being developed byenvironmentclearance.nic.in/writereaddata/formb/tor/pfr/...conceptual plan -...
TRANSCRIPT
Conceptual Plan For
Proposed Multistory Building , Row Housing & Commercial Spaces
At Gram- Aurangabad Khalsa , Tehsil & Dist. - Lucknow
Total Plot Area = 50791.0 m2 Total Built Up Area = 81369.62 m2
Schedule 8(a); Cat.B2
Being Developed By
Environmental Consultant
Sawen Consultancy Services Pvt. Ltd. 417 A & B, Sahara Shopping Center,
Faizabad road, Lucknow-226016 QCI-NABET Accreditation S.No.123 (Dec’ 16) Telefax: 522-2341312; Mobile: 7379444471-73
Email: [email protected] Website: www.sawenconsultancyservices.com
Lucknow Nagar Nigam
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 2
LIST OF CONTENTS
Chapter
No.
List of Chapters Page No.
Executive Summary 4-5
1 Introduction 6-11
2 Project Description 12-18
3 Site Analysis 19-24
4 Project Planning 25-27
5 Proposed Infrastructure 28-29
6 Present Environmental Scenario 30
7 Environment Management Plan 31-42
8 Emergency Preparedness Plan 43-46
9 Analysis Of Proposal (Final Recommendations) 47-48
10 Disclosure Of Consultant 49-52
LIST OF FIGURES
Figure
No.
List of Figures Page No.
1 Construction work process flow chart 14
2 Water Balance Diagram 32
3 Process Flow For Sewage Treatment Plant 33
4 Schematic Of Sewage Treatment Plant 34
5 Rain Water Harvesting 36
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 3
LIST OF TABLES
Table No. List of Tables Page No.
1 Capital expenditure 13
2 Recurring expenditure 13
3 Khasra Details 25
4 Land uses at project site 25-26
5 Plotted Population Break Up 26
6 Parking Details 28
7 Water Use Calculations 31
8 Quantum of rainwater available for harvest 37
9 Municipal Solid Waste generation 38
10 Waste Generated from Floating Population 38
11 Details/ Distribution of Tree Plantation 39
12 Environment Monitoring Plan 41-42
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 4
EXECUTIVE SUMMARY
This document presents the findings of the Environmental Pre Feasibility of the construction
of proposed group housing and Commercial Space, which provide HIG Flats, LIG Units, EWS
Unit , commercial facilities, community blocks and well developed green area with developed
road area. The project is proposed at gram- Aurangabad, Dist.- Lucknow, Uttar Pradesh.
being developed by Lucknow Nagar Nigam. SAWEN Consultancy Services Pvt. Ltd.,
Lucknow was contracted by LMC to secure Environment Clearance from MoEF/ SLEAC and
No Objection Certificate (NOC) from Uttar Pradesh Pollution Control Board (UPPCB) for the
proposed project.
The proposed Multistory Building & Commercial Space is providing the residential
facilities proposed LMC, having total plot area of 50971.0 m2. The project provides well
furnished and comfortable flats with adequate green belt development to create the proper
and sustainable environment. Parking facilities shall be appropriately provisioned by
developing open Parking within the proposed project. The project provides greenery and
open spaces, thereby making available more area defining the quality of work environment.
The land is having total built up area of 81369.0 m2, the proposed site for the residential
project will be easily accessible by Road No.-1 and Amar Shaheed Path , also well connected
to various places, through national highways, rail links, bus ways and telecommunication.
The estimated cost of the project will be 291.25 Crore. The Uttar Pradesh State Electricity
Board will provide necessary expected demand load to meet the power requirement of the
proposed group housing. During power failure 02 no. DG Set of 300 KVA & 400 KVA each
shall be provisioned.
The development will also have green area and the other facilities required for residential
projects. Appropriate fire fighting measures including entry and exit way marking signs,
emergency lights, ventilation, essential emergency electrical services and stationary fire
pump (jockey) shall be provided for the proposed project.
In the layout, some area has been reserved for landscaping and a vision to create a buffer to
help in creation of calm, serene and cool environment for institute and act as buffer between
the building area and the adjoining traffic routes. Green belt planning on 7630.0 m2 will be
provided with ecological perspectives for the proposed project taking into consideration of
urban biodiversity and native species.
The water with overall requirement of 320.0 KLD shall be managed by 02 no. of Bore wells.
Noise level shall be maintained by providing acoustic enclosures in DG sets and traffic norms
will be followed within the residential building project.
300 KLD Sewage Treatment Plant shall be installed for the treatment of waste water
generated from domestic requirement of the proposed residential building. Within the
proposed project, Stack Height of 5.2 m shall be provided above the tallest building.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 5
Natural slope of the area will be retained and will be graded to fall towards the roads or
drain paths and storm water will be made to percolate to 08 nos. of recharge pit proposed
for ground water recharge. For traffic noise, plantation along the traffic route shall be
provided to act as a noise barrier.
It has been roughly estimated that of 2268.0 Kg/day of municipal waste generated from the
residential building. Required Parking for the residents and floating population is fulfilled by
open parking facilities within the proposed group housing and commercial spaces.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 6
CHAPTER 1: INTRODUCTION
Housing is a basic human requirement of any civilized society. With the growth of urbanization, cities have been expanding alarmingly in the last few decades, which have resulted in haphazard growth of urban areas as well as acute housing shortage. Uttar Pradesh Housing and Urban Planning Department was established to ensure planned development of urban areas and create an enabling environment to provide comfortable housing. The multiplicity of urban laws has always been a nightmare for the urban populace. Rapid Urbanization is an intrinsic part of the development process. One of the major challenges before the nation is to provide planned neat urban settlements with adequate greenery and open spaces rather than unplanned haphazard and polluted slum like urban settlements. The quality of the urban centre determines the quality of life of the inhabitant. Planning of a new urban centre therefore is of utmost importance for defining the quality of life. The proposed Multistory Building, Row Hoses & Commercial Spaces at Gram-
Aurangabad , Tehsil -Lucknow, District- Lucknow is comprises of following units:
HIG Units , MIG Units, LIG Units, EWS Units, Row Houses, Community Centre And Shops.
1.1 ENVIRONMENTAL CONCERNS OF BUILDING & CONSTRUCTION PROJECT
Building account for about a third of energy consumption world-wide and with
commercial/residential buildings contributing slightly more than half of that percentage. From
1980 to 2006, total building energy consumption worldwide has increased more than 46%
whether such growth rates will continue in the future is uncertain. Use of water by buildings
worldwide has grown significantly between 1985 and 2005. Such increases in water use are
occurring in the context of stresses to the water supply caused by recent droughts and
growing concerns about drying trends in the climates of Indian Subcontinent.
1.2 LOCATION:
The proposed construction of Multistory Building and commercial Spaces at Gram-
Aurangabad , Tehsil – Lucknow, Uttar Pradesh.
Demographics:
The population of Lucknow Urban Agglomeration (LUA) rose above one million in 1981
while the 2001 census estimated it had risen to 2.24 million. This included about 60,000
people in the Lucknow Cantonment and the 2.18 million in Lucknow city and represented an
increase of 34.53 percent over the 1991 figure.
As reported by the Census of India 2011 Lucknow city had a population of 2,815,601 of which
1,470,133 were men and 1,345,468 women. This was an increase of 25.36 percent compared
to the 2001 figures.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 7
Between 1991 and 2001 the district population registered growth of 32.03 percent,
significantly lower than the 37.14 percent which was registered between 1981 and 1991.The
initial provisional data for the district suggests a population density of 1,815 per km2 in 2011
compared to 1,443 in 2001. Although the total area covered by the Lucknow district is only
about 2,528 square kilometers (976 sq mi), the population density was much above that of
the 690 persons per km2 recorded at state level. Over 36.37 percent of the total population
resides in rural areas leaving barely around 63.3 percent composed of urbanites.
These were, however, high figures when compared to the state as whole, where urban
population only constituted around 21% of the total population. The sex ratio in Lucknow
city stood at 915 females per 1000 males in 2011 compared to 2001 census figure of 888. The
average national sex ratio in India is 940 according to the Census 2011 Directorate.
Decadal Growth of Urban Agglomeration & Lucknow Municipal Corporation (1951-2021) Lucknow Urban Agglomeration Lucknow Municipal Corporation Lucknow Cantonment
Year Population Decadal Growth
Growth Rate %
Population Decadal Growth
Growth Rate %
Population Decadal Growth
Growth Rate %
1981 1007604 193622 23.79 947990 173346 22.38 59614 20276 51.54 1991 1669204 661600 65.66 1619116 671125 70.79 50089 -9525 -15.98 2001 2245509 576305 34.53 2185927 566811 35 59582 9493 18.95 2011* 3226000 980491 43.66 3166000 980073 44.84 60000 418 0.70 2021* 4500000 1274000 39.49 4440000 1274000 40.24 60000 0 0
Source: Master Plan: 2021; * Projected Population
1.3 IDENTIFICATION OF PROJECT AND PROPONENT
The proposed construction of group housing being developed by Lucknow Nagar Nigam, at
Gram- Aurangabad, Tehsil & Dist.- Lucknow, Uttar Pradesh.
As per the EIA Notification, 2006, the project having built up area more than 20,000 m2
requires Environmental Clearance from SEIAA , but as per Water Act, 1974 & Air Act, 1981
every project required consent to establishment (NOC) from the respective State Pollution
Control Board, before commencement of project.
The proposed project is having Built up area 59699.40 m2 which is > 20000.0 m2 hence
the project requires environmental clearance from SEIAA under schedule 8 (a), Cat. B2 &
also falls under the preview of NOC from the UPPCB as per EIA Notification 2006.
1.5 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
The project has been provisioned to serve the purpose of mitigating the residential problem
of the Lucknow city. The basic concept of the project is as:
Quality based resident units
Spacious Commercial Shops
Good environment
High quality infrastructure development
Employment opportunities at one place
Well planed connectivity emphasizing the walk to work concept.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 8
The main purposes of the Plan are:
1. To develop a luxury flats furnished with all modern facility of group housing such as
amenity block , surface, basement and stilt parking facility, proper greenery etc.
