise-level information and control access.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-5 Project Title Revised January 18, 2016 A-xxxxxx
3. Information management including monitoring, transmission, archiving, retrieval, and reporting functions.
4. Diagnostic monitoring and reporting of BACS functions. 5. Offsite monitoring and management access.
6. Energy management. 7. Standard applications for terminal HVAC systems. 8. Environmental Index Monitoring (optional) 9. Energy Reporting of Utility Data
1.4 Work By Others
A) The demarcation of work and responsibilities between the BACS Contractor and other related trades shall be as outlined in the BACS RESPONSIBILITY MATRIX
BACS RESPONSIBILITY MATRIX WORK
FURNISH INSTALL Low Volt.
WIRING/TUBE LINE
POWER BACS low voltage and communication wiring
BACS BACS BACS N/A
VAV box nodes BACS 23 BACS 26 BACS conduits and raceway BACS BACS BACS BACS Automatic dampers BACS 23 N/A N/A Manual valves 23 23 N/A N/A Automatic valves BACS 23 BACS N/A VAV boxes 23 23 N/A N/A Pipe insertion devices and taps including thermowells, flow and pressure stations.
BACS 23 BACS BACS
BACS Current Switches. BACS BACS BACS N/A BACS Control Relays BACS BACS BACS N/A Power distribution system monitoring interfaces
26 26 BACS 26
BACS interface with Chiller controls BACS BACS BACS BACS Chiller controls interface with BACS 23 23 BACS 26 BACS interface with Classroom unit controls
BACS BACS BACS 26
Classroom unit controls interface with BACS
23 23 BACS 26
ADD OTHER THIRD PARTY EQUIPMENT HERE
N/A N/A N/A N/A
All BACS Nodes, equipment, housings, enclosures and panels.
BACS BACS BACS BACS
Smoke Detectors 26 26 26 26 Fire/Smoke Dampers 23 23 BACS 26 Fire Dampers 23 23 N/A N/A Chiller Flow Switches 23 23 BACS N/A Boiler wiring 23 23 23 23 Water treatment system 23 23 23 26 VFDs 23 26 BACS 26 Refrigerant monitors 23 BACS BACS 26
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-6 Project Title Revised January 18, 2016 A-xxxxxx
Computer Room A/C Unit field-mounted controls
23* 23 BACS 26
Fire Alarm shutdown relay interlock wiring
26 26 26 26
Fire Alarm smoke control relay interlock wiring
26 26 BACS 26
Fireman’s Smoke Control Override Panel 26 26 26 26 Fan Coil Unit controls BACS BACS BACS 26 Unit Heater controls BACS BACS BACS 26 Packaged RTU space mounted controls 23* BACS BACS 26 Packaged RTU factory-mounted controls 23* 23 BACS 26 Packaged RTU field-mounted controls BACS BACS BACS 26 Cooling Tower Vibration Switches 23 23 26 26 Cooling Tower Level Control Devices 23 23 26 26 Cooling Tower makeup water control devices
23 23 26 26
Pool Dehumidification Unit Controls 23* 23 BACS 26 Starters, HOA switches 26 26 N/A 26 Control damper actuators BACS BACS BACS 26
1.5 Submittals
A. Shop Drawings, Product Data, and Samples 1. The BACS contractor shall submit a list of all shop drawings with submittals dates
within 30 days of contract award. 2. Submittals shall be in defined packages. Each package shall be complete and shall
only reference itself and previously submitted packages. The packages shall be as approved by the Architect and Engineer for Contract compliance.
3. Allow 23 working days for the review of each package by the Architect and Engineer in the scheduling of the total BACS work.
4. Equipment and systems requiring approval of local authorities must comply with such regulations and be approved. Filing shall be at the expense of the BACS Contractor where filing is necessary. Provide a copy of all related correspondence and permits to the Owner.
5. Prepare an index of all submittals and shop drawings for the installation. Index shall include a shop drawing identification number, Contract Documents reference and item description.
6. The BACS Contractor shall correct any errors or omissions noted in the first review.
7. At a minimum, submit the following: a. BACS network architecture diagrams including all nodes and
interconnections. b. Systems schematics, sequences and flow diagrams. c. Points schedule for each point in the BACS, including: Point Type, Object
Name, Expanded ID, Display Units, Controller type, and Address.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-7 Project Title Revised January 18, 2016 A-xxxxxx
d. Samples of Graphic Display screen types and associated menus. e. Detailed Bill of Material list for each system or application, identifying
quantities, part numbers, descriptions, and optional features. f. Control Damper Schedule including a separate line for each damper
provided under this section and a column for each of the damper attributes, including: Code Number, Fail Position, Damper Type, Damper Operator, Duct Size, Damper Size, Mounting, and Actuator Type.
g. Control Valve Schedules including a separate line for each valve provided under this section and a column for each of the valve attributes: Code Number, Configuration, Fail Position, Pipe Size, Valve Size, Body Configuration, Close off Pressure, Capacity, Valve CV, Design Pressure, and Actuator Type.
h. Room Schedule including a separate line for each VAV box and/or terminal unit indicating location and address
i. Details of all BACS interfaces and connections to the work of other trades. j. Product data sheets or marked catalog pages including part number, photo
and description for all products including software.
1.7 Record Documentation
A. Operation and Maintenance Manuals 1. Three (3) copies of the Operation and Maintenance Manuals shall be provided to
the Owner's Representative upon completion of the project. The entire Operation and Maintenance Manual shall be furnished on Compact Disc media, and include the following for the BACS provided: a. Table of contents. b. As-built system record drawings. Computer Aided Drawings (CAD) record
drawings shall represent the as-built condition of the system and incorporate all information supplied with the approved submittal.
Provide “first draft” of as-built system record drawings to project commissioning agent no later than project completion date.
c. Manufacturers product data sheets or catalog pages for all products including software.
d. System Operator’s manuals. e. Archive copy of all site-specific databases and sequences. f. BACS network diagrams. g. Interfaces to all third-party products and work by other trades.
2. The Operation and Maintenance Manual CD shall be self-contained, and include all necessary software required to access the product data sheets. A logically organized table of contents shall provide dynamic links to view and print all product data sheets. Viewer software shall provide the ability to display, zoom, and search all documents.
1.8 Warranty
A. Standard Material and Labor Warranty: 1. Provide a one-year labor and material warranty on the BACS.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-8 Project Title Revised January 18, 2016 A-xxxxxx
2. If within twelve (12) months from the date of acceptance of product, upon written notice from the owner, it is found to be defective in operation, workmanship or materials, it shall be replaced, repaired or adjusted at the option of the BACS Contractor at the cost of the BACS Contractor.
3. Warranty work shall be done during BACS Contractor’s normal business hours.
2. Part 2 – Products
2.1 General Description
A. The Building Automation Controls System (BACS) shall use an open architecture and fully support a multi-vendor environment. To accomplish this effectively, the BACS shall support open communication protocol standards and integrate a wide variety of third-party devices and applications. The system shall be designed for use on the Internet, or intranets using off the shelf, industry standard technology compatible with other owner provided networks.
B. The Building Automation Controls System shall consist of the following: 1. Standalone Network Automation Engine(s) 2. Field Equipment Controller(s) 3. Input/Output Module(s) 4. Local Display Device(s) 5. Portable Operator's Terminal(s) 6. Distributed User Interface(s) 7. Network processing, data storage and communications equipment 7. Other components required for a complete and working BACS
C. The system shall be modular in nature, and shall permit expansion of both capacity and functionality through the addition of sensors, actuators, controllers and operator devices, while re-using existing controls equipment.
D. System architectural design shall eliminate dependence upon any single device for alarm reporting and control execution. 1. The failure of any single component or network connection shall not interrupt the
execution of control strategies at other operational devices. 2. The System shall maintain all settings and overrides through a system reboot.
E. The System shall comply with (UL) 864 (UUKL) Ninth Edition Smoke Control Listing including the UL 864 Ninth Edition Standard for Control Units and Accessories for Fire Alarm Systems. 1. The System shall comply with the following NFPA Codes and Standards as
applicable: a. NFPA 70 National Electrical Code b. NFPA 72 National Fire Alarm Code c. NFPA 101 Life Safety Code d. NFPA 90A Standard for the Installation of Air-Conditioning and
Ventilation Systems e. NFPA 92B Guide for Smoke Management Systems in Malls, Atria, and
Large Areas 2. The System shall comply with the following International Code Council (ICC)
Codes:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-9 Project Title Revised January 18, 2016 A-xxxxxx
a. Building Officials and code Administrators International (BOMA) model code
b. International Conference of Building Officials (ICBO) model code c. Southern Building Code Congress International (SBCCI) regulations
F. Acceptable Manufacturers 1) Johnson Controls Metasys or Automated Logic WebCTRL
2.2 BACS Architecture
A. Automation Network 1. The automation network shall be based on a PC industry standard of Ethernet
TCP/IP. Where used, LAN controller cards shall be standard “off the shelf” products available through normal PC vendor channels.
2. The BACS shall network multiple user interface clients, automation engines, system controllers and application-specific controllers. Provide application and data server(s) as required for systems operation.
3. The automation network shall be capable of operating at a communication speed of 100 Mbps, with full peer-to-peer network communication.
4. Network Automation Engines (NAE) or LAN Gate Routers (LGR) shall reside on the automation network.
5. The automation network will be compatible with other enterprise-wide networks. Where indicated, the automation network shall be connected to the enterprise network and share resources with it by way of standard networking devices and practices.
B. Control Network 1. Network Automation Engines (NAE) or LAN Gate Routers (LGR) shall provide
supervisory control over the control network and shall support all three (3) of the following communication protocols, as necessary for the specific project: a. BACnet Standard MS/TP or BACnet ARCnet Bus Protocol ASHRAE
SSPC-135, Clause 9 ◊ The NAE or LGR shall be BACnet Testing Labs (BTL) certified and
carry the BTL Label. ◊ The NAE or LGR shall be tested and certified as a BACnet Building
Controller (B-BC). b. LonWorks enabled devices using the Free Topology Transceiver (FTT-
10a). c. The Johnson Controls N2 Field Bus.
d. The Automated Logic ARCnet Communication Network 2. Control networks shall provide either “Peer-to-Peer,” Master-Slave, or Supervised
Token Passing communications, and shall operate at a minimum communication speed of 9600 baud (JCI) or 156k baud (ALC)
3. DDC Controllers shall reside on the control network. 4. Control network communication protocol shall be BACnet Standard MS/TP or
BACnet over ARCnet Bus Protocol ASHRAE SSPC-135. C. Integration
1. Hardwired
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-10 Project Title Revised January 18, 2016 A-xxxxxx
a. Analog and digital signal values shall be passed from one system to another via hardwired connections.
b. There will be one separate physical point on each system for each point to be integrated between the systems.
2. Direct Protocol (Integrator Panel) a. The BACS system shall include appropriate hardware equipment and
software to allow bi-directional data communications between the BACS system and 3rd party manufacturers’ control panels. The BACS shall receive, react to, and return information from multiple building systems, including but not limited to the chillers, boilers, variable frequency drives, power monitoring system, and medical gas.
b. All data required by the application shall be mapped into the Automation Engine’s database, and shall be transparent to the operator.
c. Point inputs and outputs from the third-party controllers shall have real-time interoperability with BACS software features such as: Control Software, Energy Management, Custom Process Programming, Alarm Management, Historical Data and Trend Analysis, Totalization, and Local Area Network Communications.
3. BACnet Protocol Integration - BACnet a. The neutral protocol used between systems will be BACnet over Ethernet
and comply with the ASHRAE BACnet standard 135-2003. b. A complete Protocol Implementation Conformance Statement (PICS) shall
be provided for all BACnet system devices. c. The ability to command, share point object data, change of state (COS) data
and schedules between the host and BACnet systems shall be provided.
2.3 User Interface
a. Existing.
2.4 Network Automation Engines (NAE)
A. Network Automation Engine (NAE 55XX)
1. The standard NAE provided at the University of Kansas shall be an NAE 55XX unless the application requires that a different model be utilized. Confirm with KU DCM and FO representatives on each specific project. The Network Automation Engine (NAE) shall be a fully user-programmable, supervisory controller. The NAE shall monitor the network of distributed application-specific controllers, provide global strategy and direction, and communicate on a peer-to-peer basis with other Network Automation Engines.
2. Automation network – The NAE shall reside on the automation network and shall support a subnet of system controllers.
3. User Interface – Each NAE shall have the ability to deliver a web based User Interface (UI) as previously described. All computers connected physically or virtually to the automation network shall have access to the web based UI. a. The web based UI software shall be imbedded in the NAE. Systems that
require a local copy of the system database on the user’s personal computer are not acceptable.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-11 Project Title Revised January 18, 2016 A-xxxxxx
b. The NAE shall support up a minimum of four (4) concurrent users. c. The web based user shall have the capability to access all system data
through one NAE. d. Remote users connected to the network through an Internet Service
Provider (ISP) or telephone dial up shall also have total system access through one NAE.
e. Systems that require the user to address more than one NAE to access all system information are not acceptable.
f. The NAE shall have the capability of generating web based UI graphics. The graphics capability shall be imbedded in the NAE.
g. Systems that support UI Graphics from a central database or require the graphics to reside on the user’s personal computer are not acceptable.
h. The web based UI shall support the following functions using a standard version of Microsoft Internet Explorer: ◊ Configuration ◊ Commissioning ◊ Data Archiving ◊ Monitoring ◊ Commanding ◊ System Diagnostics
i. Systems that require workstation software or modified web browsers are not acceptable.
j. The NAE shall allow temporary use of portable devices without interrupting the normal operation of permanently connected modems.
4. Processor – The NAE shall be microprocessor-based with a minimum word size of 32 bits. The NAE shall be a multi-tasking, multi-user, and real-time digital control processor. Standard operating systems shall be employed. NAE size and capability shall be sufficient to fully meet the requirements of this Specification.
5. Memory – Each NAE shall have sufficient memory to support its own operating system, databases, and control programs, and to provide supervisory control for all control level devices.
6. Hardware Real Time Clock – The NAE shall include an integrated, hardware-based, real-time clock.
7. The NAE shall include troubleshooting LED indicators to identify the following conditions: a. Power - On/Off b. Ethernet Traffic – Ethernet Traffic/No Ethernet Traffic c. Ethernet Connection Speed – 10 Mbps/100 Mbps d. FC Bus A – Normal Communications/No Field Communications e. FC Bus B – Normal Communications/No Field Communications f. Peer Communication – Data Traffic between NAE Devices g. Run – NAE Running/NAE in Startup/NAE Shutting Down/Software Not
Running h. Bat Fault – Battery Defective, Data Protection Battery Not Installed i. 24 VAC – 24 VAC Present/Loss Of 24VAC j. Fault – General Fault k. Modem RX – NAE Modem Receiving Data l. Modem TX – NAE Modem Transmitting Data
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-12 Project Title Revised January 18, 2016 A-xxxxxx
8. Communications Ports – The NAE shall provide the following ports for operation of operator Input/Output (I/O) devices, such as industry-standard computers, modems, and portable operator’s terminals. a. Two (2) USB port b. Two (2) URS-232 serial data communication port c. Two (2) RS-485 port d. One (1) Ethernet port
9. Diagnostics – The NAE shall continuously perform self-diagnostics, communication diagnosis, and diagnosis of all panel components. The Network Automation Engine shall provide both local and remote annunciation of any detected component failures, low battery conditions, or repeated failures to establish communication.
10. Power Failure – In the event of the loss of normal power, The NAE shall continue to operate for a user adjustable period of up to 10 minutes after which there shall be an orderly shutdown of all programs to prevent the loss of database or operating system software. a. During a loss of normal power, the control sequences shall go to the normal
system shutdown conditions. All critical configuration data shall be saved into Flash memory.
b. Upon restoration of normal power and after a minimum off-time delay, the controller shall automatically resume full operation without manual intervention through a normal soft-start sequence.
11. Certification – The NAE shall be listed by Underwriters Laboratories (UL). 12. Controller network – The NAE shall support the following communication
protocols on the controller network: a. The NAE shall support BACnet Standard MS/TP Bus Protocol ASHRAE
SSPC-135, Clause 9 on the controller network. ◊ The NAE shall be BACnet Testing Labs (BTL) certified and carry the
BTL Label. ◊ The NAE shall be tested and certified as a BACnet Building
Controller (B-BC). ◊ A BACnet Protocol Implementation Conformance Statement shall be
provided for the NAE. ◊ The Conformance Statements shall be submitted 10 days prior to
bidding. ◊ The NAE shall support a minimum of 100 control devices.
b. The NAE shall support LonWorks enabled devices using the Free Topology Transceiver FTT10. ◊ All LonWorks controls devices shall be LonMark certified. ◊ The NAE shall support a minimum of 255 LonWorks enabled control
devices. c. The NAE shall support the Johnson Controls N2 Field Bus.
◊ The NAE shall support a minimum of 100 N2 control devices. ◊ The Bus shall conform to Electronic Industry Alliance (EIA) Standard
RS-485. ◊ The Bus shall employ a master/slave protocol where the NAE is the
master.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-13 Project Title Revised January 18, 2016 A-xxxxxx
◊ The Bus shall employ a four (4) level priority system for polling frequency.
◊ The Bus shall be optically isolated from the NAE. ◊ The Bus shall support the Metasys Integrator System.
B. LAN Gate Router (LGR XX) 1. The standard LGR provided at the University of Kansas shall be an LGR 25 unless
the application requires that a different model be utilized. Confirm with KU DCM and FO representatives on each specific project. The Lan Gate Router (LGR) shall be a fully user-programmable, supervisory controller. The LGR shall monitor the network of distributed application-specific controllers, provide global strategy and direction, and communicate on a peer-to-peer basis with other Lan Gate Routers.
2. Automation network – The LGR shall reside on the automation network and shall support a subnet of system controllers.
3. Processor – The LGR shall be microprocessor-based with a minimum word size of 32 bits Motorola Power PC microprocessor with cache memory Fast Ethernet controller, high performance 32-bit communication co-processor, ARCNET communication co-processor and I/O expansion CAN co-processor.
4. Memory – 16MByte non-volatile battery-backed SDRAM (with 12 Mbytes available for use), 8MByte Flash memory, 32-bit memory bus. (Shelf life of the battery is 10 years with 720 hours of continuous operation.)
5. Hardware Real Time Clock – The LGR shall include an integrated, hardware-based, real-time clock with Battery Back Up.
6. The LGR shall include troubleshooting LED indicators to identify the following conditions: a. Power - On/Off b. Ethernet Traffic – Ethernet Traffic/No Ethernet Traffic c. Ethernet Connection Speed – 10 Mbps/100 Mbps d. EIA-232/485 communications Bus e. ARCNET Communication – Data Traffic between LGR Devices f. Run – LGR Running/LGR in Startup/LGR Shutting Down/Software Not
Running g. Bat Fault – Battery Defective, Data Protection Battery Not Installed h. 24 VAC – 24 VAC Present/Loss Of 24VAC i. Fault – General Fault
7. Communications Ports – The LGR shall provide the following ports for operation of operator Input/Output (I/O) devices, such as industry-standard portable operator’s terminals. a. Ethernet port (10/100Mbps) for BACnet over Ethernet communications b. EIA-485 port for ARCNET 156 Kbps or BACnet MS/TP c. EIA-485 MS/TP (9600 baud or 76.8 Kbps) d. EIA-232/485 configurable port for BACnet PTP e. Rnet port for RS room sensors and local BACview display f. Xnet (500Kbps) port of MEX I/O expansion modules g. Local access port.
