bagmati river basin improvement project€¦ · bagmati river basin improvement project (rrp nep...

141
Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project Project Administration Manual

Upload: others

Post on 06-Aug-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Bagmati River Basin Improvement Project (RRP NEP 43448)

Project Number: 43448 October 2013

Nepal: Bagmati River Basin Improvement Project

Project Administration Manual

Page 2: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Contents

ABBREVIATIONS

I. PROJECT DESCRIPTION 1

A. Project Rationale 1 B. Impact and Outcome 2 C. Outputs 3

II. IMPLEMENTATION PLANS 5

A. Project Readiness Activities 5 B. Overall Project Implementation Plan 6

III. PROJECT MANAGEMENT ARRANGEMENTS 7

A. Project Implementation Organizations–Roles and Responsibilities 7 B. Key Persons Involved in Implementation 10 C. Project Organization Structure 11

IV. COSTS AND FINANCING. 13

A. Detailed Cost Estimates by Expenditure Category 14 B. Allocation and Withdrawal of Loan/Grant Proceeds 15 C. Detailed Cost Estimates by Financier 17 D. Detailed Cost Estimates by Outputs/Components 18 E. Detailed Cost Estimates by Year 20 F. Contract and Disbursement S-curve 21 G. Fund Flow Diagram 21

V. FINANCIAL MANAGEMENT 24

A. Financial Management Assessment 24 B. Disbursement 28 C. Project Financial Reporting, Auditing, and Public Disclosure 30 D. Accounting and Auditing 30 E. Auditing 30

VI. PROCUREMENT AND CONSULTING SERVICES 31

A. Advance Contracting and Retroactive Financing 31 B. Procurement of Goods, Works and Consulting Services 33 C. Consultant's Terms of Reference 34

VII. SAFEGUARDS 34

IX. PERFORMANCE MONITORING, EVALUATION, REPORTING AND COMMUNICATION 40

A. Project Design and Monitoring Framework 40 B. Monitoring 43 C. Evaluation 44 D. Reporting 44 E. Stakeholder Communication Strategy 45

X. INFORMATION DISCLOSURE 45

A. Participation and institutional Strategic plan 48 B. Establishment and Development of a Bagmati RBO and IWRM 48 C. Mechanisms to Promote Participation, Coordination, and Integrated Water

Dialogue 49

Page 3: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

D. Institutional Development 51 E. Inter-Organizational Relations 52 F. NGO Platform 52

XI. ANTICORRUPTION POLICY 54

XII. ACCOUNTABILITY MECHANISM 55

XIII. RECORD OF PAM CHANGES 55

APPENDIXES

Appendix 1: Detailed Procedures For Disbursements, Accounting, and Auditing 56

Appendix 2: Financial Statements Templates 58

Appendix 3: Statement of Audit Needs 68

Appendix 4: Procurement Plan 73

Appendix 5: Draft Terms of Reference for Project Management Design and Supervision Consultant (PMDSC) 77

Appendix 6: Draft Terms of Reference for Flood Forecasting and Early Warning System And Decision Support System 97

Appendix 7: Draft Terms of Reference for Consultancy For Rbo Formation (Under WFPF TA Grant) 117

Appendix 8: Draft Terms of Reference for Independent Environmental Monitoring Consultant 120

Appendix 9: Draft Terms of Reference for NGO Packages 123

Page 4: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Project Administration Manual Purpose and Process

1. The project administration manual (PAM) describes the essential administrative and management requirements to implement the project on time, within budget, and in accordance with Government and Asian Development Bank (ADB) policies and procedures. The PAM should include references to all available templates and instructions either through linkages to relevant URLs or directly incorporated in the PAM.

2. The executing and implementing agencies are wholly responsible for the implementation of ADB financed projects, as agreed jointly between the borrower and ADB, and in accordance with Government and ADB’s policies and procedures. ADB staff is responsible to support implementation including compliance by executing and implementing agencies of their obligations and responsibilities for project implementation in accordance with ADB’s policies and procedures.

3. At Loan Negotiations the borrower and ADB shall agree to the PAM and ensure consistency with the Financing Agreement. Such agreement shall be reflected in the minutes of the Loan Negotiations. In the event of any discrepancy or contradiction between the PAM and the Financing Agreement, the provisions of the Financing Agreement shall prevail.

4. After ADB Board approval of the project's report and recommendations of the President (RRP) changes

in implementation arrangements are subject to agreement and approval pursuant to relevant Government and ADB administrative procedures (including the Project Administration Instructions) and upon such approval they will be subsequently incorporated in the PAM.

Page 5: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Abbreviations

ADB – Asian Development Bank BRBIP – Bagmati River Basin Improvement project DDC – district development committee DMF – design and monitoring framework DOI – Department of Irrigation DSS – decision support system DWIDP – Department of Water Induced Disaster Preparedness EARF – environmental assessment and review framework EIA – environmental impact assessment EMP – environmental management plan FFEW – flood forecasting and early warning GON – Government of Nepal HPCIDBC – High Powered Committee for the Integrated Development of the Bagmati

Civilization ICB – international competitive bidding IEE – initial environmental examination IPP – indigenous peoples plan IPPF – indigenous people planning framework IRBDMP – integrated river basin development master plan IWRM – Integrated Water resources Management KVDA – Kathmandu Valley Development Authority MOF – Ministry of Forestry MOI – Ministry of Irrigation MOUD – Ministry of Urban Development NCB – national competitive bidding NGO – nongovernment organization PAM – project administration manual PIU – project implementation unit PPTA – project preparatory technical assistance PCMU – project coordination and management unit PMDSC – project management design and supervision consultant PSC – project steering committee QCBS – quality- and cost-based selection RBO – river basin organization RRP – Report and Recommendation of the President SOE – statement of expenditure SPS – Safeguard Policy Statement SPRSS – summary poverty reduction and social strategy TOR – terms of reference VDC – village development committee WECS – Water and Energy Commission Secretariat

Page 6: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

I. PROJECT DESCRIPTION

A. Project Rationale

1. The Bagmati River Basin (BRB) has a cultural and economic significance to the people of Nepal. The water flowing in the Bagmati River is considered holy and is used for cultural and ritual ceremonies practiced at the many significant temples located along its banks. The river flows through Kathmandu which is the administrative and economic center of the country as well as Nepal’s gateway for tourism. It provides most of the city’s drinking water in its upper basin, hydropower generation in the middle basin, and large-scale irrigation in the lower basin.

2. BRB is considered the most water stressed basin in Nepal. The basin is seeing a decline in water resources availability owing to natural and anthropogenic causes while experiencing significant increases in fresh water demand to meet the expanding population and industrial sector, and demands for irrigated agriculture. The rapid and unplanned expansion of Kathmandu City has placed tremendous pressure on the water resources of the upper BRB. In the absence of appropriate solid waste and waste water management, the river has become the main waste collector drain: it now contains high levels of fecal contamination, pathogenic bacteria, bacteriological and physicochemical pollutants. The absence of pollution safety measures has created serious health hazards to local people, livestock, and aquatic flora and fauna, while its physical deterioration has led to a loss of cultural and recreational amenity for the local communities whom no longer respect or cherish the river environment. Rapid urbanization has also led to increased demands on the valley’s water supply distribution. During dry season, around 80% of the upper Bagmati River flow is diverted for domestic use leaving very little flow for irrigation and other sectors including environment. Current utilization of surface water is only 10% as water in rainy season is untapped due to absence of seasonal storage facilities. As a result, municipal authorities, individuals and companies continue to extract groundwater at an unsustainable rate. Ground water extraction is estimated to be 4 to 5 times higher than the natural recharge and the water table has retreated by 35 meters (m) in the last 20 years. The situation is further aggravated by: (i) the conversion of the recharge areas into residential areas, and (ii) upstream catchment degradation. In the Kathmandu valley, the river is biologically dead and made of heavily polluted sewage water that endangers the health of the capital’s population and downstream water users. Throughout the basin, frequent floods and river bank erosion are the main threat to infrastructure, agricultural land, people’s lives, and their livelihoods.

3. Until now the planning, development and management of water resources in BRB has been generally ad-hoc, uncoordinated and reactive. Government agencies have operated in isolation leading to ineffective investments and inequitable allocation of water for human needs, productive use, and the environment. This hampers the government’s development efforts to improve water security in the basin. The government now recognizes the importance of addressing these problems by moving away from this silo-management approach and embracing the principals of IWRM. The current Water Resources Act (1993) has sought to quantify existing use and allocation rights.1Subsequent strategy and planning documents2 recognized the importance of IWRM and established the need for holistic and systematic management and development of water resources. They also ensured conservation of resources and protection of the environment. The Bagmati River Basin Improvement Project

1 The Act provided only 18 months to assess existing water rights. As this could not be completed within this period

subsequently water use could not managed, monitored or allocations enforced. 2 Water Resources Strategy (WRS, 2002) and National Water Plan (NWP, 2005)

Page 7: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

2

(BRBIP) will support the effort in developing appropriate legal and institutional frameworks for operationalizing the IWRM approach and develop a model that can be replicated in the other basins of the country.

4. In 2009, the government approved the Bagmati Action Plan (2009-2014)3 to address the poor state of the river and its tributaries in Kathmandu Valley. The Plan has the vision of “a clean, green and healthy river system that is full of life and valued by all” and provides a long list of interventions that collectively aim to restore and conserve the river environment in the valley. Some of these interventions are already being implemented by the High Powered Committee for the Integrated Development of the Bagmati Civilization (HPCIDBC) but due to lack of capacity and funds many of the plan recommendations are still to be implemented. The government has also sought to address drinking water scarcity and improve wastewater management in Kathmandu Valley through several ADB-financed projects.4 However, while these projects will address the immediate human needs, they do not resolve other critical priorities of the basin inhabitants nor provide a long-term sustainable management framework for BRB.

5. Where the Bagmati River enters the Tarai plain, frequent floods and river bank erosion have become the main threat to people’s livelihoods. The worst recent flood, in 1993, claimed 789 lives, affected 30,200 people and caused major damage to houses and public infrastructure in the lower reaches alone. The BRBIP will support the development and implementation of a flood forecasting and warning system for the entire Bagmati Basin.

6. Such priorities were identified and developed under the Capacity Development TA “Supporting Investment on Water Security in River Basins”5 which strategically assessed current and planned interventions from a river basin perspective. The TA produced a basin strategic investment road map and initiated studies aiming at resolving critical priorities. In particular, it produced a water balance and quality model to assess the interventions that are required to restore the environment in the Upper Bagmati River (UBR) and achieving bathing standards at Pashnupatinath and Gokarna. Interventions identified include: (i) physical restoration of the urban riparian environment and social mobilization to reconnect riverine communities with their river; (ii) increasing water availability in the river during the dry season to raise the river’s assimilative capacity; and, (iii) strategic placement of wastewater treatment facilities with higher treated effluent standards. The need for a flood forecasting and early warning system was also identified as a critical priority, particularly in the lower basin where communities are regularly suffering from extreme flood hazards.

B. Impact and Outcome

7. The project expected impact will be increased water security in the BRB. The expected outcome will be improved river environment and flood management.

3 Government of Nepal, 2009

4 ADB. 2011. Technical Assistance to Nepal for Preparing the Kathmandu Valley Urban Environment Improvement

Project. Manila (TA 7936-NEP), later renamed to Kathmandu Valley Wastewater Management Project; ADB. 2000. Report and Recommendation of the President to the Board of Directors: Proposed Loan to Nepal for Melamchi Water Supply Project. Manila (Loan 1820-NEP); Kathmandu Valley Water Supply Augmentation through Public-private Partnerships; ADB. 2012. Country Operations Business Plan: Nepal, 2013–2015. Manila.

5 ADB. 2010. Regional Technical Assistance for Supporting Investment on Water Security in River Basins. Manila.

(TA 7547-REG).

Page 8: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

3

C. Outputs

8. The expected outputs of the Project are:

(i) Output 1: Established systems and capacity for integrated and participatory river basin management. This output will include: (a) legal and institutional strengthening for IWRM and formation of a river basin organization (RBO); (b) mobilization and awareness raising of basin stakeholders; (c) capacity building and technical training for raising the RBO’s competence; (d) establishment of a Central Water Resources Information system including a Decision Support System (DSS) and an operational water quality monitoring network; and (v) preparation of a 15-year participatory Integrated River Basin Master Plan.

(ii) Output 2: Improved riverbank environment in urban areas. This output will include:(a) 7.2 km of river corridor constructed with aesthetic river walls and recreational amenities, (d) rehabilitation of two former irrigation regulator structures, (e) improving the river channel profile around 2 cultural sites and stabilize temple ghats, (f) removal and safe disposal of contaminated and accumulated riverbed material at key sites, (f) riverbank stabilisation at Sundarijal where existing housing structures are under threat of river bank erosion, (g) enhancement and management of the riparian banks (green zones with foot and bicycle paths), and (h) enhancement and beautification of the riparian banks (green zones with foot paths and amenities areas

Further to the riparian river works in the Upper Bagmati the project provides for additional riparian river improvement works in other tributaries to the Bagmati River, including the Bishnumati River. The project will assess the feasibility for these works, providing designs of same aesthetic quality as for the Upper Bagmati, and implement the works.

Non-structural interventions will include: (i) Mobilization of local communities for adopting river stretches for river environment protection which will include prevention of disposal of solid waste along the stretches, (ii) implementation of a Communication strategy Action Plan for awareness raising and community ownership of the river, (iii) a Gender Action Plan addressing gender needs and issues; and (iv) mobilizing the private sector by project closure to maintain at least 2 km of the river stretch as a pilot

(iii) Output 3: Increased water availability in the basin during dry season and watershed conservation. This output will include: (i) the construction of a dam downstream of the existing Dhap within the Shivapuri National Park with a storage capacity of 850,000 m3 to enable dilution of wastewater effluents and increase environmental flows in Upper Bagmati during the dry season, (b) detail design of a Nagmati Dam with the potential capacity of 8 million cubic meters (c) installation of rain water harvesting by 2500 households to provide 45,000 m3 of safe water supply and recharge 135,000 m3 groundwater, and (d) 12.5 ha of outward sloping agricultural land prone to soil erosion will be stabilised by establishing community interventions to increase water retention and reduce soil erosion.

(iv) Output 4: Functioning flood forecasting and early warning system for the

Page 9: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

4

Bagmati River Basin. The provision of a Flood Forecasting and Warning System for the Bagmati Basin.

(v) Output 5: Efficient project management with effective stakeholder

communication. This output will be achieved by setting up Project Coordination and Management Unit (PCMU) supported by a Project Management Design and Supervision Consultancy (PMDSC), which besides supporting the PCMU will assist in overseeing and supervising construction, as well as supporting the formation of an RBO.

Page 10: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

5

II. IMPLEMENTATION PLANS

A. Project Readiness Activities

N. Actions Who When

1 Approve Loan Fact Finding Aide Memoire

MOUD/MOF 20 June 2013

Project Management - Finance

2 Appoint a Project Director MOUD Completed

3 Appoint WECs and DOI head of PIU WECs/DOI Completed

4 Project Confirmed as P1 project MOUD/MOF Completed

5 Include 1st year implementation budget

(incl. retro-active actions) in red book PCMU, DOI, WECs

Completed

6 Appoint project management unit (PMU) staff (stage 1)

MOUD/MOF Completed

7 Appoint WECs and DOI PIU staff (stage 1)

DOI/WECS 15 October 2013

8 PCMU/DOI PIU office established MOUD/HPCIDBC 15 October 2013

Environment Safeguards

1 Request permission to MFSC to conduct the EIA

MOUD with Support from PPTA and DOI

15 May 2013

2 Finalize ADB EIA PPTA consultant 05 May 2013

3 Draft ADB EIA submitted to GON ADB 15 May 2013

4 Publish Environment in any national level news paper, requesting the Village Development Committee or Municipality where the proposal is to be implemented , as well as the schools , hospitals , health posts and concerned individuals or institutions of the area to offer in writing their suggestions within 15 days of publication of notice

MOUD with support from PPTA consultant

30 May 2013

5 Disclose ADB EIA ADB 18 June 2013

6 Finalize scoping documents and TORs for the Government EIA

PPTA consultant with support from DOI

15 September 2013

7 Submit scoping documents and TORs for the Government EIA to MOSTE

MOUD with support from PPTA and DOI

22 September 2013

8 Obtain approval of the Government EIA through regular follow-up with MOSTE

MOUD/DOI with support from PPTA consultant

February 2014

Page 11: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

6

B. Overall Project Implementation Plan

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

1 - (i) Systems and capacity for

integrated and participatory river basin

management established

RBO Formation and Training isc

Legal and policy amendments isc

Develop IRBDMP

DSS ten der

WQ Laboratory ten der

2 - Improved river banks environment

in urban areas

River Improvement - detail design (PMDSC) t e n d e r

River Improvement - construction t e n d e r

Mobilization, Communication & Gender ten der

EMP for river improvement w orks

3 Increased Water Availability in the

Basin during the Dry Season and

watershed conservation

EIA for GON Approval for EIA

Dhap Dam Design&Build tender

Rainw ater harvesting & solid w aste ten der

Watershed management ten der

Nagmati Dam Detailed Design tender

4 Flood forecasting and early warning

system in the Bagmati River Basin is

functional

FF (to be tendered w ith DSS) ten der

5 The project is efficiently managed

with effective stakeholder

communication

PMSC supporting PMU and PIUs tender

Form PMU and PIUs

Financial System/open imptrest account

Setup M&E system in PMU

Provision of training to PMU

 6 Implementation of GESI Action Plan

Legend:

full time

intermittent

2018Item

2013 2014 2015 2016 2017

Page 12: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

7

III. PROJECT MANAGEMENT ARRANGEMENTS

A. Project Implementation Organizations–Roles and Responsibilities

1. Project Steering Committee

9. The Project Steering Committee (PSC), to be chaired by the Secretary of Ministry of Urban Development (MOUD), will be established to provide policy guidance, oversee project implementation, and ensure cooperation of all agencies involved in the project and accomplish reform measures. Indicative members of the PSC are: Secretary, MOUD (chair); Joint secretary MOUD, project manager, HPCIDBC; General Director DOI, General Director DHM, Chief warden Shivapuri Nagarjun National Park, a representative each from MOF, WECS KVDA, KUKL PID, project director KVWMP (members); project director, PMUC BRBIP (member secretary).Project Steering Committee may co-opt other members and form sub-committees for specific purposes, as necessary. PSC will meet as required, but at least once every quarter.

2. Executing Agency

10. The Executing Agency (EA) will be the Ministry of Urban Development responsible for overall strategic planning, guidance and management of the project, and for ensuring compliance with loan covenants.

3. Implementing Agencies

11. HPCIDBC will be the implementing agency (IA) for output 2 and 5 and part of output 3 including rainwater harvesting schemes and watershed management. HPCIDBC will establish the PCMU with its own staff, staff deputed from other department or recruited from the market when specialities are not available within government. The PCMU will have units for Contracting & Finance, River Works Planning, Design & Construction Supervision, Social Mobilisation & Communication, Safeguards and Monitoring & Evaluation (M&E), and DSS. The staffing requirement for each unit is presented below

Unit Position Class

PCMU Project Director Class I officer

Finance Senior Accountant Class II officer

Accountant Class III officer

Sub Accountant Class I non-gazetted

Procurement Procurement and Contracting Specialist - Engineer

Class II officer

Procurement and Contracting Specialist

Class III officer

River Works Planning & Supervision

Senior engineer Class II officer

Design engineer (2 persons) Class III officer

River engineer (2 persons) Class III officer

Page 13: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

8

Social mobilization and communications unit

Senior sociologist Class II officer

sociologist Class III officer

Gender specialist Class III officer

Communications specialist Class III officer

Safeguards and Monitoring and Evaluation

Senior safeguard specialist Class II officer

Environmentalist Class III officer

Socio-economist Class III officer

Monitoring and Evaluation

specialist

Class III officer

Gender specialist Class III officer

Decision Support System Unit Senior engineer Class II officer

Hydrologist Class III officer

Water quality specialist Class III officer

Database specialist Class III officer

Administration Support Senior Administration officer Class II officer

Secretary Class I non-gazetted

Office Assistant (4 persons) Peon class I

Driver (4 persons) Driver class I

12. WECS will be the IA for outputs 1 and 4, including RBO Formation, IWRM implementation DSS, IRBDMP and FFEW inputs and activities. Output 4 will be implemented in collaboration with the Department of Hydro-meteorology (DHM). The PIU in WECS will be headed by a class II Engineer and staffed by DSS Engineers (two persons, of Class III), 1 Administration officer, one secretary and one driver. The WECs will work closely with DHM for the FFEW installation. The Department of Irrigation (DOI) will be the IA for part of the output 3 including the detail design and construction of the Dhap Dam and the detail design of the Nagmati dam. DOI will establish a PIU with the following staff

Unit Position Class

Head of PIU Senior Engineer Class II

Design Unit Engineer Class III officer

Engineer geologist Class III officer

Sub engineer Class I non-gazetted

Construction Unit Engineer Class III Officer

Sub engineer Class I non-gazetted

Accounts Officer Class III officer

Page 14: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

9

Sub-accounts officer Class I non-gazetted

Administration officer Class III officer

Driver (three persons) Driver Class I

Office Assistant (three persons)

Peon class I

Project implementation

organizations Management Roles and Responsibilities

Executing Agency MOUD

Chairs the Project Steering Committee (PSC) Provides overall strategic planning, guidance and

management support to the project Coordinates with other ministries on matters on

projects issues under their jurisdiction Ensures adequate counterpart funding Oversee implementation of the loan project Monitor and ensure compliance of loan covenants

and environmental and social safeguards and facilitate the implementation of corrective action

Procure international consultant(s) and contractor(s)

Oversee overall financial management including undertaking financial audits and implement recommended action

Project Steering Committee (PSC)

The PSC will be chaired by MOUD and will include members from HPCIDBC, WECS, MOF, DOI, KUKL PID,DHM, Civil Society, etc

Oversee implementation of the project Monitor progress of the project Rectify issues hindering progress of the project Guide the Executing Agency and the Implementing

Agencies Meet at least once each quarter

Implementing Agency 1 HPCIDBC

Establish a Project Coordination and Management Unit (PCMU) which will be responsible for day-to-day implementation of the sub-project

Coordination of the 2 PIUs, for budget planning, compliance of procurement, request for reimbursement, and direct payments

Procure and supervise contractor for Upper Bagmati River Improvement works

Manage WQ monitoring consultants Procure NGO services Manage international consultants and national

consultants and contractors

Page 15: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

10

Implement the Upper Bagmati River Improvement sub-project

Submission of the withdrawal application to ADB, retention of supporting documents, submission of any reporting requirements, including, the trimester project progress reports and financial statements, and maintaining the imprest account

Conduct and coordinate project review missions and consolidate implementation reports from IAs in preparation of quarterly progress report to ADB

Establish project performance monitoring system and a website for disclosure

Prepare project completion report at the end of the project and submit to ADB

Implementing Agency 2 WECS

Procure international DSS, IRBDMP and FFEW, WQ consultants

Manage DSS, IRBDMP and FFEW international and local consultants

Manage international and local consultants and legal expert for RBO formation

Implement the RBO formation sub-project component

Implementing Agency 3 DOI

Procure and manage international Design & Build contractors for the Dhap Dam

Implement the Dhap Dam sub-project Procure and manage international consultants for

SI and detailed design of the Nagmati Dam

ADB Procure international PMDSC consultants. The EA retains the responsibility for negotiating and signing the contract with the consultant, issuing the notice to proceed, and supervising the consultant’s services." (Ref. Project Administration Instruction, Section 2.05, para 47).

Conduct regular loan review missions Review and issues no-objection to procurement

and disbursement documents Overall coordination and advisory support

B. Key Persons Involved in Implementation

Executing Agency Ministry of Urban Development (MOUD)

Officer's Name: Kishore Thapa Position Secretary Telephone:+977-1-4211673 Email address: [email protected] Office Address: Singhdurbar, Kathmandu

Page 16: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

11

Implementing Agencies HPCIDBC Officer’s Name: Gajendra Kumar Thakur

Position : Project Manager Telephone No.9841743005

Email address: [email protected] WECS Officer’s Name: Sunil Bahadur Malla

Position : Joint Secretary Telephone No.+977-1-4211428

Email address:[email protected] DOI Officer’s Name: Shiv Kumar Sharma

Position : Director General Telephone No.+ 977-1-5537136

Email address:[email protected] ADB Environment, Natural Resources and Agriculture Division

Officer’s Name: Takashi Matsuo Position : Director Telephone No.+63 (2) 632 4444

Email address: [email protected] Mission Leader Staff Name: Arnaud Cauchois

Position : Senior Water Resources Specialist Telephone No.+977 (1) 4227779 Email address: [email protected]

C. Project Organization Structure

13. The project implementation structure entails that WECS and DOI will have their own PIUs. The PCMU and PIU of DOI will be housed in HPCIDBC, while the WECS PIU will be in WECS office. Each executing agency will be responsible for managing their procurements and payments under the guidance of the PCMU. However all official communications with ADB (request for payment, approvals of procurements, etc) will have to be routed through the PCMU and the Project Director. The PIU heads will report to their direct supervisor in their respective organizations, while keeping the Project Director of the PCMU informed of progress. Each PIU will provide quarterly reports to the PCMU that will be consolidated into the project quarterly report and sent to ADB. The Project Director will provide annual performance evaluation of each PIU heads.

Page 17: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

12

Page 18: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

13

IV. COSTS AND FINANCING.

14. The project is estimated to cost $36 million (Table 1).

Table 1: Project Investment Plan ($ million)

Item Amounta

A. Base Costb

1. Systems and Capacity for Integrated and Participatory RBWM Established 2.2 2. Improved river banks environment in urban areas 15.1 3. Increased Water availability in the Basin the dry season and watershed

conservation 6.5 4.Flood Forecasting and Early Warning System in the BRB is functional 0.5

5. Project is Efficiently Managed with Effective Stakeholders Communication 3.7 Subtotal (A) 28.0 B. Contingencies

7.3

C. Financing Charges During Implementation 0.7 Total (A+B+C) 36.0 a Exchange rate of $1 = NRs87 is used.

b In mid-2013 prices. c Physical contingencies computed at 10% for all items. Price contingencies computed at 2.2%, 1.9% and 1.8% for

thereafter for 5 years from 2014 on foreign exchange costs and 9% and 7% thereafter local currency costs; includes provision for potential exchange rate fluctuation.

d Interest during construction for Asian Development Bank loan(s) is computed at 1.0% per annum. Source: Asian Development Bank estimates.

15. The government has requested a loan in various currencies equivalent to $25.5 million from ADB’s Special Funds resources to finance the project and a grant of $4.5 million. The loan will have a 32-year term, including a grace period of 8 years, an interest charge of 1.0% per annum during the grace period and 1.5% per annum thereafter, and such other terms and conditions set forth in the loan and project agreements. The ADB loan, which is 71% of the total project cost, will be used to finance all equipment and part of the other outputs and financing charges.

16. The government will contribute $6 million or 16.7% of the total project cost to finance taxes and duties for all cost categories, and part of all other costs categories excluding equipment which will be financed by the Bank. The financing plan is in Table 2.

Table 2: Financing Plan

Source Amount ($ million) Share of Total (%)

Asian Development Bank 30.0 83.3 Special Funds resources (loan) 25.5 70.8 Special Funds resources (grant) 4.5 12.5

Government 6.0 16.7 Total 36.0 100.0

Source: Asian Development Bank estimates.

Page 19: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

14

A. Detailed Cost Estimates by Expenditure Category

Items

(Nepal Rupees million) (USD million) Foreign Local Total Foreign Local Total % of

Total Base Cost

Exchange Currency Cost Exchange Currency Cost

A. Investment Costs

1 Civil Works 1.08 1,484.57 1,485.64 0.01 17.06 17.07 61%

2 Equipment 54.38 0.81 55.19 0.63 0.01 0.64 2.3%

3 Capacity Building & Training 12.62 48.11 60.72 0.15 0.55 0.69 2.5%

4 Surveys, Design and Mapping (Nagmati)

91.35 148.10 239.45 1.05 1.70 2.75 9.8%

5 Consultancy Services 213.82 151.42 365.24 2.46 1.74 4.19 15 %

6 Community Initiatives 0.00 142.98 142.98 0.00 1.64 1.64 5.9%

7 Government Counterpart Staff (PCMU/PIUs) 5.40 77.96 83.36 0.06 0.89 0.96 3.5%

Subtotal (A) 378.65 2,053.94 2,432.59 4.39 23.61 28.00 100.0%

B. Recurrent Costs

1 Salaries 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

2 Accommodation 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

3 Equipment Operation and Maintenance 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

Subtotal (B) 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

Total Base Cost 378.65 2,056.94 2,432.59 4.39 23.61 28.00 100.0%

C. Contingencies

1 Physical 37.78 203.87 241.65 0.43 2.34 2.78 10.0%

2 Price 9.27 382.94 392..21 0.11 4.40 4.52 16.1%

Subtotal (C) 47.04 586.81 633.85 0.54 6.74 7.30 26.1%

D. Financing Charges During Implementation

1 Interest During Implementation 60.48 0.00 60.48 0.70 0.00 0.70 2.0%

2 Commitment Charges 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

Subtotal (D) 60.48 0.00 60.48 0.70 0.00 0.70 2.0%

Total Project Cost (A+B+C+D) 486.17 2,640.75 3,126.92 5.65 30.35 36.00 128.1%

Page 20: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

15

B. Allocation and Withdrawal of Loan/Grant Proceeds

17. The loan allocation and withdrawal table will be finalized, once the loan agreement is finalized

ALLOCATION AND WITHDRAWAL OF LOAN PROCEEDS

Category ADB Financing

No. Item Total Amount Allocated for ADB Financing ($/SDR) Category WECS

Total Amount Allocated for ADB Financing ($/SDR) Category DOI

Total Amount Allocated for ADB Financing ($/SDR) Category HPCIDBC

Total Amount Allocated for ADB Financing ($/SDR) Category TOTAL

Percentage and Basis for Withdrawal from the Loan Account

1 Civil Works - $2,895,000 $14,276,000 $17,171,000

84%of total expenditure claimed

2 Equipment $339,000 $66,000 $213,000 $618,000

94% of total expenditure claimed

3

Capacity Building and Training $165,000 - $346,000 $511,000

80% of total expenditure claimed

4

Surveys, Design and Mapping $105,000 $2,351,000 $52,000 $2,508,000

85% of total expenditure claimed

5 Consultancy Services $250,000 - $458,000 $708,000

16% of total expenditure claimed*

6 Community Initiatives - - $1,300,000 $1,300,000

67% of total expenditure claimed

Sub -total $859,000 $5,312,000 $16,645,000 $22,816,000

7 Interest Charge $695,000

100% of amounts due

8 Unallocated $1,989,000

Total $25,500,000 * Exclusive of taxes and duties imposed within the territory of the Borrower.

Page 21: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

16

18. The grant allocation and withdrawal table will be finalized, once the loan agreement is finalized.

ALLOCATION AND WITHDRAWAL OF GRANT PROCEEDS

Category ADB Financing

No. Item Total Amount Allocated for ADB Financing ($/SDR) Category WECS

Total Amount Allocated for ADB Financing ($/SDR) Category DOI

Total Amount Allocated for ADB Financing ($/SDR) Category HPCIDBC

Total Amount Allocated for ADB Financing ($/SDR) Category TOTAL

Percentage and Basis for Withdrawal from the Loan Account

1 Civil Works 2 Equipment

3

Capacity Building and Training

4

Surveys, Design and Mapping

5 Consultancy Services $1,319,000 - $2,414,000 $3,733000

84% of total expenditure claimed*

6 Community Initiatives - - $415,000 $415,000

21% of total expenditure claimed

Sub Total S1,319,000 $2,829,000 $4,148,000

8 Unallocated - $352,000

Total - $4,500,000 * Exclusive of taxes and duties imposed within the territory of the Borrower.

Page 22: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

17

C. Detailed Cost Estimates by Financier

($ million)

ADB Loan ADB Grant

GON

Amount

Percentage of Cost

Category Amount

Percentage of Cost

Category Amounta

Percentage of Cost

Category Total Cost

Percentage of Total

Item {A} {A/C} {B} {B/C} {B} {B/C} {C}

A. Investment Costs

1 Civil Works 17.17 84.0% 0.0 0.0% 3.27 16.0% 20.42 56.7%

2 Equipment 0.62 94.3% 0.0 0.0% 0.01 5.7% 0.66 1.8%

3 Capacity Building & Training 0.51 80.4% 0.0 0.0% 0.12 19.6% 0.64 1.7%

4 Surveys, Design and Mapping 2.51 84.6% 0.0 0.0% 0.46 15.4% 2.97 8.3%

5 Consultancy Services* 0.71 15.1% 3.73 79.6% 0.25 5.3% 4.68 13.0%

6 Community Initiatives 1.30 66.8% 0.42 21.3% 0.23 11.8% 1.95 5.4%

7

Government Counterpart Staff (PCMU/PIUs)

0.00 0.0% 0.0 0.0% 1.16 100.0% 1.16 3.2%

Subtotal (A) 22.76 70.3% 4.14 12.7% 5.53 17.0% 32.47 90.2%

B. Recurrent Costs

Subtotal (B) 0.0 0.0% 0.0 0.0% 0.0 0.0% 0.0 0.0%

Total (A+B) 22.76 70.3% 4.14 12.7% 5.53 17.0% 32.47 90.2%

C. Contingencies 1.98 70.3% 0.36 12.7% 0.47 17.0% 2.83 7.9%

D. Financing Charges During Implementation

0.70 100.0% - 0.0% 0.00 0.0% 0.70

1.9%

Total Project Cost (A+B+C+D) 25.50 70.8% 4.50 12.5% 6.00 16.7% 36.00 100.0%

% Total Project Cost

70.8%

12.5%

16.7%

ADB = Asian Development Bank, GON = Government of Nepal, PCMU = project coordination and management unit, PIU = project implementation unit. * The government's financing for consultancy services category is for taxes and duties imposed within the territory of the borrower so that ADB loan and ADB grant will finance the consultancy services on a net-of-tax basis a Inclusive of taxes

Page 23: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

18

D. Detailed Cost Estimates by Outputs/Components

Item

($ million)

Total Cost

RBO Effective integrated and participatory river basin management

Upper Bagmati Improved river environment in the Kathmandu Valley

Increased Water Availability in the Basin during the Dry Season

Reduced Water-Induced Disaster Impact on Basin Communities

Efficient Project Management and Stakeholders Coordination

Amount % of Cost Category

Amount % of

Cost Category

Amount % of

Cost Category

Amount % of Cost

Category Amount

% of Cost

Category

A. Investment Costsa

1 Civil Works 17.07 0.00 0.0% 14.05 77.7% 3.03 22.3% 0.00 0.0% 0.00 0.0%

2 Equipment 0.64 0.33 51.4% 0.00 0.0% 0.03 6.0% 0.03 4.8% 0.24 37.8%

3 Capacity Building & Training

0.69 0.40 57.2% 0.24 34.7% 0.00 0.0% 0.06 8.1% 0.00 0.0%

4 Surveys, Design and Mapping

2.75 0.09 4.9% 0.00 0.0% 2.60 91.5% 0.02 0.9% 0.05 2.7%

5 Consultancy Services 4.19 1.41 34.1% 0.00 0.0% 0.00 0.0% 0.39 9.5% 2.43 56.4%

6 Community Initiatives 1.64 0.00 0.0% 0.78 47.6% 0.86 52.4% 0.00 0.0% 0.00 0.0%

7

Government Counterpart Staff (PCMU/PIUs)

0.96 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.96 100.0%

Subtotal (A) 28.00 2.23 7.9% 15.07 53.8% 6.52 23.3% 0.50 1.8% 3.68 13.1%

B. Recurrent Costs

1 Salaries 0.00 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%

2 Accommodation 0.00 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%

3 Equipment Operation & Maintenance

0.00 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%

Subtotal (B) 0.00 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%

Total Base Cost 28.00 2.23 7.9% 15.07 53.8% 6.52 23.3% 0.50 1.8% 3.68 13.1%

C. Contingencies

1 Physicalb 2.78 0.22 7.9% 1.51 53.8% 0.65 23.3% 0.05 1.8% 0.36 13.1%

2 Pricec 4.52 0.18 3.9% 3.13 73.1% 0.74 14.8% 0.01 0.0% 0.44 8.6%

Page 24: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

19

Subtotal (C) 7.30 0.40 5.5% 4.64 63.5% 1.39 19.1% 0.06 0.8% 0.80 10.9%

D.

