bat sizing rev 1.3 1 show information... navigation links: move the cursor across the links and wait...

60
Bat sizing rev 1.3 1 Show information... Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key. Click the APC logo link to jump back to the previous showed slide. Click the left margin area to jump to the index (“List of contents”) From the index -links, you may jump to any other subjects. - use the APC-return logo to return to the index slide again .

Upload: preston-perry

Post on 11-Jan-2016

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

1

Show information...Show information...

•Navigation links: Move the cursor across the links and wait for the “hand” symbol

•- then click left mouse key.

•Click the APC logo link to jump back to the previous showed slide.

•Click the left margin area to jump to the index (“List of contents”)

•From the index -links, you may jump to any other subjects.

• - use the APC-return logo to return to the index slide again .

Page 2: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

2

BatteryBattery

SizingSizing

Page 3: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

3

List of contentsList of contents

Head linesHead lines

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 4: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

4

Battery load...Battery load...

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 5: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

5

UPS inverter

Battery load

Calculate the battery load...Calculate the battery load...

Pbat

+-

D C

A C

UPS load = Pout

Pbat = the battery load powerPout = the output load power

Inv. = the inverter efficiency

PF = The power factor

What is the required battery load - for a given UPS load…?

*

PBat = Pout x PF / Inverter

From kVA to kWCal. the Battery load

Cal

cula

tin

g

Page 6: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

6

What is the total battery load (kW)…?

Battery load

Battery load - example...Battery load - example...

Pbat

+-

PBat = Pout x PF / Inverter

PBat = 56 x 0,8 / 0,95 = 47,2 kW

Example:

UPS load/ Pout……..…………....56kVA

UPS load, PF…………………......0,8

UPS inverter efficiency………....95% or 0,95

You need to know...You need to know...

*

Battery load

Total load is the three phase loads added together

Page 7: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

7

Ncell = Number of battery cells to be used

Vlow = The lowest DC voltage

(before inverter shut down will take place)

Inv. = The inverter efficiency with the actual load.

Ich-max = The max. battery charging current.

Parameters...Parameters...

For the most used battery type - the lead acid - the following parameters are used:

For a specific Silcon DP300E type and an actual output load,the above data can be found in the Quick Reference Manual, section “DC Data”.

Battery load

Page 8: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

8

Battery Bank...Battery Bank...

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 9: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

9

Battery bank

Battery cells and blocks...Battery cells and blocks...

+ -

+ -

+ -

1 x 2 volt = 2 V

- battery cell

3 x 2 volt = 6 V

- battery block

6 x 2 volt = 12V

- battery block

*

Page 10: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

10

Battery bank

Battery string...Battery string...

Serial connected battery blocks - forms a battery string.

More strings can be connected in parallel - to increase the battery bank capacity.

- - -+ + +

- - -+ + +

Page 11: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

11

Battery pack for DP300E...Battery pack for DP300E...

How to make a battery pack for DP300E…?

2 x192 battery cells = 2 x 384 VDC2 x192 battery cells = 2 x 384 VDC

2 x 32 battery blocks of 12V = 2 x (32 x 12 V) = 2 x 384 VDC2 x 32 battery blocks of 12V = 2 x (32 x 12 V) = 2 x 384 VDC

Battery bank

12 V12 V- - -+ + +12 V12 V

- - -+ + +12 V12 V

32 blocks of 12V

32 blocks of 12V

Page 12: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

12

Cell Specification... Cell Specification...

+ -

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 13: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

13

Cell specifications

Cell LOAD... Cell LOAD... Actual Cell LOAD / Matching Battery SizeActual Cell LOAD / Matching Battery Size

Calculating the watt/ cell capacity…?

Cell load = Total battery load / Number of cells

Example1: 47.200W / (2 x 192 cells) = 123 W/cell

During battery operation the load on the battery bank is supposed to be constant at the max. specified load…

*

Watt+ -

Example 1:

PBat = Pout x PF / Inverter

PBat = 56 x 0,8 / 0,95 = 47,2 kW

Page 14: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

14

Lowest cell voltage...Lowest cell voltage...

