basic training guide

87
e-DPP ( electrical - Data Processing Program ) Basic Training Guide  Eltechs Engineeri ng & Consultin g Co., Ltd. Page 1 of 87 V er.3.0.0 Basic Training Guide e-DPP (electrical - Data Processing Program) has been developed with technical cooperation from major engineering companies. The abundant knowle dge and experience of these companies that ha ve been cultivated f rom the actual execution of the design, construction and operation of various overseas and domestic projects were condensed in e-DPP . e-DPP supports your design and coherent engineering work flow from the initial design stage up to material  procurement and field commissioning. This guide was prepared for new users (beginners) to quickly understand the basic functions and operations of e-DPP using the “Example” Project that comes with the software. For more detailed information and operations, please refer to the separate document "e-DPP User Guide".

Upload: hendrias-ari-sujarwo

Post on 15-Feb-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 1/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 1 of 87 Ver.3.0.0 

Basic Training Guide

e-DPP (electrical - Data Processing Program) has been developed with technical cooperation from major engineering

companies. The abundant knowledge and experience of these companies that have been cultivated from the actualexecution of the design, construction and operation of various overseas and domestic projects were condensed in e-DPP.

e-DPP supports your design and coherent engineering work flow from the initial design stage up to material

 procurement and field commissioning.

This guide was prepared for new users (beginners) to quickly understand the basic functions and operations of e-DPPusing the “Example” Project that comes with the software.

For more detailed information and operations, please refer to the separate document "e-DPP User Guide".

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 2/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 2 of 87 Ver.3.0.0 

Contents

1. 

Opening a Project File ............................................................. .................................................. 3 

2. 

Setting Default Data ......................................................... ......................................................... 4 

3.  Data Import............................................................................. ................................................. 11 

4. 

Data Filling................................................................ .............................................................. 20 

5.  Adding & Editing Electrical Loads .................................................................... ..................... 26 

6.  Motor Schedule and Data Sheet ............................................................. ................................. 29 

7. 

Load Summary .................................................... ........................................................... ......... 34 

8.  Power Cable Sizing ........................................................ ......................................................... 42 

9.  Cable Schedule & Summary.................................................................................................... 51 

10 

Cable Sizing Chart................................................ ........................................................... ........ 55 

11  Drum Schedule .................................................. ........................................................... ........... 59 

12. 

Control Signal Schedule ........................................................... ............................................... 72 

13.  MCC Schedule................................................................................ ......................................... 77 

14.  Project Editor.............................. ................................................................ ............................. 79 

15. 

Revision Control............................................... ................................................................ ....... 81 

16.  ETAP Interface ....................................................... .......................................................... ....... 86 

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 3/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 3 of 87 Ver.3.0.0 

1. Opening a Project File

(1)  Double-click the e-DPP 3.0 icon on the desktop.

(2)  e-DPP starts, reload the most recently accessed project (by default) and display the “Login” dialog window. Click“Cancel” button to open another project.

 Note: You may set e-DPP to “not” reload the most recently accessed project at startup in the main menu “ToolsUser

Options…“

(3)  On the main menu, select “File Open Project…” and browse to “C:¥Program Files¥eDPPv300¥Example” folderand select and open “Example.mdb”.

“Example.mdb” project has been pre-prepared with base data and will be used in this training to explore the e-DPPfunctions.

(4)  Click “OK” button on the “Login” dialog box.

(End of Chapter 1)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 4/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 4 of 87 Ver.3.0.0 

2. Setting Default Data

2.1 Project DefaultThe project default data contains information common to the entire project. In this exercise, this data have been

 pre-populated. In short, the following procedures will be executed only to show their significance.

2.1.1 Project Information

(1)  On the main menu, select “Project Information…” or click the icon from the “Project” toolbar.

(2)  The “Project: Information” dialog window will be displayed. The information here will be used as part of the outputreports like schedule or data sheet, but will not affect any calculation process. You may try to modify any entries asyou like.

(3)  Click “OK” or “Cancel” button to close the window.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 5/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 5 of 87 Ver.3.0.0 

2.1.2 Project Standard

(1)  On the main menu, select “Project Standard…” or click the icon from the “Project” toolbar.

(2)  The “Project : Standard” dialog window will be displayed. Here, the power frequency and project standards aredefined. However, do not change the current setting since the Example project had been prepared based on these

conditions.

(3)  Click “Cancel” button to close the window.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 6/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 6 of 87 Ver.3.0.0 

2.1.3 Project Settings

2.1.3.1 Loading Categories

(1)  On the main menu, select “Project Settings… Loading Categories…” or click the icon from the“Project” toolbar and select “Loading Categories…”.

(2)  The “Loading Category” dialog window will be displayed.

You may define an appropriate name for each loading category. The current version of e-DPP supports up to 3loading categories. Loading category is used in the load summary calculation to account the different possible

loading state of each load at different instance in the electrical system.

(3)  Click “OK” button to close the window.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 7/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 7 of 87 Ver.3.0.0 

2.1.3.2 System Configurations

(1)  On the main menu, select “Project Settings… System Configurations…” or click the icon from the

“Project” toolbar and select “System Configurations…”.

(2)  The “System Configurations” dialog window will be displayed.

You may define an appropriate name for each configuration. System configuration is used in the load summary

calculation to account the different possible configuration of the electrical system at different instance. Forexample, a certain bus or switchgear is out of service at a particular time.

(3)  Click “OK” button to close the window.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 8/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 8 of 87 Ver.3.0.0 

2.1.4 Project Electrical

(1)  On the main menu, select “Project Electrical…” or click the icon from the “Project” toolbar.

(2)  The “Project:Electrical” dialog window will be displayed.

e-DPP accommodates a maximum of 8 voltage levels including a DC voltage. The voltage levels correspond to the

available voltage levels in a project. These voltages and the associated parameters are used as criteria in the data fillingand calculations.

Do not modify the preset settings. These setting will be the basis of the calculations that will be carried out later.

(3)  Click “Cancel” button to close the window.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 9/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 9 of 87 Ver.3.0.0 

2.2 Setting Motor Default

(1)  On the main menu, select “Defaults 

Induction Motor…” or click the icon from the “Defaults and DataFilling” toolbar.

(2)  The “Induction Motor – Default Data” dialog window will be displayed.

The “Induction Motor – Default Data” dialog contains 3 tabs, the “Rating and Specification”, “Accessories and Others”,and “Cables”. The data specified on these tabs will be used to populate the missing parameters of the induction motorsin the load schedule when the “Data Filling” function is executed.

(3)  On the “Rating and Specification” tab, enter 60 and 30 to “%Loading <2>” and “%Loading<3>” respectively.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 10/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 10 of 87 Ver.3.0.0 

(4)  On the “Accessories and Others” tab, modify any data as desired.

(5)  On the “Cable” tab, enter “325” in the “Default Length” textbox inside the “Main Power Cable” frame and select“1:U/G Buried” on the “Raceway Type” pull down menu under of the “Cable Installation” frame.

 Note: When the “Data Filling” function is executed, e-DPP will generate cable numbers automatically according to the naming

convention indicated in the “Cable Numbering” frame. In addition, the specification of the LCS, CCR, and Space Heater cables will be obtained from the values specified in the “Cable Specification” frame.

(6)  Click “Save” and then “Close” button to save the changes and close the window respectively.

(End of Chapter 2)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 11/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 11 of 87 Ver.3.0.0 

3. Data Import

3.1 Data Import from Excel File

(1)  On the main menu, select “File Import Import MS Excel” or click this icon from the “File” toolbar.

(2)  The “Excel File Import” dialog window will be displayed. On this window (see the images on next page), do thefollowing:

a.  Click “Create” button on the “Mapping Selection” frame. The “Create New Mapping ID” dialog will be

displayed.

 b.  Type “My Excel Import” on the textbox of “Create New Mapping ID” dialog and click “OK” button.

c.  Click “Find…” button on the “Source File” frame.

d.  On the “Open” dialog box, browse and open the “Example.xls” file located at “C:¥Programfiles¥eDPPv300¥Example” folder.

e.  Select “Example Sheet” from the “Sheet” drop down list on the “Source File” frame.

f.  Select “DPPElecLoad” from the “Table” drop down list box on the “Destination File (e-DPP ProjectDatabase) frame.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 12/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 12 of 87 Ver.3.0.0 

a

ce

b

f

dd

b

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 13/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 13 of 87 Ver.3.0.0 

g.  Map the data. Click column “Col 2” of the “User Field (Source File)” table and drag & drop to “row 1” of“e-DPP Field (Destination File)” table. Notice the cell under “User Field”, it will contain the name “Col

2”.

Complete the data mapping based on the following relationship:

User Field (Source File) Table e-DPP Field (Destination File) Table

Col 3   Row 2

Col 4   Row 3

Col 4   Row 4

Col 4   Row 5

Col 8   Row 155

Col 9   Row 6

Col 10

  Row 7Col 11   Row 8

Col 12   Row 9

Col 13   Row 10

Col 14   Row 11

Col 15   Row 12

Col 16   Row 13

Col 17   Row 17

Col 18   Row 20

Col 19   Row 21

Col 20   Row 22

Col 21   Row 23

 Note: On “e-DPP Field (Destination File)” frame, navigate the table downward to locate “Row 155”. If you make a mistake,

click the corresponding cell under “User Field” column on the “e-DPP Field (Destination File)” frame and press “Delete”key on the keyboard.

g

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 14/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 14 of 87 Ver.3.0.0 

h.  In the “User Field (Source File)” table, click repeatedly the vertical navigation button until row 4 isdisplayed at the top row.

i.  In the “e-DPP Field (Destination File)” table, notice Row 3, 4, and 5. They contain the same cell “Col 4”.This means that the data of the “Col 4” from the excel file (i.e. “User Field (Source File)” table) will be

assign to these three fields.

 j.  In the “e-DPP Field (Destination File)” table, click the cell in row 3:column “Op” and select “LUT” from the drop down list.