Financing Charges During Implementation

d

1 Interest During Implementation

0.70 0.05 7.9% 0.38 53.8% 0.16 23.3% 0.01 1.8% 0.09 13.1%

2 Commitment Charges 0.00 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%

Subtotal (D) 0.70 0.05 7.9% 0.38 53.8 0.16 23.2% 0.01 1.8% 0.09 13.1

Total Project Cost (A+B+C+D) 36.00 2.68 7.4% 20.09 55.8% 8.07 22.4% 0.56 1.6% 4.46 12.7%

PCMU = project coordination and management unit, PIU = project implementation unit, RBO = river basin organization.

a In mid-2013 prices.

b Computed at 10% for all items.

c Computed at 2.2%, 1.9% and 1.8% for thereafter for 5 years from 2014 on foreign exchange costs and 9% and 7% thereafter on local currency costs .

d Includes Interest during construction has been computed at the 1% during grace period and 1.5% thereafter

Source: PPTA estimates.

Page 25: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

20

E. Detailed Cost Estimates by Year

($ million)

Total Cost

Item Year 1 Year 2 Year 3 Year 4 Year 5

A. Investment Costs

1 Civil Works 17.07 0.76 7.13 6.38 2.81 0.00

2 Equipment 0.64 0.38 0.17 0.08 0.00 0.00

3 Capacity Building & Training 0.69 0.34 0.21 0.09 0.05 0.00

4 Surveys, Design and Mapping 2.75 1.97 0.51 0.23 0.01 0.02

5 Consultancy Services 4.19 1.80 1.41 0.49 0.26 0.23

6 Community Initiatives 1.64 0.41 0.46 0.41 0.18 0.18

7 Government Counterpart Staff (PCMU/PIUs) 0.96 0.28 0.17 0.17 0.17 0.17

Subtotal (A) 28.00 5.94 10.07 7.85 3.48 0.61

B. Recurrent Costs

1 Salaries 0.00 0.00 0.00 0.00 0.00 0.00

2 Accommodation 0.00 0.00 0.00 0.00 0.00 0.00

3 Equipment Operation and Maintenance 0.00 0.00 0.00 0.00 0.00 0.00

Subtotal (B) 0.00 0.00 0.00 0.00 0.00 0.00

Total Base Cost 28.00 5.94 10.07 7.85 3.48 0.61

C. Contingencies 7.30 0.78 2.29 2.49 1.45 0.28

D. Financing Charges During Implementation 0.70 0.15 0.25 0.20 0.09 0.01

Total Project Cost (A+B+C+D) 36.00 6.87 12.61 10.54 5.02 0.91

% Total Project Cost 100% 19% 35% 29% 14% 3% PCMU = project coordination and management unit, PIU = project implementation unit. Source: PPTA estimates.

Page 26: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

21

F. Contract and Disbursement S-curve

G. Fund Flow Diagram

19. Explanations about the fund flow diagram are provided in the section Disbursement. Details are also provided in appendix 2.

-

20.00

40.00

2013 2014 2015 2016 2017 2018

Am

ou

nt

($ m

n)

Year

NEP: Bagmati River Basin Improvement Project

Planned Cum. Disbursements Planned Cum Contract Awards

Page 27: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

22

FUNDS FLOW DIAGRAM Authority Flow and Reporting Reimbursement Procedure: Fund flow and Reporting

MOF

MOUD

PCMU

WECS DOI

Project Implementation

ADB

GON Central Account FCGO

MOF

FCGO

Concerned DTCO (Under TSA system)

WECS DOI

PCMU

Contractors/suppliers/consultants

Authority Flow Reporting

Reimbursement

WA request through PCMU

Fund Flow Reporting

Page 28: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

23

IMPREST FUND AND DIRECT PAYMENT PROCEDURES: FUND FLOW AND REPORTING

ADB

PCMU

Imprest Account (USD)

Payment to large civil works contractors/consultants

WA request through PCMU

WECS DOI

Direct payment by ADB

Replenishment

Local contractors/suppliers/consultants (PCMU will make the payment through Imprest account including payments to be made of WECS and DOI as per their request)

Fund Flow Request/reporting Issue contract

GON Central account

Reimbursement to GON of ADB’s eligible expenditures

Payment through Imprest Account

Page 29: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

24

V. FINANCIAL MANAGEMENT

A. Financial Management Assessment

20. The financial management assessment (FMA) was conducted by the PPTA consulting team in November 2012 in accordance with ADB’s Guidelines for the Financial Management and Analysis of Projects6 and Financial Due Diligence: a Methodology Note, and Technical Guidance Notes.7 The FMA considered the capacity of the executing agency and implementing agencies, including funds-flow arrangements, governance, staffing, budgeting, accounting and financial reporting systems, internal control procedures, financial information systems, and internal and external auditing arrangements. The key findings are summarized below.

Table 1: Key Findings per area of assessment

Area of Assessment

Findings

Executing and Implementing Agencies

The Executing Agency is the Ministry of Urban Development (MOUD). The Implementing Agencies are the Water and Energy Commission Secretariat (WECS), the High Powered Committee for the Integrated Development of the Bagmati Civilization (HPCIDBC) and the Department of Irrigation (DOI)

Major Experiences of Managing Externally-financed projects

DOI is currently implementing the World Bank funded Irrigation and Water Resource Management Project and ADB funded Community Managed Irrigated Agri-Support Project, in addition to many other projects completed. HPCIDBC does not have experience with externally financed project. WECS is currently implementing a component of the World Bank funded Integrated Water Resources Management Project.

Fund Flow Arrangements

The fund flow arrangement of the ADB is from Financial Controller General, Ministry of Finance to the project management unit (PMU). This is an established procedure for other Bank funded projects.

Organization and Staffing

WECS finance division consists of two staff, an Under-secretary and an Accountant. HPCIDBC finance division consists of an Account Officer and Accountant. At the DOI Head Office, the finance division comprises of a Chief Accounting Controller, 2 Account officers, 5 Accountants and 3 Sub-Accountants. At the divisional level there is 1 Account Officer and an Accountant. The DOI accounting staff does not have experience in externally financed projects. WECS present staffs have experience in projects in previous organizations.

Accounting Policy and Procedures

The accounting system is prepared, designed, developed, and operated within the framework of the financial policies, strategies, and systems according to Nepal Accounting Standards with refinements to meet International Standards as per ADB format. However, training is needed to fulfill the later requirement.

Segregation of Duties

All the financial accounting functions are appropriately segregated before receipt and payment.

Budgeting System

A budget is prepared for all significant activities in detail to provide meaningful tools for easy monitoring. There is a mechanism to compare the budget with actual expenditure, which includes the statement of actual past expenditure and expected expenditure in the forthcoming fiscal year. The Finance Section is responsible for preparing and presenting the budget to the Project Director for approval.

6 ADB. 2005. Financial Management and Analysis of Projects. Manila. Available:

http://www.adb.org/Documents/Guidelines/Financial/default.asp 7 ADB. 2009. Financial Due Diligence: A Methodology Note. Manila. Available:

http://www.adb.org/documents/financial-due-diligence-methodology-note

Page 30: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

25

Area of Assessment

Findings

Policies/Procedures The accounting is on a cash basis as these are all government agencies

Internal Audit There is no internal audit at present However the DTCO is the internal auditor and their staff visit intermittently

External Audit The financial statement of agencies is audited by Auditor General of the government annually based on the National Accounting Standards.

Reporting and Monitoring

The financial and procurement reports of the agencies are prepared according to the accounting standard of government, which is consistent to International Standards. The reporting of the financial statement is on a monthly basis.

Information System The financial management and procurement system are not fully computerized. No automated accounting software program exists in these agencies for preparing financial reports. These systems are proposed in the project.

Table 2: Risk Matrix and mitigation measures

Findings Potential Risks Risk Mitigation

(a) Manual systems of accounting and reporting increases the risks of misstatement, error and fraud

Financial statements may not represent a true and fair view of the project

The project financial accounting must be computerized using a simple off-the-shelf accounting package

(b) Internal audit does not review internal controls in a systematic manner

Internal control weaknesses may go undetected leading to error and/or fraud

The Terms of Reference (TOR) of the external auditor to include review of internal controls

(c) External audit does not review internal controls in a systematic manner

Internal control weaknesses may go undetected leading to error and/or fraud and external audit may not comply with International Auditing Standards as required by ADB

The TOR of the external auditor to include review of internal controls and a Management letter stating internal control weaknesses

(d) WECS and HPCIDBC have limited experience with donor funded projects

Proper financial management of the project may be hampered by the lack of experience of staff

The PMU to be staffed by financial and procurement consultants experienced in ADB projects

21. The project implementing agencies are WECS, HPCIDBC and DOI. WECS is an apex body under the Ministry of Energy (MOE), HPCIDBC is under the Ministry of Urban Development (MOUD) and DOI is a government department under the Ministry of Irrigation (MOI). The financial management of all these institutions is generally satisfactory.

22. WECS. WECS has divisions for water resources, energy, legal and institutional development and a socio-economic and environment, each headed by a Joint Secretary. The Finance division has two staff; an Undersecretary and reporting to him, an Accountant. This staffing is adequate given the current scale of operations. WECS financial management is generally satisfactory, and reporting is done on a cash basis in the manner in which the operational and capital budgets have been expended.

Page 31: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

26

23. The Financial reporting system is based on cash book, budget sheet and vouchers, all prepared manually, in formats that have been agreed with the Office of the Auditor General (OAG). Reporting is in the form of budget heads for recurrent and capital budgets with amount allocated and amounted expended for the period and in cumulative terms.

24. WECS operates under the Treasury Single Account (TSA) system (recently implemented) where all payments are made by the District Treasury Comptroller (DTCO). The vouchers and other relevant documents are approved by WECS and a summary sheet of payments is sent to DTCO who processes the cheque in the name of the recipient. The experience of WECS is that the new TSA system has not resulted in undue delays in payments. The TSA was implemented to ensure that the GON had up-to-date information on government expenditure from a single source.

25. The Internal Auditor of WECS is the DTCO, whose officers visit WECS intermittently. The internal audit work is of the nature of checking to ensure that transactions are within government regulations and the resulting recovery of funds (if any). An audit of internal controls and the system is not part of the scope.

26. The annual external audit is carried out by the OAG. The external audit work is of the nature of checking to ensure that transactions are within government regulations and the resulting recovery of funds (if any). An audit of internal controls and the system is not, generally part of the scope.

27. WECS has limited experience with donor funded projects; it currently implements Component C of the World Bank funded Integrated Water Resources Management Project, which had a budget of Rs. 15 million for 2012 mainly for consultancy services. Both accounting personnel have experience with ADB procedures for Statements of Expenditure (SOE) and Withdrawal Applications, gained from previous experience.

28. HPCIDBC. HPCIDBC comprises of a 28 member committee which provides policy directive to the head of the institution who is designated Member Secretary/Project Manager. Reporting to the Project Manager, are divisions for construction, procurement, social development, finance and administration. As a government department, it is committed to implement the policies of the Ministry of Urban Development (MOUD).

29. The finance division of HPCIDBC comprises of an Account Officer and Accountant. HPCIDBC financial management is generally satisfactory. Since it is a government entity financial statements are not prepared on a commercial basis using accrual accounting rather it is on a cash basis, reporting the manner in which the operational and capital budgets have been expended. Financial reporting system is similar to that of WECS and also operates under the TSA. Similar to many government departments in Nepal, HPCIDBC does not have an internal auditor, but internal auditing is carried out by the DTCO. An officer of the DTCO is not usually assigned full-time to a single entity and therefore internal auditing is not carried out on a daily basis, as it should. The internal audit work is of the nature of checking to ensure that transactions are within government regulations and the resulting recovery of funds (if any). An audit of internal controls and the system is not, generally part of the scope. An external audit of HPCIDBC is carried out annually by OAG in a similar manner to WECS.

30. HPCIDBC has no experience with donor funded projects, and therefore the accounting staffs do not have experience with the system of Statements of Expenditure (SOE) and

Page 32: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

27

Withdrawal Applications. However, they have access to a national Financial Consultant until the end of 2014, who has experience with donor projects.

31. DOI. DOI is headed by a Director General with divisions for irrigation management, groundwater irrigation, surface irrigation, and design, planning and monitoring and support divisions for administration, finance and legal. As a government department, it is committed to implement the policies of the Ministry of Irrigation (MOI).

32. At the Head Office level, the finance division is headed by a Chief Accounting Controller with 2 Account Officers, 5 Accountants and 3 Sub-Accountants. At the divisional level, there is one Account Officer and an Accountant. DOI financial management is generally satisfactory.

33. The financial reporting system is similar to that of WECS and HPCIDBC. It also operates under the TSA. Similar to many government departments in Nepal, DOI does not have an internal auditor, but internal auditing is carried out by the DTCO and the external audit is by the OAG.

34. Conclusion and Recommendations. Financial management practice of the 3 IAs is generally sufficient for ADB purposes, once key risks highlighted in the risk matrix have been mitigated. However, HPCIDBC staff has no experience in implementing ADB or other donor funded project, whereas WECS staff have some experience. DOI are currently have implemented many ADB projects and are also currently implementing a project and their staff are well versed with ADB procedures. Therefore it is important that finance staff at both HPCIDBC and WECS receive training in ADB procedures. The following recommendations are required to improve the financial management of the IAs:

(i) Training of Accounting Personnel in ADB Procedures. Whilst some staff may have experience with the use of SOE, Withdrawal Applications and Imprest Account procedure, it is important that training on these procedures is provided on a regular basis. This is especially so since government staffs are transferred at regular intervals and newcomers may not be familiar with these procedures. Together with these training, staff should be provided with the formal documentation on ADB processes (ADB manuals and guidelines) that should be maintained in each agency for the project. There is sufficient experience in-country and a suitably experienced specialist will be recruited for the PCMU to provide this expertise. Among other, he will ensure that Financial and Accounting Manuals are in place or that government finance regulations are available to the PCMU and followed.

(ii) Strengthening Internal Auditing and Audit Training. The current internal and

external auditing procedures involve checking transactions for their accuracy and compliance with regulations. This is merely one aspect of auditing. The more important aspect is to ensure that internal controls are in place and actually follow the Government internal procedures. The TOR of the project external auditor will include the submission of a Management Letter with a review if internal controls and recommendations to improve any identified weaknesses.

(iii) Use of Computerized Accounting and Training. HPCIDBC and WECs

continue to use manual systems in their accounting, although PMUs implementing DOI projects use computerized systems. It is important that all three institutions and particularly the one hosting the PCMU use computerized systems to record project transactions to ensure that information is available in a

Page 33: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

28

timely and accurate manner. Such computerized accounting system should include an asset register that track both internal and ADB funded assets. The fixed Asset Register will be maintained, physical assets coded, and records reconciled to physical assets at least every 3 year. Provisions were made in the project budget to procure necessary equipments and provide consultant expertise for establishing computerized accounting and provide training.

B. Disbursement

1. Disbursement Arrangements for ADB Funds

35. The Loan proceeds will be disbursed in accordance with ADB’s Loan Disbursement Handbook (2012, as amended from time to time),8 and detailed arrangements agreed upon between the Government and ADB.

36. Prohibited investment activities. Pursuant to ADB's Safeguard Policy Statement (2009) (SPS),9 ADB funds may not be applied to the activities described on the ADB Prohibited Investment Activities List set forth at Appendix 5 of the SPS. All financial institutions will ensure that their investments are in compliance with applicable national laws and regulations and will apply the prohibited investment activities list (SPS, Appendix 5) to subprojects financed by ADB.

37. Basic Requirements. After the annual budget is approved by the parliament, MOF will issue authorization letter to MOUD and MOUD will issue authorization letter to PCMU, WECS and DOI separately to spend the annual budget as per approved annual program. PCMU will report to MOUD regarding the project implementation progress. There will be separate budget code No. in the Red Book of MOF to identify with P1 project. PCMU will be responsible to prepare and submit to MOUD the annual budget and program of the project in consultation with WECS and DOI. Annual program will be approved by the National planning commission. PCMU will maintain close coordination with the concerned stakeholders for timely budget release for the project implementation. GON will ensure for the allocation of sufficient counterpart fund for each FY.

38. Before the submission of the first withdrawal application, the borrower/recipient will submit to ADB sufficient evidence of the authority of the person(s) who will sign the withdrawal applications on their behalf, together with the authenticated specimen signatures of each authorized person. The format is provided in Appendix 4B (evidence of authority to sign withdrawal applications) of the Loan Disbursement Handbook 2012.

39. Imprest Fund Procedure. An Imprest Account for the project will be established in Nepal Rastra Bank. The currency of the Imprest account will be in USD. The imprest account is to be used exclusively for ADB’s share of eligible expenditures. The government EA who established the imprest account in its name is accountable and responsible for proper use of advances to the imprest account.

40. The ceiling of the advance to the Imprest Account is 10% of the respective loan/grant amount. The EA through the PCMU may request for initial and additional advances to the imprest account based on an Estimate of Expenditure Sheet10 setting out the estimated

8 Available at: http://www.adb.org/Documents/Handbooks/Loan_Disbursement/loan-disbursement-final.pdf

9 Available at: http://www.adb.org/Documents/Policies/Safeguards/Safeguard-Policy-Statement-June2009.pdf

Page 34: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

29

expenditures to be financed through the account for the forthcoming six (6) months, and submission of evidence satisfactory to ADB that the imprest account has been duly opened. Supporting documents should be submitted to ADB or retained by the borrower EA through the PCMU in accordance with ADB’s Loan Disbursement Handbook. The Imprest Account will be operated by the PCMU with the joint signatories as authorized by MOF. The Imprest Account will be used for small payments to the contractors, suppliers and consultants and to reimburse the ADB’s eligible expenditures to the GON treasury. 41. Statement-of-expenditure (SOE) procedure11. The SOE procedure will be used for reimbursement of eligible expenditures or liquidation of advances to the imprest account(s). the ceiling of the SOE procedure is the equivalent of [$100,00011] per individual payment. Supporting documents and records for the expenditures claimed under the SOE should be maintained and made readily available for review by ADB's disbursement and review missions, upon ADB's request for submission of supporting documents on a sampling basis, and for independent audit. Reimbursement and liquidation of individual payments in excess of the SOE ceiling should be supported by full documentation when submitting the withdrawal application to ADB.

2. Government counterpart Funds and contract award/disbursement projections

42. GON will provide counterpart fund as well as ADB’s reimbursable fund to the project as per financing and disbursement percentage. The expenditures to be funded by the donor funding is first made by the government and later on it is reimbursed from the donor as per eligible expenditure. Fund will be channelized through Financial Comptroller General Office (FCGO). Concerned District Treasury and Controller Office (DTCO) will issue the cheques in the name of contractors/suppliers/consultants etc as per the payment order request from PCMU, DOI and WECS as per newly implemented GON treasury single account (TSA) system. PCMU, DOI and WECS will maintain the separate record for GON fund and donor’s fund and prepare/submit the monthly/annual financial statement to the concerned DTCO in each month. Similarly, DOI and WECS will also submit the monthly/annual financial statements along with SOEs to PCMU.

43. PCMU will then consolidate and verify the eligible expenditures and prepare/submit withdrawal application to ADB along with SOEs and supporting documents. The Project director will be the entity authorised to sign on the withdrawal applications. A copy of the bank statement of Imprest account, Imprest account turnover ratio, Imprest account reconciliation statement will be also submitted along with the withdrawal application for replenishment.

44. Disbursment practice. PCMU should submit to ADB, annual contract awards and disbursement projections at least a month before the start of each calendar year using the templates in Appendix 2. PCMU is responsible for (i) requesting budgetary allocations for counterpart funds, and (ii) collecting supporting documents. PCMU is responsible for preparing and sending withdrawal applications to ADB.

11

SOE forms are available in Appendix 9B and 9Cof the Loan Disbursement Handbook. 11

For project loans, normally the ceiling is not exceeding $100,000 per individual payment (section 9.18 of the Loan Disbursement Handbook).

Page 35: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

30

C. Project Financial Reporting, Auditing, and Public Disclosure

1. Project Financial Reporting

45. The government will maintain, or cause to be maintained, separate financial records for the project, by funding source, and prepare project financial statements in accordance with financial reporting arrangements acceptable to ADB. The PCMU under HPCIDBC will be the reporting entity and will compile information from both DOI and WECs PIUs. The reporting will be in English. A template for financial statement is provided in Appendix 2.

D. Accounting and Auditing

46. The PCMU, WECS and DOI will maintain separate books and records by funding source for all expenditures incurred on the project and accounts adequate to identify the goods and services financed by the loan proceeds, financing received, expenditure incurred, and use of counterpart fund. The account books will be maintained in accordance with sound accounting principles. Consolidated project financial statements and related financial statements will be prepared in accordance with international accounting principles and practices or those prescribed by the Government’s accounting laws and regulations. ADB reserves the right to verify the project’s financial statements’ records to confirm that the ADB’s financing is used in accordance with ADB’s policies and procedures E. Auditing

47. The HPCIDBC/PCMU will cause the detailed consolidated project financial statements to be audited in accordance with International Standards on Auditing and/or in accordance with the Government's audit regulations by an auditor acceptable to ADB. The audited financial statements will be submitted in the English language to ADB within 6 months of the end of the fiscal year by the executing agency. The annual audit report will include a separate audit opinion on the use of the imprest accounts and loan proceeds, and the SOE procedures and compliance with all financial covenants of the Loan Agreement, and a management letter. The audited project financial statements will be disclosed on ADB‘s website in accordance with ADB‘s Public Communications Policy (2011). The Government and PCMU have been made aware of ADB’s policy on delayed submission, and the requirements for satisfactory and acceptable quality of the audited accounts financial statements. ADB reserves the right to verify the project's financial accounts to confirm that the share of ADB’s financing is used in accordance with ADB’s policies and procedures. Further, any critical audit observations on the project should be reported to ADB, and action taken should also be monitored. A template statement of audit needs is attached in Appendix 3.

48. A formal request for the project to be included in the OAG audit schedule should be sent through the DEA to OAG office. This request is best sent when the loan and project agreements are signed, and the request should include a copy of the loan and project agreements, and any other relevant documents. OAG would then advise the appropriate field office to include the project in its audit schedule. 49. In addition, to ensure that audited financial statements are submitted on a timely basis, HPCIDBC through the PCMU should submit its consolidated project financial statements for audit to OAG within 3 months from the close of the financial year. To this end, all accounts of DOI, HPCIDBC and WECS should be closed within two months of the end of the FY and submitted to HPCIDBC to ensure timely consolidation. HPCIDBC shall be responsible for the

Page 36: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

31

consolidated Project financial statements. By 15 October of each year, OAG should receive the unaudited financial statements. It will then take 3 months to complete the audit, and issue an opinion no later than 6 months from the end of the financial year.

VI. PROCUREMENT AND CONSULTING SERVICES

A. Advance Contracting and Retroactive Financing

50. The government has requested for advance contracting and retroactive financing to expedite implementation of the project. All advance contracting and retroactive financing will be undertaken in conformity with ADB’s Procurement Guidelines (2013, as amended from time to time)12 and ADB’s Guidelines on the Use of Consultants (2013, as amended from time to time).13 The issuance of invitations to bid under advance contracting and retroactive financing will be subject to ADB approval. The government, MOUD and HPCIDBC have been advised that approval of advance contracting and retroactive financing does not commit ADB to finance the Project. Specifically, the government has requested ADB's approval of advance contracting for the recruitment of PMSC for the operation of the PCMU. Retroactive financing will be up to 10% of the total ADB loan amount for eligible expenditures incurred prior to loan effectiveness but not earlier than 12 months prior to the signing of the loan agreement.

51. Advance contracting. Advance contracting includes tendering and bid evaluation for civil works packages, equipment and recruitment of consultants. The detailed advance action schedules, which will be updated on regular basis, are presented in the tables below.

Table 5.1: Project Management Design and Supervision Consultant (PMSC) No Activity Days Timeframe Action By Status

1 Prepare Request for Expression of Interest (REOI) 0 Completed

2 ADBBO 0 9 July 2013 ADB Completed

3 EOI submission 30 7 Aug 2013 Completed

4 Issue Request For Proposal (RFP) 47 22 Sept 2013 ADB Not yet due

5 Proposal Submission 45 7 Nov 2013 ADB Not yet due

6 Technical Evaluation 10 17 Nov 2013 ADB Not yet due

7 Public Opening of the Financial Proposals 21 8 Dec 2013 ADB Not yet due

8 Invite 1st Ranked Firm – Negotiate/Draft Contract 30 7 Jan 2014 PCMU Not yet due

9 Contract Signing & Issue Notice to Proceed 36 12 Feb 2014 PCMU Not yet due

Table 5.2: Construction of River Works No Activity Days Timeframe Action By Status

1 Finalize Bidding Document 0 Sept 2014 PMDSC Not yet due

2 ADB Review & non-objection 30 30 Oct 2014 PCMU Not yet due

3 Final Revisions as Necessary 5 4 Nov 2014 ADB Not yet due

4 Advertise Invitation For bids in Newspaper/ADBBO 10 14 Nov 2014 PCMU Not yet due

5 Preparation of bids 45 29 Dec 2014 external Not yet due

6 Public opening 1 30 Dec 2014 PCMU Not yet due

7 Evaluate Technical Envelop (Qual./Technical) 25 24 Jan 2015 PCMU Not yet due

8 Review by procurement committee 7 31 Jan 2015 PCMU Not yet due

9 ADB‘ Review 20 20 Feb 2015 ADB Not yet due

10 Public opening 5 25 Feb 2015 PCMU Not yet due

8 Evaluate Financial Bid 8 5 Mar 2015 PCMU Not yet due

9 Bid Evaluation Report & Recommend Award 5 10 Mar 2015 PCMU Not yet due

10 ADB Review and No Objection 20 30 Mar 2015 ADB Not yet due

11 Issue Notice of Award 6 4 Apr 2015 PCMU-PMC Not yet due

12 Contract signing & Issue Notice to Proceed 15 19 Apr 2015 PCMU Not yet due

12

Available at: http://www.adb.org/Documents/Guidelines/Procurement/Guidelines-Procurement.pdf 13

Available at: http://www.adb.org/Documents/Guidelines/Consulting/Guidelines-Consultants.pdf

Page 37: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

32

Table 5.3: Detailed Design and Construction of Dhap Dam Works No Activity Days Timeframe Action By Status

1 Finalize Bidding Document 0 On going

2 ADB Review & non-objection 30 30 Sept 2013 DOI through PMCU

Not yet due

3 Final Revisions as Necessary 5 5 Oct 2013 ADB Not yet due

4 Advertise Invitation For bids in Newspaper/ADBBO 10 15 Oct 2013 DOI Not yet due

5 Preparation of bids 45 29 Nov 2013 External Not yet due

6 Public opening 1 30 Nov 2013 DOI Not yet due

7 Evaluate Technical Envelop (Qual./Technical) 25 25 Dec 2013 DOI Not yet due

8 Review by procurement committee 7 1 Jan 2014

9 ADB‘ Review 20 21 Jan 2014 DOI through PCMU

Not yet due

10 Public opening 5 26 Jan 2014 ADB Not yet due

11 Evaluate Financial Bid 8 3 Feb 2014 PCMU Not yet due

12 Bid Evaluation Report & Recommend Award 5 8 Feb 2014 DOI through PCMU

Not yet due

13 ADB Review and No Objection 20 28 Feb 2014 ADB Not yet due

14 Issue Notice of Award 6 6 Mar 2014 DOI Not yet due

15 Contract signing & Issue Notice to Proceed 15 21 Mar 2014 DOI Not yet due

Table 5.4 Detail design: Nagmati Dam

No Activity Days Timeframe Action By Status

1 Prepare Request for Expression of Interest (REOI) PPTA/WECS On going

2 Advertise in the newspaper & ADBBO 0 30 Oct 2013 DOI Not yet due

3 EOI submission 30 29 Nov 2013 External Not yet due

4 Submission(1) to ADB: shortlisting/Draft RFP 15 14 Dec 2013 DOI through PCMU

Not yet due

5 ADB‘s Review & No-Objection 20 3 Jan 2014 ADB Not yet due

6 Issue Request For Proposal (RFP) 5 8 Jan 2014 DOI Not yet due

7 Proposal Submission 45 22 Feb 2014 external Not yet due

8 Submission (2) to ADB Technical Evaluation 15 9 Mar 2014 DOI through PCMU

Not yet due

9 ADB‘ Review & No-Objection 16 25 Mar 2014 ADB Not yet due

10 Public Opening of the Financial Proposals 8 2 Apr 2014 DOI Not yet due

11 Submission (3) to ADB: Financial Evaluation/Ranking 10 12 Apr 2014 DOI through PCMU

Not yet due

12 ADB‘ Review & No-Objection 16 28 Apr 2014 DOI Not yet due

13 Invite first ranked firm – negotiate draft contract 8 6 May 2014 DOI Not yet due

14 Submission (4) to ADB: Draft negotiated contract 5 11 May 2014 DOI through PCMU

Not yet due

15 ADB Review & non-objection 15 26 May 2014 ADB Not yet due

16 Contract Signing & Issue Notice to Proceed 18 13 Jun 2014 DOI Not yet due

Table 5.5: Decision Support System, FEW, WQ and IRBMP

No Activity Days Timeframe Action By Status

1 Prepare Request for Expression of Interest (REOI) PPTA/WECS On going

2 Advertise in the newspaper & ADBBO 0 30 Sept 2013 WECS Not yet due

3 EOI submission 30 30 Oct 2013 External Not yet due

4 Submission(1) to ADB: shortlisting/Draft RFP 15 14 Nov 2013 WECS through PCMU

Not yet due

5 ADB‘s Review & No-Objection 20 4 Dec 2013 ADB Not yet due

6 Issue Request For Proposal (RFP) 5 9 Dec 2013 WECS Not yet due

Page 38: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

33

7 Proposal Submission 45 23 Jan 2014 external Not yet due

8 Submission (2) to ADB Technical Evaluation 15 7 Feb 2014 WECS through PCMU

Not yet due

9 ADB‘ Review & No-Objection 16 21 Feb 2014 ADB Not yet due

10 Public Opening of the Financial Proposals 8 1 Mar 2014 WECS Not yet due

11 Submission (3) to ADB: Financial Evaluation/Ranking 10 11 Mar 2014 WECS through PCMU

Not yet due

12 ADB‘ Review & No-Objection 16 27 Mar 2014 WECS Not yet due

13 Invite first ranked firm – negotiate draft contract 8 4 Apr 2014 WECS Not yet due

14 Submission (4) to ADB: Draft negotiated contract 5 9 Apr 2014 WECS through PCMU

Not yet due

15 ADB Review & non-objection 15 24 Apr 2014 ADB Not yet due

16 Contract Signing & Issue Notice to Proceed 18 12 May 2014 WECS Not yet due

B. Procurement of Goods, Works and Consulting Services

52. A procurement capacity assessment was undertaken by the PPTA procurement expert early 2013 for all three IAs and concluded that while DOI had good experience with procurement with external aided project including ADB, WECS and HPCIDBC had respectively little and no experience with external aid project. Overall the procurement capacity risk was rated average. Consequently, adequate resources were built in the PMDSC to train and support PCMU procurement activities. Similarly trainings on ADB procurement rules and guidelines will be regularly proposed to strengthen PCMU capacity.

53. All procurement of works, goods and services, financed by ADB, will be carried out in accordance with ADB‘s Procurement Guidelines (2013, as amended from time to time) (footnote 14). International competitive bidding (ICB) procedures will be used for any civil works contract estimated to cost more than $1 million, and any goods contract estimated to cost more than $500,000. National competitive bidding (NCB) procedures will be used for any civil works contract estimated to cost $1 million or less and any goods contract estimated to cost $500,000 or less. Shopping will be used for any civil works or goods contract estimated to cost less than $100,000. Consultants‘ selections and engagements will be carried out in accordance with ADB‘s Guidelines on the Use of Consultants (2013, as amended from time to time) (footnote 15). ADB will undertake the recruitment of the project management design and supervision consultants (PMDSC) on behalf of the government. The EA retains the responsibility for negotiating and signing the contract with the consultant, issuing the notice to proceed, and supervising the consultant’s services (reference: Project Administration Instruction, section 2.05, para. 47). The consulting firms will be engaged using the quality- and cost-based selection (QCBS) method with a standard quality-cost ratio of 90:10. Before the start of any procurement, ADB and the government will review the public procurement laws of the government to ensure consistency with ADB‘s Procurement Guidelines. A Procurement Plan is given in Appendix 4.