2. To create an environment that could support the culture of good standard of living by
collocating essential facilities required for day to day living.
3. To meet the growing demands of housing in Lucknow in an environmentally
sustainable manner’
4. To enhance the surrounding with greenery, landscaping and recommended aesthetics;
5. To emphasize the policy of afforestation and rain water harvesting to create a better
microclimate in the area.
6. To create a healthy environment for living.
7. To promote planned integrated development of towns & cities. The components of
assistance under the scheme include all urban infrastructural development.
8. Improved infrastructural facilities and help create durable public assets and quality
oriented services in cities and towns.
The main objective of the project is as follows:
1. To promote a healthy relationship between urban development and environment
particularly emphasizing on effective and planned space utilization.
2. Reinforcement of natural infrastructure;
3. Conservation of resources;
4. Development of a monitored landscape management program.
5. Developed the well developed infrastructure facilities like water supply, sewerage,
community centre.
The proposed development will cover rapid and time bound urban infrastructure
construction, improvement & maintenance of ecological features. This land is needed to be
developed for residential purpose with provision of all basic amenities and facilities for
creation of quality spaces to the public assets.
1.5 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE REGION
As the Lucknow dist. is one of the developing district of Uttar Pradesh and many people from
nearby areas come for their settlements which develop the continuous demands of flats, in the
city. The proposed group housing will provide luxurious flats of 2 BHK , 3 BHK , EWS Flats , LIG
Flats with amenities facility within the housing. Well developed greenery in the surrounding
of the flats and appropriate parking facilities provide to the residents and visitors. As a result,
it may help to increase the economic growth of the city.
1.6 SITE SELECTION FOR PROPOSED PROJECT AND ITS APPROVAL
The site is strategic for developing modern developed and luxurious group housing at Village –
Aurangabad, Tehsil & District- Lucknow, U.P.
1.7 LAND USE- WITH REFERENCE TO PROPOSED LOCATION
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 9
The site is plane vacant land of Gram- Aurangabad, which is approachable through Amar Shaheed
Path & Road no.-1 from project site.
1.8 EMPLOYMENT GENERATION (DIRECT & INDIRECT) DUE TO THE PROJECT
The proposed development of project will provide better residential facility to the
residents. The benefit of developing group housing is related to the direct employment to the
people associated with the construction. It provides employment to skilled and unskilled
laborers during construction 150 nos. of labors are working for the project. Additional
employment opportunities will lead to a rise in the income and improve employment opportunities
for nearby population and their standard of living from the regions of Aurangabad Khalsa,
BarauliKhalilabad, Barauna, Devamau, Gusval kala, Mujaffar Nagar, Ghusval etc . The proposed
facility will also generate jobs for the women labourers during construction phase. This will
considerably reduce their travel time in any employment and therefore enable them to attend the
childrens and their nutritional demands with house hold chores.
1.9 ENVIRONMENTAL LEGISLATIONS APPLICABLE TO THE PROJECT:
1. The Water (Prevention and Control of Pollution) Act, 1974
a. The Water (Prevention and Control of Pollution) Rules, 1975 - Schedules
b. Central Board for the Prevention and Control of Water Pollution (Procedure for
Transaction of Business) Rules, 1975
c. The Water (Prevention and Control of Pollution) CESS Act, 1977
d. The Water (Prevention and Control of Pollution) Cess (Amendment) Act, 2003
2. The Air (Prevention and Control of Pollution) Act, 1981
a. The Air (Prevention and Control of Pollution) Rules, 1982 and Schedules
b. The Air (Prevention and Control of Pollution) (Union Territories) Rules, 1983
3. The Environment (Protection) Act, 1986
a. The Environment (Protection) Rules, 1986 and Schedules
b. Environment (Protection) Third Amendment Rules, 2002
c. Rules for the Manufacture, Use, Import, Export and Storage of Hazardous Micro
Organisms Genetically Engineered Organisms or Cells, 1989
d. The Environment (Protection) (Second Amendment Rules), 1999 - Emission Standards
for New Generator Sets
4. Hazardous Wastes (Management and Handling) Rules, 1989
a. The Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989
b. Manufacture, Storage and Import of Hazardous Chemical (Amendment) Rules, 2000-
Draft Notification
c. Hazardous Wastes (Management, Handling & Transboundry Movement) Rules, 2010
5. Bio-Medical Waste (Management and Handling) Rules, 1998
a. Hazardous wastes (Management and handling) amendment rules 2000
b. Hazardous Wastes (Management and Handling) Amendment Rules, 2002
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 10
6. S.O.979 (E), [27/8/2003] - Amendments to S.O.763 (E) dates 14/9/1999
Dumping and disposal of fly ash discharged from coal or lignite based thermal
power plants on land
7. Municipal Solid Wastes (Management & Handling) Rules, 2000
8. Battery (Management and Handling) Rules, 2000.
9. The Noise Pollution (Regulation and Control) Rules, 2000
a. The Noise Pollution (Regulation and Control) Rules, May 2002
10. Re-cycled Plastics Manufacture and Usage Rules, 1999
a. Re-cycled Plastics Manufacture and Usage Amendment Rules, 2002
b. The Recycled Plastics Manufacture and Usage (Amendment) Rules, 2003
11. Ozone Depleting Substances (Regulation) Rules, 2000
12. The Indian Forest Act, 1927
a. The Forest (Conservation) Act, 1980
b. The Forest (Conservation) Rules, 1981
c. Guidelines for diversion of forest lands
d. Forest (Conservation) Rules, 2003
13. The Wild Life (Protection) Act, 1972 and Schedules
a. The Wild Life (Transactions and Taxidermy) Rules, 1973
b. The Wild Life (Stock Declaration) Central Rules, 1973
c. The Wild Life (Protection) Licensing (Additional Matters for Consideration) Rules, 1983
d. The Wild Life (Protection) Rules, 1995
e. The Wild Life (Specified Plants- Conditions for Possession by Licensee) Rules, 1995
f. Recognition of Zoo Rules 1992
g. The Circular Concerning Joint Forest Management
h. The Wild Life (Protection) Amendment Act, 2002
14. The Public Liability Insurance Act, 1991
a. The Public Liability Insurance Rules, 1991
15. The National Environmental Tribunal Act, 1995
a. The National Environment Appellate Authority Act, 1997
16. Provisions of Indian Penal Code
a. Provisions of Criminal Procedure Code
b. Provisions of Factories Act, 1948
17. No.59 of 1960- The Prevention of Cruelty to Animal Act, 1960
18. The Biological Diversity Act, 2002
a. Draft Biological Diversity Rules, 2003
b. 2-T Oil (Regulation of Supply and Distribution) Order, 1998
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 11
CHAPTER 2: PROJECT DESCRIPTION
2.1 PROJECT SUMMARY
The site proposed for construction of Multistory Building, Row Houses and Commercial Spaces
at Village – Aurangabad, Tehsil & District- Lucknow, U.P.
The details of the proposed Residential Flats are tabulated below:
Description Area in SQMT
Plot Area 50971.0
Built Up Area 81369.62
Permissible FAR (1.5) 76186.5
Purchasable FAR ( 0.33) 16761.03
F.A.R Achieved (1.5) 76186.5
Total Road Area 17141.0
Total Green Area 7630.0
Total Ground Coverage 16493.21
Standby DG Set 01 x 300 KVA
01 x 400 KVA
Total Parking Provision 941 ECS
Total Expected Population 4215Personnel
Sources of Water Supply 02 No. of Borewell
Total Consumption of Water 320.0 KLD
Total Waste Water Generated 242.0 KLD
Total MSW Generated 2268.0Kg/Day
Proposed Rain Water Harvesting 08 nos.
STP Capacity 300 KLD
Total Project Cost Rs. 291.25 Crore
2.2 PROJECT CATEGORY
The proposed project for the construction of group housing project with built up area of
81369.62 m2 which is > 20,000.0 m2; hence the project requires environmental clearance
from SEIAA as per the EIA notification 2006 under Schedule 8(a); Cat. B2 & also falls under the
preview of NOC from the State Pollution Control Board as per the EIA notification 2006.
2.3 Project Cost
The project cost of the proposed project is Rs. 291.25 Crore
Table 1: Capital Expenditure
S. No.
Description Cost (Rs. in Lacs) TIME FRAME
1. Landscaping 03 Years
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 12
Table 2: Recurring Expenditure
2.4 PROJECT DESCRIPTION WITH PROCESS DETAILS
Major construction elements of the proposed project include foundation treatment as well
as other facilities for water supply and drainage, fire-fighting and lighting. The buildings
will be of masonry-concrete structures, roads will be made of mass concrete and yard
surface will be made of high-strength interlocking concrete blocks. Pollution sources
during the construction period consist mainly of mechanical noise, engineering dust,
engineering wastewater and construction waste & temporary hutment waste. An analysis
of environmental impacts and proposition of environment management plan during
construction period for the proposed project and proposals on pollution prevention and
control measures and managerial requirements may reduce negative impacts by project
construction to a minimum.
2. Air Pollution Control System 06 months
3. 200 KLD STP Before Building Occupancy
4. Rain Water Harvesting 06 months
5. Waste Management Before Building Occupancy
6. Power Backup 06 months
7. Solar & Energy Conservation Measures
01 year
Total -
S. No. Description Cost (Rs. in Lacs)
1. Landscaping
2. Air Pollution Control System
3. 200 KLD STP
4. Rain Water Harvesting
5. Waste Management
6. Power Backup
7. Solar & Energy Conservation Measures
Total
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 13
Construction work of proposed Multistory Building.