 Note: The value “C”, “I”, and “S” from the Col 4 of the excel file will not berecognized by e-DPP since the destination fields, i.e. “ContQty”, “InterQty”,

and “SpareQty” accept only integer type data. As such, these raw data should be converted accordingly.

k.  Click the “Show…” button. The “Import – Look-up Table” table will

 be displayed.

l.  After the inspection, click the “Close” button.

 Note: The “Look-up Table” is defined in the Value List Editor that can be

accessed from the main menu “DefaultValue List…”

m.  Repeat step “j” above to rows 4 (InterQty), 5 (SpareQty), 8 (EquipType), and 10 (HP_KW) respectively.

h

i

 j

k

l

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 15/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 15 of 87 Ver.3.0.0 

n.  In the “User Field (Source File)” table, click repeatedly the horizontal navigation button until “Col 4” isdisplayed at the left-most column.

o.   Notice “Col 15”. This column corresponds to the rated voltages of the loads and the values are expressedin Volts. e-DPP recognizes the unit of voltage in “kilovolts” only. Therefore, the raw data should be

converted to kV.

 p.  In the “e-DPP Field (Destination File)”table, click the cell in row 12, column “Op”and select “/” from the drop down list.

q.  Enter “1000” on the adjacent cell under“Operand” column. This will divide theraw data by 1000.

r.  In the “e-DPP Field (Destination File)”table, notice that no entry have beenmapped to row 16 (PercentLoad0). Enter“80” to the cell under “Constant” column.e-DPP will assign 80% loading value to allthe loads that will be imported.

n

o

q

p

r

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 16/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 16 of 87 Ver.3.0.0 

s.  Similarly, enter the following:

DegreeProtection = IP55

Rotation = CW

CCRLenghtValue = 60

 Note: Navigate the table downward tolocate “CCRLenghtValue” (Row 44)

t.  In the “When a record with the same IDexists” frame, select “Do not overwrite”.

u.  In the “Data Area” frame “Starting Row#” text box, enter “4”

 Note: The value “4” is the row number of the

first record in the “User Field (Source File)”table.

v.  In the “Elec. Load Table Options” frame,do the following options:

i.  Check “Extract ID suffix”

ii.  Select “Only one (1) alphabet”

 Note: These options will group electricalloads in which their IDs constitute a series.

The IDs will be identified as in series if the lastcharacter is an alphabet and it precedes anumerical character and from this backward to

the first character the IDs are identical.

w.  In the “MS-Excel Options” frame, do thefollowing options:

i.  Check “Terminate by blank cell”

ii.  Enter “10” in the “Number ofconsecutive blank cells (Max.99)” text box

iii.  Check “Terminate by specificstring”

iv.  Enter “<End of Records>” in the“Specific string (Max. 32 chr)”text box

s

tu

v(i)

v(ii)

w(i)w(ii)

w(iii)

w(iv)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 17/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 17 of 87 Ver.3.0.0 

x.  In the “Mapping Selection” frame, click “Save” button.

y.  Click “Import” button.

z.  Click “Yes” button on the succeeding dialog to view the results.

x

y

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 18/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 18 of 87 Ver.3.0.0 

aa.  The results will be displayed on the “Import Quick View” dialog. Click the control button to closethe dialog.

 bb.  Click the “Close” button on the “Excel File Import” dialog to close it.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 19/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 19 of 87 Ver.3.0.0 

3.2 Data Confirmation

(1)  On the main menu, select “Edit All Electrical Loads Electrical Load Schedule (Form-1)” or from the “Edit

Data (Load & Cable)” toolbar, click the down-arrow button adjacent to “All Elec Loads” icon and select“Electrical Load Schedule (Form-1)”.

(2)  The Electrical Load Schedule (Form-1) table will be shown. Notice that there are 45 records that have beenimported.

(End of Chapter 3)

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 20/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 20 of 87 Ver.3.0.0 

4. Data Filling

4.1 Induction Motor

(1)  On the main menu, select “Edit All Motors Motor Characteristic Data” or from the “Edit Data (Load &Cable)” toolbar, click the down-arrow button adjacent to “All Motors” icon and select “Motor Characteristic Data”.

(2)  The “Motor Characteristic Data” table will be shown. Notice that many parameters contain zero value yet (i.e. FLA,

Machine RPM, PF100, PF050, etc). You may populate these parameters manually or automatically. Clickcontrol button to close the table.

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 21/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 21 of 87 Ver.3.0.0 

(3)  To fill in data automatically, on the main menu select “Data Filling Induction Motors…” or from the “Defaults &

Data Filling” toolbar, click the icon .

(4)  The “Data Filling – Induction Motor” dialog window will be displayed. On this window, do the following:

a.  Select “Blank/Zero Data Only”. As the title implies, this option will fill data to the parameters with blank orzero value only.

 b.  Click “Set All” button. This action will select all the checkboxes (candidate parameters).

Example: If the “KV” is checked in the “By Project Information” frame, any motors in the load schedule without KVrating will be filled-in with voltage according to the criteria set in the “Project : Electrical” editor (to access this, in the mainmenu, select “ProjectElectrical…”). Say if the motor rated output is between 151kW and 1500kW and no voltage is

currently specified to this motor in the load schedule, e-DPP will assign 4kV.

c.  Click “Fill Up” button.

d.  Click “OK” button on the “Information” dialog that will be displayed subsequently.

e.  Click “Close” button. Note: The fill-in-data will come from the default data described in section 4.0

a

b

ce

OR

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 22/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 22 of 87 Ver.3.0.0 

(5)  To verify the results, open again the “Motor Characteristic Data” table. Refer to step “(1)” above.

 Notice the parameters that contain zero value (e.g. FLC(A), Machine RPM, PF100, PF050, etc) in step “2” above

now contain data. See image below.

(6)  Click the control button to close the “Motor Characteristic Data” table.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 23/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 23 of 87 Ver.3.0.0 

4.2 Static Load

(1)  On the main menu, select “Edit All Electrical Loads Input Data for Cable Sizing” or from the “Edit Data

(Load & Cable)” toolbar, click the down-arrow button adjacent to “All Electrical Loads” icon and select “InputData for Cable Sizing”. The “Input Data for Cable Sizing” table will be shown. It shows all types of electricalloads.

(2)  To filter the table to “Static Loads” type only, on the “MDI Editor”, click “Filter” icon. The “Filter” dialog window

will be displayed.

 Note: To show the “MDI Editor”, on the main menu, select “ViewToolbarsMDI Editor”

(3)  On the “Filter” dialog window, do the following:

a.  Click “Set” button

 b.  Select “EquipCode” on the 1st drop down list

c.  Select “=” on the 2nd drop down list

d.  Select “4” on the 3rd drop down list. Note, the code “4” stands for “Static Load”

e.  Select “AND” on the 4th drop down list

f.  Click “OK” button

a

b

c

d

f

e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 24/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 24 of 87 Ver.3.0.0 

(4)  The “Input Data for Cable Sizing” table will be filtered as shown below. Notice the “FLC(A)”, “PF100(%)”,

“Power Cable ID” and other related parameters are blank/zero. Click the control button to close the table.

(5)  On the main menu, select “Data Filling Static Loads…” or from the “Defaults & Data Filling” toolbar, click the

icon . The “Data Filling – Static Load” window will be displayed.

(6)  On the “Data Filling – Static Load” window, do the following:

a.  Select “Blank/Zero Data Only”.

 b.  Click “Set All” button.

c.  Click “Fill Up” button.

d.  Click “OK” button on the “Information” dialog that will be displayed successively.

e.  Click “Close” button.

a

b

c e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 25/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 25 of 87 Ver.3.0.0 

(7)  To verify the results, open again the “Input Data for Cable Sizing” table. Refer to step “1” above. The “Input Datafor Cable Sizing” table will be shown as follows. Notice the “FLC(A), “PF100(%), “Power Cable ID” and other

related parameters contain data now. Click the control button to close the window.

(End of Chapter 4)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 26/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 26 of 87 Ver.3.0.0 

5. Adding & Editing Electrical Loads

(1)  On the main menu, select “Edit All Electrical Loads Electrical Load Schedule (Form-1)” or from the “Edit

Data (Load & Cable)” toolbar, click the down-arrow button adjacent to “All Electrical Loads” icon and select“Electrical Load Schedule (Form-1)”. The “Electrical Load Schedule (Form-1)” table will be shown.

(2)  On the “MDI Editor”, click “Add ID” icon.