54. A total of 364 person months of consulting services (43 person-months international and 321 person-months national) will be provided to support the PCMU in project management planning and implementation, design review, RBO formation support, Development of an Integrated River Basin Development Management plan, procurement assistance and construction supervision.

55. A total of 97 person-months of consultancy services (25 person-months international and 72 national will be provided to support WECS in establishing a Decision Support System for

Page 39: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

34

support to Bagmati RBO formation and preparing the 15 years integrated River Basin Development Master Plan. In addition, a total of 20 person-months (8 international person-months and 12 national person-months) will be provided to upgrade the HPCIDBC water quality monitoring system. Moreover, a total of 31 person-months (9 person-months international and 22 person months national) will be provided to Department of Hydrology and Meteorology and upgrade their existing flood forecasting system and provide operational flood warning dissemination.

56. 12 person months (national) will be provided for independent environmental monitoring and evaluation. Under a TA Grant 22 person-months of individual consultants (international) will be provided to support WECS for RBO formation.

57. Further, an estimated 136 person-months (all national) of NGOs will be provided to assist the PCMU in implementing the Community Awareness and Participation Program and Gender Equality and Social Inclusion (GESI) Action Plan, Rainwater Harvesting and Solid Waste program at household level and Watershed Management in Shivapuri National Park.

C. Consultant's Terms of Reference

58. Draft terms of reference for the consultants’ packages are available in Appendix 5.

VII. SAFEGUARDS

59. Environmental Safeguards. The Environmental Impact Assessment (EIA) prepared for the project includes Environmental Management Plans which describe mitigatory measures to be adopted during design, construction and operation of the dam/s and the Upper Bagmati River Improvement works The following are institutional roles and responsibilities to ensure the EMPs are implemented during design, construction and operation. The MOUD will in parallel, obtain approval under GON regulations. This will be obtained by January 2014.

60. The Project Coordination and Management Unit (PCMU) with assistance from the environmental consultant engaged by the PMDSC is to do the following: (ii) update the EIA including EMP based on detailed designs; (iii) ensure EMPs are included in bidding documents and civil works contracts; (iv) provide oversight on environmental management aspects of the project and ensure EMPs are implemented by the contractors (v) facilitate and ensure contractors comply with all government rules and regulations regarding forest and road permits as well as any other relevant approvals required for works; (vi) supervise and provide guidance to the contractors to properly carry out implementation of the EMPs; (vii) review, monitor and evaluate the effectiveness with which the EMPs are implemented, and recommend necessary corrective actions to be taken as necessary; (viii) consolidate quarterly environment monitoring reports f and submit semi-annual monitoring reports to ADB; (ix) ensure timely disclosure of final EIAs in locations and forms accessible to the public; (x) take corrective actions when necessary to ensure no environmental impacts; (xi) conduct ongoing consultation with the community during implementation of the project; and (xii) establish a grievance redress mechanism and ensure it is operated satisfactorily.

61. The preliminary designs have incorporated measures to mitigate risks related to earthquakes, landslides, floods, and climate change. The detailed designs of the Dhap Dam and Upper Bagmati on River Improvement works will be based on projections of impacts of climate change on the river basin air temperature impact on evaporation, rainfall run-off and river hydrology.. The PCMU will include an environmental specialist who will be trained and work with

Page 40: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

35

the PMSC environmental specialist in monitoring implementation of the EMP during construction. During operations, it is expected that the HPCIDBC/RBO will take on the function of environmental monitoring.14 Training will be provided to staff ear marked in these organizations. The estimated cost for implementing the EMP is $ 132,500

62. Involuntary Resettlement. No resettlement is foreseen necessary under the project. However, a Draft Resettlement Framework (DRF) has been prepared for the project as a prudent measure to guide the preparation of safeguards documents for mitigating any unforeseen resettlement impacts during project implementation. (b) Indigenous Peoples. No IP issues are foreseen to be addressed during the project implementation.

VIII. GENDER AND SOCIAL DIMENSIONS

63. The PCMU will ensure that civil works contracts and bidding documents under the project include specific provisions requiring contractors to comply with all (i) applicable labour laws and core labour standards on (ii) prohibition of child labour as defined in national legislation for construction and maintenance activities, on (iii) equal pay for equal work of equal value regardless of gender, ethnicity or caste, and on (iv) elimination of forced labour, and (v) the requirement to disseminate information on sexually transmitted diseases including HIV/AIDS to employees and local communities surrounding the project sites.

64. A Gender Equality and Social Inclusion (GESI) action plan has been prepared for the project with the objective to implement all components of the project in a GESI responsive manner. The Strategy guides the development of GESI Action Plan during detail project preparation. The strategy encompasses both the Asian Development Bank (ADB) and Government of Nepal’s broader principles on GESI as it relates to water resources management as specified by the proposed amendments in the Irrigation Policy, 2069 and National Water Resources Policy, 2011, also adhering to the Three Year Interim Plan of Nepal-2007 of GON on ensuring inclusion of the vital stakeholders as right holders groups, such as, women, indigenous populations, dalits and socially excluded groups in all development programs. It is required that specific gender design features are to be included in 50% or more of project outputs. Most of these in turn should have at least 3 gender design features and targets.

65. The project will organize orientation to the staff and partner implementing NGOs on BRBIP GESI aims and the operational strategy, containing potential actions and measuring (monitoring) indicators. Thus capacity building on GESI concept and skills will be done at two levels, community and project staff level. While doing this activity at staff and partner NGO level, the responsible counterpart government implementing agencies will also be included for capacity building so that a common understanding about GESI realities and approach is internalized within the responsible institution for sustaining the processes, activities, institutions initiated or strengthened by BRBIP.

66. The PCMU is to ensure implementation of the GESI, and will be supported by the PMSC to implement these plans. An adequate budget is allocated for the PCMU/PMSC to implement the GESI. A Social Development and Gender Specialist in PMSC will assist the Social Mobilisation & Communication Unit in the PCMU (staffed with a sociologist, a gender specialist and a sociologist) in monitoring and reporting on gender and social aspects.

14

Once the river basin organization is formed HPCIDBC will become part of the RBO

Page 41: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

36

67. Pursuant to ADB's Safeguard Policy Statement (2009) (SPS), ADB funds may not be applied to the activities described on the ADB Prohibited Investment Activities List set forth at Appendix 5 of the SPS.

Page 42: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

37

Table 6.1: Gender Equality and Social Inclusion (GESI) Action Plan. Activity Targets/Performance Indicators Responsibility Year

Output 1: Systems and capacity for integrated and participatory river basin management established

1 Establishment of RBOs with participation of women, poor and excluded in both leadership (council, secretariat, sub basin committees, and IRMCs) and non-leadership (staff) positions

RBO established with: at least 20% women and 15%representation from the diverse communities of the river basin

RBO Secretariat: at least 2 core professional staff are women out of 5 and at least 33% in technical, managerial and other staff positions.

Sub-basin committees and other committees: 33% women and 20% from other social groups representing local communities and CSOs

IRMC: at least 33% women and 20% from other social groups

Grievance redress committee: 33% women and special support and privacy for women involved in any grievance process

WECS, HPCIDBC

Yrs 1 and 2

2 IRBDMP for Bagmati 2015-2040 prepared Consultation process for the development and approval of the IRBDMP includes local communities of which 50% are women

Women only forums will be convened for women to participate in the consultation process and disclosure (where needed)

IRBDMP for Bagmati is inclusive and equitable in approach and addresses the needs/priorities of local communities

IRBDMP consultants , WECs , HPCIDBC

Year 1 and 2

3 The database management system (DSS) includes gender and socio-economic parameters

The information system includes sex and caste/ethnicity disaggregated data and information

DSS consultants, WECs

Year 2 and 3

4 GESI responsive social mobilization plan developed for effective implementation of IRBDMP Inclusive and representative NGO Platform established Livelihood activities and awareness raising activities targeting local communities especially women, poor and socially excluded implemented

Increased number of women, poor and excluded utilizing the project resources, benefits through social mobilization efforts

NGO platform includes representatives from NGOs, local village groups with 50% participation of women

Livelihood activities support to 296 HHs in the SNNP gives preference to poor, FHH and excluded groups

IRBDMP consultants , WECs, HPCIDBC

Year 1 and 2

Output 2: Improved river bank environment in urban areas

5 Improved river environment through rehabilitation/ protection of ghats, river banks, regulators and engagement with local community, basin settlers, and local CSOs/NGOs

300 pm employment generated from rehabilitation works of which 20% is by women and 10% by poor and socially excluded .

Equal pay for work of equal value

HPCIDBC Year 2 to 4

6 Local users committee mobilised for community participation for conservation related activities in the water shed management areas comprising women and excluded groups

33% of women members and 20% from the poor and socially excluded groups women in local users groups, and proportionate representation from other social groups

Preference to be given to local user groups/committees for protection/conservation works and river training

IEC materials on river environment conservation are simple and in local languages and disseminated to all basin stakeholders through Radio, TV

NGOs PMDSC First year

Page 43: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

38

Output 3: Increased water availability in the basin during dry season and watershed conservation

7 Capacity building training program on RWH system installation and O&M includes women and socially excluded

Sub-engineers, engineers, architects, plumbers – 20% women as trainees

Students: 50% women and proportionately from other social groups

HH level: At least one female member of each of the interested HHs are trained on RWH installation to O&M and solid waste management, special consideration to FHHs.

Information materials on RWH technology are in simple and local language

NGOs PMDSC Year 2 and 3

8 Training and awareness programs on conservation and protection of watershed areas to the stakeholders – users groups, local settlers, national park staff, army personnel to include women and socially excluded groups

At least 30% of the total 750 trained on conservation and protection of watershed, solid waste disposal are women and proportionately from socially excluded groups.

NGOs, PMDSC Year 2 to 4

9 Training and demonstration on use of energy efficient wood cooking stoves – key target women of SNNP settlement

100% women of the 250 households to be considered will receive training and demonstration kits

HPCIDBC/NGO Year 2 to 4

Output 4: Flood Forecasting and Early Warning System in the Bagmati River Basin is functional

10 Community –based early warning system and flood adaptation programs implemented.

Community based early warning system and flood adaptation program considers specific needs of women and vulnerable groups

DHM Year 2 to 4

Output 5: Efficient Project Management and Effective Stakeholder Coordination

11 Ensure GESI-sensitive project management GESI Action Plan adopted and annual action plan formulated (Responsibility: PCMU)

Implementation of GESI Action plan monitored and reported in quarterly progress reports and on QCPRM (Responsibility: PCMU)

HPCIDBC, RBO, WECS, sub-basin committees and local users groups, and partner NGOs oriented on the GESI Action Plan as well as on the use of GESI mainstreaming tools (Responsibility: PCMU)

GESI-sensitive monitoring system established and regularly populated with sex-,ethnicity-, caste-, and poverty level-disaggregated data. (Responsibility: PCMU)

Local community motivators and social mobilisers hired include 50% women and 40% from socially excluded groups

PCMU and PMDSC

Year 1 to 5

12 Capacity building on GESI mainstreaming conducted for community, project staff/government officials and NGOs

Community level training: 50% women and proportionate representation from excluded groups

Project staff, government officials and NGOs: 30% women

PMDSC/PCMU Year 1 to 2

Page 44: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

39

CSO = civil society organization, DSS = decision support system, DWIDP = Department of Water Induced Disaster Prevention, FHH = female headed household, GESI = gender equity and social inclusion, HH = household, HPCIDBC = High Powered Committee for the Integrated Development of the Bagmati Civilization, IEC = information education and communication , IRBDMP = integrated river basin development master plan, IRMC = integrated resource management committees, NGO = nongovernment organization, O&M = operation and maintenance, PCMU = project coordination and management unit, QCPRM = quarterly country portfolio review meeting , RBO = river basin organization, RWH = rain water harvesting , SNNP = Shivapuri Nagarjun National Park, WECS = Water and Energy Commission Secretariat. Source: Asian Development Bank.

Page 45: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

40

IX. PERFORMANCE MONITORING, EVALUATION, REPORTING AND COMMUNICATION

A. Project Design and Monitoring Framework

Design Summary Performance Targets and Indicators with

Baselines

Data Sources and Reporting

Mechanisms Assumptions

and Risks

Impact

Improved water security in the Bagmati River Basin

By 2025: Water allocation recommendations by the RBO council approved (baseline: no water allocations currently in the basin)

Water availability in the upper BRB during the dry season improved by 50% from 2013 baseline (average 38 l/s at Gaurighat)

Water quality in the upper Bagmati River improved to bathing water standards of World Bank and World Health Organization (DO > 3 mg/l) at Pashupatinath temple on a perennial basis (baseline: highest DO = 1 mg/l in 2012–2013 dry season)

Water downstream of Pashupatinath temple in Kathmandu City improved to standards for partial contact

a (DO > 1.5 mg/l) (baseline:

highest DO = 0 mg/l in 2012–2013 dry season)

WECS annual reports DHM and GWRDB surface and groundwater annual records RBO Secretariat (HPCIDBC) water quality assessment reports RBO Secretariat (HPCIDBC) water quality assessment reports

Assumption

Related projects in Kathmandu addressing problems in drinking water supply and sewage collection and/or water treatment are successfully completed on time. Risk

Climate change impact exceeds model projections.

Outcome

Improved river health and flood management

By the end of the project (by 2019):

Bathing water quality standard (DO> 3 mg/l) achieved at Pashupatinath when reservoir water is released (baseline: highest DO = 1 mg/l in 2012–2013 dry season)

Annualized cost of flooding in Bagmati River Basin reduced by 10% (baseline 1993–2013: $850,000)

b

RBO Secretariat (HPCIDBC) water quality assessment reports

DWIDP annual reporting

Assumption

KVWMP is implemented without delay and achieves the target of effluent standards of WWT plants at Gokarna and Guheshwori

Outputs

1. Established systems and capacity for integrated and participatory river basin management

By 2016: 15-year IRBDMP for Bagmati approved by majority of basin stakeholders

By 2017: Water resources (including quality and quantity) real-time data and decision support systems in place

By 2018: RBO legally established, financed, and staffed (20% are women and 15% representatives of diverse communities in the river basin, in leadership and non leadership positions)

For all indicators:

Project progress reports prepared by WECS and HPCIDBC

Assumption

Frequent turnover of government officials does not affect commitment for IWRM. Risk

Nepal adopts a federal structure that fails to recognize water as a state subject.

2. Improved riverbank environment in urban areas

By 2017: 7.2 km of river corridor constructed with aesthetic river walls, green zones and recreational amenities employing 20% of women and 10% poor and socially excluded as workers during construction

For all indicators:

Project progress reports prepared by MOUD and HPCIDBC

Assumption

Solid waste problems related to provision of collection services and deposition are solved through the implementation of the

Page 46: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

41

Design Summary Performance Targets and Indicators with

Baselines

Data Sources and Reporting

Mechanisms Assumptions

and Risks

11 aeration weirs constructed

2 regulators rehabilitated

By 2018: 7 VDCs and user community groups, comprising at least 33% women members and 20% from poor and socially excluded groups, mobilized to monitor and prevent solid waste disposal into the river corridor

300 households adopt improved solid waste management

By 2019: 2 km of riverbank maintained with private sector support

2011 Solid Waste Act Risk

Political instability compromises necessary coordination between municipalities, VDC and HPCIDBC on river bank monitoring and maintenance

3. Increased water availability in the basin during dry season and improved watershed conservation

By 2017: 850,000 m

3 of storage capacity established

with the Dhap dam

By 2019:

178,000 m3 rooftop water harvested annually

by 2,500 households to provide 45,000 m3 of

water supply and recharge 135,000 m3 of

groundwater

12.5 ha erosion-prone cultivated area in SNNP stabilized with fruit-tree planting and improved cropping practices

80% of households converted from traditional wood stoves to energy-saving stoves (baseline 2013: 296 households in SNNP use traditional stoves)

For all indicators:

Project progress reports prepared by MOUD and DOI

Assumption

SNNP authorities continue to cooperate with the project. Risk

Construction of water storage in SNNP is resisted by other stake holders.

4. Functioning flood forecasting and early warning system for the Bagmati River Basin

By 2016: Flood early warning system in place

By 2017: Flood warnings disseminated 72 hours before flood events (baseline 2013: 24 hours before flood events with low reliability)

By 2018: 25 most flood-prone riverine villages implement community-based flood adaptation programs with protocols that consider needs of women, children, disabled, and elderly during disasters

For all indicators:

WECS and DHM annual reports

5. Efficient project management with effective stakeholder communication

By 2013: PCMU established with at least 33% women representation

Sector PIUs established

The project communication strategy is successfully implemented

By 2019: Annual project contract award and disbursement targets met

For all indicators:

PCMU and PIU annual and quarterly progress reports

Page 47: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

42

Activities with Milestones Inputs

1. Established systems and capacity for integrated and participatory river basin management

1.1 Recruit DSS, FFEW, IRBDMP water quality consultants (Sep 2013–May 2014) 1.2 Select and mobilize RBO and legal consultants (Oct 2013–Feb 2014) 1.3 Conduct consultations to finalize the RBO structure (Feb–Oct 2014) 1.4 Draft new water act and legislature for the RBO (Mar 2014–Apr 2015) 1.5 Procure equipment for DSS and water quality (Jun 2014–Aug 2014) 1.6 Develop and implement DSS and water quality monitoring system (Jun 2014–Aug 2016) 1.7 Develop IRBDMP (Mar 2014–Apr 2016) 2. Improved riverbank environment in urban areas

2.1 Recruit NGOs for river community mobilization, gender, and solid waste management (Jan–Jul 2014)

2.2 Form community groups, establish stakeholder consultations and gender groups for the duration of the project (Jul 2014–Dec 2015)

2.3 Undertake community mobilization, stakeholder interaction, and gender activities (Apr 2016–Oct 2018) 2.4 Undertake detailed design by PMDSC (Feb–Aug 2014) 2.5 Construct river improvement works (Apr 2015–Dec 2017)

3. Increased water availability in the basin during dry season and watershed conservation

3.1 Process approval of EIA for Dhap dam (May 2013–Apr 2014) 3.2 Tender design and build contract for Dhap dam (Sep 2013–Mar 2014)

Loan ADB: $25.5 million Government: $6.0 million Grant ADB: $4.5 million WFPF: $0.5 million

3.3 Recruit Nagmati dam design consultants (Oct 2013–Jun 2014) 3.4 Recruit NGOs for watershed management and rainwater harvesting (Mar–Jul 2014) 3.5 Process approval of EIA for Dhap dam (May 2013–Apr 2014) 3.6 Undertake detailed design for Dhap dam by contractor (Jul 2014) 3.7 Undertake detailed design for Nagmati dam (Jun 2014–Jul 2015) 3.8 Implement EMP for Dhap dam construction (Nov 2014–Jun 2017) 3.9 Construct Dhap dam (Nov 2014–Jun 2017) 3.10 Implement rainwater harvesting and watershed management (Apr 2014–Oct 2015)

4. Functional flood forecasting and early warning system in the Bagmati River Basin

1.1 Mobilize FFEW consultants under DSS contract (May 2014) 1.2 Procure equipment for FFEW (Aug 2014–Oct 2014) 1.3 Develop, implement, and test FFEW (Oct 2014–Jun 2016)

5. Efficient project management and stakeholder coordination

5.1 Recruit project management design and supervision consultants (Jul 2013–Feb 2014)

5.2 Form a PCMU (May–Nov 2013) and PIUs (May–Dec 2013)

5.3 Set up financial management system and open imprest account in the PCMU (Oct–Nov 2013)

5.4 Set up monitoring and evaluation system in the PCMU (Oct 2013–Apr 2014)

5.5 Implement communication strategy (Apr 2014–Oct 2018)

5.6 Produce quarterly and annual reports (Feb 2014) 5.7 Establish grievance mechanism in the PCMU (Aug 2014)

ADB = Asian Development Bank, BRB = Bagmati River Basin, DHM = Department of Hydrology and Meteorology, DO = dissolved oxygen, DOI = Department of Irrigation, DSS = decision support system, DWIDP = Department of Water Induced Disaster Prevention, EIA = environmental impact assessment, EMP = environmental management plan, FFEW = flood forecasting and early warning system, GWRDB = Ground Water Resource Development Board, ha = hectare, HPCIDBC = High Powered Committee for the Integrated Development of the Bagmati Civilization, IRBDMP = integrated river basin development master plan, IWRM = integrated water resources management, km = kilometer, KVWMP = Kathmandu Valley Wastewater Management Project, l/s = liter per second, m

3 = cubic meter, mg/l = milligram per liter,

MOUD = Ministry of Urban Development, NGO = nongovernment organization, PCMU = project coordination and management unit, PIU = project implementation unit, PMDSC = project management design and supervision consultant,

RBO = river basin organization, SNNP = Shivapuri Nagarjun National Park, UBR= upper Bagmati River, VDC = village

development committee, WECS = Water and Energy Commission Secretariat, WFPF = Water Financing Partnership Facility.

Page 48: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

43

a The PCMU will select the water quality monitoring points.

b The costs of flooding are based on average costs from 2000 to 2004 and the costs of the large flood in 1993, amortized. (SILT et.al. 2005. Preparation of Water-Induced Hazard Maps of the Bagmati River Basin. Volume 1 (Main Report).

Report to Ministry of Water Resources, Department of Water Induced Disaster Prevention; and Flood Disaster Impacts and Responses in Nepal Terai’s marginalized Basins. http://www.i-s-e-t.org/images/pdfs/Winds%20Ch_6.pdf Source: Asian Development Bank. B. Monitoring

68. Project performance monitoring The PCMU will establish a project performance management system using the targets, indicators, assumptions, and risks in the project DMF. The PCMU will also expand the DMF into a Monitoring and Evaluation Framework taking into account the important monitoring parameters in addition to those included in DMF. The baseline data corresponding to indicators and targets set out in the DMF, and M&E Framework will be gathered, building on primary data collected during the PPTA and through further data collection, within 12 months of loan effectiveness, disaggregated by income levels, sex, caste, and ethnicity. After the initial baseline survey, the PCMU will conduct annual monitoring using the same indicators and submit the reports to ADB throughout project implementation. Results of a comprehensive completion survey will be included in the project completion report. These quarterly reports will provide information necessary to update ADB's project performance reporting system.15

69. The PMSC will support the PCMU in monitoring performance based on the DMF, M&E Framework and project performance management system (PPMS) for the project. The PID, with support from DSC and CAPC will prepare a quarterly progress report, which among other items; will include compliance of implementation of (i) assurances, covenants and conditions; (ii) safeguards; (iii) GESI; (iv) CAPP, etc.

70. Compliance monitoring: Status of compliance with assurances, conditions and loan covenants—policy, legal, financial, economic, environmental, and others— will be reviewed at each ADB review mission. All non-compliance issues, if any, will be updated in quarterly progress reports together with remedial actions. The PID will include status of compliance in quarterly progress reports.

71. Safeguards monitoring: Status of the updating and implementation of the Environmental safeguards documents (EIAs and EMPs,), and Social safeguards documents (RF) will be discussed at each ADB review mission and integrated into quarterly progress reports. Semi annual environmental monitoring reports will be provided to ADB and the Government. These reports will be disclosed to the public through ADB’s website.

72. Gender and social dimensions monitoring: Status of the implementation of the GESI Action Plan and CAPP will be discussed at each ADB review mission and integrated into quarterly progress reports.16

15

ADB's project performance reporting system is available at: http://www.adb.org/Documents/Slideshows/PPMS/default.asp?p=evaltool 16

ADB's Handbook on Social Analysis: A Working Document, is available at: http://www.adb.org/Documents/Handbooks/social-analysis/default.asp,Staff Guide to Consultation and Participation: http://www.adb.org/participation/toolkit-staff-guide.asp, and CSO Sourcebook: A Staff Guide to Cooperation with Civil Society Organizations: http://www.adb.org/Documents/Books/CSO-Staff-Guide/default.asp

Page 49: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

44

C. Evaluation

73. Within 6 months of physical completion of the Project the Executing Agency, MOUD will submit a project completion report to ADB.17

74. Evaluation of outcome level and impact level indicators for river environment should be monitored at the points indicated in the schematic diagram below:

Figure 1: Longitudinal Profile of the Upper Bagmati River

D. Reporting

75. The EA/PCMU will provide ADB with (i) quarterly progress reports in a format consistent with ADB's project performance reporting system; (ii) consolidated annual reports including (a) progress achieved by output as measured through the indicator's performance targets, (b) key implementation issues and solutions; (c) updated procurement plan and (d) updated implementation plan for next 12 months; and (iii) a project completion report within 6 months of physical completion of the Project. To ensure projects continue to be both viable and sustainable, project accounts and the executing agency AFSs, together with the associated

17

Project completion report format is available at: http://www.adb.org/Consulting/consultants-toolkits/PCR-Public-Sector-Landscape.rar

Page 50: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

45

auditor's report, should be adequately reviewed. Safeguards documents and safeguard monitoring reports will be forwarded to ADB for disclosure on the ADB website.

E. Stakeholder Communication Strategy

76. A key part of BRBIP implementation strategy will be a Stakeholder Communications Strategy focusing on information sharing and consultation that will guide communications with stakeholders during project implementation. An important finding of the PPTA Team is that all sectors in the Bagmati River Basin need to understand other sectors. The detailed stakeholder Communication Strategy is presented in

77. To contribute to project objective of improving water security in the Bagmati River Basin, communication will be maximized to:

(i) Disclose information about project to key stakeholders particularly affected

people, and set up mechanisms for grievance and feedback (ii) Encourage Dialogue and Constructive Action to support BRBIP implementation (iii) Engage key stakeholders to develop common platform for planning,

implementation and M&E (iv) Foster behaviour changes among key relevant audiences to: (a) improve local

governance; (b) improve project management and maintenance; (c) sustainably use water resources; (d) prepare for river-related disasters (i.e., flooding, etc.)

(v) Maximize communication approaches to mitigate risks related to physical investments

78. INFORMATION DISCLOSURE: The Stakeholders Communication Strategy implementation will engage and inform relevant Bagmati River stakeholders and sectors with timely, accurate, and comprehensive information shared among stakeholders. Such information sharing will help to build consensus and ensure continuous stakeholder support throughout the Project.

BRBIP IWRM/RBO Stakeholder Communication Strategy

MESSAGE COMMUNICATION METHODS AND

TOOLS

RESPONSIBLE FOR IMPLEMENTATION

WHEN IMPLEMENTED

Awareness o Description and

Definition of IWRM and River Basin Issues BRBIP Project

Description BRBIP

Components Focused on IWMR and Basin Issues

o How BRBIP Can Help Address IWRM and Basin Issues Project Benefits Project Impacts

Direct Communication by BRBIP Consultants

Media Outlets

Roundtable Discussions

BRBIP Working Groups

Talk Shows

Consultation Meetings

Sensitization Workshops

International Observation and

BRBIP Consultants

Donor Organizations (e.g. ADB NRM) Assist

NGOs Assist

BRBIP Executing and Implementing Agencies Play a Role in Implementation

Early in BRBIP Project Implementation

Page 51: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

46

o BRBIP Project Implementation Processes

Study Tours

Awake o Knowledge

Dissemination o Orientation Towards

Action o Key Integration Roles

and Responsibilities of GON Bodies

Direct Communication by BRBIP Consultants

Media Outlets

Roundtable Discussions

BRBIP Working Groups

Talk Shows

International Observation and Study Tours

BRBIP Consultants

Donor Organizations (e.g. ADB NRM) Assist

NGOs Assist

BRBIP Executing and Implementing Agencies Play a Role in Implementation

Early in BRBIP Project Implementation, but After Awareness Has Been Developed

Action o Practical Steps to

Implement IWRM and Basin Approach in Nepal

Direct Communication by BRBIP Consultants

BRBIP Consultants

Donor Organizations (e.g. ADB NRM) Assist

NGOs Assist

BRBIP Executing and Implementing Agencies Play a Role in Implementation

Approximately Mid-Project Implementation

79. The key messages that will be communicated in the strategy will be: (i) respecting the river, (ii) using the political process to institute change, (iii) municipalities respecting the law, (iv) the public changing their behaviour towards the Bagmati River, and (v) fund-raising activities.

80. The primary audiences for the SCS are local communities along the Bagmati River (local resident people, women’s groups, other community members), the general public (private sector, NGO’s development partners, key individual decision makers) and Government and authorities (local VDCs/DDCs, GON institutions and ministries).

81. SCS activities will include door-to-door awareness campaigns, public meetings, holding annual events, publicity programs with educational institutes, mother’s groups, youth clubs etc., workshops for media and provision of media kits, web page design and hosting, news provision and awareness raising using, radio, television, videos, You Tube and printed media. The exact mix of activities will be determined following the stakeholder analysis

BRBIP River Environment Communication Strategy (Audience: Local Communities [Primarily in Upper Bagmati])

MESSAGE COMMUNICATION METHODS AND

TOOLS

RESPONSIBLE FOR IMPLEMENTATION

WHEN IMPLEMENTED

Awareness o Description of Problem/Issue o Description of Project

Components Scientific Rationale

Door-to-Door in Local Communities

Brochure Hand-Outs

Continue Public Consultation

Local CBOs from the Riverside Community with Support from BRBIP

Short, Medium, and Long-Term

On-Going Throughout Project

Page 52: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

47

Realistic in What Project Can Accomplish

o Key Project Benefits o Project Implementation

Process Opportunities for

Local Communities’ Participation

Meetings already on-going from PPTA.

Hoarding Board (Billboard) o Slogan/Pictorial

Message in Riverside; in Clusters.

Religious organizations ("Guthis") such as Pasupati Area Development Trust (PADT)

Small-Scale, Local Activities

Awake o Knowledge Dissemination re

Options for Action o Orientation Towards Action

and Mobilization

Face-to-Face Meetings with Local Groups.

Brochure Hand-Outs

Focus Group Discussions

Local CBOs from the Riverside Community with Support from BRBIP

Religious organizations ("Guthis") such as Pasupati Area Development Trust (PADT)

Small-Scale, Local Activities

Short, Medium, and Long-Term

On-Going Throughout Project

Action o Local Communities’

Involvement and Participation in Direct Action

Annual Workshops

River Cleaning Campaign

Competition (competition between VDCs in Upper Bagmati).

Music, Literature, Art, Dramas

Plantation and Forestation

Sports Activities

Clean Up Rally and Campaign

Develop and Implement Reward System for Clean-Up.

Slogan/Pictorial Message along Riverside; Clusters.

Educational Institutes

Mothers Groups

Forest User Groups

Youth Clubs

Political Groups

Business Houses (private sector)

Wards and VDCs

Religious organizations ("Guthis") such as Pasupati Area Development Trust (PADT)

Supported by BRBIP

Short, Medium, and Long-Term

On-Going Throughout Project

BRBIP River Environment Stakeholder Communication Strategy

(Audience: Public-at-Large) MESSAGE COMMUNICATION

METHODS AND EVENTS RESPONSIBLE WHEN

IMPLEMENTED

Awareness o Don’t Pollute Bagmati Components Scientific

Rationale o Key Project Benefits

Annual Mega-Event o Bagmati River Festival Display/Exhibition Entertainment Sports Literature

Government

NGOs/CBOs

Private Sector

Religious organizations ("Guthis") such as

June Through August

Annual Event

Coordinate with Annual Nepalese Silthinakeha-

Page 53: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

48

o Project Implementation Process

o Public’s Potential Roles in Bagmati Clean-Up

Music Sidewalk Art Display Music Video at

Bagmati

Website Development Supported

Pasupati Area Development Trust (PADT)

Funding Needed from These Organizations

Krishnastatni Festival o Annual Mega-

Event is an Integral Part of Nepalese Festival.

o Link Mega-Event to Local Festivals to Give Attention.

Awake o Knowledge

Dissemination re Options for Action

o Orientation Towards Action and Mobilization

o How Public Can Be Involved Campaigns Activities

Media Mobilization o Media Workshop Exposure (e.g. if VDCs

do a good job, bring the media), visit for all

Briefings to media re Project

o Radio, TV programs o Three-Minute Video

Produced

Website Development Supported

NGOs/CBOs (with project support)

Religious organizations ("Guthis") such as Pasupati Area Development Trust (PADT)

Every Three Months.

F. Participation and institutional Strategic plan

82. Seven key stakeholder, participation, and institutional strategies are envisaged for BRBIP including: (i) a Bagmati River Basin Organization (RBO) that introduces and implements the objectives of integrated water resources management (IWRM) to river restoration, (ii) improved mechanisms for participation and water dialogue, (iii) institutional strengthening and capacity development, (iv) the development of an NGO Platform, (v) a stakeholder communication strategy, (vi) the introduction of knowledge-based decisions, and (vii) a proper legal framework. The detailed participation and institutional plan is available as supplementary appendix 19 of the project RRP.

G. Establishment and Development of a Bagmati RBO and IWRM

83. The overlapping mandates, interests and duplication among the different government agencies and other stakeholders calls for an institutional framework for coordination, integration and regulation of all activities within the Bagmati River Basin. An Integrated Water Resources Management (IWRM) approach that “promotes coordinated development and management of water, land and related resources to maximize the resultant economic and social welfare in an equitable manner without compromising the sustainability of vital ecosystems”. A key challenge for the RBO will be to mainstream the participation of local communities in river basin management.

84. The key governmental agencies like WECS, MOUD, HPCIDBC, Dept of National Parks and Wildlife Conservation (DNPWC)/Shivapuri Nagarjun National Park have a key role of executing and implementing the Project. As it is a multi-sectoral project requiring a river basin management/IWRM approach. River Basin Organization (RBO) to coordinate, integrate and monitor the river basin development and management is thus needed for Bagmati River Basin.

Page 54: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

49

85. Component 1 – Towards Integrated and Participatory River Basin Management – Proposal for Bagmati RBO concludes that current water management problems in the Bagmati river basin make it highly suitable for the introduction of IWRM, and one possible solution to promote this would be formation of an RBO.