8. Diagnostics – The LGR shall continuously perform self-diagnostics, communication diagnosis, and diagnosis of all panel components. The LAN Gate Router shall provide both local and remote annunciation of any detected
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-14 Project Title Revised January 18, 2016 A-xxxxxx
component failures, low battery conditions, or repeated failures to establish communication.
9. Power Failure – In the event of the loss of normal power, The LGR shall continue to operate for a user adjustable period of up to 720 hours after which there shall be an orderly shutdown of all programs to prevent the loss of database or operating system software. a. During a loss of normal power, the control sequences shall go to the normal
system shutdown conditions. All critical configuration data shall be saved into Flash memory.
b. Upon restoration of normal power and after a minimum off-time delay, the controller shall automatically resume full operation without manual intervention through a normal soft-start sequence.
10. Certification – The LGR shall be listed by Underwriters Laboratories (UL). 11. Controller network – The LGR shall support the following communication
protocols on the controller network: a. The LGR shall support BACnet Standard ARCNET Protocol ASHRAE
SSPC-135. ◊ The LGR shall be BACnet Testing Labs (BTL) certified and carry the
BTL Label. ◊ The LGR shall be tested and certified as a BACnet Building
Controller (B-BC). ◊ A BACnet Protocol Implementation Conformance Statement shall be
provided for the NAE. ◊ The Conformance Statements shall be submitted 10 days prior to
bidding. ◊ The LGR shall support a minimum of 99 control devices.
b. The LGR shall support the Automated Logic ARCNET Network. ◊ The LGR shall support a minimum of 99 Nodes ◊ The Network shall conform to Electronic Industry Alliance (EIA)
Standard RS-485. ◊ Fully programmable for the execution of complex control strategies
for high-level system integration. ◊ The LGR shall supports a wide range of open and proprietary
protocol translator drivers allowing to serve as a gateway to other manufactures equipment.
2.5 DDC System Controllers
A. Field Equipment Controller (FEC X610) 1. The Field Equipment Controller (FEC) shall be a fully user-programmable, digital
controller that communicates via BACnet MS/TP protocol. a. The FEC shall support BACnet Standard MS/TP Bus Protocol ASHRAE
SSPC-135, Clause 9 on the controller network. ◊ The FEC shall be BACnet Testing Labs (BTL) certified and carry the
BTL Label. ◊ The FEC shall be tested and certified as a BACnet Application
Specific Controller (B-ASC).
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-15 Project Title Revised January 18, 2016 A-xxxxxx
◊ A BACnet Protocol Implementation Conformance Statement shall be provided for the FEC.
◊ The Conformance Statement shall be submitted 10 days prior to bidding.
2. The FEC shall employ a finite state control engine to eliminate unnecessary conflicts between control functions at crossover points in their operational sequences. Suppliers using non-state based DDC shall provide separate control strategy diagrams for all controlled functions in their submittals.
3. Controllers shall be factory programmed with a continuous adaptive tuning algorithm that senses changes in the physical environment and continually adjusts loop tuning parameters appropriately. Controllers that require manual tuning of loops or perform automatic tuning on command only shall not be acceptable.
4. The FEC shall be assembled in a plenum-rated plastic housing with flammability rated to UL94-5VB.
5. The FEC shall include a removable base to allow pre-wiring without the controller.
6. The FEC shall include troubleshooting LED indicators to identify the following conditions: a. Power On b. Power Off c. Download or Startup in progress, not ready for normal operation d. No Faults e. Device Fault f. Field Controller Bus - Normal Data Transmission g. Field Controller Bus - No Data Transmission h. Field Controller Bus - No Communication i. Sensor-Actuator Bus - Normal Data Transmission j. Sensor-Actuator Bus - No Data Transmission k. Sensor-Actuator Bus - No Communication
7. The FEC shall accommodate the direct wiring of analog and binary I/O field points.
8. The FEC shall support the following types of inputs and outputs: a. Universal Inputs - shall be configured to monitor any of the following:
◊ Analog Input, Voltage Mode ◊ Analog Input, Current Mode ◊ Analog Input, Resistive Mode ◊ Binary Input, Dry Contact Maintained Mode ◊ Binary Input, Pulse Counter Mode
b. Binary Inputs - shall be configured to monitor either of the following: ◊ Dry Contact Maintained Mode ◊ Pulse Counter Mode
c. Analog Outputs - shall be configured to output either of the following ◊ Analog Output, Voltage Mode ◊ Analog Output, current Mode
d. Binary Outputs - shall output the following: ◊ 24 VAC Triac
e. Configurable Outputs - shall be capable of the following:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-16 Project Title Revised January 18, 2016 A-xxxxxx
◊ Analog Output, Voltage Mode ◊ Binary Output Mode
9. The FEC shall have the ability to reside on a Field Controller Bus (FC Bus). a. The FC Bus shall be a Master-Slave/Token-Passing (MS/TP) Bus
supporting BACnet Standard protocol SSPC-135, Clause 9. b. The FC Bus shall support communications between the FECs and the NAE. c. The FC Bus shall also support Input/Output Module (IOM)
communications with the FEC and with the NAE. d. The FC Bus shall support a minimum of 100 IOMs and FECs in any
combination. e. The FC Bus shall operate at a maximum distance of 23,000 Ft. between the
FEC and the furthest connected device. 10. The FEC shall have the ability to monitor and control a network of sensors and
actuators over a Sensor-Actuator Bus (SA Bus). a. The SA Bus shall be a Master-Slave/Token-Passing (MS/TP) Bus
supporting BACnet Standard Protocol SSPC-135, Clause 9. b. The SA Bus shall support a minimum of 10 devices per trunk. c. The SA Bus shall operate at a maximum distance of 1,200 Ft. between the
FEC and the furthest connected device. 11. The FEC shall have the capability to execute complex control sequences involving
direct wired I/O points as well as input and output devices communicating over the FC Bus or the SA Bus.
12. The FEC shall support, but not be limited to, the following: a. Hot water, chilled water/central plant applications b. Built-up air handling units for special applications C. Terminal units c. Special programs as required for systems control
B. Field Equipment Controller (ME 812U) 1. The Field Equipment Controller (FEC) shall be a fully user-programmable, digital
controller that communicates via BACnet ARCNET protocol. a. The FEC shall support BACnet Standard ARCNET Bus Protocol ASHRAE
◊ The FEC shall be BACnet Testing Labs (BTL) certified and carry the BTL Label.
◊ The FEC shall be tested and certified as a BACnet Advanced Application Controller (B-AAC).
◊ A BACnet Protocol Implementation Conformance Statement shall be provided for the FEC.
◊ The Conformance Statement shall be submitted 10 days prior to bidding.
2. The FEC shall employ a finite state control engine to eliminate unnecessary conflicts between control functions at crossover points in their operational sequences. Suppliers using non-state based DDC shall provide separate control strategy diagrams for all controlled functions in their submittals.
3. The FEC shall be assembled in a rugged aluminum housing rated to UL916. 4. The FEC shall include a removable screw terminal blocks. 5. The FEC shall include troubleshooting LED indicators to identify the following
conditions:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-17 Project Title Revised January 18, 2016 A-xxxxxx
a. Power On b. Power Off c. EIA-232/485 communication d. Low Battery Status e. Seven segment status display for running, error, and power status
6. The FEC shall accommodate the direct wiring of analog and binary I/O field points.
7. The FEC shall support the following types of inputs and outputs: a. Universal Inputs - shall be configured to monitor any of the following:
◊ Analog Input, Voltage Mode ◊ Analog Input, Current Mode ◊ Analog Input, Resistive Mode ◊ Binary Input, Dry Contact Maintained Mode ◊ Binary Input, Pulse Counter Mode
b. Binary Inputs - shall be configured to monitor either of the following: ◊ Dry Contact Maintained Mode ◊ Pulse Counter Mode
c. Analog Outputs - shall be configured to output either of the following ◊ Analog Output, Voltage Mode ◊ Analog Output, current Mode
d. Binary Outputs - shall output the following: ◊ 24 V-dc @ 50mA relay drive. With HOA switches & potentiometer
e. Configurable Outputs - shall be capable of the following: ◊ Analog Output, Voltage Mode ◊ Binary Output Mode
8. The FEC shall have the ability to reside on a Field Controller Bus (FC Bus). a. The FC Bus shall be a Master-Slave/Token-Passing ARCNET Bus
supporting BACnet Standard protocol SSPC-135 b. The ARCNET Bus shall support communications between the FECs and
the LGR. c. The ARCNET Bus shall also support Input/Output Module (IOM)
communications with the FEC and with the LGR. d. The ARCNET Bus shall support a minimum of 99 ZNs and FECs in any
combination. 9. The FEC shall have the capability to execute complex control sequences involving
direct wired I/O points as well as input and output devices communicating over the ARCNET Bus.
10. The FEC shall support, but not be limited to, the following: a. Hot water, chilled water/central plant applications b. Built-up air handling units for special applications C. Terminal units c. Special programs as required for systems control
2.6 Field Devices/Controllers
A. Input/Output Module (IOM X710)
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-18 Project Title Revised January 18, 2016 A-xxxxxx
1. The Input/Output Module (IOM) provides additional inputs and outputs for use in the FEC.
2. The IOM shall communicate with the FEC over the FC Bus or the SA Bus. 3. The IOM shall support BACnet Standard MS/TP Bus Protocol ASHRAE SSPC-
135, Clause 9 on the controller network. a. The IOM shall be BACnet Testing Labs (BTL) certified and carry the BTL
Label. b. The IOM shall be tested and certified as a BACnet Application Specific
Controller (B-ASC). c. A BACnet Protocol Implementation Conformance Statement shall be
provided for the FEC. d. The Conformance Statement shall be submitted 10 days prior to bidding.
4. The IOM shall be assembled in a plenum-rated plastic housing with flammability rated to UL94-5VB.
5. The IOM shall have a minimum of 4 points to a maximum of 17 points. 6. The IOM shall support the following types of inputs and outputs:
a. Universal Inputs - shall be configured to monitor any of the following: ◊ Analog Input, Voltage Mode ◊ Analog Input, Current Mode ◊ Analog Input, Resistive Mode ◊ Binary Input, Dry Contact Maintained Mode ◊ Binary Input, Pulse Counter Mode
b. Binary Inputs - shall be configured to monitor either of the following: ◊ Dry Contact Maintained Mode ◊ Pulse Counter Mode
c. Analog Outputs - shall be configured to output either of the following ◊ Analog Output, Voltage Mode ◊ Analog Output, current Mode
d. Binary Outputs - shall output the following: ◊ 24 VAC Triac
e. Configurable Outputs - shall be capable of the following: ◊ Analog Output, Voltage Mode ◊ Binary Output Mode
7. The IOM shall include troubleshooting LED indicators to identify the following conditions: a. Power On b. Power Off c. Download or Startup in progress, not ready for normal operation d. No Faults e. Device Fault f. Normal Data Transmission g. No Data Transmission h. No Communication
B. Input/Output Module (MEX--xxxU)
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-19 Project Title Revised January 18, 2016 A-xxxxxx
1. The Input/Output Module (IOM) provides additional inputs and outputs for use in the FEC.
2. The IOM shall communicate with the FEC over the Xnet. 3. The IOM shall support BACnet Standard ARCNET Protocol ASHRAE SSPC-135,
a. The IOM shall be BACnet Testing Labs (BTL) certified and carry the BTL Label.
b. The IOM shall be tested and certified as a BACnet Advanced Application Controller (B-AAC)
c. A BACnet Protocol Implementation Conformance Statement shall be provided for the FEC.
d. The Conformance Statement shall be submitted 10 days prior to bidding. 4. The IOM shall be assembled in a rugged aluminum housing listed by UL916 5. The IOM shall have a minimum of 8 points to a maximum of 24 points. 6. The IOM shall support the following types of inputs and outputs:
a. Universal Inputs - shall be configured to monitor any of the following: ◊ Analog Input, Voltage Mode ◊ Analog Input, Current Mode ◊ Analog Input, Resistive Mode ◊ Binary Input, Dry Contact Maintained Mode ◊ Binary Input, Pulse Counter Mode
b. Binary Inputs - shall be configured to monitor either of the following: ◊ Dry Contact Maintained Mode ◊ Pulse Counter Mode
c. Analog Outputs - shall be configured to output either of the following ◊ Analog Output, Voltage Mode ◊ Analog Output, current Mode
d. Binary Outputs - shall output the following: ◊ 24 V-dc @ 50mA relay drive with HOA switches and potentiometer.
e. Configurable Outputs - shall be capable of the following: ◊ Analog Output, Voltage Mode ◊ Binary Output Mode
7. The MEX shall include troubleshooting LED indicators to identify the following conditions: a. Power On b. Power Off c. EIA-232/485 communication d. Low Battery Status e. Seven segment status display for running, error, and power status
C. Networked Thermostat (TEC 26X6)
1. Networked thermostat shall be capable of controlling a variety of terminal HVAC systems or similar equipment. Exact model of TEC shall be determined by project.
2. The TEC shall communicate over the Field Controller Bus using BACnet Standard MS/TP Bus Protocol ASHRAE SSPC-135, Clause 9.
3. The TEC shall be BACnet Testing Labs (BTL) certified and carry the BTL Label.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-20 Project Title Revised January 18, 2016 A-xxxxxx
a. The TEC shall be tested and certified as a BACnet Application Specific Controller (B-ASC).
b. A BACnet Protocol Implementation Conformance Statement shall be provided for the TEC.
c. The Conformance Statement shall be submitted 10 days prior to bidding. 4. The Networked Thermostat shall support remote read/write and parameter
adjustment from the web based User Interfaceable through a Network Automation Engine.
5. The Networked Thermostat shall include an intuitive User Interface providing plain text messages. a. Two line, 8 character backlit display b. LED indicators for Fan, Heat, and Cool status c. Five (5) User Interface Keys
◊ Mode ◊ Fan ◊ Override ◊ Degrees C/F ◊ Up/Down
d. The display shall continuously scroll through the following parameters: ◊ Room Temperature ◊ System Mode ◊ Schedule Status – Occupied/Unoccupied/Override ◊ Applicable Alarms
6. The Networked Thermostat shall provide the flexibility to support any one of the following inputs: a. Integral Indoor Air Temperature Sensor b. Duct Mount Air Temperature Sensor c. Remote Indoor Air Temperature Sensor with Occupancy Override and LED
Indicator d. Two configurable binary inputs
7. The Networked Thermostat shall provide the flexibility to support any one of the following outputs: a. Three Speed Fan Control b. Two On/Off c. Two Floating d. Two Proportional (0 to 10V)
8. The Networked Thermostat shall provide a minimum of six (6) levels of keypad lockout.
9. The Networked Thermostat shall provide the flexibility to adjust the following parameters: a. Adjustable Temporary Occupancy from 0 to 24 hours b. Adjustable heating/cooling deadband from 2º F to 5º F c. Adjustable heating/cooling cycles per hour from 4 to 8
10. The Networked Thermostat shall employ nonvolatile electrically erasable programmable read-only memory (EEPROM) for all adjustable parameters.
D. Networked Thermostat (RC642)
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-21 Project Title Revised January 18, 2016 A-xxxxxx
1. Networked thermostat shall be capable of controlling a variety of terminal HVAC systems or similar equipment.
2. The RC642 shall communicate over the Field Controller Bus using BACnet Standard ARCNET Protocol ASHRAE SSPC-135
3. The RC642 shall be BACnet Testing Labs (BTL) certified and carry the BTL Label. a. The RC642 shall be tested and certified as a BACnet Advanced Application
Controller (B-AAC). b. A BACnet Protocol Implementation Conformance Statement shall be
provided for the TEC. c. The Conformance Statement shall be submitted 10 days prior to bidding.
4. The Networked Thermostat shall support remote read/write and parameter adjustment from the web based User Interface able through a WebCTRL Software.
5. The Networked Thermostat shall have a Large easy to read high contrast LCD display zone temperature, outside air temperature, heating and cooling setpoints, time, schedule, and local overrides.
6. The flexibility to support any one of the following inputs: a. Six Universal Inputs b. Four Relay Driven Binary Outputs c. Two 0-10V-dc Analog Outputs
7. The Networked Thermostat shall fully programmable for any terminal application. 8. The Networked Thermostat shall provide a minimum of six (6) levels of keypad
lockout. 9. The Networked Thermostat shall provide the flexibility to adjust the following
parameters: a. Adjustable Temporary Occupancy b. Adjustable heating/cooling deadband
10. The Networked Thermostat shall utilize a 16-bit microprocessor with 1 Mbyte Flash and 512 Kbyte of RAM—firmware upgrades with remote ability.
E. VAV Modular Assembly (VMA 26X0)
1. The VAV Modular Assembly shall provide both standalone and networked direct digital control of pressure-independent, variable air volume terminal units. It shall address both single and dual duct applications.
2. The VMA shall be BACnet Testing Labs (BTL) certified and carry the BTL Label. a. The VMA shall be tested and certified as a BACnet Application Specific
Controller (B-ASC). b. A BACnet Protocol Implementation Conformance Statement shall be
provided for the VMA. c. The Conformance Statement shall be submitted 10 days prior to bidding.
3. The VAV Modular Assembly shall communicate over the FC Bus using BACnet Standard protocol SSPC-135, Clause 9.
4. The VAV Modular Assembly shall have internal electrical isolation for AC power, DC inputs, and MS/TP communications. An externally mounted isolation transformer shall not be acceptable.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-22 Project Title Revised January 18, 2016 A-xxxxxx
5. The VAV Modular Assembly shall be a configurable digital controller with integral differential pressure transducer and damper actuator. All components shall be connected and mounted as a single assembly that can be removed as one piece.
6. The VAV Modular Assembly shall be assembled in a plenum-rated plastic housing with flammability rated to UL94-5VB.
7. The integral damper actuator shall be a fast response stepper motor capable of stroking 90 degrees in 30 seconds for quick damper positioning to speed commissioning and troubleshooting tasks.
8. The controller shall determine airflow by dynamic pressure measurement using an integral dead-ended differential pressure transducer. The transducer shall be maintenance-free and shall not require air filters.
9. Each controller shall have the ability to automatically calibrate the flow sensor to eliminate pressure transducer offset error due to ambient temperature / humidity effects.
10. The controller shall utilize a proportional plus integration (PI) algorithm for the space temperature control loops.
11. Each controller shall continuously, adaptively tune the control algorithms to improve control and controller reliability through reduced actuator duty cycle. In addition, this tuning reduces commissioning costs, and eliminates the maintenance costs of manually re-tuning loops to compensate for seasonal or other load changes.
12. The controller shall provide the ability to download and upload VMA configuration files, both locally and via the communications network. Controllers shall be able to be loaded individually or as a group using a zone schedule generated spreadsheet of controller parameters.
13. Control setpoint changes initiated over the network shall be written to VMA non-volatile memory to prevent loss of setpoint changes and to provide consistent operation in the event of communication failure.
14. The controller firmware shall be flash-upgradeable remotely via the communications bus to minimize costs of feature enhancements.
15. The controller shall provide fail-soft operation if the airflow signal becomes unreliable, by automatically reverting to a pressure-dependent control mode.
16. The controller shall interface with balancer tools that allow automatic recalculation of box flow pickup gain (“K” factor), and the ability to directly command the airflow control loop to the box minimum and maximum airflow setpoints.
17. Controller performance shall be self-documenting via on-board diagnostics. These diagnostics shall consist of control loop performance measurements executing at each control loop’s sample interval, which may be used to continuously monitor and document system performance. The VMA shall calculate exponentially weighted moving averages (EWMA) for each of the following. These metrics shall be available to the end user for efficient management of the VAV terminals.