The lowest battery voltage - “when the back-up time expires”

- is defined from the battery spec. and programmed into the UPS

Cell-end voltage - and how to find it…?

Example 1:

Vcell low = 2X326V / 2X192 cells =

1,7V/cell

Vcell low = VInverter low / number of cellsCell voltage

Time

Cell specifications

1,7 V

Page 15: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

15

Example 2...Example 2...

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 16: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

16

A customer want to protect a 3x400V computer load…- with an 10min.

UPS Back-up time

The highest phase current is determine the Silcon DP300E size.Silcon DP380E has a 400V full load output current at 3 x 115A and is therefore sufficient for IL2

Choice: Silcon DP380E

Example 2 Example 2

Result from measuring- full load current on the 3 phases...

IL1 100A PF 0,8

IL2 112A PF 0,9

IL3 105A PF 0,8

- example 2

Page 17: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

17

Calculating the total power...

Line to line voltage……...400V

Line to neutral voltage….230V

PL1 = 230 x 100 x 0,8 = 18.400W

PL2 = 230 x 112 x 0,9 = 23.184W

PL3 = 230 x 105 x 0,8 = 19.320W

Total =

60.904W

- or close to 61kWPBatt = 61 / 0,94 = 64.890 W from 384 cells

Pcell = 64.890 / 384 = 169W/cell VLow = 2 x 326 / 384 = 1,7V/cell

Example 2 Example 2 - calculating cell load- calculating cell load

- and lowest cell voltage - and lowest cell voltage

Required data...

Silcon DP380E max load…..…80kW

Actual load……………………..61 kW

Load percentage………………75%

Inverter efficiency:

Linear load……………….…….96%

SMPS load……………….…….94%

- example 2

Example 2 - Load spec.Voltage 3x400V

IL1 100A PF 0,8

IL2 112A PF 0,9

IL3 105A PF 0,8Back-up time 10 min.

Page 18: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

18

Type UPS12-140: Capacity……….174W/cell Back-up time…..10 min. End point cell voltage……1,7V

Example 2Example 2- choosing battery- choosing battery

Min.Min.TypeType 5 10 15 20

UPS12-140 254 174 137 111

UPS12-170 272 204 165 136

UPS12-200 360 200

Data sheet example: JOHNSONS CONTROL

- fits the demand of 169 W/cell.

- example 2

Example 2 - Load spec.Voltage 3x400V

IL1 100A PF 0,8

IL2 112A PF 0,9

IL3 105A PF 0,8Back-up time 10 min.

Page 19: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

19

UPS specificationsUPS specifications concerning batteries...concerning batteries...

Common Data from Quick reference:

Nominal voltage 2x384V Number of battery cells 2x192 pcs. Charging window float 2x(410V - 460V) Factory setting:

2x438V Charging window boost 2x(438V - 460V) Factory setting:

2x438V Low bat. warning window 2x(336V - 384V) Factory

setting: 2x346V Low bat. shut down window 2x(316V - 336V) Factory

setting: 2x326V

- example 2

Page 20: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

20

Battery ambient temperatureBattery ambient temperature

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 21: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

21

Battery…Battery…Capacity and life timeCapacity and life time

°C

20

21

22

23

24

25

Typ. battery specification temperature

26

27

28

29

30Ambient temperature - Battery capacity…General rule:

- if ambient temp. is lowered from 25 °C to 20 °C- The battery must be 4% oversized

Ambient temperature - Battery life time…

General rule:- if ambient temp. increases 10 °C - The battery life time will be halved.

But temperature compensated charging voltage - as in the Silcon DP300E series- reduces the influence to the half. +

4% oversized

+ -

Battery amb. temperature

Page 22: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

22

Battery life time...Battery life time...

High temperature

Poor charge control

80%100% Capacity

The capacity of the battery falls with the age.

The point where 80% is left is often used to define the life time.

20% oversizing is required for the W/cell if not included from manufacture

Ageing

End of life time

Battery amb. temperature

Page 23: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

23

Battery rechargingBattery recharging

2 4 6 8

0

10 hours

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 24: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

24Recharging time is often specified 4-10 hours

Battery recharging

DP300E rechargingDP300E recharging normal capacity on batteries...normal capacity on batteries...