86. Although most existing government agencies function well enough within normal funding constraints, there is need for greater coordination and focus on key issues, and elimination of overlaps which appear to occur in certain areas. However, an analysis of water management functions indicated that there are gaps in key areas (e.g. basin-wide water balance, water allocation, groundwater management) which need to be resolved.

87. The Project considers that formation of an RBO to address key planning functions together with rationalisation of other water management functions could make a significant positive impact on the water management in the basin, and start to resolve key issues. A draft roadmap of IWRM activities with corresponding timetable and milestones is presented in the Project Component 1 Report.

H. Mechanisms to Promote Participation, Coordination, and Integrated Water Dialogue

1. Challenges and Issues

88. There are no mechanisms in the Bagmati River Basin for developing integrated and multi-sectoral water resources management strategies in the Upper Bagmati. The basin is also plagued by: (i) limited room for water dialogue involving civil society, (ii) limited networking mechanisms for sharing data and information, and (iii) limited community awareness and education.

89. The lack of a multi-sectoral strategic approach highlights the need for both a process and an institutional mechanism for key stakeholders to actively support coordinated Bagmati water resources development and river environment management.

2. Goals and Targets of These Mechanisms and Processes

90. The goal or target of these institutional mechanisms and processes is integrated water resources management in the Bagmati River Basin. The objective is to better manage water resources in an integrated way, not necessarily to build a Bagmati River Basin Organization (RBO). There are multiple institutional structures (including an RBO) that might accomplish this, but the goal itself is not necessarily an RBO per se, but sustainable water resources management in the basin. An RBO could possibly be a good technical and institutional tool for facilitating and structuring integrated water resources management, but the organizational apparatus (e.g. an RBO) is a tool or a means to an end, not the end itself.

3. Mechanisms and Processes to Promote Participation, Coordination, and Integrated Water Dialogue

91. There is a clear need to build better water governance in the Bagmati Basin. Some key principles for building better water governance include:

(i) Stakeholders involvement and agreement (including CSOs and NGOs) on multi-stakeholders’ coordination mechanisms.

Page 55: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

50

(ii) Knowledge, data, information- sharing and cooperation on projects; basin awareness.

(iii) Inter-sector collaboration. (iv) Integrated knowledge of the basin profile. (v) Steering water resources development and river environment strategy and

implementation. (vi) Updating and/or setting up of a regulatory framework.

92. To follow these principles and achieve the stated goal of integrated water resources management (IWRM) in the Bagmati Basin, the Project will support the development of a multi-stakeholders’ mechanism that mainstreams IWRM. This will involve designing and implementing a stepwise framework for water resources coordination:

(i) At least two multi-sectoral Technical Working Groups formed and supported:

Working Group on Bagmati Water Resources Management

Working Group on Bagmati River Environmental Management (ii) A Bagmati IWRM Project Steering Committee. (iii) River Basin Organization

4. Multi-Sectoral Technical Working Groups

93. A key element of these processes and mechanisms is the formation of at least two technical working groups on the Bagmati Basin: (i) Bagmati Water Resources Management Working Group, and (ii) Bagmati River Environmental Management Working Group. These are technical working groups, focusing on technical aspects of water resources management and river environmental management. These working groups would provide multi-sector platforms and mechanisms for stakeholder coordination, collaboration, and participation, at least initially focusing only on technical matters.

94. The working groups could start out informally, with little or no official government authority, and gradually evolve into a key part of the official Bagmati RBO as the official RBO is being developed. To this extent, the two working groups are a transitional mechanism to keep integrated water dialogue going while legal, budgetary, and administrative arrangements are made for the RBO. Ultimately, these working groups would be integrated into the long-term organizational chart of the Bagmati RBO.

95. The roles of the working groups would be: (i) Consultative aiming at following up and giving recommendations for the

preparation of the Bagmati RBO. (ii) Discuss status of water related projects in the Bagmati River Basin and develop

methods for intersectoral screening and evaluation (water dialogue). (iii) Provide forum for exchange of views on challenges and issues facing Bagmati

stakeholders. (iv) Share knowledge and information and advice on public awareness campaigns. (v) Help develop ideas and actions related to a Bagmati Community Empowerment

Program – Information, Awareness, Education. (vi) Develop awareness framework and guidelines for better involvement of a wider

range of stakeholders. (vii) Remain current and help develop a Bagmati Basin Info System and knowledge

base as way to consolidate and network various sectors.

Page 56: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

51

96. It is also important the two working groups become a part of the BRBIP/KVUEIP Joint Communication Strategy. Although much of the work of the communication strategy will be done by NGOs and CSOs, the two technical working groups can help guide and give direction to the joint communication strategy.

97. Potential stakeholders as members of the working groups would include: (i) HPCIDBC (ii) WECS (iii) KVWSMB/KUKL (iv) MOI/DOI (v) Municipalities (vi) VDCs and DDCs (vii) CSOs (including representatives from local vulnerable groups, including farmers’

groups in Upper Bagmati) (viii) NGOs

98. It is particularly important to note that local groups such as VDCs, DDCs, and local leaders could potentially block BRBIP Project activities (construction, etc.) and mobilize opposition to the project. It is critically important therefore that these local leaders and representatives of the VDCs/DDCs are fully engaged in the Project processes/activities and the Working Groups, to incorporate them as participants into the project, rather than just as observers. There could be a tendency to exclude these local groups from the Working Groups, but it should be stressed that the objectives of the Working Groups will only be fulfilled if VDCs/DDCs, CSOs, and other local leaders fully participate in the Working Groups.

5. Multi-Sectoral Bagmati IWRM Project Steering Committee

99. If the working groups show initial progress and promise, an informal Bagmati IWRM Project Steering Committee could also be formed. This IWRM Steering Committee would primarily be technical, and would directly address larger IWRM issues on the river basin. Again, early on in the project, this IWRM Steering Committee (separate but coordinated with the larger Project Steering Committee), would operate more informally, without the need for formal government authorization.

6. Bagmati RBO

100. The whole process of developing mechanisms and processes to promote coordination, participation, and water dialogue would be a step-wise process. The first step is the establishment and development of the technical working groups, which would be a transitional step while the formal Bagmati RBO is being established and legally authorized. The second step would be to merge the working groups into the formal Bagmati RBO.

I. Institutional Development

101. BRBIP will also work with executing and implementing agencies to improve the overall governance of project operations, including a focus on a proper legal and regulatory framework, and key processes and procedures within government agencies.

102. At least one of the key processes and procedures to improve Bagmati River institutions will be the development of multi-stakeholders’ mechanism that mainstreams IWRM. This will involve developing and supporting at least two Technical Working Groups: (i) Working Group on

Page 57: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

52

Bagmati Water Resources Management, and (ii) Working Group on Bagmati River Environmental Management. These will be technical working groups, focusing on technical aspects of water resources management and river environmental management. These working groups would provide a multi-sector platform and mechanism for stakeholder coordination, collaboration, and participation, at least initially focusing only on technical matters. Three key functions of these working groups that would directly contribute to institutional development are: (i) consultative aiming at following up and giving recommendations for the preparation of the Bagmati RBO, (ii) discuss status of water related projects in the Bagmati River Basin and develop methods for intersectoral screening and evaluation (water dialogue), and (iii) provide a forum for exchange of views on challenges and issues facing Bagmati stakeholders.

J. Inter-Organizational Relations

103. RBO - Inter-organizational relations will be improved in BRBIP, primarily through the establishment and operation of the Bagmati RBO. Presently, inter-sectoral and institutional capacities and knowledge of river basin coordination and cooperation are not yet fully developed along the Bagmati River Basin. RBOs are a relatively new concept to Nepal, particularly for a river like the Bagmati which flows through a highly urban and industrialized area.

104. BRBIP will directly address these weaknesses by emphasizing at least two areas of RBO development:

(i) Processes and Procedures – The processes and procedures needed to design, develop, and begin implementation of an RBO will be designed and implemented, including a step-wise development of Technical Working Groups that would ultimately lead to full legal authority for an RBO.

(ii) Institutional and Implementation Arrangements – Once the RBO is actually formed, more expertise will be required in actual river basin management, and in operating the RBO on a day-to-day basis. BRBIP through its organizational development activities described above will focus on these arrangements.

105. NGOs and CSOs - Another key part BRBIP’s inter-organizational capacity development activities will be focused on incorporating recognized NGOs, CSOs, local development partners, and local government bodies into project operations. BRBIP will emphasize the benefits of cooperation and collaboration between these different organizations and institutions.

106. The Role of a “Champion” - Another key inter-organizational capacity development activity will be the identification and support of a “champion” for the loan project from among the key stakeholders. This champion could take on the role of a driving force supporting integrated, stable institutions within the Bagmati River Basin, and coordinating multi-sectoral improvement efforts.

K. NGO Platform

107. The Upper Bagmati River environment improvement will require community participation in maintaining the river environment. While the interventions proposed to manage liquid and solid waste and to increase the flows in the river will provide the basis of the restoration of the river environment to its conditions of 30-40 years ago, the river banks and the green belts created in the flood plains will need to be owned by communities and other local stakeholders. There are some good examples of communities and other civil society organizations (CSOs) coming together to improve the rivers by developing green zones and parks on certain stretches

Page 58: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

53

of the river like the UN Park in Lalitpur and the initiatives taken by community organizations like the MakaibariToleSudharSamiti, WEPCO and PWEDO (Populations Women Environmental Development Organization) to manage and control solid waste dumping in certain stretches of the river. Such efforts need to be scaled up and extended to cover the whole stretch. Such initiatives would be best carried out by community level organizations with very little help from the government.

108. The adoption of river stretches by communities, private sector and local NGOs would be an important way of ensuring that the river environment is improved and the communities benefit from the river front development. It is proposed that the greenbelts and river banks along the improved Bagmati River be managed by the user committees formed by the local communities or by interested private sector or local CSOs and NGOs. The following modality of adoption of river stretches is proposed.

(i) A national NGO working in the field of environment and community mobilization will be recruited under a NGO contract with the responsibility of mobilizing the communities and forming user committees to take up the responsibility of adoption of river stretches.

(ii) The selected NGO will carry out community awareness and mobilization activities and assist in establishing user communities to adopt and manage stretches of the river. These stretches can be developed by the communities as gardens and parks for local communities’ benefits, including development of floriculture and small forestry patches for beautification.. The user committees will be registered with the local ward offices of the VDCs or municipalities or with the District Administrative Office (DAO) depending on the scope and area of coverage. Selected NGO will assist the user committees in the registration process. The CSOs can even raise funds by collecting subscriptions from visitors to sustainable maintenance of the parks.

(iii) Competition for award giving will be organized periodically by the VDCs or municipalities in order to boost up the morale of the CSOs and NGOs involved in nature conservation work. The CSOs and NGOs can even build temples or cultural promotional small museums within the park to attract regular visitors.

(iv) HPCIDBC, the Implementing Agency (IA) for the project, will prepare the technical guidelines and regulations for the operation of the green belts and the development to be carried out within it. HPCIDBC along with the VDCs and Municipalities will monitor and regulate the activities of the user committees. HPCIDBC will allocate the river stretches to be managed and adopted by each user committee. Private sector may also apply to adopt certain stretches of the rivers under their corporate social responsibility (CSR) activities or support user committees or local NGOs to do so.

(v) The forum of all user committees adopting the river stretches may be established to work with HPCIDBC and VDCs and municipalities to self monitor the activities. Such a forum will coordinate with other activities like the annual Bagmati River Festival to showcase their achievements. A “Score Card” system will be used to select the best performing user communities and to encourage others to improve. The modality of the “score card” systems needs to be development by the participating communities, private sectors and the local bodies (municipality wards and VDCs).

(vi) Seed money will be provided to community- or private sector-led local initiatives on river environment management to the CSOs and small private entrepreneurs.

Page 59: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

54

X. ANTICORRUPTION POLICY

109. The Office of Anticorruption and Integrity (OAI) is the initial point of contact for allegations of integrity violations involving ADB-related activities or ADB staff. Independent since October 2009, OAI‘s mission is to ensure ADB and its partners maintain the highest ethical and professional standards, and prevent resources intended to improve the lives of the poor from being used to line the pockets of the unscrupulous. ADB reserves the right to investigate, directly or through its agents, any violations of the Anticorruption Policy relating to the Project.18 All contracts financed by ADB shall include provisions specifying the right of ADB to audit and examine the records and accounts of the executing agency and all Project contractors, suppliers, consultants and other service providers. Individuals/entities on ADB’s anticorruption debarment list are ineligible to participate in ADB-financed activity and may not be awarded any contracts under the Project.19

110. To support these efforts, relevant provisions are included in the loan agreement, project agreement and the bidding documents for the project. In particular, all contracts financed by ADB in connection with the project will include provisions specifying the right of ADB to audit and examine the records and accounts of the executing agency and all contractors, suppliers, consultants, and other service providers as they relate to the project.20

18

Available at: http://www.adb.org/Documents/Policies/Anticorruption-Integrity/Policies-Strategies.pdf 19

ADB's Integrity Office web site is available at: http://www.adb.org/integrity/unit.asp 20

Governance and Anticorruption Action Plan (GACAP) II Guidelines available at: http://www.adb.org/Documents/Guidelines/GACAP-II-Guidelines.pdf. See also Sourcebook: Diagnostics to Assist Preparation of Governance Risk Assessments: http://www.adb.org/documents/books/Diagnostics-to-Assist-Preparation-of-GRAs/default.asp.

Score Card System will be based on the factors/indicators such as:

1. Hygiene (Health) –bacterial level suitable for religious

2. Biological function – dissolve oxygen

3. Aesthetic – smell, color

4. Social function – people’s perception, use of the river

5. Physical – quantity and depth of water (Details of the score card system will be worked out through consultations with the participating community organizations during project implementation.

Page 60: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

55

XI. ACCOUNTABILITY MECHANISM

111. The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures. It consists of two separate but complementary functions: problem solving function and compliance review function. People who are, or may in the future be, adversely affected by the project may submit complaints to ADB’s Accountability Mechanism. The Accountability Mechanism provides an independent forum and process whereby people adversely affected by ADB-assisted projects can voice, and seek a resolution of their problems, as well as report alleged violations of ADB’s operational policies and procedures. Before submitting a complaint to the Accountability Mechanism, affected people should make a good faith effort to solve their problems by working with the concerned ADB operations department. Only after doing that, and if they are still dissatisfied, should they approach the Accountability Mechanism.21

112. The project will establish a Grievance Redress Mechanism to ensure greater accountability. Within 12 months of loan effectiveness, the PCMU will prepare a Grievance Redress Mechanism, acceptable to ADB, and establish a special committee to receive and resolve complaints/grievances or act upon reports from stakeholders on misuse of funds and other irregularities, including grievances due to resettlement. The special committee will (i) make public of the existence of this Grievance Redress Mechanism; (ii) review and address grievances of stakeholders of the project, in relation to either the project, any of the service providers, or any person responsible for carrying out any aspect of the project; and (iii) proactively and constructively responding to them.

XII. RECORD OF PAM CHANGES

113. A draft PAM was prepared at the loan fact-finding mission in April 2013, and agreed with the government.

21

For further information see: http://www.adb.org/Accountability-Mechanism/default.asp.

Page 61: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

56 Appendix 1

DETAILED PROCEDURES FOR DISBURSEMENTS, ACCOUNTING, AND AUDITING

Page 62: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 1 57

Page 63: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

58 Appendix 2

FINANCIAL STATEMENTS TEMPLATES

Cumulative

upto

beginning of

prior year

During the

Prior Year

Cumulative as

at

[commencem

ent

date/begininn

g of current

period]

For the period

[commencem

ent date] to

July 16, 20XX

As at July

16, 20XX

Cumulative

upto

beginning of

prior year

During the

Prior Year

Cumulative as

at

[commencem

ent

date/begininn

g of current

period]

For the

period

[commence

ment date]

to July 16,

2014

As at

July 16,

2014

[For 1st year,

nil]

[For 1st

year, nil]

[For 1st year,

nil]

For current

period

At current

year end

[For 1st year,

nil]

[For 1st

year, nil]

[For 1st year,

nil]

A: II Civil Works 1 I

GON Fund II Consulting Services 2 I

GON Reimburseable Fund Training Courses 3 I

ADB Reimburseable Vehicles 4 I

Equipment and

Materials 5 I

Total Remiburseable Staff Development 6 I

III Studies and Reviews 7 I

ADB Grant: Project Management, Monitoring and Evaluation8 I

Reimbursement Others 9 I

Replenishment

Transfer to Central Treasury

Direct Payment

Charged in the next year

Subtotal

B:

ADB

Special Imprest IV Imprest A/c Balance

Account/ Initial Deposit

Oustanding

Replenishment

Exchange Gain Exchange Loss

Subtotal

Grand Total

Notes I to VI of the financial statements form an integral part of these financial statements

( ) ( ) ( ) ( ) ( )

Account-In Charge Project Manager Secretary Ministry of Education (Financial Comptroller General) Auditor General

For the period [July 17, 20xx or loan effectiveness date] to July 16, 20xx

NR NR

Government of Nepal

Ministry of Urban Development

HPCIDBC

Bagmati River Basin Improvement Project

Funded by ADB under Grant / Loan [Insert Number]

Sources and Uses of Funds

Fiscal year 2011/ xx

Sources Note Applications

Catego

ry Note

Page 64: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 2 59

Statement of Budget Vs Actual (or Consolidated Annual Financial Statement)

GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total

xx

xx

xx

xx

Sub Total

Budget Head - Capital Expenditure

xx

xx

xx

xx

Sub Total

Grand Total

GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total GON

ADB

Reimbursable

Loan

ADB D.P.

Loan Total

xx

xx

xx

xx

Sub Total

Budget Head - Capital Expenditure

xx

xx

xx

xx

Sub Total

Grand Total

Notes I to VI of the financial statements form an integral part of these financial statements

Budget Head - Recurrent Expenditure

Cumulative to Date

Budget Head - Recurrent Expenditure

Current Year Amount in NRs

Item No. Budget Item

Budget Allocation Budget Released Expenditure Balance (Released-Expenditure)

( )

Financial Comptroller General Auditor General

( )( )

Account-In Charge Project Manager Secretary Ministry of Education

( ) ( )

Government of Nepal

Ministry of Urban Development

HPCIDBC

Bagmati River Basin Improvement Project

Funded by ADB under Grant / Loan [Insert Number]

July 17, 20xx to July 16, 20xx

Budget Allocation Budget Released Expenditure Balance (Released-Expenditure)

Amount in NRs

Fiscal Year 20xx/xx

Budget ItemItem No.

Page 65: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

60 Appendix 2

Notes to Account - I Category- wise Expenditures

Cumulative upto

beginning of prior

year

During the

Prior year

Cumulative upto

beginning of current

year/ period

For the period

[commencement

date] to July 16,

2014

As at July 16,

2014 (End of

Current Year)

1 Civil Works

xx Building Construction

xx Capital Improvement

Subtotal

2 Consulting Services

xx

xx

Subtotal

3 Training Courses

xx

xx

Subtotal

4 Vehicles

xx

xx

Subtotal

5 Equipment and Materials

xx

xx

Subtotal

6 Staff Development

xx

xx

Subtotal

7 Studies and Reviews

xx

xx

Subtotal

8

Project Management, Monitoring

and Evaluation

xx

xx

xx

xx

Subtotal

9 Others

xx

xx

xx

Subtotal

Grand Total

Government of Nepal

Ministry of Urban Development

HPCIDBC

Bagmati River Basin Improvement Project

Funded by ADB under Grant / Loan [Insert Number]

July 17, 20xx to July 16, 200x

Fiscal year 20xx/xx

Category NRParticularLine Item

Page 66: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 2 61

Fiscal year 20xx/xx

Notes to Account - II - GON Replenishment and Reimburseable

Cumulative

upto beginning

of prior year [nil

for 1st year]

Prior year [nil for 1st

year]

Cumulative upto

beginning of

current year/ period

[nil for 1st year]

For the period

[commencement

date] to July 16,

2014

As at

July 16,

2014

A Total Budget Release

GON Fund

GON Reimburseable

Subtotal A

Less:

B Unspent Balance

Subtotal B

C Reimbursements

Subtotal B

Total Fund (A-B-C)

D GON Fund

E GON Reimburseable Fund

F ADB Direct Payment

Total Fund (D+E+F)

S. N

Government of Nepal

Ministry of Urban Development

HPCIDBC

Bagmati River Basin Improvement Project

Funded by ADB under Grant / Loan [Insert Number]

July 17, 20xx to July 16, 200x

NRParticular

Page 67: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

62 Appendix 2

Notes to Account - II I- Details of Payment by ADB by Currency and Method of Funding

NRs US$ SDR NRs US$ SDR NRs US$ SDR NRs US$ SDR NRs US$ SDR

Direct Payments

Civil Works 1

Consulting Services 2

Training Courses 3

Vehicles 4

Equipment and Materials 5

Staff Development 6

Studies and Reviews 7

Project Management, Monitoring

and Evaluation 8

Others 9

Subtotal

Replenishment

Civil Works 1

Consulting Services 2

Training Courses 3

Vehicles 4

Equipment and Materials 5

Staff Development 6

Studies and Reviews 7

Project Management, Monitoring

and Evaluation 8

Others 9

Subtotal

Reimbursement

Civil Works 1

Consulting Services 2

Training Courses 3

Vehicles 4

Equipment and Materials 5

Staff Development 6

Studies and Reviews 7

Project Management, Monitoring

and Evaluation 8

Others 9

Subtotal

Total

Imprest Account Initial Deposit

Diff between Disb and Liquidation

Sub Total of Imprest A/c

Interest Capitalization

Grand Total

Government of Nepal

Cumulative upto

beginning of prior year [nil

for 1st year]

Prior year [nil for 1st

year]

Cumulative upto

beginning of current year/

period [nil for 1st year]

For the period

[commencement date] to

July 16, 2014 As at July 16, 2014Catego

ryParticulars

Fiscal year 2010/11

July 17, 20xx to July 16, 200x

Funded by ADB under Grant / Loan [Insert Number]

Bagmati River Basin Improvement Project

HPCIDBC

Ministry of Urban Development

Page 68: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 2 63

Notes to Account IV - Statement of Imprest Account

S.N. Particulars Equivalent NRs US$

A Balance in Imprest Account as at [beginning of the current year]

Exchange Rate 1 UD$ = NRs xx.xx

B Outstanding Replenishments as of [previous year]

(i) Remibursement to GON

(ii) Direct Payment

Total B

C Add:

Disbursements during the year

(i) Remibursement to GON

(ii) Direct Payment

Total C

D Less:

Replenishment during the year

(i) Remibursement to GON

(ii) Direct Payment

Total D

E Liquidation/ Recovery of Initial Balance

(i) Remibursement to GON

(ii) Direct Payment

Total E

F Outstanding Replenishment as of [end of the current year]

(i) Remibursement to GON (B+C-D-E)

(ii) Direct Payment (B+C-D-E)

Total F

G Outstanding Amount of Imprest Account (A+F)

H Initial Deposit as at (original date)

I Exchnage Gain/Loss (G-H)

Ministry of Urban Development

Government of Nepal

Fiscal year 20xx/xx

July 17, 20xx to July 16, 200x

Funded by ADB under Grant / Loan [Insert Number]

Bagmati River Basin Improvement Project

HPCIDBC

Page 69: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

64 Appendix 2

Prior

Year

Current

Year

Cumulativ

e to Date

Prior

Year

Current

Year

Cumulativ

e to Date

Prior

Year

Current

Year

Cumulative

to Date Prior Year

Current

Year

Cumulati

ve to

Date

Prior

Year

Current

Year

Cumulativ

e to Date

Prior

Year

Current

Year

Cumulati

ve to

Date

Prior

Year

Current

Year

Cumulati

ve to

Date

Civil Works

Consulting Services

Training Courses

Vehicles

Equipment and Materials

Staff Development

Studies and Reviews

Project Management, Monitoring

and Evaluation

Others

Total

Total Expenditure

Output 2: Improved river banks

environment in urban areas

Output 4 : Effectice Project

Management and M&E Unallocable Costs

Government of Nepal

Ministry of Education

Council for Technical and Vocational Training

Skills Development Project

Funded by ADB under Grant [Insert Number]

July 17, 20xx to July 16, 200x

Fiscal year 20xx/xx

Category

in NR

Notes to Account V - Project Output Wise Cost

Output 1 : Systems and

capacity for integrated and

participatory river basin

management established

Output 3: Increased water

availability during the dry

season and watershed

conservation

Output 4 : Flood forecasting and

early warning system in the

Bagmati River Basin is

functional

Page 70: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 2 65

1. Project Nature and Activities

1.1

1.2

2. STATEMENT OF COMPLIANCE

3. SIGNIFICANT ACCOUNTING POLICIES

3.1

Fiscal year 20xx/xx

NOTES VI TO THE FINANCIAL STATEMENTS - Accounting policies and explanatory

notes

Government of Nepal

Ministry of Urban Development

HPCIDBC

Bagmati River Basin Improvement Project

Funded by ADB under Grant / Loan [Insert Number]

July 17, 20xx to July 16, 200x

Description of the Project, the nature of activities, commencement and expected

completion dates. Mention location, domicile, legal form, controlling IA/ EA, brief nature

of the project outputs,

Give legislative framework

Project Financial Statements have been prepared in accordance withn the

Government Auditing Standards Part 3: Segment Audit Guidelines - Project Financial

Statements issued by the Office of the Auditor General, Nepal in October 2005, and

the Statement of audit Needs provided by the Asian Development Bankunder the Loan

_________ dated _______

Basis of measurement

The project has maintained accounts according to the Government of Nepal

Accounting policies on a cash basis of accounting and double entry accounting

systems. Capitalisation amount is not included in the main Sources and Application of

Funds, and is shown is Note III to the Project Financial Statements.

Page 71: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

66 Appendix 2

66

A

pp

en

dix

2

3.2 Fund Flow mechanism

3.3

3.4

3.5

3.6

i)

iii)

3.7

(a)

(b)

Describe nature of different types of income and how they are recognised. For

eaxample grants, sale of proceeds of fixed assets, interest income on bank

Free of cost office space, electricity and certain other services provided by

{insert name] are not valued and accordingly, are not recognized in these

financial statements as income of the Project.

Foreign currency transactions and translation

Functional and presentation

Items included in the financial statements of the Project are measured using the

currency of the primary economic environment in which the entity operates (the

functional currency), which is the Nepal Rupee (NR).

Transactions and balances

Foreign currency transactions are translated into functional currency using the

exchange rate prevailing at the date of the transaction. Foreign exchange gains

and losses resulting from the settlement of such transactions and from the

translation at year-end exchange rates of monetary assets and liabilities

denominated in foreign currencies are recognised in the income and expenditure

account. Conversion Rate: USD $ 1= INR __ as of 30 June 20__

Cash and cash equivalents

Cash equivalents comprise [ define components of cash]. Explain if the entity controls

unspent advances, only petty cash, or has a nil balance , as applicable

Accrued and other liabilities

Disclose any major liabilities which have not been accrued under the cash basis

policy

Income

-2-

Describe the fund flow mechanism , in particular , whether the IA/EA control funds or

whether all payments are centralised

Advances and other receivables

Advances are treated as expenditure. Unspent advances are ___________________

Page 72: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 2 67

3.8

4. Funds Received from the Government

5. Funds from ADB

5.1

5.2

6. DATE OF AUTHORIZATION

Givepertinent details of the ADB grant including effective date, amount in US$, period

etc.

Give details of the government budgeting and funding mechanism. Explain the

replenishment and reimbursement mechanism

These financial statements have been authorized for issue by the

_____________ of _________________ on …………………..

Allocation of Common Costs

Describe how commom costs are allocated to differenet output/ activities

-3-

Loan

Grant

Page 73: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

68 Appendix 3

STATEMENT OF AUDIT NEEDS

A. BACKGROUND

1. The ADB and the Government of Nepal (GON) have entered into a Loan and Grant Agreement whereby, ADB shall provide $ 25.5 million and $ 4.5 million for the purpose of financing the Bagmati River Basin Improvement Project in Nepal. The GON shall contribute $ 6 million against this funding. This will be carried out through the Ministry of Urban Development (MOUD), the High Power committee for the Integrated Development of the Bagmati Civilization (HPCIDBC), the Department of Irrigation (DOI), and the Water and Energy Commission Secretariat (WECS). HPCIDBC, WECS and DOI shall maintain separate books of account which will be consolidated by the PCMU with respect to the items of expenditure financed out of the proceeds of the loan and the Grant.

2. The audit of the project financial statements shall be performed in accordance with the Government Auditing Standards Part 3: Segment Audit Guidelines for Project Financial Statements issued on October 2005 by the Office of the Auditor General Nepal (Government Auditing Standards). However, in case of contradiction between this Statement of Audit Needs and the Government Auditing Standards, this Statement shall prevail.

B. PROGRAM DEVELOPMENT OBJECTIVES 3. The proposed project will support the Government of Nepal in increasing water security in the Bagmati River Basin and more particularly in improving river health and flood management. The project focuses on priority issues selected by the basin stakeholders from a long list of actions identified under the basin strategic investment road map. The road map is based on the 2009 Bagmati Action Plan and further consultations with basin stakeholders. The project outputs will be:

(i) Systems and capacity for integrated and participatory river basin management established. This output will include: (a) legal and institutional strengthening for IWRM and formation of a river basin organization (RBO); (b) mobilization and awareness raising of basin stakeholders; (c) capacity building and technical training for raising the RBO’s competence; (d) establishment of a Central Water Resources Information system including a decision support system (DSS) and an operational water quality monitoring network; and (v) preparation of a 15-year participatory integrated river basin master plan.

(ii) Improved river banks environment in urban areas. This output will include: (a) removal of contaminated river bed material; (b) construction of weirs for river bed stabilization and re-aeration; (c) riverbank stabilization and beautification; and (d) social mobilization, community awareness raising and capacity building of local government, communities and the private sector for river bank management and maintenance.

(iii) Increased water availability during the dry season and watershed conservation. This output will include: (a) construction of the 861,000 cubic meters (m3) Dhap dam and detail design of the 8 million m3 Nagmati dam; (b) provision of roof top rainwater harvesting and ground water recharge; and (c) upstream watershed management.

(iv) Flood forecasting and early warning system in the Bagmati River Basin is functional. This output will include: (a) upgrading the existing flood forecasting system; (b) installation of a flood early warning system; and (c) community awareness and capacity building for flood response.

Page 74: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 3 69

Financial Reporting and Audit Requirements 4. ADB’s audit needs under the Project are as follows.

(i) Submission of audited project financial statements within 6 months of the end of the fiscal year in English. The key objective is to enable ADB to obtain sufficient assurance where the auditor expresses a professional opinion on the Project Financial Statements (PFS) of the BRBIP as of July 17 each year. This shall not be construed to refer to the financial statements of BRBIP as a whole. The auditor will review that the funds received from all sources and expenditures incurred during the reporting period are as per agreed terms and conditions. This will include all expenditure to the extent that it relates to the activities of the BRBIP and MOUD supporting this Project.

(ii) The audit shall be conducted by the Office of the Auditor General (OAG), in

accordance with Government Auditing Standards Part 3: Segment Audit Guidelines

– Project Financial Statements issued by the OAG in October 200522

(iii) Project Financial statements shall prepared on a cash basis in accordance with

Government of Nepal accounting policies and in accordance with the financial statement templates agreed within this Statement of Audit Needs in Annexure C.

This Template is based on Annexure 1 of the above Government Auditing

Standards but has been tailored to incorporate the requirements of the Nepal Public

Sector Accounting Standards, which have been approved for adoption by the GON

in 2009. Although these are not yet effective in Nepal, given the elevated status of

the NPSAS to top of the government accounting reform agenda, template Project

Financial Statements have incorporated some of the key requirements. This is even

more relevant since under ADBs revised Public Disclosure Policy2011, Project

Financial Statements shall be disclosed on ADBs website.

(iv) A complete set of financial statements is received annually which includes:

Cover Letter from the OAG and/or MOUD/PCMU BRBIP

Audit Opinion on the Project Financial Statements (Annex A) Separate Audit Opinion on Specific Donor Requirements (Annex B)

Project Financial statement and Statement of Budget Vs. Actual along with

complete notes to the financial statements including necessary break downs

and details, summary of accounting policies and explanatory notes (Annex

C)

Management Letter (paragraph F below)

Annexes to the Financial Statements as listed in paragraph E below

(v) ADB reserves the right to commission supplementary audit, if OAG considers it

unfeasible to satisfy specific donor audit needs as part of its constitutional statutory

audit.

C. SPECIFIC NEEDS

5. The audit is carried out in accordance with Government Auditing Standards of the OAG, which are based on International Standards on Auditing (ISA) or INTOSAI Standards. Audit Opinion Template in accordance with these Standards has been given as ‘Annex A’ to this Statement of Audit Needs.

22

These Guidelines were specifically prepared to cater to donor requirements by the OAG and shall hereinafter referred to as Government Auditing Standards

Page 75: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

70 Appendix 3

6. The audit would cover the entire Project i.e. covering all sources and application of funds, including the ADB and the GON. The Financing Arrangement as currently agreed with ADB, includes Direct Payments by ADB to suppliers (DPs). The Project Director shall provide all pertinent information to the Auditors including preservation and use of resources procured and its reflection in the project accounts, so as to facilitate comprehensive audit coverage. The audits should be carried out annually from commencement of the Project. The audit for the first year should also cover transactions, which occurred from the commencement of the project, i.e. till the end of the fiscal year. In case the period is less than 6 months, GON may agree with ADB to provide APFS from the commencement of the Project to the end of the subsequent fiscal year.

7. ADB will also require an assessment by the auditors of compliance with provisions of the financing agreement with ADB, especially those relating to accounting and financial matters. An audit opinion shall be provided that will inter alia include verification that:

(i) All funds have been used in accordance with the conditions of the loan agreements, with due regard to economy and efficiency, and only for the purposes for which the funds were provided;

(ii) The Ministry of urban Development, HPCIDBC, DOI and WECs were in compliance as at [insert date] with all financial covenants of the loan agreement

(iii) With respect to SOEs, (i) adequate supporting documentation has been maintained to support claims to the Asian Development Bank for reimbursement of expenditures incurred; and (ii) except for ineligible expenditures as detailed in the audit observations, if any, appended to this audit report, expenditures are eligible for financing under the Loan Agreement

(iv) The Imprest Account gives a true and fair view of the receipts collected and payments made during the year ended [insert date], and (ii) these receipts and payments support the Imprest Account Liquidation/ replenishments during the year

8. Template for the audit opinion on specific donor requirements has been given at Annex B.

9. ADB would expect that the auditors should advise a calendar for discussion/review of audit observations (particularly any serious matters) through tri-partite meetings and review meetings to facilitate executive follow-up on audit observations and recommendations. Moreover, ADB would need a review of actions taken on the recommendations presented in the previous audit report on the progress made.

