batman smells
TRANSCRIPT
-
8/11/2019 Batman Smells
1/48
-
8/11/2019 Batman Smells
2/48
What is a Load Flow Study A load flow study is done on a power system
to ensure that
Generation supplies the demand (load) pluslosses.
Bus voltage magnitudes remain close to ratedvalues
Generation operates within specified real and
reactive power limits Transmission lines and transformers are not
overloaded.
-
8/11/2019 Batman Smells
3/48
A Load Flow Study Specifically
Investigates the Following Busbar voltages
Effect of rearranging circuits and
incorporating new circuits on system loading. Effect of injecting in-phase and quadrature
boost voltages on system loading.
Optimum system running conditions and load
distribution. Optimum system losses.
Optimum rating and tap range oftransformers.
-
8/11/2019 Batman Smells
4/48
The Load Flow Problem The starting point of a load flow
problem is a single line diagram of the
power system, from which input datafor computer solutions can be obtained.Input data consist of bus data,
transmission line data and transformerdata.
-
8/11/2019 Batman Smells
5/48
-
8/11/2019 Batman Smells
6/48
The Load Flow Problem Each bus k is categorized into one of the following bus types:
Swing bus- There is only one swing bus which forconvenience is normally numbered as bus 1, and is a referencebus for which V1and d1are 1 and 0orespectively
Load Busor PQ bus- Most buses in a typical load flowprogram are load buses. Pkand Qkare specified and theprogram computes Vkand dk.
Voltage Controlled bus or PV bus- These aregenerally generator buses where Pkand Vkare specified andQkand dkare computed.
-
8/11/2019 Batman Smells
7/48
The Load Flow Problem There are two methods of solving the
load flow problem.
A) The Gauss Seidel Method
B) The Newton Raphson Method
-
8/11/2019 Batman Smells
8/48
The Gauss-Seidel Method This method solves, by an iterative process,
the following equation that represents a powersystem having N buses
1
*
1 1
11 1
k
k Nk k
k kn n kn n
n n kkk
P jQV i Y V i Y V i
Y V i
-
8/11/2019 Batman Smells
9/48
GPLS POWER SYSTEM GPLS power system, with an installed
capacity of 105 MW, consists of the following:
Demerara Interconnected System Berbice Interconnected System
Anna Regina System
Bartica System
Wakenaam System
Leguan System
-
8/11/2019 Batman Smells
10/48
THE OBJECTIVES OF THIS STUDY
WERE AS FOLLOWS:
To model the (GPLS) Demerara system for loadflow studies.
To perform load flow studies on GPLs presentDemerara 60 Hz system.
To use a static model of the frequency convertersand perform studies on the Demerara 50 and 60
Hz system. To perform load flow studies on GPLs future
Demerara power system (all load converted to 60Hz.).
To analyse the results of the load flow studies.
-
8/11/2019 Batman Smells
11/48
Demerara Interconnected System Data Installed Capacity76 MW
Peak Load - 67 MW
Three power stations, two at Garden ofEden and one at Versailles, generating at13.8 kV, 60Hz
Two power stations at Kingston generatingat 11 kV, 50 Hz
-
8/11/2019 Batman Smells
12/48
Demerara Interconnected System Data Demerara Power, an Independent Power
Producer, owns and operates two power
stations at Garden of Eden and Kingston
All other power stations are owned by GPL
-
8/11/2019 Batman Smells
13/48
Demerara Interconnected System Data
The 25 MVA rotary frequency converterstation at Sophia has machines rated at
13.8 kV, 60 Hz and 11 kV, 50 Hz whichoperate as motors or generatorsdepending on the flow of power
-
8/11/2019 Batman Smells
14/48
Demerara Interconnected System Data
A 69 kV transmission system connects the
Garden of Eden stations and the Sophiafrequency converter station
-
8/11/2019 Batman Smells
15/48
The Newton-Raphson Method The Newton-Raphson method solves the
nonlinear equationy= f(x) where thex,y
and fvectors for the power flow problem aredefined as
1
1
( ) cos( )
( ) sin( )
2,3,......
N
k k k k kn n k n kn
n
N
k N k k k kn n k n kn
n
Y P P x V Y V
Y Q Q x V Y V
k N
d d
d d
-
8/11/2019 Batman Smells
16/48
Single Line Diagram of theDemerara Interconnected System
KINGSTON
B
11 KV
SOPHIA
69KV
SOPHIA
13.8KV
SOPHIA
11KV
DEMERARAPOWER
GOE
DEMERARA
POWER
KINGSTON
VERSAILES
GOE
11 KV
11 KV
69 KV
13.8 KV
13.8 KV
69 KV
11 KV/4KV
69/13.8KV
13.8/69KV
11(50Hz)/
13.8(60Hz)
KV
DATEORIGINAL
LATESTREVISION
SCALE
JOBNO.
