benefit cost analysis and public sector economics
TRANSCRIPT
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
1
CHAPTER 9
Benefit Cost Analysis and Public Sector Economics
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 2
9.1 Public Sector Projects
• Public Sector:• Ownership – by citizens(the public)
• Public Sector Projects:• Provide needed services to the public with “no profit”
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 3
Types of Projects
• Hospitals• Parks and recreation facilities• Highways, dams, bridges• Courts, schools, prisons• Public housing• Many other types
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economics (KHU, 2015) 4
Characteristics – Compared
Characteristic Public Sector Private Sector
Size of Investment
Larger Some Large; medium to small
Life Estimates Quite Long: 30-50 years
Shorter:2-25 years
Annual Cash Flow Estimates
No Profit: costs and benefits
Revenues –profit cost estimates
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 5
Estimating for Public Projects: Costs
• Basic elements for public projects:• Costs
• Construction, operations, maintenance less any salvage values• Initial costs are fairly well known• Future O&M are less known and must be estimated
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 6
Estimating: Benefits
• BENEFITS to the public (users) must be estimated in terms of periodic dollar values• Very difficult to do• Benefits = the advantages to the public stated in $$• Owners – generally the public
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 7
Estimating: Disbenefits
• Disbenefits• Expected undesirable (negative) consequences to the owners (public)• Assuming the project is undertaken• May be indirect economic disadvantages to the public• Very hard to estimate and convert to $ amounts
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 8
General Principle
• For public projects we find:
It is very difficult to estimate and reach agreement on the economic impacts of
benefits and disbenefits for public sector projects.
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economics (KHU, 2015) 9
Funding Sources – Compared
Characteristic Public Sector Private SectorFunding Taxes, fees,
bonds, private funds
Sale of new stock, bonds, loans
Interest Rate Tends to be lower
Higher: At market cost
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 10
Funding Public Projects
• Generally low interest charges• Public entities do not pay taxes• Project investments basically backed by public agencies• Cost-sharing arrangements often exist• Less perceived risk with public projects
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 11
Determination of an Interest Rate
• Determined differently than in the private sector• Called the social discount rate• For Governmental Projects(Korea), a current working rate (2013) is 5.5% per year
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economics (KHU, 2015) 12
Additional Comparisons
Characteristic Public Sector Private Sector
Selection criteria
Multiple Rate of return or present value
Environment of the evaluation
Political arena(debated,
pressure groups)
Primarily economic
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 13
Selection Process
• Not as “clean” as in the private sector• Involves interest and pressure groups• Often draws media attention• Involves many different viewpoints
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 14
9.2 B/C Analysis – Single Project
• Historical Point•B/C analysis philosophy was instituted and promoted by the Flood Control Act of 1936•Introduced to promote a sense of objectivity in an analysis
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 15
B/C Formulations
• Assignable life, N - years• Estimate costs ($)• Estimate benefits in ($)• Estimate disbenefits in ($)• Assign an interest rate – i (%/year)
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 16
B/C Formulations
• Then convert all amounts to either a• Present Worth – PW(i%)• Annual Worth – AW(i%)• Then calculate a B/C ratio in one of three ways
( )/(cos )
PW benefitsB CPW ts
=( )(cos )
AW benefitsAW ts
=( )
(cos )FW benefitsFW ts
=
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 17
Notes Regarding Signs
• By convention:• Revenues are assigned (+) signs• Costs are assigned (+) signs• Salvage values are subtracted from costs• Disbenefit values are subtracted from benefits
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 18
Decision Rule
• IF B/C ratio (=>) 1.00• Economically accept the alternative
• IF B/C ratio (<) 1.00, economically reject the alternativev IF B/C ratio “close” to 1.00, then intangible factors may sway the decision to accept or reject
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 19
Conventional B/C Ratio
• The conventional B/C Ratio is:
- disbenefits/ Benefits B DB CCosts C
-= =
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 20
Modified B/C Ratio
• Costs will be mainly initial investment• Subtracts the maintenance and operations costs in the numerator
modifiedBenefits - disbenefits-M&O costs/
CostsB C =
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 21
Convention vs. Modified?
• It makes no difference which approach is used• However, the ratio values will differ (magnitude)• But, the absolute (accept/reject) decision will be the same
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 22
Example 9.2
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 23
Profitability index(PI)
• Private perspective• PI = PW of NCF / PW of initial investment
Decision Guidelines of PI Analysis
If PI ≥ 1.0, project is economicallyjustified at discount rate appliedIf PI < 1.0, project is not economicallyacceptable
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 24
Example 9.3
• PW of investment=$80.02• PW of benefits=$158.23• PW of costs=$26.8• PW of disbenefits=$80.12
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 25
9.3 & 9.4 Incremental B/C for Multiple Projects
• Select from three or more mutually exclusive alternatives• Same approach as that in Chapter 8, Section 8.6• Remember, the Do Nothing alternative always exists and should be evaluated as an alternative.