D. PROGRAM FINANCIAL STATEMENTS (PFSs)

10. The Project Annual Financial Statements (APFSs) shall include: (i) Sources and Consolidated Uses of Funds showing the funds received and

expended from ADB and GON for BRBIP, as well as imprest account balances. (ii) Statement of Budget Vs Actual showing expenditure for the current year and

cumulative year to date (iii) Detailed notes to the financial statements including break down of expenditure,

reconciliation of reimbursements, Details of expenditure by Currency/Method of Funding, Statement of Imprest Account, and Accounting Policies

11. Annex to the APFS shall include the (i) Statement of Expenditure (ii) Imprest Account Ledger (iii) Imprest Account Reconciliation Statements (iv) Reconciliation Statement of

Reimburseable Fund (v) Disbursement Details (vi) Photocopy of the Imprest Account Bank

Statement, and (vii) Bank voucher for unspent balances.

Page 76: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 3 71

12. Project Books of Account shall be maintained by the Project Coordination and

Management Unit (PCMU) of the HPCIDBC.

13. Project Financial Statements shall provide sufficient level of detail to identify types of

expenditures as identified in the allocation Table of the Grant and loan Agreements; namely civil

works, consulting services, training, equipments, community initiatives and design and surveys.

14. The project financial statements shall also provide sufficient level of detail to be able to identify expenditure relating to each of the 5 Output of the Project; namely, (i) Output 1:Systems

and capacity for integrated and participatory river basin management established , (ii) Output 2:

Improved river banks environment in urban areas, (iii) Output 3: Increased water availability

during the dry season and watershed conservation, (iv) Output 4: Flood forecasting and early

warning system in the Bagmati River Basin is functional and (v) Output 5 The project is

efficiently managed with effective stakeholder communication 15. Draft template for the

Financial Statements has been given as Annex C to the Statement of Audit Needs. This has

been developed in line with Annexure 1 given in the Government Auditing Standards of the

Office of the Auditor General – Nepal 2005 as well as to incorporate key elements of the Nepal

Public Sector Accounting Standards, which have been approved by the GON, but shall be

effective from September 2016. Although these are not yet effective in Nepal, given the elevated

status of the NPSAS to top of the government accounting reform agenda, template for Project Financial Statements have incorporated some of the relevant requirements. A Summary of the

modifications to the Annexure given in the GAS is as follows: (i) Including a column for prior year comparative information in all statements and

notes (ii) Inclusion of an additional financial statement showing Budget Vs Actual, which was

previously treated as an Annexure to the financial statements

(iii) Inclusion of an additional Note V to the financial statements showing a break up of

all expenditure by each of the Output Components as per the Grant Agreement

(iv) Inclusion of an additional Note VI to the financial statements giving detailed

explanatory notes, and accounting policies

16. Please note that the template is a working draft, which may require adjustment based on

the actual activities of the Project. No Template has been provided for the Annexure to the financial statements. These should be prepared in accordance with above referred Government Accounting

Standards.

E. MANAGEMENT LETTER

17. In addition to the audit report, ADB will require a separate management letter. The management letter should be prepared in accordance with Annexure 12 of the Government Auditing Standards Part 3: Segment Audit Guidelines for Project Financial Statements issued by the Office of the Auditor General, Nepal in October 2005.

18. The management letter should specifically:

(i) Give comments and observations on the notes to the accounts, accounting records, systems, and internal controls that were examined during the course of the audit;

(ii) Identify specific deficiencies and areas of weakness in systems and internal controls and make recommendations for their improvement including MOE response to the identified deficiencies;

Page 77: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

72 Appendix 3

(iii) Communicate matters that have come to attention during the audit which might have a significant impact on the implementation of the Project; and

(iv) Bring to GON and ADB attention any other matters that the auditor considers

pertinent.

19. Serious issues, which affect the auditor’s opinion as to whether the financial statements give

a true and fair view, should be referred to in the audit opinion. Management Letter should include

only those issues which do not affect the fairness of the financial statements.

F. GENERAL

20. In case an external auditor needs to be commissioned for a supplementary audit, the auditor should be given access to all legal documents, correspondences, and any other information associated with the commission and deemed necessary by the auditor. Confirmation should also be obtained of amounts disbursed and outstanding with ADB and Government etc.

21. The auditor may examine the semi-annual financial reports prepared during the years to assess the methods used to compile them to ascertain that the information on these reports accurately reflects the underlying records and documents to ensure that there no material misstatements.

The auditor should also make follow-up of audit recommendations to their conclusion.

Note: This is a statement of audit needs of ADB and does not in any way intend to limit the scope of the statutory audit.

Page 78: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 4 73

PROCUREMENT PLAN

Basic Data Project Name: Bagmati River Basin Improvement Project Country: Nepal Executing Agency: Ministry of Urban

Development Government of Nepal

Loan/grant Amount: 24,5/5,5 Million US dollar Grant/Loan (Project) Number: Date of First Procurement Plan {Loan approval date} Date of this Procurement Plan: April, 2013

A. Process Thresholds, Review and 12-month Procurement Plan

1. Project procurement Thresholds

1. Except as the ADB may otherwise agree, the following process thresholds shall apply to procurement of gods and works, consulting services and NGO services.

Page 79: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

74 Appendix 4

3. Goods and works Contracts Estimated to Cost More than $1 million.

3. The following table lists goods and works contracts for which procurement activity is expected to commence within the next 18 months.

General Description Contract

value $ million

Procurement method

Prequalification Yes/No

Advertisement Period

(Quarter/Year)

Comments

Design & Construction of Dhap Dam

3.6

ICB Works

No

3/2013

Unit Rate

Construction of Upper Bagmati River Environment Improvement works

17.2

ICB Works

No

3/2013

Unit Rate

4. Consulting Services Contracts Estimated to Cost More than $100,000

4. The following table lists consultancy contracts for which procurement activity is expected to commence within the next 12 months.

General Description Contract

value $ million

Procurement method

Advertisement date

(Quarter/Year)

International or National Assignment

Comments

Detailed Design of Nagmati Dam

2.55

QCBS FTP

3/2014

International

Quality Cost ratio 90:10 (Full Technical Proposal)

Project Management Design & Supervision Consultant (PMSC)

2.75

QCBS FTP

3/2013

International

Quality Cost ratio 90:10 (Full Technical Proposal)

DSS Development, Flood Forecasting, IRBDMP and WQ Independent Environment Monitoring

1.72

0.065

QCBS FTP

ICS

3/2013

3/2014

International Quality Cost ratio 90:10 (Full Technical Proposal)

5. NGO Services Contracts Estimated to Cost More than $100,000

5. The following table lists consultancy contracts for which procurement activity is expected to commence within the next 12 months.

General Description Contract value $ million

Procurement method

Advertisement date

(Quarter/Year)

International or National Assignment

Comments

Rainwater Harvesting

0.68 QCBS STP

3/2013 National Quality Cost ratio 80:20 (Simplified Technical Proposal)

Page 80: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 4 75

Solid Waste and Social Mobilization

0.85

QCBS STP

3/2013

National

Quality Cost ratio 80:20 (Simplified Technical Proposal)

Watershed management

0.255

QCBS STP

3/2013

National

Quality Cost ratio 80:20 (Bio Data Proposal)

C. National Competitive Bidding (NCB Annex)

6. National competitive bidding (NCB) shall be in accordance with that described as "by inviting bids and a national level" as set forth in "The Public Procurement Act, 2007" (PPA) and "The Public Procurement Regulations, 2007" (PPR) and subject to the following: 7. The first NCB document for both goods and works procurement shall be reviewed and approved by ADB prior to issue. These will be used for all NCB procurement under the project. The document shall include qualification and evaluation criteria and ADB's right to audit and inspect in accordance with para 1.14 of ADB's Procurement Guidelines. No other criteria other than that described in the bidding document may be used to determine the lowest evaluated responsive bidder and no form of domestic preference may be employed. A positive assessment of a bidder's qualifications to perform a contract will be a pre-requisite to an award.

8. All qualified ADB member bidders and ADB member produced goods, services and works shall be eligible. Registration and licensing shall be permitted only as a condition of contract award and not participation in bidding. No award may be withdrawn for failure to obtain tax registration; license or fulfill any similar requirement without ADB's prior concurrence. No bidder will be held ineligible based on provision 63 of the PPA without ADB prior concurrence.

9. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper or freely accessible, nationally-known website allowing a minimum of twenty-eight (28) days for the preparation and submission of bids. Invitations for bids for contracts estimated at $500,000 or more for goods and $1,000,000 or more for civil works shall be advertised on ADB’s website. No restriction will be placed on the sale of bidding documents.

10. The approved Standing List of a Procuring Entity prepared in accordance with the law shall only be accepted to supplement an advertised open pre-qualification exercise for the specific contract provided that those on the standing list meet the qualification criteria.

11. Bids shall be opened at a single location immediately after the deadline for submission. Multiple locations for submission and opening are not acceptable.

12. Government-owned enterprises in Nepal shall be eligible to participate only if they meet the conditions of para 1.8 (c) of the Procurement Guidelines.

13. Extension of bid validity of more than 4 weeks beyond the original validity shall not be allowed without the prior concurrence of ADB.

Page 81: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

76 Appendix 4

14. Cancellation of bidding and re-bidding shall not be carried out without the prior concurrence of ADB.

15. Percentage variations from rates fixed by a district rate fixation committee shall not be used for the purpose of evaluating bids.

16. In the event of a conflict between these provisions and the law, these provisions shall prevail.

Page 82: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 77

DRAFT TERMS OF REFERENCE FOR PROJECT MANAGEMENT DESIGN AND SUPERVISION CONSULTANT (PMDSC)

1. The proposed Bagmati River Basin Improvement Project (the project) will improve water security and resilience to potential climate change impact in the Bagmati River Basin. It builds on the general public’s desire to restore the river environment in the Kathmandu Valley and the Government’s efforts mitigate the impact of water-induced disasters in the middle and lower reaches of the basin. The Project adopts the principles of integrated water resources management (IWRM) and provides Nepal with its first opportunity to apply this policy element since its adoption under the 2005 national water plan.

2. The project will complement the Government of Nepal’s (the government) ongoing efforts towards improving the wastewater services in Kathmandu Valley23 with the overall objective of improving the river water quality in the Bagmati River and achieve bathing water standards at strategic religious sites in the Upper Bagmati providing a safe environment for bathing and religious use of the river at the prominent temple sites at Gokarna and Pashupatinath.

3. The proposed Bagmati River Basin Improvement Project (the project) will provide the following non-structural measures: (i) legal and institutional strengthening for IWRM; (ii) support for formation of an RBO; (iii) capacity building and technical training for raising the RBO’s competence; (iv) legal support for allocating water from the Shivapuri reservoirs; (v) preparation of an Integrated River Basin Development and Management Plan (IRBDMP); (vi) establishment of a Central Water Resources Information and Modeling Decision Support System (DSS) including water quality monitoring, flood forecasting and warning; and (vii) preparation of design guidelines for land development (land-pooling) that introduces sustainable international best practices for storm water, wastewater and solid waste management.

4. Besides, the Project will construct (i) a small to medium sized dam with a storage capacity of 850.000 m3 a short distance downstream an existing small dam in Shivapuri Nagarjun National Park (SNNP), (ii) provide watershed enhancement and income generating activities for all 296 households in SNNP, (iii) construct eleven 1 meter high check dams/weirs, (iv) construct 14 km of river walls, (v) rehabilitate 2 existing regulators, (vi) upgrade and project two ghats, (vii) construct 1.2 km of gabion walls for river bank stabilization, (viii) develop 12.2 km of linear green zone with foot and bicycle paths, and develop 1.8 km green zone parks with foot paths and amenities.

5. ADB on behalf of the Project Management Unit (PCMU) of the High Powered Committee

for Integrated Development for Bagmati Civilization (HPCIDBC) will engage an international consulting firm as the Project Management Design and Supervision Consultant (PMDSC) in accordance with the Quality and Cost- Based Selection (QCBS) procedure set out in ADB‘s Guidelines on the Use of Consultants (2013, as amended from time to time) to provide for the project, the following services: (i) Support the Government of Nepal (GON) through the PCMU in project management and implementation of the Bagmati River Basin Improvement Project, using an integrated approach, including institutional support and capacity building, (ii) assist GON through the PCMU and DOI PIU in managing and supervising contractors engaged in construction of the works and consultants engaged in the production of detail designs The consultant will ensure timely progress of the works, enforce specified materials and workmanship requirements, and control the quality of the detail designs and the construction of

23

Kathmandu Valley Wastewater Management Project.ADB Project Number 43524.

Page 83: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

78 Appendix 5

river bank improvement works and dhap dam., (iii) provide support for RBO formation (local consultants) in addition to International Consultants to be provided under ADB Technical Assistance, (iv) Provide assistance for updating of by-laws for solid waste handling and rainwater harvesting at household levels, and for monitoring and enforcement of regulations for solid waste handling and rainwater harvesting. The consultant will also provide feasibility studies that meet ADB requirement and design build tender document in ADB format for river banks and river environment improvements on other tributaries of the Bagmati River in the Kathmandu valley including the Manohara, Dhobi Khola, Hanumante and Bishnumati. The consultant will support the PCMU, DOI and WECs with the procurement /contracting of works, goods consultants and NGOs as per requirements.

6. A total of 364 person months of consulting services (43 person-months international and

321 person-months national) will be required. The PMDSC will report to and work under the overall guidance of the PCMU, and is expected to commence its services by November 2013. The PMDSC is expected to provide the services during the following phases: (i) project implementation planning (3 months), design review, RBO formation support/procurement assistance and construction supervision through PCMU (24 months), and (iii) continued RBO formation support, support to PCMU (33 months). A. Scope

7. The scope of project management services of PMDSC will include but not necessarily be limited to the following: Planning and programming; (i) Procurement of works and services; (ii) Strengthening of institutions involved in the project; (iii) Promoting beneficiary participation in the project; Social and environmental safeguards, and Monitoring and evaluation.

8. The scope of the construction supervision is to assist the PCMU in the full-time supervision of construction of project works in the upper Bagmati river basin:

(i) Storage dam and reservoir at Nagmati Dhap; (ii) Restoration and protection of the Ghats at the Uttarbahini/KantiBhairab Temple

Complex & GokarneshworMahadev Temple Complex (iii) 11 Check dams between Gokarna and Sinamangal Bridge; (iv) Removal and safe disposal of contaminated and accumulated riverbed material

at key sites; (v) Rehabilitation of two former irrigation regulator structures downstream the

GokarneshworMahadev and Pashupatinath temple complexes; (vi) River environment improvement green zoning and provision of flood safety of the

riparian banks which are under government ownership from Gokarna to Guheshwori and from Tilganga to Sinamangal Bridge;

(vii) River bank beautification and phytoremediation from Tilganga to Sinamangal Bridge.

(viii) Rainwater harvesting and groundwater recharge sub-projects. (ix) Feasibility study and design of river improvement and beautification works in

other tributaries to the Bagmati River including for potential additional financing purposes.

Page 84: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 79

B. Staffing

9. The estimated personnel requirement for project management, support for RBO formation and construction supervision for the scope of works as outlined below is indicated in Table-1. Table 1: Summary of Proposed Project Management Consultancy Inputs

International Specialists months

Team Leader / Water Resources Specialist 20

M&E Specialist 3

Procurement Specialist 3

River Hydraulics & Structures Specialist 2

River Environment Beautification Specialist 2

Dam Specialist 3

Chief Construction Supervisor 6

Unallocated 4

Total International Specialists 43

National Specialists months

Deputy Team Leader/ Institutions Specialist 46

M&E Specialist 10

Procurement Specialist 14

Hydrologist 2

River Training and Improvement Specialist 3

Architect 3

Urban Planner & Land Pooling Expert 13

Watershed Management / Wetland Specialist 4

Social Development and Gender Specialist 12

Environment Specialist 14

Project Economist 4

Financial management specialist 4

Water Resources Specialist 11

Legal Specialist, Solid waste, Rainwater harvest by-laws 5

M&E Enforcement Specialist 5

Training Specialist 5

RBO Coordinator/Institutions Specialist 34

RBO Legal Specialist 6

RBO Other 6

Construction Supervision Specialist 1 18

Construction Supervision Specialist 2 16

Construction Supervision Specialist 3 16

Unallocated 70

Total National Specialists 321

TOTAL 364

Page 85: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

80 Appendix 5

10. Additionally, the PMDSC will allow adequate staff/allocation for CAD, IT, accounting, administrative support, etc., as required for the contract duration.

11. The PMDSC consultants‘ period of engagement shall be for a period of 60 months

starting from November 2013. The Team Leader shall be responsible for overall project management, design review and construction supervision, delivery of required outputs and consolidation of all required reports and deliverables under the contract. The planning and deployment of manpower shall be arranged such that the person-months allocations among PCMU and DOI PIU management support, design review, procurement management and construction supervision parts shall be optimum. It must also be ensured that the mobilization of consultants‘ resources, including manpower, during the supervision of works will fully match with the implementation schedule of the construction contractor so that there will be no unnecessary cost overruns during the supervision phase. C. Activities – International Specialists

1. Team Leader/Water Resources Specialist (International, 20 person-months)

12. The Team Leader/Water Resources Specialist will have extensive knowledge and experience on integrated water resources management preferably in South Asia. A minimum of Master's degree in civil/water resources engineering or related fields and15 years of work experience in water resources management and river environmental improvement related fields is required. S/he will be the main point of contact in assisting GON with implementation of all aspects of the Project. S/he will report to the PCMU project Manager and will lead the consulting team. S/he will be responsible for quality assurance, document preparation and coordination, project management and ensuring timely implementation of sub-projects. The Team Leader will:

(i) Be responsible for ooverall direction of the consultant team, coordination of inputs, and management of individual specialists;

(ii) Manage the relationships with government, the ADB and other stakeholders; (iii) Carry out a comprehensive review of the feasibility studies and draw attention to

changes which may have become necessary since its preparation; (iv) For project implementation, itemize key tasks and identify the resources and

schedules required, supporting the PCMU for sustainable system management and strategies for sustainable operation and maintenance of sub-project works;

(v) Identify tasks on the critical path and ensure that implementation schedules follow an integrated approach;

(vi) Ensure close coordination with KVUEIP implementation team; (vii) Assist the PCMU with all aspects of project administration, performance and

monitoring and preparation of reports; (viii) Ensure timely delivery of specified reports in a format acceptable to government

and the ADB. 13. As Water Resources Specialist s/he will assist GON in implementing IWRM for the Bagmati River Basin, including consultations and promoting legal and institutional changes necessary to establish an RBO. An important task will be updating the IWRM strategic roadmap agreed in the loan conditions and promoting its adoption, together with progress monitoring. He will:

Page 86: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 81

(i) Lead the project sub-component designed to improve water governance in the Bagmati basin following IWRM principles;

(ii) Promote updating and implementation of the IWRM strategic roadmap for the Bagmati river basin including establishment of a suitable River Basin Organization; (RBO) together with institutional changes and capacity building necessary for the sustainable establishment of such an RBO;

(iii) Assist the government by identifying requirements and modalities for the pursuance of IWRM, including monitoring of progress and meeting specified roadmap targets.

2. Monitoring and Evaluation (M&E) Specialist (International, 3 person-months)

14. The M & E Specialist will have relevant degree and a minimum of 10 years of experience on M & E of water and river engineering projects. S/he will work closely with the National M&E Specialist to develop capacities of PCMU staff and set up the HPCIDBC M&E system and ensure that the project is implemented in accordance with the project design and monitoring framework (DMF) and that issues arising are quickly identified and brought to the attention of government and the ADB for prompt resolution. S/he will:

(i) Carry out a review of the project preparation documents with regard to project monitoring and evaluation and draw attention to changes which may have become necessary since their preparation;

(ii) Support the Team Leader and PCMU in ensuring that the project is implemented in accordance with the project design and monitoring framework (DMF)and that issues arising are quickly identified and resolved;

(iii) Guide, coordinate and support the activities of the national M&E Specialist; (iv) Together with other experts of the Consultant, set up monitoring and evaluation

frameworks and PPMS for overall project activities. The PPMS will include a participatory baseline survey to be conducted within the first year of the Project with follow-up surveys to evaluate any changes. Monitoring and evaluation of pro-poor effects of the project will be integrated into the PPMS;

(v) Prepare the necessary guidelines for M&E consistent with project documents (RRP, the Loan Agreement, PAM, IEE/EIA and EMP, RF and RPs, IPPP or EMDP, SPRSS, GAP, etc.), ADB’s requirements, and regulations of the Government;

(vi) Together with the national M&E specialist, set up standards, contents and schedules for assistance to the PCMUs for M&E to ensure the project components are implemented as scheduled and outputs are as specified in the Loan Agreement;

(vii) Monitor and evaluate project performance and impacts as part of the project management information system;

(viii) Develop a community participation process in monitoring and evaluation for M&E systems;

(ix) Coordinate with the national M&E specialist in collection of data and evaluation of project implementation results;

(x) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

Page 87: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

82 Appendix 5

3. Procurement Specialist (International, 3 person-months)

15. The International Procurement Specialist will have a degree in engineering, project management, procurement management or finance and at least 10 years of relevant experience in procurement and contract management of infrastructure projects. H/she will work closely with the National Procurement Specialist to assist the PCMU with setting up the financial management system as per PAM recommendations and assist PCMU with procurements of the project ensuring compliance with ADB rules and regulations. Further ensure that all procurement for the project is carried out in accordance with the Project Administration Manual (PAM) and that issues arising are quickly identified and brought to the attention of government and the ADB for prompt resolution. The International Procurement Management Specialist will:

(i) Carry out a review of the Project Procurement Plan and contract packages in the Project Administration Manual and draw attention to changes which may have become necessary since their preparation;

(ii) Assess requirements under the Public Procurement Act 2063 of Nepal and ADB Procurement Guidelines and ensure that all project procurement is done is accordance with these guidelines

(iii) Assess procurement capacity of project institutions and recommend improvements

(iv) Assist PCMU in the preparation of bidding documents and Request for Proposals (RFP) for recruitment of consultants

(v) Assist project institutions in advance procurement/recruitment where necessary (vi) Prepare procurement guidelines for the project including but not limited to bid

notification and bid submission, bid evaluation and contract award and contract supervision and payment.

(vii) Guide, assist and monitor the activities of National Procurement in assisting the project team to prepare, update and adjust the detailed procurement plan every year, including content, schedule, resources, contract awards and disbursement

4. River Hydraulics and Structures Specialist (International, 2 person-months)

16. River Hydraulics and Structures Specialist will have a professional degree in river hydraulics or related fields and a minimum of 10 years of experience in river engineering design and supervision. The main task of the International River Hydraulics and Structures Specialist will be to oversee the technical aspects of construction of river hydraulic and structural works to be constructed in the Bagmati River and support feasibility studies of similar interventions in its tributaries. The River Hydraulics and Structures Specialist will:

(i) Review the design relating to river hydraulic and structural works under the Design & Build contract (including river front restoration, river training and erosion control) and draw attention to changes necessary, based on all available geotechnical and topographical survey information.

(ii) Assess suitability for construction of proposed structures; (iii) Identify and take into consideration any technical, environment or social

safeguard issues according to international best practices that should be addressed during construction;

(iv) Provide technical support to the Dam Specialist.

Page 88: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 83

(v) Lead the feasibility study and designs of additional river bank improvement works to be identified and undertaken in tributaries of the Bagmati rivers and financed out of the project and potential additional financing

(vi) Support design team in ensuring climate change potential impacts are factored in the design

(vii) In coordination with the KVUEIP project provide advice to urban planning authorities on implementation of sustainable urban drainage schemes (SUDS) within the river corridor;

(viii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

5. River Environment Specialist (International, 2 person-months)

17. The River Environment Beautification Specialist will have a professional degree on architecture/ landscape design or related fields with a minimum 10 years experience in landscape planning and/or river environment improvement. S/he will review the design and oversee the river improvement works, green zoning and phyto-remediation under the Design & Build contract covering all river environment works. The River Environment Beautification Specialist will:

(i) Review the design and oversee the river improvement works, green zoning and phyto-remediation under the Design & Build contract covering all works from Gokarna to Sinamangal Bridge and draw attention to changes necessary to optimize environmental benefits and aesthetic value of the works.

(ii) Assess suitability of the vegetation, both terrestrial for green zoning, and aquatic for beautification and phyto-remediation.

(iii) Assess the need for maintenance of green zones and phytoremediation and prepare maintenance guidelines and plans for the various river sections with green zones and with and without phytoremediation.

6. Dam Specialist (International, 3 person-months)

18. The International Dam Specialist will have degree in civil/water resources engineering or related fields and a minimum of 10 years of demonstrated experience in dam design and planning. S/he will oversee the technical aspects of design & and support construction supervision of the Dhap dam in the Shivapuri National Park. The Dam Specialist will:

(i) Carry out a review of the design of the Dhap Dam under the Design & Build contract, based on all available geotechnical and topographical survey information, and draw attention to changes which may have become necessary since their preparation;

(ii) Advise DOI and the construction supervisor on necessary dam construction supervision procedures

(iii) Carry out review of the detailed design of the Nagmati dam (iv) With assistance from other team members, review environment and social

safeguard issues relating to dam design, implementation and operation; (v) Ensure that all matters relating to dam design, implementation and operation are

dealt with according to international best practice (vi) Assist the Team Leader and Deputy Team Leader in timely preparation of

reports.

Page 89: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

84 Appendix 5

7. Chief Construction Supervisor (International, 6 person-months)

19. The Chief Construction Supervisor will have a degree in construction management/structural engineering or related and a minimum of 10 years of demonstrated work experience on construction supervision of infrastructure projects preferably in South Asia. S/he will be the main point of contact in assisting GON through the PCMU with supervising construction of the project works. S/he will manage and supervise the contractors engaged in construction of the works, ensuring timely progress, enforcing specified materials and workmanship requirements, and ensuring quality of construction. The Chief Construction Supervisor will:

(i) Manage and supervise contractors in the role of Engineer; (ii) Prepare partial, substantial and final completion certificates; (iii) Supervise and monitor the local consultants and contractors; (iv) Supervise construction on a day-to-day basis and control and monitor quality of

construction; (v) Issue interim paymentcertificates; (vi) Examinecontractors’claims; (vii) Examine need for contract variations; (viii) Monitor compliance with environmental mitigation and management plans; (ix) Monitor preparation of as-built drawings.

8. Un-allocated (International, 4 person-months)

20. As the support consultancy progresses, it is likely to become evident that specialised expertise will be required for certain areas of water management and organization. Consequently four person-months of international expertise are allocated for this purpose, details to be defined after the consultancy has commenced.

D. Activities – National Specialists

1. Deputy Team Leader / Institutions Specialist (National, 46 person-months)

21. The Deputy Team Leader/Institutions Specialist will have a relevant degree with a demonstrated work experience of a minimum of 7 years in water resources/environment project implementation. S/he will be the main point of contact in assisting GON with implementation of all aspects of the Project. The Deputy Team Leader will assist the Team Leader with quality assurance, document preparation and coordination, project management and ensuring timely implementation of sub-projects. The Deputy Team Leader will:

(i) Assist the Team Leader in coordination of inputs and management of individual specialists;

(ii) Ensure good working relationships with government and other stakeholders; (iii) Work with the Team Leader in making a comprehensive review of the feasibility

studies and drawing attention to changes which may have become necessary since its preparation;

(iv) Assist the Team Leader in itemizing key tasks for project implementation and identifying the resources and schedules required, supporting the PCMU for sustainable system management and strategies for sustainable operation and maintenance of sub-project works;

(v) Ensure close coordination with KVUEIP implementation team;

Page 90: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 85

(vi) Assist the PCMU with all aspects of project administration, performance and monitoring and preparation of reports;

(vii) Ensure timely delivery of specified reports in a format acceptable to government and the ADB.

22. As Institutions Specialist he will assist GON and the International Institutions, Community and Participation Specialist in gaining the support of institutions and beneficiaries in implementation of the Project. He will:

(i) At the local level, assist the International Institutions, Community and Participation Specialist in promoting social and institutional aspects of participation, ownership, acceptance, and adoption of project activities, and developing strategies to overcome any local concerns or other issues;

(ii) Work together with other team members to facilitate cooperation between sector ministries/agencies, local government and communities in implementing the Project;

(iii) Assist NGOs, CBOs and/or the private sector where they have a role in implementing the Project;

(iv) Lead project stakeholder validation and consultation workshops. (v) Assist the International Institutions, Community and Participation Specialist in

implementation of the communication, consultation and participation plan, engaging civil society, politicians, academia, private sector and other stakeholders throughout project implementation, and including use of local and electronic media.

2. Monitoring and Evaluation Specialist (National, 10 person-months)

23. The National Monitoring and Evaluation (M&E) Specialist will have a degree in management or engineering or related field and a minimum of 5 years of demonstrated experience in project M & E. S/he will work closely with the International M&E Specialist and the Team leadership to ensure that the project is implemented in accordance with the project design and monitoring framework (DMF) and that issues arising are quickly identified and brought to the attention of government and the ADB for prompt resolution. The National M&E Specialist will:

(i) Assist the International M&E Specialist in carrying out a review of the project preparation documents with regard to project monitoring and evaluation and draw attention to changes which may have become necessary since their preparation;

(ii) Support the International M&E Specialist, Team Leader and PCMU in ensuring that the project is implemented in accordance with the project design and monitoring framework (DMF)and that issues arising are quickly identified and resolved;

(iii) Together with other experts of the Consultant, set up monitoring and evaluation frameworks and PPMS for overall project activities. The PPMS will include a participatory baseline survey to be conducted within the first year of the Project with follow-up surveys to evaluate any changes. Monitoring and evaluation of pro-poor effects of the project will be integrated into the PPMS;

(iv) Prepare evaluation criteria for each activity, and role and tasks of the agencies; (v) Work with government experts and other specialists in the team to develop:

indicators that is objective, obvious and effective,

databases for effective data collection and management,

Page 91: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

86 Appendix 5

methods for evaluation and analysis,

procedures for audit and control (vi) Assist in preparation of necessary guidelines for M&E consistent with project

documents (RRP, the Loan Agreement, PAM, IEE/EIA and EMP, RF and RPs, IPPP or EMDP, SPRSS, GAP, etc.), ADB’s requirements, and regulations of the Government;

(vii) Set up standards, contents and schedules for assistance to the PCMUs for M&E to ensure the project components are implemented as scheduled and outputs are as specified in the Loan Agreement;

(viii) Prepare M&E/PPMS Manuals for monitoring and assessment and ensure that relevant agencies comply with these manuals;

(ix) Collect data, monitor and evaluate project performance and impacts as part of the project management information system;

(x) Assist in development of a community participation process in monitoring and evaluation for M&E systems;

(xi) Support the team in preparation and organization of training/workshop programs on data management and using M&E for the PCMU, project stakeholders and other government staff;

(xii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

3. Procurement Specialist (National, 14 person-months)

24. The National Procurement Specialist have a degree in engineering, project management, procurement management or finance and at least 5 years of relevant experience in procurement and contract management of infrastructure projects. H/she will ensure that all procurement for the project is carried out in accordance with the Project Administration Manual (PAM) and that issues arising are quickly identified and brought to the attention of government and the ADB for prompt resolution. The National Procurement Specialist will:

(i) Carry out a review of the Project Procurement Plan and contract packages in the Project Administration Manual and draw attention to changes which may have become necessary since their preparation;

(ii) Assess requirements under the Public Procurement Act 2063 of Nepal and ADB Procurement Guidelines and ensure that all project procurement is done is accordance with these guidelines

(iii) Assess procurement capacity of project institutions and recommend improvements

(iv) Assist PCMU in the preparation of bidding documents and Request for Proposals (RFP) for recruitment of consultants

(v) Assist project institutions in advance procurement/recruitment where necessary (vi) Assist the International Procurement Specialist in carrying out a review of the

project preparation documents with regard to procurement and financial management and draw attention to changes which may have become necessary since their preparation;

(vii) Support the International Procurement / Financial Management Specialist, team leadership and PCMU in ensuring that the project is implemented in accordance with the Project Administration Manual (PAM) to ensure that management and operation mechanisms will be effective, obvious and sustainable, and that issues arising are quickly identified and resolved;

Page 92: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 87

(viii) Assist the International Procurement / Financial Management Specialist to prepare, update and adjust the detailed procurement plan every year, including content, schedule, resources, contract awards and disbursement;

(ix) Assist in preparation of a handbook for procurement in accordance with ADB procurement policies and guidelines and GON regulations;

(x) Guide, support and monitor the PCMU and other relevant agencies from central to local levels in procurement and financial management in accordance with the above handbook;

(xi) Assist the PCMU with reviewing contents of packages and the procurement plan and updating as necessary of tender documents in accordance with ADB policy and government regulations (including forms of payment, audit procedures, disbursement and preparation of reports related to financing activities);

(xii) Prepare standard criteria and checklists for evaluation of the tenders and assist the PCMU in preparation of the bid evaluation reports and assist the PCMU in reviewing the selection process of bidders;

(xiii) Support the PCMU in procurement activities for national competitive bidding (NCB), international competitive bidding (ICB), selection of consultants according to the ADB’s guidance and the Government’s regulations;

(xiv) Assist the PCMU with contract negotiations, preparation of contracts and contract awards;

(xv) Provide advice to the PCMU on claims, if any, related to the procurement and contracts;

(xvi) Coordinate with the M&E Specialists in setting up a monitoring system on procurement and contracts for the whole project from central to local level in a unified framework in accordance with the monitoring framework and project design;

(xvii) Assist the project implementation officers of the PCMU in preparing and delivering (on-the-job) training programs related to procurement, contracts, financial management and disbursements;

(xviii) Update, monitor and evaluate the payment and disbursement of all packages in the project and identify the causes to the existing problems, delays and propose the measures;

(xix) Assist the PCMU in preparing monthly reports for procurement preparation, contract awards, contract management and performance for each contract package;

(xx) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

4. Hydrologist (National, 2 person-months)

25. The Hydrologist will have a degree in hydrology or water resources/civil engineering and a minimum of 5 years of experience in hydrological studies and analysis of water/river engineering projects. The principal role of the National Hydrologist will be to ensure that project designs and operational procedures are consistent with the latest hydrological information, and to promote good cooperation between the project and existing agencies responsible for hydrometry and associated disciplines. The National Hydrologist will:

(i) Carry out a review of the project preparation documents with regard to hydrological analysis and draw attention to changes which may have become necessary since their preparation;

Page 93: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

88 Appendix 5

(i) Review the existing hydro-met monitoring system within the river basin in terms of its appropriateness to the project, and recommend any improvements (including rainfall and flow monitoring) necessary to support the development of both the IWRM programmed DSS; Support design team in ensuring climate change potential impacts are factored in the design

(ii) Support the Dam Specialist and DSS / River Modeling Specialist by contributing hydrological information and design parameters for their work;

(iii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

5. River Training Specialist (National, 3 person-months)

26. The National River Hydraulics and Structures Specialist will have a degree in River Engineering or related field and a minimum of 5 years of relevant work experience. S/he will assist in overseeing the technical aspects of construction of river hydraulic and structural works to be constructed in the Bagmati River and its tributaries. The National River Hydraulics and Structures Specialist will:

(i) Assist others in the team to review previous documents relating to river hydraulic and structural works (including river front restoration, river training and erosion control) also all available geotechnical and topographical survey information, and draw attention to changes which may have become necessary since their preparation;

(ii) Assist the team in considering technical, environment or social safeguard issues according to international best practices that should be addressed during construction;

(iii) Provide technical support to the Dam Specialist, Decision Support System / River Modeling and other technical specialists;

(iv) Assist in providing advice to urban planning authorities on implementation of sustainable urban drainage schemes (SUDS) within the river corridor;

(v) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

6. Architect (National, 3 person-months)

27. The architect will have a professional degree on architecture/landscape design or related fields with a minimum 10 years of experience in landscape planning and/or river environment improvement. S/he will review the design of river improvement and beautification and oversee the proper materials are used, the general works, green zoning and amenity provisions under the Design & Build contract covering all river environment works. The Architect will:

(i) Review the design and oversee the river improvement works, green zoning and amenity provision under the Design & Build contract covering all works from Gokarna to Sinamangal Bridge and draw attention to changes necessary to optimize environmental benefits and aesthetic value of the works.