(3)  The “Add New Item” dialog window will be displayed. On this window, do the following:

a.  Enter “PM-8000”

 b.  Click “Find” button.

c.  Enter “1” in the cell Q’ty row and“Cont” column. This means thatwe are creating one new item with

continuous operation mode.

d.  Select “IM” (Induction Motor) inthe “Equip.Type” frame.

e.  Enter “Back feed pump” in the

“Service” text box. This is thedescription of the new item.

f.  Click “OK” button

(4)   Notice that the new motor has been added to the “Electrical Load Schedule (Form-1)” table. Click “PM-8000” on

the table.

(5)  On the “MDI Editor” toolbar, click the “Library Quick Pick” icon. We will populate the motor with nameplate data

from the library.

4

a b

c

d

e

f

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 27/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 27 of 87 Ver.3.0.0 

(6)  The “Library Quick Pick” dialog window will be displayed. On this window, do the following:

a.  Select “60 Hz” in the “Frequency” frame

 b.  Select “KW” in the “Unit” frame

c.  In the “Manufacturer”, “Enclosure Type”, “KV”, “Poles”, and “Output” list boxes, select

“DPPTEFC0.442160” respectively

d.  Click “OK” button

e.  Click “Yes” button on the “Please Confirm” dialog window that will appear subsequently.

(7)  Save the changes by clicking “Save” icon on the “Edit” toolbar.

a

b

c

d

e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 28/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 28 of 87 Ver.3.0.0 

(8)  Other data like “Rotation”, “Degree of Protection”, and others may be populated as desired. “Electrical Load

Schedule (Form-1)” table is in spreadsheet format and the data may be entered and/or edited in a manner like anyordinary spreadsheet program.

To edit/enter data in the other wayaround, right-click on item“PM-8000” and select“Properties..” on the pop-up menu.

(9)  “Property List” dialog window will be displayed. On this window, do the following:

a.  Enter the following data to the respectivefields:

Protection Degree = IP55

Rotation = CW

Power Cable ID = PM-8000-P

Power Cable Length = 200 m

Power Cable Raceway Type = U/G Buried

 Notes:

 Navigate down to view other fields.

You may view the fields by group or in ascending

alphabetical order by switching between the icons

which are located on the top-left most

of the window. 

 b.  Click “Save” and “Close” button

(End of Chapter 5)

Navigate down to view

other fields

b

a

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 29/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 29 of 87 Ver.3.0.0 

6. Motor Schedule and Data Sheet

6.1 Generating Motor Schedule

(1)  On the main menu, select “Edit All Motors Motor Schedule (Form-1)” or from the “Edit Data (Load &Cable)” toolbar, click the down-arrow button adjacent to “All Motors” icon and select “Motor Schedule (Form-1)”.

(2)  The “Motor Schedule (Form-1)” table will be shown.

(3)  On the “MDI Editor” toolbar, click “To Excel” icon.

(4)  The “To Excel” dialog window will be displayed. On this window, click “OK” button.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 30/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 30 of 87 Ver.3.0.0 

(5)  The Excel report will be generated as shown below.

(6)  You may now print output.

 Note: Depending on the settings of your printer, a page would be split to more than one. In such case, adjust a scale factor or

top/bottom margins on the “Printer Setup” menu of EXCEL.

(7)  Close the excel file without saving.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 31/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 31 of 87 Ver.3.0.0 

6.2 Generating Motor Data Sheet

While a motor schedule indicates more than one motor per sheet in a spread form, a data sheet indicates only one motor

item (or group of identical motors) per sheet.

(1)  On the main menu, select “Edit Induction Motor Induction Motor Datasheet” or from the “Edit Data (Load& Cable)” toolbar, click the down-arrow button adjacent to “Induction Motor” icon and select “Induction MotorDatasheet”.

(2)  The “Induction Motor Datasheet” table will be shown.

(3)   Notice that there are 38 inductions motors. However, our intention is to print only datasheet for motorPM-101A/B/C. To do so, filter first the table by clicking the “Filter” icon on the “MDI

On the Filter dialog (see image on next page), do the following:

a.  Click “Set” button

 b.  Select “IDbody” on the 1st drop down list

c.  Select “=” on the 2nd drop down list

d.  Select “PM-1001” on the 3rd drop down list.

e.  Select “AND” on the 4th drop down list

f.  Click “OK” button

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 32/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 32 of 87 Ver.3.0.0 

(4)  The “Induction Motor Datasheet” table will be filtered as shown below.

(5)  We can generate datasheet for each item above. But since each item are identical in nature (same nameplate data),we will generate only one datasheet for all. On the “MDI Editor” toolbar, click “Compress” icon.

(6)  A new window “Induction Motor Datasheet ####Compressed###” will be displayed as shown below.

(7)  On the “MDI Editor” toolbar, click “To Excel” icon.

a

b

f

c

d

e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 33/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 33 of 87 Ver.3.0.0 

(8)  The “To Excel” dialog window will be displayed. On this window, click “OK” button.

(9)  The Excel report will be generated as shown below.

(10) Close the Excel file without saving.

(11) Close the “Induction Motor Datasheet ####Compressed###” and “Induction Motor Datasheet” tables.

(End of Chapter 5)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 34/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 34 of 87 Ver.3.0.0 

7. Load Summary

The following system has been pre-configured. e-DPP currently supports a radial system only.

See notes

 Notes:

1. < top > is an imaginary element in e-DPP. It represents the power source of the electrical system (radial). It can only beconnected to one bus (the main supply power bus) or one switchboard (the main supply power switchboard) in eachconfiguration. The ID “< top >” is case sensitive and it has space between “<” and “t” and between “p” and “>”.

2. SG-01 is a dummy bus. This bus is necessary since there are two upstream buses, SG-01A and SG-01B and the imaginary

element < Top > cannot be connected to more than one bus as mentioned in note 1.

< top >

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 35/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 35 of 87 Ver.3.0.0 

7.1 Bus Interconnection and Bus Load Assignment (Spread Table Method)

(1)  To verify the bus connections, on the main menu select “Edit Bus Bus List” or from the “Edit Data (Load

Summary Base)” toolbar, click the down-arrow on the right of “Bus” icon and select “Bus List”

(2)  The “Bus List” table will be displayed. Notice the “Bus ID” and “Source Bus1” columns. These columns indicate

the connection of the buses. For example, the dummy bus “SG-01” is connected to “< top >”, “SG-01A” isconnected to “SG-01” dummy bus, etc. Refer to the one line diagram shown above.

The “Source Bus2” and “Source Bus3” columns are other system interconnections (or system configuration) withrespect to the “Bus ID” column. In short, there are three system configurations and are summarized in thefollowing table.

System Configuration Connection

From To

Configuration 1 Bus ID Source Bus 1

Configuration 2 Bus ID Source Bus 2

Configuration 3 Bus ID Source Bus 3

(3)  Click the control button to close “Bus List” table for the time being.

(4)  To verify the loads connected on each bus, on the main menu select “Edit Bus Bus Connected Loads” or from

the “Edit Data (Load Summary Base)” toolbar, click the down-arrow beside the “Bus” icon and select “BusConnected Loads”

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 36/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 36 of 87 Ver.3.0.0 

(5)  The “Bus Connected Loads” table will bedisplayed. Click the header of the “Bus

ID” column to sort the bus ID inascending order (note: clicking the header

repeatedly will switch the sortingascending and descending and viceversa).

 Notice the “Bus ID” and the “Item No.”

columns. The items on the “Item No.”column are connected to the bus on the

“Bus ID” column. For example, theloads (Item No.) on row 1 to11 are allconnected to bus “DP-01”. Refer to theone line diagram on page 34 to confirm

that the loads are correctly connected tothe appropriate bus.

(6)  The Item No. “PM-8000” (row 46) is not

connected yet to any bus. Connect it to bus “MC-021B” by typing “MC-021B” incell under “Bus ID” column.

(7)  Save the changes by click “Save” icon on the “Edit” toolbar.

(8)  Close the “Bus Connected Loads” table by clicking the control button located on the upper-right corner oftable.

6

5

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 37/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 37 of 87 Ver.3.0.0 

7.2 Bus Interconnection and Bus Load Assignment (GUI Method)

The bus interconnections and bus load assignment were already pre-configured. The following steps will be presented

to show only the significance of the GUI method.

(1)  On the main menu select “Load Summary Bus Loads…” or from the “Load Summary” toolbar, click the“Bus Load Editor” icon.

(2)  The “Edit: Bus Contents” dialog window will be displayed (see the image below). Notice the following:

a.  The “System Configuration” drop down list contains the different bus interconnection schemes. On the dropdown list are the User Specified Names of the system configurations. These User Specified Names

correspond to the following:

System Configuration

User Specified Name* Correspondence

 Normal Configuration 1

Emergency Configuration 2

Shut Down Configuration 3

User Define 4 Configuration 4

User Define 5 Configuration 5

User Define 6 Configuration 6

User Define 7 Configuration 7

User Define 8 Configuration 8

User Define 9 Configuration 9

User Define 10 Configuration 10

Refer to section 7.1.(2) to see the

interconnection scheme that Configuration1, 2, and 3 represents.

Configurations 4 to 10 (i.e. Source Bus 4 to10 column) are not shown in the “Bus List”table. To access them, a new table must becreated using the “User-defined” templatefunction.

