beach and inlet projects update · – provide shore protection for residential structures,...
TRANSCRIPT
• Project Cross-Section
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
14
16
18
20
-50 0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
Elev
atio
n (
ft N
AV
D8
8)
Distance to Baseline (ft)
Station 220+00
220+00 (Post-Matthew) Berm Only-Mid (75ft) MHW
Post-Matthew
ProfileBeach Fill
Template
Berm Only
38.4 cy/ft
Ocean
Mean High Water
Sta 220+00
75 ft
Pre-
Project
MHW
Post-
Project
MHW
85 ft
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
14
16
18
20
-50 0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
Elev
atio
n (
ft N
AV
D8
8)
Distance to Baseline (ft)
Station 220+00
220+00 (Post-Matthew) Berm Only-Mid (75ft) MHW
Post-Matthew
ProfileBeach Fill
Template
Berm
~40-55 cy/ft
Ocean
Mean High Water
Sta 220+00
120 ft
Pre-
Project
MHW
Post-
Project
MHW
110 ft
USACE “Delta” Project
• Original Project Plan
– USACE plan showed a ~120-130 ft berm from Town line to SE 63rd
street
– Base project is from Town line to SE 77th (4,000’) = 163,345 CY
shown on plans
– Delta project is from SE 77th to SE 58th (6,000’) = 251,526 CY
– Both have ~ 40-55 cy/ft placement rate
– Unit rate for “Delta” work = $11.93/cy
– Town has allotted up to $3 million for this project
– Project was completed in summer
– Received pre- and post-project surveys in December
USACE “Delta” Project
• Project Results
– USACE showed a ~120-130 ft berm from Town line to SE 63rd street –
project was actually constructed to SE 58th street as originally
planned and with a 150 ft berm
– Base project is from Town line to SE 77th (4,000’) = 163,345 CY shown
on plans – 246,245 CY placed
– Delta project is from SE 77th to SE 58th (6,000’) = 251,526 CY shown on
plans – 394,010 CY placed
– Unit rate for “Delta” work = $11.93/cy - $7.61/CY actual
– Total volume placed from Town line to SE 58th street =
640,255 cy
USACE “Delta” Project
Hot Spot Shoreline Change and Dune Escarpment
Feb 2018
Jun 2018
Feb 2018
Jun 2018
MHW
Mar 2015 (BD)
Mar 2015 (AD)
Structure
Lockwoods Folly Inlet Projects - SDI-5 Permit
• O’Brien and Gere Have Been Working to Get This
Permit for the Town
• Allows Town to complete projects like the USACE to
currently permitted widths and depths for just the inlet itself
• Timeline for approval is now late January
Lockwoods Folly Inlet Projects - AIWW Crossing Project
• USACE Released a Plan Set In Early Fall That Showed
Placing 88,000 CY of Material on West End Of Oak
Island
• Placement on Oak Island due to lower number of easements
required
• Moved western edge of placement area further east
• Contract has been awarded and USACE is awaiting final schedule
before determining if Town can pay for additional material to be
dredged out of bend widener and placed (bid showed $7.50/cy)
• Town of Holden Beach has requested as well so meeting will take
place to discuss options if schedule allows for additional material to
be dredged
• Special meeting may need to be called for Town to approve
additional monies if additional material can be dredged/placed
Lockwoods Folly Projects – Nearshore Placement
• Town Has Asked that Next Project Be Placed Near
West End Hotspot – Currently Estimated ~30,000 CY -
$95,000 Town Share
• Channel to be dredged to -10’ deep and 150’ wide
• Total cost = $676,000 = 30 days of dredging
• Most of funding from State Shallow Draft Fund
• Material will be placed in nearshore area near historical
hotspot
• Will also complete additional survey monitoring in future to
track offshore feature and hotspot behavior
• USACE Is Current Showing Limited Availability for
Special Purpose Hopper Dredges Next Year
• Next few projects will likely be completed with sidecaster
dredge at Federal expense
• Town and County has reminded USACE that local funds
were provided contingent on beneficial placement of the
