be1268_dissertation_clarke_ricky_w13032289

124
A STUDY OF THE FACTORS AFFECTING THE QUALITY OF PRODUCTION INFORMATION USING BIM BASED DESIGN CLARKE RICKY 13032289 19 SEPTEMBER 2014 MSC BUILDING DESIGN MANAGEMENT AND BIM

Upload: ricky-clarke

Post on 16-Jul-2015

122 views

Category:

Documents


0 download

TRANSCRIPT

A STUDY OF THE FACTORS AFFECTING THE QUALITY OF PRODUCTION

INFORMATION USING BIM BASED DESIGN

CLARKE

RICKY

13032289

19 SEPTEMBER 2014

MSC BUILDING DESIGN MANAGEMENT AND BIM

UNIVERSITY OF NORTHUMBRIA AT

NEWCASTLE

FACULTY OF ENGINEERING & ENVIRONMENT

A Study of the Factors Affecting the Quality of

Production Information Using BIM Based Design

A DISSERTATION SUBMITTED IN PARTIAL FULFILMENT OF

THE REQUIREMENTS FOR THE DEGREE OF

MSc Building Design Management and Building

Information Modelling

Ricky Clarke

13032289

September 2014

i

Declaration Form

I declare the following:

1. That the material contained in my dissertation/thesis is the end result of my own

work and that due acknowledgement has been given in the bibliography and

references to ALL sources, be they printed, electronic or personal, using the

Northumbria Harvard referencing system.

2. The word count of my dissertation/thesis is 20,620 words.

3. That unless my dissertation/thesis has been confirmed as confidential, I agree to an

entire electronic copy or sections of my dissertation/thesis being placed on the

eLearning portal and shared hard drive, if deemed appropriate, to allow future

students and staff the opportunity to see examples of past students’

dissertations/theses.

4. I agree to my dissertation/thesis being submitted to a plagiarism detection service

where it will be stored in a database and compared against work submitted from this

or any other programme within Northumbria University and from other UK, EU and

international institutions using the service.

In the event of the service detecting a high degree of similarity between the content

of my dissertation/thesis and the documents contained within the database, this will

be reported back to my supervisor and examiners, who may decide to undertake

further investigation that may ultimately lead to disciplinary action (according to

ARNA), should instances of plagiarism be detected.

5. I have read the Northumbria University policy statements on Ethics in Research

and Consultancy and confirm that ethical issues have been considered, evaluated and

appropriately addressed during my research and during the production of my

dissertation/thesis.

6. I agree to the module tutor and/or programme leader nominating my

dissertation/thesis on my behalf for appropriate academic/research awards, such as

the CIOB, RICS and APM annual master’s dissertation awards.

Date ................................................................................................................................

Sign ................................................................................................................................

ii

Acknowledgements

I would like to thank Mr Eric Johansen, my supervisor at the University of

Northumbria, for his straightforward guidance and timely feedback in response to all

my requests.

I would also like to express my thanks to the research participants who helped me

with the data collection and were generous with their time and forthcoming with

useful insights.

Lastly, I’d like to thank my family, who have encouraged and supported me

throughout my studies, with special thanks to my mum for proof reading this for me.

iii

Contents

Declaration Form .......................................................................................................... i

Acknowledgements ...................................................................................................... ii

Contents ...................................................................................................................... iii

List of Figures ............................................................................................................ vii

List of Tables............................................................................................................. viii

Preface ......................................................................................................................... ix

List of Abbreviations.................................................................................................... x

Glossary ...................................................................................................................... xi

Structured Abstract.................................................................................................... xiii

1.0 Chapter One - Introduction ............................................................................... 1

1.1 Introduction ................................................................................................... 1

1.2 Background – Industry Wide Problems ........................................................ 3

1.3 Rationale for Study ........................................................................................ 4

1.4 Research Aim and Objectives ....................................................................... 6

1.5 Research Scope .............................................................................................. 6

1.6 Research Design ............................................................................................ 7

1.7 Research Structure ......................................................................................... 7

2.0 Chapter Two - Literature review ....................................................................... 8

2.2 Part A -The problem of Production Information Quality................................... 8

.............................................................. 8 2.2.1 Design Documentation Quality

The Extent of the Problem ..................................................................... 8 2.2.2

General Causes of Poor Quality Production Information ...................... 9 2.2.3

Fragmentation ...................................................................................... 11 2.2.4

Problems with Information Management............................................. 13 2.2.5

iv

Problems with the Existing 2D Drawing-based Design Documentation2.2.6

14

Rework ................................................................................................. 16 2.2.7

2.3 Part B – Solutions ........................................................................................ 17

Introduction .......................................................................................... 17 2.3.1

Drivers for BIM - Government Intervention ........................................ 17 2.3.2

The BIM based Design Paradigm - What is BIM? .............................. 19 2.3.3

The BIM based design paradigm ......................................................... 20 2.3.4

Inherent Characteristics of the BIM Based Design Paradigm ............. 21 2.3.5

....................................................................... 23 2.3.6 General Benefits of BIM

BIM maturity Level 2........................................................................... 24 2.3.7

PAS 1192-2 .......................................................................................... 27 2.3.8

The Information delivery cycle ............................................................ 28 2.3.9

Collaborative Working within the context of PAS1192-2. .................. 29 2.3.10

BIM Model Federation ......................................................................... 30 2.3.11

Specific benefits of federated BIM models .......................................... 30 2.3.12

Improved Visualisation and 3D Design Review .................................. 31 2.3.13

Design coordination and Model Checking ........................................... 31 2.3.14

Multi-disciplinary Integration and Simultaneous working .................. 33 2.3.15

3.0 Chapter Three - Theoretical Framework ......................................................... 34

3.1 Introduction ................................................................................................. 34

3.2 Theoretical Framework for the Study ......................................................... 35

3.3 Principal Factors Affecting the Quality of Production Information ............ 36

3.4 Strategic countermeasures under PAS1192-2 ............................................. 38

4.0 Chapter Four - Research design ...................................................................... 41

4.1 Introduction ................................................................................................. 41

4.2 Rationale for Research Paradigm ................................................................ 42

v

4.3 Rationale for Inductive research approach .................................................. 43

4.4 Rationale for Qualitative Research Method ................................................ 44

4.5 The Research Sample .................................................................................. 46

4.6 Data Collection Method .............................................................................. 48

4.7 Interview Schedule, Pilot Interview and Interview Process ........................ 49

4.8 Data analysis and synthesis ......................................................................... 50

4.9 Ethical Considerations ................................................................................. 51

4.10 Issues of trustworthiness ......................................................................... 52

5.0 Chapter Five - Data Analysis and Discussion ................................................. 53

5.1 Data Analysis and Discussion ..................................................................... 53

5.2 Factor 1: Virtual prototyping ....................................................................... 55

5.3 Factor 2: Visualisation and Understanding ................................................. 56

5.4 Factor 3: Upfront Investment Driving Downstream Value ......................... 57

5.5 Factor 4: Process Rigour and Transparency ................................................ 59

5.6 Factor 5: Information Cohesion, Integrity & Automation .......................... 61

5.8 Factor 6 - User capability and organisational BIM maturity ....................... 62

5.9 Factor 7 - Harnessing the Potential of Innovative BIM technologies ......... 63

5.10 Factor 8: Balancing Risk and Reward ......................................................... 64

5.11 Factor 9: Integration Barriers ....................................................................... 67

5.12 Summary of Findings................................................................................... 70

6.0 Chapter Six – Conclusions .............................................................................. 73

6.1 Introduction ................................................................................................. 73

6.2 Conclusions ................................................................................................. 73

6.3 Recommendations ....................................................................................... 77

6.4 Limitations of the Study .............................................................................. 79

6.5 Recommendations for Future Research ...................................................... 80

References .................................................................................................................. 81

vi

Bibliography ............................................................................................................... 87

Appendices ................................................................................................................. 89

Appendix A: The seven core components of Level 2 BIM ................................... 90

Appendix B: Fundamental principles of Maturity Level 2 BIM. .......................... 92

Appendix C: Summary of Research Design .......................................................... 94

Appendix D: Interview protocol and Semi-Structured Interview questions. ........ 95

Appendix F: Extract from Thematic Analysis of research data ............................. 97

vii

List of Figures

Figure 1 2012 UK Industry report based on Key Performance Indicators .................. 3

Figure 2: The Over the wall approach.......................................................................... 8

Figure 3: Cause and effect separated by time and location. ......................................... 8

Figure 4 Some common connotations of multiple BIM terms ................................... 19

Figure 5 Illustration of data integrity across 2D CAD and BIM design paradigms. . 21

Figure 6 Short and long term benefits of BIM. .......................................................... 24

Figure 7 BIM Maturity Levels. ................................................................................. 25

Figure 8 The central relationship between PAS1192:2 and the Government Strategy

documents .................................................................................................................. 27

Figure 9 The Information delivery cycle in PAS1192-2 ............................................ 29

Figure 10 Functions of an integrated virtual BIM model ......................................... 30

Figure 11 The ‘Mcleamey Curve. .............................................................................. 33

Figure 12 Theoretical Framework for the study. ...................................................... 35

Figure 13 Root cause Analysis. .................................................................................. 37

Figure 14 The Interrelationship of Factors affecting the quality of Production

Information ................................................................................................................. 54

viii

List of Tables

Table 1 Inherent Characteristics of BIM associated with production information .... 22

Table 2 Bew-Richards maturity levels explained ...................................................... 25

Table 3 Revised Requirements for Level 2 BIM ....................................................... 26

Table 4 Summary of Categories and concepts contained within the Theoretical

framework .................................................................................................................. 40

Table 5 Rationale and selection of Qualitative research method for the Study ......... 45

Table 6 Research Sample Information and Demographic ........................................ 47

ix

Preface

The motivation for carrying out this study into the impact of BIM based design on

the quality of Production Information stems for the author’s prior working

experience of the challenges, inefficiencies and responsibilities faced when

attempting to deliver high quality contract documentation documents in sub-optimum

project environments. Within this context, this can be taken to mean using traditional

2DCAD based tools and processes with uncollaborative standard forms of contract

and unrealistic design programmes. These arguably typical conditions have been

found to be unconducive to success and a major source of inefficiency in a

substantial body of literature.

Fortunately for many, the long term aspiration for fundamental change to industry

practices has coincided with the advent of functional BIM technologies with a

progressive and ambitious Government Construction Strategy. The momentum this

has generated offers great potential to counteract many of the factors leading to poor

project performance. There are long standing cultural and institutional challenges

that must be also be addressed as part of any solution, however despite the lack of

holistic solutions many are experiencing for themselves the benefits of barriers

brought about by what represents a significant opportunity for industry improvement.

The purpose and scope of this research is therefore to investigate the relationship

between the theory of BIM based design and the practice as experienced by industry

practitioners who have experience of both 2DCAD and BIM based design

paradigms. It is the primary intention to identify the main factors that impact upon

the successful application of BIM. The secondary intention is to make practical

recommendations for organisations considering adopting BIM or for those who may

have already started their transition.

x

List of Abbreviations

BEP BIM Execution Plan

BIM Building Information Modelling

BIMM Building Information Modelling and Management

2DCAD Computer-aided design (Two Dimensional)

COBie Construction Operations Building Information Exchange

DBB Design Bid Build

D&B Design & Build

DFMa Design for manufacture and assembly

FM Facility Management

gbXML Green Building XML

IFC Industry Foundation Classes

IPD Integrated Project Delivery

M&E Mechanical & Electrical

NBS National Building Specification

PAS Publically Available Specification

PoW Plan of Work

RIBA Royal Institute of British Architects

xi

Glossary

Computer-aided design (CAD): is the use of computer systems to assist in the

creation, modification, analysis, or optimisation of a design. CAD software is used to

increase the productivity of the designer, improve the quality of design, improve

communications through documentation, and to create a database for manufacturing

(Narayan, K. Lalit, 2008).

Collaborative BIM: Collaborative BIM is the converse of Lonely BIM and can be

construed as being when all designing parties are utilising BIM. There is, however,

no agreement as to whether level 2 BIM is truly ‘collaborative’, although if all

parties are producing 3D models and working collaboratively then there is no reason

for this not to be the case. (Sincalir, 2013)

Common Data Environment (CDE): A single location (typically a server or

extranet) for storing information that can then be collated, managed and disseminated

amongst multi-disciplinary teams working collaboratively (BSI, 2013).

Federated Model: means a Model consisting of connected but distinct individual

Models.

Information Model: all documentation, non-graphical information and graphical

information which the Project Team is required to provide into the Information

Model by the Scope of Services for the Project Team and which is provided for the

purpose of delivering Project Outputs (BSI, 2013).

PAS1192: Specification for information management for the capital/delivery phase

of construction projects using Building Information Modelling.

Project BIM Protocol: The Project Specific BIM Protocol setting out the

obligations of the principal members of the Project Team in respect of the use of

BIM on the Project.

Project Information Plan: the plan for the structure and management and exchange

of information from the Project Team in the Information Model and the related

processes and procedures.

xii

Production Information: Construction project Information Committee (CPIC)

defines production information as ‘the information prepared by designers that is

passed to a construction team to enable a project to be constructed’ (BSI, 2007).

4D (time) BIM: The intelligent linking of individual 3D CAD components or

assemblies with time- or schedule-related information. The use of the term 4D is

intended to refer to the fourth dimension: time, i.e. 4D is 3D plus schedule (time).

5D (cost) BIM: The ability of BIM models to contain cost information and quantity

schedules.

6D (FM) BIM: The intelligent linking of individual 3D CAD components or

assemblies with all aspects of project life-cycle management information. The

principal means of achieving this is by adding data to the model as the project

develops.

xiii

Structured Abstract

Background: Building Information Modelling (BIM) is a core enabler of digitally

enabled design and construction practices. It offers the potential for

significant improvements in the quality of Production Information

and overall project performance. As such it represents a major

opportunity for change and improved project delivery.

Aim: The aim of the study was to identify and explain the factors associated

with the delivery of improved Production Information quality using

BIM enabled design practices.

Research

Design:

This study used existing theoretical sources to identify the factors

leading to poor quality Production Information. Additionally, the

requirements of PAS1192-2 were introduced to contextualise the

mandated use of BIM based design solutions.

Primary research was carried out using an inductive/qualitative

approach via in-depth semi-structured interviews with seven

experienced project professionals primarily from the Architectural

industry.

Findings:

Nine core factors were identified via a Thematic analysis of the data.

User capability was found to be the most important positive factor in

the delivery of quality Production Information, irrespective of the

design platform used. Uncollaborative procurement practices

incompatible with the workflow required by BIM enabled design

were found to be the most important negative factor, which prevents

discipline integration and erodes the potential presented by BIM

enabled working practices.

Conclusions:

BIM based design presents significant opportunities at both a

business and project level for organisations willing and able balance

the risks and rewards of investment in innovative technology and

development of a capable project team. The study concluded with

twelve recommendations for practice.

Keywords: BIM, Production Information, Quality, PAS1192-2, Rework.

1

1.0 Chapter One - Introduction

1.1 Introduction

The body of evidence supporting the case for a change to the way in design

information is produced and managed has led many, including the UK Government

to embrace the uncertainty of adopting Building Information Modelling, as the

mechanism to instigate wide ranging process changes with the intention of making a

fundamental improvement in the construction project design and delivery process.

In understanding the context of this phenomenon it is necessary understand the

background to the problem and to briefly explain the relationships between three

concepts underpinning the context of the discussion; Building Design, Quality and

Production Information.

Firstly, by defining building design one is able to see how the process of constructing

a building is dependent on the translation of knowledge and information into

something physical that can be used to understand the creative intentions of the

designer, hence building design can be defined as;

‘…a process which maps an explicit set of client and end-user requirements

to produce, based on knowledge and experience, a set of documents that

describe and justify a project which would satisfy these requirements plus

other statutory and implicit requirements imposed by the domain and/or the

environment’ (Hassan,1996).

The provision of graphical and written representations, traditionally in the form of

drawings and specifications allow contractors and subcontractors to transform

concepts and ideas into physical reality. How effectively and efficiently this

transformation occurs, depends largely on the quality of the design and

documentation provided (Tilley and Barton 1997). The assessment of design and

documentation quality can be highly subjective and open to interpretation, when

considering design quality, McGeorge (1988), stated that:

“…a good design will be effective (i.e. serve the purpose for which it was

intended) and constructible with the best possible economy and safety.”

2

But whilst the design itself needs to be ‘effective’, it also needs to be communicated

effectively through the documentation (i.e. drawings, specifications, etc.). When

documentation quality is considered, a number of criteria determine the level of

quality and it is these which form the basis of understanding quality in the context of

this research; (Tilley, 2005).

• Timeliness - being supplied when required, so as to avoid delays;

• Accuracy - free of errors, conflicts and inconsistencies;

• Completeness - providing all the information required;

• Coordination - thorough coordination between design disciplines; and

• Conformance - meeting the requirements of performance standards

and statutory regulations.

Therefore, the quality of the design and documentation process can simply be

defined as:

‘The ability to provide the contractor with all the information needed to

enable construction to be carried out as required, efficiently and without

hindrance’ (Tilley, 2005).

For the purposes of this research the information needed to enable construction will

be referred to as Production Information and is defined as ‘the information prepared

by designers that is passed to a construction team to enable a project to be

constructed.’ In a BIM working environment the delivery may take the form of

three-dimensional models with associated information attached by direct attribution

or population from a database (BSi, 2007). For the purposes of this research the term

is also taken to be used interchangeably with the terms, ‘Contract Documentation’,

‘Working drawings’ and ‘Design Documentation.’

The quality of Production Information remains a major concern to many parties

within the construction industry as it has a major influence on the overall

performance and efficiency of construction projects (Burati et al 1992).

3

1.2 Background – Industry Wide Problems

The need for the Construction industry to improve performance is well recognised. In

the UK, Construction is a significant economic activity which contributes some 7%

of GDP and is worth about £110 billion per annum - more if the whole-life

contribution through planning, design, construction, maintenance, decommissioning

and reuse, is taken into account (Cabinet office, 2011). Yet performance remains

poor against a wide range of benchmarks (See Figure 1 below) and consistently fails

in its capacity to deliver value to industry stakeholders.

The defining characteristics of the UK construction industry are its inability to

complete projects predictably and its chronically low levels of profitability (Crotty

2012). Thus the need for improvements in the construction industry has long been

recognised. Two major reports from the nineties began reform and mapped the

process to change the construction industry. 'Constructing the Team' by Latham,

condemned existing industry practices as being'...ineffective, adversarial,

fragmented, and incapable of delivering for its customers.’ Latham wished to delight

clients by promoting;

‘Openness, co-operation, trust, honesty, commitment and mutual

understanding among team members,’ calling for industry ‘to increase

efficiency and to replace the bureaucratic, wasteful, adversarial atmosphere

prevalent in most construction projects at the time' (Latham 1994).

Figure 1 2012 UK Industry report based on Key Performance Indicators (Adapted from

Constructing Excellence, Author)

4

Of the recommendations in the report, the most notable with reference to this

research included the following;

'The use of co-ordinated project information should be a contractual

requirement.'

However in the last two decades while most other industries have managed to

improve considerably in most aspects of their performance, construction has failed to

show any such improvement (Crotty, 2012). Latham’s aspirations have remained on

the agenda right up until and including today.

1.3 Rationale for Study

With the advent of widespread adoption of Building Information Modelling, the

potential to significantly realise the benefits of improved collaboration and digital

design and fabrication are promising developments in the industry. Over time it is

hoped that BIM will help to reduce the prevailing failure and achieve a higher level

of quality and performance. Capitalising on the opportunity for change, the UK

government has embarked on an ambitious programme of 'mobilisation and

implementation,' (Cabinet Office, 2011) that in order to exploit BIM technology and

design, create and maintain assets more efficiently (BIS, 2011). This premise is

supported a growing body of research which suggests BIM can enable a number of

benefits including time and cost reductions throughout the project life cycle (Bryde

et al, 2013).

In 2014 the UK government has published the results of the Ministry of Justice

Cookham Wood trial project. This appears to have realised an overall cost saving of

20 per cent and a host of other benefits, however these results were achieved not only

through BIM, but also a synthesis of other new procurement initiatives that promote

collaborative working. These included Lean Principles, BIM, Soft Landings, Two

Stage Tendering with early Contractor Engagement and Project Bank Accounts

(BIM Task Group, 2014). While this case study appears to demonstrate success, it

does acknowledge a number of challenges that remain to be overcome. The

challenges for other less high profile projects are likely to be more significant.

5

Examples from the literature include Erodogan, Anumba, Bouchlaghem and Neilson,

(2008) who suggest that companies adopting BIM technologies often fail to achieve

the full benefits of their implementations. The reasons for this were found to be

focusing too much on the technical factors and ignoring or underestimating the

factors related to change, implementation, human and organisational factors and the

roles of management and end users. Similarly, a study by Neff, Fiore-Silvast and

Dossick, (2010) found that most architects were using BIM primarily for

visualisation and analysis instead of increased collaboration and that deeply

embedded disciplinary thinking is not easily overcome by digital representations of

knowledge.

Lu, Zhang and Rowlinson, (2013) suggest BIM adoption in isolation does not change

the fragmented nature of the construction sector and that an understanding of how to

realise a more holistic and collaborative approach in BIM projects is crucial to realise

its full potential. This view is supported by Bouchlaghem, (2011) who suggests that

effective collaboration cannot result only from the implementation of information

systems or approaches that focus exclusively on sociological, organisational or

cultural issues. In order to extract the best possible, any effective implementation of

BIM has to involve a fundamental change in the working procedures in the project

delivery process; a cultural shift the key challenge. (Philp; 2012; Eastman et al,

2011).

The mandated BIM protocols aim to harness the benefits of best practice and

navigate the industry towards greater efficiency. However, as discussed above

organisations will encounter a number of Technology, Process and People (TPP)

related issues during their transition to collaborative BIM working. The rationale for

this study is therefore to identify what factors are currently being experienced by

industry professionals, which factors are the most important and what factors are

preventing project organisations from realising further value for themselves and

other stakeholders. Similarly the research intendeds validate the benefits reported in

the literature with those experienced in practice in order to understand how greater

BIM can be used to greatest effect.

6

1.4 Research Aim and Objectives

In consideration of the preceding paragraphs, the aim of the study is to investigate the

factors associated with the delivery of improved Production Information quality using

BIM enabled design practices.

In support of this aim the research has the following objectives which must be

achieved;

1. To review the literature and identify core the factors resulting in poor quality

Production Information.

2. To review the core principles of PAS1192-2 in conjunction with the literature

to establish how BIM based design impacts upon the process of delivering

Production Information.

3. To interview a sample of industry practitioners to explore their experiences of

BIM enabled working practices when compared to the traditional (2D CAD)

design paradigm.

