Foxground & Berry bypass
Gerringong upgradeBerry to Bomaderry upgrade
BBU – Berry to Bomaderry UpgradeCommunity Sessions
May 2012
![Page 2: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/2.jpg)
Introductions
Project team:• Roads & Maritime Services
– Nick Boyd – Project manager– Carla Brookes – Project communications– Mark Keech – Design– Keith Pepper – Design– Bill Healy – Property– Brianna Royal – Property
• AECOM– Jon Williamson – Project manager– Stuart Dalziel – Principal engineer– Kerri Hale – Project communications– Wendy Carlson – Facilitator and project communications
![Page 3: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/3.jpg)
Welcome
Meeting purpose• To inform the community of project status• To gather information from the community to improve the design
Meeting process• Presentation• Question & answer session• Next steps
Housekeeping• Refreshments• Facilities
![Page 4: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/4.jpg)
Welcome
Problems identified during early community sessions• The project team acknowledges a problem with invitations
– About 250 people living on the highway and on the affected side streets were invited– We are not sure why some people received their invitations & why others did not
• The problem concerns the project team– We want to speak to as many people as possible– We want to gather as much feedback as possible
• We propose to…– Continue with the three scheduled sessions as they are booked in– We will then assess the need for more sessions to speak to those who missed an invite– We will consider other ways of distributing invites to households (letterbox drop)
• Please let us know of anyone who we should speak to
![Page 5: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/5.jpg)
Nowra
Berry
Bomaderry
KangarooValley
Gerringong
Kiama
Foxground
South Nowra
Shoalhaven Heads
Culburra
Jamberoo
Princes Highway upgrade
Princes Highway upgrades• North Kiama bypass• Oak Flats to Dunmore
Gerringong to Bomaderry (G2B)• Route announced June 2009
State Government commitment• $500M towards G2B project• Funding for this term of government
![Page 6: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/6.jpg)
Nowra
Berry
Bomaderry
KangarooValley
Gerringong
Kiama
Foxground
South Nowra
Shoalhaven Heads
Culburra
Jamberoo
Princes Highway upgrade
G2B split into three projects:
• Gerringong Upgrade (GU)– Tender awarded
• Foxground & Berry Bypass (FBB)– Planning
• Berry to Bomaderry Upgrade (BBU)– Planning
![Page 7: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/7.jpg)
BBU overview – current status
Berry bypass southern review• Last community meeting held 30 April 2012• Decision to be made by Minister Roads & Ports• Next community meeting planned upon announcement• Refer to www.rta.nsw.gov.au/fbb for latest information
Implications for BBU• Decision may affect northern section of this project• BBU is proceeding as planned until advised otherwise• Tonight is for people potentially affected by BBU…
![Page 8: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/8.jpg)
BBU overview – project extent
BBU project extent:• Andersons Ln to Cambewarra Rd
![Page 9: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/9.jpg)
BBU overview – current status
Concept design• Community input sought 2009• Concept design drafted 2011• Community input required to improve concept design• We need to know of adverse impacts and benefits
Environmental assessment• Some environmental studies commenced• Remainder to be completed once concept design finalised
![Page 10: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/10.jpg)
BBU overview – proposed future milestones
![Page 11: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/11.jpg)
BBU overview – project need
Commitment to need for Princes Highway upgrade• 2008 Coronial Inquest• State Infrastructure Strategy 2008/09 to 2017/18• Current State Government commitment of $500M
Deficiencies• Approx. 10 reported crashes per year (40% casualty)• Traffic performance LOS D in some locations
Network consistency• Four lanes Sydney to Shoalhaven• Construction of GU & FBB would leave BBU as a substandard link
![Page 12: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/12.jpg)
BBU overview – project objectives
Project objectives• Improve road safety• Improve traffic efficiency• Support regional & local economies• Provide value for money• Minimise environmental impacts & look for opportunities for benefits• Optimise potential local social benefits
![Page 13: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/13.jpg)
Project proposal – typical cross section
Typical cross section:• Divided carriageway• Two lanes each way• 3.5 metre lane widths• 5.0 metre median• Central barrier• Turning restrictions• 2.5 metre shoulders• 100km/hr• 1:100 flood immunity• Batters range 2:1 – 4:1