◊ Absolute temperature loop error ◊ Signed temperature loop error ◊ Absolute airflow loop error ◊ Signed airflow loop error ◊ Average damper actuator duty cycle
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-23 Project Title Revised January 18, 2016 A-xxxxxx
18. The controller shall detect system error conditions to assist in managing the VAV zones. The error conditions shall consist of:
◊ Unreliable space temperature sensor ◊ Unreliable differential pressure sensor ◊ Starved box ◊ Actuator stall ◊ Insufficient cooling ◊ Insufficient heating
The controller shall provide a flow test function to view damper position vs. flow in a graphical format. The information would alert the user to check damper position. The VMA would also provide a method to calculate actuator duty cycle as an indicator of damper actuator runtime.
19. The controller shall provide a compliant interface for ASHRAE Standard 62-1989 (indoor air quality), and shall be capable of resetting the box minimum airflow Based on the percent of outdoor air in the primary air stream.
20. The controller shall comply with ASHRAE Standard 90.1 (energy efficiency) by preventing simultaneous heating and cooling, and where the control strategy requires reset of airflow while in reheat, by modulating the box reheat device fully open prior to increasing the airflow in the heating sequence.
21. Inputs: a. Analog inputs with user defined ranges shall monitor the following analog
signals, without the addition of equipment outside the terminal controller cabinet: ◊ 0-10 VDC Sensors ◊ 1000ohm RTDs ◊ NTC Thermistors
b. Binary inputs shall monitor dry contact closures. Input shall provide filtering to eliminate false signals resulting from input “bouncing.”
c. For noise immunity, the inputs shall be internally isolated from power, communications, and output circuits.
d. Provide side loop application for humidity control. 22. Outputs
a. Analog outputs shall provide the following control outputs: ◊ 0-10 VDC
b. Binary outputs shall provide a SPST Triac output rated for 500mA at 24 VAC.
c. For noise immunity, the outputs shall be internally isolated from power, communications, and other output circuits.
23. Application Configuration a. The VAV Modular Assembly shall be configured with a software tool that
provides a simple Question/Answer format for developing applications and downloading.
24. Sensor Support a. The VAV Modular Assembly shall communicate over the Sensor-Actuator
Bus (SA Bus) with a Network Sensor. b. The VMA shall support an LCD display room sensor.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-24 Project Title Revised January 18, 2016 A-xxxxxx
c. The VMA shall also support standard room sensors as defined by analog input requirements.
d. The VMA shall support humidity sensors defined by the AI side loop. F. VAV Modular Assembly (ZN 341/141)
1. The VAV Modular Assembly shall provide both standalone and networked direct digital control of pressure-independent, variable air volume terminal units. It shall address both single and dual duct applications.
2. The ZN shall be BACnet Testing Labs (BTL) certified and carry the BTL Label. a. The ZN shall be tested and certified as a BACnet Advanced Application
Controller (B-AAC). b. A BACnet Protocol Implementation Conformance Statement shall be
provided for the ZN c. The Conformance Statement shall be submitted 10 days prior to bidding.
3. The VAV Modular Assembly shall communicate over the ARCNET Bus using BACnet Standard protocol SSPC-135
4. The VAV Modular Assembly shall have internal electrical isolation for AC power, Universal inputs, and ARCNET communications.
5. The VAV Modular Assembly shall be a configurable digital controller with integral differential pressure transducer and damper actuator. All components shall be connected and mounted as a single assembly that can be removed as one piece.
6. The VAV Modular Assembly shall be assembled in a plenum-rated plastic housing with flammability rated to UL94-5VB.
7. The integral damper actuator shall be Brushless DC motor, torque 35 inch-pounds. 8. The controller shall determine airflow by precision low flow AWM series 0-2”
W.C. sensitive down to +/- 0.001” W.C. 9. Each controller shall have the ability to automatically calibrate the flow sensor to
eliminate pressure transducer offset error due to ambient temperature / humidity effects.
10. The controller shall utilize a proportional plus integration (PI) algorithm for the space temperature control loops.
11. The controller shall provide the ability to download and upload programming files, both locally and via the communications network. Controllers shall be able to be loaded individually or as a group.
12. Control setpoint changes initiated over the network shall be written to non-volatile memory to prevent loss of setpoint changes and to provide consistent operation in the event of communication failure.
13. The controller firmware shall be flash-upgradeable remotely via the communications bus to minimize costs of feature enhancements.
14. The controller shall provide fail-soft operation if the airflow signal becomes unreliable, by automatically reverting to a pressure-dependent control mode.
15. The controller shall interface with balancer tools that allow automatic recalculation of box flow pickup gain (“K” factor), and the ability to directly command the airflow control loop to the box minimum and maximum airflow setpoints.
16. The controller shall provide a compliant interface for ASHRAE Standard 62-1989 (indoor air quality), and shall be capable of resetting the box minimum airflow Based on the percent of outdoor air in the primary air stream.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-25 Project Title Revised January 18, 2016 A-xxxxxx
17. The controller shall comply with ASHRAE Standard 90.1 (energy efficiency) by preventing simultaneous heating and cooling, and where the control strategy requires reset of airflow while in reheat, by modulating the box reheat device fully open prior to increasing the airflow in the heating sequence.
18. Inputs: a. Analog inputs with user defined ranges shall monitor the following analog
signals, without the addition of equipment outside the terminal controller cabinet: ◊ 0-5 VDC Sensors ◊ Type II Thermistors
b. Binary inputs shall monitor dry contact closures. Input shall provide filtering to eliminate false signals resulting from input “bouncing.”
c. For noise immunity, the inputs shall be internally isolated from power, communications, and output circuits.
19. Outputs a. Analog outputs shall provide the following control outputs:
◊ 0-10 VDC b. Binary outputs shall provide a Relay contact rated at 1A max @ 24V-ac/dc c. For noise immunity, the outputs shall be internally isolated from power,
communications, and other output circuits. 20. Application Configuration
a. The VAV Modular Assembly shall be configured with Eikon Graphical Software.
21. Sensor Support a. The VAV Modular Assembly shall communicate over the Rnet Bus with a
Network Sensor. b. The ZN shall support an LCD display room sensor. c. The ZN shall also support standard room sensors as defined by analog input
requirements. d. The ZN shall support humidity sensors.
G. Network Sensors (NS-XXX700X)
1. The Network Sensors (NS) shall have the ability to monitor the following variables as required by the systems sequence of operations: a. Zone Temperature b. Zone Humidity c. Zone Setpoint d. Discharge Air Temperature
2. The NS shall transmit the information back to the controller on the Sensor-Actuator Bus (SA Bus) using BACnet Standard protocol SSPC-135, Clause 9.
3. The NS shall be BACnet Testing Labs (BTL) certified and carry the BTL Label. a. The NS shall be tested and certified as a BACnet Smart Sensors (B-SS). b. A BACnet Protocol Implementation Conformance Statement shall be
provided for the NS. c. The Conformance Statement shall be submitted 10 days prior to bidding.
4. The Network Zone Sensors shall include the following items:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-26 Project Title Revised January 18, 2016 A-xxxxxx
a. A backlit Liquid Crystal Display (LCD) to indicate the Temperature, Humidity and Setpoint
b. An LED to indicate the status of the Override feature c. A button to toggle the temperature display between Fahrenheit and Celsius d. A button to initiate a timed override command e. Available in either surface mount or wall mount f. Available with either screw terminals or phone jack
5. The Network Discharge Air Sensors shall include the following: a. 4 inch or 8 inch duct insertion probe b. 10 foot pigtail lead c. Dip Switches for programmable address selection d. Ability to provide an averaging temperature from multiple locations e. Ability to provide a selectable temperature from multiple locations
H. Network Sensors (RS-BASE/PLUS/PRO/PROF) 1. The Network Sensors (NS) shall have the ability to monitor the following variables
as required by the systems sequence of operations: a. Zone Temperature b. Zone Humidity c. Zone Setpoint d. Zone CO2
2. The NS shall transmit the information back to the controller on the Sensor-Rnet using BACnet Standard protocol SSPC-135.
3. The NS shall be BACnet Testing Labs (BTL) certified and carry the BTL Label. a. The NS shall be tested and certified as a BACnet Smart Sensors (B-SS). b. A BACnet Protocol Implementation Conformance Statement shall be
provided for the NS. c. The Conformance Statement shall be submitted 10 days prior to bidding.
4. The Network Zone Sensors shall include the following items: a. A backlit Liquid Crystal Display (LCD) to indicate the Temperature,
Humidity and Setpoint b. An LED to indicate the status of the Override feature c. A button to toggle the temperature display between Fahrenheit and Celsius d. A button to initiate a timed override command e. Available for wall mount f. Available with either screw terminals
2.7 System Tools
A. System Configuration Tool (SCT) or Job Builder Tool (JBT) 1. The Configuration Tool software or (JBT) is existing and shall be utilized for the
development of software on this project.
2.8 Input Devices
A. General Requirements 1. Installation, testing, and calibration of all sensors, transmitters, and other input
devices shall be provided to meet the system requirements.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-27 Project Title Revised January 18, 2016 A-xxxxxx
B. Temperature Sensors 1. General Requirements:
a. Sensors and transmitters shall be provided, as outlined in the input/output summary and sequence of operations.
b. The temperature sensor shall be of the resistance type, and shall be either two-wire 1000 ohm nickel RTD, two-wire 1000 ohm platinum RTD; or Type II Thermistor.
c. The following point types (and the accuracy of each) are required, and their associated accuracy values include errors associated with the sensor, lead wire, and A to D conversion:
Point Type Accuracy
Chilled Water + .5°F.
Room Temp + .5°F.
Duct Temperature + .5°F.
All Others + .75°F.
2. Room Temperature Sensors a. Room sensors shall be constructed for either surface or wall box mounting. b. Room sensors shall have the following options when specified:
◊ Setpoint reset slide switch providing a +3 degree (adjustable) range. ◊ Individual heating/cooling setpoint slide switches. ◊ A momentary override request push button for activation of after-
hours operation. ◊ Analog thermometer.
3. Room Temperature Sensors with Integral Display a. Room sensors shall be constructed for either surface or wall box mounting. b. Room sensors shall have an integral LCD display and four button keypad
with the following capabilities: ◊ Display room and outside air temperatures. ◊ Display and adjust room comfort setpoint. ◊ Display and adjust fan operation status. ◊ Timed override request push button with LED status for activation of
after-hours operation. ◊ Display controller mode. ◊ Password selectable adjustment of setpoint and override modes.
4. Thermo wells a. When thermo wells are required, the sensor and well shall be supplied as a
complete assembly, including wellhead and Greenfield fitting. b. Thermo wells shall be pressure rated and constructed in accordance with the
system working pressure. c. Thermo wells and sensors shall be mounted in a threadolet or 1/2” NFT
saddle and allow easy access to the sensor for repair or replacement. d. Thermo wells shall be constructed of 326 stainless steel.
5. Outside Air Sensors
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-28 Project Title Revised January 18, 2016 A-xxxxxx
a. Outside air sensors shall be designed to withstand the environmental conditions to which they will be exposed. They shall also be provided with a solar shield.
b. Sensors exposed to wind velocity pressures shall be shielded by a perforated plate that surrounds the sensor element.
c. Temperature transmitters shall be of NEMA 3R construction and rated for ambient temperatures.
6. Duct Mount Sensors a. Duct mount sensors shall mount in an electrical box through a hole in the
duct, and be positioned so as to be easily accessible for repair or replacement.
b. Duct sensors shall be insertion type and constructed as a complete assembly, including lock nut and mounting plate.
c. For outdoor air duct applications, a weatherproof mounting box with weatherproof cover and gasket shall be used.
7. Averaging Sensors a. For ductwork greater in any dimension that 48 inches and/or where air
temperature stratification exists, an averaging sensor with multiple sensing points shall be used.
b. For plenum applications, such as mixed air temperature measurements, a string of sensors mounted across the plenum shall be used to account for stratification and/or air turbulence. The averaging string shall have a minimum of 4 sensing points per 12-foot long segment.
c. Capillary supports at the sides of the duct shall be provided to support the sensing string.
8. Acceptable Manufacturers: Johnson Controls, Setra. C. Humidity Sensors
1. The sensor shall be a solid-state type, relative humidity sensor of the Bulk Polymer Design. The sensor element shall resist service contamination.
2. The humidity transmitter shall be equipped with non-interactive span and zero adjustments, a 2-wire isolated loop powered, 4-20 mA, 0-100% linear proportional output.
3. The humidity transmitter shall meet the following overall accuracy, including lead loss and Analog to Digital conversion. 3% between 20% and 80% RH @ 77 Deg F unless specified elsewhere.
4. Outside air relative humidity sensors shall be installed with a rain proof, perforated cover. The transmitter shall be installed in a NEMA 3R enclosure with sealtite fittings and stainless steel bushings.
5. A single point humidity calibrator shall be provided, if required, for field calibration. Transmitters shall be shipped factory pre-calibrated.
6. Duct type sensing probes shall be constructed of 304 stainless steel, and shall be equipped with a neoprene grommet, bushings, and a mounting bracket.
7. Acceptable Manufacturers: Johnson Controls, Veris Industries, and Mamac. D. Differential Pressure Transmitters
1. General Air and Water Pressure Transmitter Requirements:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-29 Project Title Revised January 18, 2016 A-xxxxxx
a. Pressure transmitters shall be constructed to withstand 100% pressure over-range without damage, and to hold calibrated accuracy when subject to a momentary 40% over-range input.
b. Pressure transmitters shall transmit a 0 to 5 VDC, 0 to 10 VDC, or 4 to 20 mA output signal.
c. Differential pressure transmitters used for flow measurement shall be sized to the flow sensing device, and shall be supplied with Tee fittings and shut-off valves in the high and low sensing pick-up lines to allow the balancing Contractor and Owner permanent, easy-to-use connection.
d. A minimum of a NEMA 1 housing shall be provided for the transmitter. Transmitters shall be located in accessible local control panels wherever possible.
2. Low Differential Water Pressure Applications (0” - 20” w.c.) a. The differential pressure transmitter shall be of industrial quality and
transmit a linear, 4 to 20 mA output in response to variation of flow meter differential pressure or water pressure sensing points.
b. The differential pressure transmitter shall have non-interactive zero and span adjustments that are adjustable from the outside cover and meet the following performance specifications: ◊ .01-20” w.c. input differential pressure range. ◊ 4-20 mA output. ◊ Maintain accuracy up to 20 to 1 ratio turndown. ◊ Reference Accuracy: +0.2% of full span.
c. Acceptable Manufacturers: Setra and Mamac. 3. Medium to High Differential Water Pressure Applications (Over 21” w.c.)
a. The differential pressure transmitter shall meet the low pressure transmitter specifications with the following exceptions: ◊ Differential pressure range 10” w.c. to 300 PSI. ◊ Reference Accuracy: +1% of full span (includes non-linearity,
hysteresis, and repeatability). b. Standalone pressure transmitters shall be mounted in a bypass valve
assembly panel. The panel shall be constructed to NEMA 1 standards. The transmitter shall be installed in the panel with high and low connections piped and valved. Air bleed units, bypass valves, and compression fittings shall be provided.
c. Acceptable Manufacturers: Setra and Mamac. 4. Building Differential Air Pressure Applications (-1” to +1” w.c.)
a. The differential pressure transmitter shall be of industrial quality and transmit a linear, 4 to 20 mA output in response to variation of differential pressure or air pressure sensing points.
b. The differential pressure transmitter shall have non-interactive zero and span adjustments that are adjustable from the outside cover and meet the following performance specifications: ◊ -1.00 to +1.00 w.c. input differential pressure ranges. (Select range
appropriate for system application) ◊ 4-20 mA output. ◊ Maintain accuracy up to 20 to 1 ratio turndown. ◊ Reference Accuracy: +0.2% of full span.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-30 Project Title Revised January 18, 2016 A-xxxxxx
c. Acceptable Manufacturers: Johnson Controls and Setra. 5. Low Differential Air Pressure Applications (0” to 5” w.c.)
a. The differential pressure transmitter shall be of industrial quality and transmit a linear, 4 to 20 mA output in response to variation of differential pressure or air pressure sensing points.
b. The differential pressure transmitter shall have non-interactive zero and span adjustments that are adjustable from the outside cover and meet the following performance specifications: ◊ (0.00 - 1.00” to 5.00”) w.c. input differential pressure ranges. (Select
range appropriate for system application.) ◊ 4-20 mA output. ◊ Maintain accuracy up to 20 to 1 ratio turndown. ◊ Reference Accuracy: +0.2% of full span.
c. Acceptable Manufacturers: Johnson Controls and Setra. 6. Medium Differential Air Pressure Applications (5” to 21” w.c.)
a. The pressure transmitter shall be similar to the Low Air Pressure Transmitter, except that the performance specifications are not as severe. Differential pressure transmitters shall be provided that meet the following performance requirements: ◊ Zero & span: (c/o F.S./Deg. F): .04% including linearity, hysteresis
and repeatability. ◊ Accuracy: 1% F.S. (best straight line) Static Pressure Effect: 0.5%
F.S. (to 100 PSIG. ◊ Thermal Effects: <+.033 F.S./Deg. F. over 40°F. to 100°F. (calibrated
at 70°F.). b. Standalone pressure transmitters shall be mounted in a bypass valve
assembly panel. The panel shall be constructed to NEMA 1 standards. The transmitter shall be installed in the panel with high and low connections piped and valved. Air bleed units, bypass valves, and compression fittings shall be provided.
c. Acceptable manufacturers: Johnson Controls and Setra. E. Flow Monitoring
1. Air Flow Monitoring a. Fan Inlet Air Flow Measuring Stations
◊ At the inlet of each fan and near the exit of the inlet sound trap, airflow traverse probes shall be provided that shall continuously monitor the fan air volumes and system velocity pressure.
◊ Each traverse probe shall be of a dual manifolded, cylindrical, type 3003 extruded aluminum configuration, having an anodized finish to eliminate surface pitting and unnecessary air friction. The multiple total pressure manifold shall have sensors located along the stagnation plane of the approaching airflow. The manifold should not have forward projecting sensors into the air stream. The static pressure manifold shall incorporate dual offset static tops on the opposing sides of the averaging manifold so as to be insensitive to flow-angle variations of as much as + 20° in the approaching air stream.
◊ The airflow traverse probe shall not induce a measurable pressure drop, nor shall the sound level within the duct be amplified by its
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-31 Project Title Revised January 18, 2016 A-xxxxxx
singular or multiple presence in the air stream. Each airflow-measuring probe shall contain multiple total and static pressure sensors placed at equal distances along the probe length. The number of sensors on each probe and the quantity of probes utilized at each installation shall comply with the ASHRAE Standards for duct traversing.
◊ Airflow measuring stations shall be manufactured by Air Monitor Corp., Tek-Air Systems, Inc., Ebtron, or Dietrich Standard.
b. Single Probe Air Flow Measuring Sensor ◊ The single probe airflow-measuring sensor shall be duct mounted
with an adjustable sensor insertion length of up to eight inches. The transmitter shall produce a 4-20 mA or 0-10 VDC signal linear to air velocity. The sensor shall be a hot wire anemometer and utilize two temperature sensors and a heater element temperature. The other sensor shall measure the downstream air temperature. The temperature differential shall be directly related to airflow velocity.
c. Duct Air Flow Measuring Stations ◊ Each device shall be designed and built to comply with, and provide
results in accordance with, accepted practice as defined for system testing in the ASHRAE Handbook of fundamentals, as well as in the Industrial Ventilation Handbook.