4. To analyse the research data, to identify and explore the emergent factors

affecting the quality of Production Information using BIM enabled design

processes.

5. To conclude the study with a series of recommendations that can assist design

organisations in maximising the potential of BIM enabled design processes.

1.5 Research Scope

The scope of this primary research is focused upon the views of architects and the

buildings they design. This is because architects often act in the role of Lead

Designer and as such are more likely to have a holistic view of the changes brought

about by BIM. The delivery of Production Information is the area of work in which

particular focus is paid and factors concerning pre-planning and post occupancy

project stages are generally excluded from the scope. Similarly the framework within

which BIM functionality and the research questions are discussed is PAS1192-2,

however owing the time restrictions of the dissertation and the wide ranging

implications contained within this document, the study focuses only on selected

relevant aspects of this document.

7

1.6 Research Design

In consideration of the nature of the aims and objectives for this study, an approach

was taken which would enlist beliefs, opinions and views to gather data, which was

rich in content and scope and open to interpretation (Fellows and Liu, 2003). A

qualitative approach to the research was therefore selected. The primary data was

obtained by conducting semi-structured interview interviews. The secondary data

was obtained from academic journals and government publications. Data analysis

was conducted using a Thematic analysis approach using descriptive and interpretive

coding process. Refer to Chapter four for full details of the Research Design.

1.7 Research Structure

This study is organised as follows;

Chapter 2 presents the Literature review which is broken into 2 parts:

Part A explores the problem of poor quality Production Information.

Part B explores proposed solutions at strategic and functional levels.

Chapter 3 – Concludes the findings form the literature review and presents the

theoretical model for the study.

Chapter four discusses the Research Design, the rationale for the methodology

selected, research ethics and data analysis, and specifies key characteristics of the

research participants.

Chapter five encompasses data analysis, discussion and summary of findings.

Chapter six presents the conclusion, the recommendations, the limitations and

opportunities for future research.

8

2.0 Chapter Two - Literature review

2.2 Part A -The problem of Production Information Quality

2.2.1 Design Documentation Quality

The importance of a new paradigm for managing the design and documentation

process and improve quality is now widely recognised as low quality Production

Information has been identified as a major factor in leading to a reduction in the

overall performance and efficiency of construction projects. As such it can be

directly attributed to variations, delays, disputes, cost overruns and rework (Love &

Li 2000; Tilley, 2005).

The literature reveals a common theme of deficient practice leading to poor quality.

The major issues are indicated below (Swelinger, 1996; Koskela, 1997; Tilley et al.

2002);

1. Poor communication of brief

2. Lack of adequate documentation

3. Deficient or missing input information

4. Poor information management

5. Deficient planning and unbalanced resource allocation

6. Lack of coordination between disciplines

7. Erratic decision making

8. Client changes

2.2.2 The Extent of the Problem

The extent of the substandard, incomplete, conflicting and erroneous design and

documentation information is not only widespread but continues to get worse despite

the negative impact on the industry (Tilley et al.2002). According to Barrett and

Barrett (2004) ‘…projects that run over time and budget are often underpinned by

faulty documentation that looks professional, but in fact does not properly specify or

describe the built solution.’

9

A report by NEDC showed that more than 50% of problems on building sites were

related to poor design information (NEDC, 1987). While according to Hibberd

(1980), 60% of variations were directly design documentation related. Similarly

during a study of defects in construction performed during the period 1986–1990 and

a deeper study performed during 1994–1996, it was found upon analysis that, on

average, 32% of the defect costs originated in the early phases, i.e., in relation to the

client and the design. (Josephson and Hammarlund, 1998). According to Love et al

(1997) a large proportion of rework cost were not only attributable to deficiencies in

design and documentation but also to the transfer of information during the design

process.

2.2.3 General Causes of Poor Quality Production Information

The causes of poor documentation can in part be attributed to the complex and

challenging nature of the design process as it involves thousands of decisions,

sometimes over a period of years, with numerous interdependencies, under a highly

uncertain environment (Tzortzopoulos & Formoso, 1999). In addition, many of the

traditional project management approaches are inappropriate for managing the design

process. For example, the design planning process is typically unstructured which

leads to insufficient understanding of the design process between parties and is a

barrier to people working effectively together (Taylor, 1993), while, Alarcón and

Mardones ,(1998) found that there is a lack of standards and a lack of constructability

of the designs.

Additionally, DeFraites (1989) suggests that overall project quality is greatly

determined by the level of professional services provided and that the quality of these

services is generally determined by how the services are selected and how the fees

are negotiated. Clients that select designers with the misunderstanding that low fees

or ‘cheapness’ can equate to value have been found to experience a limited level of

quality of service and expertise which generally translates into additional project

costs to the owner (Tilley, 2005).

10

Known factors which are the result of low fees include the use of inexperienced staff

that lack technical knowledge (Coles, 1990), as well as ‘time boxing’ which is where

design tasks are allocated to a specific duration, irrespective of whether the

documentation or each individual task is complete or not (Love et al., 2000).

Furthermore Tilley, (2005) suggests that while insufficient design fees are considered

to be the main problem by a large proportion of the industry, insufficient time to

properly carry out the design process, runs a very close second with unrealistic client

demands for earlier completion of projects being a major contributing factor to the

production of incomplete and erroneous contract documentation (Tilley and

McFallen, 2000).

In a survey by Tilley et al. (2002), it was found that the availability of design time

had declined by 37% over the previous 12–15 year period, but in contrast designers

generally spend around 20% more time on a project than was initially budgeted for.

Notably the survey also reported an industry perception that if more time was

allowed for the design and documentation process, then quality would improve.

11

2.2.4 Fragmentation

The integration of design process and all of all key players into a multi-disciplinary

team at both project management and design implementation levels is vital to project

success (Kagioglou et al, 1998).However, the design process is marred by

inefficiencies from fragmentation (Gallaher, O'Connor, Dettbarn, & Gilday, 2004).

The increasing complexity of building design has tended to lead to the specialisation

of professionals with many disciplines having their own distinct body of knowledge,

culture and commercial objectives which fosters competition based on values

associated with each party’s specialty (Ballard, 1999). This un-integrated and

sometimes adversarial working methodology of focusing on one’s own process with

little attention on the development of the whole project process exacerbates the

problem and is generally known as ‘working in silo’s.’ This is where disciplines

work independently of one another while making decisions that inevitably affect the

outcome of what is intended to be a coordinated design product (Karhu and

Lahdenpera, 1999).

This way of working is also characterised by Evbuomwana & Anumba, (1998) as the

‘over the wall approach,’ (See Figure 2 below) where based on the clients brief, the

architect produces an architectural design, which is the given to the structural

engineer, who the passes the project on to the quantity surveyor and so on until the

project documentation is passed onto the contractor who takes responsibility for the

construction.

Figure 2 The Over the wall approach (Evbuomwana, Anumba, 1997)

12

As a result, fragmentation leads to poor communication between the architects,

engineers, contractors and owners leading to a number of detrimental consequences,

including:

Inadequate capturing translating, transforming and delivering (CTTD) client

needs (Shahrin and Johansen, 2013)

Data loss caused by the fragmentation of design, resulting in inefficiencies

due to the inability to reuse information; data generated at one stage are not

readily re-used downstream;

Development of pseudo-optimal design solutions;

The lack of integration, co-ordination and collaboration between the various

functional disciplines involved in the life-cycle-issues of the project;

The fragmentation of design and construction data, leading to

misunderstandings, misconceptions, clashes , omissions and errors

The lack of true life-cycle analysis of projects (including costing,

maintenance, etc.);

and poor communication of design intent and rationale which leads to

unwarranted design

Changes, unnecessary liability claims, increase in design time and cost, and

inadequate pre- and post-design specifications.

Elimination of viable design alternatives due to pressure of time;

Prevalence of costly engineering changes and design iterations;

Characterization of the design process with a rigid sequence of activities;

13

2.2.5 Problems with Information Management

A number of studies have highlighted both the extent (Hendrickson and Au, 2003)

and importance (Howell, 1999) of information management activities in

construction. Owen et al. (2010) neatly sums up the current situation;

“In general, silo mentalities and cultures prevail and document-based

information exchange across professions and throughout supply chains

ensures that information and, particularly, any associated intelligence,

coordination and agility is either corrupted or even lost. Thus decisions are

frequently made autonomously without multidisciplinary participation, and in

the absence of holistic or comprehensive and accurate knowledge. The use of

an iteratively and incrementally developed design, pulled from an end user or

client perspective, is virtually impossible within current structures, or at least

rarely achieved.”

The principal design activity of any project is the processing of information (Baldwin

et al, 1994) yet as described above this is poorly performed (Latham, 1994).

Jacobsson and Linderoth (2010), found that owing to the transient nature of project

teams the drive to deploy better information management technologies is limited.

Similarly, research suggest that information management and exchange within

construction typically still take place manually, predominantly through the use of

schedules which individuals or organizations reformat and manually distribute

normally on a document level (Dawood et al., 2002;Anumba et al., 2008). The

seemingly archaic delivery of information results in wasted time and money when in

data is lost through information exchange, the wasted time taken to identify the

useful information in a document or searching through incomplete, uncoordinated

information which leads to inefficiencies of rework (Anumba et al., 2008). When

Information Management suffers from multiple problems of this kind, this can lead

to the abandonment of design planning (Koskela et al, 1997), perpetuating a cycle

likely to create further difficulties. In addition, the fragmented nature of the

construction industry frequently leads to incompatibilities in semantics, process and

software between collaborating organizations amplifying the waste mentioned above

(Abukhder and Munns, 2003; Anumba et al., 2008).

14

2.2.6 Problems with the Existing 2D Drawing-based Design Documentation

Modern construction projects and the organisational structures which support their

delivery can be extremely complex and communications intensive. On a

conventional 2D CAD/paper based project of modest size this may give rise to a

huge body of 'unintelligent ' information. For example, in 1995 a European

construction IT R&D project found that up to 400 individual documents, or

documents about documents, are generated for every million pounds worth of project

value (CICC 1998). It was also found that there may be up to 60 consulting and

contracting firms in a typical £50m project. The problem therefore appears to be not

a lack of information in itself, but rather ‘…a problem in the lack of information

made for decision-making’ (Winch, 2010).

Crotty, (2012) has suggested conventional drawing-based design documentation,

suffers from four main deficiencies:

1. The use of arbitrary lines and symbols lead to ambiguity and

misunderstanding.

2. It can be difficult to ensure that individual document sets are properly and

internally consistent.

3. It can be difficult to ensure that related document sets are correctly

coordinated.

4. It can be difficult to ensure that the documentation is fully complete.

These deficiencies then lead to 2 main problems;

Firstly, owing to these inherent flaws, the output of the design production process is

essentially of low quality and untrustworthy. Secondly, the information is basically

incomputable and anybody wishing to reuse it has to reconstruct the data, either via

computer if the data is to be reused, or intellectually in one's mind if one attempts to

visualise the 3D form of a design conventionally delivered in 2D on paper.

15

The fundamental problem with this process is explained by Barker (2011), who

suggests;

‘2D CAD essentially replicates the single line graphical processes of the

drawing board and, with a few exceptions, involves the use of unintelligent

unrelated objects. This method of working has been unable to keep up with

the demands of a very risk averse industry which demands greater certainty

in design, cost and programme whilst accommodating increasing levels of

complexity and depth in the information to be delivered.’

It appears that drawing-based design is flawed and a root cause 3 major problems;

Firstly, the clients inability to accurately visualise the design; secondly, the difficulty

of integrating and coordinating cross-disciplinary design information and; thirdly, the

limited ability of contractors to accurately visualise in detail the designer's intentions

(Crotty, 2012).

In general, any piece of discipline specific design or technical information that needs

to be interpreted or coordinated manually requires skill and judgement on the part of

the recipient. It may therefore give rise to errors in understanding and

communication, particularly on complex cross-referenced documentation that is

typical in most construction projects.

16

2.2.7 Rework

Rework is a recognised as a significant factor contributing to poor project

performance. It is defined by Love, (2002) as ‘the unnecessary effort of redoing a

process or activity that was incorrectly implemented the first time.’ Rework

contributes towards delays and cost increases which Barber et al, (2000) found can

be as much as 23% of contract value when taking into account indirect costs which

are the cost of man hours to redesign and manage the deficient documents. This is

separate to the actual (direct) cost of the rectification, such as additional hiring of

resources (including labour and plant), schedule slippage, and reductions in project

scope or quality (Li et al., 2000). Rework is characterised by Eden et al., (2000) as

being hidden within the design documentation as a latent defect, giving the illusion

that the project is progressing smoothly until the latter phases of the project when the

errors are discovered resulting in rework and delay at a time when the impact of

design changes are at their highest. The cause and effect by time and location of

errors in a project is illustrated in Figure 3 below. This shows a (typical) example of

a dimensional error as found in a case study by Love, (2004). The source of the error

resides in the processes and interfaces of the design consultants but is hidden by time

and location, identified and resolved only during construction phase. Ackermann et

al., (1997) (cited in Love 2004) found that adverse consequences of these problems

include higher overall costs and profit loss, delay, reputational damage and costly

litigation over responsibility ultimately leading to risk avoidance among the design

consultants which may transpire as reluctance to sanction the approval of each

other’s work resulting in poor coordination and integration of design team members,

perpetuating the cycle of low productivity and quality.

Figure 3 Cause and effect separated by time and location. (Love, 2004)

17

2.3 Part B – Solutions

2.3.1 Introduction

In Part B of the literature review the intervention that the UK government has taken

to improve the performance of the industry is introduced. This is followed by a brief

introduction to BIM and the requirements for BIM level 2 compliance. Specific

aspects of PAS1192-2 are then discussed in terms of the functionality they enable.

2.3.2 Drivers for BIM - Government Intervention

In 2011, the most recent Government Construction Strategy was launched with the

aim of promoting the public sector as a better client, ‘more informed and better co-

ordinated.’ It also aims to modernise the current business model to reduce overall

costs of Government construction projects by 15-20% (Cabinet Office 2012). Setting

out a range of activities to reform industry practice, reduce waste and drive better

value from its procurement of construction, the hypothesis was that ‘…the

Government as a client can derive significant improvements in cost, value and

carbon performance through the use of open sharable asset information’(HMG Task

Group, 2011).

The fundamental characteristic of the strategy was the recognition and inclusion of

Building Information Modelling; ‘…Government will require fully collaborative 3D

BIM (with all project and asset information, documentation and data being

electronic) as a minimum by 2016’ (Cabinet Office, 2011, p. 14).

By doing so the UK Government aims to strengthen the public sector’s client

capability in BIM implementation so that all central government department projects

will be adopting at least Level 2 BIM by 2016 (Cabinet Office, 2012, p. 6).

In support of these objectives the BIM Strategy Paper (2011), recommended giving a

‘push’ to the supply side of industry to enable all players to reach a minimum

performance level in the area of BIM use within 5 years (BIS, 2011). Similarly, the

report advocated a ‘pull’ from the client side to specify, collect and use the all the

derived information in a value adding way.

18

Moreover, and in support of the strategic objective, the Cabinet Office began to

develop standards enabling all members to work collaboratively because in its

opinion the;

‘…lack of compatible systems, standards and protocols, and the differing

requirements of the clients and lead designers, have inhibited widespread

adoption of a technology which has the capacity to ensure that all team

members are working from the same data’ (Cabinet Office, 2011, p. 13).

19

2.3.3 The BIM based Design Paradigm - What is BIM?

A review of the literature on BIM reveals a plethora of definitions and descriptions

of BIM. Much of the confusion surrounding BIM can be attributed to its potential to

affect many aspects and actors of the Construction delivery cycle. Figure 4 below

gives an overview of some common connotations associated with BIM;

Without being actively involved in BIM related activities it may be difficult for

individuals or organisations to grasp the holistic nature of BIM. The term and

concept of ‘BIM’ is multifaceted and unsurprisingly there is no definitive or agreed

upon definition. It is therefore important to understand each of the main aspects that

BIM represents. It firstly be thought of ‘a technological entity;’ the Building

Information Model itself; (which is essentially a database)

‘…a data-rich, object-oriented, intelligent and parametric digital

representation of the facility, from which views and data appropriate to

various user’s needs can be extracted and analysed to generate information

that can be used to make decisions and improve the process of delivering the

facility’ (Azhar, Hein and Sketo, 2008).

Secondly, it can be thought of as Building Information Modelling, ‘a process’ which

involves; ‘… the structured creation, sharing, use and re-use of digital information

about a building or built asset throughout its entire lifecycle, from design through

procurement and construction and beyond, into its operation and management. This

involves the use of coordinated 3D design models enriched with data which are

Figure 4 Some common connotations of multiple BIM terms (Succar, 2009, p. 359).

20

created and managed using a range of interoperable technologies.’ (BIM Academy,

2012).

Thirdly, the view of BIM as ‘a way of working’ which encompasses both Building

Information Management and Modelling. This last view of BIM (or BIMM) is

described as;

‘…an interoperable process for project delivery, defining how individual

teams work and how many teams work together to conceive, design, build

and operate a facility.’ (buildingSMART alliance, 2012)

If organisations use BIM in a way in which each of the three aspects is not

overlapped or integrated the potential of BIM is diminishes. Hence the terms ‘lonely

BIM’, ‘partial BIM’ and ‘collaborative BIM’ also arise.

For the purposes of this research the term ‘BIM’ can be taken to mean the resultant

change effected by a synergy between each of these aspects; From the technological

perspective the BIM database becomes the central repository of digital design data

enabling value generating processes to efficiently control and manipulate aspects

virtual prototype while also facilitating a collaborative and open methodology of data

exchange for the mutual benefit of all project stakeholders which opens new

possibilities towards improving procurement practices with better communication

and co-ordination across the whole building-sector.

2.3.4 The BIM based design paradigm

As explained in section 2.10, BIM is a methodology to manage the essential building

design and project data in digital format throughout the building's life-cycle

(Eastman 2008; Penttilä 2006, cited in Succar 2009;) and as such has been termed the

‘new paradigm’ in building design technology (Ibrahim, Krawczyk, Schipporeit,

2004). The principal difference between BIM and 2D CAD is that the latter describes

a building by independent 2D views such as plans, sections and elevations composed

of lines, arcs and circles etc. While the former is made up of intelligent contextual

data, where objects are defined in terms of building elements and systems such as

spaces, walls, beams and columns (CRC Construction Innovation, 2007).

21

As discussed in Part A, efficiency losses caused by the flawed drawing based

paradigm are significant. BIM processes inherently counteract the data loss

experienced using paper based processes by storing all information digitally while

also making it easily readable to every person involved. Similarly, while drawing

based design fails in recapturing all information after each stage, BIM assists in

maintaining data integrity (Harty, 2012). A visual comparison of the information

integrity across the two platforms is illustrated in Figure 5 below;

Figure 5 Illustration of data integrity across 2D CAD and BIM design paradigms (BIM Task

Group, 2014).

2.3.5 Inherent Characteristics of the BIM Based Design Paradigm

In essence, Building Information Modelling is a digital representation of physical

and functional characteristics of a facility that create a shared knowledge resource for

information about it forming a reliable basis for decisions during its lifecycle (BIM

Industry Working Group 2011). The corollary of this is the reliability of the data.

Stemming from this is the validity and the trustworthiness of what is distributed or

available. Through a review of the literature the following Table 1 below describes

the inherent characteristics of BIM which positively impact upon the quality of

production information;

22

Inherent Characteristics

of BIM associated with

production information

Description

Maintenance of

Information and

Design Model Integrity

BIM models store each piece of information once and displayed the data

according to the output required by the user. In contrast the 2D paradigm

requires repetition of common information in multiple files and drawings

increasing the coordination effort required and to maintain consistency

between multiple representations of data which increases the work load and

risk of error.

Earlier and More

Accurate Visualisations

of a Design

The 3D BIM model is geometrically consistent and viewable in any

combination of real-time views and perspectives. It can be used to view any

number of design modifications giving an instant and real time update of the

effect of design changes to corresponding elements. This saves time and

effort and streamlines the process

Automatic Low-Level

Corrections When

Changes Are Made to

Design

The rules and relationships between model based parameters have an

inherent intelligence that automatically adjust geometrically to database

driven modifications which allow auto adjustment of corresponding

elements reducing the coordination and document management effort and

assisting to eliminate spatial coordination errors.

Generation of Accurate

and Consistent 2D

Drawings at Any Stage

of the Design

Accurate and consistent drawings can be extracted for any set of objects or

specified view of the project. This significantly reduces the amount of time

and number of errors associated with generating construction drawings for

all design disciplines. When changes to the design are required, fully

consistent drawings can be generated as soon as the design modifications are

entered.

Earlier Collaboration

of Multiple Design

Disciplines

By subdividing the BIM database simultaneous working is possible my

multiple design disciplines. Design issues are identified earlier and can be

resolved in innovative ways at a time when design changes cost less. It also

shortens the design time and leads to less errors and omissions.

Information

consistency and

reliability

As a ‘single source of the truth’ BIM models can be distributed to project

team members with confidence that the model contains the information as it

is intended to be viewed in a complete three dimensional form. This requires

less ‘reconstruction’ of information on the part of the receiver and enhances

communication, understanding and reliability of the information without

having to produce a series of drawings to adequately ‘frame’ the

information.

Table 1 Inherent Characteristics of BIM associated with production information (Adapted from

Sacks, Koskela, Dave and Owen 2010; Eastman el al. 2011)

23

2.3.6 General Benefits of BIM on the associated with Production of

Information

Research by McGraw Hill Construction, (2012) shows that generally the benefits of

BIM increase as teams get more collaborative. Of the short term benefits observed,

reduced documents errors and omissions as well as reduced rework were both in the

top 3 benefits as can be seen in Figure 6 overleaf. Similarly, in a case-study research

study by Barlish and Sullivan, (2012) reduced rework and improved coordination

and visualisation were included in the top 4 benefits reported. While according to

Azhar, (2011) the key benefit of BIM is its accurate geometrical representation of the

parts of a building in an integrated data environment. Other related benefits are;

Faster and more effective processes – information is more easily shared, can

be value-added and reused.

Better production quality – documentation output is flexible and exploits

automation.

Better customer service – proposals are better understood through accurate

visualisation. (CRC Construction Innovation, 2007).

Bryde, Broquetas, & Volm (2012) discussed the benefits of BIM based on their case

study and found the main benefits be to reduced cost and time, improved

communication, coordination and work quality. While according to Jernigan (2008)

and Love et al. (2011), use of BIM technology could reduce the chance of having

design changes, design errors, and improve the quality of design documentations.

Finally, Hansford, (2014) outlined a number of operational improvements that have

been found as a result of BIM Maturity Level 2 including Design visualisation, clash

detection and Constructability.