material in the nearshore
Lockwoods Folly Projects – Nearshore Placement
Dune Monitoring Project
• Bi-Weekly Monitoring May 15 – August 31, 2018
– Color, Temperature and Grain Size Monitoring
Dune Monitoring Project- Temperature Results
Average Max Temperature
- Dune Stations: 89.9 F
- Control Stations: 88.0 F
Average Temperature
- Dune Stations: 84.0 F
- Control Stations: 83.0 F
• Measurements set up to record hourly
• Temperature that produces 50% of each gender is 84.6 f
• Gender determined in middle third of incubation
Average Min Temperature
- Dune Stations: 74.1 F
- Control Stations: 74.1 F
Dune Monitoring Project - Color Results
• Color improved when contractor changed where
borrowing material from in pit
Caswell Beach 5th PL West 54th PL West 51st PL W 42nd PL W 23rd PL W 13th PL W 3rd PL E 11th PL E 37th PL E 46th ST SE 55th ST SEWeather
5/14/2018 7/1 7/1 7/1 3/4 4/3 3/4 4/3 4/3 5/1 3/6 3/6 3/6 Sunny
5/21/2018 7/1 7/1 7/2 5/1 4/1 4/1 4/2 5/1 4/1 3/4 4/3 4/2 Sunny
6/5/2018 7/1 7/1 7/1 4/1 5/2 3/3 5/2 5/1 4/1 3/4 3/3 4/4 Sunny
6/21/2018 7/1 6/2 6/1 4/2 4/1 4/2 3/2 4/2 4/2 4/4 3/4 4/3 Sunny
7/3/2018 7/1 8/1 7/1 4/1 5/1 5/2 4/2 5/1 6/1 6/1 3/3 3/4 Sunny
7/20/2018 7/1 7/1 7/1 4/1 5/1 3/4 4/3 5/2 4/1 3/6 4/4 3/4 Wet Sand
8/9/2018 7/1 5/1 7/1 5/1 5/1 4/1 4/1 4/1 5/1 4/2 4/3 4/2 Sunny
8/24/2018 7/1 7/1 6/1 4/2 4/2 4/2 4/3 4/3 4/2 4/4 4/3 5/2 Sunny
9/11/2018 7/1 7/1 7/1 7/1 5/1 5/2 4/2 4/2 5/1 4/4 3/4 5/2 Sunny
4/4
CONTROL STATIONS OBSERVATION STATIONS
29th PL E
3/4
Date
3/3
4/4
4/1
3/3
4/3
4/4
4/3
• Final report was submitted to agencies October 1, 2018 with
no comments received
• Temperatures recorded in dune stations were slightly warmer
(approximately 1 degree avg) than control stations
• Most dune stations were installed on leeward side of dune
crest which would be expected to be warmer
• Munsell color values were lower for non-nourished areas –
color improved when contractor moved
• Sediment grain size is compatible
• All nests laid in the dune restoration project area were
relocated this year (11 of 51 nests laid – 46 false crawls with
17 in dune restoration area)
Dune Monitoring Project – Overall Results
• Completed just before Hurricane Florence arrived in
early September
• Survey consists of:
– Beach profiles
– Eastern Channel
– Lockwoods Folly Inlet
Annual Monitoring Survey (2017-2018)
• Lockwoods Folly Inlet Results
– Some movement of inlet throat to east
– Some deepening/straightening of inlet over bar
Annual Monitoring Survey (2017-2018)
• Beach Profile Shoreline and Volume Change Results
• After initial meeting with FEMA, appears that Town may
qualify for emergency dune restoration project
• Will hopefully know something this Spring
Post-Florence Monitoring Survey
• Eastern Channel Results
Post-Florence Monitoring Survey
Reach 1 Reach 2 Reach 3 Total Reach 4 Reach 5 Total
Sep 2018 - Oct 2018 237 454 1,230 1,921 532 1,650 2,182 4,103
Template - Oct 2018 88,883 4,318 15,692 108,894 128 217 345 109,238
Date Range
Shoaled Volume (cy)
Beach Compatible Non Beach Compatible Combined
Total
• Lockwoods Folly Inlet Results
– Some minor shoaling within inlet over outer bar
– 0-2’ where shoaling occurred
September 2018 October 2018
Post-Florence Monitoring Survey
• Initial Project Budget for Volume of 364,000 cy
– FEMA authorization of $ 6,026,365 (75% of Cost)
• State/Town expected contribution of $ 2,008,788
• Total project expected cost = $ 8,035,153
• Additional Town Funds (Possible)
– Contribute $5 – 7 million: 435,000 – 609,000 cy
• Total potential project volume: 750,000 -1,000,000 cy
• May also incorporate Post-Florence project volume
depending on FEMA approval and reimbursement timeline
FEMA Turtle Habitat Restoration Project
FEMA Turtle Habitat Restoration Project
• Turtle Habitat Restoration ONLY
– Turtle Habitat: 20 ft wide dune at 10 ft NAVD88 with 70 ft berm at 7 ft NAVD88