2 4 6 8

0

10 hours

0

1 hour

Back-up time is often specified less than 1 hour

Normal charging current

Page 25: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

25

The following broad rule can be used for batteries wherealmost all the energy is taken out

- this is the case with back-up times of 2-3 hours or more:

FOR RECHARGE TIMES IN THE AREA OF 4 - 6 HOURS: - it last t hours to recharge the battery to 80% capacity,3xt to reach 90% and 8xt to reach 100%

FOR RECHARGE TIMES IN THE AREA OF 10 - 12 HOURS:

- it last 2xt to reach 90% and 4xt to reach 100%

But how to find t...?But how to find t...?

General rule about recharging...General rule about recharging...

Battery recharging

Page 26: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

26

Recharging general rule ...Recharging general rule ...

FOR RECHARGE TIMES IN THE AREA OF 4 - 6 HOURS:

1 x t 3 x t 8 x t

1009080

Battery recharging

Page 27: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

27

The following can be assumed:

We have to put the same energy back into the battery as taken out + the losses arising by rechargingThe losses by recharging are about 10%...

The Silcon DP300E will recharge with max. charging current, at least until 80% of the energy has been restored

The battery cells has a average voltage of 2V

Pbat

+ -Pbat outPbat in

100% 90%

Battery losses...Battery losses...

Battery recharging

Page 28: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

28

If 4 hours back-up time is required...

- it will take a week to reach

the 100 % battery capacity level

by too low charging current

One week...

One week charging …?One week charging …?

Battery recharging

Page 29: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

29

Example: DP310E output load 8kW (3-phase) Back-up time 4 hours Max. 12 hours recharge time to 90% required.

Let´s take an example...Let´s take an example...

Energy taken from battery during battery operation:Output load/DP310E bat.opr.efficiency = 8/0,9=8,9kWDischarge current=8900W/(2Vx384) cells=11,6AEnergy used 11,6x4 hours=46,4AH

Energy to be recharged=46,4/0,9=51,5AH

If 90% is to be restored within 12 hours, 80% has to takeplace within 12/2=6 hours.

Battery recharging

Page 30: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

30

If 51,5AH has to be restored within 6 hours…the charging current must be 51,5/ 6 = 8,6AThis gives a required charging power of 384 x 2 x 8,6 = 6,6 kWAs the standard DP300E has a charging capacity equal to 10% of the output power - The DP380E has to be used

But as the standard programming of the DP300E can be changed into a special setting - giving the double charging capacity

With a corresponding reduction of the max. output power - a DP340E can be used

8kW is then available for charging

A max. output load of 36kW is more than enough for the actual 8kW load.

A separate charger might be a better economic solution

Let´s take an example...Let´s take an example...

Battery recharging

Page 31: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

31

Battery parallel connection...Battery parallel connection...

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 32: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

32

Parallel stringsParallel strings

Numbers of blocks, depends on type of battery pack and parallel strings.

The battery type UPS12 have 6 cells of 2 volt and the UPS6 have 3 cells of 2 volt

If the W/cell is above numbers in table it is necessary to make parallel strings

Cellload [W/ cell] With ___ parallel string = = = _____ [W/ cell] Number of strings

The numbers of cells in the Silcon DP300E series is...

2 x 192 pcs. = total 384 cells.

- therefor divide the total 384 with the number of battery cells

UPS12 = 384 : 6 = 64 battery block

UPS 6 = 384 : 3 = 128 battery block

And then multiply this with the number of strings

Page 33: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

33

Example 3...Example 3...

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 34: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

34

Example 3 Example 3 Specify the battery...Specify the battery...

Example 3

UPS type: DP3120E Total load: 110 kVA PF: 0,8 SMPS Requested back-up: 20 min

Specify the battery…!

Data:

Page 35: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

35

Example 3 Example 3 Specify the battery...Specify the battery...

