batman smells

Upload: parikshith-bharath

Post on 02-Jun-2018

240 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Batman Smells

    1/48

  • 8/11/2019 Batman Smells

    2/48

    What is a Load Flow Study A load flow study is done on a power system

    to ensure that

    Generation supplies the demand (load) pluslosses.

    Bus voltage magnitudes remain close to ratedvalues

    Generation operates within specified real and

    reactive power limits Transmission lines and transformers are not

    overloaded.

  • 8/11/2019 Batman Smells

    3/48

    A Load Flow Study Specifically

    Investigates the Following Busbar voltages

    Effect of rearranging circuits and

    incorporating new circuits on system loading. Effect of injecting in-phase and quadrature

    boost voltages on system loading.

    Optimum system running conditions and load

    distribution. Optimum system losses.

    Optimum rating and tap range oftransformers.

  • 8/11/2019 Batman Smells

    4/48

    The Load Flow Problem The starting point of a load flow

    problem is a single line diagram of the

    power system, from which input datafor computer solutions can be obtained.Input data consist of bus data,

    transmission line data and transformerdata.

  • 8/11/2019 Batman Smells

    5/48

  • 8/11/2019 Batman Smells

    6/48

    The Load Flow Problem Each bus k is categorized into one of the following bus types:

    Swing bus- There is only one swing bus which forconvenience is normally numbered as bus 1, and is a referencebus for which V1and d1are 1 and 0orespectively

    Load Busor PQ bus- Most buses in a typical load flowprogram are load buses. Pkand Qkare specified and theprogram computes Vkand dk.

    Voltage Controlled bus or PV bus- These aregenerally generator buses where Pkand Vkare specified andQkand dkare computed.

  • 8/11/2019 Batman Smells

    7/48

    The Load Flow Problem There are two methods of solving the

    load flow problem.

    A) The Gauss Seidel Method

    B) The Newton Raphson Method

  • 8/11/2019 Batman Smells

    8/48

    The Gauss-Seidel Method This method solves, by an iterative process,

    the following equation that represents a powersystem having N buses

    1

    *

    1 1

    11 1

    k

    k Nk k

    k kn n kn n

    n n kkk

    P jQV i Y V i Y V i

    Y V i

  • 8/11/2019 Batman Smells

    9/48

    GPLS POWER SYSTEM GPLS power system, with an installed

    capacity of 105 MW, consists of the following:

    Demerara Interconnected System Berbice Interconnected System

    Anna Regina System

    Bartica System

    Wakenaam System

    Leguan System

  • 8/11/2019 Batman Smells

    10/48

    THE OBJECTIVES OF THIS STUDY

    WERE AS FOLLOWS:

    To model the (GPLS) Demerara system for loadflow studies.

    To perform load flow studies on GPLs presentDemerara 60 Hz system.

    To use a static model of the frequency convertersand perform studies on the Demerara 50 and 60

    Hz system. To perform load flow studies on GPLs future

    Demerara power system (all load converted to 60Hz.).

    To analyse the results of the load flow studies.

  • 8/11/2019 Batman Smells

    11/48

    Demerara Interconnected System Data Installed Capacity76 MW

    Peak Load - 67 MW

    Three power stations, two at Garden ofEden and one at Versailles, generating at13.8 kV, 60Hz

    Two power stations at Kingston generatingat 11 kV, 50 Hz

  • 8/11/2019 Batman Smells

    12/48

    Demerara Interconnected System Data Demerara Power, an Independent Power

    Producer, owns and operates two power

    stations at Garden of Eden and Kingston

    All other power stations are owned by GPL

  • 8/11/2019 Batman Smells

    13/48

    Demerara Interconnected System Data

    The 25 MVA rotary frequency converterstation at Sophia has machines rated at

    13.8 kV, 60 Hz and 11 kV, 50 Hz whichoperate as motors or generatorsdepending on the flow of power

  • 8/11/2019 Batman Smells

    14/48

    Demerara Interconnected System Data

    A 69 kV transmission system connects the

    Garden of Eden stations and the Sophiafrequency converter station

  • 8/11/2019 Batman Smells

    15/48

    The Newton-Raphson Method The Newton-Raphson method solves the

    nonlinear equationy= f(x) where thex,y

    and fvectors for the power flow problem aredefined as

    1

    1

    ( ) cos( )

    ( ) sin( )

    2,3,......

    N

    k k k k kn n k n kn

    n

    N

    k N k k k kn n k n kn

    n

    Y P P x V Y V

    Y Q Q x V Y V

    k N

    d d

    d d

  • 8/11/2019 Batman Smells

    16/48

    Single Line Diagram of theDemerara Interconnected System

    KINGSTON

    B

    11 KV

    SOPHIA

    69KV

    SOPHIA

    13.8KV

    SOPHIA

    11KV

    DEMERARAPOWER

    GOE

    DEMERARA

    POWER

    KINGSTON

    VERSAILES

    GOE

    11 KV

    11 KV

    69 KV

    13.8 KV

    13.8 KV

    69 KV

    11 KV/4KV

    69/13.8KV

    13.8/69KV

    11(50Hz)/

    13.8(60Hz)

    KV

    DATEORIGINAL

    LATESTREVISION

    SCALE

    JOBNO.