User Template can be created as desiredfrom the main menu “TemplateSchedule

Sheet” or” Template Datasheet”

*Specified in the “ProjectSettingSystem Configuration” (see section 2.1.3.2.(2))

 b.  The “Bus No.” drop down list refers tothe “From” (Bus ID column) described insection 7.1.(2).

c.  The “Source Bus” drop down list refers tothe “To” (Source Bus 1, Source Bus 2,

Source Bus 3 columns) described insection 7.1.(2).

d.  The “Allocated to Bus” list box shows theloads connected to the selected bus in the“Bus No.” drop down list.

e.  Click the “Check Connection” button toverify the connection between the

“From” (i.e. Bus. No.) and “To” (i.e.Source Bus) does not constitute to alooped connection.

f.  Click “Close” button to close the dialogwindow.

a

b

c

d

e

f

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 38/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 38 of 87 Ver.3.0.0 

7.3 Load Summary Calculation

Load summary calculation can be executed “Bus” or “Switchboard” base. “Bus” base load summary calculates the total

load “bus wise” as if the CB-Tie of the multi-ended switchboards is open. Whereas “Switchboard” base load summary

calculates the total loads “switchboard wise” as if the CB-Tie of the multi-ended switchboards is close. For switchboardwith one bus only, the result of the load summary in “Bus” base and “Switchboard” base calculation are equal.

In the following procedure, only the “Bus” base load summary calculation will be considered. The target of calculationmay be the “All Buses” or “One Bus” only.

7.3.1 “All Buses” Load Summary

The “All Buses” option, as the title implies calculates the loading of all buses at once. Under this option you may alsoconsider the loading of each bus based on the directly connected loads or including the indirectly connected loads fromthe downstream switchboard(s) (Roll-up).

(1)  On the main menu select “Load Summary 

Run Load Summary…” or from the “Load Summary” toolbar, click

the “Run Load Summary” icon.

(2)  The “Load Summary – Switchboard*” dialog window will be displayed. On this window, do the following:

a.  Select “Bus” in the “Summary Base” frame.

 b.  Select “All Buses” and check “Roll-Up” in the “Targets of Load Summary” frame

c.  You may click the “Details…” button to verify how the electrical loads will be treated in the calculation.

d.  Select “Normal” in the “System Configuration” frame. See section 7.1.(2) and 7.2.(2).a for the significance of

system configuration.

e.  Select “Design” in the “Loading Category” frame.

f.  Select “Method <1>” in the “Total Load Calculation Method” frame.

g.  Click “Run” button to execute the calculation. The “Grid: Bus Digest” dialog window will be displayed.

 Note: For the description of the above options, refer to the on-line help by clicking the “Help” button.

*Toggles between “Switchboard”, “Bus”, and “Lumped Load” depending which option in the “Summary base” frame.

a

e

b

c

d

f

g

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 39/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 39 of 87 Ver.3.0.0 

h.  The “Grid: Bus Digest” dialog window shows the total demand of each bus. The components of the totaldemand i.e. Continuous, Intermittent, and Spare load are also shown. Click the “Summary View” button to see

the detail loading of each bus.

i.  The “Grid : All Bus” dialog window shows a page of the detail loading of each bus. You can change switch the page to another bus by clicking the appropriate tab at the bottom.

 Note: What you see on the screen can be printed directly by clicking the “Preview” button

 j.  The “Cancel” button on the “Grid : All Bus” and “Grid : Bus Digest” dialog windows respectively.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 40/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 40 of 87 Ver.3.0.0 

(3)  On the “Load Summary – Bus” dialog window, do the following:

a.  Select “Summary” in the “Report Type” frame.

 b.  Select “e-DPP Predefined Form” in the “MS Excel Form for Report Type ‘Summary’” frame.

c.  Click the “To Excel” button. Report will be generated in Excel.

d.  On the Excel report output, you can see the result of the load summary per bus similar to the one shown in step7.3.1.(2).i. You can change switch the page to another bus by clicking the appropriate tab at the bottom.

e.  After inspecting the result, close the Excel file without saving.

a

b

c

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 41/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 41 of 87 Ver.3.0.0 

7.3.2 “One Bus” Load Summary

The “One Bus” option calculates the loading of a particular bus considering only the directly connected loads.

(1)  On the “Load Summary – Bus” dialog window, do the following:

a.  Select “One Bus” inthe “Targets of LoadSummary” frame.

 b.  Select “SG-02A” busin the adjacent dropdown list

c.  Click the “Run” button to execute thecalculation. The“Grid : One Bus”dialog window will be displayed.

d.  The “Grid: One Bus” dialog window shows the total demand of bus “SG-02A”. Notice that only 2 loads wereconsidered since these are the only loads that are directly connected to the said bus. Refer to the one-linediagram on page 34.

e.  After inspecting the result, click “Cancel” button

(2)  Back to the “Load Summary – Bus” window, you may click the “To Excel” button to output the result in Excel asdesired. To end up, click the “Close” button.

(End of Chapter 6)

d

e

a

b

c

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 42/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 42 of 87 Ver.3.0.0 

8. Power Cable Sizing

In Section 4, a cable number was assigned to each load. The cable numbers were generated automatically when the“Data Filling” function was executed. In this section, the cable specification and size will be determined.

(1)  To view the power cables, on the main menu, select “Edit All Electrical Loads Input Data for Cable Sizing”

(2)  In Section 4.2.(2), the “Input Data for Cable Sizing” table was filtered by “Static Loads”. Clear the filter in order to

view all the power cables associated to the loads. On the “MDI Editor” toolbar, click “Filter” icon. The “Filter”dialog window will be displayed.

(3)  On the “Filter” dialog window, click “Clear” and “OK” button .

(4)  On the “Input Data for Cable Sizing” table, notice the following:

a.  Power Cable ID exists.

 b.  Cable size and specification not yet determined.

(5)  Click the control button on the “Input Data for Cable Sizing” table to close it.

(6)  On the main menu, select “Cable Management Power Cable Sizing…”. The “Cable Sizing Criteria” dialog

window will be displayed.

a b

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 43/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 43 of 87 Ver.3.0.0 

(7)  On the “Cable Sizing Criteria” window, do the following:

a.  In the “Allowable Voltage Drop (%)” frame, enter the values as indicated on the image.

 b.  Check the “Apply Default Minimum Cable Sizes” option. This option will override the calculated size thatmet the voltage drop and ampacity criteria but is smaller than the minimum required size.

c.  Click the “Show Min. Cable Size” button. The “Minimum Cable Sizes” dialog window will be displayed.

d.  On the “Minimum Cable Sizes” dialog window, do the following: (See image on the next page)

i.  Select “LV-1 (3ph)” in the “Motor Voltage Class”.

 Note: Some of the voltage classes are inactive because they are not used in the project since they were not set in the“Project : Electrical” dialog window (see section 2.1.4.(2))

ii.   Notice that the “Min Cable Size Table Exists” for the “LV-1(3ph)” has a check mark already. It meansthat a Minimum Cable Size selection table already exists. Click “Delete” button and “Yes” button to thesubsequent dialog window to confirm the deletion.

 Note: When the table is deleted, the Motor Voltage Class moves to “MV-1”. Select again “LV-1 (3ph)”.

iii.  Select “KW” in the “Motor Output Unit” frame.

iv.  Select “Metric” in the “Cable Size Unit” frame.

v.  In the “Material Types” frame, specify the cable specification as indicated on the image:

 Note: Only the “Cable Type” that satisfies the information in the “Cable Data” frame will be considered. The

“Applicable Standard” and “Rated Voltage” parameters were set in the “Project Standard” and “Project:Electrical”dialog windows respectively (see section 2.1.2.(2) and 2.1.4.(2)).

vi.  Click “Edit” button. The “Minimum Cable Sizes – Edit” dialog window will be displayed.

a

bc

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 44/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 44 of 87 Ver.3.0.0 

vii.  The table part (lower section of the dialog) of the “Minimum Cable Sizes – Edit” dialog window will be

initially populated with default kW ratings (KW column) and Cable Sizes (Cable Size column).

On this dialog window, do the following: (See image on the next page)

(a)  Click “Add” button.

 New row will beadded at the bottom.

(b)  In the “kW” and“Cable” size cell,enter the values asindicated on the

image.

(c)  Click “Save” buttonand “Yes” on thesucceedingconfirmation dialog

window.

(d)  Click “Close” button to close the

window and go back to the previousone.

iii

iv

i

v

vi

ii

(b)

(c) (d)

(a)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 45/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 45 of 87 Ver.3.0.0 

e.  Going back to the “Minimum Cable Sizes” dialog window, do the following:

i.  Click the “MV-1” voltage class.

ii.   Notice that the “Min Cable Size Table Exists” for the “MV-1” has a check mark already. As explainedabove on Section 8.(7).d.ii, a Minimum Cable Size selection table already exists. Click “Delete” button

and “Yes” button to the subsequent dialog window to confirm the deletion.

 Note: When the table is deleted, the Motor Voltage Class returns to “LV-1 (3ph)”. Select again “MV-1”.

iii.  In the “Material Types” frame, specify the cable specification as indicated on the image:

iv.  To calculate the minimum cable size, enter the following and then click the “Calc” button.

Conductor Type = Copper

Standard = IEC

Insulation Material = XLPE

Fault Clearing Time = 0.05 sec (assume CLF device will be used to protect the cable)

Fault Current = 25 kA

The result of the calculation is 39.37 mm2.