Transfer output power to kW´s, if information is in kVA or Amps…

PTotal W 88.000% load on UPS = x 100 = x 100 = 73,3

[%] UPS1/1 load W 120.000

PTotal W = PTotal VA x PF = 110.000 [VA] x 0,8 = 88.000 [W]

Calculate the percentage of the load compared with the capacity of the UPS...

Example 3

Example 3 - Battery…?.

UPS type DP3120E

Total load 110 kVA

PF 0,8 SMPS

Back-up time 20 min.

Page 36: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

36

Inverter DataInverter Data

25% 50% 75% 100% 25% 50% 75% 100%DP310E 88,8% 92,6% 93,0% 93,5% 85,5% 89,0% 89,5% 90,0%DP320E 89,3% 93,1% 93,5% 94,0% 86,0% 89,3% 90,0% 90,5%DP340E 91,0% 94,0% 94,5% 94,5% 88,0% 90,1% 91,7% 92,3%DP360E 93,0% 94,5% 95,5% 96,0% 89,0% 92,0% 92,8% 93,2%DP380E 93,2% 95,5% 96,0% 96,1% 90,0% 92,8% 93,2% 93,5%DP3120E 88,6% 93,0% 94,2% 94,6% 89,7% 92,5% 92,9% 93,2%DP3160E 91,2% 93,9% 94,6% 94,7% 90,0% 92,8% 93,2% 93,5%DP3240E 90,0% 94,2% 95,2% 95,4% 88,5% 92,0% 93,0% 93,2%DP3320E 92,2% 95,0% 95,4% 95,5% 90,0% 92,8% 93,2% 93,5%DP3480E 91,7% 94,5% 94,8% 95,0% 90,0% 92,8% 93,2% 93,5%

Linear Load SMPS Load Load DP

Efficiencies DC to AC DP 3120 E and 73,3 % SMPS loaded

Find the efficiencies DC to AC percentage..!

Example 3

Page 37: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

37

Example 3 Example 3 Specify the battery...Specify the battery...

Calculate the battery load and the cell load

- decide if parallel strings is needed...

BatteryLoad [W] 94.725Cell load = = = 247 [W/ cell]

Number of cells 2 x 192

PTotal [W] 88000Battery load = 100 = x 100 = 94.725 [W]

Inv. eff. [%] 92,9

Cell load:

Battery Load:

Efficiencies DC to AC (table)= 73,3 % (SMPS-% load of the UPS) = 92,9 inv. Eff %.

Example 3

Example 3 - Battery…?.

UPS type DP3120E

Total load 110 kVA

PF 0,8 SMPS

Back-up time 20 min.

Page 38: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

38

Example 3 Example 3 Specify the battery...Specify the battery...

Find the necessary battery type, table Johnson battery.

247 [W/cell] in 20 min...

Min.Min.TypeType 5 10 15 20 30 40 50 60 90

UPS12-140 254 174 137 111 82 54 53 46

UPS12-170 272 204 165 136 105 86,6 74,4 65 46,7

UPS12-200 360 251 200 167 124 100 73 53

UPS12-270 457 336 263 218 163 132 111 94

UPS12-310 560 400 304 248 184 150 125 108

UPS12-370 610 450 355 293 219 171 142 123

UPS12-475 725 555 460 375 302 245 205 178

UPS6-620 890 720 600 520 405 332 280 243 170

Example 3

Example 3 - Battery…?.

UPS type DP3120E

Total load 110 kVA

PF 0,8 SMPS

Back-up time 20 min.

Page 39: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

39

Battery pack Battery pack specifications...specifications...

Find the weight and dimension of the battery pack

MODELWATT/CELL15 Min./167

V/C

LENGTH

IN (MM)

WIDTH

IN (MM)

HEIGHT

IN (MM)

WEIGHT

LBS. (KGS)

UPS12-140 140 7.78 (197) 5.22 (132)) 7.26 (184) 27 (12)

UPS12-170 170 8.99 (228)) 5.47 (139) 8.74 (222) 40 (18)

UPS12-270 270 10.30 (261) 6.83 (173) 8.74 (222) 57 (26)

UPS12-310 310 12.08 (307) 6.87 (174)) 9.51 (241) 66 (30)

UPS12-370 370 13.51 (343) 6.76 (172) 9.48 (240) 75 (34)

UPS12-475 475 13.57 (344) 6.76 (172) 10.93 (276) 105 (48)

UPS12-520 620 12.65 (321) 7.00 (177) 10.21 (259) 72 (33)

Example 3

Example 3 - Battery…?.