24

Figure 6 Short and long term benefits of BIM (McGraw-Hill, 2012).

2.3.7 BIM maturity Level 2

As part of the mandate for ‘fully collaborative 3D BIM’ the government published

what is known as the Bew–Richards maturity ramp (as illustrated in Figure 7

overleaf). The purpose of defining the levels from 0 to 3 was to in essence an

attempt to take the ambiguity out of the term BIM and;

‘…categorise the types of technical and collaborative working to enable a

concise description and understanding of the processes, tools and techniques

to be used’ (BIS, 2011).

However, despite being useful to as an aid to visualising the scale of BIM maturity

levels, much debate and ambiguity has remained. Table 2 Overleaf gives a brief

explanation of the requirements necessary for both information and modeling

management for each of the levels of the maturity ramp.

25

Figure 7 BIM Maturity Levels (Department of Business, Innovations and Skills, 2011, p. 16).

BIM Maturity

Level

Explanation/Details Information

management

Information

Modelling

0

2DCAD

Unmanaged CAD. Paper-based and it is characterised

by 2D CAD drawings.

No project wide common

standards for flow and

production of information

2D CAD and

paper issue

1

‘Lonely BIM’

Introduces the adoption of the 3D format, in addition

to 2D data, following the

British Standard BS1192:2007,

However, the model is created only for visualisation

purpose and information is not shared.

A project wide consistent

approach to information

flow (Common data

environment CDE)

2D/3D CAD

Produced

independently

by members of

the team

2

‘Collaborative

BIM’

A series of domain specific models (e.g. architectural,

structural, services etc.) with the provision of a single

environment to store shared data and information in

our case (COBie UK 2012). (BIM Task Group, 2014)

Possible 4D and 5D models are adopted in the

process.

A project wide consistent

approach to flow and

production of information

3Dmodels

produced by all

team members

to common

levels of detail

using common

tools

3

‘iBIM’

Level 3 is the higher level of the index and it is

characterised by an Integrated BIM

process where openBIM data are shared during the

overall lifecycle of the facility via web services. This

is a Vision and undefined.

As BIM level 2 Single project

model

Table 2 Bew-Richards maturity levels explained (By Author)

26

The original accompanying definition of Level 2 was as a ‘Managed 3D environment

held in separate discipline “BIM” tools with attached data. The approach may utilise

4D programme data and 5D cost elements as well as feed operational systems’ (BIS,

2011). However, in 2014 and in line with the ongoing development of the processes

and tools available, as well as with feedback from early adopter projects and other

industry experience, the UK Government refined its definition of level 2 BIM to

include the components as detailed in Table 3 below:

For a detailed description of each of the major components of BIM level 2 as listed

below, refer to Appendix A.

Government Construction Strategy Requirement Level

0

Level

1

Level

2

Data

2D Drawings (PDF) x x x

Discipline Specific 3D (native) x x

Non-Graphical Data (COBie-UK-2012) x

Documents

PAS91:2013 Construction Prequalification Questionnaires (Table 8) x

BIM Employer’s Information Requirements x

Pre-Contract BIM Execution Plan x

Post-Contract BIM Execution Plan x

BIM Protocol x

Collaboration

PAS 1192-2:2013 Specification for information management for the

capital/delivery phase of construction projects using Building Information

Modelling

x

BS1192:2007 Collaborative Information Production x

File-Based Collaboration & Library Management x

Model Federation x

Single Common Data Environment (CDE) x

Information Manager Role

PAS 1192-3:2014 Specification for information management for the

operational phase of construction projects using BIM

x

Government Soft Landings x

In development

Digital plan of works (dPOW) x

BS 1192-4:2014 Collaborative production of architectural, engineering and

construction information – Client information requirements

x

Classification System (UNICLASS2 ) x

Table 3 Revised Requirements for Level 2 BIM (adapted from BIM Task Group, 2014).

27

2.3.8 PAS 1192-2

Publically Available Specification (PAS)1192:2 ‘Specification for information

management for the capital/delivery phase of construction projects using Building

Information Modelling’ is a core publication of the Governments suite of documents

for delivering BIM level 2 compliance as illustrated in Figure 8 below. It is intended

that the use of the PAS is of equal value to small as well a multi-national practices as

the impact of poor information management and waste is potentially equal on all

projects (BSI, 2013). It is also intended to be adopted for both public and private

procurement firstly in the UK by becoming a British standard and then

internationally by becoming an ISO standard.

Figure 8 The central relationship between PAS1192:2 and the Government Strategy documents (BIM

Task Group, 2014)

28

2.3.9 The Information delivery cycle

Focusing specifically on the ‘delivery’ phase of projects (from strategic identification

of need through to handover of asset), PAS1192-2 communicates the explicit set of

requirements for working at BIM Level 2 by setting set out the framework for

collaborative working and providing specific guidance for the information

management requirements and structuring of design data associated with projects

delivered using BIM. The information delivery cycle contained in PAS describes the

process of accumulating of both ‘graphical’ and ‘non-graphical’ project data which

allows for the fact that all information on a project will be originated, exchanged or

managed in BIM format. By doing so PAS mandates all project information to be

managed in a consistent and structured way to enable efficient and accurate

information exchange. The mechanism used to regulate this process is BS119:2007

which is the existing code of practice for the collaborative production of

architectural, engineering and construction information.

Central to the information delivery cycle is the shared use of individually authored

models within the common data environment (CDE) which being a single source of

both BIM and conventional information for any given project, is used to collect,

manage and disseminate all relevant approved project documents for multi-

disciplinary teams (BSI, 2013;BIM task Group, 2014). Refer to Figure 9 overleaf for

a representation of the Information delivery cycle contained in PAS.

Refer also to Appendix B for further details on fundamental principles of Level 2

Building information modeling.

29

Figure 9 The Information delivery cycle in PAS1192-2 (Note the both information and management

processes) (BSI, 2013).

2.3.10 Collaborative Working within the context of PAS1192-2.

Collaboration is a highly complex and challenging activity in which a shared task is

achievable only when the collective resources of a team are assembled. Contributions

to the work are coordinated through communications and the sharing of knowledge

(Bouchlaghem, 2011). Collaboration can therefore said to be the alignment of

individuals, working towards the attainment of a common goal within a common

environment, where knowledge and other resources are shared, outcomes and

decision making is by consensus and communication, respect and trust is present

among the parties. Collaborative working can be taken to mean the coalition of

multi-disciplinary groups and teams temporarily formed to work together as a project

team to deliver greater benefits than they would otherwise be able to achieve

separately. PAS1192-2 makes explicit reference to ‘Collaborative working’, stating

that ‘In a collaborative working environment, teams are asked to produce

information using standardised processes and agreed standards and methods, to

ensure the same form and quality, enabling information to be used and reused

without change or interpretation’ (BSI, 2013).

30

2.3.11 BIM Model Federation

A key enabler of collaborative working practices using PAS is the requirement to

federate models for interdisciplinary working. A Federated Model is defined in the

CIC BIM protocol as ‘…a Model consisting of connected but distinct individual

Models’ (CIC, 2013). In practice discipline specific models will be combined to form

an integrated building model which in effect becomes a virtual building which can be

clearly observed, audited and subjected to a number of value adding analyses. Figure

10 below gives an illustration of a number of functions that the Virtual building

model can perform;

Figure 10 Functions of an integrated virtual BIM model (BIPS, 2008).

2.3.12 Specific benefits of federated BIM models on Production Information

The benefits of federated BIM models on Production Information can be generally

grouped under the following 3 categories;

Improved visualisation and 3D design review

Design coordination and model checking,

Multi-disciplinary integration

31

2.3.13 Improved Visualisation and 3D Design Review

One of the single biggest benefits of BIM is the ability to generate a dimensionally

consistent 3D model that can be used to visualise the design at any stage of the

process (Eastman, 2011). This 'what you see is what you get' functionality resolves

the problem of understanding and interpretation highlighted in Part A of the literature

review. It enables a consistent baseline for communication and understanding,

reducing the room for ambiguity and enabling design problems to be solved

innovatively and collaboratively, ultimately leading to better decisions.

Similarly, the real-time geometrically consistent visualisation benefits inter-

disciplinary coordination, as BIM models can be shared amongst multiple

geographically diverse project design team members, using agreed project protocols

to determine exchange methods. Use of 3D models in design meetings allows a

multidisciplinary review of design enables the team to focus and visualise the issues

quickly and accurately leading to efficient early resolution. Comments from design

reviews can also be recorded directly in the models enabling the team to track issues,

keeps all disciplines up to date avoiding the risk of receiving a large batch of changes

late in the process. Hence, this whole-project view enabled by BIM is a platform that

positively impacts on multi-disciplinary collaboration, improving design quality,

preventing designers from “making do” (Koskela 2004a) and reducing rework in the

field as a result of incomplete design.

2.3.14 Design coordination and Model Checking

On complex projects, conflict identification and resolution is an extremely expensive

and difficult task. In many instances, designers do not have the time or budget to

sufficiently resolve conflict issues. Finding coordination issues or contradictory

dimensions inevitably found within hundreds of traditionally drawn 2D drawings is a

time consuming and particular skill performed manually using traditional 2D CAD

tools to overlay CAD layers to visually identify potential conflicts. These manual

approaches are slow, costly, prone to error, and depend on the use of up-to-date

drawing which are not always available because specialist trade packages such as

HVAC may not be let at the design stage. Complex coordination and clash resolution

using coloured two dimensional overlays is inherently subject to error and omissions

32

(Ashcraft, 2009). As a result some clashes may not be identified only be discovered

on-site. In 3D BIM based design this risk is significantly reduced because the virtual

3D building model is the source for all 2D and 3D drawings, making the

identification of issues and early mitigation easier and reducing design errors caused

by inconsistent 2D drawings, speeding up the construction process, reducing costs

and minimising the likelihood of legal disputes and generally enabling a smoother

process for the entire project team (Eastman, 2011; Hardin 2012).

33

2.3.15 Multi-disciplinary Integration and Simultaneous working

The literature suggests that model based collaboration enables the simultaneous

working or overlapping of design phases by multiple design disciplines (Succar,

2009). It is facilitated through the interchange of models either via propriety or non-

propriety file formats and through network/server technology, allowing early two-

way access to project stakeholders and their information within a common data

environment. As a consequence more design effort and integration is required at the

front-end of the process as illustrated in the widely cited Mcleamey curve shown in

Figure 11 below. A major benefit of simultaneous working on the quality of

production information is to shorten the design time and significantly reduce design

errors and omissions. It also gives earlier insight into design problems and presents

opportunities for a design to be continually improved. This is much more cost

effective than waiting until a design and nearly complete and then applying value

engineering only after the major design decisions have been made.

Figure 11 The ‘Mcleamey Curve’ describes how the preferred design process should evolve

compared to the traditional design process. In the early phases abilities are bigger to impact on cost

and functionality where the cost of change is lower. (Tommasson, 2011).

34

3.0 Chapter Three - Theoretical Framework

3.1 Introduction

A theoretical framework is essentially bridge between paradigms that explain the

research issue and the actual practice of investigating that issue. As a ‘working tool,’

it enables reasoned defensible choices, the matching of research questions with those

choices and it guides data collection, analysis and interpretation (Bloomberg and

Volpe, 2012). In fulfilment of this function this chapter provides detail of the key

constructs for the framework that have emerged from the review of the literature,

combined with the researchers own experiences to inform the design and conduct of

this study.

Figure 12 overleaf shows a diagrammatic overview of the key constructs of the

model, the framework is also discussed in narrative form. The model is broadly into

two sections that reflect the issues identified in the literature;

Part A; Problems and the factors associated the quality of Production Information

and Part B; Solutions and the attributes associated with using BIM based design.

35

3.2 Theoretical Framework for the Study

Problems with low quality and

untrustworthy Production

Information

Failure to deliver quality

across a number of

indicators;

- Timeliness

- Accuracy

- Completeness

- Coordination

- Conformance

Industry wide

performance

problems

Factors;

- Fragmentation/Silo’s = lack

of integration, co-ordination

and collaboration between

disciplines ,misunderstandings

and misconceptions

- Poor Information

management =wasted time

spent identifying useful

information, incomplete,

uncoordinated and/or

inappropriate exchange of

information

- Flawed 2D drawing-based

design paradigm

Inherent functionalities via

BIM based processes;

- Maintenance of Information

and Design Model Integrity

- Earlier and More Accurate

Visualisations of a Design

- Automatic Low-Level

Corrections When Changes

Are Made to Design

- Generation of Accurate and

Consistent 2D Drawings at

Any Stage of the Design

- Earlier Collaboration of

Multiple Design Disciplines

- Information consistency and

reliability

PROBLEMS (Part A) SOLUTIONS (Part B)

Government

Construction Strategy.

BIM Level 2 mandate

Building Information

Modelling (BIM)

Discipline Specific 3D models

Model federation

File based collaboration

Information

Management

using

PAS1192-2

Improvements via

PAS1192-2;

- Improved

Visualisation and 3D

design review

- Design coordination

and model checking

- Multi-disciplinary

Integration and

Simultaneous working

- Better information

flow

Improved quality of

Production

Information

Other

components

of BIM

Level 2

Reduced

incidence of

Rework

Other short/

long term

benefits

Strategic intervention

of BIM based design

into existing 2D CAD

paradigm

Factors affecting

successful

implementation

Other

components

PAS1192-

(Outside scope

of research)

Figure 12 Theoretical Framework for the study (Author).

36

3.3 Principal Factors Affecting the Quality of Production Information

The findings from Part A of the literature review suggests that the many factors

affecting the incidence of rework are not only well known but also that there has

been a systematic failure to successfully implement workable and lasting solutions

that can adequately address the shortcomings of the 2D design management

paradigm. The complex nature of the construction process is such that piecemeal

solutions have been unable to adequately address the problem. Based on the literature

reviewed for this study the principal categories identified as leading to poor quality

production information are;

1. Poor briefing and communication

2. Fragmentation of design disciplines

3. Flawed design documentation and delivery paradigm

4. Flawed drawing based design paradigm

5. Poor information management practices.

Sub factors relating to each are shown diagrammatically on Figure 13 overleaf which

shows a Root Cause Analysis of the problem.

37

POO

R B

RIE

FIN

G A

ND

C

OM

MU

NIC

ATI

ON

LOW

QU

ALI

TY

PR

OD

UCT

ION

IN

FOR

MA

TIO

N

REQ

UIR

ING

R

EWO

RK

FRA

GM

ENTA

TIO

N

OF

DES

IGN

D

ICIP

LIN

ES

FLA

WED

DES

IGN

&

DO

CU

MEN

TATI

ON

D

ELIV

ERY

PAR

AD

IGM

POO

R

INFO

RM

ATI

ON

M

AN

AG

EMEN

T

FLA

WED

DR

AW

ING

B

ASE

D D

ESIG

N

Inab

ility

to

adeq

uate

ly

visu

alis

e th

e de

sign

Clie

nt

chan

ges

Cos

tly

rede

sign

&

iter

atio

n

Uni

tegr

ated

w

orki

ng (S

ilos’s)

Unc

oord

inat

ed

proj

ect

info

rmat

ion

Poor

Coo

rdin

atio

n be

twee

n di

scip

lines

Inad

equa

te C

TTD

of

use

r ne

eds,

m

issi

ng p

roje

ct

info

rmat

ion

Uns

tand

ardi

sed

pro

cess

es

Insu

ffic

ient

fe

es, t

ime

&

expe

rtis

e

Line

ar p

roce

ss

2D C

AD

not

fit

for

purp

ose

Unt

rust

wor

thy

Info

rmat

ion

Line

s &

sym

bols

, am

bigu

ous

& L

ow q

ualit

y In

form

atio

n

Unc

onst

ruct

able

de

sign

s

Lack

of a

gree

d st

anda

rds

Uns

truc

ture

d &

low

un

ders

tand

ing

of p

roce

ss

Mis

sing

, una

vaila

ble,

un

dist

ribu

ted

info

rmat

ion

Uns

truc

ture

d pr

ojec

t in

form

atio

n m

anag

emen

t sy

stem

s

Erra

tic

deliv

ery

of

info

rmat

ion

Aba

ndon

men

t of

de

sign

pla

nnin

g

Figure 13 Root cause Analysis; The factors leading to low quality production information (Author).

Note the causes considered to be the most important in the context of this study are shown in Red.

38

3.4 Strategic countermeasures under PAS1192-2

While it not possible to definitively attribute the occurrence of rework only to those

factors identified in the literature review in this study, it is clear that a number of the

identified flaws of the current drawing based paradigm result inaccurate, incomplete

and uncoordinated production information which in turn directly affect the incidence

of rework. Within this context and according to the theory, BIM based design as

specified in PAS1192-2 contains a number of specific countermeasures which if

implemented may result a range of potential qualitative and quantitative benefits for

project organisations adopting BIM.

Through the process of analysis and reflection conducted during the literature review

each counter measure is in effect a Category that will be used for the purpose of

structuring the questions to be asked to the research participants in support of

Objective 3; To interview a sample of industry practitioners to explore their

experiences of BIM enabled working practices when compared to the traditional (2D

CAD) design paradigm.

The intention of subdividing the research problem into core categories is to construct

a holistic picture of the issues and influences, via the primary data collection.

The principal countermeasure can be taken to be working in BIM itself. In the

context of this study this is categorised as ‘Production Information Processes.’ By

mandating the use of ‘…fully collaborative 3D BIM’ a strategic intervention is made

which adds a ‘third dimension’ to the existing design paradigm. By doing so a

fundamental shift in the process of generating Production Information is enabled via

the inherent functionality of working using 3DBIM. This offers the potential to

resolve a number of the inefficiencies and flaws associated with unintelligent design

information detailed in Part A of the literature review and as summarised in the Root

Cause Analysis.

39

The actual intervention can be considered to be a change to the working practices

experienced by the project team that is enabled by the functionality of new software

and the associated changes to behaviour and the processes involved in delivering of

Production Information in a BIM based environment. The core inherent

characteristics enabled by BIM were explored in detail in Part B of the literature, for

clarity they are repeated here as being;

The maintenance of information and design model integrity, earlier and more

accurate visualisations of a design, automatic low-level corrections when

changes are made to design, generation of accurate and consistent 2D

drawings at any stage of the design, earlier collaboration of multiple design

disciplines and information consistency and reliability.

‘Design review and coordination processes’ is a core category which contains the

concept of ‘Visualisation’. The benefits of enhanced visualisation offered by a virtual

building comprised of intelligent and data rich elements is a direct countermeasure to

the basic problem of understanding of what is to be built, through the process of

modelling each geometric interface and design element. Similarly a federated and

integrated BIM model enables a rigour of coordination and clash detection not

possible in drawing based design, as such this functionality can be considered to be

an intervention which reduces misunderstanding as well as incomplete and

uncoordinated information which leads to poor quality information and rework.

The category ‘Simultaneous working’ is a function of the integration of discipline

specific BIM models which potentially improves the quality of final product by

counteracting the problem of ‘Over the wall’ and unintegrated information

exchanges and working practices among design disciplines. As previously discussed,

it is characterised via the Mcleamey curve which will be used in the primary research

phase as a visual prop that can be used to determine the level of the research

participants understanding of BIM processes as well as visual aid for reflection on

how the adoption of BIM based design has impacted upon the workflow of

consultant teams.

Similarly, ‘Collaborative working’ in the context of PAS1192-2 requires teams to

work together to produce information using standardised processes and agreed

40

standards to ensure the same form and quality of information. Working in this way

requires mutual understanding and trust which is a risk management related

countermeasure that can avoid wasteful practices and reduce disputes.

The final category is ‘Information Management’ which is a function not only of BIM

as a database or repository of data, but also via collaborative procedures contained in

BS1192:2007 used to ensure a standardised and proven quality control mechanism

for ensuring information is consistently produced and authorised for its intended

purpose. In parallel to this is the Common Data Environment through which project

participants can effectively distribute and access current information. Each of these

concepts can be specifically related as countermeasures to the problems of

unstructured project information systems, erratic delivery of information, missing,

unavailable or undistributed information resulting from a lack of agreed standards

and poor Information Management generally.

Based on the theoretical relationships between the categories and concepts of both

the problems and the intervening solutions delivered via PAS1192-2, the Theoretical

model will be tested within the context of the real world project environment. Table

4 below tabulates a summary of categories and concepts used in the development of

the interview questions conducted during the primary research phase of the

dissertation.

Category Concepts

Production information

processes

Better Information integrity, Exploitation of automation, inherent

consistency, facilitation of collaboration.

Design review and

coordination processes

Three dimensional visualisation leading to enhanced understanding,

collaborative 3D design review, Design coordination and element based

model checking.

Simultaneous working Multidisciplinary integration, compression of design programme.

Collaborative working Trust, Win/Win Solutions, Mutual Understanding, better Communication,

facilitated Problem Solving, Innovation, better Decision making.

Information management Standardisation and proven quality procedures for information exchange

Rework Latent errors and omissions, RFI’s/variations, Wasted time, Reputation.

Quality Timeliness, Accuracy, Completeness, Coordination, Conformance.

Table 4 Summary of Categories and concepts contained within the Theoretical framework (Author).

41

4.0 Chapter Four - Research design

4.1 Introduction

The aim of this dissertation was to investigate the factors associated with the delivery

of improved Production Information quality using BIM enabled design practices.

This was explored primarily through the gathering and analysis of secondary data via

the literature review, as well as primary data collection via a sample of industry

practitioner’s reflections and experiences of BIM based processes when compared to

the 2D drawing based paradigm. It was considered that although the benefits of

adoption BIM are becoming clearer as more BIM projects and research are

completed, the specific benefits on the quality of Production Information and the

identification of the critical factors impacting upon quality were relatively

unexplored and worthy of study.

This chapter describes the study’s research methodology and includes discussions

around the following areas;

1. Rationale for research approach

2. Description of research sample

3. Methods of data collection

4. Analysis and synthesis of data

5. Ethical considerations

6. Issues of trustworthiness

The limitations of the study are addressed in Chapter 5.

42

4.2 Rationale for Research Paradigm

A Social Constructivist approach was selected for this study in the form of an

inductive/grounded theory investigation conducted via 7 in depth interviews. The

following paragraphs clarify the rationale for this approach;

Bryman, (2102) suggests that while practical considerations may seem uninteresting

compared to philosophical debates surrounding discussions on epistemology and

ontology, they are nonetheless important ones. Clough and Nutbrown, (2012) suggest

social research is the coming together of the ideal and the feasible;

‘…a characteristic purpose of a methodology is to show not such and such

appeared to be the best method for the given purposes of the study, but how

and why this way of doing it was unavoidable - was required by - the context

and purpose of this particular enquiry.'