◊ Airflow measuring stations shall be fabricated of 14-gauge galvanized steel welded casing with 90 Deg. connecting flanges in configuration and size equal to that of the duct into which it is mounted. Each station shall be complete with an air directionalizer and parallel cell profile suppressor (3/4” maximum cell) across the entering air stream and mechanically fastened to the casing in such a way to withstand velocities up to 6000 feet per minute. This air directionalizer and parallel cell honeycomb suppressor shall provide 98% free area, equalize the velocity profile, and eliminate turbulent and rotational flow from the air stream prior to the measuring point.
◊ The total pressure measurement side (high side) will be designed and spaced to the Industrial Ventilation Manual 26th Edition, Page 9-5. The self-averaging manifolding will be manufactured of brass and copper components.
◊ The static pressure sensing probes (low side) shall be bullet-nosed shaped, per detailed radius, as illustrated in Industrial Ventilation Manual 26th Edition, Page 9-5.
◊ The main take-off point from both the total pressure and the static pressure manifolds must be symmetrical.
◊ Total and static pressure manifolds shall terminate with external ports for connection to control tubing. An identification label shall be placed on each unit casing, listing model number, size, area, and specified airflow capacity.
◊ Installation Considerations
(i) The maximum allowable pressure loss through the Flow and Static Pressure elements shall not exceed .065” w.c. at 1000 feet per minute, or .23” w.c. at 2000 feet per minute. Each unit shall measure the airflow rate within an accuracy of plus 2% as determined by U.S. – GSA
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-32 Project Title Revised January 18, 2016 A-xxxxxx
certification tests, and shall contain a minimum of one total pressure sensor per 36 square inches of unit measuring area.
(ii) The units shall have a self-generated sound rating of less than NC40, and the sound level within the duct shall not be amplified nor shall additional sound be generated.
(iii) Where the stations are installed in insulated ducts, the airflow passage of the station shall be the same size as the inside airflow dimension of the duct. Station flanges shall be two inch to three inch to facilitate matching connecting ductwork.
(iv) Where control dampers are shown as part of the airflow measuring station, opposed blade precision controlled volume dampers integral to the station and complete with actuator, pilot positioner, and linkage shall be provided.
(v) Stations shall be installed in strict accordance with the manufacturer’s published requirements, and in accordance with ASME Guidelines affecting non-standard approach conditions.
◊ Acceptable manufacturers: Air Monitor Corp., Tek-Air, Ebtron, and Johnson Controls.
d. Static Pressure Traverse Probe ◊ Duct static traverse probes shall be provided where required to
monitor duct static pressure. The probe shall contain multiple static pressure sensors located along exterior surface of the cylindrical probe.
◊ Acceptable manufacturers: Cleveland Controls e. Shielded Static Air Probe
◊ A shielded static pressure probe shall be provided at each end of the building. The probe shall have multiple sensing ports, an impulse suppression chamber, and airflow shielding. A suitable probe for indoor and outdoor locations shall be provided.
2. Water Flow Monitoring ◊ Water flow meters shall be electromagnetic type with integral
microprocessor-Based electronics. The meter shall have an accuracy of 0.25%.
◊ Acceptable manufacturers: Onicon F. Power Monitoring Devices
1. Current Measurement (Amps) a. Current measurement shall be by a combination current transformer and a
current transducer. The current transformer shall be sized to reduce the full amperage of the monitored circuit to a maximum 5 Amp signal, which will be converted to a 4-20 mA DDC compatible signal for use by the Facility Management System.
b. Current Transformer – A split core current transformer shall be provided to monitor motor amps. ◊ Operating frequency – 50 - 400 Hz. ◊ Insulation – 0.6 Kv class 10Kv BIL.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-33 Project Title Revised January 18, 2016 A-xxxxxx
◊ UL recognized. ◊ Five amp secondary. ◊ Select current ration as appropriate for application. ◊ Acceptable manufacturers: Veris Industries
c. Current Transducer – A current to voltage or current to mA transducer shall be provided. The current transducer shall include: ◊ 6X input over amp rating for AC inrushes of up to 120 amps. ◊ Manufactured to UL 1244. ◊ Accuracy: +.5%, Ripple +1%. ◊ Minimum load resistance 30kOhm. ◊ Input 0-20 Amps. ◊ Output 4-20 mA. ◊ Transducer shall be powered by a 24VDC regulated power supply (24
VDC +5%). ◊ Acceptable manufacturers: Veris Industries
G. Smoke Detectors
1. Ionization type air duct detectors shall be furnished as specified elsewhere in Division 26 for installation under Division 23. All wiring for air duct detectors shall be provided under Division 26, Fire Alarm System.
H. Status and Safety Switches 1. General Requirements
a. Switches shall be provided to monitor equipment status, safety conditions, and generate alarms at the BACS when a failure or abnormal condition occurs. Safety switches shall be provided with two sets of contacts and shall be interlock wired to shut down respective equipment.
2. Current Sensing Switches a. The current sensing switch shall be self-powered with solid-state circuitry
and a dry contact output. It shall consist of a current transformer, a solid state current sensing circuit, adjustable trip point, solid state switch, SPDT relay, and an LED indicating the on or off status. A conductor of the load shall be passed through the window of the device. It shall accept over-current up to twice its trip point range.
b. Current sensing switches shall be used for run status for fans, pumps, and other miscellaneous motor loads.
c. Current sensing switches shall be calibrated to show a positive run status only when the motor is operating under load. A motor running with a broken belt or coupling shall indicate a negative run status.
d. Acceptable manufacturers: Veris Industries 3. Air Filter Status Switches
a. Differential pressure switches used to monitor air filter status shall be of the automatic reset type with SPDT contacts rated for 2 amps at 120VAC.
b. A complete installation kit shall be provided, including: static pressure tops, tubing, fittings, and air filters.
c. Provide appropriate scale range and differential adjustment for intended service.
d. Acceptable manufacturers: Johnson Controls, Cleveland Controls
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-34 Project Title Revised January 18, 2016 A-xxxxxx
4. Air Flow Switches
a. Differential pressure flow switches shall be bellows actuated mercury switches or snap acting micro-switches with appropriate scale range and differential adjustment for intended service.
b. Acceptable manufacturers: Johnson Controls, Cleveland Controls 5. Air Pressure Safety Switches
a. Air pressure safety switches shall be of the manual reset type with SPDT contacts rated for 2 amps at 120VAC.
b. Pressure range shall be adjustable with appropriate scale range and differential adjustment for intended service.
c. Acceptable manufacturers: Johnson Controls, Cleveland Controls 6. Water Flow Switches
a. Water flow switches shall be equal to the Johnson Controls P74. 7. Low Temperature Limit Switches
a. The low temperature limit switch shall be of the manual reset type with Double Pole/Single Throw snap acting contacts rated for 26 amps at 120VAC.
b. The sensing element shall be a minimum of 23 feet in length and shall react to the coldest 18-inch section. Element shall be mounted horizontally across duct in accordance with manufacturers recommended installation procedures.
c. For large duct areas where the sensing element does not provide full coverage of the air stream, additional switches shall be provided as required to provide full protection of the air stream.
d. The low temperature limit switch shall be equal to Johnson Controls A70.
2.9 Output Devices
A. Actuators 1. General Requirements
a. Damper and valve actuators shall be electronic and/or pneumatic, as specified in the System Description section.
2. Electronic Damper Actuators a. Electronic damper actuators shall be direct shaft mount. b. Modulating and two-position actuators shall be provided as required by the
sequence of operations. Damper sections shall be sized Based on actuator manufacturer’s recommendations for face velocity, differential pressure and damper type. The actuator mounting arrangement and spring return feature shall permit normally open or normally closed positions of the dampers, as required. All actuators (except terminal units) shall be furnished with mechanical spring return unless otherwise specified in the sequences of operations. All actuators shall have external adjustable stops to limit the travel in either direction, and a gear release to allow manual positioning.
c. Modulating actuators shall accept 24 VAC or VDC power supply, consume no more than 23 VA, and be UL listed. The control signal shall be 2-10 VDC or 4-20 mA, and the actuator shall provide a clamp position feedback signal of 2-10 VDC. The feedback signal shall be independent of the input
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-35 Project Title Revised January 18, 2016 A-xxxxxx
signal and may be used to parallel other actuators and provide true position indication. The feedback signal of one damper actuator for each separately controlled damper shall be wired back to a terminal strip in the control panel for trouble-shooting purposes.
d. Two-position or open/closed actuators shall accept 24 or 120 VAC power supply and be UL listed. Isolation, smoke, exhaust fan, and other dampers, as specified in the sequence of operations, shall be furnished with adjustable end switches to indicate open/closed position or be hard wired to start/stop associated fan. Two-position actuators, as specified in sequences of operations as “quick acting,” shall move full stroke within 20 seconds. All smoke damper actuators shall be quick acting.
e. Acceptable manufacturers: Johnson Controls, Mamac, Belimo 3. Electronic Valve Actuators
a. Electronic valve actuators shall be manufactured by the valve manufacturer. b. Each actuator shall have current limiting circuitry incorporated in its design
to prevent damage to the actuator. c. Modulating and two-position actuators shall be provided as required by the
sequence of operations. Actuators shall provide the minimum torque required for proper valve close-off against the system pressure for the required application. The valve actuator shall be sized Based on valve manufacturer’s recommendations for flow and pressure differential. All actuators shall fail in the last position unless specified with mechanical spring return in the sequence of operations. The spring return feature shall permit normally open or normally closed positions of the valves, as required. All direct shaft mount rotational actuators shall have external adjustable stops to limit the travel in either direction.
d. Modulating Actuators shall accept 24 VAC or VDC and 120 VAC power supply and be UL listed. The control signal shall be 2-10 VDC or 4-20 mA and the actuator shall provide a clamp position feedback signal of 2-10 VDC. The feedback signal shall be independent of the input signal, and may be used to parallel other actuators and provide true position indication. The feedback signal of each valve actuator (except terminal valves) shall be wired back to a terminal strip in the control panel for trouble-shooting purposes.
e. Two-position or open/closed actuators shall accept 24 or 120 VAC power supply and be UL listed. Butterfly isolation and other valves, as specified in the sequence of operations, shall be furnished with adjustable end switches to indicate open/closed position or be hard wired to start/stop the associated pump or chiller.
f. Acceptable manufacturers: Johnson Controls or Belimo B. Control Dampers
1. The BACS Contractor shall furnish all automatic dampers. All automatic dampers shall be sized for the application by the BACS Contractor or as specifically indicated on the Drawings.
2. All dampers used for throttling airflow shall be of the opposed blade type arranged for normally open or normally closed operation, as required. The damper is to be sized so that, when wide open, the pressure drop is a sufficient amount of its close-off pressure drop to shift the characteristic curve to near linear.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-36 Project Title Revised January 18, 2016 A-xxxxxx
3. All dampers used for two-position, open/close control shall be parallel blade type arranged for normally open or closed operation, as required.
4. Damper frames and blades shall be constructed of either galvanized steel or aluminum. Maximum blade length in any section shall be 60”. Damper blades shall be 26-gauge minimum and shall not exceed eight (8) inches in width. Damper frames shall be 26-gauge minimum hat channel type with corner bracing. All damper bearings shall be made of reinforced nylon, stainless steel or oil-impregnated bronze. Dampers shall be tight closing, low leakage type, with synthetic elastomer seals on the blade edges and flexible stainless steel side seals. Dampers of 48”x48” size shall not leak in excess of 8.0 cfm per square foot when closed against 4” w.g. static pressure when tested in accordance with AMCA Std. 500.
5. Airfoil blade dampers of double skin construction with linkage out of the air stream shall be used whenever the damper face velocity exceeds 2300 FPM or system pressure exceeds 2.5” w.g., but no more than 4000 FPM or 6” w.g. Acceptable manufacturers are Johnson Controls D-7250 D-1250 or D-1300, Ruskin CD50, and Vent Products 5650.
6. One piece rolled blade dampers with exposed or concealed linkage may be used with face velocities of 2300 FPM or below. Acceptable manufacturers are: Johnson Controls D-2600, Ruskin CD36, and Vent Products 5800.
7. Multiple section dampers may be jack-shafted to allow mounting of piston pneumatic actuators and direct connect electronic actuators. Each end of the jackshaft shall receive at least one actuator to reduce jackshaft twist.
C. Control Relays 1. Control Pilot Relays
a. Control pilot relays shall be of a modular plug-in design with retaining springs or clips.
b. Mounting Bases shall be snap-mount. c. DPDT, 3PDT, or 4PDT relays shall be provided, as appropriate for
application. d. Contacts shall be rated for 10 amps at 120VAC. e. Relays shall have an integral indicator light and check button. f. Acceptable manufacturers: Johnson Controls, Lectro
2. Lighting Control Relays a. Lighting control relays shall be latching with integral status contacts. b. Contacts shall be rated for 20 amps at 277 VAC. c. The coil shall be a split low-voltage coil that moves the line voltage contact
armature to the ON or OFF latched position. d. Lighting control relays shall be controlled by:
◊ Pulsed Tri-state Output – Preferred method. ◊ Pulsed Paired Binary Outputs. ◊ A Binary Input to the Facility Management System shall monitor
integral status contacts on the lighting control relay. Relay status contacts shall be of the “dry-contact” type.
e. The relay shall be designed so that power outages do not result in a change-of-state, and so that multiple same state commands will simply maintain the commanded state. Example: Multiple OFF command pulses shall simply keep the contacts in the OFF position.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-37 Project Title Revised January 18, 2016 A-xxxxxx
D. Control Valves 1. All automatic control valves shall be fully proportioning and provide near linear
heat transfer control. The valves shall be quiet in operation and fail-safe open, closed, or in their last position. All valves shall operate in sequence with another valve when required by the sequence of operations. All control valves shall be sized by the control manufacturer, and shall be guaranteed to meet the heating and cooling loads, as specified. All control valves shall be suitable for the system flow conditions and close against the differential pressures involved. Body pressure rating and connection type (sweat, screwed, or flanged) shall conform to the pipe schedule elsewhere in this Specification.
2. Chilled water control valves shall be modulating plug, ball, and/or butterfly, as required by the specific application. Modulating water valves shall be sized per manufacturer’s recommendations for the given application. In general, valves (2 or 3-way) serving variable flow air handling unit coils shall be sized for a pressure drop equal to the actual coil pressure drop, but no less than 5 PSI. Valves (3-way) serving constant flow air handling unit coils with secondary circuit pumps shall be sized for a pressure drop equal to 25% the actual coil pressure drop, but no less than 2 PSI. Mixing valves (3-way) serving secondary water circuits shall be sized for a pressure drop of no less than 5 PSI. Valves for terminal reheat coils shall be sized for a 2 PSIG pressure drop, but no more than a 5 PSI drop.
3. Ball valves shall be used for hot and chilled water applications, water terminal reheat coils, radiant panels, unit heaters, package air conditioning units, and fan coil units except those described hereinafter.
4. Modulating plug water valves of the single-seat type with equal percentage flow characteristics shall be used for all special applications as indicated on the valve schedule. Valve discs shall be composition type. Valve stems shall be stainless steel.
5. Butterfly valves shall be acceptable for modulating large flow applications greater than modulating plug valves, and for all two-position, open/close applications. In-line and/or three-way butterfly valves shall be heavy-duty pattern with a body rating comparable to the pipe rating, replaceable lining suitable for temperature of system, and a stainless steel vane. Valves for modulating service shall be sized and travel limited to 50 degrees of full open. Valves for isolation service shall be the same as the pipe. Valves in the closed position shall be bubble-tight.
6. Pressure independent delta-p valves may be used for hydronic heating applications. E. External Manual Override Stations
1. External manual override stations shall provide the following: a. An integral HAND/OFF/AUTO switch shall override the controlled device
pilot relay. b. A status input to the Facility Management System shall indicate whenever
the switch is not in the automatic position. c. A Status LED shall illuminate whenever the output is ON. d. An Override LED shall illuminate whenever the HOA switch is in either the
HAND or OFF position. e. Contacts shall be rated for a minimum of 1 amp at 24 VAC.
F. Electronic/Pneumatic Transducers 1. Electronic to Pneumatic transducers shall provide:
a. Output: 3-23 PSIG.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-38 Project Title Revised January 18, 2016 A-xxxxxx
b. Input: 4-20 mA or 0-10 VDC. c. Manual output adjustment. d. Pressure gauge. e. External replaceable supply air filter. f. Acceptable manufacturers: Johnson Controls, Mamac, ACT
2.10 Miscellaneous Devices
A. Variable Frequency Motor Speed Control Drives 1. Variable frequency drives shall be Danfoss, supplied by BACS
Contractor. Provide 3-contactor bypass with integral disconnect. B. Local Control Panels
1. All control panels shall be factory constructed, incorporating the BACS manufacturer’s standard designs and layouts. All control panels shall be UL inspected and listed as an assembly and carry a UL 508 label listing compliance. Control panels shall be fully enclosed, with perforated sub-panel, hinged door, and slotted flush latch.
2. In general, the control panels shall consist of the DDC controller(s), display module as specified and indicated on the plans, and I/O devices—such as relays, transducers, and so forth—that are not required to be located external to the control panel due to function. Where specified the display module shall be flush mounted in the panel face unless otherwise noted.
3. All I/O connections on the DDC controller shall be provide via removable or fixed screw terminals.
4. Low and line voltage wiring shall be segregated. All provided terminal strips and wiring shall be UL listed, 300-volt service and provide adequate clearance for field wiring.
5. All wiring shall be neatly installed in plastic trays or tie-wrapped. 6. A convenience 120 VAC duplex receptacle shall be provided in each enclosure,
fused on/off power switch, and required transformers. C. Power Supplies
1. DC power supplies shall be sized for the connected device load. Total rated load shall not exceed 75% of the rated capacity of the power supply.
2. Input: 120 VAC +10%, 60Hz. 3. Output: 24 VDC. 4. Line Regulation: +0.05% for 10% line change. 5. Load Regulation: +0.05% for 50% load change. 6. Ripple and Noise: 1 mV rms, 5 mV peak to peak. 7. An appropriately sized fuse and fuse block shall be provided and located next to
the power supply. 8. A power disconnect switch shall be provided next to the power supply. 9. When the application is life safety or mission critical, provide an uninterruptible
power supply of capacity and duration sufficient to maintain operation of system. D. Thermostats
1. Electric room thermostats of the heavy-duty type shall be provided for unit heaters, cabinet unit heaters, and ventilation fans, where required. All these items shall be
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-39 Project Title Revised January 18, 2016 A-xxxxxx
provided with concealed adjustment. Finish of covers for all room-type instruments shall match and, unless otherwise indicated or specified, covers shall be manufacturer’s standard finish.
3. Part 3 – Execution
3.1 BACS Specific Requirements
A. Graphic Displays 1. Graphics will be developed for the project will be representative of the systems
controlled by the BACS. Floor plans will be provided by the project Architect/Engineer and will be used to develop floor-level graphics to speed recognition and response for operation of BACS. Level of graphics capability will be based on the type of system controlled.
a. Provide floor plan(s) defining spaces (with University approved numbering) that are served by each air handling unit. b. Provide schematic drawing showing the unit configuration and control devices for each air handling unit.
B. Custom Reports: 1. As required.
C. Actuation / Control Type 1. Primary Equipment
a. Controls shall be provided by equipment manufacturer as specified herein. b. All damper and valve actuation shall be electric.
2. Air Handling Equipment a. All air handers shall be controlled with a HVAC-DDC Controller b. All damper and valve actuation shall be electric.