Process Flow Chart: Figure 1
The project shall be executed in 02 Years and the process flow chart is as follows:
Earth Work
Civil Construct
Electrical & Sanitary work
Furnishing
(Aluminum, wood, marble)
Painting
Horticulture/ Landscaping/ Rain Water Harvesting
Operation of proposed Multistory Building & Commercial Spaces
2.5 RAW MATERIAL REQUIRED FOR CONSTRUCTION & MODE OF TRANSPORT OF
RAW MATERIAL/FINISHED PRODUCT.
List of Raw & Building Materials
i. For Civil construction ii. For Furnishing
1. Cement 1. Wooden planks, Doors
2. Concrete 2. Gypsum board false ceiling
3. Reinforcement Steel 3. Glass
4. Sand 4. Sanitary fittings & fixtures
ii. For Civil construction ii. For Furnishing
1. Bricks 6. Paint & Polishing
2. Marbles / Granite 7. Electrical fittings & fixtures
3. Plaster of Paris 8. Air conditioners
4. Steel 9. Aluminum windows
5. Stone aggregate
10. Fly ash
11. Water Proofing compound
12. Tiles
13. Shuttering plates
14. M.S Scaffolding
iii Electrical and mechanism equipment
1. PVC wires/cables 5. Fire fighting system
2. Polycarbonate switches/ sockets 6. Fire fighting system
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 14
3. Ms boxes / panels 7. MCB, DBS
4. UPS, Transformers
iv. List of machinery used during construction
Loader : loading of materials
Dumper : Mud and material handling
Concrete mixer with hopper : RCC work
JCB : Digging and earth work
Concrete Batching Plant : Concrete mixing
Cranes : Lifting and moving of materials
Road roller : Compacting the earth
Tractor Trolley : Carrying & transporting material
During transportation of raw / construction material, a water ditch with its width at 3.5
meter, length at 10 meters and depth at 0.2 meter shall be made at the exit to and from the
construction site, in which crushed stones with a diameter at 50 millimeters will be laid, so as
to reduce the amount of earth on tires of vehicle to and from the construction site; covers will
be made on materials to be transported or they will be transported by enclosed vehicles,
routes of transportation vehicles shall avoid environmentally sensitive areas, and vehicle
speed shall also be limited.
2.6 DRAINAGE PATTERN AT SITE
The drainage of the district is controlled by river Gomti, Sai its tributaries. Tributaries of
Gomti River are Akhadi Nala, Jhilingi Nala, Behta Nadi. The project site lies on the city
municipal sewer system. The drainage system shall be designed accordingly to connect
through underground drains after sewage treatment have been planned.
2.7 SEWERAGE SYSTEM
The trunk sewer line is available for the city and is being improved as per development of
various sectors as part of Master Plan 2021.
The proposed project will be developed with a dedicated and efficient sewage collection system
having proper internal connectivity with the proposed sewage treatment plant to ensure the
proper treatment of the sewerage to the city sewerage network of area with a sewer network of
municipal department, the diameters varying from 150 mm to 900 mm. This sewer network
has been upgraded and connected to the newly laid sewer system. The total waste water
generated from the Multistory Building and Commercial spaces shall be treated in the 300
KLD Sewage Treatment Plant based on FAB Technology within the premises.
2.8 SOLID WASTE MANAGEMENT
A state of the art system for collection of solid waste from residential areas has already been
put into place through Lucknow Municipal Corporation. Efforts are on for scientific disposal of
the waste through MoEF/CPCB/UPPCB approved vendors. The objective is to provide a neat
and clean healthy environment in the building. The estimation of waste generation from the
proposed project shall be done as per the standards described in Lucknow Development Plan
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 15
2021. The collection system through garbage chutes has been proposed to develop within the
project. From those depots, tippers or carnage vans will cart the waste up to designated disposal
site for treatment.
2.9 ELECTRIFICATION/ POWER REQUIREMENT & ITS SOURCE
Power supply is provided by Uttar Pradesh State Electricity Board. The electrical cables from
electric substation will be laid underground. At proposed project site the initial assessment of
the development area and the mode of conceptual philosophy of electrical infrastructure
development have been thought to include the following main components:
2.10 AVAILABILITY OF WATER & ITS SOURCE.
For availability of water in the region, water demand has been calculated based on the
saturation density (ultimate population) proposed in Lucknow Development Plan 2021.
Provision of water supply i.e. distribution networks, Bore well, rising mains, overhead tank
have been made accordingly. For the proposed Group Housing during operation phase the
source of water supply is through Municipal Supply.
2.11 SCHEME FOR WASTES MANAGEMENT/ DISPOSAL
For efficient waste collection management system, the Lucknow city is divided into Zone, the
work relating to primary collection of waste has been decentralized at the zone level where it
is supervised by health officers with the assistance of ward level inspectors, Sanitary
supervisor. The primary collection involves waste disposal from commercial and institutional
places.
LMC has fleets of vehicles for collecting and transporting waste from collection points to the
disposal site. Each of the vehicles is allotted specific area for collection and transportation to
waste disposal site.
Following steps have been proposed by for collection, treatment and disposal of MSW:
Step-1: Collection and Segregation of MSW at source of generation
Step-2: Transportation of MSW to the disposal site
Step-4: Shredding of the compostable waste to desired particle size
Step-5: Treatment of biodegradable waste through composting
Step-6: Disposal of non bio-degradable solid waste into Secured Landfill.
The year 2021 envisages a comprehensive and sustained solid waste management system with modern and scientific answers to collection, transportation and disposal.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 16
CHAPTER 3: SITE ANALYSIS
3.1.1 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND
PROJECT BOUNDARY & PROJECT SITE LAYOUT) WITH COORDINATES.
In the preparation of an environmentally compatible urban development plan, it is a
prerequisite to understand linkages and interactions that exist between different components
of the urban environment. Lucknow is located on NH 25, NH 24 & NH 28 which links the city to
many large cities in the north – west and the south – east. State Highways connect Agra,
Allahabad, Kanpur, Meerut and Jhansi. The city is connected by the broad gauge railway line to
Delhi, Kolkata and Mumbai. The city is also served by regular air services to Mumbai, Delhi,
Hyderabad and Bangalore. Large portion of city areas and New Lucknow are separated by
railway line & river Gomti which acts as divider in social. The present city stands segregated
distinctly in two parts Trans & cis Gomti.
It mainly comprises of institutional land use.
The project area falls in Trans Gomti region of the city.
The Gomti River is flowing South-West side from project site.
The project area is the commercial/ residential part of city in terms of density, intensity of
buildings and movement of traffic because of rapid socio-economic and physical change.
The coordinates of the proposed project is as follows :
A= 26°45'11.94"N
80°55'45.72"E
B= 26°45'12.58"N
80°55'38.94"E
C= 26°45'14.24"N
80°55'31.20"E
D= 26°45'15.89"N
80°55'31.24"E
E= 26°45'16.17"N
80°55'33.00"E
F= 26°45'22.26"N
80°55'44.79"E
G= 26°45'18.54"N
80°55'47.33"E
H= 26°45'12.73"N
80°55'47.02"E
119 – 122 m elevation from mean sea level.
3.2 CRITERIAS FOR SELECTION OF LAND
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 17
The land area of Vill:- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, is of Nagar Nigam
Lucknow, for the development of Multistory Building, Row Houses & Commercial Space.
Following criteria’s were selected for selection of land.
1. a) Proximity to linkage:
It was observed that development pattern generally follows the transportation corridors
because of high accessibility development as opposed to haphazard growth, which is seen in
most cities. The proposed site is situated at Village- Aurangabad Khalsa, Tehsil & District-
Lucknow, U.P., easily approachable through Amar Shaheed Path, towards NW, at a distance of 0.9
Km from the project site and Road no.-1 is adjacent to the Project site in NW direction..
1. b) Proximity to existing settlements:
The areas of project site already existing in a high developed zone and population pressure is
likely to witness growth pattern influenced by the surrounding existing institutes, &
commercial establishments.
1. c) Hydrogeology:
Ground water occurs in the pore spaces of the unconsolidated alluvium sediments in the zone of saturation under phreatic and semi confined conditions. In deeper aquifer it occurs under semi confined to confined conditions.
On the basis of NHS & piezometres Pre-monsoon Depth to water map 2008. Post-monsoon
Depth to water map 2008 & fluctuation maps has been prepared. On the basis of Pre-monsoon
map (Plate-II) it is revealed that shallowest water level less than 2 metres & between 2-5
metres occurs in the eastern part of district in the Gosainganj block along the Sharda Sahyak
Canal. Depth to water between 5 to 10 metres occurs in the northern & southern part of
districts in part of Bakshi-Ka-Talab, Chinhat & Mohanlal ganj blocks. The western part of the
district depth to water ranges between 10-20 meters in Mal, Malihabad, part of of Bakshi-Ka-
Talab. Kakori, Sarojini Nagar & part of Chinhat blocks. Minimum water level of 1.80 mbgl was
observed at Gosainganj and maximum of 32.60 mbgl was observed at Gulistan Colony in the
Lucknow town. In the urban areas depth to water generally remains more than 20 mbgl.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 18
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 19
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 20
d) Geomorphology & Soil Type:
The district forms a part of Ganga basin with flat alluvial terrain. General elevation varies
from 103 m to 130 metres above mean sea level. The general slope of the district is south-
east.
Geomorphologically the district is divided into two geomorphic units:
(i) Older flood plain
(ii) Active flood plain Older flood plains are represented by two level of terraces viz Erosional terrace
(Te) occupying at higher level and Depositional terrace (Td) at lower depressions.
Older flood plain exists between elevation of 103 and 110 mamsl. Both the terraces
are developed on the either side of Gomti River.
Erosional Terrace is also developed along Sai Nadi. Active flood plains are restricted
to present day bank line of the rivers. These are represented by land forms like
point bars channel bars and lateral bars.
Quaternary sediments have been divided upto older & newer alluvium.
The older alluvium is comprised of grey to brown coloured silt clay and sand with
or without Kankar of middle to late Pleistocene age.