When the “MV-1” voltage class has been selected, the “Minimum Size Calculation By Fault Current” frame

 becomes active. This frame contains the 3rd criterion for sizing cable. In MV application, the use of smaller sizecable is technically possible because the operating current is generally small and the voltage drop and ampacitylimitation will allow such use. However, in the event of short circuit fault the cable may melt. Therefore, it is also

necessary to verify if the cable can withstand the destructive energy of the short circuit current.

v.  Click “Edit” button. The “Minimum Cable Sizes – Edit” will be displayed.

On the “Minimum Cable Sizes –Edit” dialog window (see image on next page), notice the minimum sizeof the cable for the entire range of the kW rating is “50 mm2”. This size is the next standard size(available from the library) of the size calculated in the “Minimum Size Calculation By Fault Current”.

ii

i

iii

iv

v

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 46/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 46 of 87 Ver.3.0.0 

vi.  On the “Minimum Cable Sizes – Edit” dialog box, do the following:

(a)   Notice the text box “Calculated Min. Size” in the “Cable” frame. It shows 39.37 mm2. This was

the size calculated in earlier in the “Minimum Size Calculation By Fault Current”. Based from this,the next standard size (available from the library) i.e. “50 mm2” was allocated to the entire range of

the kW ratings.

(b)  Click “Add” button

(c)  In the “kW” and

“Cable Size” cells,enter the values as

indicated on theimage.

 Note: At the moment

the “35” is selected,a message will

appear to warn youthat the size selected

is smaller than sizedescribed in (a)

above. Re-select“50” to concede to

the minimumrequirement.

(d)  Click “Save” button and “Yes”

on the succeedingconfirmationdialog window.

(e)  Click “Close” button to close the window and go back to the previous one.

vii.  Going back again to the “Minimum Cable Sizes” dialog window, you may specify minimum cable sizetable to “HV-2” and “LV (1ph)” voltage levels as well by doing similarly the procedures above. To

conclude, click the “Close” button.

f.  To continue with the Cable Sizing Criteria, check “Adjust by Ambient Temp (deg C)” option (see the image on

the next page).

This option will de-rate the cable ampacity by the temperature correction factor. The temperature correctionfactor will be calculated based on the ambient temperature of the installation’s surrounding medium and the

cable’s maximum conductor temperature and base ambient temperature.

g.  Select “20” (deg. C) in the “U/G” drop down list.

This is the prospective ambient temperature for the underground cable installation.

h.   Notice the “Temp Factor” column in the “U/G” section of the “Cable Application” frame. The values changeddue to step g.

(b)

(c)

(d)

(a)

(e)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 47/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 47 of 87 Ver.3.0.0 

i.  Select “50” (deg. C) in the “A/G” drop down list.

This is the prospective ambient temperature for the aboveground cable installation. Notice the “Temp Factor”column in the “A/G” section of the “Cable Application” frame. The values changed.

 j.  In the “Group Factor” column in the “U/G” section, enter 0.5 to all voltage classes. Note the grouping factor isto be manually determined outside of e-DPP.

k.  In the “Group Factor” column in the “A/G” section, enter 0.75 to all voltage classes.

l.  The “Application MF” is another ampacity de-rating factor. Just maintain the default values

m.  Select “DPP” in the “Manufacturer” drop down list. Currently, only “DPP” is available in the cable library.The cable sizing routine uses the library to extract information such as impedance to be able to perform thecalculation.

n.   Notice the “Frequency (Hz)”, “Units”, and “Standards” textboxes. Only the cables from the “DPP”manufacturer of the cable library that satisfy the specified “Frequency (Hz), “Units”, and “Standard” willconsidered.

 Note: The “Frequency”, “Units”, and “Standard” were set in the “Project : Standard” dialog window (see section 2.1.2.(2))

o.   Notice the “System kV” column. The voltages here were the ones specified in the “System Nominal (kV)”

column in the “Project : Electrical” dialog window (see section 2.1.4.(2))

 Note: Some of System voltages are blank (inactive) because they are not used in the project since they were not set in the“Project : Electrical” dialog window.

g

f

h

i

 jk

l

nm

o p

q

r s

t

u w

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 48/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 48 of 87 Ver.3.0.0 

 p.   Notice the “Cable Voltage” column. In each voltage level, only the cables from “DPP” manufacturer (see “p”on image above) of the cable library that satisfy the “cable voltage” will be considered. Similar to “Load kV”

column, the cable voltages here were the ones specified in the “Cable Voltage” column in the “Project :Electrical” dialog window (see section 2.1.4.(2)).

q.  Select all the active checkboxes in the “Run Sizing” column. Cable sizing will be performed to the loads thatfall under the particular voltage class.

r.  In the “Cable Type” under “U/G”, select the following respectively:

Voltage Class

System KV Cable Voltage

Cable Type

13.8 8.7/15kV Cu XLPE/SWA/PVC 3C

4.16 3.6/6kV Cu XLPE/SWA/PVC 3C

0.48 0.6/1kV Cu XLPE/SWA/PVC 3C

0.24 0.6/1kV Cu XLPE/SWA/PVC 2C

s.  In the “Cable Type” under “A/G”, select the following respectively:

Voltage Class

System KV Cable Voltage

Cable Type

13.8 8.7/15kV Cu XLPE/PVC 3C

4.16 3.6/6kV Cu XLPE/PVC 3C

0.48 0.6/1kV Cu XLPE/PVC 3C

0.24 0.6/1kV Cu XLPE/PVC 2C

t.  The options in the “Target Data for Cable Sizing” frame are self explanatory. Leave the default settings.

u.  Finally, click the “Run” button. The “Cable Sizing Results” will be displayed.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 49/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 49 of 87 Ver.3.0.0 

v.  On the “Cable Sizing Results” dialog window, do the following:

i.   Navigate the window to the right. The yellow area is the result of the calculation. Inspect the result.

ii.   Notice the load XP-5001A (row 46), the calculated size is “Err_3_2”. This error occurred because theload is a capacitor. Currently, e-DPP does not support cable sizing for such type of load

iii.  Click “Save” button to apply the result of the calculation in the project.

iv.  Click “Close” button to quit the window.

w.  Click “Close” button on the “Cable Sizing Criteria” to conclude.

i

iii iv

ii

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 50/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 50 of 87 Ver.3.0.0 

(8)  To verify that the power cable sizing routine applies the result to the project, on the main menu, select “Edit All

Electrical Loads Load Cables (Power and LCS)”. The “Load Cables (Power and LCS)” table will be displayed.

It indeed reflects the result of the power cable sizing.

(9)  Click the control button on the “Load Cables (Power and LCS)” table to close it.

(End of Chapter 8)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 51/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 51 of 87 Ver.3.0.0 

9. Cable Schedule & Summary

9.1 Cable ScheduleIn Section 4, Power, SH, LCS, and CCR cables where created for each load and in Section 8 the power cables were sized.

These cables reside in the “Electrical Load Schedule”. Let’s export these cables to the Cable Schedule.

(1)  On the main menu, select “Data Filling Cables…”.

(2)  On the “Data Filling – Cable Schedule” dialog window, do the following:

a.  In the “Target Cables” frame, check all the checkboxes. This means that all the Power, CCR, LCS, and SHcables from the Electrical Load Schedules are subject for export to the “Cable Schedule”

 b.  In the “Cable ID – Naming Convention” frame, do the following:

i.  Select “Transfer IDs from Electrical Load Schedule” option

ii.  Select “A,B,C (PM-1200A-P “A”)” in the “Suffix for Parallel Cables” sub-frame

iii.  Select “R,S,T (PM-1200A-P1“R”) in the “Suffix for Single Core Cables” sub-frame

 Note: In the Electrical Load Schedule, power cable IDs already exist. The selected option in “i” above will transfer these

IDs as they are in the Cable Schedule. However, if there are parallel cables and/or single-core cables in the former, thecable IDs of such will be refined to identify each physical cable with unique ID since the Electrical Load Schedule treats the

ID of a parallel cable (and/or single-core cable) common to each physical cable. In the cable schedule, each physicalcable should be assigned with ID. The sub-options “ii” and “iii” will handle the refinement.

For example, in the Electrical Load a 2 x 3/C parallel cable will be given ID “M-1234P” only. However, the 2 x 3/C cable is

actually composed of 2 physical cables. In the Cable schedule, these two physical cables will be assigned with ID say“M-1234P-1”, and “M-1234P-2”.

c.  Leave the options in the “Data Mapping” frame as they are. The mapping dictates which fields to be exportedfrom the Electrical Load Schedule to the Cable Schedule and to which fields in the later the fields in the formermust be assigned.

d.  Click “Fill Up” button

a

cb.i

b.ii

b.iii

d

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 52/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 52 of 87 Ver.3.0.0 

(3)  On the main menu, select “Edit Cable Cable Schedule (Form-1)”.

(4)  The “Cable Schedule (Form-1)” table will be displayed.

(5)  To generate the report, on the “MDI Editor” toolbar, click the “To Excel” icon.

(6)  The “To Excel” dialog window will be displayed. On this window, click “OK” button.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 53/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 53 of 87 Ver.3.0.0 

(7)  The Excel report will be generated as shown below.

(8)  Close the Excel file without saving.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 54/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 54 of 87 Ver.3.0.0 

9.2 Cable Summary

(1)  On the main menu, select “Cable Management 

Cable Summary…” or click the icon from the “CableManagement” toolbar.