(ii) Assess suitability of the park and green zone vegetation, and oversee implementation,

(iii) Asses the suitability of the building materials, detailed design and construction methods used, in order for this to harmonise with the conceptual designs developed during the feasibility study.

Page 94: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 89

(iv) Oversee works and construction activities to ensure compatibility with architectural design.

(v) Assess the need for maintenance of riparian river improvement works, green zones, amenities and prepare maintenance guidelines and plans for the various river sections with green zones and with and without phytoremediation.

7. Urban Planner & Land Pooling Expert (National, 13 person-months)

28. The Urban Planner & Land Pooling Expert will have a degree in civil engineering, urban planning or related field and a minimum of 5 years of relevant work experience. S/he will provide support for the use of best practice in land pooling projects in the Upper Bagmati basin. The Urban Planner & Land Pooling Expert will:

(i) Prepare best practice guidelines for land pooling based on experience from the range of land pooling projects carried out already in Kathmandu in close cooperation with stakeholders in the Upper Bagmati;

(ii) Promote the Best Practice Guidelines to all parties involved or potentially involved in land pooling in Upper Bagmati;

(iii) Provide training on best Practice to KVDA, relevant PCMU staff, VDCs, local community groups and landowners;

(iv) Assist the PCMU in overseeing and monitoring any land pooling project activities in the Upper Bagmati;

(v) On a regular basis review the Best Practice Guidelines for land pooling as project activities progresses and update the Guidelines when required.

(vi) Assist the PCMU reporting on urban development activities, including land pooling in the Upper Bagmati.

8. Watershed Management/Wetland Specialist (National, 4 person-months)

29. The National Watershed Management/Wetland Specialist will have a degree in environment, watershed management, natural resources management or related field and a minimum of 5 years of relevant experience. S/he will oversee the technical and community participation aspects of the construction and operation of works to be constructed in the Shivapuri Nagarjun National Park and the Bagmati river corridor. The National Watershed Management / Wetland Specialist will:

(i) Carry out a review of the project preparation documents with regard to watershed management, wetlands and rainwater harvesting and draw attention to changes which may have become necessary since their preparation;

(ii) Act as the principal point of contact between the project, community groups and government agencies responsible for watershed and wetland management, and rainwater harvesting, including construction and operational aspects;

(iii) With assistance from other team members, oversee implementation of the project sub-component relating to watershed and wetland management, rainwater harvesting, community participation and subsequent operation;

(iv) Assist the SNNP authorities with tree replantation program; (v) Assist the SNNP authorities in delineating buffer zone and preparing

management plan; (vi) Assist SNNP authorities in (a) mapping the dam(s) foot print and direct

surrounding area and (b) preparing specific management plan(s) to mitigate possible impact of increased tourism/visitors;

Page 95: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

90 Appendix 5

(vii) Support the team in preparation and organization of training/workshop programs on data management and using M&E for the PCMU, project stakeholders and other government staff;

(viii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

9. Social Development and Gender Specialist (National, 12 person-months)

30. The National Social Development and Gender Specialist will have degree in social science, gender studies or related field and a minimum of 5 years of experience in social development or gender mainstreaming, S/he will ensure that the project is implemented in accordance with the principles of GON and the ADB to minimise adverse social impact and to promote positive aspects of the project for the community, including their active participation towards the project’s goals. The specialist will also pursue positive aspects of the project with regard to gender and the approved Gender Equality and Social Inclusion (GESI) Plan. The National Social Development and Gender Specialist will:

(i) Carry out a review of the feasibility studies (including safeguard documents, SPRSS and GESI) with regard to social impact, participation and gender and draw attention to changes which may have become necessary since their preparation;

(ii) During the inception period the Specialist will review the nature of the project with regard to land acquisition and resettlement and, if there are significant issues, draw attention to these so that they can be adequately dealt with at inception by expanding project management inputs (e.g. with a specialist specifically to oversee resettlement and an Independent Resettlement Monitor).

(iii) Take primary responsibility for overseeing the project from a social and gender perspective and implementation of project components and mechanisms to ensure (a) the active participation of the beneficiary community, and (b) participation of women and girls;

(iv) Ensure the quality and timely implementation of the GESI Action Plan (v) Provide GESI technical support in the implementation of all components, as well

as ensure that implementing partner NGOs adhere to the GESI Action Plan targets

(vi) Assist the PCMU in coordinating project implementation with relevant agencies and stakeholders, and in implementing an integrated programme of community mobilization, agricultural and social support;

(vii) Provide monitoring of project progress with particular regard to social and gender targets and indicators set out in the Design and Monitoring Framework (DMF);

(viii) In carrying out field appraisal, stakeholder consultation and review of existing initiatives, ensure that data collected are disaggregate by sex;

(ix) Contribute a gender perspective to the activities and outputs of other team members, particularly the institutions and environment specialists;

(x) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

10. Environment Specialist (National, 14 person-months)

31. The National Environmental Specialist will have a degree in environmental science or engineering or related field and a minimum of 5 years of work experience in overseeing environmental management plans of infrastructure projects. S/he is expected to be familiar with

Page 96: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 91

the GON and ADB's environmental safeguard requirements including climate change project adaptation measures. S/he will ensure that the project is implemented in accordance with the environmental laws of Nepal and the ADB environmental safeguard policy by overseeing implementation of Environmental Management Plans (EMP) and assisting the PCMU to monitor impacts. The National Environmental Specialist will:

(ii) Carry out a review of the feasibility studies (including safeguard documents, IEE and EIA) with regard to environmental impact and draw attention to changes which may have become necessary since their preparation;

(iii) Update the EMP based on detailed designs and ensure that contractor complies with measure state,

(iv) Carry out a review of the Environmental Management Plans (EMP) and monitoring mechanisms and recommend any updating which may be required;

(v) Assist the PCMU with implementation and coordination of EMPs and with identification and subsequent implementation of corrective management actions;

(vi) Oversee preparation and approval of the site EMPs of construction contractors and monitor implementation of these for the purposes of quarterly reporting;

(vii) Undertake a review of potential cumulative and induced environmental impacts which may occur downstream or elsewhere in the Bagmati river basin as a result of project interventions;

(viii) Provide monitoring of project progress with regard to environmental targets and indicators set out in the Design and Monitoring Framework (DMF);

(ix) Support design team in ensuring climate change potential impacts are factored in the designs of additional river bank improvement works.

(x) Provide semi- annual environmental monitoring reports (xi) Assist the Team Leader and Deputy Team Leader in timely preparation of

reports.

11. Project Economist (National, 4 person-months)

32. The National Project Economist will have a degree in economics or related field with a minimum of 7 years of work experience in related field, with working experience from ADB projects. The project economist will be responsible for the economic analysis of other tributaries of the upper Bagmati (such as the Bishnumati), that may be identified once the project is being implemented. He will

(i) Carry out a detailed economic analysis of river works and other project interventions in selected tributaries of the upper Bagmati in accordance with ADB Guidelines for the Economic Analysis of Projects (1997)

(ii) Prepare detailed budget of such investments, analyse project benefits and poverty impact analysis of the works consistent with ADB guidelines.

12. Financial Management Specialist (National, 4 person-months)

33. The National Financial Management Specialist will have a degree in finance or professional certification in accounting with at least 5 years relevant experience in financial management preferably in donor funded projects or in the public/ private sector. He/she will work closely with the International Financial Management Specialist national Financial Management Specialist will:

Page 97: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

92 Appendix 5

(i) Assist PCMU in overall financial management, i.e., disbursement of funds, review of Withdrawal Applications, monitoring of project and counterpart funds.

(ii) Plan and implement training programs for PCMU staff in project accounting and ADB procedures for disbursements

(iii) Assist PCMU staff in the preparation of project accounts in a format suitable for both ADB and national requirements;

(iv) Assist PCMU staff in developing a system of internal control to ensure accurate and reliable financial information

(v) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

13. Water Resources Specialist (National, 11 person-months)

34. The Water Resources Specialist will have a professional degree in water resources engineering/management or related fields and a minimum of 10 years of experience in water resources. As National Water Resources Specialist s/he will assist the Team Leader to support GON in implementing IWRM for the Bagmati River Basin, including consultations and promoting legal and institutional changes necessary to establish an RBO. An important task will be updating the IWRM strategic roadmap agreed in the loan conditions and promoting its adoption, together with progress monitoring. S/he will support the Team Leader to carry out the following:

(i) Support the sub-component designed to improve water governance in the Bagmati basin following IWRM principles;

(ii) Promote updating and implementation of the IWRM strategic roadmap for the Bagmati river basin including establishment of a suitable River Basin Organization; (RBO) together with institutional changes and capacity building necessary for the sustainable establishment of such an RBO;

(iii) Assist the government by identifying requirements and modalities for the pursuance of IWRM, including monitoring of progress and meeting specified roadmap targets.

14. Legal Specialist, Solid Waste, RWH Bye-laws Specialist (National, 5 person-months)

35. The Specialist will have a professional degree in law or related fields and a minimum of 10 years of experience in legal and policy issues related to water and sanitation. As Legal Specialist (solid waste/RWH), s/he will assist the Team Leader in reviewing and formulating bye-laws to support RWH and SWM. An important task of the specialist will be to guide managing the selected NGO to undertake activities related to RWH and SWM S/he will:

(i) Reformulation of by-laws to make the construction of rain water harvesting system mandatory in the new buildings;

(i) Update existing bye-laws and guidelines to incorporate internationally best and nationally appropriate practices of solid waste management and ensure its effective implementation;

(ii) Any other activity required to enhance the enabling environment to promote RWH/SWM.

Page 98: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 93

15. M & E Enforcement Specialist (National, 5 person-months)

36. The National M&E Enforcement Specialist will have a degree in management or engineering or related field and a minimum of 5 years of demonstrated experience in project M & E enforcement. S/he will work closely with the International/national M&E Specialist and the Team leadership to ensure that the M & E of project is as per the M & E policy and in accordance with the project design and monitoring framework (DMF). The National M&E Enforcement Specialist will:

(i) Assist the PCMU in carrying out a review of the project preparation documents with regard to project monitoring and evaluation and draw attention to changes which may have become necessary since their preparation;

(ii) Support the PCMU in ensuring that the project is implemented in accordance with the project design and monitoring framework (DMF)and that issues arising are quickly identified and resolved;

(iii) Support the PCMU to enforce the project activities are consistent with project documents (RRP, the Loan Agreement, PAM, IEE/EIA and EMP, RF and RPs, IPPP or EMDP, SPRSS, GAP, etc.), ADB’s requirements, and regulations of the Government;

(iv) Support the PCMU to enforce standards, contents and schedules to ensure the project components are implemented as scheduled and outputs are as specified in the Loan Agreement;

(v) Support the PCMU to enforce project activities are as per the M&E/PPMS Manuals for monitoring and assessment and ensure that relevant agencies comply with these manuals;

(vi) Collect data, monitor and evaluate project performance and impacts as part of the project management information system;

(vii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

16. Training Specialist (National, 5 person-months)

37. The National Training Specialist will have a degree in management or engineering or related field and a minimum of 5 years of demonstrated experience in designing and implementing training programs. S/he will work closely with other subject specialists to prepare and implementing a training and capacity building program for the BRBIP. The Training Specialist will:

(i) Assess the capacity of the relevant staff of EA/IA and other key stakeholders with regards to the skills and capacity required to implement the Project;

(ii) Assist the PCMU and the PIUs in preparing and implementing a training and capacity building program to support the project; and

(iii) Implement training programs as per the agreed plan in cooperation with the consultants and teams undertaking the project activities.

17. RBO Coordinator/ Institutions Specialist (National, 34 person-months)

38. The Deputy Team Leader / Institutions Specialist will be having degree in IWRM or related field and a minimum of 7 years of work experience in related fields. S/he will be the main point of contact in assisting GON and HPCICBC with capacity building and training for the Bagmati RBO. He will support the Team Leader and RBO secretariat in the main task of

Page 99: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

94 Appendix 5

forming and strengthening the RBO. As Institutions Specialist he will ensure that the RBO is fully engaged with stakeholders and relevant institutions. He will:

(i) Support the Team Leader and RBO secretariat in forming and strengthening the RBO and in gaining the support of stakeholders and relevant institutions and in continuing IWRM/RBO policy and dialogue for institutional reform;

(ii) Assist the team in carrying out a comprehensive review of the past and present water resources institutional and management initiatives and discuss need for any updating with the specialist carrying out legal studies on establishment of the RBO;

(iii) Establish and maintain contact with relevant NGOs and community-based organizations in the area covered by the Bagmati RBO;

(iv) Together with the International Institutions Specialist and other team members, conduct interviews, focus groups or other meetings with stakeholders to confirm their interests, constraints, and willingness to engage with IWRM;

(v) Work under the guidance of the International Institutions, Community and Participation Specialist to promote social and institutional aspects of participation, acceptance and adoption of RBO activities, and develop strategies to overcome any local concerns or other issues;

(vi) Assist GON and BRBIP to identify and agree the form and structure of the Bagmati RBO;

(vii) Work with the International Institutions and Training Specialists to focus on the most urgent social needs (including awareness-raising) within the basin to assist the Institutional and Community Outreach section of the RBO secretariat;

(viii) Ensure timely delivery of specified reports in a format acceptable to government and the ADB.

18. Water legal Specialist (National, 6 person-months)

39. The Legal Specialist will have a degree in Law or related fields and a minimum of 7 years of experience in water law or related fields. S/he will study the existing legal background and do legal drafting for the formation of an RBO based in IWRM principles, and establishing legal basis for water allocation in the Upper Bagmati basin. The Legal Specialist will:

(i) Prepare the legal requirements for the formation of an RBO for the Bagmati river basin, to ensure it is sufficiently empowered to guarantee its effectiveness and longevity following completion of the Project.

(ii) Identify the legal reforms needed to reduce and eventually eliminate the overlapping mandates of KVDA, HPCIDBC, WECS, MUD, KUKL, Municipalities and other prominent agencies.

(iii) In the context of IWRM, identify legal reforms needed relating to stopping (i) the dumping of solid waste in the Bagmati river and on its banks, (ii) sand mining, and (iii) uncontrolled discharge of wastewater to the river.

(iv) Based on (i), (ii) and (iii) propose and promote through dialogue with stakeholders the legal strengthening measures that would support IWRM;

(v) Draft the legal requirements for: (i) environmentally safe allocation of water emerging from the Shivapuri National Park, (ii) enforcement of best practices in land pooling, and (iii) establish the ownership and responsibility for management of groundwater.

(vi) Provide further legal assistance to the RBO formation during the foreseen three year period for emerging needs.

Page 100: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 5 95

19. RBO Un-allocated (National, 6 person-months)

40. As the support consultancy progresses, it is likely to become evident that specialised expertise will be required for certain areas of water management and organization. Consequently six person-months of national expertise are allocated for this purpose, details to be defined after the consultancy has commenced.

20. Construction Supervisor 1 (National, 18 months)

41. The Construction Supervisor will have a degree in construction management/civil engineering or related field and a minimum of 5 years of work experience in construction supervision. Under the guidance of the International Chief Construction Supervisor, the Construction Supervisor No1 will deputise for the Chief Construction Supervisor, and assist in management and supervision of the contractors engaged in construction of designated works, ensuring timely progress, enforcing specified materials and workmanship requirements, and ensuring quality of construction. The National Construction Supervisor No1 will:

(i) Manage and supervise contractors in the role of Engineer; (ii) Prepare partial, substantial and final completion certificates; (iii) Supervise and monitor the local consultants and contractors; (iv) Supervise construction on a day-to-day basis and control and monitor quality of

construction; (v) Examine contractors’ claims and need for contract variations; (vi) Monitor compliance with environmental mitigation and management plans; (vii) Monitor preparation of as-built drawings.

21. Construction Supervision Specialist 2 (National, 16 months)

42. The Construction Supervisor will have a degree in construction management/civil engineering or related field and a minimum of 5 years of work experience in construction supervision. The second National Construction Supervision Specialist (No2) will work under the guidance of the Team Leader and his deputy, to assist in management and supervision of contractors engaged in construction of designated works, to ensure timely progress, enforcement of specified materials and workmanship requirements, and to ensure quality of construction. The National Construction Supervision Specialist No2 will:

(i) Manage and supervise contractors in the role of Engineer; (ii) Prepare partial, substantial and final completion certificates; (iii) Supervise and monitor the local consultants and contractors; (iv) Supervise construction on a day-to-day basis and control and monitor quality of

construction; (v) Examine contractors’ claims and need for contract variations; (vi) Monitor compliance with environmental mitigation and management plans; (vii) Monitor preparation of as-built drawings.

22. Construction Supervision Specialist 3 (National, 16 months)

43. The Construction Supervisor will have a degree in construction management/civil engineering or related field and a minimum of 5 years of work experience in construction supervision. The third National Construction Supervision Specialist (No3) will also work under

Page 101: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

96 Appendix 5

the guidance of the Team Leader and his deputy. His duties will be as those of National Construction Supervision Specialist No2.

23. Un-allocated (national, 70 person-months)

44. As the support consultancy progresses, it is likely to become evident that specialised expertise will be required for certain areas of water management and organization. Consequently four person-months of international expertise are allocated for this purpose, details to be defined after the consultancy has commenced

E. Reporting

45. Minimum reporting requirements from the PMDSC is as follows:

(i) Inception Report: As soon as the project is commenced, the consultant shall prepare an Inception Report. Based on the output of discussions with the PCMU and field visits, the consultant shall review and verify the content of the tasks required. The consultant shall also elaborate in detail: (i) overall assessment of the tasks for the outputs required, and any changes proposed, (ii) work and staffing plans, and any changes proposed, (iii) programme for delivery of required reports.

(ii) Quarterly Reports: Based on the results of monitoring and day-to-day progress, the consultant shall prepare a quarterly report every three months. These reports must present all the findings related to procurement and to monitoring requirements identified in the DMF, including progress on delivering the outputs. Quarterly reports will also summarise the results of relevant data collected.

(iii) Mid-term Report: The Mid-term Report will summarise all aspects of project implementation up to the specified date of the mid-term review together with progress against the loan and the DMF. The report will summarise and discuss all specialist aspects of the project including construction, capacity building, social and environmental safeguards, together with conclusions and any recommendations for adjustment.

(iv) Final Report: The Final Report will present a summary of all aspects of project implementation and comparison with the expectations of the loan (or as subsequently adjusted) and of the DMF. The report will summarise and discuss the results of specialist aspects of the project including construction, capacity building, social and environmental safeguards, together with conclusions, recommendations and lessons learned for future projects.

46. For each report, four copies in English are to be submitted. In addition to hard copies, one digital electronic copy shall also be submitted. At the end of the contract, a digital copy of all documents relevant to the project shall be compiled in an orderly manner on a CD and be submitted to the PCMU.

Page 102: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 97

DRAFT TERMS OF REFERENCE FOR FLOOD FORECASTING AND EARLY WARNING SYSTEM AND DECISION SUPPORT SYSTEM

A. Overview

1. The proposed Bagmati River Basin Improvement Project (the project) will improve water security and resilience to potential climate change impact in the Bagmati River Basin. It builds on the general public’s desire to restore the river environment in the Kathmandu Valley and the Government’s efforts to mitigate the impact of water-induced disasters in the middle and lower reaches of the basin. The Project adopts the principles of integrated water resources management (IWRM) and provides Nepal with its first opportunity to apply this policy element since its adoption under the 2005 national water plan.

2. The project plans to engage an international firm(s) (in association with a national firms if necessary) to undertake the following packages:

(i) Package 1: Development of the Decision Support System (DSS) (ii) Package 2: Flood Forecasting and Early Warning System (FFEWS)

3. The two activities are separate activities contributing to different outputs, namely, Output 1 - Effective integrated and participatory river basin management and Output 4 -Reduced water-induced disaster impact on basin communities. These may be awarded to different firms or to a single firm depending on the experience and expertise of the applying consulting firms. Development of the Decision Support System (DSS) B. Package 1: Development of the Decision Support System (DSS)

1. Objective of the Bagmati DSS

4. The Bagmati DSS will support Integrated Water Resources Management planning and investment decisions in the Bagmati river basin. Its scope includes not only the Bagmati DSS itself, but also the development of core institutional capabilities to assist in the evaluation of alternative development strategies and the identification of investment project at the basin or sub-basin level in future.

5. The basic purpose of the Bagmati DSS is to provide a framework for knowledge sharing, understanding the river system behavior, designing and evaluating alternative development scenarios, investment projects, and management strategies. The Bagmati DSS should help to “enhance the capacity to support basin wide communication and information exchange, and identify opportunities for sector cooperative development of the Bagmati water resources”.

2. The Development Process

6. The Bagmati DSS development process is based on a thorough needs assessment and a subsequent conceptual design of the system. Based on the situation analysis in terms of hydrology, water availability and use patterns, environmental and socio-economic issues a stakeholder’s workshop is planned for shared training needs assessment and identification of requirements to the Bagmati DSS.

Page 103: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

98 Appendix 6

3. Institutional Context

7. WECS is considered to be the implementing agency for the DSS development. WECS has established an Information Centre that provides updated information on water resources at basin level to stakeholders via its Web-Page. WECS operates and updates their information system on a regular basis.

8. The functional requirements of the DSS will depend on institutional interaction between data collection institutions (DHM for hydrology and meteorology, HPCIDBC presently doing water quality monitoring etc.), and the institutions that will have access to, and use the Bagmati DSS information.

4. Capacity for DSS Development, Operation and Maintenance

9. Being a new concept, the national capacity for DSS design and development is somewhat limited. The design and development of DSS systems for IWRM is carried out be highly specialized consultants.

10. Based on developments carried out e.g. for the Nile Basin24 and the DSS Planning project25 in India, generic frameworks for IWRM DSS systems are readily available. The development of the DSS for the Bagmati is therefore considered to be based on available technology and generic DSS development systems provided by international consultants.

11. However, it is foreseen that major parts of the adaptation of the DSS framework to the Bagmati Basin will be carried out by national professionals, being trained and supervised by the international consultant.

12. A training programme will be tailor made to enable WECS staff to operate, update and maintain the Bagmati DSS together with the Bagmati River Basin Organization (BRBO) to be formed.

13. Besides, the WECS core staff will be further trained, to be able to roll-out the DSS to other River Basin Organizations in Nepal, and train the BRBO staff in the use of the DSS system for their specific basin planning and management purposes.

5. Scope

14. Based on the existing Information System and expanded to the DSS, WECS expects that the DSS can support them, by providing support to:

(i) Flood/Drought forecasting (early warning system). (ii) Basin planning and management. (iii) Techno-economic clearance for projects. (iv) Water allocation. (v) Regulation. (vi) Monitoring and evaluation. (vii) Benefit optimization. (viii) Conflict Resolution.

24

http://www.nilebasin.org/newsite/index.php?option=com_content&view=section&layout=blog&id=10&Itemid= 71&lang=en 25

http://hydrology-project.gov.in/dss.htm

Page 104: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 99

(ix) IWRM implementation. (x) Co-ordination. (xi) Sustainable WR development. (xii) Demand/supply projection. (xiii) WR Infrastructure Operational policy development.

15. It should be noted that the mandate for Flood Forecasting is with DHM, and considered to remain there. However, the DSS will have functionalities to receive the forecasts for any use of a future Bagmati RBO.

6. Overall Concept for the DSS

a. Interfacing with Existing and Future Models 16. The model system of the Bagmati DSS would provide an open interface to existing and future models being used for the Bagmati river basin can interact, be interfaced and linked dynamically. This would allow for exchange and sharing of data between models at runtime. This modeling interface would be simple and flexible enabling the user to define model interfacing without accessing the source code of the individual model systems.

b. Overall Conceptual Design 17. The Bagmati DSS encapsulates the existing WECS Information system, listing the types of basic information foreseen to be included in the core Data Base.

18. An important feature adding to the present WECS Information System will be the integration of existing and future models, the ability to define planning scenarios, and the facilities for Multi-Criteria-Analyses and optimisation.

c. Training 19. Software related user training including a series of training workshops in conjunction with the installation of the DSS Releases. These trainings are to be held at the location of WECS to be able to directly use the newly installed systems or updates for the training and at the same time subject it to user testing. The training would cover the background, algorithms and use of the software, as well as hands on exercises with relevant test cases to familiarize the core team and selected (RBO) users with the system.

20. The software training to be synchronized with the release of the corresponding user manuals, to be used as course material in the training and to compile user feedback for the improvement of the manuals.

7. Time Schedule

21. It is expected that the DSS development and implementation will be completed in 30 months time

8. Expertise Required

22. A summary of the consultant inputs is listed in the table below:

Page 105: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

100 Appendix 6

Table 1 : Summary of Proposed DSS Consultancy Inputs

International Specialists months

Team Leader / Chief Technical Advisor DSS Development & Customization Expert Process modeling expert incl. water quality Database expert

6 3 4 2

DSS implementation and training expert 2

Total International Specialists 17

National Specialists months

Modeling experts / DSS experts 15 GIS and database experts 10 Implementing and training expert

Hydrologist Unallocated

8 1 6

Total National Specialists 40

TOTAL 57

a. Team Leader / Chief Technical Advisor (International, 6 person-months) 23. The Team Leader / Chief Technical Advisor (CTA) will have a MSc degree in water resources systems, software engineering, information technology, environmental sciences, hydrology, or similar; with a minimum of 20 years of professional experience including management of large software development and water resources management projects, international experience including developing countries. S/he will work closely with WECS to develop a Bagmati DSS and the development of core institutional capabilities to assist in the evaluation of alternative development strategies and the identification of investment project at the basin or sub-basin level in future.S/he will:

(i) Be responsible for overall direction of the consultant team, coordination of inputs, and management of individual specialists;

(ii) Prepare and implement a tailor made training program to enable WECS staff to operate, update and maintain the Bagmati DSS together with the Bagmati River Basin Organization (BRBO) to be formed;

(iii) Develop a Bagmati DSS based on the use and expansion of the existing Information System that supports:

Flood/Drought forecasting (early warning system).

Basin planning and management.

Techno-economic clearance for projects.

Water allocation.

Regulation.

Monitoring and evaluation.

Benefit optimization.

Conflict Resolution.

IWRM implementation.

Co-ordination.

Page 106: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 101

Sustainable WR development.

Demand/supply projection.

Water resources infrastructure Operational Policy Development (ix) Ensure timely delivery of specified reports in a format acceptable to government

and the ADB.

b. DSS Development & Customization Expert (International, 3 person-months) 24. The DSS Development & Customization Expert will have MSc degree in relevant fields; with a minimum of 15 years of relevant experience in the application of multi-objective decision making processes. S/he will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

(ii) Work closely with other members of the DSS team to develop and setup of the Bagmati DSS using multi-objective decision making framework that support river-basin level decision making;

(iii) Contribute to the trainings provided to WECS and BRBO staff; and (iv) Assist the Team Leader in timely delivery of all outputs and preparation of

reports.

c. Process Modeling Expert incl. water quality (International, 4 person-months) 25. The Process Modeling Expert will have a MSc degree in natural resources or environmental sciences; with a minimum of 15 years of working experience in process modeling including water quality for a DSS. S/he will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

(ii) Provide specific inputs on developing inventories of environmental assets and aquatic ecosystems, development and applications of environmental indicators, assessing environmental impacts of water resources management and development interventions, and preparing environmental management plans, including water quality monitoring; develop quantitative linkages between alternatives and social and environmental indicators;

(iii) Contribute to the trainings provided to WECS and BRBO staff; and (iv) Assist the Team Leader in timely delivery of all outputs and preparation of

reports.

d. Database Expert (International, 2 person-months) 26. The Database expert will have an MSc degree or higher preferred in computer science, information technology, data management, or database administration; with a minimum of 15 years of working experience in design, development and administration of databases, preferably related to water resources engineering projects. S/he will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

Page 107: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

102 Appendix 6

(ii) Provide specific inputs on development of database management systems, Geographic Information System (GIS)-based modeling applications and simulation/optimization tools;

(i) Contribute to the trainings provided to WECS and BRBO staff; and (ii) Assist the Team Leader in timely delivery of all outputs and preparation of

reports.

e. DSS Implementation and Training Expert (International, 2 person-months) 27. The DSS Implementation and Training Expert will have a Masters level degree or higher preferably in engineering and management or related field with a minimum of 15 years of working experience in designing and implementing training programs related to river basin management and modeling. S/he will:

(i) Work closely with other members of the DSS on capacity building and trainings to WECS and BRBO staff to manage and use the developed Bagmati DSS for future decision making;

(ii) Provide specific inputs on training program development and implementation so that the developed DSS is fully operational and managed by WECS staff at the end of the project;; and

(iii) Assist the Team Leader in timely delivery of all outputs and preparation of reports.

f. Modeling /DSS Experts (National, 15 person-months) 28. The National Modeling/DSS experts will have MSc degree in water resources systems/hydrology or closely related fields; a minimum of 10 years of relevant experience in IWRM, hydrological modeling required for a river-basin level DSS. This position may be filled by one or more specialists as per the modeling needs of the DSS. The experts will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

(ii) Provide specific inputs on water resources assessment, hydrological modeling, river hydraulics, sediment transport, hydrodynamic modeling, flood and drought forecasting, data acquisition and processing, river morphology and soil and water conservation;

(iii) Contribute to the trainings provided to WECS and BRBO staff; and (iv) Assist the Team Leader in timely delivery of all outputs and preparation of

reports.

g. GIS and Database Expert (National, 10 person-months) 29. The National GIS and Database Expert will have a Masters level degree or higher preferred in computer science, information technology, data management, or database administration; with a minimum of 10 years of working experience in design, development and administration of standard database and knowledge of current GIS tools and technologies, preferably related to water resources engineering projects. S/he will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

Page 108: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 103

(ii) Provide specific inputs on development of database management systems, Geographic Information System (GIS)-based modeling applications and simulation/optimization tools;

(iv) Contribute to the trainings provided to WECS and BRBO staff; and (v) Assist the Team Leader in timely delivery of all outputs and preparation of

reports.

h. Implementation and Training Expert (National, 8 person-months) 30. The National Implementation and Training Expert will have a Masters level degree or higher preferably in engineering and management or related field with a minimum of 7 years of working experience in designing and implementing training programs related to water resources management and modeling. S/he will:

(i) Work closely with International Implementation and Training Expert and other members of the DSS on capacity building and trainings to WECS and BRBO staff to manage and use the developed Bagmati DSS for future decision making;

(ii) Provide specific inputs on training program development and implementation so that the developed DSS is fully operational and managed by WECS staff at the end of the project;; and

(iii) Assist the Team Leader in timely delivery of all outputs and preparation of reports.

i. Hydrologist (national, 1 person-month) 31. The Hydrologist will have MSc degree in water resources systems/hydrology or closely related fields; a minimum of 15 years of relevant experience in hydrological modeling required for a river-basin level DSS. S/he will:

(i) Work closely with other members of the DSS to develop and setup of the Bagmati DSS;

(ii) Provide specific inputs on water resources assessment, hydrological modeling, river hydraulics, sediment transport, hydrodynamic modeling, flood and drought forecasting, data acquisition and processing, river morphology and soil and water conservation;

(iii) Contribute to the trainings provided to WECS and BRBO staff; and (iv) Assist the Team Leader in timely delivery of all outputs and preparation of

reports. j. Unallocated (national, 6 person-month) 32. An international consulting firm (17 person-months (p-m) of international consultants and 40 p-m of national consultants) will be selected (if necessary in association with a national firm) to undertake the activities described above. Package 2: Flood Forecasting and Early Warning System (FFEWS)

9. Objective of the Bagmati FFEWS

33. The overall objective of the component is to equip DHM with a fully operational real time flood forecasting and warning system including an effective community based early warning system for the Bagmati river basin.