The Newer alluvium overlies the older alluvium and has been sub divided into
terrace alluvium and channel alluvium & belongs to Holocene age. The newer
alluvium comprises of light Khaki grey silt, clay and fine to medium and coarse
grained grey sand which is micaceous in nature.
Soils in the district exhibits a vide variation in composition texture and appearance.
The major position of the district is occupied by soils locally known as "Bhur" or
"Silty Sand" on the ridges. "Matiyar" or "Clay Soils" occurs along topographic lows
and "Dumat or Loamy soils" in the level lands.
Clay is dominant in the areas where "Reh" (Usar) prevails. Along the river valleys, a
very fertile soil called "Dumat" is prevalent which is youngest.
1. e) Drainage
The proposed project site falls in the drainage of existing sewer line. The general slope of the
area is from south-east to north-west i.e. towards the sewer line.
1. f) Seismicity of Lucknow
The seismic hazard map of India was updated in 2000 by the Bureau of Indian Standards
(BIS). The Lucknow city is located in the seismic zone III with majority of the portion having
provision of earthquake resistance in construction.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 21
CHAPTER 4: PROJECT PLANNING
4.1 PLANNING CONCEPT The proposed project is being developed to offer well spacious residential flats comprises of HIG Units, MIG Units, LIG Units, EWS Units, Row Houses, Community Centre and Commercial blocks at Village-Aurangabad Khalsa, Tehsil & District- Lucknow, U.P. The total land area of 5.0791 Ha for the proposed project is of Lucknow Nagar Nigam. Table 3: Units Details of the Proposed Project
DESCRIPTION NO. OF FLOORS TOTAL NO. OF UNIT
GROUND COVERAGE
TOTAL COVERED AREA
HIG UNITS
Block-A G+8 324 5643.27 48618.63
Block-B G+3 48 1842.48 7321.95
MIG UNITS
Block-C G+3 112 2028.81 8115.24
LIG UNITS
Block-D G+3 168 2804.55 11218.2
EWS UNIT
Block-E G+3 12 2057.72 2057.72
HIG FLATS (ROW H)
Block- F G+1 21 2116.38 4037.88
Community Centre G+3 481.77 1927.08
TOTAL 685 16493.21 81369.62 The Build up area = 81369.62 m2 Gorund Coverage = 16493.21 m2
4.2 Land Uses of Proposed project Table 4: Land Uses
DETAILS AREA PERC ENTAGE
GC 16493.21 32.5
GREEN AREA 7630 15.0
SHOPS 474 0.9
OPEN SPACES 7510 14.8
ROAD AREA 17141 33.7
PRIMARY SCHOOL 1061 2.1
COMMUNITY CENTRE 481.77 0.9
50791.0 100
4.3 Population details for Project
Table 6: Plotted Population Break Up at Project Site:
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 22
S. NO. STAFF DESIGNATION Population
1 Residents (685 Dwelling Units @ 5 person per unit) 3425
2 Service Staff 50
3 Floating Population 700
4 Commercial Staff 40
Total Expected Population 4215
Therefore, the total expected population of proposed group housing will be 4215 personnel.
4.4 SITE SETTINGS
Nearby Towns/Villages:-
Alinagar Khurd – 2.5 Km, SE
Asharaf Nagar – 2.5 Km, SW
Omax City- 0.42 Km, NW
Rasoolpur Induria- 1.05 Km, SE
Hospitals
SGPGI- 2.17 Km, SE
Javitri Hospital – 3.02 Km, NE
Schools
JB Memorial Inter College, 3.05 Km, SW
Baba Bhim Rao Ambedkar University- 1.0 Km, NW
Worship Places
Jumma Masjid, 2.7 Km, SW
Gayatri Prajapati Temple – 4.51 Km, NW
Forest
SGPGI Forest – 0.25 Km, NW
Water Courses:
Gomti River – 9.5Km, NE
Canal- 0.81 Km, W
Eldeco Lake – 1.5 Km, NE
PGI Forest Lake – 0.15 Km, South
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 23
CHAPTER 5: PROPOSED INFRASTRUCTURE
5.1 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD/RAIL/METRO/ WATER
WAYS ETC.) WITH IN THE DEVELOPMENT REGION.
5.1.1 Road Network
The delineated project site is located at Village Aurangabad Khalsa, Tehsil & District- Lucknow,
U.P. The proposed site is well connected to various places, like Airport, Railway, Bus Terminus &
other parts of the city by road.
The major road linkages are –
Road No.-1, adjacent, NW
Amar Shaheed Path – 0.9 Km, NW
Bijnour Road – 1.31 Km, W
Raebareilly Road – 2.25 Km, E
5.1.2 Rail Linkages
Utrathiya Railway Station- 4.6 Km, NE
Manak Nagar Railway Station- 7.18 Km, NW
Lucknow Railway Station- 8.5 Km, N
5.1.3 Air Network
The Chaudhary Charan Singh, Amausi airport at Lucknow is located at a distance of 4.43 Km,
NW from the proposed project site. It has been placed strategically on Kanpur Road,
presumably to ensure availability of uninterrupted air space in low-density zones.
5.2 PARKING DETAILS:
Required Parking:
HIG @ 1.5 ECS/UNIT = 372*1.5 = 558
MIG @ 1.25 ECS/UNIT = 112*1.25 = 140
LIG @ 1 ECS/UNIT = 168*1 = 168
Commercial @ 2 ECS /100 m2 = 9
Total Required Parking = 875
Parking Provided:
First Basement Area for parking = 17000 sqm/32.0 = 531 ECS
Second Basement Area for parking = 12000 sqm/32.0 = 375 ECS
Surface Area for Parking = 35 ECS
Total Provided Parking = 941 ECS
So, the provided 941 ECS shall meet the total expected requirement with adequate
area. Hence, area statement is justified.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 24
5.3 LANDSCAPE AREA DETAIL:
Total Landscape Area is = 7630.0 m2
Plantation Details:
As per MoEF Laws = 1 tree/80 sqm of the total plot area
=50791.0/80 = 635.0 nos. trees required
5.4 APPROACH ROAD & BUILDING HEIGHT
The maximum height of the proposed building is 2B+G+8 as follows:
DESCRIPTION NO. OF FLOORS
HIG UNITS
Block-A G+8
Block-B G+3
MIG UNITS
Block-C G+3
LIG UNITS
Block-D G+3
EWS UNIT
Block-E G+3
HIG FLATS (ROW H)
Block- F G+1
Community Centre G+3
Parking in Basement-1 B1
Parking in Basement-2 B2
5.5 Solar Light Provision Following area are sources through solar light provision
Park Lights Street Light Common Area Light
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 25
CHAPTER 6: ENVIRONMENTAL MANAGEMENT PLAN
6.1 WATER MANAGEMENT (SOURCE & SUPPLY OF WATER).
Total water demand of the residential building including green areas excluding fire fighting
water demand and losses is calculated to be 320.0 KLD. About 7.6 KLD water out of total water
demand will be utilized for the irrigation of the green and landscape area proposed inside the
project premises. The water demand estimation has been tabulated in Table 7. The one time
water requirement for firefighting demand will be 3.2 KLD based on CPHEEO guidelines, i.e. fire
demand for < 50,000 population = 1% of total water demand.
## Source of Water Supply through Municipal Supply
6.1.1 Water supply for green area
The water demand estimated for maintenance of green covers of residential building in the non-
monsoon period works out to be 7.6 KLD. It has been calculated by assuming 1.0 liters of water
required for 1 m2 of green area. The salient features for the water supply to the green area will be:
• Garden hydrants will be provided along the supply line so as to access this water to irrigate the
nearby green covers;
• The spacing proposed for water hydrant will be in the range from 60 m to 100 m as per the
requirement;
• The pressure at outlet of hydrant will be maintained equivalent to 15 m head.
One time Fire Fighting Demand = 3.2 KLD (As per CPHEEO Manual, GOI)
Table 10: WATER USE CALCULATION S. No.
Water Use
Population
Per Capita in (LPCD)
Water Requirement
(KLD)
Waste Water
Generation (KLD)
1 Residents 3425 86 295.0 235.0 2 Service Staff 50 45 2.4 2.0 3 Commercial Staff 40 45 2.0 1.8 3 Floating Population 700 15 10.5 8.4
TOTAL DOMESTIC WATER REQUIREMENT 309.9 247.2
5 DG Set Cooling 300 KVA + 400 KVA
0.9l/4hr/KVA 2.5 NIL
6 Gardening 7630.0 m2 1 l/m2 7.6 NIL
TOTAL WATER REQUIREMENT
320.0 247.2
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 26
6.1.2 Water Balance Diagram Figure 2
*The grey water is the waste water generated from sinks, showers, washing machines, dish washers
etc.
**Black water is any waste from a toilet or urinal. In the proposed residential black water is
generate from flushing process only. It contains disease causing organisms that can result in
human illness by direct contact so disposed in the sewerage treatment plant.
Grey Water 167.0 KLD
Waste Water
NIL
Total Waste Water
242.0 KLD
Fresh Water Requirement 234.9 KLD
Treated Water Requirement
85.1 KLD
7.831 KLD
300 KLD STP (Based on FAB
Technology)
Flushing 75.0 KLD
Gardening Requirement
7.6 KLD
Black Water 75.0 KLD
Domestic Requirement
234.9 KLD
Total Water Requirement
320.0 KLD
DG Set Cooling 2.5 KLD
Treated Water 218.0 KLD
For Car washing,
Cleaning etc
132.9 KLD
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 27
6.1.3 Sewerage
At the project site of proposed building, total 242.0 KLD (Grey Water = 167.0 KLD & Black
Water = 75.0 KLD) waste water generated from domestic requirement, which will be treated
in Sewerage Treatment Plant of capacity 300 KLD based on FAB Technology.
About 85.1 KLD of treated water shall be reused for flushing ,DG Set Cooling ,Gardening
purpose, within the project and about 132.9 KLD used for street washing and drain cleaning,
car washing etc within the premises.