![Page 14: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/14.jpg)
Project proposal – typical cross section
![Page 15: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/15.jpg)
Project details – outline
Main project features:• Changes to access• Property impacts• Environmental assessment (noise & visual impacts)• Bus stops, pedestrians & cyclists• Heavy vehicle facility
Following these slides we will facilitate aquestion and answer session
![Page 16: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/16.jpg)
Berry
Bomaderry
Jaspers Brush
MerooMeadow
Project details – changes to access
Dual carriageway restricts turning movements
Need an access strategy
Three levels of access:• Grade separation• Right turn / u-turn• Left in / left out
![Page 17: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/17.jpg)
Berry
Bomaderry
Jaspers Brush
MerooMeadow
Project details – changes to access
Grade separation:
• Jaspers Brush Rd / Strongs Rd
• Devitts Ln / Morschels Ln
• Meroo Rd / Pestells Ln
![Page 18: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/18.jpg)
Left in / left out junction at
Strongs Road
Left in / left out junction at Jaspers
Brush Road
New overpass
Project details – changes to access
Grade separation• Jaspers Brush Road / Strongs Road
![Page 19: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/19.jpg)
Left in / left out junction for Devitts Lane
Left in / left out junction for
Morschels Lane
New underpass
Project details – changes to access
Grade separation• Devitts Lane / Morschels Lane
![Page 20: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/20.jpg)
Northbound onload & offload
ramps
Provision for future southbound
ramps
Project details – changes to access
Grade separation• Meroo Road / Pestells Lane
![Page 21: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/21.jpg)
Berry
Bomaderry
Jaspers Brush
MerooMeadow
Project details – changes to access
Right turn / u-turn:
• Mullers Ln• Croziers Rd• south of Jaspers Brush Rd• Silos Winery• Lamonds Ln• south of Abernethys Ln
![Page 22: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/22.jpg)
Berry
Bomaderry
Jaspers Brush
MerooMeadow
Project details – changes to access
Left in / left out:
• Anderson Ln• O’Keefe Ln• Turners Ln• Boxsells Ln• Abernethys Ln
• Driveways
![Page 23: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/23.jpg)
Project details – changes to access
• Typical right turn / u-turn • Typical left in / left out
![Page 24: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/24.jpg)
Project details – property impacts
Property acquisition• Dual carriageway corridor requires more width
– Current road corridor is as narrow as 20 metres in some locations– New road corridor would be at least 40 metres (plus cut & fill batters, etc)
• Many properties adjoining the Princes Highway will require some partial strip acquisition
• Some properties may be more affected– Possible full acquisition– Business / operational impacts
• Any changes to concept & detailed designs will potentially increase impacts on some properties
![Page 25: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/25.jpg)
Berry
Bomaderry
Jaspers Brush
MerooMeadow
Devitts
Lane
Boxsells Lane
Jaspers Brush RoadTurners Lane
MerooRoad
Croziers Road
Cambewarra Road
Mullers Lane
Project details – property impacts
![Page 26: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/26.jpg)
Project details – property impacts
More details on the property acquisition process are contained in the RMS Land Acquisition Information Guide
• Land is valued on current market value as if unaffected by the proposal• Two valuations can be compared for agreement
– RMS valuation– Independent valuation
• When do property negotiations commence?– Most acquisitions considerations do not commence until after the concept design is finalised– RMS may consider requests for "hardship" acquisitions before the concept design is finalised
• RMS will consult with property owners before negotiations
![Page 27: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/27.jpg)
Project details – noise & visual impacts
Review of Environmental Factors (REF)• Preliminary assessments were conducted during G2B route selection
– Hydrology / hydraulics– Aboriginal and non aboriginal cultural heritage– Water quality assessment– Terrestrial & aquatic flora & fauna– Urban design, landscape & visual amenity– Social-economic– Noise & vibration– Climate & air quality
• Preliminary assessments found no significant issues with the proposed alignment that could not be mitigated
• Detailed assessments will commence for the REF
![Page 28: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/28.jpg)