Based on this, the circumstances of this study featured strongly in the decision

making process. Most modern construction design projects typically involve a

number of specialist disciplines interacting through a variety of conventional and

digital media where information is shared and converted into design drawings and

documentation. A fundamental principle of BIM based design as specified using

PAS1192-2 is the requirement for project teams to increase and improve their

collaborative working practices for the mutual benefit of the project and ultimately

themselves. The project organisation was therefore the social context within which

this study was conducted and as such the essence of the research data was the

reflections and experiences of what is a socially constructed process. Based on this,

the Social Constructivism approach was the preferred theoretical perspective.

The basic tenet of the constructivism paradigm is that that reality is socially

constructed, that individuals develop subjective meanings of their own personal

experience, and that this gives way to multiple meanings (Lincoln and Guba, 2000).

It therefore challenges the scientific-realist assumption of post positivism that reality

can be reduced to its component parts. (Creswell, 2009). Constructivist research

attempts to understand social phenomenon from a context-specific perspective and it

is the researcher’s role to understand the multiple realities from the perspective of the

participants.

43

4.3 Rationale for Inductive research approach

BIM based design procedures as specified by PAS1192-2 are a relatively recent

development in construction and subject to a large number of factors which the

research aimed to discover, the aim of the research was to develop and explain the

phenomenon inductively via the findings rather than test a preconceived theory

deductively (as in post positivism). Bryman, (2012) suggests that a deductive

approach is associated with quantitative research approach, while an inductive

strategy of linking data and theory is typically associated with a qualitative research

approach.

The 5 main qualitative research traditions suggested by Creswell, (2007) are: Case

study, Ethnography, Phenomenology, Grounded Theory and narrative research. Of

these, a case study was considered relevant for this study, however this was rejected

as the researcher considered being too dependent on accessing information from a

single source within a constrained research period to be a risk to the timely

completion of the dissertation.

Although not strictly as intended by Glaser and Strauss, (1967) the grounded theory

approach was considered to be the closest approach appropriate to the researchers

study as a core component is that the theory development is generated or ‘grounded’

in ‘context-rich data’ from the field. (Strauss and Corbin, 1998).

The goal of grounded theory is to move beyond description and to have the

researcher generate or discover a theory of a process, an action, or an interaction

grounded in the views of the research participants (Strauss and Corbin, 1998). Study

participants would all have experienced the process, and the development of theory

might explain practice, or provide a framework for further research.

Two primary characteristics of grounded theory are the constant comparative method

of data analysis (i.e. the on-going comparison of data with emerging categories) and

theoretical sampling of different groups to maximise the similarities and differences

between of information. However it is noted that the former of these characteristics is

somewhat limited by the timescale and scope of the study and to a large extent the

study can be thought of as having inductive/grounded theory tendencies rather than

as a hard and fast distinction.

44

4.4 Rationale for Qualitative Research Method

The overall perspective to this research was more one of enquiry rather than

hypothesis testing. This suggested a qualitative approach to the research since one of

the chief reasons for taking such an approach is if the subject is relatively unexplored

in which the research seeks to listen to the participants and build an understanding

based on their ideas (Creswell 2008). There is an increasing amount of quantitative

research on the benefits of BIM (Coates, Arayici, Koskela, Kagioglou, Usher and

O’Reilly, 2010; Azhar, 2011; Barlish and Sullivan, 2012; Succar, Sher and Williams,

2012). However, the development of robust metrics that can be used to measure the

benefits of BIM would require a study beyond the scale and scope of this research

and present ethical issues regarding access to commercially sensitive information. In

addition, at the time of writing there is currently little or no available research into

the experiences of UK practitioners with specific regard to the benefits of BIM on

the quality of Production Information using processes as specified in PAS1192-2,

with the exception of the Ministry of Justice Cookham Wood project results (BIM

Task Group, 2014).

An approach was therefore taken which would enlist beliefs, opinions and views to

gather data, which was rich in content and scope and open to interpretation (Fellows

and Liu 2003) while also 'tolerating ambiguity and contradictions which lead to the

prospect of alternative explanations during the process of analysis' (Denscombe

2007).

It was acknowledged that by selecting a qualitative study in lieu of a Quantitative or

mixed methods approach that the research conclusions would have lower validity,

the data may be less representative and the interpretation may be ‘bound up with the

self of the researcher,' however it was considered that due to the scope and time

constraints imposed by dissertation framework that a only qualitative could be

justified.

Table 5 overleaf surmises the considerations and selection of characteristics for both

Quantitative and Qualitative approaches to the study.

For a summary of the Research Design for the study refer to Appendix C.

45

Quantitative Qualitative

Deductive: Hypothesis or theory is

generated and through data collection it is

either rejected or selected (testing of

theory).

Inductive: Starts with data collection and

concludes with hypothesis or theory (theory

emerges from data).

Epistemological position:

Natural science model, in particular

positivism

Epistemological position:

Interpretivism

Ontological orientation: Objectivism Ontological orientation: Constructivism

Some common contrasts between

quantitative and qualitative:

Some common contrasts between

quantitative and qualitative:

Numbers Words

Point of view of researcher Point of view of participants

Researcher distant Researcher close

Theory testing Theory emergent

Static Process

Structured Unstructured

Generalisation Contextual understanding

Hard reliable data Rich, deep data

Macro Micro

Behaviour Meaning

Artificial settings Natural settings

Table 5 Rationale and selection of Qualitative research method for the Study (Adapted from Bryman,

2012)

46

4.5 The Research Sample

A criterion based sampling strategy was selected for this study with the intention of

targeting specific research participants who have experienced the processes involved

with the delivery of Production Information in both 2DCAD and BIM environments.

A primary consideration in the sampling strategy was obtain views from individuals

representing two broad classifications of BIM maturity, in order to identify

distinctions between the factors and benefits affecting organisations operating at

different maturity levels. Architects were identified as the principle research group as

generally they perform the Lead designer role on a project and as such could be

expected to have a holistic view of Production Information processes. The Criterion

for selection was therefore as detailed below;

Criterion 1; Participants must be senior Architectural practitioners at Associate level

or above with a minimum of 15 years total industry experience and have delivered

production information in both CAD and BIM environments. This was achieved by

contacting the authors pre-existing contacts and by identifying participants from a

delegate list from the 2014 BIM Show Live conference. This is justified because

according to the NBS, (2014) only 54% of industry was ‘using BIM’ as of 2013 and

of that potential pool, the diversity of the practices using BIM is considerable and the

definition ‘using BIM’ is itself open to wide interpretation. By using the delegate list

research participants were identified that could reasonably be expected to be using

BIM and in a manner which met the criteria for inclusion in study which was;

Criterion 3; Participants were selected to fall within the category of ‘Early adopter’

with between 4 and 10 years BIM experience, or the ‘Early majority’ category with

between 2 and 4 years’ experience. The rationale for this was that it was considered

to be important to obtain views on the factors and benefits associated with BIM

adoption from both the perspectives of both industry leaders and those recently

commencing BIM adoption to see how the potential benefits of BIM may be

influenced by an organisation’s relative experience in using it. This also

corresponded with the scale of the organization which was generally classified as

falling in the categories of local, national and international.

Refer to Table 6 overleaf for a summary of the sample demographics and data.

47

Table 6 Research Sample Information and Demographic

Interviewee

Code

Interviewee

01

Interviewee

02

Interviewee

04

Interviewee

05

Interviewee

06

Maturity

Classification

Early

adopter

Early

adopter

Early

adopter

Early

majority

Early

Majority

Organisation

type

Architects Architects Architects Architects Architects

No. of

Employees

800+ 100 20 20 40

Interviewee Role Director of

Information

&

Technology

& Architect

Associate

Architect &

Associate

Technologist

Associate

Architect

Associate

Architect

IT Director

&

Architectural

Technologist

Organisational

scale

International

scale

National

scale

Local

scale

Local

scale

Local

Scale

Sex M M M M M

Organisation

BIM experience

(years)

4 10 4 2 3

Interviewees

Total Industry

years’

experience

20+ 15+ 15+ 15+ 15

Interviewees

Years CAD

Experience

20+ 15+ 15+ 15+ 10+

Interviewees

Years BIM

Experience

4 6 4 2 3

48

4.6 Data Collection Method

The data collection method selected for this study was the qualitative semi-structured

interview, used with the aim of eliciting the experiences and views from the

participants via focussed discussion and the gathering of rich, valid and reliable data

(Saunders et al, 2011). Each of the three alternative qualitative data collection types

(Observations, Documents and Audio- Visual materials) suggested by Creswell,

(2009), were rejected as being inappropriate to the context of this study.

The interview options within this data collection type include the email internet

interview, focus group, face-to-face and telephone interviews. The first two types

were rejected on the grounds that email interviews were considered inferior to face-

to-face interviews because the data inputted may be incorrect, incomplete and

unverifiable as without human/non-verbal cues it is difficult to gain clarifications of

responses and explore emerging concepts as they arise. Similarly focus groups were

considered to be an inferior approach in the context of this study as the practicality of

attempting to arrange for the selected research participants to attend a focus group in

a mutually convenient location and time represented a risk to the timely completion

of the study. Overall, face-to-face interviews were considered the best method of

obtaining and managing the data collection technique and this was the primary

technique used, however it is acknowledged that a limitation of the interview is that

of representation and the ‘fusion of the researcher and knowledge’ (Alvesson, 2003).

This is primarily due to the potential of the researcher to bias responses and as such it

is accepted the generalisability of the findings is limited. Telephone interviews were

also used in the study to resolve logistical barriers and their inclusion in the study,

alongside face to face interviews was considered to be a compatible approach.

Interviews can be categorised as structured, semi-structured and unstructured

(Saunders et al, 2011). The semi-structured interview was considered to be the most

preferable option for this study because the flexible nature of question sequencing

using open-ended questions was considered to be essential in discovering as much as

possible about the topics included in the interview. Similarly the structure retained

via the use of an interview guide enabled easy analysis and comparison of data (Qu

and Dumay, 2011).However it was acknowledged that a drawback of semi-structured

interviews is the potential for the researcher to influence the responses of the

49

interviewee. In this regard care was taken to avoid leading questions and direct

prompting, although it is also acknowledged in the literature that that by virtue of the

research design and the role of the researcher in qualitative studies such as this that

some values and bias are inherent and difficult to completely eliminate (Bryman,

2008).

4.7 Interview Schedule, Pilot Interview and Interview Process

The ten Categories derived from the theoretical framework were used as the basis for

developing open-ended interview questions, the categories were;

Production information processes, Design review processes, Coordination

benefits, Advantages of simultaneous working, Collaborative working,

Information management, Rework, Quality, Overall benefits and Barriers.

The interview questions were approved by the dissertation supervisor before being

incorporated with an interview schedule and piloted in a single face-to-face

interview. From the pilot a number of comments we received and incorporated into

final interview question set. Once finalised interviews were arranged via telephone

and email with care being taken to ensure that the research participants met the

criteria for inclusion the study. In total, seven, one and a half hour interviews were

conducted during the period 19th

- 27th

August 2014 at various locations within the

North and South East regions of the UK. All interviews were recorded and field

notes were also taken, on completion the audio was transcribed for analysis.

Refer to Appendix D for details of the Research Questions.

50

4.8 Data analysis and synthesis

The main objective when conducting the data analysis was the discovery of the

factors that impact upon the quality of Production Information. The Grounded theory

approach to analysis not considered to the most appropriate analysis method for this

study as the intention was to identify and explain rather than result in theory.

However the coding process associated with Grounded Theory was considered to be

a relevant method of extracting meaning from the data. On this basis a Thematic

Analysis was selected which uses makes use of codes but is not as prescriptive as

Grounded Theory (King, 2004).The actual process followed in this study was in

keeping with that recommended by Miller and Crabtree (1999);

“…researchers can develop codes only after some initial exploration of the

data has taken place, using an immersion/ crystallisation or editing

organising style. A common intermediate approach is when some initial

codes are refined and modified during the analysis process.”

Using the initial categories identified in the Literature review to frame the responses

the following list represents the sequence and elements of the analysis;

1. The Interviews were transcribed and entered into a spreadsheet so that a

holistic view could be taken of the data set.

2. The data was then printed out at A1 size for an initial exploration of the

data. Important and relevant responses where highlighted manually.

3. Connections between responses were made using a pencil and to draw

link and add relevant notes which informed a complete understanding and

the relationships between data sets.

4. The relevant sections of text were given reference numbers and assigned

an initial descriptive code. Coded data was grouped together into a master

document. The grouping of data was refined as the through a process of

abstraction/interpretive coding.

5. The data was subsequently connected corroborated and legitimised into

group of themes.

Refer to Appendix E for an extract form the initial exploration and of the data.

Refer to Appendix F for extracts from the Thematic Analysis process.

51

4.9 Ethical Considerations

Although during proposal stage the research project ethics form was completed and

approved as no significant ethical risks were posed to the participants, this study

employed a number of safeguards as required in the Northumbria University

Research Ethics and Governance Handbook (REGH, 2014) to ensure the protection

of participants and commercially sensitive data obtained during the study.

As such the study followed the 6 core ethics principles as identified by Economic

and Social Research Council’s Framework for Research Ethics (ERSC, 2010) as

below;

1. Research should be designed, reviewed and undertaken in a way that ensures its

integrity and quality;

2. Researchers and research subjects/participants must be fully informed about the

purpose, methods and intended possible uses of the research, what their

participation in the research entails and what risk, if any, are involved;

3. The confidentiality of information supplied by research subjects re. the

anonymity of respondents must be respected;

4. Research participants must participate in a voluntary way, free from any

coercion;

5. Harm to research participants must be avoided; and

6. The independence and impartiality of researchers

52

4.10 Issues of trustworthiness

Bryman, (2012) suggests credibility is an important indicator of the trustworthiness

of a study because it is the credibility of the account of the researcher that is going to

determine its acceptability to others. Respondent validation and Triangulation are

two common techniques used to validate the researcher has correctly understood the

social reality of the study. Principles of Triangulation were employed in this study.

Respondent validation was rejected because due to the time constraints of the study

and the wish to keep the time commitments of the research respondents to a

minimum was considered important. It was considered important to include an

element of triangulation in the study as the research was in effect asking Architects

to consider the quality implications of work that they themselves produce. As such it

could be argued that their answers could contain the potential for Bias. In order to

have a reference point to validate the credibility of the views of the Architects,

aspects of the interviews which dealt specifically with quality were crossed

compared with the views of two professionals from outside the Architectural

profession in the study. On this basis, one representative from Design Management

and one representative from the Civil Engineering design and contracting professions

were included, making the total interviewees for the study seven.

53

5.0 Chapter Five - Data Analysis and Discussion

5.1 Data Analysis and Discussion

This Chapter presents the qualitative data analysis with the findings that will support

the conclusions and recommendations in Chapter 6. The findings are based on 7 in-

depth interviews, which through the data sorting and analysis process generated 9

main themes. The themes emerged from a process of abstraction of descriptive and

interpretive coding of the interview transcripts.

Each of themes identified in some way affect the quality of Production Information

using BIM based design. In this regard they can be also be thought of as ‘Factors,’

and will be referred to as such in the following discussion provided in part fulfilment

of Dissertation Objective 4;

To analyse the research data, to identify and explore the emergent factors affecting

the quality of Production Information using BIM enabled design processes.

The nine factors, their associated sub-factors and the relationships between them are

presented diagrammatically in Figure 14 overleaf. The following sections of this

Chapter explain and compare each factor within the context of the Theoretical model

presented in Chapter 3.

54

Information

Management using

BIM

Process Rigour and

Transparency

Balancing Risk and

Reward

User capability and

organisational BIM

Maturity

Skilled people;

Access &

investment

1:Experience

2:Training

3:Education

4:Diligence

Upfront Investment

for driving

downstream value

Harnessing data and

potential of

Innovative

(IM&BIM)

Technologies

BIM execution

planning

Visualisation and

understanding

Taking and making

opportunities

Informed decision

making

Information

Cohesion and

integrity/

Automation

Strategic

Intervention of BIM

based design

Barriers:

Uniformed

clients

Barriers:

Non-alignment/

integration/

procurement issues

Effective

Virtual Prototyping

Improved quality of

production information

Reduced

incidence of

Rework

Figure 14 The Interrelationship of Factors affecting the quality of Production Information (Author)

55

5.2 Factor 1: Virtual prototyping

‘Effective virtual prototyping’ is considered to be the core output resulting from the

interaction of the remaining factors identified in the research. In building projects,

the information which the construction team uses to convert an idea into a physical

element is based upon the quality of output produced during the design process,

which typically manifests as drawings, schedules and specifications. These

documents represent a translation of a design team’s intellectual investment in the

project and their attempts to accurately communicate their intentions. As identified in

the literature review the 2D Production Information processes and the associated data

management practices are inherently unintegrated which leads to problems in

understanding, not only among the construction team but also among clients and the

designers themselves. Virtual Prototyping can be taken to mean the process of

virtually constructing every major element of the building in advance of the

construction phase. Working in this way is a major improvement and offers the user

a range of value adding functionalities and benefits not possible in traditional

drawing based design. It is therefore considered to be a fundamental factor in the

delivery of better quality Production Information.

56

5.3 Factor 2: Visualisation and Understanding

BIM based design directly addresses the core problem of erroneous information

interpretation by generating a virtual prototype capable of enabling the whole team to

accurately visualise and understand the design through the generation of a verifiable

and interactive visual representation. This reduces the risk of wasted effort resulting

from ill-informed decision making and unresolved designs. An extract from

interview 5 gives an example of the potential for major benefits of both 3D and 4D

visualisation;

“…there was a major bit of work to be put it that was on their critical

path...it wasn't until we showed the 3D model and the scheduling that showed

a 4D visualisation program, that they realised within 20minutes that they had

got a real issue because this isn't a 5 minute job,... it allowed them to go

away and rethink about their requirements and rethink how we should phase

that work in order to meet everything else that's going on in terms of the

construction, in this case it was Crossrail, it was important to them, would

they have got that understanding without a 3D model?... that would not have

come about, we would have all carried on quite blindly building what we said

we were going to build without understanding the consequences…”

Other examples notable examples from the research include;

“…I can fly through a model, if I fly through it enough I know where I'm

going and I've never been to site…”

“…what we have found is if you include 3D image on that drawing of what

this is going to look like and how it will function, then we get an instant

reaction…”

In addition to quantifiable benefits such as time and cost saving, the ability to be

being better able to clearly visualise, understand and interact with problems also

appears to facilitate learning among the project team. These types of benefits not

necessarily tangible but that are important nonetheless;

‘…subsequential learning is embedded in the way you work in BIM’

(Interviewee 1).

57

5.4 Factor 3: Upfront Investment Driving Downstream Value

This factor is central to the diagram presented in Figure 16. As such it has

associations with numerous other factors. Firstly, at an organisational level it

manifest as a business’s commitment to invest in innovative technology and the

skills needed to operate it. The cost of adopting BIM is a significant barrier for many

in the industry. For many of the Interviewees it represents a major investment, taken

either proactively with the intention harnessing the potential offered by BIM

technologies to generate downstream value or reactively by seeking to maintain

existing work steams post 2016. In this regard this factor is closely related with Risk

and Reward (See Factor 8).

The second aspect of factor 3, can be taken to be the process of investing increased

time and effort to populate the BIM database at earlier stages of the project as

illustrated in the Mcleamey curve illustrated in Figure 13. The upfront investment in

intellectual effort used to create the BIM database appears to be a function of the

fundamental change to Production Information processes. The adjustments to

working practices required to accommodate this process change appear to bring

about a number of challenges, particularly with regard to managing the design

programme. However, the upside to this Factor can be significant downstream

efficiency savings and the opening of a number of opportunities to manipulate the

data in value adding ways, for example, 4D BIM (Construction programming), 5D

BIM (Cost) and 6D (FM & Asset lifecycle). An Example from the research includes

one given by Interviewee 4, where the BIM database was manipulated to serve as the

platform for the testing and optimisation of sustainable design solutions using energy

modelling software and cloud based environmental databases;

“…we can optimise and validate our designs, reducing (the clients) running

costs by £10k per year, in the end it will become added value coming out

straight out of the BIM workflow, its only now we can justify our design

responses rather than in our head..”

Other day to day benefits driven by the early creation of the BIM database include

being able to respond to queries quickly as the rapid generation of additional views

58

and sections reduces time and cost that it may have taken to manually draw, present

and issue each additional output.

“…normally it would take a week, all together I did it in an afternoon, and

additional requests for information can be dealt with quickly…”

“…you can pull in stuff that potentially is ready to go for construction that

contains all the information they need and that’s backed up with

specifications…”

“…because you are building it virtually, even just to produce a bunch of GA's

a lot more has got to be done up front, it forces you to think about it…”

“…to get the efficiencies we want everything has to have data associated with

it…”

59

5.5 Factor 4: Process Rigour and Transparency

In order to generate a graphical representation of each component in the model, BIM

software requires that the user input sufficient design information into each

component parameter. In doing so the user is forced to consider the ‘preloaded’

design variables for each building element, how the building would be constructed in

reality and how each element interfaces with adjoining elements. The population of

each field in the BIM database with design information not only forces the user to

consider the design variable in the first place, but also to rectify interfaces that don’t

work or that may not have been considered in the first place. Similarly the

standardisation of processes required by BIM based design adds another level of

rigour and transparency to the process which is considered to be a significant factor

in reducing the waste from rework and is a functionality not present in the 2DCAD

paradigm as the constituent parts of the a drawing were geometric primitives with no

inherent intelligence or parametric functionality.

As discussed in Factor 3, the time taken to produce the initial model is increased as

the resolution of design interfaces requires upfront effort on the part of the designer.

However, the increase in time taken to develop the model corresponds with the

increased intellectual effort applied that was always necessary to resolve the design.

