beating the queue – connection policies for a liberalised ... · 3. grid capacity is getting...

23
Beating the queue – connection policies for a liberalised market Dan Harris June 2008 Tel: +44-20-7406-1700 Fax: +44-20-7406-1702 [email protected]

Upload: others

Post on 20-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

Beating the queue – connection policies for a liberalised market

Dan HarrisJune 2008

Tel: +44-20-7406-1700Fax: +44-20-7406-1702

[email protected]

jenna curto
Text Box
Copyright © 2008 The Brattle Group Ltd
Page 2: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

2

Contents

• Current problems with connection policy.

• The Policy Tools:

• Facilitate market transactions;

• Generator payments;

• TSO Decisions.

• Conclusions.

Page 3: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

3

Grid capacity is getting scarce

• Several countries are experiencing problems with generator connection policy. Typical problems are:

• Many developers want to connect in the same place, creating a connection queue.

• Current connection policy does not distinguish between ‘real’ and ‘fantasy’projects – the latter can hold up the former.

• Generators can ‘play games’, deliberately holding up rival projects in the connection queue.

• Grids make investments for generation projects which never happen.

• The focus of this talk is on connection policies that can help solve these problems.

Page 4: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

4

Recent problems – the UK

• In the UK, National Grid noted that “reforms and government incentives to encourage renewable generation has led to a significant queue for transmission capacity clustered in specific areas”

• “there may be little incentive for … [u]sers to fully consider the viability of projects before Bilateral Agreement signature. This could lead to unviable projects being accepted and included in the background against which transmission reinforcements are planned”.

Page 5: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

5

Recent problems – the US

• In a December 2007 speakers at a Federal Energy Regulatory Commission conference described the system for interconnecting new generation resources to the power grid as ‘broken’.

• The existing system relies on a:

• ‘first-in, first-out’ approach that can leave viable projects stuck in line behind projects of questionable viability.

• heavy financial commitment of the first developer at a site to pay for the transmission upgrades serving that site. This creates reluctance and delays.

Page 6: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

6

The Netherlands

• TenneT in the Netherlands has experienced a large volume of connection requests in Maasvlakte and Eemshaven.

• There is about 10,000 MW of new generation connection planned in NL from now until 2013.

• TenneT began investments of €400 mln to increase capacity, but was outpaced by requests.

• TenneT will connect new generators on an interruptible basis until re-enforcements are complete.

Maasvlakte

Eemshaven

Page 7: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

7

Contents

• Current problems with connection policy.

• The Policy Tools:

• Facilitate market transactions;

• Generator payments;

• TSO Decisions.

• Conclusions.

Page 8: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

8

Three policy ‘tools’

Facilitate marketsThere are existing market

mechanisms – try and make them work better

Generator PaymentsGive generators better ‘signals’

TSO DecisionsPerhaps the TSO’s connection

policy can be improved

Page 9: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

9

Options Considered

Deep charges

Bring back G charges

Up-front payments

Auction available capacity

Tradable rightsForced site auctionsPublish more information

Facilitate Market

Generator Payments

Just say YES: all firm

Advanced planning/building

Start saying NOTSO Decisions

Say YES to small units

Policy options Considered

Page 10: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

10

• International Precedent: UK regulator obtained commitment from dominant generators.

• Policy Goal: Stop the strategic behaviour of hoarding ‘retired’ sites and their grid connections.

• Assessment:

If there is market power, incumbents would simply out-bid new entrants.

‘Dead parrot’ problem – owners could claim the plant is not retired, it’s just mothballed.

• Recommendation: Probably ineffective. Better to leave site sales to ex post regulation by the competition authorities.

Facilitate Market Forced Site Auctions

Page 11: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

11

Facilitate Market Publish More Information

• International Precedent: Some US TSOs publishes substantial information on the connection queue and available capacity. Elia publishes data on available capacity.

• Policy Goal: Improve transparency without violating confidentiality.

• Assessment:

Available capacity– publish existing and forecast, with a map of network.

Length of queue– indicate position, estimated time, likelihood of getting capacity.

• Recommendation: Yes. TSO can keep data ‘live’ on the web.

Page 12: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

12

Contents

• Current problems with connection policy.

• The Policy Tools:

• Facilitate market transactions;

• Generator payments;

• TSO Decisions.