3. Terminal Equipment: a. Terminal Units (VAV, UV, etc.) shall have electric damper and valve
actuation. b. All Terminal Units shall be controlled with HVAC-DDC Controller)
3.2 Installation Practices
A. BACS Wiring 1. All conduit, wiring, accessories and wiring connections required for the installation
of the Building Automation Controls System, as herein specified, shall be provided by the BACS Contractor unless specifically shown on the Electrical Drawings under Division 26 Electrical. All wiring shall comply with the requirements of applicable portions of Division 26 and all local and national electric codes, unless specified otherwise in this section.
2. All BACS wiring materials and installation methods shall comply with BACS manufacturer recommendations.
3. The sizing, type and provision of cable, conduit, cable trays, and raceways shall be the design responsibility of the BACS Contractor. If complications arise, however, due to the incorrect selection of cable, cable trays, raceways and/or conduit by the BACS Contractor, the Contractor shall be responsible for all costs incurred in replacing the selected components.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-40 Project Title Revised January 18, 2016 A-xxxxxx
4. Class 2 Wiring a. All Class 2 (24VAC or less) wiring shall be installed in conduit unless
otherwise specified. b. Conduit is not required for Class 2 wiring in concealed accessible locations.
Class 2 wiring not installed in conduit shall be supported every 5’ from the building structure utilizing metal hangers designed for this application. Wiring shall be installed parallel to the building structural lines. All wiring shall be installed in accordance with local code requirements.
5. Class 2 signal wiring and 24VAC power can be run in the same conduit. Power wiring 120VAC and greater cannot share the same conduit with Class 2 signal wiring.
6. Provide for complete grounding of all applicable signal and communications cables, panels and equipment so as to ensure system integrity of operation. Ground cabling and conduit at the panel terminations. Avoid grounding loops.
7. Remove all cabling this has been abandoned or is no longer in service. 8. Color code wiring in accordance with KU standards.
B. BACS Line Voltage Power Source 1. 120-volt AC circuits used for the Building Automation Controls System shall be
taken from panel boards and circuit breakers provided by Division 26. 2. Circuits used for the BACS shall be dedicated to the BACS and shall not be used
for any other purposes. 3. DDC terminal unit controllers may use AC power from motor power circuits.
C. BACS Raceway 1. All wiring shall be installed in conduit or raceway except as noted elsewhere in
this specification. Minimum control wiring conduit size 1/2”. 2. Where it is not possible to conceal raceways in finished locations, surface raceway
(Wiremold) may be used as approved by the Architect. 3. All conduits and raceways shall be installed level, plumb, at right angles to the
building lines and shall follow the contours of the surface to which they are attached.
4. Flexible Metal Conduit shall be used for vibration isolation and shall be limited to 3 feet in length when terminating to vibrating equipment. Flexible Metal Conduit may be used within partition walls. Flexible Metal Conduit shall be UL listed.
D. Penetrations 1. Provide fire stopping for all penetrations used by dedicated BACS conduits and
raceways. 2. All openings in fire proofed or fire stopped components shall be closed by using
UL approved fire resistive sealant and/or system. 3. All wiring passing through penetrations, including walls shall be in conduit or
enclosed raceway. 4. Penetrations of floor slabs shall be by core drilling. All penetrations shall be
plumb, true, and square. E. BACS Identification Standards
1. Node Identification. All nodes shall be identified by a permanent label fastened to the enclosure. Labels shall be suitable for the node location.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-41 Project Title Revised January 18, 2016 A-xxxxxx
Cable types specified in Item A shall be color coded for easy identification and troubleshooting.
F. BACS Panel Installation 1. The BACS panels and cabinets shall be located as indicated at an elevation of not
less than 2 feet from the bottom edge of the panel to the finished floor. Each cabinet shall be anchored per the manufacturer’s recommendations.
2. The BACS contractor shall be responsible for coordinating panel locations with other trades and electrical and mechanical contractors.
G. Input Devices 1. All Input devices shall be installed per the manufacturer recommendation 2. Locate components of the BACS in accessible local control panels wherever
possible. H. HVAC Input Devices – Genera1
1. All Input devices shall be installed per the manufacturer recommendation 2. Locate components of the BACS in accessible local control panels wherever
possible. 3. The mechanical contractor shall install all in-line devices such as temperature
wells, pressure taps, airflow stations, etc. 4. Input Flow Measuring Devices shall be installed in strict compliance with ASME
guidelines affecting non-standard approach conditions. 5. Outside Air Sensors
a. Sensors shall be mounted on the North wall to minimize solar radiant heat impact or located in a continuous intake flow adequate to monitor outside air conditions accurately.
b. Sensors shall be installed with a rain proof, perforated cover. 6. Water Differential Pressure Sensors
a. Differential pressure transmitters used for flow measurement shall be sized to the flow-sensing device.
b. Differential pressure transmitters shall be supplied with tee fittings and shut-off valves in the high and low sensing pick-up lines.
c. The transmitters shall be installed in an accessible location wherever possible.
7. Medium to High Differential Water Pressure Applications (Over 21” w.c.): a. Air bleed units, bypass valves and compression fittings shall be provided.
8. Building Differential Air Pressure Applications (-1” to +1” w.c.): a. Transmitters exterior sensing tip shall be installed with a shielded static air
probe to reduce pressure fluctuations caused by wind. b. The interior tip shall be inconspicuous and located as shown on the
drawings. 9. Air Flow Measuring Stations:
a. Where the stations are installed in insulated ducts, the airflow passage of the station shall be the same size as the inside airflow dimension of the duct.
b. Station flanges shall be two inch to three inch to facilitate matching connecting ductwork.
10. Duct Temperature Sensors:
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-42 Project Title Revised January 18, 2016 A-xxxxxx
a. Duct mount sensors shall mount in an electrical box through a hole in the duct and be positioned so as to be easily accessible for repair or replacement.
b. The sensors shall be insertion type and constructed as a complete assembly including lock nut and mounting plate.
c. For ductwork greater in any dimension than 48 inches or where air temperature stratification exists such as a mixed air plenum, utilize an averaging sensor.
d. The sensor shall be mounted to suitable supports using factory approved element holders.
11. Space Sensors: a. Shall be mounted per ADA requirements, or as stated on project drawings. b. Provide lockable tamper-proof covers in public areas and/or where
indicated on the plans. 12. Low Temperature Limit Switches:
a. Install on the discharge side of the first water or steam coil in the air stream. b. Mount element horizontally across duct in a serpentine pattern insuring
each square foot of coil is protected by 1 foot of sensor. c. For large duct areas where the sensing element does not provide full
coverage of the air stream, provide additional switches as required to provide full protection of the air stream.
13. Air Differential Pressure Status Switches: a. Install with static pressure tips, tubing, fittings, and air filter.
14. Water Differential Pressure Status Switches: a. Install with shut off valves for isolation.
I. HVAC Output Devices 1. All output devices shall be installed per the manufacturers recommendation. The
mechanical contractor shall install all in-line devices such as control valves, dampers, airflow stations, pressure wells, etc.
2. Actuators: All control actuators shall be sized capable of closing against the maximum system shut-off pressure. The actuator shall modulate in a smooth fashion through the entire stroke. When any pneumatic actuator is sequenced with another device, pilot positioners shall be installed to allow for proper sequencing.
3. Control Dampers: Shall be opposed blade for modulating control of airflow. Parallel blade dampers shall be installed for two position applications.
4. Control Valves: Shall be sized for proper flow control with equal percentage valve plugs. The maximum pressure drop for water applications shall be 5 PSI. The maximum pressure drop for steam applications shall be 7 PSI.
5. Electronic Signal Isolation Transducers: Whenever an analog output signal from the Building Automation Controls System is to be connected to an external control system as an input (such as a chiller control panel), or is to receive as an input a signal from a remote system, provide a signal isolation transducer. Signal isolation transducer shall provide ground plane isolation between systems. Signals shall provide optical isolation between systems.
3.3 Project Acceptance
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-43 Project Title Revised January 18, 2016 A-xxxxxx
A. The BACS contractor shall have all control points operating and viewable on the campus Metasys or Automated Logic WebCTRL system at substantial completion: 1. Provide a document containing “screen captures” of all the Metasys or WebCTRL
views of every piece of HVAC equipment including, but not limited to, chillers, cooling towers, pumps, air handling units, and terminal boxes. Two hard copies and one electronic copy shall be provided to Owner.
2. Provide “first draft” of current as-built submittals to the Owner no later than substantial completion date. One hard copy and one electronic copy. Final comprehensive as-built submittals shall be routed per the usual project process.
3. Complete graphics in timely fashion to facilitate building maintenance. Deliver to Owner at the same time as the project Cx report (by others).
3.4 Training
A. The BACS contractor shall provide the following training services: 1. One day ( 8 hours or as determined by project requirements) of on-site orientation
by a system technician who is fully knowledgeable of the specific installation details of the project. This orientation shall, at a minimum, consist of a review of the project as-built drawings, the BACS software layout and naming conventions, and a walk through of the facility to identify panel and device locations.
a. System technician shall demonstrate the operation of each air handling unit control device and conformance to the project sequence of operation. b. Demonstration shall be coordinated with project commissioning agent.
3.5 Commissioning
A. Fully test all aspects of the Building Automation Controls System work. B. Acceptance Check Sheet
1. Prepare a check sheet that includes all points for all functions of the BACS as indicated on the point list included in the contract documents.
2. Submit the check sheet to the Engineer for approval 3. The Engineer will use the check sheet or other means as the basis for acceptance of
the BACS system. C. VAV box performance verification and documentation:
1. The BACS Contractor shall test each VAV box for operation and correct flow. D. Promptly rectify all listed deficiencies and submit to the Engineer that this has been done. E. Coordination with project commissioning (Cx) agent:
1. Provide allowance for assistance with project Cx agent. 2. Provide copies of all acceptance check sheets and VAV box verification. 3. Provide “first draft” of current as-built submittals to the Cx agent no later than substantial completion date.
3.6 Sequences of operation and points lists
A. Per construction documents. B. Zone setpoints shall be 69 degrees (winter) and 76 degrees (summer) (adjustable) for
non-research spaces. Winter and Summer zone setpoints shall be created for all systems.
BUILDING AUTOMATION CONTROLS SYSTEM
University of Kansas 230900-44 Project Title Revised January 18, 2016 A-xxxxxx
C. The A/E shall consult with Owner for zone setpoints in research or other specialized occupancies.
END OF SECTION 230900
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ACS
OL-C
Autocalibration Solenoid C
omm
andB
LR5IS
OV-S
Boiler 5 Isolation Valve S
tatusB
P6-S
Boiler P
ump 6 S
tatusC
H3C
W-F
Chiller 3 C
W Flow
CH
6-MS
Chiller 6 M
aint Sw
CLG
FBD
-OC
oog
ace &
ypass a
pe
Output
CT3-S
Tower 3 S
tatusC
T7LVL-ATow
er 7 Level AlarmC
WP
8-BA
Con W
ater Pum
p 8 Belt Alarm
BLD
G-L
Building Load
BLR
5-LOB
oiler 5 Lockout Sw
itchB
P7-C
Boiler P
ump 7 C
omm
andC
H3C
W-FS
Chiller 3 C
W Flow
Sw
itchC
H6-S
Chiller 6 S
tatusC
LG-O
Cooling O
utputC
T3VIB-A
Tower 3 Vibration Alarm
CT7LVL-S
Tower 7 Level S
tatusC
WP
8-CC
on Water P
ump 8 C
omm
and
BLD
G-P
Building S
tatic Pressure
BLR
5LW-T
Boiler 5 Leaving W
ater Temperature
BP
7-SB
oiler Pum
p 7 Status
V-C
Com
mand
CH
6SP
-OC
hiller 6 Setpoint O
utputC
LG-O
Cooling O
utputC
T4-BA
Tower 4 B
elt AlarmC
T7MU
V-CTow
er 7 MU
Valve Com
mand
CW
P8-LO
Con W
ater Pum
p 8 Lockout Sw
itch
BLR
1-AB
oiler 1 AlarmB
LR5-M
SB
oiler 5 Maint S
wB
P8-C
Boiler P
ump 8 C
omm
andC
3CS
OV-S
Ce
3 C so
ato
ae
Status
CH
7-%FLA
Chiller 7 P
ercent FLAC
OC
Com
bustion Dam
per Com
mand
CT4B
H-E
NTow
er 4 Basin H
eater Enable
CT7-O
Tower 7 O
utputC
WP
8-OL
Con W
ater Pum
p 8 Overload
BLR
1-CB
oiler 1 Com
mand
BLR
5-OB
oiler 5 Output
BP
8-SB
oiler Pum
p 8 Status
CH
3CW
L-T
g Tem
peratureC
H7-A
Chiller 7 Alarm
SC
ombustion D
amper S
tatusC
T4BS
N-T
Tower 4 B
asin Temperature
CT7-O
LTow
er 7 Overload
CW
P8-S
Con W
ater Pum
p 8 Status
BLR
1-EN
Boiler 1 E
nableB
LR5-S
Boiler 5 S
tatusB
YP
V-OB
ypass Valve Output
CH
3-EN
Chiller 3 E
nableC
H7-AM
PS
Chiller 7 Am
psC
OM
P1-C
Com
pressor Stage 1 C
omm
andC
T4BS
N-TS
Tower 4 B
asin Temp S
tatusC
T7-STow
er 7 Status
CW
R-T
Con W
ater Return Tem
perature
BLR
1EW
-TB
oiler 1 Entering W
ater Temperature
BLR
5SP
-OB
oiler 5 Setpoint O
utputC
D-F
Cold D
eck FlowC
H3-M
SC
hiller 3 Maint S
wC
H7C
HW
E-T
Chiller 7 C
HW
Entering Tem
peratureC
OM
P2-C
Com
pressor Stage 2 C
omm
andC
T4-CTow
er 4 Com
mand
CT7VIB
-ATow
er 7 Vibration AlarmC
WS
-TC
on Water S
upply Temperature
BLR
1-FSB
oiler 1 Flow S
witch
BLR
6-AB
oiler 6 AlarmC
D-O
Cold D
eck Dam
per Output
CH
3-SC
hiller 3 Status
CH
7CH
W-F
Chiller 7 C
HW
FlowC
P-C
Cooling P
ump C
omm
andC
T4-FAULT
Tower 4 VFD
FaultC
T8-BA
Tower 8 B
elt AlarmD
A1-PD
ischarge Air Static P
ressure 1
BLR
1HT-A
Boiler 1 H
igh Temperature Alarm
BLR
6-CB
oiler 6 Com
mand
CD
-OC
old Deck D
amper O
utputC
H3S
P-O
Chiller 3 S
etpoint Output
CH
7CH
W-FS
Chiller 7 C
HW
Flow S
witch
CP
-LOC
ooling Pum
p Lockout Sw
itchC
T4H-C
Tower 4 H
I Com
mand
CT8B
H-E
NTow
er 8 Basin H
eater Enable
DA2-P
Discharge Air S
tatic Pressure 2
BLR
1ISO
V-CB
oiler 1 Isolation Valve Com
mand
BLR
6-EN
Boiler 6 E
nableC
D-O
Cold D
eck Dam
per Output
CH
4-%FLA
Chiller 4 P
ercent FLAC
CS
OV-C
Ce
C
soato
a
e C
omm
andC
P-O
LC
ooling Pum
p Overload
CT4IS
OV-C
Tower 4 Iso Valve C
omm
andC
T8BS
