bay park sewage treatment plant public meeting · 2014. 10. 8. · phase e1 electrical distribution...
TRANSCRIPT
Bay Park Sewage Treatment Plant
Public Meeting
August 13, 2014
7 October 2014 2
Meeting Agenda
• Introductions
• Plant Treatment Performance
• Active Construction Contracts
• Schedule Update
• County Efforts to Reduce Construction
Impacts
• Other Discussions
• Discussion & Questions
7 October 2014 3
Plant Treatment Performance
7 October 2014 4
Plant Treatment Performance
7 October 2014 5
Active Construction Projects -
Perimeter Berm
7 October 2014 6
Active Construction Projects –
Plant-wide Odor Control Upgrades
7 October 2014 7
Active Construction Projects –
Primary Source Power Generation
Controls Rehabilitation
7 October 2014 8
Active Construction Projects –
Digesters Repair & Cleaning
7 October 2014 9
Active Construction Projects –
Sludge Thickening Improvements
7 October 2014 10
Active Construction Projects –
Final Settling Tank Rehabilitation
7 October 2014 11
Active Construction Projects –
Phase E1 Electrical Distribution System
7 October 2014 12
Schedule Update –
Capital Projects
Existing Capital Projects Construction Start
Construction
Complete
Odor Control at Bay Park & Cedar Creek 28-Oct-13 15-Oct-15
Influent Screening Facility Improvements 27-May-14 24-Nov-16
Grit Removal Facility Improvements 27-Aug-14 23-Aug-16
Sludge Thickening Facility Improvements 28-Oct-13 27-Oct-15
Cleaning & Repair of Digesters & Storage Tanks 20-May-13 9-Jun-15
Generator Controls 15-Nov-13 20-Apr-15
Hurricane Sandy Pump Stations Projects Construction Start
Construction
Complete
Dock Place & Southland Drive 28-Oct-13 22-Aug-14
Cedar, Roosevelt, Whitewood, Biltmore & Alhambra 2-Apr-15 2-Oct-16
Wantagh, Newbridge, Merrick & Ray 2-Apr-15 2-Oct-16
Millar, Mott, Long Beach, Royal & Lido 9-Apr-15 9-Oct-16
Ocean, Mill, Woodmere, Longagree & Doxey 6-Apr-15 6-Oct-16
East, Inwood, Doughty & Bayview 4-May-15 3-Nov-16
Roslyn Road 4-May-15 3-Nov-16
Barnes Ave SSO & Hempstead Flow Diverson 11-May-15 10-Nov-16
7 October 2014 13
Schedule Update –
Capital Projects
Hurricane Sandy Projects
Construction
Start
Construction
Complete
Final Settling Tank Rehabilitation 28-Oct-13 27-Oct-15
Phase E1 Electrical Distribution System Improvements 27-May-14 26-Mar-16
Phase E2 Substation No.2 & Electrical Distribution 29-Dec-14 27-Dec-16
Phase E3 Main Substation & Electrical Distribution 18-May-15 28-Dec-17
Perimeter Flood Protection 27-May-14 4-Jun-16
Flood Protection Phase 1 Stormwater Pumping Stations 20-Jul-15 2-Aug-17
Flood Protection Phase 2 Stormwater Green Infrastructure 4-Jul-17 3-Jul-18
Sludge Dewatering 22-Jun-15 21-Jun-18
Sludge Dewatering Demolition 11-Aug-14 6-Feb-15
Vehicle Fueling & Tanks Reconstruction 11-Sep-14 7-Jun-15
Effluent Tide Pumping Building 30-Jul-15 6-Oct-17
Effluent Screening & Disinfection 26-Nov-15 9-Dec-17
Digesters 11-Feb-16 24-Feb-18
Secondary Treatment 11-Feb-16 24-Feb-18
Influent Screens & RSPs 4-Jan-16 17-Jan-18
Grit Removal & Primary Settling 11-Feb-16 24-Feb-18
Central & Distributed HVAC 11-Feb-16 28-Aug-17
Odor Control Systems 11-Feb-16 28-Aug-17
General Plant Site Facilities 11-Feb-16 24-Feb-18
Sludge Thickening 14-Feb-16 4-Mar-17
Lawrence STP & Sage Lake PS 2-Jul-15 1-Jan-17
7 October 2014 14
• Vibration Monitoring
• Purpose: Real-time Monitoring
Allowing Instance Correction. Record
and Document Vibrations Caused by
Construction Activity During Work
Day.
• Example, August 6, 2014 (8:00AM –
1:30PM)
• Baseline Reading Taken From
8:30AM to 11:00AM
• Record at Every 5 Minutes.
• At 11:00AM, Contractor Began
Moving Soils around Construction
Site.
• Result – No Vibration in Exceedance
Efforts to Reduce Construction Impacts –
Vibration Monitoring
7 October 2014 15
Other Discussions
• Home Inspection
Discussion & Questions