SCHEME OF SEWAGE TREATMENT PLANT: During operation phase in the proposed building, generated waste water will be treated in
proposed 300 KLD STP based on FAB technology.
TREATMENT PROCESS:
The sewage treatment plant (Fluidizes Aerobic Bed Reactor- FAB) 300 KLD shall propose to
be installed to treat the raw sewage.
The process for Sewage Treatment Plant is as follows: (Figure 3)
OIL & GREASE TRAP
RECEIVING SUMP
BAR SCREEN CHAMBER
RAW SEWAGE
FILTRATE
FLUIDIZED AEROBIC BED
REACTORS (FAB) FILTER PRESS
SOLID SLUDGE
PLATE SETTLER TANK
TERTIARY TREATMENT
(Including U.V Treatment)
pH 6.5-7.5
BOD mg/l <10
COD mg/l <50
TSS mg/l <10
Oil & Grease
mg/l
NIL
After Tertiary Treatment
TREATED WATER TANK
FOR REUSE
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 28
TUBE SETTLERSCRENNING &
OIL / GREASE
REMOVAL
V V V V V V V V
M
M
AEROBIC
REACTOR - IAEROBIC
REACTOR - II
AIR BLOWERS
AIR
DIFFUSERS
FLOATING
MEDIA
FILTER
PRESS
SLUDGE
TREATED
WATER
TERTIARY
TREATMENT
(including U.V
treatment)
Wast
e
Wate
r
FOR REUSE
TUBE SETTLERSCRENNING &
OIL / GREASE
REMOVAL
V V V V V V V V
M
M
AEROBIC
REACTOR - IAEROBIC
REACTOR - II
AIR BLOWERS
AIR
DIFFUSERS
FLOATING
MEDIA
FILTER
PRESS
SLUDGE
TREATED
WATER
TERTIARY
TREATMENT
(including U.V
treatment)
Wast
e
Wate
r
FOR REUSE
SCHEMATIC DIAGRAM OF SEWAGE TREATMENT PLANT (Figure 4)
TREATMENT PROCESS FOR FAB
The sewage is first passed through a Bar Screen Chamber & an Oil & Grease Chamber
where any extraneous / floating matter gets trapped.
The sewage is then collected in a Receiving Sump where the variations in flow and
characteristics are dampened, which otherwise can lead to operational problems and
moreover it allows a constant flow rate downstream. Here the sewage is kept in mixed
condition by means of coarse air bubble diffusion.
The equalized sewage is then pumped to the Fluidized Aerobic Bed Reactors (FAB) where
BOD/COD reduction is achieved by virtue of aerobic microbial activities. The FAB reactors
run in series. The oxygen required is supplied through coarse air bubble diffusers.
The excess bio-solids formed in the biological processes which are separated in the
downstream Plate Settler Tank. The clear supernatant is sent to the tertiary treatment
section comprising of a Dual Media Filter and an Activated Carbon Filter, and UV
disinfections system. If needed Softener shall be provided.
The biological sludge generated from the FAB will be passed through filter press where it
will be dewatered and form a cake and then used as manure in green area of the block.
BENEFITS OF USING FAB TECHNOLOGY
Small space requirement
The concept of compact sewage treatment plants is promoted so that expensive conventional
treatment is dispensed herewith. The treatment scheme is also versatile, in the sense that
units can be re-arranged in any which way the space and pile caps are available.
Lower operating power requirements
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 29
The system utilizes aeration tanks of much smaller size, thereby reducing the overall power
required in aerating the raw sewage. Since the bio-reactor depth is more, efficient transfer of
oxygen takes place, thereby reducing the overall power consumed in treatment.
Simplicity in operation and maintenance
The system adopted has much less moving parts (only pumps and blowers). Further there is
no moving part inside the bio-reactor. This gives the advantage of continuously running the
bio-reactor system, under widely fluctuating conditions. All the maintenance on the
mechanical systems can be done with normal skilled mechanics available.
The system is unique in operation, such that, only inlet and outlet parameters (i.e. raw
sewage BOD / COD / TSS /TP and treated sewage BOD / COD / TSS / TP etc.) need to be
analyzed. Since the bio-reactor is self sustaining, there is no requirement of recycling the
biomass from the secondary clarifier. Hence, analysis such as MLSS / MLVSS / SVI (sludge
volume index) / F / M ratio etc. is not required to be done. This greatly reduces the analytical
load on the plant chemist / supervisor, and makes the system very simple to operate and
control.
The bio-reactor system adopted in the FAB based STP is provided with nutrients removal, and removal of disease causing E-coli bacteria. Nutrient removal The bio-reactor system operates at very food to micro-organisms ratio (F / M ratio). This
helps in totally converting the Ammonical nitrogen to nitrate nitrogen. In the process of
synthesis of organic substrate, about 40–50% of the total phosphates load is also reduced.
The remaining phosphates can be precipitated by addition of aluminum ions dosed in form
of Poly Aluminum Chloride (PAC). Phosphates react with aluminum ions and precipitate as
aluminum phosphate, which is an insoluble salt. Thus the total phosphates load can be easily
reduced by more than 90%.
Coliform removal
The outlet BOD of the bio-reactor system being very low (in other words, hardly any food is
available to the E-coli), most of the coliform are killed in the reactor itself. Remaining
coliform are killed by nominal chlorine dosing (of the order of 2–3 mg/l). The treated
sewage outlet coliform count will conform to WHO standards, with such low chlorine doses.
This will also ensure that there is not much residual chlorine.
Sludge handling The sludge generated in the bio-reactors is totally digested. Since the F / M ratio in the bio-
reactors is very low, the excess sludge generation is lower than compared to the
conventional ASP system. Normally, this sludge is an-aerobically digested to stabilize the
organic matter. The present system does not envisage any sludge digestion (since the sludge
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 30
is aerobically stabilized in the bioreactors itself), making the system more suitable for
operation with less manpower.
The excess sludge is separated in the secondary clarifier, and then disposed off either on
drying beds, or can be directly used as soil conditioner.
Water Conservation & Augmentation
1. For horticulture, a garden hydrant ring with pumping facilities has been proposed.
2. The sewer shall be treated within building for bringing down the characteristics of
sewer within the norms specified by Ministry of Environment & Forest, Govt. of India for
safe disposal.
3. The residential building shall get piped water supply through an appropriately
designed system and no area shall be having any individual system of water supply
(i.e. jet pumps, hand pumps or individual bore well).
4. It is outlined in Master Plan-2021 that lakes, ponds and small water storage bodies
should be conserved and protected from misuse as well as efficient water harvesting
system should be ensured in the construction projects.
5. Taps and other water flushing devices including showers used shall be designed to
waste less water.
6. Awareness plays a major role in water conservation. Public messages shall be
prominently displayed for water conservation.
7. Water leaks shall be tracked and corrected regularly.
8. Dual flush WC (3 – 6 liters instead of 10 liters) shall be used to optimize the water demand.
6.2 RAINWATER HARVESTING (Figure 5)
SIZE
PIT DIAMETER = 3000 mm
EFFECTIVE DEPTH = 3000 mm
PLAN OF RECHARGE PIT
Brick Wall
200 dia over flow to outside
Drain (as per site)
560 dia M.H. Opening
560 dia M.H.Opening
200 dia
drain
pipe from
desilting
chamber
Ground Level
200 dia over flow to outside
Drain (as per site)
200 dia
drain
pipe from
desilting
chamber
600 x 600 x 100 MM
R.C.C. Deflector or
Stone Slab
3000 MM dia
30
0
Step
30
0
560 dia CoverR.C.C.Slab
PLUG 560 dia Cover
230 TK
345 TK
Brick Wall / as per
Str. Design
Mesh
Coarse Sand 1.5 to 2 mm
Gravels 5 to 10 mm
50 – 150 MM Size Boulders
Slotted Pipe or 1 MM V.Wire
LCG Johnson Screen
250 to 300 mm dia Bore Filled
With Pea Gravels (3 – 6 MM)
16 mm dia PVC Pipe
Slotted Pipe or 1 mm V.Wire
LDG Johnson Screen
Bail Plug
30
0
Ground Level
Variable (as per site)
30
00
50
05
00
50
0D
ep
th V
ari
ab
le a
s p
er
wate
r ta
ble
1000 M
M
RECHARGE PIT
SIZE
PIT DIAMETER = 3000 mm
EFFECTIVE DEPTH = 3000 mm
PLAN OF RECHARGE PIT
Brick Wall
200 dia over flow to outside
Drain (as per site)
560 dia M.H. Opening
560 dia M.H.Opening
200 dia
drain
pipe from
desilting
chamber
Ground Level
200 dia over flow to outside
Drain (as per site)
200 dia
drain
pipe from
desilting
chamber
600 x 600 x 100 MM
R.C.C. Deflector or
Stone Slab
3000 MM dia
30
0
Step
30
0
560 dia CoverR.C.C.Slab
PLUG 560 dia Cover
230 TK
345 TK
Brick Wall / as per
Str. Design
Mesh
Coarse Sand 1.5 to 2 mm
Gravels 5 to 10 mm
50 – 150 MM Size Boulders
Slotted Pipe or 1 MM V.Wire
LCG Johnson Screen
250 to 300 mm dia Bore Filled
With Pea Gravels (3 – 6 MM)
16 mm dia PVC Pipe
Slotted Pipe or 1 mm V.Wire
LDG Johnson Screen
Bail Plug
30
0
Ground Level
Variable (as per site)
30
00
50
05
00
50
0D
ep
th V
ari
ab
le a
s p
er
wate
r ta
ble
1000 M
M
RECHARGE PIT
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 31
As the district receives 25 mm peak hourly rainfall rainwater harvesting in RWH pits.
Construction of Percolation tanks and recharge shafts may be an economical option in areas
with deeper water levels via roof by channelizing the clean water to rainwater recharging
pits, commercial complexes; institutional, etc also rain water harvesting has been made
mandatory in Building Regulations.