N-T
Tower 8 B
asin Temperature
DA-F
Discharge Air Flow
BLR
1ISO
V-SB
oiler 1 Isolation Valve Status
BLR
6EW
-TB
oiler 6 Entering W
ater Temperature
CD
-PC
old Deck S
tatic Pressure
CH
4-AC
hiller 4 AlarmO
V-SC
hiller 7 CH
W Isolation Valve S
tatusC
P-S
Cooling P
ump S
tatusC
T4ISO
V-STow
er 4 Iso Valve Status
CT8B
SN
-TSTow
er 8 Basin Tem
p Status
DA-H
Discharge Air H
umidity
BLR
1-LOB
oiler 1 Lockout Sw
itchB
LR6-FS
Boiler 6 Flow
Sw
itchC
D-T
Cold D
eck Temperature
CH
4-AMP
SC
hiller 4 Amps
CH
7CH
WL-T
Chiller 7 C
HW
Leaving Temperature
CT1-B
ATow
er 1 Belt Alarm
CT4L-C
Tower 4 LO
Com
mand
CT8-C
Tower 8 C
omm
andD
APH
I-AD
ischarge Air High D
uct Pressure
BLR
1LW-T
Boiler 1 Leaving W
ater Temperature
BLR
6HT-A
Boiler 6 H
igh Temperature Alarm
CD
-VPC
old Deck Velocity P
ressureC
CT
Ce
C
te
g Tem
peratureC
H7C
L-OC
hiller 7 Current Lim
it Output
CT1B
H-E
NTow
er 1 Basin H
eater Enable
CT4-LO
Tower 4 Lockout S
witch
CT8-FAU
LTTow
er 8 VFD Fault
DA-Q
Discharge Air Q
uality
BLR
1-MS
Boiler 1 M
aint Sw
BLR
6ISO
V-CB
oiler 6 Isolation Valve Com
mand
CD
-VPC
old Deck Velocity P
ressureC
H4C
HW
-FC
hiller 4 CH
W Flow
CH
7CW
E-T
Chiller 7 C
W E
ntering Temperature
CT1B
SN
-TTow
er 1 Basin Tem
peratureC
T4LVL-ATow
er 4 Level AlarmC
T8ISO
V-CTow
er 8 Iso Valve Com
mand
DA-S
DD
ischarge Air Sm
oke Alarm
BLR
1-OB
oiler 1 Output
BLR
6ISO
V-SB
oiler 6 Isolation Valve Status
CD
-VPC
old Deck Velocity P
ressureFS
Chiller 4 C
HW
Flow S
witch
CH
7CW
-FC
hiller 7 CW
FlowC
T1BS
N-TS
Tower 1 B
asin Temp S
tatusC
T4LVL-STow
er 4 Level Status
CT8IS
OV-S
Tower 8 Iso Valve S
tatusD
A-TD
ischarge Air Temperature
BLR
1-SB
oiler 1 Status
BLR
6-LOB
oiler 6 Lockout Sw
itchC
H1-%
FLAC
hiller 1 Percent FLA
CC
SO
V-CC
e
C so
ato
ae
Com
mand
CH
7CW
-FSC
hiller 7 CW
Flow S
witch
CT1-C
Tower 1 C
omm
andC
T4M-C
Tower 4 M
ED
Com
mand
CT8-LO
Tower 8 Lockout S
witch
DA-VP
Discharge Air Velocity P
ressure
BLR
1SP
-OB
oiler 1 Setpoint O
utputB
LR6LW
-TB
oiler 6 Leaving Water Tem
peratureC
H1-A
Chiller 1 Alarm
OV-S
S
tatusC
Chiller 7 C
W Isolation Valve C
omm
andC
T1-FAULT
Tower 1 VFD
FaultC
T4MU
V-CTow
er 4 MU
Valve Com
mand
CT8LVL-A
Tower 8 Level Alarm
DA-VP
Discharge Air Velocity P
ressure
BLR
2-AB
oiler 2 AlarmB
LR6-M
SB
oiler 6 Maint S
wC
H1-AM
PS
Chiller 1 Am
psC
H4C
HW
L-T
g Tem
peratureS
Chiller 7 C
W Isolation Valve S
tatusC
T1H-C
Tower 1 H
I Com
mand
CT4-O
Tower 4 O
utputC
T8LVL-STow
er 8 Level Status
DA-VP
Discharge Air Velocity P
ressure
BLR
2-CB
oiler 2 Com
mand
BLR
6-OB
oiler 6 Output
CH
1CH
WE
-TC
hiller 1 CH
W E
ntering Temperature
CH
4CL-O
Chiller 4 C
urrent Limit O
utputC
H7C
WL-T
Chiller 7 C
W Leaving Tem
peratureC
T1ISO
V-CTow
er 1 Iso Valve Com
mand
CT4-O
LTow
er 4 Overload
CT8M
UV-C
Tower 8 M
U Valve C
omm
andD
CP
L-FD
ecouple Loop Flow
BLR
2-EN
Boiler 2 E
nableB
LR6-S
Boiler 6 S
tatusC
H1C
HW
-FC
hiller 1 CH
W Flow
CH
4CW
E-T
g
Temperature
CH
7-EN
Chiller 7 E
nableC
T1ISO
V-STow
er 1 Iso Valve Status
CT4-S
Tower 4 S
tatusC
T8-OTow
er 8 Output
DC
PL-S
Decouple Loop D
irection
BLR
2EW
-TB
oiler 2 Entering W
ater Temperature
BLR
6SP
-OB
oiler 6 Setpoint O
utputC
H1C
HW
-FSC
hiller 1 CH
W Flow
Sw
itchC
H4C
W-F
Chiller 4 C
W Flow
CH
7-MS
Chiller 7 M
aint Sw
CT1L-C
Tower 1 LO
Com
mand
CT4VIB
-ATow
er 4 Vibration AlarmC
T8-OL
Tower 8 O
verloadD
CP
L-TD
ecouple Loop Temperature
BLR
2-FSB
oiler 2 Flow S
witch
BLR
7-AB
oiler 7 AlarmC
H1C
HW
ISO
V-CC
hiller 1 CH
W Isolation Valve C
omm
andC
H4C
W-FS
Chiller 4 C
W Flow
Sw
itchC
H7-S
Chiller 7 S
tatusC
T1-LOTow
er 1 Lockout Sw
itchC
T5-BA
Tower 5 B
elt AlarmC
T8-STow
er 8 Status
DP
R-O
Supply Air D
amper O
utput
BLR
2HT-A
Boiler 2 H
igh Temperature Alarm
BLR
7-CB
oiler 7 Com
mand
CH
1CH
WIS
OV-S
Chiller 1 C
HW
Isolation Valve Status
V-C
Com
mand
CH
7SP
-OC
hiller 7 Setpoint O
utputC
T1LVL-ATow
er 1 Level AlarmC
T5BH
-EN
Tower 5 B
asin Heater E
nableC
T8VIB-A
Tower 8 Vibration Alarm
DP
R-O
Supply Air D
amper O
utput
BLR
2ISO
V-CB
oiler 2 Isolation Valve Com
mand
BLR
7-EN
Boiler 7 E
nableC
H1C
HW
L-TC
hiller 1 CH
W Leaving Tem
peratureV-S
S
tatusC
H8-%
FLAC
hiller 8 Percent FLA
CT1LVL-S
Tower 1 Level S
tatusC
T5BS
N-T
Tower 5 B
asin Temperature
CTB
H-E
NTow
er Basin H
eater Enable
DP
R-O
Supply Air D
amper O
utput
BLR
2ISO
V-SB
oiler 2 Isolation Valve Status
BLR
7EW
-TB
oiler 7 Entering W
ater Temperature
CH
1CL-O
Chiller 1 C
urrent Limit O
utputC
H4C
WL-T
Ce
C
ea
g Tem
peratureC
H8-A
Chiller 8 Alarm
CT1M
-CTow
er 1 ME
D C
omm
andC
T5BS
N-TS
Tower 5 B
asin Temp S
tatusC
TLVL-ATow
er Level AlarmE
AD-C
Exhaust Air D
amper C
omm
and
BLR
2-LOB
oiler 2 Lockout Sw
itchB
LR7-FS
Boiler 7 Flow
Sw
itchC
H1C
WE
-TC
hiller 1 CW
Entering Tem
peratureC
H4-E
NC
hiller 4 Enable
CH
8-AMP
SC
hiller 8 Amps
CT1M
UV-C
Tower 1 M
U Valve C
omm
andC
T5-CTow
er 5 Com
mand
CTLVL-S
Tower Level S
tatusE
AD-O
Exhaust Air D
amper O
utput
BLR
2LW-T
Boiler 2 Leaving W
ater Temperature
BLR
7HT-A
Boiler 7 H
igh Temperature Alarm
CH
1CW
-FC
hiller 1 CW
FlowC
H4-M
SC
hiller 4 Maint S
wC
H8C
HW
E-T
Chiller 8 C
HW
Entering Tem
peratureC
T1-OTow
er 1 Output
CT5-FAU
LTTow
er 5 VFD Fault
CTM
UV-C
Tower M
U Valve C
omm
andE
AD-O
Exhaust Air D
amper O
utput
BLR
2-MS
Boiler 2 M
aint Sw
BLR
7ISO
V-CB
oiler 7 Isolation Valve Com
mand
CH
1CW
-FSC
hiller 1 CW
Flow S
witch
CH
4-SC
hiller 4 Status
CH
8CH
W-F
Chiller 8 C
HW
FlowC
T1-OL
Tower 1 O
verloadC
T5H-C
Tower 5 H
I Com
mand
CT-T
Tower B
asin Temperature
EA-F
Exhaust Air Flow
BLR
2-OB
oiler 2 Output
BLR
7ISO
V-SB
oiler 7 Isolation Valve Status
CH
1CW
ISO
V-CC
hiller 1 CW
Isolation Valve Com
mand
CH
4SP
-OC
hiller 4 Setpoint O
utputC
H8C
HW
-FSC
hiller 8 CH
W Flow
Sw
itchC
T1-STow
er 1 Status
CT5IS
OV-C
Tower 5 Iso Valve C
omm
andC
T-TSTow
er Basin Tem
perature Sw
itchE
A-HE
xhaust Air Hum
idity
BLR
2-SB
oiler 2 Status
BLR
7-LOB
oiler 7 Lockout Sw
itchC
H1C
WIS
OV-S
Chiller 1 C
W Isolation Valve S
tatusC
H5-%
FLAC
hiller 5 Percent FLA
OV-C
C
omm
andC
T1VIB-A
Tower 1 Vibration Alarm
CT5IS
OV-S
Tower 5 Iso Valve S
tatusC
TV-OTow
er Valve Output
EAH
R-T
Exhaust Air H
eat Recovery Tem
p
BLR
2SP
-OB
oiler 2 Setpoint O
utputB
LR7LW
-TB
oiler 7 Leaving Water Tem
peratureC
H1C
WL-T
Chiller 1 C
W Leaving Tem
peratureC
H5-A
Chiller 5 Alarm
C8C
SO
V-SC
hiller 8 CH
W Isolation Valve S
tatusC
T2-BA
Tower 2 B
elt AlarmC
T5L-CTow
er 5 LO C
omm
andC
W-F
Condenser W
ater FlowE
A-PE
xhaust Air Static P
ressure
BLR
3-AB
oiler 3 AlarmB
LR7-M
SB
oiler 8 Maint S
wC
H1-E
NC
hiller 1 Enable
CH
5-AMP
SC
hiller 5 Amps
CH
8CH
WL-T
Chiller 8 C
HW
Leaving Temperature
CT2B
H-E
NTow
er 2 Basin H
eater Enable
CT5-LO
Tower 5 Lockout S
witch
CW
P1-B
A
p
AlarmE
APLO
-AE
xhaust Air Low D
uct Pressure
BLR
3-CB
oiler 3 Com
mand
BLR
7-OB
oiler 7 Output
CH
1-MS
Chiller 1 M
aint Sw
T
g Tem
peratureC
H8C
L-OC
hiller 8 Current Lim
it Output
CT2B
SN
-TTow
er 2 Basin Tem
peratureC
T5LVL-ATow
er 5 Level AlarmC
WP
1-C
p
C
omm
andE
A-QE
xhaust Air Quality
BLR
3-EN
Boiler 3 E
nableB
LR7-S
Boiler 7 S
tatusC
H1-S
Chiller 1 S
tatusC
H5C
HW
-FC
hiller 5 CH
W Flow
CH
8CW
E-T
Chiller 8 C
W E
ntering Temperature
CT2B
SN
-TSTow
er 2 Basin Tem
p Status
CT5LVL-S
Tower 5 Level S
tatusC
WP
1-LOC
ode
se
ate
up
oc
out S
witch
EA-S
DE
xhaust Air Sm
oke Alarm
BLR
3EW
-TB
oiler 3 Entering W
ater Temperature
BLR
7SP
-OB
oiler 7 Setpoint O
utputC
H1S
P-O
Chiller 1 S
etpoint Output
FSC
hiller 5 CH
W Flow
Sw
itchC
H8C
W-F
Chiller 8 C
W Flow
CT2-C
Tower 2 C
omm
andC
T5MU
V-CTow
er 5 MU
Valve Com
mand
CW
P1-O
LC
ondenser Water P
ump 1 O
verloadE
A-TE
xhaust Air Temperature
BLR
3-FSB
oiler 3 Flow S
witch
BLR
8-AB
oiler 8 AlarmC
H2-%
FLAC
hiller 2 Percent FLA
OV-C
e C
omm
andC
H8C
W-FS
Chiller 8 C
W Flow
Sw
itchC
T2-FAULT
Tower 2 VFD
FaultC
T5-OTow
er 5 Output
CW
P1-S
Condenser W
ater Pum
p 1 Status
EA-VP
Exhaust Air Velocity P
ressure
BLR
3HT-A
Boiler 3 H
igh Temperature Alarm
BLR
8-CB
oiler 8 Com
mand
CH
2-AC
hiller 2 AlarmC
5CS
OV-S
Ce
5 C so
ato
ae
Status
C8C
SO
CC
hiller 8 CW
Isolation Valve Com
mand
CT2H
-CTow
er 2 HI C
omm
andC
T5-OL
Tower 5 O
verloadC
WP
2-BA
Co
dese
ate
u
p
et
AlarmE
A-VPE
xhaust Air Velocity Pressure
BLR
3ISO
V-CB
oiler 3 Isolation Valve Com
mand
BLR
8-EN
Boiler 8 E
nableC
H2-AM
PS
Chiller 2 Am
psC
H5C
HW
L-T
g Tem
peratureS
Chiller 8 C
W Isolation Valve S
tatusC
T2ISO
V-CTow
er 2 Iso Valve Com
mand
CT5-S
Tower 5 S
tatusC
WP
2-C
p
C
omm
andE
CO
N-C
Econom
izer Enable C
omm
and
BLR
3ISO
V-SB
oiler 3 Isolation Valve Status
BLR
8EW
-TB
oiler 8 Entering W
ater Temperature
CH
2CH
WE
-TC
hiller 2 CH
W E
ntering Temperature
CH
5CL-O
Chiller 5 C
urrent Limit O
utputC
H8C
WL-T
Chiller 8 C
W Leaving Tem
peratureC
T2ISO
V-STow
er 2 Iso Valve Status
CT5VIB
-ATow
er 5 Vibration AlarmC
WP
2-LO
p
Sw
itchE
CO
N-E
NE
conomizer E
nable
BLR
3-LOB
oiler 3 Lockout Sw
itchB
LR8-FS
Boiler 8 Flow
Sw
itchC
H2C
HW
-FC
hiller 2 CH
W Flow
CH
5CW
E-T
Ce
5 C
teg
Temperature
CH
8-EN
Chiller 8 E
nableC
T2L-CTow
er 2 LO C
omm
andC
T6-BA
Tower 6 B
elt AlarmC
WP
2-OL
Condenser W
ater Pum
p 2 Overload
EF-A
Exhaust Fan Alarm
BLR
3LW-T
Boiler 3 Leaving W
ater Temperature
BLR
8HT-A
Boiler 8 H
igh Temperature Alarm
CH
2CH
W-FS
Chiller 2 C
HW
Flow S
witch
CH
5CW
-FC
hiller 5 CW
FlowC
H8-M
SC
hiller 8 Maint S
wC
T2-LOTow
er 2 Lockout Sw
itchC
T6BH
-EN
Tower 6 B
asin Heater E
nableC
WP
2-SC
ondenser Water P
ump 2 S
tatusE
F-BA
Exhaust Fan B
elt Alarm
BLR
3-MS
Boiler 4 M
aint Sw
BLR
8ISO
V-CB
oiler 8 Isolation Valve Com
mand
CH
2CH
WIS
OV-C
Chiller 2 C
HW
Isolation Valve Com
mand
CH
5CW
-FSC
hiller 5 CW
Flow S
witch
CH
8-SC
hiller 8 Status
CT2LVL-A
Tower 2 Level Alarm
CT6B
SN
-TTow
er 6 Basin Tem
peratureC
WP
3-BA
Co
dese
ate
u
p 3 e
t Alarm
EF-C
Exhaust Fan C
omm
and
BLR
3-OB
oiler 3 Output
BLR
8ISO
V-SB
oiler 8 Isolation Valve Status
CH
2CH
WIS
OV-S
Chiller 2 C
HW
Isolation Valve Status
C5C
SO
V-CC
e 5 C
soato
a
e C
omm
andC
H8S
P-O
Chiller 8 S
etpoint Output
CT2LVL-S
Tower 2 Level S
tatusC
T6BS
N-TS
Tower 6 B
asin Temp S
tatusC
WP
3-CC
ode
se
ate
up 3
Com
mand
EF-C
Exhaust Fan C
omm
and
BLR
3-SB
oiler 3 Status
BLR
8-LOB
oiler 8 Lockout Sw
itchC
H2C
HW
L-TC
hiller 2 CH
W Leaving Tem
peratureV-S
S
tatusC
HLR
1-LOC
hiller 1 Lockout Sw
itchC
T2M-C
Tower 2 M
ED
Com
mand
CT6-C
Tower 6 C
omm
andC
WP
3-LO
p
Sw
itchE
F-LOE
xhaust Fan Lockout Sw
itch
BLR
3SP
-OB
oiler 3 Setpoint O
utputB
LR8LW
-TB
oiler 8 Leaving Water Tem
peratureC
H2C
L-OC
hiller 2 Current Lim
it Output
CH
5CW
L-T
g Tem
peratureC
HLR
2-LOC
hiller 2 Lockout Sw
itchC
T2MU
V-CTow
er 2 MU
Valve Com
mand
CT6-FAU
LTTow
er 6 VFD Fault
CW
P3-O
LC
ondenser Water P
ump 3 O
verloadE
F-OE
xhaust Fan Output
BLR
4-AB
oiler 4 AlarmB
LR8-M
SB
oiler 7 Maint S
wC
H2C
WE
-TC
hiller 2 CW
Entering Tem
peratureC
H5-E
NC
hiller 5 Enable
CH
LR3-LO
Chiller 3 Lockout S
witch
CT2-O
Tower 2 O
utputC
T6H-C
Tower 6 H
I Com
mand
CW
P3-S
Condenser W
ater Pum
p 3 Status
EF-O
LE
xhaust Fan Overload
BLR
4-CB
oiler 4 Com
mand
BLR
8-OB
oiler 8 Output
CH
2CW
-FC
hiller 2 CW
FlowC
H5-M
SC
hiller 5 Maint S
wC
HLR
4-LOC
hiller 4 Lockout Sw
itchC
T2-OL
Tower 2 O
verloadC
T6ISO
V-CTow
er 6 Iso Valve Com
mand
CW
P4-B
A
p
AlarmE
F-SE
xhaust Fan Status
BLR
4-EN
Boiler 4 E
nableB
LR8-S
Boiler 8 S
tatusC
H2C
W-FS
Chiller 2 C
W Flow
Sw
itchC
H5-S
Chiller 5 S
tatusC
HLR
5-LOC
hiller 5 Lockout Sw
itchC
T2-STow
er 2 Status
CT6IS
OV-S
Tower 6 Iso Valve S
tatusC
WP
4-C
p
C
omm
andE
HO
-SE
nergy Hold O
ff Toggle Sw
itch
BLR
4EW
-TB
oiler 4 Entering W
ater Temperature
BLR
8SP
-OB
oiler 8 Setpoint O
utputC
H2C
WIS
OV-C
Chiller 2 C
W Isolation Valve C
omm
andC
H5S
P-O
Chiller 5 S
etpoint Output
CH
LR6-LO
Chiller 6 Lockout S
witch
CT2VIB
-ATow
er 2 Vibration AlarmC
T6L-CTow
er 6 LO C
omm
andC
WP
4-LOC
ode
se
ate
up
oc
out S
witch
FBD
-OFace &
Bypass D
amper O
utput
BLR
4-FSB
oiler 4 Flow S
witch
BO
1-SP
ARE
Binary O
utput Spare 1
CH
2CW
ISO
V-SC
hiller 2 CW
Isolation Valve Status
CH
6-%FLA
Chiller 6 P
ercent FLAC
HLR
7-LOC
hiller 7 Lockout Sw
itchC
T3-BA
Tower 3 B
elt AlarmC
T6-LOTow
er 6 Lockout Sw
itchC
WP
4-OL
Condenser W
ater Pum
p 4 Overload
FBD
-OFace &
Bypass D
amper O
utput
BLR
4HT-A
Boiler 4 H
igh Temperature Alarm
BO
2-SP
ARE
Binary O
utput Spare 2
CH
2CW
L-TC
hiller 2 CW
Leaving Temperature
CH
6-AC
hiller 6 AlarmC
HLR
8-LOC
hiller 8 Lockout Sw
itchC
T3BH
-EN
Tower 3 B
asin Heater E
nableC
T6LVL-ATow
er 6 Level AlarmC
WP
4-SC
ondenser Water P
ump 4 S
tatusFC
BO
-SFan C
ontrol By O
thers Status
BLR
4ISO
V-CB
oiler 4 Isolation Valve Com
mand
BO
3-SP
ARE
Binary O
utput Spare 3
CH
2-EN
Chiller 2 E
nableC
H6-AM
PS
Chiller 6 Am
psCO
Chilled W
ater Bypass Valve O
utputC
T3BS
N-T
Tower 3 B
asin Temperature
CT6LVL-S
Tower 6 Level S
tatusC
WP
5-BA
Co
dese
ate
u
p 5 e
t Alarm
FFILT-DP
Final Filter Diff P
ressure
BLR
4ISO
V-SB
oiler 4 Isolation Valve Status
BO
4-SP
ARE
Binary O
utput Spare 4
CH
2-MS
Chiller 2 M
aint Sw
T
g Tem
peratureC
HW
-DP
Chill W
ater Differential P
ressureC
T3BS
N-TS
Tower 3 B
asin Temp S
tatusC
T6MU
V-CTow
er 6 MU
Valve Com
mand
CW
P5-C
p
Com
mand
FFILT-SFinal Filter S
tatus
BLR
4-LOB
oiler 4 Lockout Sw
itchB
O5-S
PAR
EB
inary Output S
pare 5C
H2-S
Chiller 2 S
tatusC
H6C
HW
-FC
hiller 6 CH
W Flow
CH
WE
-TC
hilled Water E
ntering Temperature
CT3-C
Tower 3 C
omm
andC
T6-OTow
er 6 Output
CW
P5-LO
p
S
witch
FILT-SFilter S
tatus
BLR
4LW-T
Boiler 4 Leaving W
ater Temperature
BO
6-SP
ARE
Binary O
utput Spare 6
CH
2SP
-OC
hiller 2 Setpoint O
utputC
6CFS
Chiller 6 C
HW
Flow S
witch
CH
WL-T
Chilled W
ater Leaving Temperature
CT3-FAU
LTTow
er 3 VFD Fault
CT6-O
LTow
er 6 Overload
CW
P5-O
LC
ondenser Water P
ump 5 O
verloadG
EF-C
General E
xhaust Fan Com
mand
BLR
4-MS
Boiler 3 M
aint Sw
BP
1-CB
oiler Pum
p 1 Com
mand
CH
3-%FLA
Chiller 3 P
ercent FLAO
V-C
Com
mand
CLG
1-CC
ooling Stage 1 C
omm
andC
T3H-C
Tower 3 H
I Com
mand
CT6-S
Tower 6 S
tatusC
WP
5-SC
ondenser Water P
ump 5 S
tatusG
EF-LO
General E
xh Fan Lockout Sw
ch
BLR
4-OB
oiler 4 Output
BP
1-SB
oiler Pum
p 1 Status
CH
3-AC
hiller 3 AlarmO
V-S
Status
CLG
2-CC
ooling Stage 2 C
omm
andC
T3ISO
V-CTow
er 3 Iso Valve Com
mand
CT6VIB
-ATow
er 6 Vibration AlarmC
WP
6-BA
p
Alarm
GE
F-OL
General E
xhaust Fan Overload
BLR
4-SB
oiler 4 Status
BP
2-CB
oiler Pum
p 2 Com
mand
CH
3-AMP
SC
hiller 3 Amps
CH
6CH
WL-T
Ce
6 C
eag
Temperature
CLG
3-CC
ooling Stage 3 C
omm
andC
T3ISO
V-STow
er 3 Iso Valve Status
CT7-B
ATow
er 7 Belt Alarm
CW
P6-C
Co
dese
ate
u
p 6 C
omm
andG
EF-S
General E
xhaust Fan Status
BLR
4SP
-OB
oiler 4 Setpoint O
utputB
P2-S
Boiler P
ump 2 S
tatusC
H3C
HW
E-T
Chiller 3 C
HW
Entering Tem
peratureC
H6C
L-OC
hiller 6 Current Lim
it Output
CLG
4-CC
ooling Stage 4 C
omm
andC
T3L-CTow
er 3 LO C
omm
andC
T7BH
-EN
Tower 7 B
asin Heater E
nableC
WP
6-LOC
on Water P
ump 6 Lockout S
witch
GLY
-TG
lycol Temperature
BLR
5-AB
oiler 5 AlarmB
P3-C
Boiler P
ump 3 C
omm
andC
H3C
HW
-FC
hiller 3 CH
W Flow
CH
6CW
E-T
g
Temperature
CLG
5-CC
ooling Stage 5 C
omm
andC
T3-LOTow
er 3 Lockout Sw
itchC
T7BS
N-T
Tower 7 B
asin Temperature
CW
P6-O
LC
on Water P
ump 6 O
verloadH
C-C
Heating/C
ooling Com
mand
BLR
5-CB
oiler 5 Com
mand
BP
3-SB
oiler Pum
p 3 Status
CH
3CH
W-FS
Chiller 3 C
HW
Flow S
witch
CH
6CW
-FC
hiller 6 CW
FlowC
LG6-C
Cooling S
tage 6 Com
mand
CT3LVL-A
Tower 3 Level Alarm
CT7B
SN
-TSTow
er 7 Basin Tem
p Status
CW
P6-S
Con W
ater Pum
p 6 Status
HC
-CH
eating/Cooling C
omm
and
BLR
5-EN
Boiler 5 E
nableB
P4-C
Boiler P
ump 4 C
omm
andC
H3C
HW
ISO
V-CC
hiller 3 CH
W Isolation Valve C
omm
andC
H6C
W-FS
Chiller 6 C
W Flow
Sw
itchC
LG7-C
Cooling S
tage 7 Com
mand
CT3LVL-S
Tower 3 Level S
tatusC
T7-CTow
er 7 Com
mand
CW
P7-B
AC
on Water P
ump 7 B
elt AlarmH
CFB
D-O
gg
yp
Outp.