Page 109: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

104 Appendix 6

34. The specific objectives and scope of activities include but not be limited to the following:

(i) Assess the hydro-meteorological network and data acquisition system required for flood forecasting and early warning in the Bagmati river and its tributaries and to implement priority network and data acquisition improvement activities

(ii) Assess the current forecasting capacity and install necessary flood forecasting tools (hydrological and hydraulic models, rainfall forecasting including satellite based rainfall estimates)

(iii) Develop hydrological and hydrodynamic models and calibrate with historical data. The model will have a mapping feature to display model results spatially (inundation areas, flood levels etc.). The model will be linked to a real time data acquisition system and other web-based data.

(iv) Develop a web based flood forecasting and early warning dissemination system (v) Develop an operational strategy for disseminating flood early warning at the

community level (vi) Provide necessary trainings and capacity development for sustainable operation

of the FFWES at DHM

10. Task Descriptions

Task 1- Review of the hydro-meteorological network and data acquisition system and identify network and data acquisition improvement activities

35. A detailed inventory of the hydro-meteorological network, equipment and data acquisition system will be prepared. The existing forecast system has to be reviewed with respect to its on-line data assimilation capacity and coverage. Any additions to the hydrometric network in the Bagmati Basin since the existing forecast system was developed in 2011 will have to be identified. New hydrometric stations have to be included in the data assimilation network as a basis for the updated forecast and warning system. While the development of the existing flood forecast system concentrated on covering especially the most flood prone areas in the lower Bagmati the present project the present project intends to cover all flood prone areas in the entire Bagmati basin.

Task 2 - Review of the current forecasting capacity in DHM and identify necessary flood forecasting tools (models) upgrades

36. The consultant has to acquaint himself with the current weather and hydrological forecasting models and procedures used by the DHM for data acquisition as well as the existing human resources and the computer software and hardware available. While the existing forecast system relies mainly on on-line data from DHMs hydrometric network, numerical weather models and satellite based rainfall forecasts will provide the basis for the flood forecasts. This will require an update of the MIKE11 model as well as upgrade of communication facilities.

Task 3 – Procurement of Software and Hardware

37. Based on the inventory of available equipment and the identified need of additional computational capacity and communication facilities specifications for procurement are needed. The selection and installation of the software and hardware will be made in close collaboration with DHM. The PCMU procurement specialist can provide support in the procurement process. Upon procurement the software and hardware will be installed in DHM.

Page 110: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 105

Task 4- Extension of the existing forecast system

38. The coverage of the existing flood forecast model will be extended to generate water levels at key locations and inundation forecasts for all flood prone areas in the Bagmati basin. The river topographic data on which the present flood forecasting model is based should be updated.

39. With the assistance of DHM existing cross section data not included in the existing model shall be obtained, e.g. any data from Department of Irrigation from their Bagmati Irrigation project, from HPCIDCB based on their recent river works in the Bagmati and tributaries in Kathmandu, etc.

40. Additional data needs critical for extension of the flood forecast model shall be identified, specifications to be prepared and procurement of local survey consultant(s) to be done to carry out, e.g. cross section surveys at strategic locations.

41. Based on additional topographic data and river cross section data the existing flood forecasting model will have to be extended, recalibrated and verified based on the DHM hydrometric data from the Bagmati basin.

Task 5- Development and piloting of basin-wide flood forecasting and early warning system

42. The flood forecasting and early warning system will be based on forecasts of catchment rainfall using satellite based rainfall forecasts, numerical weather models and quantitative rainfall forecasts generated by the international and regional resource centers, IMD, RIMES etc.

43. The forecast system will be equipped with facilities for communication and receive of the forecast from RIMES and IMD.

44. The system will provide facilities for preparation of flood risk maps using GIS layers of the Bagmati basin.

Task 6- Assign NGO for Warning Dissemination 45. Prepare detailed Terms of Reference for a local experienced NGO to develop, test and implement effective early warnings to flood prone communities in the Bagmati basin. The testing and implementation of the warning system shall reach at least 10 flood prone communities in the Lower Bagmati.

46. With the assistance of the procurement specialist procure the NGO following GON and ADB rules and regulations.

Task 7- Flood warning dissemination strategy

47. While the dissemination of flood warnings to authorities at district level is relatively easy, reaching the flood prone poor communities with easily understood warnings is not simple.

Page 111: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

106 Appendix 6

However, relatively successful attempts have been made in Nepal26 and neighbouring countries27 to establish warning dissemination reaching the rural poor communities.

48. Based on the lessons learned a flood warning dissemination strategy will be developed in close collaboration between the consultant and the NGO assigned. Based on the experience using mobile phones, this option for warning dissemination should be considered in addition to more traditional methods for warning distribution.

49. Based on the flood warning dissemination strategy the NGO will develop the concept and contents of the flood warning dissemination system to be tested and implemented.

Task 8- Testing and implementing the flood warning dissemination system

50. The testing and implementation of the flood warning dissemination system targets to reach the poor and flood prone communities. However, the testing in the field should also cover that forecasts reach district authorities and disaster management committees and other government agencies.

Task 9- Provision of necessary trainings and capacity development for sustainable operation of FFWES

51. The key to success of the forecasting centre at DHM is the sustainability and the national capacity to maintain and operate the data acquisition, forecasting and early warning system. While annual budgetary provision to meet the cost of the services needs to be sustained, there is a strong need to develop the necessary human resources. Hence, appropriate trainings including specialised courses and exposure visits will be provided to the counterpart staff. On-the-job trainings will be provided by the implementing consulting team.

52. As DHM and the proposed Bagmati RBO will both be involved in flood disaster risk management in the Bagmati River basin, the forecasting activities need to be established as a joint collaboration between the two. A workable institutional setup will be recommended suitable to meet the objectives of BRBO.

11. The FFEWS

53. Since the Bagmati River basin is relatively small with steep river slopes the lead time of flood forecasting along the Bagmati River mainly depends on lead time of the available weather forecast. Quantitative Precipitation Forecasts can only prove a reliable rainfall forecasts for 1, 2 and 3 days only. Therefore, the lead time of the flood forecasting model of the Bagmati river basin will be limited up to 3 days. The floods are flashy in nature in many parts of the basin, and the travel time of the flood wave from upper Bagmati to the lower part is about 12 hours. The, development of the FFEWS for the Bagmati basin should consider the above factors. The following components are included in the proposed development of FFEWS.

(i) A Rainfall-runoff model (ii) A Hydrodynamic model (iii) A Flood forecasting model with data assimilation facilities using real time data (iv) A Web based user interface with warning dissemination facilities (v) Community based early warning system

26

Banka Bardia Flood Warning programme. http://practicalaction.org/IA15000181NEP-banke-bardia-flood-warning 27

Consolidation and Strengthening of Flood Forecasting and Warning Services. Final Report. Vol V – Project Extension. Report to the Bangladesh Water Development Board. DHI. December 2006

Page 112: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 107

12. Capacity Building

a. Capacity for FFEWS Development, Operation and Maintenance

54. The development of the FFEWS for the Bagmati will be based on the MIKE11 software available with DHM and the pilot model of the Bagmati River. However, it is foreseen that the model will be updated to cover the entire basin with additional data of river cross sections, flood plain topography (DEM), structures including embankments. The model will also be updated to incorporate the real-time data (rainfall, water levels). The model will be recalibrated with the latest time series data available before an operation forecasting is implemented by DHM.

55. The operational forecasting for the Bagmati River will be mainstreamed in the forecasting activities of DHM. DHM will however need capacity support both from national and international consultants during the development of the FFEWS. DHM personnel will be trained during the development. It is expected that DHM will require external support for some period before they will be able to take over completely.

56. The training programme described below shall be tailor-made to enable DHM staff to operate, update and maintain the Bagmati FFEWS together with the proposed Bagmati River Basin Organization (BRBO). Besides, the DHM core staff will be further trained, to be able to roll-out the FFWES to other river basins in Nepal.

b. Specialized Training Courses 57. Specialised training courses will be provided in the following topics:

Concepts of computational hydrology and hydraulics, rainfall-runoff modeling, hydrodynamic modeling, data assimilation and forecasting, flood mapping, GIS, Satellite image processing, data base management and Web updating. c. On-the-job training

58. DHM staff will be involved in all stages of development and implementation of the forecasting system by consultants.

d. Exposure visits 59. Exposure visits will be conducted for DHM staff to observe operational flood forecasting system in other countries and to relevant institutions.

13. Time Schedule

60. It is expected that the model development will be completed in six months. However, it is recommended that the operational forecast is implemented for a full flood season after which evaluation and reporting will be done. Including capacity building activities the total project period for this component will be one year.

14. Expertise required for consulting services

61. A summary of the consultant inputs is listed in the table below:

Page 113: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

108 Appendix 6

Table 2 : Summary of Proposed FF and FEWS Consultancy Inputs

International Specialists months

Team Leader / Chief Technical Advisor FFEWS model expert Web based modeling expert Community based warning expert

4 3 1 1

Total International Specialists 9

National Specialists months

Modeling Expert 8 Warning Dissemination Expert 4 Community based flood warning expert Unallocated

4 6

Total National Specialists 22

TOTAL 31

a. Team Leader / Chief Technical Advisor (International, 4 person-months) 62. The Team Leader / Chief Technical Advisor (CTA) will have a MSc degree in water resources engineering/Hydrology or similar field; with a minimum of 20 years of professional experience on development of flood forecasting and early warning systems and flood risk mapping. S/he shall have proven experience in hydro-meteorological data collection, processing and management and capacity building of a hydro-meteorological agency in a developing country including management of large software development and water resources management projects, international experience including developing countries. S/he will work

closely with DHM to develop a Bagmati Flood Forecasting and Early Warning System (FFEWS) and the development of core institutional capabilities to manage and operate the system in future.S/he will:

(i) Be responsible for overall direction of the consultant team, coordination of inputs, and management of individual specialists;

(ii) Assess the hydro-meteorological network and data acquisition system required for flood forecasting and early warning in the Bagmati river and its tributaries and to implement priority network and data acquisition improvement activities

(iii) Assess the current forecasting capacity and install necessary flood forecasting tools (hydrological and hydraulic models, rainfall forecasting including satellite based rainfall estimates)

(iv) Develop hydrological and hydrodynamic models and calibrate with historical data. The model will have a mapping feature to display model results spatially (inundation areas, flood levels etc.). The model will be linked to a real time data acquisition system and other web-based data.

(v) Develop a web based flood forecasting and early warning dissemination system (vi) Develop an operational strategy for disseminating flood early warning at the

community level (vii) Provide necessary trainings and capacity development for sustainable operation

of the FFWES at DHM and BRBO; and (viii) Ensure timely delivery of specified reports in a format acceptable to government

and the ADB.

Page 114: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 109

b. FFEWS Model Expert (International, 3 person-months) 63. The FFEWS Model Expert will have MSc degree in water resources engineering/ hydrology or relevant fields; with a minimum of 15 years of relevant experience in hydrological and hydraulic modeling. S/he will:

(i) Assess the hydro-meteorological network and data acquisition system required for flood forecasting and early warning in the Bagmati river and its tributaries and to implement priority network and data acquisition improvement activities

(ii) Assess the current forecasting capacity and install necessary flood forecasting tools (hydrological and hydraulic models, rainfall forecasting including satellite based rainfall estimates)

(iii) Develop hydrological and hydrodynamic models and calibrate with historical data. The model will have a mapping feature to display model results spatially (inundation areas, flood levels etc.). The model will be linked to a real time data acquisition system and other web-based data;

(iv) Contribute to on-the-job trainings to enable DHM and BRBO staff to operate, update and maintain the Bagmati FFEWS in particular related to computational hydrology and hydraulics, rainfall-runoff modeling, data assimilation and forecasting, flood mapping, GIS and Satellite image processing; and

(v) Assist the Team Leader in timely delivery of all outputs and preparation of reports.

c. Web-based Modeling Expert (International, 1 person-month) 64. The Web-based Modeling Expert will have MSc degree in computer science, software engineering or closely related fields; with a minimum of 10 years of experience in systems analysis, design and development of web-based modeling systems preferably related to water hydrology/flood/drought forecasting and warning system. S/he will:

(i) Develop a web based flood forecasting and early warning dissemination system with a user-interface with warning dissemination facilities;

(ii) Contribute to on-the-job trainings to enable DHM and BRBO staff to operate, update and maintain the Bagmati FFEWS in particular related to database management and Web-updating; and

(iii) Assist the Team Leader in timely delivery of all outputs and preparation of reports.

d. Community-based Warning Expert (International, 1 person-month and national 4 persons months)

65. The Web-based Modeling Expert will have MSc degree in MSc degree in water resources management or rural development or closely related fields; with a minimum of 10 years of experience in community-based flood/drought warning systems. S/he will:

(i) Develop a community based flood early warning system in close coordination with the modeling experts;

(ii) Contribute to on-the-job trainings to enable DHM and BRBO staff to operate, update and maintain the Bagmati FFEWS in particular related to dissemination of flood warning to communities; and

Page 115: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

110 Appendix 6

(iii) Assist the Team Leader in timely delivery of all outputs and preparation of reports.

e. National Modeling Expert (National, 8 person-months) 66. The National Modeling Expert will have MSc degree in water resources engineering/ hydrology or relevant fields; with a minimum of 10 years of relevant experience in hydrological and hydraulic modeling. S/he will:

(i) Assist and work closely with other members of the team to develop and setup of the FFEWS;

(ii) Provide specific inputs to assess the hydro-meteorological network and data acquisition system required for flood forecasting and early warning in the Bagmati river and its tributaries and to implement priority network and data acquisition improvement activities

(iii) Assess the current forecasting capacity and install necessary flood forecasting tools (hydrological and hydraulic models, rainfall forecasting including satellite based rainfall estimates)

(iv) Develop hydrological and hydrodynamic models and calibrate with historical data. The model will have a mapping feature to display model results spatially (inundation areas, flood levels etc.). The model will be linked to a real time data acquisition system and other web-based data;

(v) Contribute to on-the-job trainings to enable DHM and BRBO staff to operate, update and maintain the Bagmati FFEWS in particular related to computational hydrology and hydraulics, rainfall-runoff modeling, data assimilation and forecasting, flood mapping, GIS and Satellite image processing; and

(vi) Assist the Team Leader and International Modeling Experts in timely delivery of all outputs and preparation of reports.

f. National Warning Dissemination Expert (National, 4 person-months) 67. The National Warning Dissemination Expert will have MSc degree in water resources engineering or social science or related field with a minimum of 7 years of relevant experience in community based disaster (preferably flood) warning systems. S/he will:

(i) Assist and work closely with other members of the team to develop community based flood early warning system;

(ii) Assist the International Community based warning expert to develop a community based early flood warning system in close coordination with the modeling experts;

(iii) Contribute to on-the-job trainings to enable DHM and BRNO staff to operate, update and maintain the Bagmati FFEWS in particular related to dissemination of flood warning to communities; and

(iv) Assist the Team Leader and International Experts in timely delivery of all outputs and preparation of reports.

g. unallocated (national, 6 person-month)

Page 116: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 111

68. An international consulting firm (9 person-months (p-m) of international consultants and 22 p-m of national consultants) will be selected (if necessary in association with a national firm) to undertake the activities described in Sections above.

C. Package 3 Water Quality monitoring system

1. Objective of the Water Quality monitoring system upgrade

69. The overall objective of the component is to reliable data and information of the present state and future developments in the Bagmati River water quality through the upgrading the existing water quality monitoring program carried out by HPCIDCB and its laboratory.

70. The specific objectives and scope of activities include but not be limited to the following:

(i) Upgrade the existing water quality monitoring programme

(ii) Upgraded the HPCIDBC laboratory with new instrumentation and equipment and safety measures such as improved ventilation.

(iii) Staff trained in carrying out the specified monitoring and water quality sampling programme.

(iv) Laboratory staff trained in analytical procedures and use of new instruments.

(v) Quality Assurance measures and Quality Control procedures introduced. A QA/QC Manual developed and the staff trained in adherence to the manual procedures in all laboratory activities

2. Task Descriptions 71. The overall tasks and activities include but are not limited to the following:

(i) Review the existing water quality monitoring system, prepare recommendations of improvement and implement these with respect to parameters measured, frequency, sample positions, need for in-situ measurements, sample handling and preservation.

(ii) Assess the state of the instrumentation and equipment of the laboratory and if needed update the list prepared by the PPTA of instruments and equipment to be procured.

(iii) Procure instruments and equipment according to GON and ADB rules, ensure timely delivery according to specifications and install and commission instruments.

(iv) Train laboratory staff in the analytical procedures of the parameters required in the water quality monitoring system. Ensure safety equipment is used and safety procedures followed.

(v) Prepare manuals and instructions for the monitoring sampling programme and all aspects of work in the laboratory, including safety procedures.

Page 117: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

112 Appendix 6

3. Time Schedule 72. It is expected that the instrument and equipment procurement as well as the laboratory upgrade will be completed within nine months.

73. The training activities will cover the period where the laboratory is taking the new instruments and equipment into use, implementing the sample handling and analytical routines and QA/QC procedures. The training is expected to be completed within a 12 month period.

74. The completion of operating manuals, final inspection of laboratory operations and reporting is expected to have a duration of 3 months, with a total Project Period of then 24 months.

4. Expertise required for consulting services 75. A summary of the consultant inputs is listed in the table below:

Table 3: Summary of Proposed Water Quality Monitoring System Upgrade Inputs

International Specialists months

Team Leader/WQ Monitoring Specialist Laboratory Expert

4 4

Total International Specialists 8

National Specialists months

Laboratory Technical Expert Monitoring specialist Unallocated

6 2 4

Total National Specialists 12

TOTAL 20

a. Water Quality Monitoring Specialist/Team Leader (International, 4 person-months, national 2 person-months)

76. The Water Quality Monitoring Specialist/Team leader will have at least an MSc level education within water resources, water quality, public management, human health, or a closely related field. 15 years of practical international experience in water quality monitoring, river environment and water-related health risks. Practical international experience in the planning, design and implementation of water quality monitoring programmes. Strong interpersonal relationship, experiences in the region preferably and fluent spoken and written English are required. S/he will be the main point of contact in assisting HPCIDBC with implementation of the laboratory upgrade. S/he will report to the PCMU and lead the consultancy. The Water Quality Monitoring Specialist/Team Leader will:

(i) Be responsible for leading the laboratory upgrade consultancy, coordination and management of the team;

(ii) Coordinate the planning and implementation of the laboratory upgrade with the leader of the HPCIDBC laboratory;

(iii) With the assistance of the Procurement Specialist from the PCMU/PMSC arrange for the purchase of instruments etc. for the upgrade of the laboratory, following GON and ADB guidelines.

Page 118: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 113

(iv) Review the existing monitoring program, methods used for sampling, sampling handling and preservation and make recommendations for any changes, if needed.

(v) Identify the parameters that should be measured in-situ, and parameters to be measured in the laboratory, and cross-check with the list of instrumentation to be purchased.

(vi) Update the present monitoring programme and prepare manuals/instructions for the monitoring programme, including safety procedures and train laboratory personnel in implementation.

(vii) Prepare instruction for maintenance and calibration of material and instruments used during field monitoring, and train the laboratory personnel in implementation of monitoring routines.

(viii) Prepare guidelines and routines for data registration, quality control, analyses and regular reporting. After review of national water quality standards ensure the analyses of results and reporting refers to national water quality standards.

(ix) Ensure timely delivery of specified reports in a format acceptable to government and the ADB.

b. Water Quality Laboratory Expert (International, 4 person-months) 77. The Water Quality Laboratory Expert will have an MSc level education within analytical chemistry in general, and water analysis in specific. Knowledge about internal quality control and quality assurance activities of analytical work, and experience with organization of laboratory services. 15 years of practical experiences in laboratory activities related to environmental management and control in developing countries. Practical international experience in training of laboratory staffs in developing countries. Strong interpersonal relationship, experiences in the region preferably and fluent spoken and written English are required. The Water Quality Laboratory Expert will:

(i) Assist the Team leader in project implementation, instrumentation procurement, coordination with laboratory staff and the PCMU.

(ii) Review the status of the instruments in the laboratory and update the instrumentation list for purchase prepared by the PPTA.

(iii) With the assistance of the Laboratory Technical Expert and the PCMU procurement Specialist review and identify national dealers and providers of laboratory equipment, and prepare specifications for the instrumentation for procurement.

(iv) With the assistance of the local laboratory technical expert install and verify the proper functioning of the instruments procured.

(v) Prepare a detailed training programme for the laboratory staff and implement this, covering sample handling, analytical training following prescribed standards, safety procedures to be followed, analytical data registration, quality assurance, reporting etc.

(vi) Prepare laboratory manuals covering all aspects of work in the laboratory, including safety procedures.

(vii) Assist the Team leader in timely delivery of specified reports in a format acceptable to government and the ADB.

Page 119: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

114 Appendix 6

c. Laboratory Technical Expert (National, 6 person-months) 78. The Laboratory Technical Expert will have a relevant technical education with a demonstrated work experience of at least 5 years in the installation and training in the use of laboratory equipment and instruments. S/he will be the main contact to local dealers and providers of laboratory instruments and equipment. The Laboratory Technical Expert will:

(i) Assist the Water Quality Laboratory Expert in coordination of the laboratory upgrade with the laboratory staff and the PCMU.

(ii) Assist the Water Quality Laboratory Expert in the preparation of specifications of instruments and equipment to be purchased.

(iii) Be responsible for checking the functioning of the instrumentation and equipment procured, and ensure the delivered are in accordance with the specifications.

(iv) Be responsible for the installation and commissioning of the laboratory instruments,

(v) Support the Water Quality Laboratory Expert in training of the laboratory staff.

d. Unallocated (national, 4 person-month) D. Package 4 Integrated River Basin Development Master Plan

1. Aim

79. The aim of the IRBDMP is to provide GON with a comprehensive development and management plan to guide the rapid rationalisation and improvement of water management in the Bagmati River basin for at least the next 20 years. The Plan will examine each aspect of water management and propose improvement in achievable stages which can be used to obtain essential funding as part of an overall IWRM strategy.

2. Scope

80. Data collection and consultations will commence during the first year of the BRBIP, and the IRBDMP itself will be compiled during the second year. After approval, the plan will be used to initiate funding for priority activities. The plan will be updated by the RBO, assumed to be established, during the last (fifth) year of the project for use by GON to continue with effective IWRM and the implementation of essential projects in the water sector.

81. The plan for the entire Bagmati River basin will include:

(i) An overview of GON policy with recommendations for improvement; (ii) Up-to-date water availability and water use information linked with the DSS; (iii) An up-to-date inventory of current and planned water-related works including

their status and condition; (iv) Assessment of water quality in the main river and tributaries linked with the DSS

in relation to current and planned abstractions and discharges. (v) Water sector goals agreed in consultation with stakeholders including GON and

civil society; (vi) Strategies for IWRM; (vii) Priority activities; (viii) Detailed programme of works and other actions by sub-basin; (ix) Performance evaluation and monitoring.

Page 120: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 6 115

3. Summary of Inputs 82. A summary of the proposed IRBDMP development support consultant inputs is listed in the table below:

Table 3: Summary of Proposed RBO Support Consultancy Inputs

IRBDMP Development Support

Specialists months

International IRBMDP Specialist 8

National IRBMDP Specialist 32

Total 40

4. Activities – International and National Specialists

a. IRBDMP Specialist (International, 8 person-months) 83. The Integrated River Basin Development and Management Plan (IRBDMP) Specialist will have a degree in water resources engineering/management or related field and a minimum of 10 years of demonstrated work experience in integrated river basin development and management preferably in South Asia. S/he will be responsible to prepare the IRBDMP and to carry out the following:

(i) Prepare an outline content of the IRBMDMP based on the River Basin profile for the prepared by JWA RETA with equal focus on the Upper, Middle and Lower Bagmati.

(ii) Review the existing data available and identify essential gaps for the planning process.

(iii) Prepare a plan for surveys to be carried, and implement these in close cooperation with the PCMU.

(iv) Prepare the Integrated River Basin Development and Management Plan (IRBDM) in close cooperation with the PCMU with consultation and concurrence of the key stakeholders (including GON and civil society);

(v) In cooperation with the PCMU carry out extensive consultations with the GON, ADB, key stakeholders obtaining concurrence with the contents of the plan.

(vi) Support the then formed RBO in updating of the plan at the end of the project. (vii) Ensure timely delivery of specified reports in a format acceptable to government

and the ADB.

b. IRBDMP Specialist (National, 32 person-months) 84. The National IRBDMP Specialist will have a degree in water resources engineering/ management and minimum of 5 years of demonstrated experience in river basin planning and management. S/he will support the International IRBDMP Specialist to ensure the timely delivery of specified outputs of the IRBDMP. S/he will:

Page 121: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

116 Appendix 6

(i) Support the TL in delivering the envisaged outputs of the Integrated River Basin Development and Management Plan (IRBDM) with consultation and concurrence of the key stakeholders (including GON and civil society) that will serve as a Master Plan for Basin side water sector development and management;

(ii) Coordinate the activities with the GON, ADB, key stakeholders and the BRBIP PCMU Unit; and

(iii) Ensure timely delivery of specified reports in a format acceptable to government and the ADB.

5. Reporting 72. .Reporting requirements shall be as follows:

(i) Inception Report: As soon as the support consultancy starts, the consultant shall prepare an Inception Report. Based on discussions with GON, WECS, HPCIDBC and the staff who may be allocated for the future RBO secretariat, the consultant shall review and verify the content of the tasks required. Specifically, the consultant shall review the existing information available, identify gaps and make specifications of the surveys necessary for planning purposes. The consultant will also elaborate: (i) other main tasks, (ii) work and staffing plans, and (iii) reporting programme.

(ii) Half-yearly Reports: Since the inputs are not evenly spaced out over the project period of five years, it may be appropriate to prepare half-yearly reports summarising progress in IBRDMP process, and planned work for the next reporting period.

(iii) Mid-term Report: The Mid-term Report to be provided end 2015 will present the Draft IRBDMP. Depending on comments received the IBRDMP will be updated in early 2016 with revisions presented in the ensuing half-yearly report.

(iv) Final Report: The Final Report will present a summary of all aspects of the consultancy covering RBO formation and parallel and subsequent capacity building and technical training. The report will summarise and discuss the results of specialist aspects together with conclusions, recommendations and lessons learned for future projects of this nature.

73. For each report, four copies in English are to be submitted. In addition to hard copies, one digital electronic copy shall also be submitted. At the end of the contract, a digital copy of all documents relevant to the project shall be compiled in an orderly manner on a CD and be submitted to the PCMU.

Page 122: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 7 117

DRAFT TERMS OF REFERENCE FOR CONSULTANCY FOR RBO FORMATION (UNDER WFPF TA GRANT)

A. Aim

1. The aim of the consultancy is to support the formation of an RBO for the Bagmati river basin and, after its formation, to build its capacity and provide technical training. As the RBO is being formed, the consultancy will seek to fill gaps between the roles of existing water management institutions and/or promote take-over of certain functions from other institutions, to avoid duplication of roles and responsibilities so that the RBO can operate effectively.

B. Scope

2. Scope of the consultancy is to support formation of the Bagmati RBO and provide capacity building and technical training, including:

(i) Initial review of the past and present water resources management environment; (ii) Legal studies necessary to clear the way for establishment of a Bagmati RBO

and secretariat, with support from legal specialist under the PCMU. (iii) Review of recent initiatives aimed at identifying the form and structure of the

Bagmati RBO; (iv) Consultations with stakeholders, both institutional and resource users; (v) Initial technical studies to support the embryo RBO secretariat; (vi) Assistance in refining and agreeing the type and structure of the proposed RBO; (vii) Training concentrated on the technical core of the RBO and its secretariat,

covering:

Resource Studies and Priority Works;

Water Quality, Groundwater and Disaster Management; (viii) Focus on the most urgent social needs (including awareness-raising) within the

basin to assist the Institutional and Community Outreach section of the RBO secretariat;

(ix) Arranging and assisting with study tours for RBO members and its secretariat.

3. It is expected that the RBO support consultant will be based at WECS office located in Kathmandu.

C. Summary of Inputs

4. A summary of the proposed RBO support consultant inputs is listed in the table below:

Table 1: Summary of Proposed RBO Support Consultancy Inputs

RBO Formation and Training

International Specialists months

Team Leader / Water Policy/ RBO Specialist 19

Institutions, Community and Participation Specialist 3

Total 22

Page 123: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

118 Appendix 7

D. Activities: International Specialists

1. Team Leader / WATER POLICY /RBO Specialist (International, 19 person-months)

5. The Team Leader will have a Master's degree in IWRM or related field and a minimum of 15 years of demonstrated experience in Water and institutional reform and River Basin Management or related fields. S/he will be the main point of contact with government and BRBIP in assisting them to implement IWRM through an RBO for the Bagmati River basin. In managing the team, the Team Leader will oversee all aspects of the support consultancy including consultations, promoting the necessary legal and institutional changes, assisting the RBO to update the IWRM strategic roadmap agreed in the loan conditions and progress monitoring. He will:

6. Review of the project preparation documents with regard to RBO formation, capacity building and training and draw attention to changes which may have become necessary since their preparation;

(i) Lead the consultancy team aiming to improve water governance in the Bagmati basin following IWRM principles;

(ii) Assist the government by identifying requirements and modalities for the pursuance of IWRM, including monitoring of progress and meeting specified IWRM roadmap targets and BRIBP loan covenants;

(iii) Oversee initial review of the past and present water resources management initiatives and liaise with the specialist carrying out legal studies necessary for establishment of a Bagmati RBO and secretariat;

(iv) Oversee consultations with stakeholders, both institutional and resource users; (v) Assist GON in refining and agreeing the type and structure of the proposed RBO; (vi) Supervise training concentrated on resource studies, water quality, groundwater

and disaster management, also arranging study tours; (vii) Ensure timely delivery of specified reports in a format acceptable to government

and the ADB.

2. Institutions, Community and Participation Specialist (International, 3 person-months)

7. The Institutions, Community and Participation Specialist will have degree in management, social science or related fields and a minimum of 10 years of demonstrated work experience preferably in South Asia. S/he will oversee the institutional and participatory aspects of the capacity building and training, working closely with the National Deputy Team Leader / Institutions Specialist and Training Specialist. Together they will ensure that the RBO is fully engaged with stakeholders and relevant institutions. The Institutions, Community and Participation Specialist will:

(i) Support the Team Leader and RBO secretariat in gaining the support of stakeholders and relevant institutions and in continuing IWRM/RBO policy and dialogue for institutional reform;

(ii) Carry out a comprehensive review of the past and present water resources institutional and management initiatives and discuss need for any updating of approach with the team and with the specialist carrying out legal studies on establishment of the RBO;

Page 124: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 7 119

(iii) Establish and maintain contact with relevant NGOs and community-based organizations in the area covered by the Bagmati RBO;

(iv) Together with the National Institutions Specialist and other team members, conduct interviews, focus groups or other meetings with stakeholders to confirm their interests, constraints, and willingness to engage with IWRM;

(v) At the local level, promote social and institutional aspects of participation, acceptance, and adoption of RBO activities, and propose strategies to overcome any local concerns or other issues;

(vi) Assist GON and BRBIP to identify and agree the form and structure of the Bagmati RBO;

(vii) Work with the National Institutions and Training Specialists to focus on the most urgent social needs (including awareness-raising) within the basin to assist the Institutional and Community Outreach section of the RBO secretariat;

(viii) Assist the Team Leader and Deputy Team Leader in timely preparation of reports.

E. Reporting

8. Reporting requirements shall be as follows:

(i) Inception Report: As soon as the support consultancy starts, the consultant shall prepare an Inception Report. Based on discussions with GON, WECS, HPCIDBC and the staff who may be allocated for the future RBO secretariat, the consultant shall review and verify the content of the tasks required. The consultant will also elaborate: (i) main tasks, (ii) work and staffing plans, and (iii) reporting programme.

(ii) Quarterly or Half-yearly Reports: Since the inputs are spaced out over a period of five years, it may be more appropriate to prepare half-yearly reports summarising progress in RBO formation and capacity building, and proposals for the next reporting period.

(iii) Mid-term Report: The Mid-term Report will summarise all aspects of RBO formation and subsequently of capacity building and technical training. This will also be an opportunity to make any fundamental changes in direction which may be required as the process of RBO formation and any associated difficulties become apparent.

(iv) Final Report: The Final Report will present a summary of all aspects of the consultancy covering RBO formation and parallel and subsequent capacity building and technical training. The report will summarise and discuss the results of specialist aspects together with conclusions, recommendations and lessons learned for future projects of this nature.

9. For each report, four copies in English are to be submitted. In addition to hard copies, one digital electronic copy shall also be submitted. At the end of the contract, a digital copy of all documents relevant to the project shall be compiled in an orderly manner on a CD and be submitted to the PCMU.

Page 125: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

120 Appendix 8

DRAFT TERMS OF REFERENCE FOR INDEPENDENT ENVIRONMENTAL MONITORING CONSULTANT

A. Aim

1. Aim of the consultancy is to strengthen project environmental management, ensure sustainable development and compliance with the environmental safeguard policy of ADB, as well as the Environmental Protection Law of Nepal.

B. Scope

2. An independent Environment Consultant with a degree in environmental science/engineering or related field and experienced and capable in environmental monitoring will be recruited to carry out the environmental monitoring tasks under the GON Project Management Unit (PCMU). The duration of this consultancy is expected to be 60 months.

3. The IEMC will be responsible for assisting the PCMU in compliance of works contractors with environmental safeguards, monitoring of the EMP, and evaluating the results of environmental monitoring and impact mitigation measures during the construction phase of the project. At the same time, the environmental monitoring consultant will assist the environmental management units of the implementing agencies in preparing and participating in capacity building activities, etc.

4. Compliance should follow the requirements of the Environmental Protection Law of Nepal and the environmental safeguard policies of ADB.

C. Activities

5. The principal activities of the IEMC will be as follows:

Activity 1: To assess and report compliance of works contractors with environmental protection requirements:

(i) During the construction phase, the IEMC will conduct periodic visits to inspect contractor compliance with environmental requirements, as detailed in the signed contracts between contractor and project owner.

(ii) The IEMC will make periodic or unannounced inspections of contractor facilities as required and give the results of his findings to contractors for inclusion in implementation progress monitoring reports to be submitted by contractors.