That intellectual effort now appears to be increasingly expended during the design

stage where it belongs rather than reactively during the construction. Numerous

examples from the research illustrated this in practice;

“…every single element of the building has been thought about, we have to

model in a way it which will actually be built, even though were putting more

effort in the front end were saving more going forward by the fact that we

haven't got to do more work when it goes to site…”

“…architects are terrible at doing sections where they know it’s easy and

avoiding the change in direction or change in details, whereas Revit does it

for you it and forces you to look at it, you look at it and realise its wrong at a

very early stage and actually tweak it so it does all work much earlier…”

“…it’s very difficult to fudge things; you have to plan them through to be

right when they come out the other end…”

60

“…BIM doesn't let you cheat, you have to think about it a lot more... they're

looking at it as physical element…”

“…there's a risk because you are forced to correct mistakes as you go which

might take you off the critical path…”

“…when people are interacting with the model they fully understand what

they have designed, because they can see it, in the past people drew stuff and

they physically don't know what they've drawn…”

“…internally we have now got rafts of process to control what we do, it’s

influenced our QMS, there's a lot more that we have to do as a company that

is inbuilt to serve BIM processes…”

“…you can’t hide anything by issuing a few sections because they get to see

the whole thing…”

“...the design was completed in a 2D world and signed off and we agreed

with the client we would go into a 3D world and just make sure it all works,

why? because we've got time before we arrived on site, that design suddenly

got brought back to detailed design because it didn't work, big fundamental

errors right up at the concept stage of the design that had been lost and were

just taken as true after that, it would be cost the client quite a lot of money, in

that instance we didn't get an increased turnover because we are not

managing change, but we shouldn't be in the business of managing change

and issues of that nature, we should be in the business of making our money

through building it right first time…”

“…BIM gives us the ability to fix things we were never fixing and were

passing downstream to on site and that is something that puts a greater onus

on the designer…”

“…I don't think there is a stark difference between working in 2D and 3D in

terms of the process, you get out of it what you put in, you put rubbish into

the 3D model you'll get rubbish back out of it, you still have to control it and

apply rigour and check everything…”

61

5.6 Factor 5: Information Cohesion, Integrity & Automation

The ‘single entry, multiple use’ of design information and the digital, centralised

structuring of information is diametrically different to the 2DCAD paradigm where

multiple files contain groups of information about similar design elements, but

without the benefit of being connected or having any inherent building design

parameters. BIM based design as a ‘central source of truth’ counters the problem of

data integrity, coordination and information loss identified in Part A of the Literature

review and in this regard the findings appear to validate the theory. A key benefit of

this with regard to Production Information is that of Automation, where any change

to one element of the virtual prototype is reflected in the output of all corresponding

views bringing about a number of efficiency gains and reducing the risk of errors and

omissions. Illustrations from the research include the following;

“…there's a greater concentration of information at point of source, if you

change a dimension it will changes it in a section and elevation, you have

more consistency of approach in change management…”

“…you don't have the issue of something being in excel and something being

in CAD and somehow that coming together on a PDF…”

“…if you link your specification and schedules to the model you get a

consistency that was never there before…”

62

5.8 Factor 6 - User capability and organisational BIM maturity

An important theme that emerged from the data was that of user capability and the

overall BIM maturity of the organisation. The fact that an organisation has decided

to implement BIM does not necessarily mean that the quality of their Production

Information is necessarily higher. Similarly, and as with most service based

industries, the most important assets are its people, as such the collective capabilities

of its users can be taken to represent the organisations overall BIM maturity. In this

regard the research suggests that the level of type of benefits and the overall project

performance can be partly attributed to these factors regardless of the design tools

employed. The Interviewees were consistent in their view that the outputs of the

Production Information process haven’t significantly changed, although the toolsets

used to arrive at the final product have. BIM tools bring a level of automation into

the process which offer potential savings in time and effort yet the interpretation of

the data output still requires a skilled and experienced user to be able to make

accurate judgments on what is presented within the virtual prototype. An example of

this from the research is provided via Interviewee 3 who represents a leading design

organisation in the ‘early adopter’ category;

“…the quality of our information is absolute, what it does affect is the

process, it will affect how much time and effort we will spend in that process,

I’d like to think that working in 2D or 3D our information would be the same

quality, we still have professional liability no matter what medium you put

that in…”

Similarly, Interviewee 7 who represents a design organisation from the ‘early

majority’ category also displayed confidence in the quality of the final product

delivered;

“…I’d be pretty confident were be able to get the document set right, I think

we have got a very strong pool of staff that enables us to do that, you still

need good people evaluating what's going on otherwise mistakes will

happen...”

These findings counter much of the literature which gives the impression that all

traditional 2D projects are inherently flawed. As such they serve as useful indications

63

of the primary importance of the quality of the human resources over and above any

contemporary technological based solutions and the process automation they bring.

This point was surmised by Interviewee 5;

“…the hard and software is only about 20per cent of what you are doing, it’s

still about people, it’s about peoples interaction how they work with each other

and the information they provide to each other...”

5.9 Factor 7 - Harnessing the Potential of Innovative BIM technologies

BIM is a powerful agent for change because the ‘digitisation’ of design information

enables a large number of potential applications and benefits for project stakeholders

across the industry (Kreider, 2010). An organisations BIM maturity is considered to

be an important factor in improving the quality of Production Information and the

generation of benefits as the research appears to show that a higher relative level of

expertise appears to enable access to value adding technologies, processes and

business opportunities. Each of the ‘early adopters’ provided examples of this in

practice. One example given by Interviewee 3 was the use of the off-site process

innovation ‘DfMA’ (Design for manufacture and assembly) which drives benefits

time, cost, and quality and carbon reduction.

“…we're developing relationships on a number of fronts, one of the more

recent or successful ones is with Laing O'Rouke their Explore faculty, for

DfMA, were picked by them on projects because we can deliver schemes that

work with that system…”

Incidentally the process also requires early contractor involvement in the process

which in itself offers significant benefits. While outside the scope of this particular

study, the effect early contractor involvement on the quality of Production

Information would be an interesting avenue for further research.

Examples from Interviewee 4 include setting up of dedicated BIM consultancy to

capitalise on frequent requests for assistance. A further example was given by

Interviewee 5 who describes how the use of iPads connected to the BIM database has

changed working practices , leading to improved quality;

64

“…we are linking the iPad, the database in the cloud and our associated

information with the objects and elements that we have actually constructed

and that gives us traceability, quality matters.. The iPad has moved 20pc of

the engineer’s time back out on site…”

With reference to the ‘short-term’ benefits identified in McGraw Hill report (Refer

Figure 8) the examples given above seem to fall within the ‘Offer new services’ and

‘market new business’ categories and in this regard the research appears to validate

the literature. For organisations in the ‘early majority’ category, the benefits are

offered by BIM technology are also available, however harnessing the potential

appears to be governed by their capability to manage the significant changes

required. This was illustrated by Interviewee 6 and in part appear to support the

findings discussed in Factor 6;

“…we’re are all aware that's there’s all sorts of advantages of other stuff we

can do, but there's so much out there, but we need to control which bits were

fully engage with because to try and to do the whole thing at the same time

would just blow our collective minds, first we are focusing on how does this

program work and then I suspect we will look at what other opportunities

does it afford us…”

5.10 Factor 8: Balancing Risk and Reward

In order to harness the potential of BIM technologies it is necessary to take the initial

decision to implement BIM and then subsequent decisions thereafter regarding the

pace and scale of the deployment, all of which initiate a process of change both at a

project level and organisational level. As such there are a number risks and rewards

that need to be managed. Ashcraft, (2010) identifies a number of legal risks to be

considered including insurance and design liability related issues as well as

technological and interoperability issues. While these issues may put people off,

there are also the risks of not adopting BIM, for example exclusion from existing

public frameworks as the government mandate come into effect and increasing

numbers of private sector clients and demand BIM and better performance. Similarly

and with regard to Production Information processes, BIM brings both risks and

rewards.

65

Balancing the risks and the rewards can be managed through a process of informed

decision making where investments in resources are carefully targeted to maximise

the potential of opportunities immediately available while also developing a long

term vision for continuous improvement and capitalisation of emerging

opportunities. An important factor in this regard is the ability to understand the

business as it exists in the present while engaging with relevant stakeholders to plan

at both business and project levels. At a project level this alludes to the importance of

BIM execution planning and at a business the importance of having a strategy and

vision in place that places the organisation in a position that balances the risk and

reward. Interviewee 5 illustrates this via analogy;

“…I liken it to riding the crest of a wave, if your windsurfing and you’re on

the wave if you get too far in front, it will just break over the top of you, and

so you have got to ride with everyone else, with the information and

technology you have got at the moment, but with the vision of where you

trying to get to… “

An example of the benefits of getting the balance right was provided by Interviewee

4;

“…without BIM this practice wouldn’t exist, this practice has grown because

of BIM it has allowed us the thrive during the recession…in 2008 we were

working on a series of £1m jobs and few smaller jobs, were now working on

£5m up to £60m…”

While an example of the executing the planning process planning is given below;

“…for every project we have a facilitated meeting with the project team to

work out what's important to them what do they really need to manage so

they can bring the technology and the skills and focus on a particular areas

that are going to give them good return, it’s like picking the low hanging

fruit…”

While specifically on Production Information the following examples were provided

in the research;

66

“…it can be completely automated, a heck of a saving for us, the legal

implications of getting it wrong were massive so it’s a risk mitigation process

for us…”

“…we are doing this because we think it has value not because the client has

asked for it, I don't think we have actually delivered one job yet where the

client has actually demanded it…”

“…do you want to schedule out all the doors on 406 flats?..No, that's soul

destroying if somebody gets a door wrong that’s 60 wrong doors, so we can

limit some of our risk with it…”

67

5.11 Factor 9: Integration Barriers

A significant theme that emerged from the research was the experience of

procurement related barriers that prevent the full potential of collaborative working

using BIM to be realised. Typically this manifested as either a delay to the

consultants information exchange necessary for an effective coordination process, or

a lack of BIM compatibility or capability altogether. The integration of design

disciplines and their respective information is one of the major benefits identified in

the literature and in this regard the degree of integration has a large impact on the

quality of Production Information. As Interviewee 6 put it;

“…because a lot of the other consultants aren't on Revit, we have to revert to

the lowest common denominator which is a bunch of drawings for them to go

through…”.

This alludes to the significant erosion of potential if members of the team are not

aligned with BIM processes as many of the reported benefits are dependent on access

to compatible and timely provision of information into the BIM database.

A particular issue appears to be a fundamental incompatibility between existing

procurement methodologies and the requirement for ‘shifting the effort’ necessary to

resolve design issues early as characterised by the Mcleamey curve. Integration

between Architects and Structural Engineers appears to occur quite satisfactorily

within the context of Level 2 BIM, however most Interviewees noted that delays to

the appointment and limitations on the scope of design services of M&E consultants

and subcontractors was a major barrier for improvements in productivity;

“…they (M&E) won’t want to do anything until design freeze and that’s too

late, on the couple of jobs I've been involved with, we've been basically fitting

in the M&E to an existing building and that's not how this process is

supposed to work…”

“…you see so much reluctance to get involved early doors because there's so

much work that would be abortive…”

68

“…all the wash about BIM being integrated it doesn't really work with the

process at the moment because of the way designs are progressed at

completely different timescales…”

“…if the whole project team isn't working to the same goal and if the whole

project team isn't looking to deliver information, it’s not going to happen…”

These issues appear to be deeply rooted within procurement and contractual related

practices as well as a simple incompatibility in the processes that each discipline

need to follow to execute a design and still achieve a profit. Further rationalisation

of the causes would be speculation and beyond the scope of this particular study,

however a future study into the benefits and barriers of using integrated procurement

methods such as IPD (Integrated Project Delivery) on BIM projects would be an

interesting avenue for further research. The Interviewees offered several views on the

issues associated with this;

“…what we have got to go to is an early contractor involvement where this

can work, because you’re engaging people from the beginning who are going

to take this right until the end…”

“…there are people on the project at execute level that needs to drive it...”

While issues such as hardware and software issues and training costs issues were

reported by the Interviewees as barriers to progress, it is apparent that there are far

greater barriers preventing the full potential of the BIM workflow that may be

beyond the remit of those responsible for the delivery of quality Production

Information to solve. An important factor appears to be the need for comprehensive

understanding of process at client and client advisor level to select a procurement

methodology that enables the BIM process to function as intended. It appears that the

design consultants are capable, willing and able to embrace the changes albeit at a

rate to suit own individual circumstances, the question seems to be if the client side

of industry can align itself to match the requirements of the BIM paradigm, this is

illustrated below;

“…at the moment it’s being left to the designers and contractors to sort out

because the client just doesn't understand…”

69

“…we can do it dead easy, but getting someone to know what they are doing

with it at the other end is a completely different ball game all together, we've

spent so long as a practice promoting 3D integration, with so much

resistance…I'm whole heartedly behind getting there I just wish we could do

it tomorrow…”

“…you explain to them that it’s a party and everyone has got to come to it for

it to work…”

“…we’re finding it very difficult to enforce on projects because the industry

just isn't ready for it, everyone's at different at stages, people won’t pay more,

they won’t pay it even if there's potential savings...”

“…the potential for simultaneous working is not ingrained in the business, it

is within our design office, it may well be within our consultants, as a

construction team or the stakeholders, were not there yet…”

Despite these challenges there remains a huge amount of potential for improvements

in quality. Industry leaders appear to be resolute in the value it brings themselves and

their partners;

“…there's nothing that stops us doing our job we still work the way we work,

if a contractor’s got zero interest in BIM, we’ll still work in BIM and they'll

get their drawings at the end of it…”

“…more and more often were working with people we want to be working

with, most companies that we work with a pretty proficient, increasing were

in a position where we can choose who we work with, I think that's key to

success, we can pick who we want to work with, we still occasionally get the

arranged marriage scenario…”

“…we’re not doing this because the government wants it, were doing it

because we perceive a business need for it...”

“…I think on the next job I think they be a bit more savvy…it’s incredible

really the benefits...everyone tends to have a light bulb moment, and will

never look back…”

70

5.12 Summary of Findings

Based on the analysis and discussion a summary in which key factors arising from

the work are presented below;

Factor 1: Effective virtual prototyping

1. That the ability to effectively virtual prototype is a fundamental difference

between the 2DCAD and BIM design paradigms. BIM enables a process of

delivering Production Information in a way that is fit for purpose. By building

virtually, design problems are brought to the surface and resolved, leading to a

reduced risk of rework.

Factor 2: Visualisation and understanding

1. The ability for the whole team to accurately and quickly visualise and understand

the design is an essential factor in delivering better quality Production

Information. The research verifies the literature on this matter.

2. BIM is a direct counter measure to the problem of erroneous interpretation and

poor decision making as problems are revealed, understood and resolved.

3. Subsequential learning is embedded in the process and is a powerful aid in

improving decision making. Over time improvements in understanding across the

industry will bring benefits from improved understanding of design and the

reduction of ‘black boxes.’

4. Visualisation does not just refer to 3D but can be taken to mean to be able to ‘see

with clarity’ many aspects of the design, e.g. 4D, 5D, 6D. Clarity brings

efficiency.

Factor 3: Upfront investment driving downstream value

1. Time invested in developing the BIM database can save the initial investment

many times over and opens up the potential to use the data for multiple value

adding activities.

2. At an organisational level investment in staff and technology that facilitates

better long term benefits represents a sound philosophy of management and

decision making.

Factor 4: Process rigour and Transparency

1. The BIM workflow forces early intellectual investment in resolving the design by

forcing the user to stop and fix design issues. This reduces the risk of unresolved

information being ‘passed down the line.’

2. The BIM workflow is based on a sound process methodology which demands a

level of rigour that directly counters the problem of incomplete and

uncoordinated information, although this this is heavily dependent on the

capability and diligence of the user.

71

Factor 5: Information cohesion, integrity and Automation

1. Automation and inherent data integrity are fundamental toolset improvements

which have a positive impact on the quality of Production Information. The

research validates the theory contained in the literature.

Factor 6: User capability and organisational BIM maturity

1. A critical factor in the delivery of quality Production Information is the

capability, experience and diligence of the user supported by an organisation with

mature practices.

2. Leading companies will likely deliver quality whatever design paradigm or tools

are used. (User capability is a more important factor)

3. Intellectual effort expended by capable, diligent and experienced staff, supported

by mature organisational processes and appropriate BIM tools are core

requirements for delivering high quality Production Information.

Factor 7: Harnessing the potential of innovative BIM technologies

1. Organisations with the aspiration and capability to take advantage of the

emerging opportunities brought about by the digitisation of the construction

industry are able to make significant advances in process and benefits.

2. BIM facilitates the consistent delivery of quality Production Information and the

generation of significant other benefits and business opportunities.

Factor 8: Balancing Risk and reward

1. BIM brings both risks and significant rewards that need to be carefully managed

and planned for both at a business level and at a project level. Correctly

balancing and managing the risk of BIM implementation brings these rewards.

2. Awareness and holistic understanding of the available options and capabilities of

project partners and the wider industry is necessary to balance the level of risk

and reward.

3. The industry is already experiencing significant changes which will continue to

gather momentum post 2016. It is necessary to be aware of and plan for changes

and opportunities brought about by a rapidly emerging field of expertise.

Factor 9: Integration barriers

1. Although BIM has the potential to facilitate ‘simultaneous working’ and

integration, procurement issues appear to significantly and negatively impact on

the ability of project teams to realise an integrated design process. The theory

contained in the literature is not therefore verified by the research conducted in

this study.

2. Significant erosion of the benefits reported in the literature result from

procurement barriers to providing the level of information required at the correct

time. While structural engineers appear to integrate satisfactorily, M&E design

appears to be a particular issue.

72

3. Regardless of the barriers, there is still inherent value in BIM processes, those

organisations interviewed would not choose to revert back to 2DCAD process.

4. Leading companies who have demonstrated the potential of BIM based design

are able to invoke a ‘light bulb moment’ for change in the thinking of clients who

have experienced the benefits of BIM based design.

73

6.0 Chapter Six – Conclusions

6.1 Introduction

The principle aim of the study was to investigate the essential factors associated with the

delivery of improved Production Information quality using BIM enabled working

practices. This chapter therefore presents concluding remarks of the study by attempting

to connect factors identified in the literature with the data collected during the study.

In support of the aim, Section 6.3 addresses objective 5 which was to conclude the study

with a series of recommendations that can assist design organisations in maximising the

potential of BIM enabled by design processes within the context of the factors identified

in the research.

The Limitations of this study and recommendation for further studies are described in

Section 6.4 and 6.5 respectively.

6.2 Conclusions

The UK construction industry, as discussed in Part A of the Literature review, has been

recognised as suffering from poor performance against a range of key benchmarks.

Untrustworthy Production Information has been found to result in failure across a

number of quality indicators including, timeliness, accuracy, completeness, coordination

and conformance, all of which lead to the waste of rework. Primary contributing factors

presented in the Root cause analysis (Refer Figure 15) included fragmentation, the

inherently flawed nature of the 2DCAD paradigm and poor information management

practices.

In Part B of the literature review, strategic countermeasures initiated by the Government

via PAS1192-2 were identified as were the characteristics and benefits of the BIM based

design paradigm. A summary of the interaction of the findings from Parts A and B of the

literature review were presented in the Theoretical model for the study in Chapter 3

which formed the basis for the research questions and data collection and analysis phase.

74

The conclusions from the primary research are presented here;

The study firstly concludes that adopting BIM based design does result in a beneficial

change to the way people work and the way Production Information is produced and

managed.

Much of this can be attributed to the fundamental change in capability of the software

which was found to facilitate ‘virtual prototyping’ of the building in way that is fit for

purpose. The ability to virtually construct and simulate the building in advance of

construction brings issues to the surface that can be accurately visualised, interpreted and

understood. The clarity that comes from understanding enables better decisions to be

taken that span across the project lifecycle. This can result in a better chance of getting

the build right first time and eliminating the waste of rework.

This study concludes that the decision to invest in BIM technologies represents a sound

long term investment that offers significant opportunities for those willing and able to

take full advantage of its potential.

The emerging standards and protocols, particularly PAS1192-2 are intended to bring

about an improved level of and standardisation and accountability which demands a

level information management many may not be used too, nor see the relevance of.

However, the fact is that BIM is the core facet and mechanism through which the

Governments construction strategy aims to deliver a change to industry working

practices. As such its implementation brings changes to the way people think and work

and with that comes both risks and rewards.

This study concludes that by carefully planning and balancing the risks and rewards of

BIM implementation, the opportunities brought about by industry change and the

development of innovative technologies can bring about significant business and project

level benefits.

The study found that considerable improvements in information integrity, cohesion and

automation enabled by BIM were an important factor in the delivery of quality

Production Information. The sooner that an organisation is able to realise and harness the

inherent potential within the technology the greater the chances of capitalising on the

emerging opportunities as the critical mass of industry begins to understand how the ever

growing applications enabled by BIM technology can enhance their business. The

75

research showed that ‘early adopter’ organisations who have correctly balanced the risk

now appear to be generating significant benefits in many facets of their business

including time and cost efficiencies, but also in terms of reputation, marketing and value

generating collaborations with other leading practices.

Looking forward, the construction industry is well known for its slow pace of change,

this in itself brings both risk and rewards as the industry changes look set to continue for

years to come. BIM maturity Level 3 has not yet officially been defined and the rapid

development of technology is certain to bring about new techniques, technologies and

opportunities for those with the foresight and capability to harness them.

This study concludes that the user capability and organisational BIM maturity is the

most important positive factor in delivering quality Production Information and

increased value.

In contrast to the holistic and wide ranging viewpoint of BIM technology, the research

found that BIM is in effect only a tool. As such, the tool is still heavily dependent in the

capability of the user to operate it, the adage ‘rubbish in, rubbish out’ is most applicable.

Without competent, experienced and diligent users BIM technology cannot realise its

full potential. Furthermore, the use of the increasing array of value adding BIM

applications may be restricted in part only by the an organisations ability to operate it. It

can therefore be concluded that a long term investment in staff development and

capability is necessary to enable those applications that will deliver the highest value.

Looking forward, the latest and most valuable technology is in time, likely to become

commonplace. Focused research, long term investment, development and application of

an organisations best human and material assets towards specific value adding

technologies is likely to bring to significant benefits. To achieve a strong staff capability

and overall BIM maturity it is necessary to invest in one.

This study concludes that uncollaborative procurement practices and a lack of

understanding at client level are major negative factors that prevent discipline

integration, leading to the erosion of the potential of BIM based design to counter the

problems associated with fragmentation.

While user capability is considered to be most important positive factor in the delivery of

quality production information, the lack of disciplinary integration resulting from

uncollaborative procurement practices was found to be the most important negative

76

factor. The quality of the final product can only be as good as the information it was

based up at the time it was produced and issued. If the necessary information is not

available at the time it is required, the major indicators of quality as defined in this study

are all adversely affected. For clarity they are repeated here; completeness, coordination,

accuracy, conformance and timeliness. A major benefit and fundamental principle of

BIM based design is the resolution of design issues in the design stage where they

belong. Regardless of the innovative technologies used rework of some kind can almost

be guaranteed if a design discipline is missing from the design process, in this regard it is

concluded that while BIM offers the potential for more integrated working, in practice

the way in which projects are procured will most likely have a greater effect on the

quality of the final output than the software platform used. BIM enables a process of

virtual prototyping that is fit for purpose, until there is widespread alignment with more

integrated project delivery methodologies, the problems of fragmentation are likely to

remain.