    REVISIONS

    N O. D A TE D ES CR IP TI ON

    DRAWNCHECKED

    GUYANA POWER& LIGHT

    DEMERARA INTERCONNECTED

    SYSTEM AS OF 2006 -

    DEMERARA INTER-CONNECTED

    SYSTEM SINGLE LINE DIAGRAM

    11 KV/4KV

    3X12.5MVA

    2X6.87MVA 2X6.87 MVA

    2X6.87 MVA

    2X6.87 MVA

    2X6.6257 MVA

    2X2.5 MVA

    12.5MVA

    16.7 MVA

    12.5MVA

    16.7 MVA16.7 MVA

    16.7 MVA 16.7 MVA 16.7 MVA

    6.25 MVA

    NOTTOSCALE

  • 8/11/2019 Batman Smells

    17/48

    Methodology of Study

    Data Collection

    Data Analysis

    Load Flow Study

  • 8/11/2019 Batman Smells

    18/48

    Data Collection

    The following data was collected:

    Single line diagram of the GPL Demerara system.

    Reactances of all generators at the DemeraraPower stations, and GPLs Garden of Eden andVersailles power stations and the Sophiafrequency converters.

    Impedances of all transmission and distributionlines and transformers.

  • 8/11/2019 Batman Smells

    19/48

    Data Collection

    Hourly operations data for the system for

    weekdays (2) and Saturday and Sunday

    Data from recent power analyser

    recordings giving feeders power factor andvoltages

  • 8/11/2019 Batman Smells

    20/48

    Analysis of Data

    The loads (MW and MVar) for the variousbusbars were calculated using hourly feedercurrent and voltages from the log sheets

    and the corresponding hourly power factordata recorded on a power demand analyser.

  • 8/11/2019 Batman Smells

    21/48

    Analysis of Data

    Sophia was found to be the major loadcentre for the Demerara system with an

    evening peak of nearly 30 MW The peak 60 Hz load is about 45 MW

    and is primarily residential

    The 50 Hz load is mainly industrial/commercial and has a day peak ofaround 20 MW.

  • 8/11/2019 Batman Smells

    22/48

    Demerara 50 AND 60 HZ System Loads (Weekday)

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    1:00

    2:00

    3:00

    4:00

    5:00

    6:00

    7:00

    8:00

    9:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    24:00

    TIME (HRS)

    LOAD

    (MW)

    50 Hz System

    60 Hz System

    Total System

  • 8/11/2019 Batman Smells

    23/48

    Analysis of Data

    50 Hz system hourly power factorsrange from 0.79 to 0.89 and the 60 Hz

    system power factors are from 0.81 to0.85.

    The frequency converters produce

    between 20 to 30 % of the MVarrequirement of the Demerara system.

  • 8/11/2019 Batman Smells

    24/48

    Analysis of Data

    Comparison of power analyzer data andstation logs revealed that the Sophia

    panel meters were overstating theSophia 13.8 kV voltages.

  • 8/11/2019 Batman Smells

    25/48

    Sophia Panel Meter and Power Analyser Voltage Readings

    12.8

    13.0

    13.2

    13.4

    13.6

    13.8

    14.0

    14.2

    14.4

    1:00

    2:00

    3:00

    4:00

    5:00

    6:00

    7:00

    8:00

    9:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    24:00

    Time (Hrs)

    Voltage(kV)

    Panel Meter

    Analyser Readings

  • 8/11/2019 Batman Smells

    26/48

    Analysis of Data

    The Demerara Power generators areused as the base load generators for

    the system, with GPLs Garden of Edenand Versailles stations being used tomaintain bus voltages levels and for

    peaking purposes.

  • 8/11/2019 Batman Smells

    27/48

    Demerara System Generation by Power Station

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.0

    1:00

    2:00

    3:00

    4:00

    5:00

    6:00

    7:00

    8:00

    9:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    24:00

    Time (hrs)

    Generation(MW)

    VERSAILLES

    GPLGOE

    DPLK'STON

    DPLGOE

  • 8/11/2019 Batman Smells

    28/48

    Load Flow Studies

    The 60 Hz machine of the frequencyconverters were modeled as generators

    and when they operated as motors thegenerators were deemed to besupplying negative power.

  • 8/11/2019 Batman Smells

    29/48

    Load Flow Studies

    The various busbars were designated as follows:

    Garden of Eden 13.8 kV busbar - Slack Bus

    Demerara Power GOE busbars - PV Bus

    Sophia Station 13.8 kV busbar - PV bus

    Versailles Power Station busbar - PV bus

  • 8/11/2019 Batman Smells

    30/48

  • 8/11/2019 Batman Smells

    31/48

    Load Flow Studies

    Hourly load flow runs were carried outfor three of the days from which hourly

    data had been collected, that is, twoweekdays and Saturday.