REVISIONS
N O. D A TE D ES CR IP TI ON
DRAWNCHECKED
GUYANA POWER& LIGHT
DEMERARA INTERCONNECTED
SYSTEM AS OF 2006 -
DEMERARA INTER-CONNECTED
SYSTEM SINGLE LINE DIAGRAM
11 KV/4KV
3X12.5MVA
2X6.87MVA 2X6.87 MVA
2X6.87 MVA
2X6.87 MVA
2X6.6257 MVA
2X2.5 MVA
12.5MVA
16.7 MVA
12.5MVA
16.7 MVA16.7 MVA
16.7 MVA 16.7 MVA 16.7 MVA
6.25 MVA
NOTTOSCALE
-
8/11/2019 Batman Smells
17/48
Methodology of Study
Data Collection
Data Analysis
Load Flow Study
-
8/11/2019 Batman Smells
18/48
Data Collection
The following data was collected:
Single line diagram of the GPL Demerara system.
Reactances of all generators at the DemeraraPower stations, and GPLs Garden of Eden andVersailles power stations and the Sophiafrequency converters.
Impedances of all transmission and distributionlines and transformers.
-
8/11/2019 Batman Smells
19/48
Data Collection
Hourly operations data for the system for
weekdays (2) and Saturday and Sunday
Data from recent power analyser
recordings giving feeders power factor andvoltages
-
8/11/2019 Batman Smells
20/48
Analysis of Data
The loads (MW and MVar) for the variousbusbars were calculated using hourly feedercurrent and voltages from the log sheets
and the corresponding hourly power factordata recorded on a power demand analyser.
-
8/11/2019 Batman Smells
21/48
Analysis of Data
Sophia was found to be the major loadcentre for the Demerara system with an
evening peak of nearly 30 MW The peak 60 Hz load is about 45 MW
and is primarily residential
The 50 Hz load is mainly industrial/commercial and has a day peak ofaround 20 MW.
-
8/11/2019 Batman Smells
22/48
Demerara 50 AND 60 HZ System Loads (Weekday)
0.0
10.0
20.0
30.0
40.0
50.0
60.0
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
TIME (HRS)
LOAD
(MW)
50 Hz System
60 Hz System
Total System
-
8/11/2019 Batman Smells
23/48
Analysis of Data
50 Hz system hourly power factorsrange from 0.79 to 0.89 and the 60 Hz
system power factors are from 0.81 to0.85.
The frequency converters produce
between 20 to 30 % of the MVarrequirement of the Demerara system.
-
8/11/2019 Batman Smells
24/48
Analysis of Data
Comparison of power analyzer data andstation logs revealed that the Sophia
panel meters were overstating theSophia 13.8 kV voltages.
-
8/11/2019 Batman Smells
25/48
Sophia Panel Meter and Power Analyser Voltage Readings
12.8
13.0
13.2
13.4
13.6
13.8
14.0
14.2
14.4
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
Time (Hrs)
Voltage(kV)
Panel Meter
Analyser Readings
-
8/11/2019 Batman Smells
26/48
Analysis of Data
The Demerara Power generators areused as the base load generators for
the system, with GPLs Garden of Edenand Versailles stations being used tomaintain bus voltages levels and for
peaking purposes.
-
8/11/2019 Batman Smells
27/48
Demerara System Generation by Power Station
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
Time (hrs)
Generation(MW)
VERSAILLES
GPLGOE
DPLK'STON
DPLGOE
-
8/11/2019 Batman Smells
28/48
Load Flow Studies
The 60 Hz machine of the frequencyconverters were modeled as generators
and when they operated as motors thegenerators were deemed to besupplying negative power.
-
8/11/2019 Batman Smells
29/48
Load Flow Studies
The various busbars were designated as follows:
Garden of Eden 13.8 kV busbar - Slack Bus
Demerara Power GOE busbars - PV Bus
Sophia Station 13.8 kV busbar - PV bus
Versailles Power Station busbar - PV bus
-
8/11/2019 Batman Smells
30/48
-
8/11/2019 Batman Smells
31/48
Load Flow Studies
Hourly load flow runs were carried outfor three of the days from which hourly
data had been collected, that is, twoweekdays and Saturday.