The “Cable Summary” dialog window will bedisplayed. The upper portion of the window

contains the filtering criteria in the hierarchicalorder (left-to-right) “Rated VoltageTypes# of

ConductorsSize”. In the middle portion arethe command buttons and the lower portion is atable that shows the summary of cables.

(2)  In this window, do the following:

a.  In the upper portion, select

“0.6/1kVXLPE/SWA/PVC3CALL” in left-to-right order

 b.  Click “Run Summary” button. Noticethe summary of the cables in the table

c.  Click “To Excel”. The excel report will be generated as shown in the below

image. After inspecting the result,close the file without saving.

(3)  Click “Cancel” button to conclude.

(End of Chapter 9)

a

bc d

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 55/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 55 of 87 Ver.3.0.0 

10 Cable Sizing Chart

The Cable Sizing Chart is a chart of cables of appropriate sizes and installation lengths against different sizes of loads(Motor or Static load). This type of chart has been proven useful in the engineering workforce.

(1)  Select “Cable Management Cable Sizing Chart…” from the menu, or click on the icon from “CableManagement” toolbar. The following screen will appear.

(2)  The “Cable Sizing Chart – Example-Motor” will be displayed. On this window, do the following:

a.  Click “Save As…” button to create a new oneusing a copy of the currently active chart.

 b.  On the “File name” of the “Save As” dialogwindow, type “My Cable Sizing Chart” and click“Save” button.

c.  On the “General” Tab, enter the following in the“Project Information” frame:

Doc No. = My Cable Sizing Chart

Date = Jan. 1, 2008

Rev. No. = A

d.  Click the “Criteria” Tab

a

c

b

d

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 56/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 56 of 87 Ver.3.0.0 

e.  On the “Criteria” tab, select the following:

System Nominal Voltage = 0.48kV

System Frequency = 60Hz

Max. Voltage Drop @

 Normal Running = 5%

Max. Voltage Drop @

Motor Starting = 20%

Wiring System = 3ph-3W

Installation = Free Air

Ambient Temperature = 50 deg.C

Grouping Factor = 0.5

f.  Click “Load/Motor” tab.

g.  On the “Load/Motor” tab, select the following:

Load Type = Motor

Output Unit = KW

 Number of Phase = 3

Manufacturer = DPP

Enclosure Type = TEFC

Rated Voltage = 0.44

 Number of Poles = 2

The loads from the library that meet the abovecriteria will be extracted to the chart.

h.  Click “Cable” tab.

fe

g h

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 57/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 57 of 87 Ver.3.0.0 

i.  On the “Cable” tab, select the following:

Standard = IEC

Unit System = Metric

Manufacturer = DPP

Conductor Type = Cu

Rated Voltage = 0.6/1kV

Insulation Type = XLPE/PVC

 Number of Cores = 3

Type of Core = C

The cables from the library that meet the above criteriawill be extracted to the chart.

 j.  Click “Others” tab.

k.  On the “Others” tab, select the following:

 Number of Parallel Cables = 2

Minimum Cable Size of

Parallel Runs = 120

The above selections enable e-DPP to create a separate

chart for 2 cables in parallel to large loads and theminimum size of such cable is 120 mm2.

l.  Click “Save” button.

m.  Click “To Excel” to generate the chart.

n.  The Cable Sizing Charts will be displayed. See next page for the images. When done inspecting the chart,close the Excel file without saving.

o.  Click “Exit” button on the “Cable Sizing Chart – MyCable Sizing Chart” dialog window to conclude.

 ji

k

l m

o

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 58/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 58 of 87 Ver.3.0.0 

“eDPP” Sheet : Single Cable Configuration

“Parallel2” Sheet : 2 Cables Parallel Configuration

(End of Chapter 10)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 59/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 59 of 87 Ver.3.0.0 

11 Drum Schedule

(1)  On the main menu, select “Cable Management 

Drum Scheduling…” or click icon from the “CableManagement” toolbar.

(2)  The “Drum Schedule” dialog window will be displayed. On this dialog, do the following:

a.  Click “Edit Drum Specifications…” button.

 b.  e-DPP will summarize the cable (base on specification) from the Cable Schedule to the “Drum Specification –Edit” dialog window. See the image on next page.

The upper part of the dialog window is a table showing the summary of the cables. In the lower part are

command buttons.

On this window, do the following:

i.  In the “Drum Max. Length” frame, enter 1000 and click the “Update…” button. The value of the cellsunder the “Max. Length” of the table will be changed to “1000”.

By default, the value on these cells will be initially populated from the library (if the particular cablesexist in the library). Otherwise, a default of 1000 will be assigned.

ii.  In the “Spare Length” frame, enter 5% and click the “Update…”button. The values of the cells under

“Spare Length” column of the table will be changed to “50”

iii.  Click the “Rated Voltage” header repeatedly to sort the records in descending order by voltage.

a

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 60/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 60 of 87 Ver.3.0.0 

iv.  In the “Option” column of the table, for rows 1 to 3, select “Round Up” option.

“Round Up” optionWhen “Round Up” option is selected, the drum’s cable length will be dynamically calculated with maximum limit

equal to the length specified in the “Max.Length” column. The drum length will be equaled to the sum of the cablesegments plus the “Spare Length” plus a portion of the “Round Up Length”. See illustration below:

Drum Length = 830m

Round Up OptionIllustration

E

50m

A200m

B

470m

C

100m

Actual

Spare

60m

X = 10m

D

190m

ActualSpare

60m

Drum Length = 250m X = ((Round Up ((A+B+C)/F))*F) - (A+B+C)

= ((Round Up ((200+470+100)/20)) *20) - (200+470+100)

= ((Round Up (38.5)) * 20) - 770

= (39*20) – 770 = 780-700 = 10 

Drum No. 1

Drum No. 2

Given

Cable Segments Drum Criteria

A: Cable 1 = 200m D: Max. Length = 1000m

B: Cable 2 = 470m E: Spare Length = 50m

C: Cable 3 = 100m F: Round Up Length = 20m

D: Cable 4 = 190m

i

ii

iii

v

iv

vi

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 61/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 61 of 87 Ver.3.0.0 

v.  Leave the “Max.Len” option to rows 4 to 23 intact.

“Max.Len” option

When “Max.Len” option is selected, the drum’s cable length is automatically equal to the value specified in the“Max.Length” column. The actual drum’s spare will be dynamically calculated but its minimum value is the value

in the “Spare Length” column. See illustration below:

vi.  Click “Save” and “Close” button

c.  On the “Drum Schedule” dialog window, click “Run Drum Scheduling…” button. The “Run DrumScheduling” dialog window will be displayed.

A

200m

B

470m

C

100m

Actual Spare

230m

E

50m

Drum Length = D

1000m

Max.Len Option

Illustration

Given

Cable Segments Drum Criteria

A: Cable 1 = 200m D: Max. Length = 1000m

B: Cable 2 = 470m E: Spare Length = 50m

C: Cable 3 = 100m F: Round Up Length = 20m (Not Applicable)

D: Cable 4 = 190m

A

190m

Actual Spare

810m

E

50m

Drum Length = D

1000m

   D  r  u  m    N  o .   1

   D  r  u  m    N  o .   2

c

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 62/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 62 of 87 Ver.3.0.0 

d.  On the “Run Drum Scheduling” dialog window, do the following:

i.  Click the “Edit” button on the “Drum No. – Naming Convention” frame.

ii.  On the “Naming Convention – Edit” dialog window, express the drum numbering according thefollowing format:

E L T E C H S - - - -

Serial number format

000

Cable Size

0015 : 1.5mm2 0500 : 50mm2

0025 : 2.5mm2 0700 : 70mm20040 : 4mm2 0950 : 95mm2

0060 : 6mm2 1200 : 120mm2

0100 : 10mm2 1500: 150mm2

0160 : 16mm2 1850: 185mm2

0250 : 25mm2 2400: 240mm2

0350 : 35mm2 3000: 300mm2

4000: 400mm2

Cable Type

PPO : PVC/PVCXPO : XLPE/PVC

XPS : XLPE/PVC/PVC

Rated Voltage

LV : 0.6/1kV

MV : 3.6/6kV

HV : 8.7/15kV

Fig. A

i

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 63/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 63 of 87 Ver.3.0.0 

(a)  Assign the code to each fragment of the intended drum number according to Fig. A. Double click the“Code” column and enter (or select) the appropriate strings in the following sections respectively:

①  Rated Voltage

②  Cable Type.

③  Cable Size

④  User Text1.

⑤  Serial Number

     

  

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 64/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 64 of 87 Ver.3.0.0 

(b)  Assemble the fragments of the intended drum number as follows:

①  Point the mouse to the “User Text 1” and drag & drop to the 1st box in the “Convention Builder”frame

②  Point the mouse to the “Rated Voltage” area and drag & drop to the 2nd box in the “ConventionBuilder” frame.

③  Point the mouse to the “Cable Type” area and drag & drop to the 3rd box in the “ConventionBuilder” frame.

④  Point the mouse to the “Cable Size” area and drag & drop to the 4th box in the “ConventionBuilder” frame.

⑤  Point the mouse to the “Serial Number”, select “3” and drag & drop to the 5th box in the“Convention Builder” frame.

⑥  Click “Clear 6” button as this fragment is not necessary.

⑦  Uncheck the checkbox between “Clear 5” and “Clear6” button as this is not also necessary.