BLR
5EW
-TB
oiler 5 Entering W
ater Temperature
BP
4-SB
oiler Pum
p 4 Status
CH
3CH
WIS
OV-S
Chiller 3 C
HW
Isolation Valve Status
V-C
Com
mand
CLG
8-CC
ooling Stage 8 C
omm
andC
T3M-C
Tower 3 M
ED
Com
mand
CT7-FAU
LTTow
er 7 VFD Fault
CW
P7-C
Con W
ater Pum
p 7 Com
mand
HC
FBD
-Og
g
yp
O
utp.
BLR
5-FSB
oiler 5 Flow S
witch
BP
5-CB
oiler Pum
p 5 Com
mand
CH
3CH
WL-T
Chiller 3 C
HW
Leaving Temperature
C6C
SO
V-SC
e 6 C
soato
a
e S
tatusC
LG-C
Cooling C
omm
andC
T3MU
V-CTow
er 3 MU
Valve Com
mand
CT7IS
OV-C
Tower 7 Iso Valve C
omm
andC
WP
7-LOC
on Water P
ump 7 Lockout S
witch
HC
-OH
eating/Cooling O
utput
BLR
5HT-A
Boiler 5 H
igh Temperature Alarm
BP
5-SB
oiler Pum
p 5 Status
CH
3CL-O
Chiller 3 C
urrent Limit O
utputC
H6C
WL-T
g
Temperature
CLG
-CC
ooling Com
mand
CT3-O
Tower 3 O
utputC
T7ISO
V-STow
er 7 Iso Valve Status
CW
P7-O
LC
on Water P
ump 7 O
verloadH
C-O
Heating/C
ooling Output
BLR
5ISO
V-CB
oiler 5 Isolation Valve Com
mand
BP
6-CB
oiler Pum
p 6 Com
mand
CH
3CW
E-T
Chiller 3 C
W E
ntering Temperature
CH
6-EN
Chiller 6 E
nableC
LGFB
D-O
g
yp
p
O
utputC
T3-OL
Tower 3 O
verloadC
T7-LOTow
er 7 Lockout Sw
itchC
WP
7-SC
on Water P
ump 7 S
tatusH
CP
-CH
eating/Cooling P
ump C
omm
and
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
ObjectN
ame
Expanded ID
HC
P-LO
Heating/C
ooling Pum
p Lockout Sw
chH
UM
HI-A
Hum
idity High Lim
itP
CH
WP
3-OL
Prim
ary CH
W P
ump 3 O
verloadP
HW
P3-C
y
p
Com
mand
RLF-S
Relief Fan S
tatusS
F-CS
upply Fan Com
mand
SU
PH
TG-C
Suplm
tl Heating C
md
ZN3-T
Zone3 Temperature
ZN8-TO
CC
Zone8 Temporary O
ccupancy
HC
P-O
LH
eating/Cooling P
ump O
verloadH
UM
-OH
umidifier O
utputP
CH
WP
3-SP
rimary C
HW
Pum
p 3 Status
PH
WP
3-LOy
p
Sw
tchR
LF-VPR
elief Air Velocity Pressure
SFH
-CS
upply Fan HI C
omm
andS
UP
HTG
-OS
upplemental H
eating Output
ZN3-TO
CC
Zone3 Temporary O
ccupancyZN
F-%Fan S
peed Status D
isplay
HC
P-S
Heating/C
ooling Pum
p Status
HU
M-S
Hum
idifier Status
PC
HW
P4-B
AP
rimary C
HW
Pum
p 4 Belt Alarm
PH
WP
3-OL
ay
u
p 3 O
verloadR
O1-S
PAR
ER
elay Output S
pare 1S
FL-CS
upply Fan LO C
omm
andS
UP
HTG
-OS
upplemental H
eating Output
ZN4D
-OZone4 D
amper O
utputZN
F-OZone Fan S
peed
HC
WE
-TH
tg/Clg E
ntering Water Tem
peratureH
W-D
PH
ot Water D
ifferential Pressure
PC
HW
P4-C
Prim
ary CH
W P
ump 4 C
omm
andP
HW
P3-S
Prim
ary HW
Pum
p 3 Status
RO
2-SP
ARE
Relay O
utput Spare 2
SF-LO
Supply Fan Lockout S
witch
SY
S-R
ES
ET
System
Reset
ZN4D
-OZone4 D
amper O
utputZN
-HZone H
umidity
HC
WL-T
Htg/C
lg Leaving Water Tem
peratureH
X1E
W-T
HX
1 Entering W
ater Temperature
PC
HW
P4-LO
Prim
ary CH
W P
ump 4 Lockout S
witch
PH
WP
4-BA
y
p
Alarm
RO
3-SP
ARE
Relay O
utput Spare 3
SFM
-CS
upply Fan ME
D C
omm
andTE
F-CToilet E
xhaust Fan Com
mand
ZN4-H
Zone4 Hum
idityZN
-HZone H
umidity
HD
-FH
ot Deck Flow
HX
1ISO
V-CH
eat Exchanger 1 Isolation Valve C
md
PC
HW
P4-O
LP
rimary C
HW
Pum
p 4 Overload
PH
WP
4-Ca
y
up
C
omm
andR
O4-S
PAR
ER
elay Output S
pare 4S
F-OS
upply Fan Output
TEF-LO
Toilet Exhaust Fan Lockout S
witch
ZN4H
TG1-C
Zone4 Heating S
tage 1 Com
mand
ZN-Q
Zone Quality
HD
-HH
ot Deck H
umidity
HX
1ISO
V-SH
X1 Isolation Valve S
tatusP
CH
WP
4-SP
rimary C
HW
Pum
p 4 Status
PH
WP
4-LOy
p
Sw
tchR
O5-S
PAR
ER
elay Output S
pare 5S
F-OS
upply Fan Output
TEF-O
LToilet E
xhaust Fan Overload
ZN4H
TG2-C
Zone4 Heating S
tage 2 Com
mand
ZN-S
PZone S
etpoint
HD
-OH
ot Deck D
amper O
utputH
X1LW
-TH
X1 Leaving W
ater Temperature
PC
HW
P5-B
AP
rimary C
HW
Pum
p 5 Belt Alarm
PH
WP
4-OL
y
p
Overload
RO
6-SP
ARE
Relay O
utput Spare 6
SF-O
Supply Fan O
utputTE
F-SToilet E
xhaust Fan Status
ZN4H
TG3-C
Zone4 Heating S
tage 3 Com
mand
ZN-T
Zone Temperature
HD
-OH
ot Deck D
amper O
utputH
X1-M
SH
eat Exchanger 1 M
aint Sw
PC
HW
P5-C
Prim
ary CH
W P
ump 5 C
omm
andP
HW
P4-S
Prim
ary HW
Pum
p 4 Status
SA-T
Supply Air Tem
peratureS
F-OL
Supply Fan O
verloadTO
T-VPTotal Velocity P
ressureZN
4HTG
-CZone4 H
eating Com
mand
ZN-TO
CC
Zone Temporary O
ccupancy
HD
-OH
ot Deck D
amper O
utputH
X1V1-O
Heat E
xchanger 1 Valve 1 Output
PC
HW
P5-LO
Prim
ary CH
W P
ump 5 Lockout S
witch
PH
WP
5-BA
y
p
Alarm
SC
HW
-FS
econdary CH
W Flow
SF-S
Supply Fan S
tatusTO
T-VPTotal Velocity P
ressureZN
4HTG
-OZone4 H
eating Output
HD
-PH
ot Deck S
tatic Pressure
HX
1V2-OH
eat Exchanger 1 Valve 2 O
utputP
CH
WP
5-OL
Prim
ary CH
W P
ump 5 O
verloadP
HW
P5-C
y
p
Com
mand
SC
HW
P1-B
AS
ec. CH
W P
ump 1 B
elt AlarmS
F-SS
upply Fan Status
UN
ITEN
-SU
nit Enable Toggle S
witch
ZN4H
TG-O
Zone4 Heating O
utput
HD
-TH
ot Deck Tem
peratureH
X2E
W-T
HX
2 Entering W
ater Temperature
PC
HW
P5-S
Prim
ary CH
W P
ump 5 S
tatusP
HW
P5-LO
ay
u
p 5 oc
out S
wtch
SC
HW
P1-C
Sec. C
HW
Pum
p 1 Com
mand
SH
W-F
Secondary H
W Flow
UN
IT-RE
SE
TU
nit Reset
ZN4-Q
Zone4 Quality
HD
V-CH
umidifier D
rain Valve Com
mand
HX
2ISO
V-CH
eat Exchanger 2 Isolation Valve C
md
PC
HW
P6-B
AP
rimary C
HW
Pum
p 6 Belt Alarm
PH
WP
5-OL
y
p
Overload
FAULT
Sec.C
HW
Pum
p 1 VFD Fault
SH
WP
1-BA
Secondary H
W P
ump 1 B
elt AlarmW
C1-AD
JZone1 W
armer/C
ooler AdjustZN
4-SP
Zone4 Setpoint
HD
-VPH
ot Deck Velocity P
ressureH
X2IS
OV-S
HX
2 Isolation Valve Status
PC
HW
P6-C
Prim
ary CH
W P
ump 6 C
omm
andP
HW
P5-S
Prim
ary HW
Pum
p 5 Status
SC
HW
P1-LO
Sec. C
HW
Pum
p 1 Lockout Sw
itchS
HW
P1-C
Secondary H
W P
ump 1 C
omm
andW
C2-AD
JZone2 W
armer/C
ooler AdjustZN
4-TZone4 Tem
perature
HD
-VPH
ot Deck Velocity P
ressureH
X2LW
-TH
X2 Leaving W
ater Temperature
PC
HW
P6-LO
Prim
ary CH
W P
ump 6 Lockout S
witch
PH
WP
6-BA
ay
u
p 6 e
t Alarm
SC
HW
P1-O
Sec. C
HW
Pum
p 1 Output
SFAULT
Secondary H
W P
ump 1 VFD
FaultW
C3-AD
JZone3 W
armer/C
ooler AdjustZN
4-TOC
CZone4 Tem
porary Occupancy
HD
-VPH
ot Deck Velocity P
ressureH
X2-M
SH
eat Exchanger 2 M
aint Sw
PC
HW
P6-O
LP
rimary C
HW
Pum
p 6 Overload
PH
WP
6-Cy
p
C
omm
andS
CH
WP
1-SS
ec. CH
W P
ump 1 S
tatusS
HW
P1-LO
Sec. H
W P
ump 1 Lockout S
witch
WC
4-ADJ
Zone4 Warm
er/Cooler Adjust
ZN5D
-OZone5 D
amper O
utput
HFV-C
Hum
idifier Fill Valve Com
mand
HX
2V1-OH
eat Exchanger 2 Valve 1 O
utputP
CH
WP
6-SP
rimary C
HW
Pum
p 6 Status
PH
WP
6-LOy
p
Sw
tchS
CH
WP
2-BA
Sec. C
HW
Pum
p 2 Belt Alarm
SH
WP
1-OS
ec. HW
Pum
p 1 Output
WC
5-ADJ
Zone5 Warm
er/Cooler Adjust
ZN5D
-OZone5 D
amper O
utput
HG
BP
V-CH
ot Gas B
ypass Valve Com
mand
HX
2V2-OH
eat Exchanger 2 Valve 2 O
utputP
CH
WP
7-BA
Prim
ary CH
W P
ump 7 B
elt AlarmP
HW
P6-O
La
y
up 6
Overload
SC
HW
P2-C
Sec. C
HW
Pum
p 2 Com
mand
SH
WP
1-SS
ec. HW
Pum
p 1 Status
WC
6-ADJ
Zone6 Warm
er/Cooler Adjust
ZN5-H
Zone5 Hum
idity
HR
EAFB
D-C
Heat R
ecovery EA FB
D C
omm
andH
XB
YP
-TH
eat Exchanger B
ypass Temperature
PC
HW
P7-C
Prim
ary CH
W P
ump 7 C
omm
andP
HW
P6-S
Prim
ary HW
Pum
p 6 Status
FAULT
Sec. C
HW
Pum
p 2 VFD Fault
SH
WP
2-BA
Sec. H
W P
ump 2 B
elt AlarmW
C7-AD
JZone7 W
armer/C
ooler AdjustZN
5HTG
1-CZone5 H
eating Stage 1 C
omm
and
HR
EAFB
D-O
Heat R
ecovery EA FB
D O
utputH
XIN
R-T
HX
Inlet Return W
ater Temperature
PC
HW
P7-LO
Prim
ary CH
W P
ump 7 Lockout S
witch
PH
WP
7-BA
y
p
Alarm
SC
HW
P2-LO
Sec. C
HW
Pum
p 2 Lockout Sw
itchS
HW
P2-C
Sec. H
W P
ump 2 C
omm
andW
C8-AD
JZone8 W
armer/C
ooler AdjustZN
5HTG
2-CZone5 H
eating Stage 2 C
omm
and
HR
-OH
eat Recovery O
utputH
XM
V-OH
eat Exchanger M
ixing Valve Output
PC
HW
P7-O
LP
rimary C
HW
Pum
p 7 Overload
PH
WP
7-Ca
y
up
C
omm
andS
CH
WP
2-OS
ec. CH
W P
ump 2 O
utputSFAU
LTS
ec. HW
Pum
p 2 VFD Fault
WC
-ADJ
Warm
er/Cooler Adjust
ZN5H
TG3-C
Zone5 Heating S
tage 3 Com
mand
HR
-OH
eat Recovery O
utputH
XS
TM-P
Heat E
xchanger Steam
Pressure
PC
HW
P7-S
Prim
ary CH
W P
ump 7 S
tatusP
HW
P7-LO
y
p
S
wtch
SC
HW
P2-S
Sec. C
HW
Pum
p 2 Status
SH
WP
2-LOS
ec. HW
Pum
p 2 Lockout Sw
itchZH
LP1-C
Zone 1 Heating P
ump C
omm
andZN
5HTG
-CZone5 H
eating Com
mand
HR
OAFB
D-C
Heat R
ecovery OA FB
D C
omm
andLIG
HT-C
Lighting Com
mand
PC
HW
P8-B
AP
rimary C
HW
Pum
p 8 Belt Alarm
PH
WP
7-OL
y
p
Overload
SC
HW
P3-B
AS
ec. CH
W P
ump 3 B
elt AlarmS
HW
P2-O
Sec. H
W P
ump 2 O
utputZH
LP2-C
Zone 2 Heating P
ump C
omm
andZN
5HTG
-OZone5 H
eating Output
HR
OAFB
D-O
Heat R
ecovery OA FB
D O
utputLT-A
Low Tem
perature AlarmP
CH
WP
8-CP
rimary C
HW
Pum
p 8 Com
mand
PH
WP
7-SP
rimary H
W P
ump 7 S
tatusS
CH
WP
3-CS
ec. CH
W P
ump 3 C
omm
andS
HW
P2-S
Sec. H
W P
ump 2 S
tatusZH
LP3-C
Zone 3 Heating P
ump C
omm
andZN
5HTG
-OZone5 H
eating Output
HR
P-C
Heat R
ecovery Pum
p Com
mand
MAD
-OM
ixed Air Dam
per Output
PC
HW
P8-LO
Prim
ary CH
W P
ump 8 Lockout S
witch
PH
WP
8-BA
y
p
Alarm
FAULT
Sec. C
HW
Pum
p 3 VFD Fault
SH
WP
3-BA
Sec. H
W P
ump 3 B
elt AlarmZH
LP4-C
Zone 4 Heating P
ump C
omm
andZN
5-QZone5 Q
uality
HR
P-LO
Heat R
ecovery Pum
p Lockout Sw
itchM
A-HM
ixed Air Hum
idityP
CH
WP
8-OL
Prim
ary CH
W P
ump 8 O
verloadP
HW
P8-C
y
p
Com
mand
SC
HW
P3-LO
Sec. C
HW
Pum
p 3 Lockout Sw
itchS
HW
P3-C
Sec. H
W P
ump 3 C
omm
andZH
LP5-C
Zone 5 Heating P
ump C
omm
andZN
5-SP
Zone5 Setpoint
HR
P-O
LH
eat Recovery P
ump O
verloadM
A-QM
ixed Air Quality
PC
HW
P8-S
Prim
ary CH
W P
ump 8 S
tatusP
HW
P8-LO
ay
u
p 8 oc
out S
wtch
SC
HW
P3-O
Sec. C
HW
Pum
p 3 Output
S3
FAULT
Sec. H
W P
ump 3 VFD
FaultZH
LP6-C
Zone 6 Heating P
ump C
omm
andZN
5-TZone5 Tem
perature
HR
P-S
Heat R
ecovery Pum
p Status
MA-T
Mixed Air Tem
peratureP
CH
WR
-TP
rimary C
HW
Return Tem
pP
HW
P8-O
Ly
p
O
verloadS
CH
WP
3-SS
ec. CH
W P
ump 3 S
tatusS
HW
P3-LO
Sec. H
W P
ump 3 Lockout S
witch
ZHLP
7-CZone 7 H
eating Pum
p Com
mand
ZN5-TO
CC
Zone5 Temporary O
ccupancy
HR
-TH
eat Recovery Tem
peratureM
IX-O
Mixing Valve O
utputP
CH
WS
-TP
rimary C
HW
Supply Tem
pP
HW
P8-S
Prim
ary HW
Pum
p 8 Status
SC
HW
P4-B
AS
ec. CH
W P
ump 4 B
elt AlarmS
HW
P3-O
Sec. H
W P
ump 3 O
utputZH
LP8-C
Zone 8 Heating P
ump C
omm
andZN
6D-O
Zone6 Dam
per Output
HR
W-B
AH
eat Recovery W
heel Belt Alarm
MO
AD-C
Min O
utdoor Air Dam
per Com
mand
PFILT-D
PP
reFilter Diff P
ressureP
HW
R-T
Prim
ary HW