• 14,000 ft (Sta. 300+00 – 430+00)
• Template Volume Required: 470,000 cy
• Turtle Habitat Restoration with Additional Town Volume
– Alternative A: 20 ft wide dune at 15 ft NAVD88 with 50 ft berm at 7 ft NAVD88
• 18,000 ft (Sta. 300+00 – 470+00)
• Template Volume Required: 1,408,000 cy
– Alternative B: 20 ft wide dune at 12 ft NAVD88 with 50 ft berm at 7 ft NAVD88
• 27,000 ft (Sta. 300+00 – 560+00)
• Template Volume Required: 1,404,000 cy
FEMA Turtle Habitat Restoration Project
Offshore Site #1• Preliminary volume
estimate in permitted central reach borrow area: 400,000 – 500,000 cy
• Distance from project: maximum 5 mi
• Hopper dredge project
• Field investigations: Jan/Feb 19
– Cultural Resource Survey:
Magnetometer and Side-
Scan (Geodynamics and
Tidewater Atlantic Research)
– Central Reach Vibracoring
(American Vibracore
Services)
• Proposed Fee and Schedule
• Proposed Schedule – 16 Months – Finalize Construction by
May 2020
– Field investigations – next 3 months
– Preliminary engineering and permitting – next 3-9 months
– Final design and bidding – next 9-12 months
– Project construction – next 12-16 months
FEMA Turtle Habitat Restoration Project
• Purpose and Need
– To Establish and Implement a Comprehensive, Long-Term, Non-
Federal Beach and Inlet Management Program that will Restore
and Maintain the Oceanfront Shoreline Of Oak Island.
– Provide Shore Protection for Residential Structures,
Infrastructure, and Recreational Assets; and Preserve the Local
Tourism-Based Economy.
– Consolidate the Shore Protection Planning and Management
Activities of the Town Under a Unified, Regional Beach and Inlet
Management Program.
Overview of Master Plan
• Verify Sediment Need for Initial Project and Over Next
50 Years
– (2-3 Mcy for Initial Project / 1 Mcy Every 6 Years = 10-15 Mcy –
Preliminary Estimate – No Storms)
– USACE Delta and FEMA Turtle Habitat Project Can Hopefully
Reduce Volume Need
– May Need to Build In Phases
– Modeling to Refine Above Estimates Currently Ongoing
Overview of Master Plan
• Field Investigations
– Geotechnical vibracoring
for sediment
compatibility
• November 2018
vibracores Eastern
Channel, LFI, AIWW
bend widener
• Jan-Mar 2019 native
sampling and vibracoring
upland sites
• Additional offshore work
planned for January-
March central reach
• Other offshore areas and
Frying Pan Shoals to be
completed later - BOEM
Overview of Master Plan
Lockwoods Folly Inlet
Management Plan
• Analytical Analysis
– Digitize inlet throat and shoreline
locations
– Look for patterns to determine “safe
corridor”
– Cultural resources are a major
constraint
• Modeling
– Field velocity studies of Lockwoods
Folly Inlet for models – late Jan/early
February
– Test options to verify analytical results
Overview of Master Plan
• USACE “Delta” Project - Completed
• Lockwoods Folly Inlet Initatives
– SDI-5 Permit – Complete By February 2019
– AIWW Crossing with Beach Placement – Complete by May 2019
– Nearshore Placement – Complete Last Half of 2019
• Dune Monitoring Report – Complete
• Annual and Post-Florence Surveys
– Annual Survey - Completed
– Post-Florence Survey – Complete by February 2019
• FEMA Request for Post-Florence Reimbursement
– Discussions with FEMA – Complete by Spring 2019
Overview Summary
• FEMA Turtle Habitat Project
– Field Investigations - Complete by March 2019
– Engineering and Permitting Submittals - Complete by May 2019
– Receive Permits and Finalize Construction Documents –
Complete by October 2019
– Bid Project – November 2019
– Project Construction – January – May 2020
• Master Plan
– Field Investigations – Ongoing – Discussions with BOEM and
Others Concerning Frying Pan Shoals
– Estimate of Engineered Beach Volume Need – Complete by
Spring/Summer 2019
– Environmental Studies and Documentation - Ongoing
Overview Summary