Rain water from the various roofs will be drained through rain water vertical down take
UPVC / MS pipes. These vertical down take pipes will be located at suitable locations inside
the shafts or embedded inside the wall. All the terraces will be sloped in a slope of 1:50 or
1:75 sloping towards down vertical pipes. Rain water disposal shall be designed as per NBC
i.e. 200 mm dia and 15 m depth of bore for rainfall @ of 25 mm/hour rainfall as per NBC.
TABLE 9: QUANTUM OF RAINWATER AVAILABLE FOR HARVEST
S.N. Description of
Area Area considered
(m2)
Harvesting
Factor or
Collection
Efficiency
Average
Annual
Rainfall
intensity (mm)
Total volume of water available for Rain Water harvesting (m3)
1 Roof Top Surface 16493.21 0.8 25 330.0
Grand Total 330.0 m3/hr
Total quantum of rainwater for 0.25 hr. = 330.0/4 = 82.5 m3
The required dimensions of pit = 2.0 m x 2.5 m x 2.0 m
Total required nos. of pits= 82.5/10 = 8.2 ~ 08 nos. Recharge pit
The total no. of rainwater harvesting pit shall be 08with dimensions of 2.0 m x 2.5 m x 1.5 m
at peak rainfall intensity of 25 mm.
Required Rain Water Harvesting Pits = 08/Nos.
6.3 AIR POLLUTION CONTROL
In order to reduce impact of dust during construction period, enclosure walls with a height
of 2 meters or above will be built around the construction site; on-site mixing will be done at
enclosed space, cement, lime powder and other construction materials shall be stored at
storage yard or tightly covered, discrete materials such as sand and soil will be covered, the
building materials to be loaded, unloaded and/or handled shall be covered, closed or
sprinkled, and none of them shall be thrown or spread into the air; a water ditch with its
width at 3.5 meter, length at 10 meters and depth at 0.2 meter shall be made at the exit to
and from the construction site, in which crushed stones with a diameter at 50 millimeters
will be laid, so as to reduce the amount of earth on tires of vehicle to and from the
construction site; covers will be made on materials to be transported or they will be
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 32
transported by enclosed vehicles, routes of transportation vehicles shall avoid residential
quarters and other environmentally sensitive areas, and vehicle speed shall also be limited.
During operation, only source of air pollution is D.G. Sets emission. Hence proper stack height
should be provided above roof top of building.
Exhaust height: In order to dispose emissions above building height, minimum exhaust
stack height would be as follows:
Minimum stack height for D.G. Set:
H = h + 0.2 × √KVA
Where, H = stack height of D.G. Set
h = height of Building
H = h + 0.2 × √ (300+400 KVA) = h + 0.2 × √700 KVA
= h + 0.2 × 26.45.0 m = h + 5.2 m
As per the information, 01 x 300 KVA & 01 x 400 KVA DG Set capacity shall be installed.
For, which cumulative stack height of 5.2 m above the proposed residential building shall be
provided. D.G set will be supplied with acoustic enclosure as per CPCB norms.
6.4 SOLID WASTE MANAGEMENT FOR MULTISTORY BUILDING, ROW HOUSES &
COMMERCIAL BLOCK
6.4.1 MUNICIPAL SOLID WASTE Details Population Rate Total Generated MSW(Kg/Day)
Residents 3425 0.625 2140.6
Service Staff 50 0.25 12.5
Commercial Staff 40 0.25 10.0
TOTAL 2163.0
Hence, the total Municipal Solid Waste generated within the housing building is expected to be
about 2163.0 Kg/Day
Table 10: Municipal Solid Waste
Type of Waste
Color of
Bins
Category
Disposal
Method
Total Waste
(Kg/ day)
Organics
Green
Bio Degradable
Municipal Solid
Waste Site
1190.0
Paper
Blue
Recyclable
Approved
Recycler 281
Metals
Glass
Textiles
Plastic
Ash & Dust
Grey
Non-Bio
degradable
Municipal Solid
waste Site
692
Total 2163.0
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 33
Table 11: Waste Generated from Floating Population @ 0.15 Kg/Day
Population Category Total
Waste
Bio-
degradable
Recyclable Non-Biodegradable
Nos. Floating Kg/ day Kg/day Kg/ Day Kg/ Day
700 Visitors 105 58 14 33
Therefore, Total expected MSW: 2268.0 Kg/day
A Solid Waste Management Scheme is depicted in the following figure for the residential project: Door to Door Collection of Waste To collect the waste from residential area the tricycles and auto tippers can be used. Numbers of tricycles and auto tippers required As one tricycle can collect waste from 200 HHs therefore for 685 HHs No. of tricycles required will be 685/200 = about 3 nos. As one auto tippers can collect waste from 1000 HHs therefore 03 auto tippers will require catering the rest of the population of proposed group housing.
2. TREATMENT OF WASTE
I. Bio-Degradable waste
Bio-degradable waste will be subjected to organic waste convertor and the compost
will be used as manure.
Horticultural Waste is proposed to be composted and will be used for gardening
purposes.
II. Recyclable wastes
Grass Recycling- The cropped grass will be spread on the green area. It will act as
manure after decomposition.
Recyclable wastes like paper, plastic, metals etc, will be sold off to recyclables.
The solid waste shall be segregated and collected as per the above scheme. These bins will be
emptied into the Garbage Collection Bin of the ground floor. Service provider from housing
society will collect the garbage and waste shall be discharged to main bin of the Group
Housing. The grey and green bins shall be picked up on the instructions of Lucknow Nagar
Nigam for disposal. The service provider carries this waste for recycling and rest to the
municipal solid waste site. The Housing Society management shall engage a vendor & they
will dispose the waste at the proposed site identified by the Lucknow Municipal Corporation.
6.5 NOISE ENVIRONMENT MANAGEMENT
The main source of the noise pollution would be vehicles like four & two wheelers within
premises.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 34
6.6 TRAFFIC MANAGEMENT
Traffic management is the planning implementation and control of transportation services
for achieving the desired objectives and also to reduce the noise level in the project scheme.
Project proponent shall be responsible for managing all parking and safety issues regarding
the use of vehicles inside premises of proposed scheme. To reduce the noise level, it will be
ensured that the traffic movement must be is smooth and horns will not be used within the
parking areas of the scheme. Incoming and outgoing gates will be different, so as to avoid any
traffic congestion due to parking. Plantation of the trees near the paved areas and roads of
the project site will be done for decreasing the air and also the noise pollution level. The
traffic manager and all persons involved with these activities shall do traffic management.
A good control system shall be setup. The following standards shall be maintained for
parking areas:
All vehicles shall have a parking sticker permanently affixed to the driver's
side back seat window.
All vehicles shall be limited to parking in designated spots.
Vehicles shall enter from Entry Gate and leave from Exit Gate.
No vehicle shall be parked in fire tender movement areas.
All vehicle users who disregard policies shall be subjected to fine, or loss of
parking privileges.
Speed Limits
In the proposed project scheme, speed limits are set to provide for the safe movement of
persons and vehicles 20 Kmph on road ways and 10-15 Kmph in parking lots.
6.7 LANDSCAPING & HORTICULTURE
Natural landscaping is also referred to as sustainable landscaping. It stresses the use of
native plants that are beautiful, hardy and that also benefit the local environment. Native
plants are especially good at preventing soil erosion, reducing flooding, sustaining wildlife
and filtering out harmful pollutants in the soil. Natural landscaping offers a way to reduce
the use of chemical pesticides and fertilizers, while introducing natural techniques that are
safer for the long-term health of the community.
Total Landscape Area is = 7630.0 m2
As per MoEF Laws = 1 tree/80 sqm of the total plot area
=50791/80 = 635 nos. trees required
Table 12: Details/ Distribution of Tree Plantation
SHRUBS/ HERBS TO BE PLANTED
Avenue Trees: Alstonia scholaris, Anthocephalus kadam, Araucaria cookii, Azardicta indica,
Bambusa vulgaris, Bauhinia blackeana, Bauhinia purpurea , Cassia fistula, Cassia javanica,
Calistemon lanceolatus, etc.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 35
Shrubs: Acalypha hisipida cat tail, Acalypha w green, Acalypha w red, Acalypha
tricolour, Acocanthera spectibilis, Allamanda nerifolia, Bauhinia accuminata, Bauhinia
tomemtosa, Beloporine guttata, Caesalpinia pulcherrima, Calliandra emarginata, Cassia
biflora, Cassia alata, Cassia laevigata, Clerodendron macrosiphon.
Palms: Fox tail palm, Cycus revoluta, Pheonix slyteris, Champange palm, Royestinia
regia, Raphis palm, Thrinax parviflora, Latania lontaroides, Livistonia rotundifolia,
Washingtonia filifera.
Initially grassing would be done with doob grass including watering and maintenance of the
lawn for 30 days or more till the grass forms a thick lawn. The project proponent has
proposed for landscaping in an area of 7630.0 m2 with ornamental plants and trees to
maintain aesthetic environment in area of the proposed project. The proposed Group
Housing project will have ornamental plants to be planted all over the landscape area.