Return Tem
pS
CH
WP
4-CS
ec. CH
W P
ump 4 C
omm
andS
HW
P3-S
Sec. H
W P
ump 3 S
tatusZN
1D-O
Zone1 Dam
per Output
ZN6D
-OZone6 D
amper O
utput
HR
W-C
Heat R
ecovery Wheel C
omm
andM
OAD
-OM
in Outdoor Air D
amper O
utputP
FILT-SP
reFilter Status
PH
WS
-TP
rimary H
W S
upply Temp
FAULT
Sec. C
HW
Pum
p 4 VFD Fault
SH
WP
4-BA
Sec. H
W P
ump 4 B
elt AlarmZN
1D-O
Zone1 Dam
per Output
ZN6-H
Zone6 Hum
idity
HR
W-FAU
LTH
eat Recovery W
heel VFD Fault
MO
AD-S
Min O
utdoor Air Dam
per Status
PH
1-CP
reheat Stage 1 C
omm
andR
AD-O
Return Air D
amper O
utputS
CH
WP
4-LOS
ec. CH
W P
ump 4 Lockout S
witch
SH
WP
4-CS
ec. HW
Pum
p 4 Com
mand
ZN1-H
Zone1 Hum
idityZN
6HTG
1-CZone6 H
eating Stage 1 C
omm
and
HR
W-LO
Heat R
ecovery Wheel Lockout S
witch
MO
A-FM
in Outdoor Air Flow
PH
1-OP
reheat 1 Output
RA-F
Return Air Flow
SC
HW
P4-O
Sec. C
HW
Pum
p 4 Output
SFAULT
Sec. H
W P
ump 4 VFD
FaultZN
1HTG
1-CZone1 H
eating Stage 1 C
omm
andZN
6HTG
2-CZone6 H
eating Stage 2 C
omm
and
HR
W-O
Heat R
ecovery Wheel O
utputM
OAF-A
Min O
utdoor Air Fan AlarmP
H2-C
Preheat S
tage 2 Com
mand
RA-H
Return Air H
umidity
SC
HW
P4-S
Sec. C
HW
Pum
p 4 Status
SH
WP
4-LOS
ec. HW
Pum
p 4 Lockout Sw
itchZN
1HTG
2-CZone1 H
eating Stage 2 C
omm
andZN
6HTG
3-CZone6 H
eating Stage 3 C
omm
and
HR
W-O
LH
eat Recovery W
heel Overload
MO
AF-BA
Min O
utdoor Air Fan Belt Alarm
PH
2-OP
reheat 2 Output
RA-P
Return Air S
tatic Pressure
SC
HW
P5-B
AS
ec. CH
W P
ump 5 B
elt AlarmS
HW
P4-O
Sec. H
W P
ump 4 O
utputZN
1HTG
3-CZone1 H
eating Stage 3 C
omm
andZN
6HTG
-CZone6 H
eating Com
mand
HR
W-S
Heat R
ecovery Wheel S
tatusM
OAF-C
Min O
utdoor Air Fan Com
mand
PH
3-CP
reheat Stage 3 C
omm
andR
APLO
-Aetu
o
uct P
ressureS
CH
WP
5-CS
ec. CH
W P
ump 5 C
omm
andS
HW
P4-S
Sec. H
W P
ump 4 S
tatusZN
1HTG
-CZone1 H
eating Com
mand
ZN6H
TG-O
Zone6 Heating O
utput
HT-A
High Tem
perature AlarmM
OAF-C
Min O
utdoor Air Fan Com
mand
PH
4-CP
reheat Stage 4 C
omm
andR
A-QR
eturn Air Quality
FAULT
Sec. C
HW
Pum
p 5 VFD Fault
SH
WP
5-BA
Sec. H
W P
ump 5 B
elt AlarmZN
1HTG
-OZone1 H
eating Output
ZN6H
TG-O
Zone6 Heating O
utput
HTG
1-CH
eating Stage 1 C
omm
andM
OAF-LO
Min O
utdoor Air Fan Lockout Sw
itchP
H5-C
Preheat S
tage 5 Com
mand
RA-S
DR
eturn Air Sm
oke AlarmS
CH
WP
5-LOS
ec. CH
W P
ump 5 Lockout S
witch
SH
WP
5-CS
ec. HW
Pum
p 5 Com
mand
ZN1H
TG-O
Zone1 Heating O
utputZN
6-QZone6 Q
uality
HTG
1-CH
eating Stage 1 C
omm
andM
OAF-O
Min O
utdoor Air Fan Output
PH
6-CP
reheat Stage 6 C
omm
andR
A-TR
eturn Air Temperature
SC
HW
P5-O
Sec. C
HW
Pum
p 5 Output
S5
FAULT
Sec. H
W P
ump 5 VFD
FaultZN
1-QZone1 Q
ualityZN
6-SP
Zone6 Setpoint
HTG
1-CH
eating Stage 1 C
omm
andM
OAF-O
LM
in Outdoor Air Fan O
verloadP
H7-C
Preheat S
tage 7 Com
mand
RA-VP
Return Air Velocity P
ressureS
CH
WP
5-SS
ec.CH
W P
ump 5 S
tatusS
HW
P5-LO
Sec. H
W P
ump 5 Lockout S
witch
ZN1-S
PZone1 S
etpointZN
6-TZone6 Tem
perature
HTG
1-OH
eating 1 Output
MO
AF-SM
in Outdoor Air Fan S
tatusP
H8-C
Preheat S
tage 8 Com
mand
RE
FRIG
-AR
efrigerant AlarmS
CH
WP
6-BA
Sec. C
HW
Pum
p 6 Belt Alarm
SH
WP
5-OS
ec. HW
Pum
p 5 Output
ZN1-T
Zone1 Temperature
ZN6-TO
CC
Zone6 Temporary O
ccupancy
HTG
2-CH
eating Stage 2 C
omm
andM
OA-VP
Min O
utdoor Air Velocity Pressure
PH
-AP
reheat AlarmR
EV1-C
Reversing Valve 1 C
omm
andS
CH
WP
6-CS
ec. CH
W P
ump 6 C
omm
andS
HW
P5-S
Sec. H
W P
ump 5 S
tatusZN
1-TOC
CZone1 Tem
porary Occupancy
ZN7D
-OZone7 D
amper O
utput
HTG
2-CH
eating Stage 2 C
omm
andM
R-T
Mechanical R
oom Tem
peratureP
HB
S-S
Preheat B
onnet Sw
itch Status
RE
V2-CR
eversing Valve 2 Com
mand
FAULT
Sec. C
HW
Pum
p 6 VFD Fault
SH
WP
6-BA
Sec. H
W P
ump 6 B
elt AlarmZN
2D-O
Zone2 Dam
per Output
ZN7D
-OZone7 D
amper O
utput
HTG
2-CH
eating Stage 2 C
omm
andO
AD-C
Outdoor Air D
amper C
omm
andP
H-C
Preheat C
omm
andR
F-AR
eturn Fan AlarmS
CH
WP
6-LOS
ec. CH
W P
ump 6 Lockout S
witch
SH
WP
6-CS
ec. HW
Pum
p 6 Com
mand
ZN2D
-OZone2 D
amper O
utputZN
7-HZone7 H
umidity
HTG
2-OH
eating 2 Output
OAD
-OO
utdoor Air Dam
per Output
PH
FBD
-OP
reheat Face & B
ypass Dam
per Output
RF-B
AR
eturn Fan Belt Alarm
SC
HW
P6-O
Sec. C
HW
Pum
p 6 Output
S6
FAULT
Sec. H
W P
ump 6 VFD
FaultZN
2-HZone2 H
umidity
ZN7H
TG1-C
Zone7 Heating S
tage 1 Com
mand
HTG
3-CH
eating Stage 3 C
omm
andO
A-FO
utdoor Air FlowP
HFB
D-O
Preheat Face &
Bypass D
amper O
utputR
F-CR
eturn Fan Com
mand
SC
HW
P6-S
Sec. C
HW
Pum
p 6 Status
SH
WP
6-LOS
ec. HW
Pum
p 6 Lockout Sw
itchZN
2HTG
1-CZone2 H
eating Stage 1 C
omm
andZN
7HTG
2-CZone7 H
eating Stage 2 C
omm
and
HTG
3-CH
eating Stage 3 C
omm
andO
A-HO
utdoor Air Hum
idityP
H-O
Preheat O
utputR
F-CR
eturn Fan Com
mand
SC
HW
P7-B
AS
ec. CH
W P
ump 7 B
elt AlarmS
HW
P6-O
Sec. H
W P
ump 6 O
utputZN
2HTG
2-CZone2 H
eating Stage 2 C
omm
andZN
7HTG
3-CZone7 H
eating Stage 3 C
omm
and
HTG
3-CH
eating Stage 3 C
omm
andO
A-QO
utdoor Air Quality
PH
-OP
reheat Output
RF-LO
Return Fan Lockout S
witch
SC
HW
P7-C
Sec. C
HW
Pum
p 7 Com
mand
SH
WP
6-SS
ec. HW
Pum
p 6 Status
ZN2H
TG3-C
Zone2 Heating S
tage 3 Com
mand
ZN7H
TG-C
Zone7 Heating C
omm
and
HTG
4-CH
eating Stage 4 C
omm
andO
A-TO
utdoor Air Temperature
PH
P-C
Preheat P
ump C
omm
andR
F-OR
eturn Fan Output
FAULT
Sec. C
HW
Pum
p 7 VFD Fault
SH
WP
7-BA
Sec. H
W P
ump 7 B
elt AlarmZN
2HTG
-CZone2 H
eating Com
mand
ZN7H
TG-O
Zone7 Heating O
utput
HTG
5-CH
eating Stage 5 C
omm
andO
A-VPO
utdoor Air Velocity Pressure
PH
P-LO
Preheat P
ump Lockout S
witch
RF-O
LR
eturn Fan Overload
SC
HW
P7-LO
Sec. C
HW
Pum
p 7 Lockout Sw
itchS
HW
P7-C
Sec. H
W P
ump 7 C
omm
andZN
2HTG
-OZone2 H
eating Output
ZN7H
TG-O
Zone7 Heating O
utput
HTG
6-CH
eating Stage 6 C
omm
andO
CC
-MO
DE
Occupancy S
tatus Display
PH
P-O
LP
reheat Pum
p Overload
RF-S
Return Fan S
tatusS
CH
WP
7-OS
ec. CH
W P
ump 7 O
utputSFAU
LTS
ec. HW
Pum
p 7 VFD Fault
ZN2H
TG-O
Zone2 Heating O
utputZN
7-QZone7 Q
uality
HTG
7-CH
eating Stage 7 C
omm
andO
CC
-SO
ccupancy Status
PH
P-S
Preheat P
ump S
tatusR
H-A
Reheat Alarm
SC
HW
P7-S
Sec. C
HW
Pum
p 7 Status
SH
WP
7-LOS
ec. HW
Pum
p 7 Lockout Sw
itchZN
2-QZone2 Q
ualityZN
7-SP
Zone7 Setpoint
HTG
8-CH
eating Stage 8 C
omm
andP
CH
W-F
Prim
ary CH
W Flow
PH
-TP
reheat Temperature
RH
-OR
eheat Output
SC
HW
P8-B
AS
econdary CH
W P
ump 8 B
elt AlarmS
HW
P7-O
Sec. H
W P
ump 7 O
utputZN
2-SP
Zone2 Setpoint
ZN7-T
Zone7 Temperature
HTG
BS
-SH
eating Bonnet S
witch S
tatusP
CH
WP
1-BA
Prim
ary CH
W P
ump 1 B
elt AlarmP
HW
E-T
Preheat E
ntering Water Tem
pR
H-O
Reheat O
utputS
CH
WP
8-CS
econdary CH
W P
ump 8 C
omm
andS
HW
P7-S
Sec. H
W P
ump 7 S
tatusZN
2-TZone2 Tem
peratureZN
7-TOC
CZone7 Tem
porary Occupancy
HTG
-CH
eating Com
mand
PC
HW
P1-C
Prim
ary CH
W P
ump 1 C
omm
andP
HW
L-TP
reheat Leaving Water Tem
p.R
HP
-CR
eheat Pum
p Com
mand
FAULT
Secondary C
HW
Pum
p 8 VFD Fault
SH
WP
8-BA
Sec. H
W P
ump 8 B
elt AlarmZN
2-TOC
CZone2 Tem
porary Occupancy
ZN8D
-OZone8 D
amper O
utput
HTG
-CH
eating Com
mand
PC
HW
P1-LO
Prim
ary CH
W P
ump 1 Lockout S
witch
PH
WP
1-BA
Prim
ary HW
Pum
p 1 Belt Alrm
.R
HP
-LOR
eheat Pum
p Lockout Sw
itchS
CH
WP
8-LOy
p
Sw
itchS
HW
P8-C
Sec. H
W P
ump 8 C
omm
andZN
3D-O
Zone3 Dam
per Output
ZN8D
-OZone8 D
amper O
utput
HTG
-CH
eating Com
mand
PC
HW
P1-O
LP
rimary C
HW
Pum
p 1 Overload
PH
WP
1-CP
rimary H
W P
ump 1 C
md
RH
P-O
LR
eheat Pum
p Overload
SC
HW
P8-O
Secondary C
HW
Pum
p 8 Output
S8
FAULT
Sec. H
W P
ump 8 VFD
FaultZN
3D-O
Zone3 Dam
per Output
ZN8-H
Zone8 Hum
idity
HTG
-OH
eating Output
PC
HW
P1-S
Prim
ary CH
W P
ump 1 S
tatusP
HW
P1-LO
Prim
ary HW
Pum
p 1 Lockout Sw
tchR
HP
-SR
eheat Pum
p Status
SC
HW
P8-S
Secondary C
HW
Pum
p 8 Status
SH
WP
8-LOS
ec. HW
Pum
p 8 Lockout Sw
itchZN
3-HZone3 H
umidity
ZN8H
TG1-C
Zone8 Heating S
tage 1 Com
mand
HTG
-OH
eating Output
PC
HW
P2-B
AP
rimary C
HW
Pum
p 2 Belt Alarm
PH
WP
1-OL
Prim
ary HW
Pum
p 1 Overload
RH
WE
-TR
eheat Entering W
ater Temp
SC
HW
R-T
Secondary C
HW
Return Tem
pS
HW
P8-O
Sec. H
W P
ump 8 O
utputZN
3HTG
1-CZone3 H
eating Stage 1 C
omm
andZN
8HTG
2-CZone8 H
eating Stage 2 C
omm
and
HTG
-OH
eating Output
PC
HW
P2-C
Prim
ary CH
W P
ump 2 C
omm
andP
HW
P1-S
Prim
ary HW
Pum
p 1 Status
RH
WL-T
Reheat Leaving W
ater Temp
SC
HW
S-T
Secondary C
HW
Supply Tem
pS
HW
P8-S
Sec. H
W P
ump 8 S
tatusZN
3HTG
2-CZone3 H
eating Stage 2 C
omm
andZN
8HTG
3-CZone8 H
eating Stage 3 C
omm
and
HTG
-OH
eating Output
PC
HW
P2-LO
Prim
ary CH
W P
ump 2 Lockout S
witch
PH
WP
2-BA
Prim
ary HW
Pum
p 2 Belt Alarm
RLF-A
Relief Fan Alarm
SF-A
Supply Fan Alarm
SH
WR
-TS
ec. HW
Return Tem
pZN
3HTG
3-CZone3 H
eating Stage 3 C
omm
andZN
8HTG
-CZone8 H
eating Com
mand
HU
M1-C
Hum
idifier Stage 1 C
md
PC
HW
P2-O
LP
rimary C
HW
Pum
p 2 Overload
PH
WP
2-CP
rimary H
W P
ump 2 C
omm
andR
LF-BA
Relief Fan B
elt AlarmS
F-BA
Supply Fan B
elt AlarmS
HW
S-T
Sec. H
W S
upply Temp
ZN3H
TG-C
Zone3 Heating C
omm
andZN
8HTG
-OZone8 H
eating Output
HU
M2-C
Hum
idifier Stage 2 C
md
PC
HW
P2-S
Prim
ary CH
W P
ump 2 S
tatusP
HW
P2-LO
Prim
ary HW
Pum
p 2 Lockout Sw
tchR
LF-CR
elief Fan Com
mand
SF-C
Supply Fan C
omm
andS
TMIS
O-C
Steam
Isolation Valve Com
mand
ZN3H
TG-O
Zone3 Heating O
utputZN
8HTG
-OZone8 H
eating Output
HU
M3-C
Hum
idifier Stage 3 C
md
PC
HW
P3-B
AP
rimary C
HW
Pum
p 3 Belt Alarm
PH
WP
2-OL
Prim
ary HW
Pum
p 2 Overload
RLF-F
Relief Air Flow
SF-C
Supply Fan C
omm
andS
TM-P
Steam
Pressure
ZN3H
TG-O
Zone3 Heating O
utputZN
8-QZone8 Q
uality
HU
M4-C
Hum
idifier Stage 4 C
md
PC
HW
P3-C
Prim
ary CH
W P
ump 3 C
omm
andP
HW
P2-S
Prim
ary HW
Pum
p 2 Status
RLF-LO
Relief Fan Lockout S
witch
SF-C
Supply Fan C
omm
andS
UM
WIN
-SS
umm
er/Winter M
ode Status
ZN3-Q
Zone3 Quality
ZN8-S
PZone8 S
etpoint
HU
M-C
Hum
idifier Cm
dP
CH
WP
3-LOP
rimary C
HW
Pum
p 3 Lockout Sw
itchP
HW
P3-B
AP
rimary H
W P
ump 3 B
elt AlarmR
LF-OR
elief Fan Output
SF-C
Supply Fan C
omm
andS
UP
HTG
1-CS
uplmtl H
eating Stage 1 C
md
ZN3-S
PZone3 S
etpointZN
8-TZone8 Tem
perature