• Conclusions.

Page 13: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

13

Generator Payments Up-front Payments

• International Precedent: US requires generators to “lend” TSO the “deep charges”, subject to refund. UK cancellation payments exceed the connection costs.

• Policy Goal: Deter artificial requests for connection capacity.

• Assessment:

Add milestones– necessary for effective cancellation policy.

Deter frivolous applications– also deter requests for more capacity than needed at a site.

• Recommendation: Yes. Focus on cancellation payments.

Page 14: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

14

Contents

• Current problems with connection policy.

• The Policy Tools:

• Facilitate market transactions;

• Generator payments;

• TSO Decisions.

• Conclusions.

Page 15: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

15

TSO Decisions Connect all ‘Small’ Units

• International Precedent: UK has special rules for generators < 100 MW.

• Policy Goal: stop a “first-come” large unit from blocking e.g. smaller renewables.

• Assessment:

Doesn’t solve problems (see next slide)

• Recommendation: No.

Page 16: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

16

TSO Decisions Connect all ‘Small’ Units

Doesn’t solve problems

• Distortions: UK now has a lot of 99.9 MW units.

• Can’t help small units without harming big one.

• Can’t offer more than one run-back without creating allocation problems. Note: first in “queue” could always reduce project size.

MW

A B A B

Renewables

Runback grows

1 2 31 2 3 1 2 3

Page 17: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

17

TSO Decisions Advanced Planning/Building

• International Precedent: The US energy regulator has approved advanced building for renewables in California.

• Policy Goal: Improve the investment climate reducing network congestion.

• Assessment:Reduce lead time

Efficient for renewables

TSO risk

• Recommendation: Allowing TSOs to recover the costs of advanced permitting would strike a good balance between speeding up new build and avoiding the risk of stranded investments.

Page 18: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

18

TSO Decisions Start Saying NO to new connections

• International Precedent: Central planning in many countries.

• Policy Goal: Optimize use of transmission network.

• Assessment:

Reject costly locations– can work if the TSO is neutral.

• Recommendation:

• Useful supplement to “advanced plan/build”, to reduce TSO risk.

• However, saying NO seems harsh relative to a “deep” connection offer.

• Perhaps offer “deep” in congested area as long as “shallow” available elsewhere.

Page 19: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

19

TSO Decisions Identify most expensive connections

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Substations numbered in order of increasing costs

Dee

p re

info

rcem

ent c

osts

, €/k

W

Deep connection costs applied to these substations

Page 20: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

20

Contents

• Current problems with connection policy.

• The Policy Tools:

• Facilitate market transactions;

• Generator payments;

• TSO Decisions.

• Conclusions.

Page 21: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

21

Summary

Deep chargesMarket too smallHarsh on renewables

Bring back G chargesLocational signals possibleInternational distortions

Up-front payments Add milestonesDeter frivolous applications

Auction available capacityMarket power abuse

Tradable rightsEfficient retirementBut with limits

Forced site auctionsThreat of illiquidityEasily evaded

Publish more infoAvailable capacityLength of queue

Facilitate Market

Generator Payments

Just say YES: all firmRe-dispatch nightmareMarket power problems

Advanced plan/buildReduce lead timeEfficient for renewablesTSO risk

Start saying NOReject costly locations

TSO Decisions

Say YES to small unitsDoesn’t solve problems

Page 22: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

22

Recommended policies

Up-front payments Add milestonesDeter frivolous applications

Tradable rightsEfficient retirementBut with limits

Publish more infoAvailable capacityLength of queue

Facilitate Market

Generator Payments

Advanced plan/buildReduce lead timeEfficient for renewablesFor permits only

Start saying NOPay for costly locations

TSO Decisions

Page 23: Beating the queue – connection policies for a liberalised ... · 3. Grid capacity is getting scarce • Several countries are experiencing problems with generator connection policy

23

Conclusions

• Many TSOs are experiencing high levels of connection request andincreasingly constrained grid capacity.

• There is no ‘silver bullet’, but a mixture of policies could greatly help reduce the current problems.

• Publishing more information;

• Use of milestones and payments to deter ‘phantom’ plants;

• Make developers pay deep costs for very costly locations;

• Permit in advance.