Plantation of avenue trees by the road side in 0.60 m dia. holes, 1 m deep dug in the ground
shall be done and mixing the soil with decayed farm yard manure. Since the proposed area
does not have any tree, nothing shall be uprooted.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 36
CHAPTER 7: PRESENT ENVIRONMENTAL SCENARIO (AT PROJECT SITE) (I) Ground Water Quality Test Results:
Sampling Site: Project Site Bore Well
Date of Sampling: 22.12.2016
Laboratory Sample code: SPLPL-1598
(II)Ambient Air Quality:
(III) Soil Quality Test Result Laboratory Sample Code: SQ/SPLPL-348; Location= Project Site Centre Laboratory Sample Code: SQ/SPLPL-349; Location= Project side periphery Date of Receipt: 22.12.2016
S.No Parameter SQ1 SQ2 1 pH 8.490 8.425 2 Electrical Conductivity 105.7 55.68 3 Total Organic Carbon % 1.36 0.50 4 Organic Matter % 2.34 0.86 5 Bulk Density (gm/cc) 1.25 1.30 6 Particle Density(gm/cc) 1.86 1.76 7 Phosphous as P2O5 (kg/ha) 0.48 0.32 8 Sulphur (mg/kg) 0.07 0.02 9 Ca + Mg(Mequi./100gm) 28.6 14.2
10 Ca (Me/100 gm Soil) 14.2 7.2 11 Mg (Me/100 gm Soil) 14.4 7.0 12 Moisture (%) 6.248 5.849
S. N.
PARAMETER TESTED UNITS RESULT DESIRABLE LIMITS
MAXIMUM PERMISSIBLE LIMIT
TEST PROTOCOL
(IS 10500:2012) 01 Colour Hazen <5 5.0 15.00 2120 B APHA 22nd
Edition 2012 02 pH Value - 8.222 6.5-8.50 No Relaxation 4500-H+ B,APHA’ 2012 03 Electrical Conductivity µs/cm 441.5 _ _ 2510 B.APHA’ 2012 04 Turbidity NTU 0.0 1.00 5.0 2130 B APHA ’ 2012 05 Total Dissolved Solids mg/L 287 500 2000 2540 D. APHA’ 2012 06 Total Hardness as
CaCO3 mg/L 232 200.0 600 2340 C. APHA’ 22nd
Edition 2012 07 Calcium ion mg/L 40.08 75.0 200 3500 B, APHA’ 2012 08 Magnesium ion mg/L 32.08 30.0 No Relaxation 3500-B, APHA’ 2012 09 Alkalinity as CaCO3 mg/L 220 200.0 600 2320B, APHA’ 2012 10 Chloride as Cl- mg/L 9.99 250.0 1000 4500 –Cl- B, APHA’
2012 11 Sulphate as SO4 mg/L 8.53 200.0 400 4500-SO42- E 2012 12 Nitrate as NO3 mg/L 0.08 45.0 No Relaxation IS 3025 (Part 34) 13 Iron as Fe mg/L 4.34 0.3 No Relaxation 3500 Fe-B APHA’ 2012 14 Fluoride as F- mg/L 0.62 1.0 1.5 4500-F- APHA 2012
S.No Sample Code Date of sampling Location 24 Hourly Concentration(µg/m3)
01. AQ/SPLPL-401 22.12.2016 At project Site PM (10) PM(2.5) SO2 NO2 112.96 40.12 8.23 30.85
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 37
(IV) Surface Water Quality Test Result:
Sampling Site: Pond inside the Project Site Date of Sampling: 22.12.2016 Laboratory Sample code:SPLPL-1599
S. No.
PARAMETER TESTED
UNITS RESULT DESIRABLE LIMITS MAXIMUM PERMISSIBLE LIMIT
TEST PROTOCOL
(IS 10500:2012) 01 Colour Hazen
units <5 5.0 15.00 2120 B APHA 22nd
Edition 2012 02 pH Value - 8.540 6.5-8.50 No Relaxation 4500-H+ B,APHA’
2012 03 Electrical
Conductivity µs/cm 269.2 _ _ 2510 B.APHA’ 2012
04 Turbidity NTU 1.2 1.00 5.0 2130 B APHA ’ 2012 15 TSS mg/L 46.0 2540 D APHA 22ND
Edition 2012 16 O & G mg/L 6.8 5210 B APHA 22nd
Edition 2012 17 COD mg/L 220 5220 B APHA 22nd
Edition 2012 18. BOD mg/L 30.0
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 38
CHAPTER 8: EMERGENCY PREPAREDNESS PLAN
8.1 FIRE FIGHTING
As most of the material and finished products are inflammable, no smoking and no fire will
be allowed. In case of fire, fire extinguisher will be used. Fire extinguishers are put at the
entrance of storage rooms. The Fire Extinguisher System has been provided as per fire safety
plan in all floors of the institute. The phone number of nearest fire service stations has been
displayed at various points and also near the fire extinguishers.
The proposed project is to provide with fire protection arrangements such as Wet Riser
system (as per N.B.C standards), Hose Reel (as per I.S – 3844 standards), Yard Hydrant and
Automatic Sprinkler System in every building. Manual call points, Automatic Detection
System in every building, portable appliance, Exit signs, P. A. System, Mechanical Ventilation,
Smoke extraction system, Pressurization shafts, staircase etc. for fire safely point view.
There is no objection for the construction of residential building as subject to the compliance
of the following fire safety recommendations:
1. Access: It must be ensured that the access roads all around the building must be
kept clear all the time for free movement of fire engines and 4.5 m head clearance shall be
provided. The access internal road shall be provided as per approved plan.
2. Exit Requirements: Exit requirements shall be in accordance with provision as per
National Building Code of India Part – IV (Clause 8.1 to 8.15.1).
(a) Means of escape/exit shall be continuous and unobstructed way of exit travel
from any point in the building to a public way. All exit doorways shall open towards
means of escape that is away from, but shall not obstruct the travel along any exit. No door
when opened shall reduce the required width of staircase/corridor/passage way.
(b) All exit and exit way marking signs, emergency lights shall be on separate
circuit/laid in separate conduit, exit signs must be illuminated and wired to
independent circuit supplied by alternate source of power supply. The wiring and all
accessories in the electrical circuit shall be fire resistant and low smoke material duly ISI
marked.
3. Material for construction: The material used for construction of the building shall
be of non-combustible. The interior finish materials shall be of very low flame spread ability,
i.e. Class-I. All the fabric used for seats, curtain, covering on sidewall, matting carpeting etc.
shall also have Class-I rating as prescribed in NBC part-IV.
4. Compartmentation: The building shall be suitably compartmentalized so that the
fire/smoke remain confined to the area where fire incidents has occurred and mechanically
exhausted as approved in the meeting, so smoke does not spread to the remaining part of the
building.
The services, standby generator, store etc. must be segregated from other by erecting
fire-resisting wall of not less than 2 hours rating. Each of the compartments must be
individually ventilated and the opening for entry into each of these compartments must be
fitted with self-closing fire/smoke check doors of not less than one hour fire rating fitted
with magnetic latches.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 39
All electric cables shall be laid in separate shafts shall be sealed at every floor with fire
resisting material of similar rating. The partition wall in between and all around the shafts
shall also be of minimum two hours fire rating.
Under no circumstances, two services shall pass through the same shaft, i.e. separate shaft be
used for different purpose.
The entry to the staircase from all levels shall be segregated with a self-closing fire/smoke
check door of not less than 1 hour fire rating. All vertical and horizontal opening at each floor
level in entire building shall be sealed properly with the non-combustible material.
Wherever false ceiling/suspended ceiling is provided, the same shall be of non-combustible
in nature and that the compartmentation shall be extended up to ceiling level.
5. Ventilation: The building shall be provided with the ventilation strictly in
accordance with Part-VIII Section-I and Clause D-1.6 of Part IV of National Building Code of
India Mechanical ventilation system having interlocking arrangements as well as upper floor
also. Extractor system shall be designed to permit 30 air changes per hour in case of fire in
basement. The smoke extraction system shall be designed as per NBC Part-IV and approved
by the department.
6. Air Conditioning System: Air conditioning system shall conform to Section-3 Part-
VIII and Clause D-1.17 of Part-IV National Building code of India 1983. Following points shall
be ensured.
All ducting shall be constructed of substantial gauge metal conforming to IS: 655. Air duct
serving main floor areas, corridors etc. shall not pass through the staircases enclosures.
Automatic fire dampers shall be provided in the ducts at the inlets of the fresh air and
return air of each compartment/floor.
Automatic fire dampers shall be closed automatically upon operation of a detector
sprinkler.
The air ducts for every floor/compartment shall be separated. In no way inter-connected
with the ducting of any other compartment
Under no circumstances, plenum shall be used as “Return Air Passage” for air
conditioning purposes.
7. Essential Emergency Electrical Services: Separate electrical circuits to feed
emergency services such as fire fighting pumps, lifts, staircase and corridor lighting blowers,
panel and such a smoke venting and signage circuit shall be laid in separate conduit so that
fire in one circuit will not affect the others. Master switches controlling essential services
circuits shall be clearly labeled. The electrical wiring shall be provided in metal conduits.
MCBs and ELCB shall be installed. The electrical services shall be strictly in accordance to
Clause D.1.12 of Appendix-‘D’ of NBC Part-IV fire resisting cables shall be used.
Power supply cables and the ducting shall not be taken through the staircase or any
passage way used as an escape route. All the cables shall be only of Fire Resistant Low
Smoke type.
8. Emergency Power Supply: The standby electric generator shall be installed of
adequate capacity to supply power to staircase and corridor lighting circuit, lifts, exit signs
and fire pump in case of failure of normal electric supply. The generator shall be capable of
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 40
taking starting current of all the machines and circuits stated above simultaneously and
must be automatic in action.
9. Static Water Tank: The underground water storage tank of the adequate quantity
shall be provided. The replenishment through bore well or from the town main shall be
ensured. This shall conform to the requirements given in National Building Code of India
Part-IV. An additional overhead tank as proposed on the terrace shall be provided for fire-
fighting as an alternative source of water supply. The underground water storage tank shall
be approachable by the fire engine.
10. Stationary Fire Pump: Two electrically driven pumps – one each for Wet Riser and
sprinkler system with 70 meters head shall be provided for wet riser and sprinkler system
so as to give adequate pressure of 3.5 kg/cm2 at the farthest point. The standby diesel engine
driven pump of similar capacity and the two-jockey pumps – one each for wet riser and
sprinkler system shall be installed. Al the pumps shall be automatic in operation shall be
provided. The pumps shall have positive suction.