Project details – noise & visual impacts
Noise assessments• Noise modelling to be conducted• Noise treatments where required• Case by case basis for treatment choice
Visual assessments• Urban design reviews• Landscaping plans
The above (and more) will all be available for review & comment during the public display of the REF
![Page 29: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/29.jpg)
Project details – bus stops, pedestrians & cyclists
Bus stops to be relocated to local roads• Avoids at-grade crossing by pedestrians• Locations serving school buses may need more investigation• Bus & coach services largely unaffected, but feedback welcomed
Pedestrian access• The highway is not designed for pedestrian access• Feedback welcome on pedestrian needs
Provision for cyclists• Proposed 2.5 metre shoulder is better than current width• Feedback welcome for specific cyclist issues
![Page 30: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/30.jpg)
Project details – heavy vehicle facility
Regardless of the dual carriageway project, there is a need for two facilities for heavy vehicles on this section of the Princes Highway:
• Heavy vehicle enforcement bay
• Heavy vehicle rest stop (truck park)
![Page 31: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/31.jpg)
Project details – heavy vehicle facility
Heavy vehicle enforcement bay:• Used by RMS enforcement officers to inspect heavy vehicles
– Vehicle road worthiness– Log books– Overweight / oversize
• A part time facility is needed northbound on the Princes Highwaybetween Nowra & Berry
• The facility would include:– Hard stand area to fit mobile inspection facilities– Room for heavy vehicles to park if log books exceeded– Lighting for use in late afternoons– Lockable gates to prevent unauthorised access when not operating
![Page 32: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/32.jpg)
Project details – heavy vehicle facility
Heavy vehicle rest stop (truck park):• Used by heavy vehicle drivers to take legally required rest stops• A facility is needed northbound on the Princes Highway• Spacing between other facilities on the network identifies BBU as a
suitable location• Specifically identified in RTA Strategy for Major Heavy Vehicle Rest
Areas on Key Rural Freight Routes in NSW• The facility would include:
– Hard stand area to fit approx. 10 heavy vehicles– Bins and a toilet– Possible seating and shelter
![Page 33: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/33.jpg)
Project details – heavy vehicle facility
Site selection needs to consider:• Impact on the community
– Noise & visual impacts
• Design constraints– Length for acceleration & deceleration lanes– Proximity to other road infrastructure (creek crossings / intersections)
• Operational constraints– Network placement– Sight distance for enforcement staff
• Environmental considerations
![Page 34: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/34.jpg)
Project details – heavy vehicle facility
Berry
Bomaderry
Jaspers Brush
MerooMeadow
![Page 35: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/35.jpg)
Project details – summary
Summary of main project features covered tonight:• Changes to access• Property impacts• Environmental assessment (noise & visual impacts)• Bus stops, pedestrians & cyclists• Heavy vehicle facility
Question and answer session…
![Page 36: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/36.jpg)
Community feedback
• Community feedback is important to the project and will be taken into consideration in the finalisation of the design process
• This is your opportunity to add value and the project team welcomes your input
![Page 37: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/37.jpg)
Community feedback
You can provide feedback by:
– Fill in the ‘have your say’ forms tonight and dropping them into the box provided
– Mail the form toBerry to Bomaderry Upgrade AECOMPO Box Q410, QVB Post Office, Sydney NSW 2000
– Email your comments to [email protected]
– Phone 1800 506 976 (free call) project information line
– Visit the Berry project office, shop 3/113 Queen Street, Berry on Fridays 10am – 5pm
![Page 38: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/38.jpg)
Community feedback
Next steps
• Your feedback from these focus group meetings will be considered in the final design
• Any comments received in May will be incorporated into a summarypaper of the feedback received
![Page 39: BBU – Berry to Bomaderry Upgrade · – Current road corridor is as narrow as 20 metres in some locations – New road corridor would be at least 40 metres (plus cut & fill batters,](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9002392377c66f99106052/html5/thumbnails/39.jpg)
Close
Thank you