In the long term and on a positive note, increased awareness of the importance of

integration combined with a demonstration of the value that BIM technology can bring

to a project of any size will result in a change in thinking and priorities in favour of using

the right tools to deliver the right results. Ultimately most people seem to have a ‘light

bulb’ moment when the holistic benefits of BIM and the associated working practices

become apparent, given time it is expected that increasing numbers of clients and

executive level stakeholders will demand a process that contains a complementary and

integrated mix software platforms and procurement practices of that allow projects to

succeed in delivering better quality Production Information and overall project

performance.

77

6.3 Recommendations

In part fulfilment of Objective 5 and within the context of the factors identified by

the research, a series of recommendations are offered to those organisations seeking

to future benefits through the use of BIM enabled design;

1. Create a strategic vision that allows capitalisation of the risk and rewards

brought about by industry changes.

2. Undertake an internal and external capability assessment to identify and

understand what factors are affecting the potential level of benefits both at

project and organisational levels.

3. Research and identify the ‘low hanging fruit’ as well as the long term

technology investments that align with an organisations vision. Ensure a

robust business case for innovative technology investments.

4. BIM complements lean thinking and lean project delivery; replace non-value

adding activities with more appropriate processes. Right process will bring

right results (Liker, 2004).

5. Develop a philosophy of developing people and teams. Long term Investment

in staff capability, is the most important investment decision. Bring in

capable staff with experience in the selected technological applications to

increase your available toolsets and increase overall BIM capability.

6. Build value adding collaborations with compatible and capable consultants.

Work together to intelligently harness the BIM database for multiple uses

across stages and design disciplines to offer new and integrated services to

clients.

7. Use the full potential of the technology to present complex design items with

clarity so that clients, contractors and the extended supply chain can

accurately interpret and understand the design intent.

8. Use the full potential of the technology to automate and standardise processes

as much as possible to reduce the risks of human error and lack of diligence.

9. Continuously seek to improve the clarity and quality of the Production

Information produced with the intention of eliminating all forms of rework.

Track progress with appropriate metrics and KPI’s.

78

10. BIM is a rapidly evolving field that will continue to evolve for some years.

Take responsibility for keeping up to date. Regularly reporting and share

knowledge with regard to changes in technologies, standards and

opportunities in order to capitalise on the growing value adding applications

offered by BIM.

11. Track the progress and deployment of more integrated forms of project

delivery (Such as IPD). Research, understand and implement those principles

and practices where possible.

12. Seek to deliver innovative solutions that instil ‘Light bulb’ moments in those

with the authority to direct project procurement routes.

79

6.4 Limitations of the Study

There are a number of limitations of the study. Firstly, the number of research

participants was only seven, to obtain a degree of statistical significance a far larger

scale study would need to be conducted, however this was not the intention of the

study nor was it feasible within the research period. Similarly, the research focused

specifically on Architects, excluding of many other disciplines however this

rationalised as often in the lead designer role, Architects were most likely to have a

holistic view of the change brought about by BIM processes. In justification of this

approach, criterion sampling was used to ensure those selected sufficiently

experienced to provide meaningful data. Triangulation via inclusion of the Civil

Engineering and Design management professions achieved little in the way of

external validity but did offer a useful cross comparison of data which was

considered more important that making wider generalisations. Similarly, because of

the sample was subdivided into the ‘early adopter’ and ‘early majority’

classifications, the transferability of the findings is considered to be limited,

representing only the researchers interpretation of the data available within the

allotted timeframe.

Another limitation was that of researcher bias, this is a well-documented risk of the

qualitative approach. In this regard, conscious efforts were taken to avoid any

preconceived notions and accurately transcribe the interviews to avoid any influence

and misinterpretation of meaning.

Finally, despite the initial intention, this study did not follow a strictly Grounded

theory approach as originally intended by Glaser & Strauss. This was because the

study came to be more one of explanation with an emphasis on providing practical

recommendations rather than generation of theory. As such the research design was

tailored to suit the objectives of the study rather than following a strict adherence to a

particular research tradition.

80

6.5 Recommendations for Future Research

Four avenues for further research were identified.

Firstly, with reference to Factor 9 identified in this study, by seeking to understand

why unintegrated procurement methods continue to be used when alternative options

appear to be available, research could be conducted to investigate the barriers

preventing the widespread use of Integrated Project Delivery (IPD) and associated

collaborative contracts in the UK. Evidence from the USA (AIA, 2007; Eastman et

al, 2011) appears to suggest that the combination of BIM and IPD brings widespread

benefits which can address the problems of fragmentation.

Secondly, although the researcher was not specifically looking for associations

between BIM and Lean thinking, many of the factors that emerged from the data

appeared to display a positive correlation with the principles of Lean. Although

PAS1192-2 does reference Lean, a specific study into the association benefits of

between BIM and Lean within the UK context would be an avenue for research.

Thirdly, detailed case studies exploring the issues associated with projects delivered

using BIM level 2 working practices as specified by PAS1192-2 would be useful to

investigate how the documents impact upon the performance of both small and large

scale projects.

Finally, by seeking to emulate the behaviours and practices of leading companies a

wider criterion based study of ‘Early adopters’ could be conducted to investigate in

detail the factors and benefits of highly performing teams who use innovative BIM

technologies to deliver better projects.

81

References

Abukhder, J., & Munns, A. K. (2003). Attributing management problems on

construction projects to project information. Proceedings 19th Annual

ARCOM Conference, Brighton.

Ackermann F., Eden C., Williams T.,(1997) Modelling litigation: mixing qualitative

and quantitative approaches, Interfaces, 27(2), 48–65.

AIA, U. (2007). AIA California Council. Integrated project delivery: a guide

[M/OL]. Washington: The American Institute of Architects, : American

Institute of Architects.

Alarcón, L. F., & Mardones, D. A. (1998). Improving the design-construction

interface. Paper presented at the 6th Annual Conference of the International

Group for Lean Construction. Proceedings… Guarujá, Brasil: IGLC.

Ashcraft, Howard W. "Building information modelling: a framework for

collaboration." Constr. Law. 28 (2008): 5.

Azhar, S. (2011). Building information modelling (BIM): Trends, benefits, risks, and

challenges for the AEC industry. Leadership and Management in

Engineering, 11(3), 241-252.

B. Hardin, (2012). BIM and Construction Management: Proven Tools, Methods and

Workflow. Indianapolis: Wiley,

Baldwin, A.N., Austin, S.A., Thorpe, A. and Hassan, T.M. (1995) Simulating quality

within the design process, in Proceedings of the American Society of Civil

Engineers (ASCE) Second Congress on Computing in Civil Engineering,

Atlanta, Georgia, June, pp. 1475± 82.

Ballard, G. (1999), Can Pull Techniques Be Used In Design Management, Presented

at the Conference on Concurrent Engineering in Construction, Helsinki,

Finland. August 26–27.

Barlish, K., & Sullivan, K. (2012). How to measure the benefits of BIM—A case

study approach. Automation in Construction, 24, 149-159.

BIM task group, (2014). The Case study for HMYOI Cookham Wood Report

Available at: http://www.bimtaskgroup.org/wp-

content/uploads/2013/07/HMYOI-Cookham-Wood.pdf (Accessed: 18th April

2014)

BIPS, 2008 - Cad-Manual 2008; anvisning; C102. Bips, press release June 2008.

Available at: http://bips.dk/værktøjsemne/cad-manual-2008

BIS. (2011). A report for the Government Construction Client Group, Building

Information Modelling (BIM) working party strategy. Department for

Business Innovation & Skills (BIS). Retrieved from

http://www.cita.ie/images/assets/uk%20bim%20strategy%20(summary).pdf

82

Bloomberg, L. D., & Volpe, M. (2012). Completing your qualitative dissertation: A

road map from beginning to end. Sage Publications.

Bloomberg, L. D., & Volpe, M. (2012). Completing your qualitative dissertation: A

road map from beginning to end. Sage Publications.

Bouchlaghem, D. (2011). Collaborative Working in Construction. Taylor & Francis.

British Standards Institute (2007) BS 1192; Collaborative production of architectural,

engineering and construction information – code of practice [Online]

Available at:

http://www.ihsti.com/CIS/Doc.aspx?AuthCode=CC700C&DocNum=285074

&from=%2fCIS%2fSearch.aspx%3fAuthCode%3dCC700C%26fs%3d0_doc

_Type_False_AND%26t%3dBS1192%26pt%3ds%26st%3d0&t=BS1192&pt

=s&type (Accessed: 10 July 2014)."

Bryde, D., Broquetas, M., & Volm, J. M. (2012). The project benefits of Building

Information Modelling (BIM). International Journal of Project Management.

doi:10.1016/j.ijproman.2012.12.001.

Bryman, A. (2012). Social research methods: Oxford university press.

Bryman, A., & Bell, E. (2011). Business Research Methods 3e: Oxford university

press.

BSI. (2013). PAS 1192-2:2013 - Specification for information management for the

capital/delivery phase of construction projects using building information

modelling. Available at http://shop.bsigroup.com/Navigate-by/PAS/PAS-

1192-22013/ (Accessed 22 January 2014)

Burati, J.L., Farrington, J.J. and Ledbetter, W.B. (1992) Causes of quality deviations

in design and construction. Journal of Construction Engineering and

Management, 118(1), 34–49.

CIC. (2011). Government construction strategy. Retrieved 1/22/1014, from

https://www.gov.uk/government/publications/government-construction-

strategy

CIC. (2013). The BIM Protocol.

Clough, P., & Nutbrown, C. (2012). A student's guide to methodology. Sage.

Coates, P., Arayici, Y., Koskela, K., Kagioglou, M., Usher, C., & O'Reilly, K.

(2010). The key performance indicators of the BIM implementation process.

Coles E. J., Design Management: A Study of Practice in the Building Industry, The

Chartered Institute of Building, Occasional Paper No.42, UK, 1990, 32.

Constructing Excellence (2012) 2011 UK industry performance report based on the

UK construction industry key performance indicators. [Online] Available at:

http://www.architectsjournal.co.uk/Journals/1/Files/2011/7/13/KPI2011v7.pd

f (Accessed: 28August 2014).

83

Construction, M. H. (2012). The business value of BIM in North America: multi-

year trend analysis and user ratings (2007-2012). Bedford, MA: McGraw-Hill

Construction.

Crabtree, B. F., & Miller, W. L. (1999). Using codes and code manuals: a template

organizing style of interpretation. Doing qualitative research, 2, 163-177.

Creswell, J. W. (2013). Research design: Qualitative, quantitative, and mixed

methods approaches: Sage.

Crotty, R. (2011). The Impact of Building Information Modelling: Transforming

Construction. Routledge.

Dawood, N. N. and Iqbal, N. (2010) 'Building information modelling (BIM): A

visual & whole life cycle approach', CONVR2010, Sendai, Japan, November

4-5, 2010, in Makanae, K., Yabuki, N. and Kashiyama, K. (eds) Proceedings

of the 10th

international conference on construction applications of virtual

reality. CONVR2010 Organizing Committee, pp.7-14"

DeFraites A. A. Jr., Fee versus quality, ASCE Journal of Professional Issues in

Engineering, 1989, 115(2), 125–128.

Denscombe, M. (2010). Ground Rules for Good Research: Guidelines for Good

Practice. 2nd edn. Maidenhead: Open University Press."

Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM handbook: A guide to

building information modelling for owners, managers, designers, engineers

and contractors: Wiley. com.

Erdogan, B., Anumba, C. J., Bouchlaghem, D., & Nielsen, Y. (2008). Collaboration

environments for construction: Implementation case studies. Journal of

Management in Engineering, 24(4), 234-244.

Evbuomwan, N. F. O. and Anumba, C. J., (1995) .Towards a concurrent engineering

model for design and build projects. Journal of the Institution of Structural

Engineers, , 74(5), 73–78.

Fellows, R., & Liu, A. (2008). Research methods for construction. Oxford, UK

Blackwell.

Formoso, C. T., Tzotzopoulos, P., Jobim, M. S., & Liedtke, R. (1998). Developing a

protocol for managing the design process in the building industry. Paper

presented at the 6th Annual Conference of the International Group for Lean

Construction, Guaruja, SP.

Gallaher, M. P., O’Connor, A. C., Dettbarn, J. L., & Gilday, L. T. (2004). Cost

analysis of inadequate inoperability in the capital facilities industry. National

Institute of Standards and Technology (NIST) Technical Report No. NIST

GCR-04-867.

Glaser, B. G., & Strauss, A. L. (2009). The discovery of grounded theory: Strategies

for qualitative research: Transaction Publishers.

84

Hardin, B. (2011). BIM and construction management: proven tools, methods, and

workflows. John Wiley & Sons.

Harty, J.; Laing, R., (2013) Facilitating meaningful collaboration in architectural

design through the adoption of BIM (Building Information Modelling),

Computer Supported Cooperative Work in Design (CSCWD), 2013 IEEE

17th International Conference on , vol., no., pp.502,508, 27-29 June

doi:10.1109/CSCWD.2013.6581013

HM Government. (2012). industrial strategy: government and industry in

partnership. Retrieved June 10, 2014, from

https://www.google.co.uk/search?q=Industrial+strategy%3A+government+an

d+indu stry+in+partnership&ie=utf-8&oe=utf-8&aq=t&rls=org.mozilla:en-

US:official&client=firefox-a"

Howell, G.A. (1999) What is lean construction: 1999, Paper presented at the Seventh

Annual Conference of the International Group for Lean Construction, 26–28

July.

Berkeley, CA.J. Harty, (2012) The Impact of Digitalisation on the Management Role

of Architectural Technology.

Jacobsson, M., & Linderoth, H. C. (2010). The influence of contextual elements,

actors’ frames of reference, and technology on the adoption and use of ICT in

construction projects: a Swedish case study. Construction Management and

Economics, 28(1), 13-23.

Josephson P-E., Hammarlund Y. (1999)The causes and costs of defects in

construction. A study of seven building projects, Automation in Construction,

8(6), 681–642.

Kagioglou, M., Cooper, R., Aouad, G., Sexton, M., and Sheath, D. (1998). “A

Generic Guide to the Design and Construction Process Protocol”. Research

Report. The University of Salford, Salford, UK.

Karhu, V., & Lahdenpera, P. (1999). A formalised process model of current Finnish

design and construction practice. International journal of construction

information technology, 7, 51-71.

King, N. (2004). Using Interviews in Quantitative Research. Essential guide to

qualitative methods in organizational research, 2.

Koskela, L., Ballard, G., & Tanhuanpaa, V.-P. (1997). Towards lean design

management. Paper presented at the Proceedings of the 5 th annual

conference of the International Group for Lean Construction.

Kreider, R., Messner, J., & Dubler, C. (2010). Determining the frequency and impact

of applying BIM for different purposes on projects. In Proceedings of the 6th

International Conference on Innovation in Architecture, Engineering &

Construction (AEC), June (pp. 9-11).

85

Li H., Love P. E. D., Drew D.,( 2000). Modelling the effects of prolonged overtime

work on project cost and quality, Engineering Construction and Architectural

Management, 7(3), 211–221.

Liker, J. K. (2004). The Toyota way: 14 management principles from the world’s

greatest manufacturer.

Love, P. E., Mandal, P., Smith, J., & Li, H. (2000). Modelling the dynamics of

design error induced rework in construction. Construction Management &

Economics, 18(5), 567-574.

Love, P. E., Mandal, P., Smith, J., & Li, H. (2000). Modelling the dynamics of

design error induced rework in construction. Construction Management &

Economics, 18(5), 567-574

Love, P.E.D. and Gunasekaran, A. (1997), "Concurrent engineering: Research and

Applications, Vol5 No.2, June, pp.155-62

Lu, W., Zhang, D., & Rowlinson, S.(2013) BIM collaboration: a conceptual model

and its characteristics. Arcom Conference

M. Bew and J. Underwood, (2010) Delivering BIM to the UKmarket,"" in Handbook

of Research on Building Information Modelling and Construction

Informatics: Concepts and Technologies, J. Underwood and U. Isikdag, Eds.

USA: Information Science Reference (an imprint of IGI Global), pp. 30-64.

M. Ibrahim, R. Krawczyk, G. Schipporeit, (2004) A web-based approach to

transferring architectural information to the construction site based on the

BIM object concept, CAADRIA 2004 Conference, Seoul, South Korea, pp.

1–10.

M. Latham, (1994) Constructing the team: The final report of the

Government/Industry review of procurement and contractual arrangements in

the UK construction industry, HMSO, UK.

McGeorge, J.F. (1988) Design productivity: a quality problem. Journal of

Management in Engineering, 4(4), 350–362.

Narayan, K. Lalit (2008). Computer Aided Design and Manufacturing. New Delhi:

Prentice Hall of India. p. 3. ISBN 812033342X.

NBS. (2014). National BIM Report 2013.

NEDC Report, Achieving quality on building sites, Building and Economic

Development Committee, NEDO, London, 1987.

Neff, G., Fiore-Silfvast, B., & Dossick, C. S. (2010). A case study of the failure of

digital communication to cross knowledge boundaries in virtual construction.

Information, Communication & Society, 13(4), 556-573.

Penttilä, H. (2006). Describing the changes in architectural information technology to

understand design complexity and free-form architectural expression.

86

Philp, D (2012) BIM and the UK Construction Strategy. Building Information

Modelling [Online], Available:

http://www.thenbs.com/topics/bim/articles/bimAndTheUKConstructionStrate

gy.asp [Accessed 05-04-2014]."

Qu, S. Q., & Dumay, J. (2011). The qualitative research interview. Qualitative

Research in Accounting & Management, 8(3), 238-264.

Ralph Kreider, John Messner, and Craig Dubler, “Determining the Frequency and

Impact of Applying BIM for Different Purposes on Building Projects,” in

Proceedings of the 6th International Conference on Innovation in

Architecture, Engineering and Construction (AEC) (Penn State University,

University Park, PA, USA, 2010), http://www.engr.psu.edu/ae/AEC2010/.

REGH. (2014). Research Ethics and Governance Handbook.

www.northumbria.ac.uk/static/5007/research/reghandbook.pdf (Accessed 11

July 2014)

Sacks, R., Koskela, L., Dave, B. A., & Owen, R. (2010). Interaction of lean and

building information modelling in construction. Journal of construction

engineering and management, 136(9), 968-980.

Saunders, M. N., Saunders, M., Lewis, P., & Thornhill, A. (2011). Research methods

for business students, 5/e: Pearson Education India.

Shahrin, F. A., & Johansen, E. (2013, June). Challenges in Engaging the Client

During the Capture, Translation, Transformation and Delivery (cttd) of Client

Requirements (cr) Within The building I. In 7th Nordic Conference on

Construction Economics and Organization (Vol. 2013). Akademika forlag.

Sinclair, D. (2012). BIM overlay to the RIBA outline plan of work. London, UK:

RIBA.

Sinclair, D. (2012). BIM Overlay to the RIBA Outline Plan of Work.

Strauss, A., & Corbin, J. (1994). Grounded theory methodology. Handbook of

qualitative research, 273-285.

Succar, B. (2009). Building information modelling framework: A research and

delivery foundation for industry stakeholders. Automation in Construction,

18(3), 357-375.

Succar, B., Sher, W., & Williams, A. (2012). Measuring BIM performance: Five

metrics. Architectural Engineering and Design Management, 8(2), 120-142.

Svelinger P.-O., (1996) Organisational Coordination in the Design Phase Report 44, ,

Chalmers, Goteborg, Sweden.

Thomassen, M. (2011). BIM & Collaboration in the AEC Industry. Construction

Management, Master's (MSc) Thesis (Released 31 August 2011, p. 120, in:

http://projekter. aau.

87

dk/projekter/files/55376698/BIM_Collaboration_in_the_AEC_Industry_by_

Mats_Thomassen. pdf.

Tilley P. A., (2000) McFallan S. L., Design and Documentation Quality Survey

Designers’ Perspectives, BCE DOC 00/113. CSIRO – Building, Construction

and Engineering, Melbourne, Australia.

Tilley, P. A., & Barton, R. (1997). Design and documentation deficiency-causes and

effects. In Proceedings of the International Conference on Construction

Process Reengineering.

Tilley, P. A., Wyatt, A., & Mohamed, S. (1997). Indicators of design and

documentation deficiency. In Proceedings of the Fifth Annual Conference of

the International Group for Lean Construction (pp. 137-148).

Winch, GM,. Managing Construction Projects. (2010) Chichester: Wiley-

Blackwell, , p.xiii.

Bibliography

Arwen, R. (2010). Early Stage Research Training: Epistemology & Ontology in

Social Science Research.

https://www2.le.ac.uk/colleges/socsci/documents/.../EpistFeb10.pdf

De Vaus, D. (2001). Research design in social research: Sage.

Farrell, P. (2011). Writing a built environment dissertation (1st ed.). Chichester,

West Sussex: Wiley-Blackwell.

Grillo, A. and Jardim-Goncalves, R. (2010) ‘Value proposition on interoperability of

BIM and collaborative working environments’, Automation in Construction,

19, pp. 522-530 Science Direct [Online] DOI: 10.1016/j.autcon.2009.11.003

(Accessed: 20 May 2013

Holzer, D. (2011). BIM's Seven Deadly Sins. International Journal of Architectural

Computing, 9(4), 463-480.

Humble, Á. M. (2012). Qualitative data analysis software: A call for understanding,

detail, intentionality, and thoughtfulness. Journal of Family Theory &

Review, 4(2), 122-137.

Leedy, P. D., & Ormrod, J. E. (2005). Practical research: Pearson Merrill Prentice

Hall Columbus, OH.

Marshall, C., & Rossman, G. B. (2010). Designing qualitative research: Sage.

Neuman, W. L. (2005). Social research methods: Quantitative and qualitative

approaches: Allyn and Bacon.

Robert Eadie, Mike Browne, Henry Odeyinka, Clare McKeown, Sean McNiff, BIM

implementation throughout the UK construction project lifecycle: An

88

analysis, Automation in Construction, Volume 36, December 2013, Pages

145-151, ISSN 0926-5805, http://dx.doi.org/10.1016/j.autcon.2013.09.001.

Saluja, C. (2009). A Process Mapping Procedure for Planning Building Information

Modelling (BIM) Execution on a Building Construction Project (Doctoral

dissertation, The Pennsylvania State University).

Saunders, M. N., Saunders, M., Lewis, P., & Thornhill, A. (2011). Research methods

for business students, 5/e: Pearson Education India.

Sebastian, R. (2010) Integrated design and engineering using building information

modelling: a pilot project of small-scale housing development in the

Netherlands. Architectural Engineering and Design Management, 6(2), 103–

10.

Veal, A. J. (2005). Business research methods: A managerial approach: Pearson

Education Australia/Addison Wesley.

Walliman, N. (2006). Social research methods: Sage.Azhar, S. (2011). Building

information modeling (BIM): Trends, benefits, risks, and challenges for the

AEC industry. Leadership and Management in Engineering, 11(3), 241-252.