UPS type DP3120E

Total load 110 kVA

PF 0,8 SMPS

Back-up time 20 min.

Page 40: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

40

Example 3 Example 3 Specify the battery...Specify the battery...

Battery Specification/Pack

Type UPS 12 - 310

Make Johnson

Number of cells 384

Cell load 247 W/cell

Min. cell voltage 1,7 V

Back-up time 20 min.

Number of blocks 64

Block dim. (HxWxL) 241x174x307 mm

Total weight 1920 kg

Solution...

Example 3

Example 3 - Battery…?.

UPS type DP3120E

Total load 110 kVA

PF 0,8 SMPS

Back-up time 20 min.

Page 41: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

41

Your turn...

Now - your turn...

Page 42: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

42

Task 1Task 1

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 43: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

43

Task 1Task 1Specify the battery...Specify the battery...

UPS type: DP380E Total load: 66 kW PF load: 1 Requested back-up: 10 min

Specify the battery…!

Data:

Task 1

Page 44: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

44

Task 1Task 1

PTotal W 66.000% load on UPS = x 100 = x 100 = 82,5

[%] UPS1/1 load W 80.000

PTotal W = PL1 + PL2 + PL3 = 66.000 [W]

Total Load:

UPS load:

Task 1 UPS type: DP380E Total load: 66 kW PF load: 1 Back-up time: 10 min

Task 1

Page 45: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

45

Inverter DataInverter Data

Find the efficiencies DC to AC percentage..!

25% 50% 75% 100% 25% 50% 75% 100%DP310E 88,8% 92,6% 93,0% 93,5% 85,5% 89,0% 89,5% 90,0%DP320E 89,3% 93,1% 93,5% 94,0% 86,0% 89,3% 90,0% 90,5%DP340E 91,0% 94,0% 94,5% 94,5% 88,0% 90,1% 91,7% 92,3%DP360E 93,0% 94,5% 95,5% 96,0% 89,0% 92,0% 92,8% 93,2%DP380E 93,2% 95,5% 96,0% 96,1% 90,0% 92,8% 93,2% 93,5%DP3120E 88,6% 93,0% 94,2% 94,6% 89,7% 92,5% 92,9% 93,2%DP3160E 91,2% 93,9% 94,6% 94,7% 90,0% 92,8% 93,2% 93,5%DP3240E 90,0% 94,2% 95,2% 95,4% 88,5% 92,0% 93,0% 93,2%DP3320E 92,2% 95,0% 95,4% 95,5% 90,0% 92,8% 93,2% 93,5%DP3480E 91,7% 94,5% 94,8% 95,0% 90,0% 92,8% 93,2% 93,5%

Linear Load SMPS Load Load DP

Efficiencies DC to AC DP 380E and 82,5% Linear

Task 1 UPS type: DP380E Total load: 66 kW PF load: 1 Back-up time: 10 min

Task 1

Page 46: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

46

Task 1Task 1

Calculate the battery load and the cell load

- decide if parallel strings is needed...

BatteryLoad [W] 68.750Cell load = = = 179 [W/ cell]

Number of cells 2 x 192

PTotal [W] 66.000Battery load = 100 = x 100 = 68.750 [W]

Inv. eff. [%] 96

Cell load:

Battery Load:

Efficiencies DC to AC (table)= 73,3 % (linear-% load of the UPS) = 96 inv. Eff %.

Task 1 UPS type: DP380E Total load: 66 kW PF load: 1 Back-up time: 10 min

Task 1

Page 47: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

47

Results of task 1Results of task 1

Battery Specification/Pack

Type UPS 12 - 170

Make Johnson

Number of cells 384

Cell load 179 W/cell

Min. cell voltage 1,7 V

Back-up time 10 min.