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 26
Steps for Multiple Incremental Analysis
1. Using either PW or AW, determine the total equivalent cost for all options. If unequal lives, apply AW
2. Create the rankings based upon lowest to highest total cost of the alternatives
3. Calculate B/C for each alternative and eliminate all with B/C < 1.0
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 27
Steps – Continued
4. The lowest-cost option is the first Defender and the next-higher cost alternative is the first Challenger.Compute the B/C ratio on the increment.If ∆ B/C < 1, eliminate the Challenger, else (∆ B/C > 1) eliminate the Defender.Current winner becomes new Defender
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 28
5. Compare the new Defender to the next-higher-cost Challenger and repeat the analysis.
6. Continue through the alternative until there are no more Challengers.
7. The last “champion” is the winner.
Steps – Continued
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.4 Incremental B/C
One of the two designs must be selected using i = 5% and B/C ratioAlternative A B
Construction cost, $ 10M 15MM&O costs, $/year 35,000 55,000Usage copay, $/year 450,000 200,000Life, years 30 30
29
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.4
30
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.6
31
• Social rate=7%, 8-year• AW of total cost = First cost(A/P,7%,8)+entrance fee
reduction
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
B/C Analysis of Independent Projects
v Independent projects comparison does not require incremental analysis
v Compare each alternative’s overall B/C with DN option
+ No budget limit: Accept all alternatives with B/C ≥ 1.0
+ Budget limit specified: capital budgeting problem; selection follows different procedure (discussed in chapter 12)
32
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economics (KHU, 2015)
Service sector projects primarily involve intangibles, not physical facilities; examples include health care, security programs, credit card services, etc.
Cost-effectiveness analysis (CEA) combines monetary cost estimates with non-monetary benefit estimates to calculate the
Cost-effectiveness ratio (CER)
Equivalent total costs (C)Total effectiveness measure (E)CER =
9.5 Service sector project & Cost-Effectiveness Analysis
33
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
CER Analysis for Independent Projects
Procedure is as follows:(1) Determine equivalent total cost C, total effectiveness measure E and CER(2) Order projects by smallest to largest CER(3) Determine cumulative cost of projects and compare to budget limit b(4) Fund all projects such that b is not exceeded
34
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.8
35
CER = Program cost per person (C)/ Patents per graduate (E)
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.8
36
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
CER Analysis for M. E. Projects
• Order projects by smallest to largest E• Without budget limit, choose the alternative
with the highest effectiveness measure, E.• With budget limit, the concept of Dominance is
utilized
Dominance occurs when(∆C/E)challenger-defender < (C/E)defender
• When dominance exists, eliminate defender. Otherwise, both alternatives remain
37
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Selection Procedure(1) Order alternatives smallest to largest by effectiveness measure E(2) Calculate CER for first alternative (defender)(3) Calculate incremental cost (∆C), effectiveness (∆E), and incremental measure
∆C/E for challenger (next higher E measure)(4) If ∆C/Echallenger < C/Edefender , challenger becomes defender (dominance);
otherwise, no dominance is present and both alternatives are retained(5) Dominance present: Repeat steps (3) and (4) with new defender & challenger
Dominance not present: Current challenger becomes new defender against next challenger, but old defender remains viable
(6) Continue steps (3) through (5) until only 1 alternative remains or only non-dominated alternatives remain
(7) Apply budget limit or other criteria to determine which of remaining non-dominated alternatives can be funded
38
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example
39
The effectiveness measure (E) is wins per person. From the cost and effectiveness values shown, determine which alternative to select.
Cost (C) Effectiveness (E) CERProgram $/person wins/person $/win
A 2200 4 550B 1400 2 700C 6860 7 980
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016) 40
Example
Order programs according to increasing effectiveness measure E
Cost (C) Effectiveness (E) CERProgram $/person wins/person $/win
B 1,400 2 700A 2,200 4 550C 6,860 7 980
Solution:
C/EB = 1400/2 = 700A vs. B: ∆C/E = (2200 – 1400)/(4 – 2) = 400 Dominance; eliminate BC vs. A: ∆C/E = (6860 – 2200)/(7 – 4) = 1553 No dominance; retain C
Must use other criteria to select either A or C
Copyright © Professor Deok-Joo Lee(Kyunghee University, Korea), Permission required for reproduction or display.
Engineering Economy (2016)
Example 9.9
41
5 vs. 4: ∆C/E = (5500 – 2500)/(2.9 – 2.1) = 3750 > 1190 No dominance; retain both2 vs. 5: ∆C/E = (4500 – 5500)/(3.1 – 2.9) = - 5000 < 1897 Dominance; eliminate 52 vs. 4: ∆C/E = (4500 – 2500)/(3.1 – 2.2) = 2000 >1190 No dominance; retain both
Must use other criteria to select either 2 or 4