(iii) The IEMC will verify the investigation results of any non-compliance of the environmental quality performance and the effectiveness of the corrective measures and report such results to the PCMU as appropriate.

Activity 2: To assess and report progress and performance of the EMP:

(i) During and after the construction phase, the IEMC will conduct periodic visits to inspect the performance of activities commissioned under the EMP.

(ii) IEMC Findings will be made known to agencies and contractors responsible for EMP components for inclusion in implementation reports.

Page 126: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 8 121

(iii) The IEMC will investigate any shortcomings in performance and effectiveness of the EMP and make recommendations where necessary to restore its effectiveness.

Activity 3: To assess and interpret the results of environmental monitoring and environmental impact mitigation measures and to draw attention to unsatisfactory outcomes and trends.

D. Reporting

6. Reporting requirements shall be as follows:

(i) Inception Report: As soon as the project is commenced, the IEMC shall prepare an Inception Report. Based on the output of discussions with the PCMU and field visits, the IEMC shall review and verify the content of the tasks required. The IEMC shall also elaborate in detail: (i) overall assessment of the tasks, (ii) work plan, and (iii) programme for delivery of required reports.

(ii) Quarterly Reports: Based on the results of monitoring and visits to contractors’ worksites, the IEMC shall prepare a quarterly report every three months. These reports must present all the findings related to monitoring requirements identified in the ToR. Quarterly reports will also summarise the results of monitoring data. The emerging environmental problems will be analysed, assessed and reported to the project owner for appropriate and timely response. In particular, the compliance or otherwise of works contractors with the requirements of their signed contracts must be properly reflected in the reports.

(iii) Final Report: The Final Report will present a summary of monitoring results, analysis of Contractor’s compliance, environmental changes caused by project implementation and comparison with the expectations of the EIA and IEE reports, together with conclusions, recommendations and lessons learned for future projects.

7. For each report, four copies in English are to be submitted. In addition to hard copies, one digital electronic copy shall also be submitted. At the end of the contract, a digital copy of all documents relevant to the project shall be compiled in an orderly manner on a CD and be submitted to the PCMU.

E. Personnel (Indicative)

Table 1: Independent Environmental Monitoring Consultant - Indicative Personnel Schedule

National: YEAR 1

YEAR 2

YEAR 3

YEAR 4

YEAR 5 TOTAL

Environmental Specialist 2 2 2 2 2 10

F. Activities – National M&E Specialist

8. The National M&E Specialist will have a degree in environmental science or engineering or related field and a minimum of 5 years of work experience in overseeing environmental management plans of infrastructure projects. S/he is expected to be familiar with the GON and ADB's environmental safeguard requirements. S/he will ensure that the project is implemented in accordance with the environmental laws of Nepal and the ADB environmental safeguard

Page 127: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

122 Appendix 8

policy by overseeing implementation of Environmental Management Plans (EMP) and assisting the PCMU to monitor impacts. The National M&E Specialist will:

(i) Carry out a review of the feasibility studies (including safeguard documents, IEE and EIA) with regard to environmental impact and request changes and updates if and when required.;

(ii) Carry out a review of the Environmental Management Plans (EMP) and monitoring mechanisms and recommend any updating which may be required;

(iii) Oversee Contractor’s implementation of EMPS and review the control procedures implemented and carried out by PCMU and PIUs, and request corrective management actions, if and when required;

(iv) Periodically control the EMPs implemented on site by construction contractors and review the quarterly reporting;

(v) Undertake a review of potential cumulative and induced environmental impacts which may occur downstream or elsewhere in the Bagmati river basin as a result of project interventions;

(vi) Monitor project progress with regard to environmental targets and indicators set out in the Design and Monitoring Framework (DMF);

(vii) Review reports delivered as per the DMF requirements and report to the EA through the PCMU/Project Director on the performance of the contractors and the efficiency of the EMPs implemented, and announce any corrections needed that require intervention from the EA, Project Director, PCMU, PIU and contractors.

Page 128: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 123

DRAFT TERMS OF REFERENCE FOR NGO PACKAGES

A. Overview

1. The proposed Bagmati River Basin Improvement Project (the project) will improve water security and resilience to potential climate change impact in the Bagmati River Basin. It builds on the general public’s desire to restore the river environment in the Kathmandu Valley and the Government’s efforts to mitigate the impact of water-induced disasters in the middle and lower reaches of the basin. The Project adopts the principles of integrated water resources management (IWRM) and provides Nepal with its first opportunity to apply this policy element since its adoption under the 2005 national water plan.

2. The project plans to engage national NGOs to support the project through three (3) NGO packages (contracts) as follows:

(i) Watershed management (ii) Rainwater harvesting and solid water management (iii) Community awareness, gender and community strategy

1. NGO Package 1 - Watershed Management

3. The community’s involvement is the prime factor for the successful conservation and improvement of the watershed areas. So, a conservation users group should be formed from among the beneficiary farmers and involved in planning and implementation of the conservation activities.

Support for declaration of the SNNP buffer zone

4. There are four main settlements in the Shivapuri watershed area i.e. Mulkharka, Chilaune, Kunegaun and Okhreni. Consultations are currently on-going for these settlements area to be declared as buffer zone and as such removed from the National park main area. Support is required for the preparation of the buffer zone management plans. This includes consultations, need identification, meeting with local people and write up management plan)

5. Support will also be required for the formation of various committees (user groups, User committee and Management committee) and strengthening those institutions for good governance, creating conducive environment for biodiversity conservation providing various types of training, exposure visits, subsidies to install fuel efficient stoves, alternate energy supply, alternate income generating activities to replace local alcohol brewing activity by local people etc.

Mapping and management of the new dams

6. Assist SNNP authorities in (a) mapping the dam(s) foot print and direct surrounding area and (b) preparing specific management plan(s) to mitigate possible impact of increased tourism/visitors.

Demonstration and training

6. Illegal tree felling for fuel wood, other domestic uses and production of alcohol and encroachment of forest for agricultural land and settlements and forest fires are taking place in

Page 129: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

124 Appendix 9

the Shivapuri watershed. A training and awareness program will be implemented in the watershed to educate the stakeholders such as National Park staff, army personnel, user groups, local people etc. regarding the consequences of watershed degradation and benefits of well-managed watershed.

7. Thirty training events will be organized for different stakeholder i.e. local people, user groups, army personnel staff and National Park staff during the project period. Such training events will help to enhance their capacity in conserving biodiversity and protecting watershed area.

8. In each training programme, there will be 25 participants. During the project period 750 people will receive training on different subjects which will enrich their knowledge and motivate them in conservation and protection of the watershed area. Within this period all households will get training. Soil loss from agricultural land during maize cultivation is considerable if there is rainfall during soil work and just after sowing of maize crop. The training program will provide knowledge on different aspect of conservation measures to be adopted in the agricultural land.

9. Organic farming and eco-tourism. As source of remunerative alternative livelihoods to activities currently being harmful to the Park ecology, organic farming and ecotourism represent strong potential. Therefore the project will provide adequate training to the farmers and households of the 4 settlements in organic farming and eco-tourisms.

10. Outward sloping agricultural land will be planted with fruit trees. Fruit trees do not require tillage operation and help in minimizing soil erosion. When trees reach fruit bearing stage, they start giving economic return to the farmers. Till that stage, farmers can do inter cropping in their land with minimum tillage/mulching. There are 323 households in the watershed area. 20 fruit saplings per household will be distributed to at least 250 households. Altogether 5000 saplings will be distributed to the farmers. This will cover about 12.5 ha of land. Fruits trees such as, pear, peach, plum, orange (at lower altitude) etc. will be distributed to farmers.

11. Promotion of more efficient cooking stoves. 296 households use traditional stoves for cooking their food. When cooking is done in such stoves, energy is wasted due to its low efficiency and more fuel wood will be required. Traditional stoves also cause health problems like lungs diseases to the people. Such stove saves at least 30 % fuel wood. Energy saving improved cook stoves will be promoted in the watershed area and training and demonstration will be done to at least 250 households.

12. Improved sanitation and waste management. Release of waste water directly in the river by these growing settlements is an increasingly worrisome source of early pollution for the Bagmati River and its tributaries. Support in the form of training and demonstration with subsidies is required to help these settlement in adopting eco-friendly household toilets and solid waste management systems.

2. Scope

13. The selected NGO will work with the Project to implement the following specific activities:

(i) Formation of conservation users groups and other committees for BZ

Page 130: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 125

(ii) Training and awareness programs to educate the stakeholders such as National Park staff, army personnel, user groups, local people etc. regarding the consequences of watershed degradation and benefits of well-managed watershed. (30 events)

(iii) Community afforestation and fruit trees distribution in 12.5 ha of community land (iv) Training and demonstration on organic farming and eco-tourism (30 households) (v) Improved cook stoves promotion and training/demonstration in at least 250

households (vi) Training and demonstration on eco friendly toilets and waste management (100

households)

3. NGO Package 2 - Rainwater Harvesting

a. Scope 14. The project interventions proposed under this package are:

b. Rainwater Harvesting (RWH) and Ground Water Recharge 15. For effective implementation of the RWH systems, following approaches will be promoted for implementing rain water harvesting on household level and institutional levels.

(i) Reformulation of by-laws to make the construction of rain water harvesting system mandatory in the new buildings.

(ii) Provision of subsidies to encourage the installment of RWH systems. (iii) Schools and government buildings should be encouraged to install rainwater

harvesting system as these organizations are good places for raising mass awareness on RWH system.

(iv) Capacity building training programmes to be conducted to train sub engineers, engineers, architects, plumbers, students and housewives to impart knowledge on different aspects of RWH systems from installation to O&M.

(v) Help desk should be established for providing technical backstopping and related technical materials to the people for installation of RWH systems.

(vi) Demonstration sites to be established to provide practical knowledge on different components, functioning, installation, operation and maintenance of the RWH systems.

(vii) Different materials such as brochures, guidelines etc on RWH system will be produced and distributed and Radio and TV programmes should be conducted to disseminate the RWH technology, installation and its advantages to the people.

16. The expected coverage area of RWH program is from Gokarna to Guheshwori area. This section of the project area is rapidly urbanizing and has a high rate of ground water extraction by household and private companies.

17. Following are the suggested approaches to implement RWH programs:

a. The selected NGO will devise detail strategy to implement all the components of RWH programs including subsidy program. While devising the subsidy implementation plan, the project will draw upon the lessons learnt from existing tax rebate program run by KMC. Currently, KMC provides 10% rebate in building construction drawing approval tax if the house owner includes RWH system in

Page 131: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

126 Appendix 9

the construction drawing and the rebate is given only after the construction of the building. The subsidy program will be managed by the selected NGO in close coordination with in-line government agencies.

b. In order to create the demand for RWH installation, it will launch intensive awareness raising program at local level. The user interested in installing the system can collect subsidy from the respected local bodies (VDC or municipal wards) or the project office. The installation of RWH system can be done by team of technical experts provided by the selected NGO. The technical team shall also aware the user about maintenance of RWH system.

c. A post-field follow-up program will be carried out on periodic basis to evaluate the effectiveness of RWH system program in the project area. Existing program shall be revised according to the evaluation received from the follow-up program.

d. Demonstration sites will be selected by the technical team based on the interest of schools and government institutions and the potential impact it will create in raising awareness. The RWH plant will be installed by providing required awareness and technical training to the respective institution. Budgeted Costs for Land Polling, Solid Waste and Rainwater Harvesting

4. NGO Package 3 - Community Awareness, Gender, Community Strategy and Solid Waste Management

a. Scope 18. The project interventions proposed under this package are:

b. Community Awareness and Community Strategy Implementation

(i) Develop Local Institutional Mechanisms to Promote Participation, Coordination, and Mobilization

19. The Project will support the development of a multi-stakeholders’ mechanism that encourages Upper Bagmati stakeholder mobilization and awareness raising, including:

Develop and nurture at least two multi-sectoral Technical Working Groups:

Working Group on Bagmati Water Resources Management

Working Group on Bagmati River Environmental Management 21. These are technical working groups, with membership including community groups from the Upper Bagmati. These working groups would provide multi-sector platforms and mechanisms for stakeholder coordination, collaboration, and participation, at least initially focusing only on technical matters. 22. The roles of the working groups would be:

Consultative and provide local feedback regarding a formal river basin organization.

Discuss status of water related projects and activities in the Bagmati River Basin.

Provide forum for exchange of views on challenges and issues facing Bagmati stakeholders.

Share knowledge, information, and advice on public awareness campaigns.

Page 132: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 127

Help develop ideas and actions related to a Bagmati Community Empowerment Program – Information, Awareness, and Education.

Develop awareness framework and guidelines for better involvement of a wider range of stakeholders.

Help develop a Bagmati Basin Information System and knowledge base as way to consolidate and network various sectors.

20. Potential stakeholders as members of the working groups would include:

GON Agencies (HPCIDBC, WECS, KVWSMB/KUKL, etc.)

Municipalities

VDCs and DDCs

CSOs (including representatives from local vulnerable groups, including farmers’ groups in Upper Bagmati)

NGOs

Private Sector 21. It is critically important that local leaders and representatives of the VDCs/DDCs are fully engaged in the Project processes/activities and the Working Groups, to incorporate them as participants into the project, rather than just as observers. The objectives of the Working Groups will only be fulfilled if VDCs/DDCs, CSOs, and other local leaders fully participate in the Working Groups.

(ii) Establishment of NGO Platform

22. The Project will support the formation and development of an NGO Platform which will encourage Upper Bagmati River environment improvement and community participation in maintaining the river environment. The river banks and the green belts created in the flood plains will need to be owned by communities and other local stakeholders. Such initiatives would be best carried out by community level organizations with very little help from the government.

23. The adoption of river stretches by communities, private sector and local NGOs would be an important way of ensuring that the river environment is improved and the communities benefit from the river front development. It is proposed that the greenbelts and river banks along the improved Bagmati River be managed by the user committees formed by the local communities or by interested private sector or local CSOs and NGOs.

24. A national NGO working in the field of environment and community mobilization will be recruited under a NGO contract with the responsibility of mobilizing the communities and forming user committees to take up the responsibility of adoption of river stretches. The selected NGO will carry out community awareness and mobilization activities and assist in establishing user communities to adopt and manage stretches of the river. These stretches can be developed by the communities as gardens and parks for local communities’ benefits, including development of floriculture and small forestry patches for beautification. Competition for awards will be organized periodically by the VDCs or municipalities in order to boost up the morale of the CSOs and NGOs involved in nature conservation work. Private sector may also apply to adopt certain stretches of the rivers under their corporate social responsibility (CSR) activities or support user committees or local NGOs to do so.

Page 133: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

128 Appendix 9

25. The forum of all user committees adopting the river stretches may be established to work with HPCIDBC and VDCs and municipalities to monitor the activities. Such a forum will coordinate with other activities like the annual Bagmati River Festival to showcase their achievements. A “Score Card” system will be used to select the best performing user communities and to encourage others to improve. Seed money will be provided to community- or private sector- led local initiatives on river environment management to the CSOs and small private entrepreneurs.

(iii) Communication Strategy

26. A key part of Upper Bagmati social mobilization will be a Stakeholder Communications Strategy (SCS) which will actively encourage local stakeholders to become involved in project preparation and implementation activities. The SCS focuses on information sharing and consultation, and guides communications with stakeholders during project implementation. Such information sharing will help to build consensus and ensure continuous stakeholder support throughout the Project.

27. The Upper Bagmati SCS includes: (i) developing and implementing institutional mechanisms for water dialogue in the river basin, (ii) supporting multiple communication methods to convey key project messages, (iii) facilitating information sharing among key implementing partners, (iv) continuing field-level discussions with affected people, particularly at the dam/reservoir sites, and (v) supporting sub-projects to achieve visible results in cleaning up the Upper Bagmati (in conjunction with KVUEIP activities).

(iv) Addressing Local Needs and Desires

28. There will be local demands for employment, economic benefits, and security from the dam, deforestation, and environmental problems. For the Project to succeed it is important that priority is given to local people in jobs associated with the project (dam construction, monitoring, etc). A thorough needs assessment through interaction and discussion with all the concerned stakeholders will also help directly address those local demands. The Project also needs to keep in close contact with local leaders to increase the awareness among the concerned stakeholders regarding the safety of the dam. Much concern has been expressed over the proposed dam and reservoir. The local people want to know the consequences of a dam failure for people living downstream and they also want assurances regarding proper safety around the dam and reservoir so people won’t fall in. Planting trees and reducing the cutting of trees will also address local demands, as will specific environmental remediation measures.

(v) Developing National and Local Political Consensus

29. Local groups are concerned that political processes will interfere with the award of economic benefits and positive impacts to the local populace. Therefore, a national and local level advocacy program might be needed to ensure that benefits do accrue to the local communities. Government policies should stress that ownership of the Project goes to locals.

(vi) Ensure Sense of Ownership of Project to Stakeholders in Upper Bagmati

30. Developing a sense of ownership could best be accomplished by providing livelihood opportunities through income generating activities to local stakeholders (park villages, etc.).

Page 134: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 129

c. Gender Action Plan

31. The project will adopt a "promotion of equality" through affirmative discriminatory strategy to include women, the poor and excluded groups during stakeholders (right holders) consultation on project activities at community level and explain to them about the potential impacts of the project in their livelihood and wellbeing, by carrying out a GAM (Gender Analysis Matrix) exercise.

32. GAM is a rapidly conducted gender analysis matrix exercise where they can assess and analyse how BRBIP could impact on their "time, labour, resources and culture” for women, men and children differently, also at household and community level. They will be empowered through this exercise to visualize impacts which will also motivate them for participation.

33. The exercise will help BRBIP to plan activities in a way so that project impacts do not create any negative impact on women's and poor and excluded groups' time, labour, resources and culture, rather makes a positive impact.

34. Moreover, the BRBIP project implementation staff will have to be equipped with GESI operational skills first to make women's participation happen in BRBIP, by ensuring through policy provision during formation of users groups.

35. The project will organize orientation to the staff and partner implementing NGOs on BRBIP GESI aims and the operational strategy, containing potential actions and measuring (monitoring) indicators.

36. Thus capacity building on GESI concept and skills will be done at two level, community and project staff level. While doing this activity at staff and partner NGO level, the responsible counterpart government agencies will also be included for capacity building so that a common understanding about GESI realities and approach is internalized within the responsible institution for sustaining the processes, activities, institutions initiated or strengthened by BRBIP.

37. A BRBIP- GESI action plan will be developed through wider consultation among relevant GON agencies, including Ministry of Water Resources and Irrigation, Ministry of Local Development, NGOs working with Water Users Association, NGOs working in climate change and environmental protection, especially on improving river basins of Bagmati Watershed areas.

38. The BRBIP GESI Action Plan will be implemented and monitored through a coordinated effort among BRBIP, GON counterpart and implementing NGO partners.

39. The lessons thus learned on GESI interventions in BRBIP will be assessed periodically and evaluated at the end of the project; will be documented and disseminated for improving GON policy on GESI mainstreaming in water resources and irrigation management.

40. The design and implementation of project activities will ensure that

(i) All kinds of "user’s associations and committees formed will have at least 33% women’s representation including proportionate representation from socially excluded groups;

(ii) Gender analysis will be carried out among sample users groups in each of river basin areas in order to identify and assess the existing power relationship between gender and caste groups and build up GESI sensitive intervention plans

Page 135: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

130 Appendix 9

so that the target communities can be appropriately enabled to access the development benefits brought by the BRBIP intervention;

(iii) Employment generation through the construction and rehabilitation of irrigation systems will ensure equal pay for equal value of work for both men and women;

(iv) Special attention will be given to seek views and feedback from women, poor and excluded communities;

(v) Community based organizations/nongovernment organizations will be included in project implementation level consultation process so that the design features have the advocacy potential to maximize the benefits reaching women, poor and excluded;

(vi) Prioritization of projects will consider the needs and demands of women, poor and excluded and that are located in geographically remote and excluded;

(vii) River training and watershed management related trainings will ensure participation of women, poor and excluded groups;

(viii) For sustainability of project activities and results on GESI impact, from the very beginning, coordination will be established and promoted by registering the groups with the relevant public service agencies, micro finance Institutions, market networks and local NGOs.

d. Solid Waste Management

(i) Update existing bye-laws and guidelines to incorporate internationally

best and nationally appropriate practices of solid waste management and ensure its effective implementation:

41. Kathmandu Valley Town Development Committee has developed a guideline entitled “Standard on Physical Development within urbanizing VDC and municipalities of Kathmandu Valley 2007”. This guideline defines engineering design standards for building construction including sewerage options and open space requirements. It also sets guideline for landpooling and apartment housing. The current guideline does not include any provisions for promoting best management practices on SWM like composting and waste segregation at household, institution and community levels. This component will update the existing guideline to include the best practices on solid waste. One of the objectives of updating the guideline is to promote concept of eco-friendly homes which adopts best practices of solid waste, storm water and waste water in an integrated manner. The guideline will be developed with technical support from Solid Waste Management Technical Support Center under the provisions of Solid Waste Management Act 2011. Implementation of the bye-laws will be done by local bodies (municipalities and VDC).

(ii) Capacity development of local bodies and other stakeholders for effective management of solid waste:

42. This component will carry activities to strengthen the capacity of local bodies i.e. VDC and municipal wards and other stakeholders like CBO, NGO and interested groups to better manage solid waste within their jurisdiction. These activities include (i) training on effective administration and management of solid waste as per the newly constituted SWMA 2011, (ii) training on 3R principles of SWM including individual and community level composting, (iii) development of guidebook and manual on effective SWM, (iv) supporting local bodies to install waste collection bins where necessary, and (v) conduct excursion visits.

Page 136: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 131

(iii) Developing a strong monitoring and enforcement mechanism against solid waste dumping along river banks:

46. SWMA 2011 strongly prohibits solid waste dumping in undesignated open space including river banks. The Act authorizes local bodies to impose fines and other penalty for anyone dumping waste in open space. This component will develop a strong monitoring and enforcement framework to oversee solid waste dumping along river banks and ensure its effective implementation. The monitoring mechanism can be developed by engaging local bodies, clubs, CBO, NGO, local police, community groups and greenbelt park management committee (where it has been formulated). This component shall support the monitoring group with necessary trainings and other components required to ensure effective monitoring.

(iv) Promoting best practices of solid waste management at household and community levels along river banks:

43. This component will promote best practices of SWM (3R principle) which includes source segregation, individual and community level composting, and effective recycling. This component will provide subsidy to source segregation bins (to separate compostable and non-compostable waste) and to individual and community level composting bins/plants. Lessons will be learnt from similar existing programs being carried out by NGO/CBO and municipalities. Innovative awareness programs will be launched to raise awareness and create demand for adoption of best practices. Subsidy will be provided through local bodies (KMC, VDC) under technical support of SWMTSC (a national level technical support center of GON) and HPCIDBC. The awareness program will be lunched in schools, local community and other places as necessary. Training programs will incorporate strong follow-up activities to effective adoption of SWM practices.

B. Implementation Arrangement

44. Three NGO packages (contracts) will be awarded to national NGOs with the relevant experience, expertise and capacity. All packages will be awarded through a quality-based selection method from qualified NGOs.

NGO Forum for Water and Sanitation (NGOFWS) is an umbrella body of civil society organizations actively working in water supply and sanitation issues. NGOFWS is seen as an appropriate candidate among others for implementing RWH component because it can utilize the technical and managerial human resources of multiple organizations within their network who working in the field of rainwater harvesting in Nepal. In addition, NGOFWS has previous experience working on RWH project of UNHABITAT Water for Asian Cities. Under the program which was launched in 2006, the organization has conducted technical trainings on rainwater harvesting installation, installed RWH in schools and government buildings as demonstration sites, and carried massive awareness raising programs.

45. The selected NGOs will be supervised and work closely with the Project Management Design and Supervision Consultants (PMDSC) and the related experts, in particular, the Social Development and Gender Specialist and the Watershed Management/Wetland Specialist.

Page 137: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

132 Appendix 9

C. Summary of Inputs

National Specialists months

Package 1- Watershed Management

Watershed Specialist Community mobilization specialist Sanitation specialist Agriculture specialist (organic farming) Renewable Energy Specialist Support staff including community organizers

6 12 2 6 2

12

Total 40

Package 2- Rainwater Harvesting (RWH)

RWH Specialist Support staff

12 6

Total 18

Package 3- Community Awareness, Gender, Community Strategy (CS) and Solid Waste Management (SWM)

Community Mobilization Specialist Communication Specialist Gender Specialist Solid Waste Management Specialist Community Mobilizers Support staff

12 12 12 6

24 12

Total 78

1. Package 1- Watershed Management

46. Watershed Specialist (6 person-months). The Watershed Management Specialist shall have a university degree in environment, watershed management, natural resources management or related field and a minimum of 5 years of relevant experience in watershed management. The specialist shall have proven experience in working with and mobilizing local communities to undertake watershed management activities and national park and buffer zone management. S/he will, on behalf of the selected NGO, assist the Project Coordination and Management Unit (PCMU) to carry out the following:

(i) Support for declaration of the SNNP buffer zone covering the settlement areas of Mulkharka, Chilaune, Kunegaun and Okhreni which includes consultations, needs assessment and preparation of a buffer zone management plan;

(ii) Support to form various committees (user groups and management committees) and strengthening these institutions for good governance, conducive environment for biodiversity conservation;

(iii) Training and demonstration/awareness programs to educate the stakeholders such as National Park staff, army personnel, user groups, local people etc. regarding the consequences of watershed degradation and benefits of well-managed watershed and buffer zones (30 events);

(iv) Training and demonstration activities alternative income generation activities; (v) Implementation of slope stabilization activities through community afforestation

with distribution of fruit saplings to at least 25 households in the watershed area and fruit trees distribution to farmers in 12.5 ha of community land/park areas and other relevant activities

Page 138: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 133

(vi) Coordinate and work with other specialists like Sanitation Specialist, Agriculture Specialist and Renewable Energy Specialist to carry out activities and training/demonstration on improved cook stoves, organic farming and improved waste water and solid waste management; and

(vii) Any other activity required to enhance watershed management. 47. Community Mobilization Specialist (12 person-months). The Community Mobilization Specialist shall have an university degree in social science, rural development or relevant field and a minimum of 5 years of experience in community mobilization. The specialist shall have proven experience in working with and mobilizing local communities. S/he will, on behalf of the selected NGO, work closely with and support the Watershed Management Specialist to carry out the following:

(i) Formation of various committees (user groups and management committees) for buffer zone management covering Mulkharka, Chilaune, Kunegaun and Okhreni settlements and strengthen these institutions for good governance, conducive environment for biodiversity conservation; and

(ii) Any other activity necessary to mobilize local communities to establish the SNNP buffer zone.

48. Agriculture Specialist (organic farming) (6 person-months). The Agriculture Specialist shall have an university degree in agriculture or relevant field and a minimum of 5 years of experience in promoting and implementing organic farming. The specialist shall have proven experience in working with local communities/farmers. S/he will, on behalf of the selected NGO, work closely with and support the Watershed Management Specialist to carry out the following:

(i) Training and demonstration of organic farming and eco-tourism activities (30 households) in proposed buffer zone area covering the four settlements;

(ii) Training and demonstration on agriculture related alternative income generation activities; and

(iii) Any other activity necessary to promote and implement organic farming and eco-tourism.

49. Sanitation Specialist (2 person-months). The Sanitation Specialist shall have an university degree in civil engineering, water supply and sanitation, environment or relevant field and a minimum of 5 years of experience in water supply and sanitation (WATSAN). The specialist shall have proven experience in working with local communities and in rural areas. S/he will, on behalf of the selected NGO, carry out the following:

(i) Training and demonstration (100 households) in the four settlements on eco-friendly toilets and waste management;

(ii) Design and plan a program with subsidies to upscale the demonstration schemes in the four settlements to help these settlements in adopting eco-friendly household toilets and solid waste management; and

(iii) Any other activity necessary to promote and implement eco-friendly household toilets and waste management systems.

50. Renewable Energy Specialist (2 person-months). The Renewable Energy Specialist shall have a university degree in renewable energy with a minimum of 5 years of experience in biomass energy and in particular promoting and installing improved cooked stoves in rural communities. The specialist shall have proven experience in working with and mobilizing local communities. S/he will, on behalf of the selected NGO, assist the Project Coordination and Management Unit (PCMU) to carry out the following:

Page 139: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

134 Appendix 9

(i) Promote alternative renewable energy use to displace the use of traditional cook stoves that have huge health benefits to communities as well as to reduce/stop use of fuel wood;

(ii) Promote and train/demonstrate the use of Improved cook stoves in at least 250 households in the watershed area; and

(iii) Any other activity required to promote the use of renewable energy source that enhance watershed management.

2. Package 2- Rainwater Harvesting

51. Rainwater Harvesting (RWH) Specialist (12 person-months). The RWH shall have a university degree in relevant field with a minimum of 5 years experience working in promoting and installing rainwater harvesting and ground water recharge systems. The specialist shall have proven experience in working with and mobilizing local communities to undertake rainwater harvesting activities. S/he will, on behalf of the selected NGO, will work with the Legal Specialist (RWH/SWM) and assist the Project Coordination and Management Unit (PCMU) in the promotion of rainwater harvesting from Gokarna to Guheshworu area and to carry out the following:

(i) Reformulation of by-laws to make the construction of rain water harvesting system mandatory in the new buildings;

(ii) Manage the provision of subsidies to encourage the installment of RWH systems including implementation of RWH systems in 2,500 households;

(iii) Encourage schools and government buildings to install rainwater harvesting system as these organizations are good places for raising mass awareness on RWH system including implementation of demonstration schemes in 5 public schools and 5 private schools;

(iv) Conduct capacity building training programmes to train sub engineers, engineers, architects, plumbers, students and housewives to impart knowledge on different aspects of RWH systems from installation to O&M (30 events);

(v) Establish a help desk for providing technical backstopping and related technical materials to the people for installation of RWH systems including extension and education programs;

(vi) Establish demonstration sites to provide practical knowledge on different components, functioning, installation, operation and maintenance of the RWH systems;

(vii) Produce and distribute different materials such as brochures, guidelines etc on RWH system and conduct Radio and TV programmes to disseminate the RWH technology, installation and its advantages to the people;

(viii) Carry out post-field follow-up program on perriodic basis to evaluate the effectiveness of RWH system program in the project area; and

(ix) Any other activity required to enhance RWH.

3. Package 3- Community Awareness, Gender Solid Waste Management and Communication Strategy

52. Community Mobilization Specialist (12 person-months). The Community Mobilization Specialist shall have a university degree in social science, rural development or relevant field and a minimum of 5 years of experience in community mobilization. The specialist shall have proven experience in working with and mobilizing local communities. S/he will, on

Page 140: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

Appendix 9 135

behalf of the selected NGO, work closely with the Social Development and Gender Specialist of the Project Coordination and Management Unit (PCMU) and assist to carry out the following:

(i) Develop local institutional mechanisms to promote participation, coordination, and mobilization;

(ii) Encourage Upper Bagmati environment improvement and community participation in maintaining the river environment through community awareness and mobilization to adopt river stretches, initiate "score card" system;

(iii) Further develop the NGO platform proposed in the PPTA phase and form a suitable NGO Platform; and

(iv) Any other activity to promote to community awareness, participation and ownership of the proposed Upper Bagmati River Improvement initiatives.

53. Communication Specialist (12 person-months). The Communication Specialist shall have a university degree in communications or relevant field with a minimum of 5 years of experience working on communications with stakeholders including media, local communities, government and the private sector. S/he will, on behalf of the selected NGO, work closely with the Institutions Specialist of the Project Coordination and Management Unit (PCMU) and assist to carry out the following:

(i) Assist in implementing the Stakeholder Communications Strategy (SCS) including development of local institutional mechanisms to promote participation, coordination and mobilization and further updating and implementing the SCS development during the PPTA

(ii) Addressing local needs and desires; (iii) Develop national and local political consensus; (iv) Ensure sense of ownership of Project to stakeholders in Upper Bagmati; and (v) Any other activity required to implement the SCS.

54. Gender Specialist (12 person-months). The Gender Specialist shall have a university degree in Gender Studies or relevant field and a minimum of 5 years of experience in gender mainstreaming and implementation of Gender Action Plans The specialist shall have proven experience in working with and mobilizing local communities. S/he will, on behalf of the selected NGO, will work closely with the Social Development and Gender Specialist of the Project Coordination and Management Unit (PCMU) and assist to carry out the following:

(i) Gender Analysis Matrix (GAM) exercise and develop/update the BRBIP Gender Equity and Social Inclusion (GESI) through wider consultations;

(ii) Organize orientation to staff and implementing partners on GESI aims and the operational strategy;

(iii) Conduct capacity building on GESI concept and skills at two levels, community and project staff level; and

(iv) Any other activity to promote to GESI action plans.

55. Solid Waste Management (SWM) Specialist (6 person-months). The SWM Specialist shall have a university degree in relevant field with a minimum of 5 years experience working in solid wastes management. The specialist shall have proven experience in working with and mobilizing local communities. S/he will, on behalf of the selected NGO, will work with the Legal Specialist (RWH/SWM) and assist the Project Coordination and Management Unit (PCMU) in the promotion of solid waste management and to carry out the following:

(i) Update existing bye-laws and guidelines to incorporate internationally best and nationally appropriate practices of solid waste management and ensure its effective implementation;

Page 141: Bagmati River Basin Improvement Project€¦ · Bagmati River Basin Improvement Project (RRP NEP 43448) Project Number: 43448 October 2013 Nepal: Bagmati River Basin Improvement Project

136 Appendix 9

(ii) Conduct capacity development of local bodies and other stakeholders for effective management of solid waste including trainings on solid waste management (6 events), organizing study tours to nearby community-based SWM systems (3 tours) and preparation of solid waste management manuals;

(iii) Develop a strong monitoring and enforcement mechanism against solid waste dumping along river banks (including 6 trainings on M & E and preparation of support materials for M & E);

(iv) Promote best practices of solid waste management at household and community levels along river banks through provisions of subsidy for composting bins, segregation bins, community level composting, awareness programs and pilot units in schools; and

(v) Any other activity required to promote SWM.

56. The selected NGOs will provide qualified support staff and community mobilizers (NGO package) undertake the activities proposed in the TOR. Strong interpersonal relationship, experience in Nepal and fluency in spoken and written English as well as Nepali are required.