89

Appendices

90

Appendix A: The seven core components of Level 2 BIM (Adapted from BIM

Task Group, 2014).

No Document Description Status

1 PAS1192:2:2013

‘Specification for information

management for the

capital/delivery phase of

construction projects using

building information

modelling’

This document provides information on the

management of data produced within a BIM

project environment, and supplements the

processes and procedures contained in BS

1192:2007. As well as expanding the CDE

(Common Data Environment) information

contained in BS 1192:2007. It also describes

documents which should be produced as part of

the BIM process, and details roles and

responsibilities necessary to implement a BIM

process on a project. It introduces concepts such

as employer’s information requirements (EIR) –

the employer’s expression what information they

require from the project and the format it should

be in, and BIM execution plans (BEP) – the

supply chain’s response to the EIR showing how

it will meet its requirements.

Available

- As of

Summer

2014

work has

started to

adopt

PAS

1192-2 as

an ISO

standard

2 PAS1192:3:2014

‘Specification for information

management for the

operational phase of assets

using building information

modelling’

This document describes the same data and

process delivery and use definitions as described

above, but for the operational phase of the asset.

Of key focus is the development of PAS 55

compliance operational strategies and the

effective transfer of data across into operations to

aid soft and effective landings from construction

to operation

Available

3 BS1192:4:2014

‘Collaborative production of

information. Part 4: Fulfilling

employers information

exchange requirements using

COBie – Code of practice’

BS 1192-4 will define expectations for the

exchange of information throughout the lifecycle

of an asset, and will include requirements for

reviewing and checking for compliance,

continuity and completeness. COBie is the UK

Government’s chosen information exchange

schema for federated BIM Level 2, alongside

graphical BIM models and PDF documents.

Draft

Available

Until 31st

July 2014

91

No Document Description Status

4 BIM Protocol Identifies building information models that are

required to be produced by the project team and

puts in place specific obligations, liabilities and

associated limitations on the use of those models.

Can also be used by clients to require the

adoption of particular ways of working – such as

the adoption of a common naming standard.

(CIC, 2013)

Available

5 Government Soft

Landings

A suite of documents describing Soft Landings

policy and processes to ensure effective

involvement of users and operators in the

development of scope, design and delivery. Also

ensuring effective training and handover into

operations and finally the structured gathering of

Post Occupation (Operational) Effectiveness data,

to enhance both the current and future assets.

Available

6 Classification Standardised system being developed to ensure

that data is able to be indexed and structured to

make it easily accessible in a common format

integrates with the Digital Plan of Work.

Currently

being

developed

(2014/15)

7 The Digital Plan

of Works (dPoW)

An industry standard method of describing

geometric, requirements and data deliveries at

key stages of the project cycle.

Currently

being

developed

(2014/15)

92

Appendix B: Fundamental principles of Maturity Level 2 BIM.

No Requirement’s Contents/notes

1 Originators produce definition information in

models which they control, sourcing

information

from other models where required by way of

reference, federation or direct information

exchange.( i.e. independent arch, Struct,

M&E models)

Level 2 Deliverables include:

3D models in native format

on graphical data (COBie)

2D PDF’s

2 (EIR’s)

Provision of a clear definition of the

employer’s information requirements and key

decision points (to form part of the contract

possibly through adoption of the CIC BIM

Protocol).

This document identifies what the client will

require from the supply team throughout the

design, construct and manage process.

Refers to the CIC Scope of Services

Levels of detail

Planning of work

Training

Collaboration process

Integrity and security for the project

Specific inclusions and exclusions

Compliance plan

Definition of project coordinates (space statement)

Schedule of software including version

Exchange of information

Clients strategic objectives

Responsibility matrix

Schedule of standards and guidance

Competence assessment process

BIM tender assessment details

3 Evaluation of the proposed approach,

capability and capacity of each supplier, and

their supply chain, to deliver the required

information, prior to contract award

N/A

4 BIM execution plan (BEP) shall be

developed by the supplier containing:

1) assigned roles, responsibilities and

authorities;

2) standards, methods and procedures; and

3) a resourced master information delivery

index (MIDI), aligned with the project

programme.

The CPix Post-contract BEP template

Roles and detailed resourcing

Revised project milestones

PIM delivery strategy

Approval process/responsibility

Survey strategy/legacy information

Responsibility matrix

Task team information delivery

Detailed project standards including; software

versions to be used, agreed exchange formats and

93

No Requirement’s Contents/notes

methodology, project specific naming conventions,

volume codes and status codes

5 (CDE)

Common data Environment

Provision of a single environment to store

shared

asset data and information

Deliverable is a process for a common environment:

All project information, whether in BIM

environments or in conventional data formats should

be shared using a single collaborative data

environment (CDE)

6 Application of the processes and procedures

contained in associated documents and

standards

BS1192:2007,

CPIx protocol,

CIC, BIM protocol

And others standards as reference n PAS 1192

94

Appendix C: Summary of Research Design

Epistemology: Constructionism

Theoretical perspective: Interpretivism

Methodology: Inductive/Grounded theory

Method: In-depth Interview

(Format taken from Crotty, 1999)

Scope: BIM implementation

Focus: People and process

Unit of analysis: Individuals within Organisational context

Sampling: Criterion

Type: Qualitative

Data managed: Thematic analysis

Analytical Approach: Inductive

Validity: 7 semi-structured interviews, in depth industry experience

When: June to Sept 2014

How Justified: Explanation of/Improvements to theory & practice

Ethical considerations: Signed consent forms

Logistics: Recorded interviews, descriptive coding, interpretive coding, Theme

generation.

(Format taken form Hart, 1998)

95

Appendix D: Interview protocol and Semi-Structured Interview questions.

Category Question

Number

Question

Production

information

processes

1 Please reflect upon your experiences of BIM based Production

Information processes and consider how they have changed when

compared to the 2DCAD paradigm?

Design review

processes

2 Please can you explain the Design review and Coordination

process you follow using BIM based design and reflect on how this

has changed since adopting BIM?

Coordination

benefits

3 With reference to the BIM based design. What are the major

benefits you are experiencing when checking and coordinating

production information.

Advantages of

Simultaneous

working

4 Theory suggests that the BIM based design requires 'shifting the

effort' as per the Mcleamey curve, please can you reflect on your

experiences of this?

Collaborative

working

5 Since adopting BIM based design. What changes have you

experienced in with regard to collaborative working, both

internally and externally?

Information

management

6 Since adopting BIM based design what changes have you observed

in the way Information is managed?

Rework 7 Since adopting BIM based design what changes have you

experienced with regard to the type and extent of rework you

perform that is caused by errors and omissions?

Quality 8 Overall How has BIM based design impacted upon the quality of

the production information you deliver?

Overall

Benefits

9 When compared to the 2D CAD, what have you experienced to be

the greatest Short and long term benefit of the BIM based design

on the delivery of quality production information?

Barriers 10 Can you give any examples of barriers that you have experienced

that prevent you from achieving quality production information?

96

Appendix E Example A1 extract from initial manual sorting and coding of data

97

Appendix F: Extract from Thematic Analysis of research data

Interview extract/Code Ref Theme

No. Q1 Production information processes

1 , it makes us do things we should have been doing, easier and it makes it

more transparent, PAS is a measurement tool for what you say you do I1Q1 Rigour and

Transparency

2 you can quantify now what defines a good job it’s not subjective, you have

got a lot of informed data instead of personalised opinion I1Q1 Rigour and

Transparency

3 'before PAS part 2 we said we did it', success depended on the individuals,

PAS demands a rigour, demands projects to be structured and managed in a

way that determines success

I2Q1 Rigour and

Transparency

4 application of PAS demands that designers do what they say they will do,

they have to prove it I2Q1 Rigour and

Transparency

5 BIM tends to not let you cut corners like a CAD sketch drawing does, I4Q1 Rigour and

Transparency

6 when you start to model in 3D it’s very difficult to fudge things you have to

plan them through to be right when they come out the other end I5Q1 Rigour and

Transparency

7 it collects data in a consistent manner that can be analysed, the consistency

in which they approach data is a totally different way they approach

construction information

I1Q1 Upfront Database

investment driving

downstream Value gains

8 so we change one basic model and everything changed, a massive saving for

cost, we have to massively front load the project with information I4Q1 Upfront Database

investment driving

downstream Value gains

9 to wack up a BIM data chunk with a consultant team it takes longer, to get

the efficiencies we want everything has to have data associated with it, I4Q1 Upfront Database

investment driving

downstream Value gains

10 you crop it and spin it can pop and twist it an explode it and pull it apart that

definitely is an upshot and based on the model of being a high enough

quality that allows you to exploit it in that way, if you've got a very basic

model you'll get very basic information out of it,

I3Q1 Upfront Database

investment driving

downstream Value gains

11 that's the benefit, your actually spending more time understanding the real

estate and the infrastructure your trying to put together than making a nice

drawing,

I5Q1 Upfront Database

investment driving

downstream Value gains

12 more skilled people need to be involved in the process I1Q1 User capability and

organisational BIM

Maturity

13 I don't think there is a stark difference between working in 2D and 3D in

terms of the process, you get out of it what you put in, you put rubbish into

the 3D model you'll get rubbish back out of it, you still have to control it and

apply rigour and check everything

I3Q1 User capability and

organisational BIM

Maturity

14 you still have to check on a detail and check it all the way round until you

come back to the beginning, it’s the right thing to do at that time not to

fudge it, it will take you longer, overall the process of fixing things before

you do other things in the big picture it’s an improvement it’s a good thing

I3Q1 User capability and

organisational BIM

Maturity

15 the business actually makes money through lean processes, doing thing

right first time, managing data correctly first time and BIM and the tools and

the management process supports lean processes

I5Q1 User capability and

organisational BIM

Maturity

16 BIM on its own is not going to deliver the savings and the cost analysis and

the improvement of BIM process it has to be connect to lean to do that I5Q1 User capability and

organisational BIM

Maturity

98

Interview extract/Code Ref Theme

17 discipline coordination was something people had to go through , not really

any different, tools and workflows facilitate, the outcomes are the still the

same

I2Q1 Process similarity

Toolset improvements

18 it’s not as if working in 3D magically fixes everything and makes it easier,

you still have to go through the same processes, I3Q1 Process similarity

Toolset improvements

19 there's a risk because you are forced to correct mistakes as you go which

might take you off the critical path I3Q1 Risk and Reward

20 it can be completely automated, a heck of a saving for us, the legal

implications of getting it wrong were massive so it’s a risk mitigation

process for us

I4Q1 Risk and Reward

21 were aware enough that BIM takes slightly more information, you need

more knowledge and information about what you’re doing up front as you've

almost got to build it straight away, that certainly is fed back into the project

team and there certainly aware they've got to work out a lot more things in

advance,

I6Q1 Risk and Reward

22 do you want to schedule out all the doors on 406 flats?... No, that's soul

destroying if somebody gets a door wrong that’s 60 wrong doors, so we can

limit some of our risk with it, in other areas it’s probably increased our risk a

little bit, its put the pressure on us to deliver documents on time, it was

calculated risk,

I7Q1 Risk and Reward

23 the design done by one person has a pretty strong understanding of how this

looks but the problem is translating that into a drawing so that the end user

the client the site actually understands what they've got, and quite often the

drawings are quite complicated in 2D and the site team don't always have

time to look at that and so quite often its left to sit and then suddenly they

need and they realise it’s not quite how they need it, and then make a design

change, but what have found is if you include 3D image on that drawing of

what this is going to look like and how it will function, then we get an

instant reaction and we able to bring forward those changes and be able to

manage those better going forward

I5Q1 Visualisation and

Understanding

24 but in terms of all working on the same model, before we would have had

people working on isolated packages, one thing now they've got the model

so they can see if something's changed but also everyone's conscious that

you have to tell everyone things are changing what's happening so team

members are more aware of changes that the project architect may have

made

I6Q1 Visualisation and

Understanding

25 if we change something then it moves the underlay so we know things have

got to change or we link it through to it, scheduling has been great as it auto

corrects itself,

I6Q1 Information cohesion

and

Integrity/Automation

26 I guess that's the other big change working on the same model together,

that's been good, there's no down side to it, normally we have 3 or 4 people

working on it and the overall project architect and they tend to go and check

what the others are doing.....even the first or second project we did it took

fewer people than it would have done rationally in AutoCAD

I6Q1 Information cohesion

and

Integrity/Automation

99

Interview extract/Code Ref Theme

No. Q2 Design review processes

27 there's a difference between what the technology can do and people

behaviour, BIM gives us the ability to fix things we were never fixing and

were passing downstream to on site and that is something that puts a greater

onus on the designer

I1Q2 Rigour and

Transparency

28 , it is a new way or working, new roles new responsibilities coming out of it,

its growing, I5Q2 Rigour and

Transparency

29 if you do it right BIM can be better, people draw things knowing there's

potentially going to be a clash and will fix it later, people are lazy, switch

back identify a clash in Navis, part of the problem is not the technology its

getting people to work with better processes,

I1Q2 User capability and

organisational BIM

Maturity

30 it has always been incumbent on the designer to ensure that all trades are

coordinated, with the software tools there's far more potential to better

automate the process providing that everyone is working to the same goals

I2Q2 User capability and

organisational BIM

Maturity

31 your able to find more problems and reduce errors in the construction

information in a way that you had always intended to do two dimensionally,

but it was harder because of human error, the human error part is reduced,

it’s not removed but is reduced

I2Q2 User capability and

organisational BIM

Maturity

32 in the future cloud based systems, so everyone is viewing it in that space, I5Q2 User capability and

organisational BIM

Maturity

33 I don’t your mind-set of the process changes it’s just that you have got a

better tool set to do it, a more complete tool set where you’re not relying so

much on judgement, I think there's a risk that it deskills you as a person, you

always need to check the output,

I7Q2 User capability and

organisational BIM

Maturity

34 so far it’s only the structural engineers that are fully engaging on the Revit,

because a lot of the other consultants aren't on Revit, we have to revert to the

lowest common denominator which is a bunch of drawings for them to go

through,

I6Q2 Non-alignment

/Integration/Procurement

issues

35 the model is just use for an ancillary item to aid the process where we can,

the review process is a major benefit, it’s not as good as it could be because

not everybody works in the 3D environment

I3Q2 Non-alignment

/Integration/Procurement

issues

36 we remove humans from the process, you can then make a judgement on

whether that is a clash or not, reduced risk for the client reduced risk for us

and makes our job a heck of a lot easier

I4Q2 Risk and Reward

37 we are doing this because we think it has value not because the client has

asked for it, I don't think we have actually delivered one job yet where the

client has actually demanded it,

I5Q2 Risk and Reward

38 our work processes are remains the same because our interests are remains

the same, it’s just the technology can actually bring that to a much sharper

and clearer image, it can be broadcast more easily to all the interested parties

I5Q2 Visualisation and

Understanding

39 through the visualisation and technology they get a better understanding,

that's got to be massive, they suddenly know what a 12 inch valve and

accessing looks like

I1Q2 Visualisation and

Understanding

40 in 3D you federate the models together and explore what works and what

doesn't and chop sections in various areas and see the structure as it in that

area

I3Q2 Visualisation and

Understanding

41 your level of understanding of how the thing is physically shaped and sits

together is much better, I can give you a 100 2D drawings of a complicated

structure and say that I'm interested in this bit here, you have to scramble

through 6 or 7 drawings to understand exactly what that means, if you go to

a model to that area and understand what is going on in that location, that

understanding actually happens much faster in the 3D world, it’s that speed

that your investing in, you also get a recognition that there's a problem in the

first place

I5Q2 Visualisation and

Understanding

100

Interview extract/Code Ref Theme

42 its more immediate you can look at it straight away and instantly slice

through things for a quick explanation of what's happening I6Q2 Visualisation and

Understanding

43 so I think we've avoided a lot of things, we can go around and have a lock

instantly at what's happening, I suspect that has avoided a lot of problems

that never turn up because what started as little issues are found straight

away and we can get it all to suit

I6Q2 Information cohesion

and

Integrity/Automation

Interview extract/Code Ref Theme

No. Q3 Coordination benefits

44 when people are interacting with the model they fully understand what they

have designed they can completely understand the design because they can

see it, in the past people draw stuff and they physically don't know what

they've drawn,

I4Q3 Rigour and

Transparency

45 in a BIM based workflow that doesn't happen because there's no way you

can trick it, the stairs have to work, your much more interactive with them

you can see them you can see how they work

I4Q4 Rigour and

Transparency

46 there's all sorts of horrible junctions that they tackle because they don't want

to in AutoCAD because it’s difficult to draw the lines and work it out etc.

whereas in Revit it does it itself, where we either realise the horrible mess

you've got or its done it you can see it and your forced to see it, architects

are terrible at doing sections where they know it’s easy and avoiding the

change in direction change in details, we all kind of have those whereas

Revit does it for you it forces you to look at it, you look at it realise it wrong

at a very early stage and actually tweak it so it does all work much early,

I6Q5 Rigour and

Transparency

47 we are into iPad technology and capturing al the inspection and testing

plans on the IPads and the drawings all the commissioning, and this is where

information management comes in because we are linking in with the iPad

and the database in the cloud our information and associated information

with the objects and elements that we have actually constructed and that

gives us traceability, quality matters, it gave us great capability in terms of

putting engineers out on site, engineers used to spend 40 per cent of their

time in offices, the iPad has moved 20pc of the engineers time back out on

site,

I5Q3 Upfront Database

investment driving

downstream Value gains

48 a visual indication that your native design has a clash with another design

and you can then fix that at source, whether you choose to fix that is another

thing, the tools are there to fix it one, we can see the problem do we devote

enough time to fix it?

I1Q3 User capability and

organisational BIM

Maturity

49 if you see a problem and you don't have time to fix it all you've done is pass

that problem down the line, but next time you do it you'll remember it and

you'll probably do it better next time, subsequential learning is embedded in

the way you work in BIM

I1Q3 User capability and

organisational BIM

Maturity

50 certain new roles have occurred, trying to ensure that certain processes that

now have to happen are allocated to certain project individuals, so your

responsible for checking the coordination every few or whatever the BEP

says,

I7Q3 User capability and

organisational BIM

Maturity

51 I’d be pretty confident were be able to get the document set right I think we

have got a very strong pool of staff that enables us to do that, I think the

software allows you to have less experienced members of the team do the

coordination, my only question would be do they have the judgement to

decide what's important and what's not important, you still need good people

evaluating what's going on otherwise mistakes will happen

I7Q3 User capability and

organisational BIM

Maturity

52 the hard and software is only about 20pc of what you are doing its still

about people, it’s about peoples interaction how they work with each other

and the information they provide to each other, and all you doing is speeding

that up so that people can actually work faster

I5Q3 User capability and

organisational BIM

Maturity

53 , because in AutoCAD if you made a change to a door schedule you'd know

you have to go round and do it, whereas Revit you go and change a door

somewhere it goes and deletes all the schedules instantly,

I6Q5 Risk and Reward

101

Interview extract/Code Ref Theme

54 the difference between building information modelling and building

information management, which is this web of information this connectivity,

there aren't many systems at the mo. that are engaging with that and that

requires that everyone be in the game, and that is your central source of

truth, because you want everyone to share in that information

I5Q3 Non-alignment

/Integration/Procurement

issues

55 and there's an awful lot of people who don't work in Revit yet we have still

got to produce that pdf drawing sheet, so we have still got to check that final

product even though that process of getting there can offer us other ways of

doing it,

I6Q5 Non-alignment

/Integration/Procurement

issues

56 I can fly through a model if I fly thorough it enough I know where imp

going and I've never been to site, I instinctively know the way finding

because I know it through the model,

I1Q3 Visualisation and

Understanding

57 I think we've avoided all sorts of issues because we can go ooh that doesn't

work and sort it out, and it just pixels at that time so easier to do Visualisation and

Understanding

Interview extract/Code Ref Theme

No. Q4 Advantages of Simultaneous working

58 allot of it has been done earlier and so you have got the ability to make

changes, because everyone's forced to look at things earlier, changes can be

made so much easier, because it’s still virtual, that very easy to, when it’s on

site it’s a different matter then its outside of CAD

I6Q4 Rigour and

Transparency

59 double whammy of trying to implement BIM and not having the resources

available to make it happen, but once it’s in place, once in place its quite

different

I2Q4 User capability and

organisational BIM

Maturity

60 it is more intensive to begin with so I would begin with that hump because

you need to know so much more about the projects, work out what's its

doing and because you are building it virtually, even just to produce a bunch

of GA's a lot more has got to be done up front it forced you to think about it,

I6Q4 Upfront Database

investment driving

downstream Value gains

61 its right in principle but somewhere along the line you have got to turn it

into a practical application on how you’re going to manage the business

how you are going to manage data, which data is worthy of putting in the

effort you have got to put in to get it for the return you’re going to get for it