Transformer taps were changed todetermine the best tap position
-
8/11/2019 Batman Smells
32/48
Load Flow Studies
The frequency converters wererepresented as an 13.8/11 kV
autotransformer in combination with acapacitor. Load flow runs were carriedout on the combined Demerara 50 and
60 Hz systems for system peak load.
-
8/11/2019 Batman Smells
33/48
Load Flow Studies
The frequency converters wereremoved from the system and the 60Hz
system was extended to cater for thepresent 50 Hz load.
Load flow runs were carried out for dayand night peaks.
-
8/11/2019 Batman Smells
34/48
Analysis of Results
The following abbreviations apply:
DPGOE - Demerara Power station at
Garden of Eden
GPLGOE - GPLs Garden of EdenStation
LFR - The hourly load flow run
-
8/11/2019 Batman Smells
35/48
Analysis of Results
As GPLGOE was the slack busbarcomparison was made between its
generation during GPL operations andthe load flow runs. For the GPLoperations GPLGOE generation was
higher than that of the LFR by 70%during the off peak periods and up to120% during evening peaks.
-
8/11/2019 Batman Smells
36/48
Analysis of Results
The LFR showed an average of 2%system losses
GPL operations showed losses as muchas 18% and averaged 11% over the
period of analysis.
-
8/11/2019 Batman Smells
37/48
COMPARISON BETWEEN GPL AND LOAD FLOW GENERATION (MW)
25.0
30.0
35.0
40.0
45.0
50.0
55.0
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
TIME (HRS)
Generation
(MW)
System Load
GPL Generation
Load Flow Generation
-
8/11/2019 Batman Smells
38/48
Analysis of Results
The LFR consistently generated around3 MVars at DPGOE. GPL operations
show MVAR generation between 8 and13 MVars at this location.
-
8/11/2019 Batman Smells
39/48
Analysis of Results
The LFR generation of MVars at Sophiawas consistently higher than that of
GPL operations. This was as high as 15MVar at peak load whereas GPLoperations generate just around 10
MVars at the same period
-
8/11/2019 Batman Smells
40/48
Analysis of Results
MVar generation at GPLGOE andVersailles were quite similar for both
GPL operations and the LFR
-
8/11/2019 Batman Smells
41/48
Comparison Between GPL and Load Flow Generation (MVAR)
10.0
15.0
20.0
25.0
30.0
35.0
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
TIME (HRS)
MVAR
SYSTEM LOAD
GPL GENERATION
LOAD FLOWGENERATION
-
8/11/2019 Batman Smells
42/48
Analysis of Results
Changing of transformer taps
The present tap positions of the GPL
transformers proved to be the optimumpositions to maintain bus voltages andminimise losses.
-
8/11/2019 Batman Smells
43/48
Analysis of Results
Static Representation of theFrequency Converters
The results achieved from the load flowrun for system peak suggest that thismodel could be acceptable if separaterepresentation is made for the mechanicallosses of the frequency converters.
-
8/11/2019 Batman Smells
44/48
Analysis of Results
Total Demerara Load at 60 Hz
The frequency converters would not be
required so capacitors would be needed atall locations to provide the MVar injectionpresently done by the frequency converters
Switched capacitors would have to be usedas different values would be required forthe day and night peaks
-
8/11/2019 Batman Smells
45/48
Conclusions
The usefulness of load flow studies in theinvestigation of the following were
demonstrated Optimum system running conditions and load
distribution.
Optimum system losses.
Optimum tap range of transformers. Effect of incorporating new circuits on system
loading.
-
8/11/2019 Batman Smells
46/48
Conclusions
The data collection and analysis highlightedproblems with GPLs system operations whichwere confirmed by the load flow study.
The difference in GPLs calculated loads andgeneration show a high level of losses inGPLs generation and transmission systemwhich require further investigation.
The Sophia 13.8 kV bus voltages are lowerthan the other bus voltages and need to beincreased for proper system operation.
-
8/11/2019 Batman Smells
47/48
Conclusions
The static representation of thefrequency converters by a transformer
and a variable capacitor is an adequatemodel for load flow studies. Convertermechanical losses can be added
subsequently to the total system losses.
-
8/11/2019 Batman Smells
48/48
Conclusions
The availability of load flow studieswould be helpful to small utilities as
they seek to integrate their powersystem with different types ofgeneration