Number of blocks 64

Block dim. (HxWxL) 222 x 139 x 228mm

Total weight 1152 kg

Results...

Task 1 UPS type: DP380E Total load: 66 kW PF load: 1 Back-up time: 10 min

Task 1

Page 48: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

48

Task 2Task 2

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 49: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

49

Task 2Task 2Specify the battery...Specify the battery...

UPS type: DP3160E Total load L1: 50 kVA, PF 0,9 SMPS Total load L2: 40 kVA, PF 0,8 SMPS Total load L3: 45 kVA, PF 0,8 SMPS Back-up time: 15 min

Specify the battery…!

Data:

Task 2

Page 50: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

50

Task 2Task 2

PTotal W 113.000% load on UPS = x 100 = x 100 = 70,6

[%] UPS1/1 load W 160.000

PL1 = PL1 x PF1 = 50kVA x 0,9 = 45.000 [W]PL2 = PL2 x PF1 = 40kVA x 0,8 = 32.000 [W]PL3 = PL3 x PF1 = 45kVA x 0,8 = 36.000 [W]

PTotal W = PL1 + PL2 + PL3 = 113.000 [W]

Total Load:

UPS load:

Task 2 UPS type: DP3160E Total load L1: 50 kVA, PF 0,9 SMPS Total load L2: 40 kVA, PF 0,8 SMPS Total load L3: 45 kVA, PF 0,8 SMPS Back-up time: 15 min

Task 2

Page 51: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

51

Inverter DataInverter Data

Find the efficiencies DC to AC percentage..!

Efficiencies DC to AC DP 3160E and 70,6% SMPS

25% 50% 75% 100% 25% 50% 75% 100%DP310E 88,8% 92,6% 93,0% 93,5% 85,5% 89,0% 89,5% 90,0%DP320E 89,3% 93,1% 93,5% 94,0% 86,0% 89,3% 90,0% 90,5%DP340E 91,0% 94,0% 94,5% 94,5% 88,0% 90,1% 91,7% 92,3%DP360E 93,0% 94,5% 95,5% 96,0% 89,0% 92,0% 92,8% 93,2%DP380E 93,2% 95,5% 96,0% 96,1% 90,0% 92,8% 93,2% 93,5%DP3120E 88,6% 93,0% 94,2% 94,6% 89,7% 92,5% 92,9% 93,2%DP3160E 91,2% 93,9% 94,6% 94,7% 90,0% 92,8% 93,2% 93,5%DP3240E 90,0% 94,2% 95,2% 95,4% 88,5% 92,0% 93,0% 93,2%DP3320E 92,2% 95,0% 95,4% 95,5% 90,0% 92,8% 93,2% 93,5%DP3480E 91,7% 94,5% 94,8% 95,0% 90,0% 92,8% 93,2% 93,5%

Linear Load SMPS Load Load DP

Task 2 UPS type: DP3160E Total load L1: 50 kVA, PF 0,9 SMPS Total load L2: 40 kVA, PF 0,8 SMPS Total load L3: 45 kVA, PF 0,8 SMPS Back-up time: 15 min

Task 2

Page 52: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

52

Task 2Task 2

BatteryLoad [W] 121.505Cell load = = = 317 [W/ cell]

Number of cells 2 x 192

PTotal [W] 113.000Battery load = 100 = x 100 = 121.505[W]

Inv. eff. [%] 93

Cell load:

Battery Load:

Efficiencies DC to AC (table)= 70,6 % (SMPS-% load of the UPS) = 93 inv. Eff %.

Task 2 UPS type: DP3160E Total load L1: 50 kVA, PF 0,9 SMPS Total load L2: 40 kVA, PF 0,8 SMPS Total load L3: 45 kVA, PF 0,8 SMPS Back-up time: 15 min

Task 2

Page 53: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

53

Results of task 2Results of task 2

Battery Specification/Pack

Type UPS 12 - 370

Make Johnson

Number of cells 384

Cell load 317 W/cell

Min. cell voltage 1,7 V

Back-up time 15 min.

Number of blocks 64

Block dim. (HxWxL) 240 x 172 x 343mm

Total weight 2176 kg

Results...