⑧  Check the checkbox between “Clear3” and Clear4” buttons to insert hyphen between the 4th and5th section of the intended drum number.

⑨  Similarly, check the checkbox between “Clear4” and Clear5” buttons.

⑩  Observe the sample drum number. This is the resulting pattern of the naming convention.

⑪  Click “Save” and “Close” button

 

   

 

 

 

 

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 65/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 65 of 87 Ver.3.0.0 

iii.  In the “Scheduling Objects” frame, do the following:

(a)  In the drop down lists on the left side of the “Scheduling Objects” frame, select the following in orderof “Top to bottom, Left to Right”:

AllCopper 3.6/6kVAllAllAllAll

 Notice the “List of Cable Specification” in the list box. The cables were filtered. Only the cables shown here

will be scheduled to the drum(s).

(b)  In the “Geographical Criteria” frame, select the following in order of “Top to button”:

ONSITEAllAllAllAll

The above selection means that the cables (if any) located in the ONSITE area regardless of their specific location

within the said area will be taken into consideration.

(c)  In the “Scheduling Scope” frame, select “Only cables without drum no” and check the “Includeexisting drums”.

Actually any of the two options (All cables …. or Only Cables ….) does not matter at this time since this is the first

attempt to do the drum scheduling. The sub-option “Include existing drums” means that if any of the existingdrums has abundant spare, the spare will be allotted to the unscheduled cables. For example, if a certain drum hasa spare of 300m cable and three unscheduled cables has length of 120m, 135m, and 180m respectively. The first

2 cables i.e. with 120m and 135m length will be schedule to the drum while the 3rd cable will be schedule to a newdrum since it cannot fit to the existing drum anymore.

(d)  In the “Orphan Control” frame, check “Substations” option.

In step “(a)” above, “All” has been selected in the “Substation” drop down list. This means that all the cables

within the “ONSITE” area regardless which substation they belong will be scheduled. The orphan control“Substation” option, however, will organize the scheduling by substation wise. For example, the cables that

 belong to Substation A will be placed to Drum A(s), the cables that belong to substation B will be placed to DrumB(s), and so on.

(c)

(d)

(b)(a)

(e)

(g)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 66/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 66 of 87 Ver.3.0.0 

(e)  Click “Run” button (see image on page 65).

(f)  Click “No” button on the subsequent dialog box. We will open the “Drum List Editor” dialog windowlater.

(g)  Click “Close” button (see image on page 65)..

e.  On the “Drum Schedule” dialog window, click “Edit Drum List…” button.

(f)

e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 67/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 67 of 87 Ver.3.0.0 

f.  On the “Drum List Editor” dialog window, do the following:

i.  Inspect the table (upper portion of the window). Six drums were created. The number of cables(segments) scheduled on each drum is shown in the “No. of Cables” column. For example, for drum

“ELTECHS-MV-XPS-1850-001”, 3 cables were scheduled.

ii.  In anticipation that a drum maybe accidentally damage due to mishandling during the construction,create a spare drum. Click the “Create New Drum” button.

iii.  The “Create New Drum No.” dialog window will be displayed. On this dialog, do the following:

(a)  Select/enter the following:

 New Drum No. = ELTECHS-MV-XPS-1850-005

Data Source = DPP

Conductor Type = CopperRated Voltage = 3.6/6kV

Cable Type = XLPE/SWA/PVC

 No. of Wires = 3/C

Cable Size = 185

Drum Length (m) = 1000

(b)  Click “OK” button

ii

ii

(a)

(b)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 68/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 68 of 87 Ver.3.0.0 

iv.  A new drum has been created with 100% spare.

v.  Click “Save”

vi.  Click “To Excel” button to generate the Drum List report in Excel. After inspection, close the excel filewithout saving.

vii.  Click “Close” button.

g.  On the “Drum Schedule” dialog window, click “Edit Drum Schedule…” button.

iv

vi v vi

g

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 69/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 69 of 87 Ver.3.0.0 

h.  Generate a drum schedule report for drum “ELTECHS-MV-XPS-1850-001”.

i.  Select the cable specs “Cu 3.6/6kV XLPE/SWA/PVC 3C-185 DPP” in the “List of Cable Specifications”

list box.

The objective in doing this is to filter the Drum list (shown in the “List of Drum” list box) by cable specification.Based on the given drum number the cable involved is a Medium Voltage- XLPE/PVC with 400mm2 size.

ii.  In the “List of Drum No.” list box, select “ELTECHS-MV-XPS-1850-001”.

 Notice the right pane of the window. The upper portion shows the information about the drum and the lower portionshows tabulate the cable segments assigned to the drum. In the table, you may edit the cable length,

origin/destination panel, location, etc.

iii.  Click “To Excel” button

iv.  The “Export Drum Schedule to MS Excel” dialog window will be displayed. On this window, to thefollowing:

(a)  Select “Current drum”option.

(b)  Click “OK” button

(c)  The Excel report will begenerated. After the

inspection of the result,close the file withoutsaving.

(d)  Click “Cancel” button toexit.

v.  On the “Drum Schedule – Edit” dialog window, click “Close” button.

i

ii

iii iv

(a)

(b) (d)

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 70/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 70 of 87 Ver.3.0.0 

i.  On the “Drum Schedule” dialog window, click “Move Drum Cables…” button.

 j.  Move cable “GM-4002B-PB” from drum “ELTECHS-MV-XPS-1850-001” to drum“ELTECHS-MV-XPS-1850-005”. See image on the next page.

i.  Select the cable specs “Cu 3.6/6kV XLPE/SWA/PVC 3C-185 DPP” in the “Cable Specifications” dropdown list. This is the specification of cable “GM-4002B-PB”.

 Notice the drums shown in “Drum Data (1)” and “Drum Data(2)” frames. They are being filtered by cable

specification.

ii.  Select the drum “ELTECHS-MV-XPS-1850-001” in the list box on the left side of the “Drum Data(1)”

frame.

 Notice the table on the right of the list box (Drum No.). It shows the cable segments currently assigned to theselected drum.

iii.  Select the drum “ELTECHS-MV-XPS-1850-005” in the list box on the right pane (“Drum Data(2)”frame).

 Notice the table on the left of the list box (Drum No.). It shows nothing since no cable has been assigned yet to theselected drum

iv.  Drag and drop cable “GM-4002B-PB” from the left table to the right table.

v.   Notice how the drum capacity varied with the movement of the cable.

vi.  Click “Save” and “Close” button to conclude.

vii.  To generate drum schedule report, refer to section 11.(2).h.

i

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 71/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 71 of 87 Ver.3.0.0 

k.  Click “Close” button on the “Drum Schedule” dialog window to exit.

(End of Chapter 11)

i

ii

iii

iv

vv

vi

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 72/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 72 of 87 Ver.3.0.0 

12. Control Signal Schedule

The operation of electrical equipment is triggered by the control signals coming from human intervention through localcontrol station and/or automatic controls through DCSs and/or PLCs. Hence, the preparation of control signal scheduleis indispensable.

The Electrical Load Schedule of e-DPP contains information about the electrical loads; ratings, types, switchboard/panelsource, etc. Therefore, we can populate the Control Signal Schedule with switchboards and loads information from the

Electrical Load Schedule.

(1)  On the main menu, select “Data Filling Switchgear/Mcc…” or click this icon from “Defaults & DataFilling” toolbar. The following message will be displayed.

(2)  Click “Yes” button on the “Data Filling – Switchgear / MCC Schedule” dialog window and the “OK” button on the

subsequent “Information” dialog window.

(3)  On the main menu, select “Edit Switchboard Schedule Control and Operation Signals”

(4)  The “Control and Operation Signals” table will be displayed as shown below. Notice the following:

a.  These fields were the ones updated from the Electrical Load Schedule. New items (records) will be added ifthe same will be found from the Electrical Load Schedule.

 b.  These fields are the associated control signals. They have been pre-defined.

a b

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 73/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 73 of 87 Ver.3.0.0 

(5)  In section 5.(2), motor “PM-8000” have been added in the Electrical Load Schedule. Let’s add this also to the

Control Signal schedule. First, close the “Control and Signals” table by clicking the control button on theupper-right corner of the table.

(6)  On the main menu, select “Edit Switchboard Switchboard Connected Loads”

(7)  On the “Switchboard Connected Loads” table, do the following:

a.  Enter Switchboard ID “MC-021” to item “PM-8000”.

 b.  Click “Save” on the “Edit” toolbar.

c.  Close the “Switchboard Connected Loads” table

(8)  On the main menu, select “Edit Switchboard Schedule Control and Operation Signals”.

(9)  The “Data Filling – Switchgear / MCC Schedule” dialog window be displayed since there was changes made in theElectrical Load Schedule, click “Yes” button to update the Control Signal Schedule.

a

c

b

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 74/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 74 of 87 Ver.3.0.0 

(10)  Subsequently, the “Control and Operation Signals” table will be displayed. The item “PM-8000” has been added inthe table. Assign control signals to item “PM-8000” using the configuration of one of the sequence diagrams from

the library by doing the following:

a.  Click the item “PM-8000”

 b.  On the “MDI Editor Toolbar”, click the “Library Quick Pick”

c.  On the “Library Quick Pick” dialog window, select “DPP-LVMCC-009” in the “Name Of The SequenceDiagram” list. Notice that the sequence diagram is very simple. It has start & stop inputs and running & stopoutputs only.

d.  Click “OK” button and “Yes” to the subsequent message.

a

b

c

d

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 75/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 75 of 87 Ver.3.0.0 

(11)  Notice that the “CCR Run Status” and “CCR Fault” signals and the “Sequence name” have been associated to“PM-8000”:

 Note: You can manually assign signals by checking the appropriate signal.