I5Q4 Risk and Reward

62 anything that's theorised as being done as a BIM project will be done

properly and we take the risk, be a bit more thoughtful on the project we do

for free, it’s a risk to do it in BIM, but were discovering ways to do this

while minimising our risk,

I4Q4 Risk and Reward

63 the other disciplines need to align themselves I1Q4 Non-alignment

/Integration/Procurement

issues

64 MEP is more calculation based, the quality of the software is not there

mature for MEP, an architect can respond to client changes far quicker than

an MEP engineer

I1Q4 Non-alignment

/Integration/Procurement

issues

65 , I don't think procurements are actually set out in that fashion to allow that

to happen, I3Q4 Non-alignment

/Integration/Procurement

issues

66 I don't think that until procurement methods are geared towards BIM

workflows that it allows that to happen, simultaneous working. It’s a

nonsense the rate if change from its inception to its completion you push me,

their design is predicated on having an architectural design to wrap that

around, so there is a linear flow in every building so trying to get those

curves to overlap will never happen, you see so much reluctance to get

involved early doors because there's so much work that would be abortive

I3Q4 Non-alignment

/Integration/Procurement

issues

67 all the wash about BIM being integrated it doesn't really work with the

process at the moment 25:38 because of the way they are completed and the

way designs are progressed at completely different timescales

I3Q4 Non-alignment

/Integration/Procurement

issues

102

Interview extract/Code Ref Theme

No. Q4 Advantages of Simultaneous working

68 the Mcleamey curve isn't going to happen unless people are getting paid,

M&E have to double handle their work, the architect, Structural Engineer

&QS contractor and client on board, its useful, but because of M&E it

flattens out

I4Q4 Non-alignment

/Integration/Procurement

issues

69 the potential for simultaneous working is not ingrained in the business, it is

within our design office, it may well be within our consultants, as a

construction team or the stakeholders, were not there yet, were not all

delving in and changing things on a live basis

I5Q4 Non-alignment

/Integration/Procurement

issues

70 what we have got to go to is an early contractor involvement where this can

work, because your engaging people from the beginning who are going to

take this right until the end, then you can start thinking about the intensity of

the information and when, and that is also controlled by your level of detail,

and that's controlled by risk

I5Q4 Non-alignment

/Integration/Procurement

issues

Interview extract/Code Ref Theme

No. Q5 Collaborative working

71 internally we have now got rafts of process to control what we do, its

influenced our QMS, there's a lot more that we have to do as a company that

is inbuilt to serve BIM processes, to suit new workflows to suit new RIBA

work stages, that's all come on a long way

I3Q5 Rigour and

Transparency

72 you can’t hide anything by issuing a few sections because they get to see the

whole thing, it’s a lot closer certainly with the engineers, because everything

in there on show,

I6Q5 Rigour and

Transparency

73 I think those all working on the same model is more collaborative because

you have to keep everyone working on the model informed I6Q5 Rigour and

Transparency

74 the quality of our information is absolute, what it does affect is the process,

it will affect how much time and effort we will spend in that process, I’d like

to think that working in 2D or 3D our information would be the same

quality, we still have professional liability no matter what medium you put

that in

I3Q5 User capability and

organisational BIM

Maturity

75 it comes down to human nature something's are just mistakes you can’t

account for that just because it’s in a BIM environment, like I said it like the

quality of what you put in you get out,

I3Q5 User capability and

organisational BIM

Maturity

76 a lot on onus has been put on designers now to do full coordination where

before that was a separate duty, now contractors are trying to push that on

them by default,

I1Q5 Risk and Reward

77 more and more often were working with people we want to be working with,

most company's that we work with a pretty proficient, increasing were in a

position where we can choose who we work with, I think that's key to

success, we can pick who we want to work with, we still occasionally get the

arranged marriage scenario

I3Q5 Risk and Reward

78 we're developing relationships on a number of fronts, one of the more recent

or successful ones is with Laing o roué their explore faculty, for duma, were

picked by them on projects because we can deliver schemes that work with

that system

I3Q5 Risk and Reward

79 for every project we have a facilitated meeting with the project team to work

out what's important to them what do they really need to manage so they can

bring the technology and the skills and focus on a particular areas that are

going to give them good return, it’s like picking the low hanging fruit

I5Q5 Risk and Reward

80 you’re putting an infrastructure together that is actually useful to people, so

that it is easy to use and they get back the information back they need, they

need to understand that I may need to take that time because within the

business I can save that many times over with other people

I5Q5 Risk and Reward

81 there are people on the project at execute level that need to drive it, I1Q5 Non-alignment

/Integration/Procurement

issues

103

Interview extract/Code Ref Theme

No. Q5 Collaborative working

82 if the whole project team isn't working to the same goal and if the whole

project team isn't looking to deliver information. It’s not going to happen, it

didn’t matter too much two dimensionally, but because you need people

working to an equivalent standard to get the clash detection exercises up and

running, without the support form everybody it just wouldn't happen

I2Q5 Non-alignment

/Integration/Procurement

issues

83 , there is more done up front than the traditional process, the architect will

always have to do something first I2Q5 Non-alignment

/Integration/Procurement

issues

84 internally it’s not a problem everyone's wants to engage in the process, I5Q5 Non-alignment

/Integration/Procurement

issues

85 you certainly notice the difference with the Structural engineers, as you

work in a whole different way on the projects, the rest are as they use to be,

and the slight frustration of the 2D plans on screen and then look back at the

Revit model, and while that's how it used to be its slightly frustrating

I6Q5 Non-alignment

/Integration/Procurement

issues

86 they won’t want to do anything until design freeze and that’s too late, on the

couple of jobs I've been involved with, we've been basically fitting in the

M&E to an existing building and that's not how this process is supposed to

work,

I7Q5 Non-alignment

/Integration/Procurement

issues

87 the client can make more informed decision because they understand I1Q5 Visualisation and

Understanding

88 there's a greater concentration of information at point of source, if you

change a dimension it will changes it in a section and elevation, you have

more consistency of approach in change management

I1Q5 Information cohesion

and

Integrity/Automation

Interview extract/Code Ref Theme

No. Q6 Information management

89 as soon as things get tight on timescales or when the pressures on the first

thing that goes out the window is process I3Q6 Rigour and

Transparency

90 if you stick to the process should be fine, but if you start going away from it

just gets in the way of getting things done, mayhem, I'm really interested to

see how it turns out, it’s all put together based on theory, if you can follow

the process you'll be fine

I3Q6 Rigour and

Transparency

91 BS1192 since 2010, the standardisation of information makes everything

allot easier for us, even from a CAD point of view, line weights and drawing

number just makes everything much more easier for us to manage so when

we’re managing information we haven't got to work back through it

I4Q6 Rigour and

Transparency

92 there's pretty good transparency through the IM tools now through thing

like 4projects, but again it’s down to how they are used, on an IM tool I can

find out who was the worse consultant for updating drawings and revisions,

I1Q6 Rigour and

Transparency

93 there is no leeway in that process to vary things like naming conventions

you have to fully comply with naming conventions, you can’t deviate from it

at all, L2 BIM is very different to what it is now,

I2Q6 Rigour and

Transparency

94 externally all the companies we work with are based on 1192 standards, we

have the infrastructure ready for PAS1192, you get something and it works,

it’s just the standardisation of everything

I4Q6 Rigour and

Transparency

95 BIM is not a magic fix, you have to put a significant amount of effort in to

the manage the data and how you assemble it I1Q6 Upfront Database

investment driving

downstream Value gains

96 the quality of that info and the risk built into that information should be

reduced because it has been through a more rigorous coordination process,

derived from a coordinated model in the first place

I2Q6 Risk and Reward

97 it’s not there yet, uncials, riding a crest of wave analogy you have got to

ride with what you have got at the moment or it will break in front of you… I5Q6 Risk and Reward

104

Interview extract/Code Ref Theme

98 when it comes to level 2, for us making that change will probably happen

over night I3Q6 Non-alignment

/Integration/Procurement

issues

99 you can see why its reluctance because it’s an idea it’s not cement

yet...there a lot of stuff going on but nothings joined up or coordinated I3Q6 Non-alignment

/Integration/Procurement

issues

100 we’re finding it very difficult to enforce on projects because the industry just

isn't ready for it, everyone's at different at stages, people won’t pay more,

they won’t pay it even if there's potential savings,

I4Q6 Non-alignment

/Integration/Procurement

issues

101 , there's been no impetus for to do the government bit and the data bit too

heavily yet, and because were new to Revit and there's not push on that bit

we've been getting used to it , so were slowly looking at that bit

I6Q6 Non-alignment

/Integration/Procurement

issues

102 the lean processes that need to come out of it and make those changes

gradually, so to think that BIM has been in for two years to think that were

done it, there's no one that doing it, they may be doing it locally or on a

project level but on a business level there's no one doing it

I5Q6 Non-alignment

/Integration/Procurement

issues

103 when I say no were not doing it it’s for the business yes were doing it on a

project level and there's a big difference, I5Q6 Non-alignment

/Integration/Procurement

issues

104 yes its managing the site a little bit better but as an overall business in terms

of making those small percentage profits that were all involved in its not

going to do, you have got to be able to dip into these systems and take things

for other parts of the business, it’s not a project wise for the business, it can’t

be you need all sorts of tool, but you need to work out the sequence and

what you going to get out of them, and then that is BIM, capturing it as you

see, using it as you need it,

I5Q6 Non-alignment

/Integration/Procurement

issues

105 to get it to the level to where I would want it to be is a 6 year plan, there are

paper based systems that we use to get the information out of it but you have

to mine it and it takes time which is not lean, you've got to have a vision for

how you’re going to get there,

I5Q6 Non-alignment

/Integration/Procurement

issues

106 if you link your specification and schedules to the model you get a

consistency that was never there before I1Q6 Information cohesion

and

Integrity/Automation

105

Interview extract/Code Ref Theme

No. Q7 Rework

107 a far greater awareness of issues, the clients now got the ability to see these

issues, there's more transparency at client level , I1Q7 Rigour and

Transparency

108 the jobs that we have properly adopted BIM on and that we have taken

through site seem to have run more smoothly an seem to have been more

profitable compared to equivalent 2D projects running at the same time

I2Q7 Risk and Reward

109 there’s always that process of looking at what was in the archive drawings

and what's now on the model to make sure someone hasn't nudged it you

have to make sure it as it was when it went out the door last time and there's

time involved in that, for the benefits it brings it brings disbenefits ,

I3Q7 Risk and Reward

110 design were completed in a 2D world and signed off, and we agreed with the

client we would go into a 3D world and just make sure it all works, why?

because we've got time before we arrived on site, that design suddenly got

brought back to detailed design because it didn't work, big fundamental

errors right up at the concept stage of the design that had been lost and were

just taken as true after that, would be cost the client quite a lot of money, in

that instance we didn't get an increased turnover because we are not

managing change, but we shouldn't be in the business of managing change

and issues of that nature, we should be in the business of making our money

through building it right first time

I5Q7 Risk and Reward

111 there's still an element of due diligence, provided you do that, you can never

eliminate the risk totally, but you can reduce it significantly, its more that

someone hasn’t done their due diligence rather than the software performing

better, regardless of whether you draw it in 2D or 3D, if you haven't drawn it

properly it can still go out the door and be wrong unless somebody checks it

I7Q7 Risk and Reward

112 the information passed to site is much more extensive, the work were giving

them is much more thorough because we have modelled every aspect of the

building, every single element of the building has been thought about, we

have to model in a way it which will actually be built, even though were

putting more effort in the front end were saving more going forward by the

fact that we haven't got to do more work when it goes to site

I4Q7 User capability and

organisational BIM

Maturity

113 the model is created and moved from discipline to discipline many times, the

information that has been developed needs to be consistent enough that it

can be used by all these disparate functions, at the moment we can get the

design side working quite well, there an argument over cost in terms of

planning we can do that, construction we can do that see a benefit there, FM

not happening, because the earlier stages are still immature enough, client

doesn't know what he wants,

I2Q7 Non-alignment

/Integration/Procurement

issues

114 for 80 of the up market where's the relevance I3Q7 Non-alignment

/Integration/Procurement

issues

115 coordination and better understanding and resolution of errors during the

design stage, it gives you a more determined outcome by the time you get to

site

I2Q7 Visualisation and

Understanding

116 actually that 3D-ness of it all has been quite amazing because actually if all

the big bits are in places then the small bit are just trickle down and happen

to be in place, so of the problems on the project might be more how do you

do this in Revit, at this stage in the project where I am you expect more

problems where at the back of your head your always expecting someone to

point out something that doesn't quite work because you haven't all worked

it out but I feel more confident in Revit that that won’t occur, because what

you see on the screen in 3D is now here, I think you just see more of it and

so there are fewer problems

I6Q5 Visualisation and

Understanding

117 the one thing that you can say about working in a BIM based environment is

that if something is wrong it’s going to be consistently wrong on all your

drawings

I3Q7 Information cohesion

and Integrity

106

Interview extract/Code Ref Theme

No. Q8 Quality

118 there will be increased standardisation of product, your no longer passing a

problem down the line, transparency is a huge thing, I1Q8 Rigour and

Transparency

119 it forces more rigour and so the information quality will be improved,

whether the resources are available to achieve deliverables, it’s the same in

2D, your still going to have the human intervention, you can still press the

wrong buttons and parameters and you’re going to fail somewhere

I2Q8 Rigour and

Transparency

120 BIM doesn't let you cheat, you have to think about it a lot more, everything

you put in your thinking about your interrogating, from the technicians point

of view, they're looking at it as physical element, whereas in CAD because

it’s not there your thinking about how it works, the quality of the info, if

you've cheated and the data you've used is rubbish they can’t use it

I4Q8 Rigour and

Transparency

121 , its only now we can justify our design responses rather than in our head, I4Q8 Rigour and

Transparency

122 we aim for the same level of production information but we have got a

different tool to get there so I think people are more ofay with the tool then

we can begin to reflect more on what you can

I6Q8 User capability and

organisational BIM

Maturity

123 it’s based on everything being done properly, it does improve the process

there's more work required to do it, 32 details at 1:5 in 6 hours, back in CAD

that would have taken us a lot longer, but that was all because we had set

this thing up correctly so it made it that quick to it, it comes back to the

quality of the model so you can just churn stuff out that right, but if you

have a bad model it’s a nightmare,

I3Q8 Upfront Database

investment driving

downstream Value gains

124 some practices have really got it right and produce a far better product, good

people will take more advantage of the tools than other, good application of

BIM tools will make significant differentiator's of quality of performance of

product, if people correctly apply the tools the gap between skills and

quality will be significant, smarter people get better outputs

I1Q8 Risk and Reward

125 at the moment its being left to the designers and contractors to sort out

because the client just doesn't understand I2Q8 Non-alignment

/Integration/Procurement

issues

126 in some cases the QS is dictating the way we model so they can cost it,

helping the consultants to help the clients and get a better product, clients at

the moment don't care, safira similar to IES, we can optimise and validate

design reduce costs by 10k per year, in the end it will become added value,

coming out of the BIM workflow

I4Q8 Non-alignment

/Integration/Procurement

issues

127 if it’s come from a 3D model and your seeing that information combination

of drawings the quality and the understanding that that gives immediately to

the recipient is there and even going as far as the client

I5Q8 Visualisation and

Understanding

128 there was a major bit of temporary work to be put it that was on their critical

path and they stipulated all the requirements and everything looked that and

it wasn't until we put the 3D model and the rebar 3D model and the

scheduling that showed a 4d visualisation program that showed how it

would be put it that they realised within 20minutes that they had got a real

issue because this isn't a 5 minute job because we will need to the time we

say we will need to do it, it allowed them to go away and rethink about their

requirements for that structure and rethink how we should phase that work in

order to meet everything else that's going on in terms of the construction, in

this case its cross rail, it was important to them, would they have got that

understanding without a 3D model, without the 3D re bar imagery and

visualisations, that would not have come about, we would have all carried on

quite blindly building what we said we were going to build without

understanding the consequences,

I5Q8 Visualisation and

Understanding

129 it’s an improvement on speed, going back to the basic principles of Revit

drawing a plan and it generates a section, its generating multiple views it

generating schedules, you don't have the issue of something being in excel

and something being in CAD and somehow that coming together on a pdf,

the scheduling thing in Revit is a massive improvement in terms of quality

and accuracy, there's a still an element of management in it but essentially

being able to hit a button,

I3Q8 Information cohesion

and Integrity

107

Interview extract/Code Ref Theme

No. Q9 Overall benefits

130 Under Pas 2D will not exist. Pas forces you to draw in 3D. We live in a 3D

world, people understand 3D better than 2D. Major benefit is that 2D will

become extinct. 2D is uncoordinated data. 3D is coordinated data.

I1Q9 Rigour and

Transparency

131 2004 we started looking at it from 2008 all projects were in Revit like it or

not, it’s a long process it’s like 10 years to where we are now we've had to

establish protocols and guidelines for people to follow in order to maintain

that quality in the work, to try and make sure that everyone does something

that looks consistent,

I3Q9 Rigour and

Transparency

132 BIM is seen as the goal and it’s not, BIM is the means of facilitating better

project outcomes, not the fact that BIM is on the project, what we’re talking

is about architecture, places and spaces for people, the quality of the built

form

I2Q9 User capability and

organisational BIM

Maturity

133 we are clear that working in BIM will provide better outcomes, will allow us

to determine more coordinated, more rigorous, better tested ,better

prototyped buildings, but it’s the building itself that actually matters, so we

can give the client a better end product, we can show other advantages in

terms of programme and cost management, through simple visualisations

and understanding of what we have created form them, it’s a facilitator it’s

not the outcome,

I2Q9 User capability and

organisational BIM

Maturity

134 Should be better concluded better understood, is facilitated by BIM but

BIM is not the be all and end all, to be honest it was all kind of happening in

2D it was just much harder to more expensive and it took longer,

I2Q9 User capability and

organisational BIM

Maturity

135 you could do a project using 2D lines and in Revit it will still be 30 pc more

efficient than doing it in AutoCAD I3Q9 Upfront Database

investment driving

downstream Value gains

136 working in BIM environment it is quicker, you do get more quality and

control out of what is being produced it does makes us more efficient,

standardised libraries, so instead of using concept stuff you can pull in stuff

that potentially is ready to go for construction that contains all the

information they need and want that's got backed with specs and stuff like

that

I3Q9 Upfront Database

investment driving

downstream Value gains

137 the ability to schedule information quickly and accurately, normally it would

take a week together I did it in an a afternoon, additional requests for

information can be dealt with quickly

I7Q9 Upfront Database

investment driving

downstream Value gains

138 the more rigorous approach demanded by the BIM methodology will help to

reduce risk I2Q9 Risk and Reward

139 cost reduction to the practice therefore better profit margins because we

haven't had to put as many resources and time on a project, the long term;

not closing off the publicly procured market, we work massively with

education projects, without BIM this practice wouldn't exist

I4Q9 Risk and Reward

140 this practice has grown because of BIM it has allowed us the thrive during

the recession, private sector is getting wind of BIM, 2008 a few 1m jobs and

series of smaller jobs, were now working on 5m - 60m, but BIM has been

very much inherent in the process of moving up to bigger projects, bigger

project sand practice growth, 2008 barn conversions now 5m -60m

I4Q9 Risk and Reward

141 BIM strategy limited, asked by surrounding consultants, consulting arm that

drives BIM, content creation, manufacturers, diversified into a BIM

consultancy, a collection of SME's, inundated with requests for help, the

ability to help them

I4Q9 Risk and Reward

142 that's why we want to do it as a business and why the governments are

saying they want it for their own FM management so were not doing this

because the government wants it, were doing it because we perceive a

business need for it which is a fundamental difference

I5Q9 Risk and Reward

108

Interview extract/Code Ref Theme

143 , as people get it into their DNA and understand how to get the outputs from

the software....so it will naturally grow, it’s not revolution, you can’t force

this on people, you’ve got to grow this in people and understand the need

and capability they get out of it

I5Q9 Risk and Reward

144 If you can make better quality information with no mistakes that helps you,

also it speeds up the process, its more accurate therefore less risk I7Q7 Risk and Reward

145 were are all aware that's there’s all sorts of advantages of other stuff we can

do, but there's so much out there but we need to control which bits were

fully engage with because to try and to the whole thing at the same time

would just blow our collective minds, first we are focusing on how does this

program work and then I suspect we will look at what other opportunities

does it afford us

I6Q9 Risk and Reward

146 .fewer staff is going to be the major advantage for us because that's more

profit or less loss I6Q9 Risk and Reward

147 we can do it dead easy, but getting someone to know what they are doing

with it at the other end is a completely different ball game all together, it’s

an industry of experts but no doers, it’s all based around theory, none of it

applies, people to start doing rather than saying, we've spent so long as a

practice to 3D integration, with so much resistance, I've got no doubt all of

that aspiration is where we should be in terms of how to build buildings,

getting that streamlined, it’s so inefficient I'm whole heartedly behind

getting there I just wish we could do it tomorrow, but the reality is the

uptake and the education and the intelligence of the people why should be

asking for it don't want it

I3Q9 Non-alignment

/Integration/Procurement

issues

148 the issues are how quickly you can bring something like this out, it is

difficult new technology, which will become commonplace in time, I5Q9 Non-alignment

/Integration/Procurement

issues

149 we may have a programme which is 6 sheets of A0 paper, there's lots of bars

on it, how long is it going to take you to understand that program, but if you

link that program to all the object in the model and you put in with it all the

cranage and the real estate, you can translate to anyone in the room within 3

minutes exactly what that program is about and how it is structured,

I5Q9 Visualisation and

Understanding

150 it is about providing an easy source of information that can be disseminated

and understood very very quickly, and BIM is about doing away with the

understanding - talking about the need, what do we need to do about this

project in order to get it to work properly and so the understanding about the

project and its intricacies and issues can be actually delivered very quickly

and you find with minutes people are sleeves up they understand what the

issues are they understand what the problems are and how were going to

resolve it, and that's where the power will come in for us

I5Q9 Visualisation and

Understanding

109

Interview extract/Code Ref Theme

No. Q10 Barriers

151 skills barrier, the base level education of the practitioner will be

significantly lower, BIM takes the rule book of 40 years and chucks it

away,

I1Q10 User capability and

organisational BIM

Maturity

152 nothing really prevents us, that sort of information has to exist regardless,

there's nothing that stops us doing our job we still work the way we work,

if a contractors got zero interest in BIM, well still work in BIM and they'll

get their drawings at the end of it,

I3Q10 User capability and

organisational BIM

Maturity

153 limitations on the number of people we have got trained up, I7Q10 User capability and

organisational BIM

Maturity

154 training of staff, a cultural change, staff understanding the benefits of

change, to get the staff to want to use the process, changing the companies

ethos, taking a very skilled guy to being an infant again, found it very

hard, you’re not producing drawings your producing model, once the

model is done the drawings appear, unlike CAD once you've started

drawing all the drawings appear, you don't get a set of drawings until the

model finished,

I4Q10 User capability and

organisational BIM

Maturity

155 training and understanding in the technology, the processes and what

they're trying to get out of it, and that manifests in 2 ways one is they are

frightened of it, it’s a black box, they don't want to touch it, that can be

seen along our supply chain, in our clients sometimes and indeed

internally, so that takes time you need the realisation you need the training

and coaching in order to be able to do that, I see that as purely a time

based process,

I5Q10 User capability and

organisational BIM

Maturity

156 but data integrated into the model, they're adopting our processes as they

can see how quickly we can do it, MCC library has been a big success and

they have changed the way they operate because of it

I3Q10 Risk and Reward

157 interoperability isn't uniform, it just doesn’t work, data attached to objects,

cost of software, hardware and training, moving 2D to BIM costs about

12k,

I2Q10 Risk and Reward

158 I think on the next job I think they be a bit more savvy, they'd ask us for

quantities, it’s incredible really the benefits really, .....no any practice that

wants to do well will not do well without BIM, it’s a no brainer, debate

with subcontractor and supply chain, everyone tends to have a light bulb

moment, and will never look back,

I3Q10 Risk and Reward

159 you explain to them that it’s a party and everyone has got to come to it for

it to work, and of one person doesn't its level 2 its not BIM it’s just

working in a slightly different way, it probably benefits us more e than it

does you,

I3Q10 Non-alignment

/Integration/Procurement

issues

160 its limited by people that aren't working on it, and M&E when they are

working on it will be far more useful we are limited a bit by them at the

moment, all the clashes with structural just don't happen but there's still the

potential with M&E

I6Q10 Non-alignment

/Integration/Procurement

issues