11. Automatic Sprinkler System: The system shall be installed in entire building in
accordance with BIS 15105/2002. Flow alarm switch/gang shall be incorporated in the
installation for giving proper indication/sound. The pressure gauge shall also be provided
near the testing facility. The entire system including pump capacity & head, size of pipe
network, housing control panel etc. shall be provided in accordance to relevant code. Fire
service inlet shall also be provided at ground floor level. Testing/flashing facilities shall be
provided at each floor. The wielding shall not be done for the pipe less than 50 mm diameter.
12. Wet Riser: The wet riser system shall be provided in the building as per NBC -05
standards.
13. Hose Boxes, Fire Hose and Branch Pipe: Hose boxes of suitable dimension shall be
provided near each internal hydrant. Its design shall be such that it can be readily opened in
an emergency.
Each box shall contain two lengths of 63 mm diameter, 15 m length, rubber lined delivery
hoses conforming to IS:636 complete with 63 mm instantaneous coupling conforming to
IS:903 and short branch pipe conforming to IS:903 with a nozzle of 16 mm diameter.
14. Hose Reel: A hose reel near each internal hydrant containing 30 m of length of 20mm
bore terminating into a shut-off nozzle of 6.5 mm outlet connected directly to riser shall be
provided. This will conform to IS: 3844.
15. Automatic Detection System: Automatic fire detection (smoke/heat) shall be provided
in all the areas of the building and shall conform to IS: 2189/1999.
16. Portable Fire Extinguishers: The portable fire extinguishers of water CO2 type and
CO2 type ISI mark shall be provided as marked on the plans. The number of the fire
extinguishers may have to be increased later when the layout of the partition etc. is known.
All the fire extinguishers will be installed and maintained in accordance with IS: 2190-1992.
17. Public Address System: The public address system shall be provided having loud
speakers on each floor level at strategic location. The microphone, amplifier and control
switches of public address system shall be installed in the fire control room.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 41
18. Lighting Protection: The lighting protection shall be provided in the building as per IS:
2309.
19. Intercommunication System: An emergency inter-communication system shall be
provided in the entire complex. The instrument shall be provided in the common areas on
each floor.
20. Yard Hydrants: Yard hydrants shall be provided in the building as per BIS
specifications.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 42
CHAPTER 9: ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
On the basis of information provided by the Project proponent and the other data procured
from the Government Agencies, Census Report, IMD etc., and the data generated by the
Consultants and analysis of generated information, the following generalized conclusions can
be drawn.
1. In the proposed project, construction will be developed at plot area of 50791.0 m2.
2. UPSEB will provide necessary expected power demand of 5397.9 KVA to proposed group
housing. During power failure 1 x 300 KVA & 1 x 400 KVA DG Set shall be provided.
3. The water demand shall be 320.0 KLD managed by using water through borewell.
4. The total fresh water requirement would be 234.9 KLD. Total waste water of 242.0 i.e
total black (75.0 KLD) and grey water (167.0KLD) shall be treated in the 300 KLD Sewage
Treatment Plant based on FAB Technology.
5. The rain water harvesting will improve ground water quality. 08 (Eight) number of rain
water harvesting pits will be provided at proposed site to recharge the ground water.
6. Ambient air quality shall remain within the prescribed standards. The recognized
sources of air pollution in the area are transport system. Efficient Traffic Management
shall be regularized within the project to control air and noise pollution.
7. Noise level shall be maintained. For traffic noise, plantation along the traffic route shall
be provided to act as a noise barrier.
8. The 2268.0 Kg/Day generated solid waste shall be segregated at source and managed
through Lucknow Municipal Corporation at designated site.
9. At proposed project, landscape will be developed in an area covering 7630.0 m2 of the
ground with various shrubs & trees planted.
The site is advantageous for development of this project due to the following reasons:
1. The site has good provision for drainage facilities.
2. The climatic conditions are suitable.
3. The connectivity of the site by rail, road and air is very much ensured keeping in
view the existing and proposed development.
4. The easy availability of nearby residential land community facilities.
5. The landscape area along with storm water drainage and STP plant will ensure
purification of waste water respectively.
6. Surface parking provision will reduce generation of dust and air pollution within
project premises
7. Proposed site is a prominent place where an uninterrupted power supply would be
ensured.
The site is strategic for developing proposed residential building of Group Housing
“Multistory Building, Row Houses & Commercial Spaces” as part of the Development
Plan 2021.
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 43
CHAPTER 10: DISCLOSURE OF CONSULTANT
The consultants engaged for the preparation of EIA/EMP of the proposed project are M/s
SAWEN Consultancy Services Pvt. Ltd. The information about the company is as follows:
INTRODUCTION
SAWEN has provided a vast range of consultancy services; Environment Impact Assessment
Studies (EIA), Environment Management Plans (EMP), Environmental Training &
Education, R&R Survey. Environmental Audit, Bio diversity studies, Socio Economic Studies,
Mine Plans, Risk Assessment and Disaster Management, Solid Waste Management, Ground
Water Studies, Rain Water Harvesting Study, water shed management studies, water &
effluent management studies, water balance studies, land use mapping green belt designing,
zonal mapping etc. to all sectors of economy notably Government Sector, Semi –Government
Sector, Corporate Sector and reputed Private Sector.
SAWEN is a multi disciplinary professionally managed consultancy group providing
consultancy on all aspects related to Environment & Pollution control and undertake study
of environmental parameters, through two complementary companies SAWEN Consultancy
Services & SAWEN Projects & Laboratories Pvt. Ltd
Legal Status of Organization
Pvt. Ltd. Company
Date of Registration/ Incorporation
SAWEN Consultancy Services was established in the year 1993.
UTTAR PRADESH POLLUTION CONTROL BOARD REGISTRATION NO.:
G35962/21/Paryavaran/S/1/99 dated 07 .09.1999
An ISO 9001:2008 Certified Quality Standard Company
Certificate No.: RQ91/JA/254.
Certificate Issue Date: 16.08.2011
EIA CONSULTANTS ACCREDITATION SCHEME (QCI-NABET) REGISTRATION NO.: 118
NABL ACCREDITATION CERTIFICATION NO.: T-2091
SERVICES & EXPERTISE
We are monitoring environmental impact & providing services of pollution control systems
to Institution, Thermal Power Plant, New Construction projects, Highways, Township &
Area Development,
Mineral Beneficiation Plant, Chemical Fertilizers, Municipalities, UPSLRP, UPDASP, NHAI,
UPSHA, Cluster mining, Mine- surface and underground for all minerals & metals, Polymer,
distilleries, sugar industry, Leather, Petrochemical, Electroplating & other polluting
industries.
So far the following EIA/ EMP projects have been executed
Sector Numbers
Building & Large Construction 51
Township & Area Development 05
Thermal Power Plants 03
Highways 15
Sugar industry 13
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 44
Mineral Beneficiation 01
Chemical Fertilizers 04
Pulp & Paper Industry 03
Leather Industry 03
Textile Industries 03
Airport 04
Electroplating & Metal Coating 04
Food Processing 04
Minor Mineral Mining 200
Major Mineral Mining 60
PERSONNEL
SAWEN is a group backed by the vision of experienced and dedicated scientists, engineers,
and management professionals having expertise in the field of Environment, Civil,
Architecture, Structural Engineering, Chemical Engineering, Agricultural, Horticultural, &
Rural Development & Road Rehabilitation Projects.
EIA COORDINATORS
S. No. Name
1 Dr. Rajesh Kumar Singh
M.Sc.(Chem.)
Ph.D. (Chem.)
2 Dr. Dharam Raj Singh
M.Sc. (Chem.),
Ph.D (Chem.)
3 Dr. Arpita Sinha
M.Sc (Env. Science),
Ph. D (Env. Science),
PGD Env. Protection Law
NET-Lecturership
4 Pankaj Pande
M.Sc (Geology)
FUNCTIONAL AREA EXPERTS
S. No. Name Functional Area/s Applied for (as
per abbv. given below)
In-house expert/s
1 Dr. Rajesh Kumar Singh
Air Pollution Control
Water Pollution Control
Air Quality Modeling
Risk & Hazard management
2 Dr. Dharam Raj Singh Solid & Hazardous Waste Management
Conceptual Plan - Multistory Building, Row Houses & Commercial Space at Gram- Aurangabad Khalsa, Tehsil & Dist.- Lucknow, Uttar Pradesh
Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow Page | 45
S. No. Name Functional Area/s Applied for (as
per abbv. given below)
3 Dr. Arpita Sinha
Solid & Hazardous Waste Management
Noise & Vibration
Soil Science
Ecology & Biodiversity
4 Mr. Satyendra Singh Socio-Economic
5 Arch. Arvind Gupta Land Use
8 Mr. Sanjay Srivastava Socio-Economic
Empanelled expert
9 Rama Shanker Shukla Land Use
TESTING LABORATORY
Name Designation Academic and Professional
Qualifications*
Experience
related to
present work
(in years)
Dr. R. K. Singh Managing
Director
Ph. D. Chemistry (Organic)
M. Sc. Chemistry (Organic) 17 years
Dr. Arpita Sinha
Management
Representative/
Quality Manager
Ph. D Environmental Sciences
M. Sc Environmental Sciences
P.G. Diploma (Environmental
Protection Law)
08 years
Mr. S. K. Singh Deputy Quality
Manager
LL.B.
B.SC. (Zoology & Botany)
P.G. Diploma (Environmental
Protection Law)
Diploma in Rural Development
14 years
Mrs. Kalpana
Singh
Lab Incharge /
Technical
Manager
M. Sc Chemistry (Organic)
B. Sc (Chemistry & Botany) 20 years
Mr. Anurag
Singh
Field Leader
Monitoring
B. Sc (Chemistry & Botany)
02 Years
Mr. Vikas
Thakur Field Leader
PCM Intermediate 05 Years
Mr. Pramod
Tiwari Lab Chemist
B. Sc (Chemistry & Botany) 05 Years
Ms. Anjali
Mishra
Environment
officer
P.G. Diploma (Environmental
Protection Law)
B.Tech.(Biotechnology)
04 Years
-End of Conceptual Plan