(12)  Click “Save” button on the “Edit” toolbar.

(13)  To verify how the “CCR Run Status” and “CCR Fault” signals came out, do the following:

a.  On the main menu, select “Library Motor Sequence…” or click on the icon from the “Library”toolbar.

 b.  On the “Library Edit – Motor Sequence Diagram”, do the following:

i.  Select “DPP-LVMCC-009” on the “Name Of The Sequence Diagram” drop-down list.ii.  Click the “CCR / LP (PLC)” tab.

iii.   Notice in the “To CCR” frame, the digital “Running Status” and “Fault” are checked.

iv.  After the inspection, click “Close” button

iii

iii

iv

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 76/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 76 of 87 Ver.3.0.0 

(14)  To generate the Control Signal Schedule Excel report, do the following:

a.  on the “MDI Editor” toolbar, select

“To Excel” icon

 b.  The “To Excel” dialog window will be

displayed. On this window, click“OK” button.

(15) The Excel report will be displayed. After the inspection close the file without saving.

(16) Close the “Control and Operation Signals” table by clicking the control button on its top-right corner.

(End of Chapter 12)

a

b

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 77/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 77 of 87 Ver.3.0.0 

13. MCC Schedule

Motor Control Center is an assembly of one or more enclosed section having a common power bus and principallycontaining motor control units. Typical MCC’s front layout is as shown below:

The MCC’s motor control units (and their components) are specified in the MCC Schedule of e-DPP.

In the following procedure, we will assign the motor “PM-8000” to unit “3G” of “MCC-021”. The 3G unit’scomponents are MCCB (400AT/AF), Contactor (400A), CT (300/5), Gnd CD (50/5), etc.

(1)  On the main menu, select “Edit 

Switchboard Schedule 

LV MCC Schedule”.

(2)  The “LV MCC Schedule” table will be displayed. Locate the Item No. “PM-8000” and enter the following:

a.  Unit No.   3G

 b.  MCCB   400

c.  Contactor   400

d.  CT   300/5

A

B

C

D

E

F

G

1 2 3 4

1A

1B

1C

1D

1E

1F

1G

2A

2B

2D

2E

2G

3A

3C

3D

3G

4A

4B

4C

4D

4E

4F

4G

 

a b c d

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 78/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 78 of 87 Ver.3.0.0 

(3)  On the “Edit” toolbar, click the “Save” button.

(4)  To generate the MCC Schedule Excel report, do the following:

a.  On the “MDI Editor” toolbar, select “To Excel” icon

 b.  The “To Excel” dialog window will bedisplayed. On this window, click “OK”

 button.

(5)  The Excel report will be displayed. After the inspection close the file without saving.

(6)  Close the “LV MCC Schedule” table by clicking the control button on its top-right corner.

(End of Chapter 13)

b

a

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 79/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 79 of 87 Ver.3.0.0 

14. Project Editor

Project Editor is an Explorer-like tree window where all electrical components/equipment can be alternatively accountedaccessed, and edited. On this window, the active library file and its corresponding path can also be easily verified.

The “Project Editor” window opens as soon as the project is opened by default. If it is close, you can open it from themain menu “Window Project Editor”.

 Note: Currently, the data on the Project Editor is updated dynamically when the changes is made in the “Property List” window.

Conversely, if changes are made in a “Table” editor (e.g. “Electrical Load Schedule (Form-1)”) the “Project Editor” does not updateautomatically. To refresh the data, close and re-open the window.

(1)  In the following procedure, we will modify the kW output rating of the following motors:

•  EF-2612 from 0.2 kW to 0.37kW

•  EF-2614 from 0.4kW to 0.75kW

a.  On the “Project Editor” window, expand the “Electrical Load” and “Induction Motor” nodes.

 b.  Select “EF-2612”, right-click and select “Properties…” The “Property List –EF-2612” window will bedisplayed..

aa

bb

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 80/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 80 of 87 Ver.3.0.0 

c.  Click the “Output” cell and change the valuefrom 0.2 to 0.37.

d.  Click the navigation dropdown list and selectmotor “EF-2614”. Click “Yes” button on the

subsequent window.

e.  Similar to step “c”, click the “Output” cell andchange the value from 0.4 to 0.75 for EF-2614.

f.  Click “Save” and “Close” button to exit

(2)  From the “Project Editor” window, table editors (i.e. templates) could also be opened. For example, select motor“AM-2001”, right-click and select “Open-Template…”. A pop-up command list will show all the templates wherethe motor AM-2001 is associated. At your will, you may open any templates to verify the function.

(End of Chapter 14)

c

d

f

e

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 81/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 81 of 87 Ver.3.0.0 

15. Revision Control

The revision control records the changes made on the project. The recording of the changes is particular to a template(table editor) under assessment.

(1)  Implement a revision to “Electrical Load Schedule (Form-2)” table.

a.  On the main menu, select “Revision Revision Up…”

 b.  The “Revision Up” dialog will be displayed. On this dialog do the following:

i.  Select the “Schedule Template” since the “Electrical Load Schedule (Form-2) is of this style.

ii.  Select “DPPElecLoad2”

 Note: “DPPElecLoad2” is the absolute name of the “Electrical Load Schedule (Form-2)” table. The latter is beingthe title of the former. See Fig. 1 on page 85.

iii.  Select “Official” in the Revision Type under “Revision No. Control” frame

iv.  Click “Rev. Up” button. The “New Revision Information” frame will be displayed below the lower

 portion of the dialog window.

v.  Populate the information about the revision as shown.

vi.  Click “OK” button and “Yes” to the subsequent confirmation message. Now, everything that have beenmade in the “Electrical Load Schedule (Form-2)” table up to this moment hold the revision “0” mark.

vii.  Click “Close” button”.

i

ii

iii

iv

v

vi

vii

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 82/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 82 of 87 Ver.3.0.0 

c.  On the main menu, select “Revision Revision View…”.

d.  Select “DPPElecLoad2”. Notice that the revision information. You may modify the revision information in

the cells with white background.

e.  Click “Close” button.

(2)  Modify some parameters in the “Electrical Load Schedule (Form-2)” table.

a.  On the “Project Editor”, select “Electrical Load Induction Motor AM-2001 Electrical Load Schedule

(Form-2)”.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 83/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 83 of 87 Ver.3.0.0 

 b.  On the “Electrical Schedule (Form-2)” table, change the output of motor AM-2001 from 22kW to 15kW.

c.  On the “Edit” toolbar, click the “Save” icon

(3)  Promote the revision of the “Electrical Load Schedule (Form-2)” table.

a.  On the main menu, select “Revision Revision Up…”

 b.  The “Revision Up” dialog will be displayed. On this dialog, perform the steps similar to the ones in section

15.(1).b.

MK LM KK

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 84/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 84 of 87 Ver.3.0.0 

c.  On the main menu, select “Revision Revision List…”.

d.  The “Revision List” dialog will be displayed. On this dialog do the following:

i.  Select the “Schedule Template”.

ii.  Select “DPPElecLoad2”

iii.  Confirm the “From” and “To” in the “Specify Rev. No.” drop-down list are “0” and “1” respectively.

iv.  Select “All” in the “Status” frame. This means all type of modification i.e. changes, additions, deletionswill be enumerated.

v.  Click “OK” button.

vi.  The modification made in the “Electrical Load Schedule (Form-2) from revision 0 to 1 will beenumerated in the table at the lower portion of the dialog window.

Remember, in section 15.(2), the rating of AM-2001 have been changed from 22 to 15. This changes isnow shown on the table.

vii.  Click “To Excel” button to generate the Revision List report.

viii.  The excel report will be generated as shown on the next page. After the inspection, close the file without

saving.

ix.  Click “Close” button to exit.

i

ii

iii

v

vi

vii

iv

viii

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 85/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 85 of 87 Ver.3.0.0 

Revision List Excel Report

(End of Chapter 15)

 Note: To open “Template List”, on the main menu select “TemplateTemplate List…”

Fig. 1

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 86/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Eltechs Engineering & Consulting Co., Ltd. Page 86 of 87 Ver.3.0.0 

16. ETAP Interface

e-DPP has been designed and developed with emphasis to data migration to ETAP® program (one of the world’s leading power system analysis software). In other words, e-DPP data exchange to ETAP is seamless and easy.

To transfer e-DPP data to ETAP, on the main menu of e-DPP program, select “File Export ETAP Interface…”

The “Export to ETAP” dialog window will be displayed as shown below. On this window, you may select theappropriate options which to apply in the data migration. Once the data exchange is executed, an intermediate databasewill be generated which in turn will be imported to ETAP.

Fig. 2 shows a sample one-line diagram of a project in ETAP that was automatically generated through data exchangefrom e-DPP.

Please refer to “ETAP” User Guide for details.

7/23/2019 Basic Training Guide

http://slidepdf.com/reader/full/basic-training-guide 87/87

e-DPP ( electrical - Data Processing Program )

Basic Training Guide

 

Fig. 2

(End of Chapter 16)