    Transformer taps were changed todetermine the best tap position

  • 8/11/2019 Batman Smells

    32/48

    Load Flow Studies

    The frequency converters wererepresented as an 13.8/11 kV

    autotransformer in combination with acapacitor. Load flow runs were carriedout on the combined Demerara 50 and

    60 Hz systems for system peak load.

  • 8/11/2019 Batman Smells

    33/48

    Load Flow Studies

    The frequency converters wereremoved from the system and the 60Hz

    system was extended to cater for thepresent 50 Hz load.

    Load flow runs were carried out for dayand night peaks.

  • 8/11/2019 Batman Smells

    34/48

    Analysis of Results

    The following abbreviations apply:

    DPGOE - Demerara Power station at

    Garden of Eden

    GPLGOE - GPLs Garden of EdenStation

    LFR - The hourly load flow run

  • 8/11/2019 Batman Smells

    35/48

    Analysis of Results

    As GPLGOE was the slack busbarcomparison was made between its

    generation during GPL operations andthe load flow runs. For the GPLoperations GPLGOE generation was

    higher than that of the LFR by 70%during the off peak periods and up to120% during evening peaks.

  • 8/11/2019 Batman Smells

    36/48

    Analysis of Results

    The LFR showed an average of 2%system losses

    GPL operations showed losses as muchas 18% and averaged 11% over the

    period of analysis.

  • 8/11/2019 Batman Smells

    37/48

    COMPARISON BETWEEN GPL AND LOAD FLOW GENERATION (MW)

    25.0

    30.0

    35.0

    40.0

    45.0

    50.0

    55.0

    1:00

    2:00

    3:00

    4:00

    5:00

    6:00

    7:00

    8:00

    9:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    24:00

    TIME (HRS)

    Generation

    (MW)

    System Load

    GPL Generation

    Load Flow Generation

  • 8/11/2019 Batman Smells

    38/48

    Analysis of Results

    The LFR consistently generated around3 MVars at DPGOE. GPL operations

    show MVAR generation between 8 and13 MVars at this location.

  • 8/11/2019 Batman Smells

    39/48

    Analysis of Results

    The LFR generation of MVars at Sophiawas consistently higher than that of

    GPL operations. This was as high as 15MVar at peak load whereas GPLoperations generate just around 10

    MVars at the same period

  • 8/11/2019 Batman Smells

    40/48

    Analysis of Results

    MVar generation at GPLGOE andVersailles were quite similar for both

    GPL operations and the LFR

  • 8/11/2019 Batman Smells

    41/48

    Comparison Between GPL and Load Flow Generation (MVAR)

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    1:00

    2:00

    3:00

    4:00

    5:00

    6:00

    7:00

    8:00

    9:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    24:00

    TIME (HRS)

    MVAR

    SYSTEM LOAD

    GPL GENERATION

    LOAD FLOWGENERATION

  • 8/11/2019 Batman Smells

    42/48

    Analysis of Results

    Changing of transformer taps

    The present tap positions of the GPL

    transformers proved to be the optimumpositions to maintain bus voltages andminimise losses.

  • 8/11/2019 Batman Smells

    43/48

    Analysis of Results

    Static Representation of theFrequency Converters

    The results achieved from the load flowrun for system peak suggest that thismodel could be acceptable if separaterepresentation is made for the mechanicallosses of the frequency converters.

  • 8/11/2019 Batman Smells

    44/48

    Analysis of Results

    Total Demerara Load at 60 Hz

    The frequency converters would not be

    required so capacitors would be needed atall locations to provide the MVar injectionpresently done by the frequency converters

    Switched capacitors would have to be usedas different values would be required forthe day and night peaks

  • 8/11/2019 Batman Smells

    45/48

    Conclusions

    The usefulness of load flow studies in theinvestigation of the following were

    demonstrated Optimum system running conditions and load

    distribution.

    Optimum system losses.

    Optimum tap range of transformers. Effect of incorporating new circuits on system

    loading.

  • 8/11/2019 Batman Smells

    46/48

    Conclusions

    The data collection and analysis highlightedproblems with GPLs system operations whichwere confirmed by the load flow study.

    The difference in GPLs calculated loads andgeneration show a high level of losses inGPLs generation and transmission systemwhich require further investigation.

    The Sophia 13.8 kV bus voltages are lowerthan the other bus voltages and need to beincreased for proper system operation.

  • 8/11/2019 Batman Smells

    47/48

    Conclusions

    The static representation of thefrequency converters by a transformer

    and a variable capacitor is an adequatemodel for load flow studies. Convertermechanical losses can be added

    subsequently to the total system losses.

  • 8/11/2019 Batman Smells

    48/48

    Conclusions

    The availability of load flow studieswould be helpful to small utilities as

    they seek to integrate their powersystem with different types ofgeneration