Task 2 UPS type: DP3160E Total load L1: 50 kVA, PF 0,9 SMPS Total load L2: 40 kVA, PF 0,8 SMPS Total load L3: 45 kVA, PF 0,8 SMPS Back-up time: 15 min

Task 2

Page 54: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

54

Task 3Task 3

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection

Page 55: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

55

Task 3Task 3Specify the battery...Specify the battery...

UPS type: DP3320E Total load: 315 kVA PF load: 0,8 Requested back-up: 20 min

Specify the battery…!

Data:

Task 3

Page 56: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

56

Task 3Task 3

PTotal W 252.000% load on UPS = x 100 = x 100 = 78,8

[%] UPS1/1 load W 320.000

Total Load:

UPS load:

Task 3 UPS type: DP3320E Total load: 315 kW PF load: 0,8 Back-up time: 20 min

PTotal W = PTotal VA x PF = 315.000 x 0,8 = 252.000 [W]

Task 3

Page 57: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

57

Inverter DataInverter Data

Find the efficiencies DC to AC percentage..!

25% 50% 75% 100% 25% 50% 75% 100%DP310E 88,8% 92,6% 93,0% 93,5% 85,5% 89,0% 89,5% 90,0%DP320E 89,3% 93,1% 93,5% 94,0% 86,0% 89,3% 90,0% 90,5%DP340E 91,0% 94,0% 94,5% 94,5% 88,0% 90,1% 91,7% 92,3%DP360E 93,0% 94,5% 95,5% 96,0% 89,0% 92,0% 92,8% 93,2%DP380E 93,2% 95,5% 96,0% 96,1% 90,0% 92,8% 93,2% 93,5%DP3120E 88,6% 93,0% 94,2% 94,6% 89,7% 92,5% 92,9% 93,2%DP3160E 91,2% 93,9% 94,6% 94,7% 90,0% 92,8% 93,2% 93,5%DP3240E 90,0% 94,2% 95,2% 95,4% 88,5% 92,0% 93,0% 93,2%DP3320E 92,2% 95,0% 95,4% 95,5% 90,0% 92,8% 93,2% 93,5%DP3480E 91,7% 94,5% 94,8% 95,0% 90,0% 92,8% 93,2% 93,5%

Linear Load SMPS Load Load DP

Efficiencies DC to AC DP 3320E and 78,8% Linear

Task 3 UPS type: DP3320E Total load: 315 kW PF load: 0,8 Back-up time: 20 min

Task 3

Page 58: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

58

Task 3Task 3

BatteryLoad [W] 264.151Cell load = = = 688 [W/ cell]

Number of cells 2 x 192

PTotal [W] 252.000Battery load = x 100 = x 100 = 264.151 [W]

Inv. eff. [%] 95,4

Cell load:

Battery Load:Efficiencies DC to AC (table)= 78,8 % (SMPS-% load of the UPS) = 95,4 inv. Eff %.

Task 3 UPS type: DP3320E Total load: 315 kW PF load: 0,8 Back-up time: 20 min

Cellload [W/ cell] 688With ___ parallel string = = = 344 [W/ cell] Number of strings 2

Strings:

Task 3

Page 59: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

59

Results of task 3Results of task 3

Battery Specification/Pack

Type UPS 12 - 475

Make Johnson

Number of cells 384

Cell load 344 W/cell

Min. cell voltage 1,7 V

Back-up time 20 min.

Number of blocks 128

Block dim. (HxWxL) 278 x 172 x 344mm

Total weight 6144 kg

Task 3 UPS type: DP3320E Total load: 315 kW PF load: 0,8 Back-up time: 20 min

Task 3

Page 60: Bat sizing rev 1.3 1 Show information... Navigation links: Move the cursor across the links and wait for the “hand” symbol - then click left mouse key

Bat sizing rev 1.3

60

ReviewReview

Review

Battery Load

Battery Bank

Cell specifications - example 1

Example 2...

Battery ambient temperature

Battery recharging

Example 3...

Task 1...

Task 2...

Task 3...

Review

Battery parallel connection