![Page 1: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/1.jpg)
Best Practices for Exceeding Project Goalsand Reducing Risk on Construction Projects
Presented by:Robyn Minter SmyersAlan S. RitchieHeather A. BartziErin Luke
![Page 2: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/2.jpg)
2
Presentation Team
Robyn Minter SmyersPartner, Thompson [email protected]
Alan RitchiePartner, Thompson [email protected]
Heather BartziPartner, Thompson [email protected]
Erin LukeSenior Associate, Thompson [email protected]
![Page 3: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/3.jpg)
3
Beginning of Design and ConstructionProject• Ideal Process
• Plenty of Time
• Ample Budget
• Project Goals ClearlyIdentified
• Competitive Selection ofDesigner and Constructor
• Abundant Information
![Page 4: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/4.jpg)
4
But, IRL…
• Starting Tomorrow
• Way Over Budget
• Unresponsive Proposals
• Scope of Project is a
Moving Target
Result: Do what you did for the last project with the
same design and construction team.
![Page 5: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/5.jpg)
5
• Late Completion
• Over-Budget
• Bad Fit, No Cooperation Among Team
• Disappointment
• Unhappy Stakeholders
What Happens?
Basically…
![Page 6: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/6.jpg)
![Page 7: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/7.jpg)
7
The Fix
• Effectively Plan the ProjectEarly
• Align Goals and AddressProject Risks and Challenges
• Select Appropriate ProjectDelivery Method
• Use Good RFP/RFQ forSelection of Designers andConstructors
![Page 8: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/8.jpg)
8
Best Practices of Construction Projects:Front End Planning and Process• We will discuss in this seminar:
• Review and prioritize critical projectparameters
• Identify constraints that limit possibledelivery options
• Review project delivery methodologies
• Compare options based upon stakeholderpriorities
• Identify special tools to enhance projectdelivery success
![Page 9: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/9.jpg)
9
Address Key Questions
• What are the critical project parameters?
• Absolute constraints that limit options?
• What is owner’s need for control vs. shifting risk todesigner and/or constructor?
• Type of project? (e.g., manufacturing,office building, infrastructure)
• Other concerns? (e.g., real estate,environmental, health & safety)
![Page 10: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/10.jpg)
10
Roles & Responsibilities Of Stakeholders
• Management Profile:In-House Expertise &Resources
• Approach to DesignManagement
• Tolerance for Risk
• Relationship Network
![Page 11: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/11.jpg)
11
Project Management – The Problem
• Project delivery system oftenselected without objective analysis…
• The way we always do it
• What the Architect/Engineer wanted
• The form the lawyer used
• LET’S DO WHAT’S NEW AND EXCITING!!!
• … and not tailored to solve project specific issues.
• Can lead to project failure—time, scope and cost
![Page 12: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/12.jpg)
12
What is Project Delivery?
• Business and legal structure that identifies andaligns:
• Project Goals
• Project Requirements
• Project Processes
• Legal Structures
• Risk Mitigation
![Page 13: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/13.jpg)
Budget
Schedule
Changes
Legal Structure
Process and Risk
Management
Safety
Quality
Aesthetics
![Page 14: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/14.jpg)
14
Acceleration of Detail/Decisions into Design
![Page 15: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/15.jpg)
15
Project Delivery Methodologies
• Multiple Prime Contracting
• Design-Bid-Build (General Contractor)
• Construction Management
• As Advisor – Not utilized often
• At-Risk (As Constructor)
• Design-Build
• Bridging Design-Build
• Integrated Project Delivery
![Page 16: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/16.jpg)
16
Design/Bid/Build (General Contractor)Approach
A/E Owner
General
Contractor
SUB SUB SUB
Consultant Consultant Consultant
Design Construction
PR
IC
E
![Page 17: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/17.jpg)
17
Design Construction
Construction Manager at Risk Approach
A/E OwnerConstruction
Manager
SUB SUB SUB
Consultant Consultant Consultant
+ Precon
PR
IC
E
![Page 18: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/18.jpg)
18
Bridging Design/Build Approach
Owner
Design/
Builder
SUB
Consultant
A/E
Consultant Consultant
SUB SUB
Criteria
A/E
Consultant Consultant Consultant
![Page 19: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/19.jpg)
19
Project Compensation Models
• Lump Sum, Stipulated Price
• Cost of the Work – No GMP
• Cost of the Work with GMP
• Target Price
![Page 20: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/20.jpg)
20
Basis of Design and PricingOwner’s Basis
of Design
Design-
Build
Bridging
Design-
Build
CM @
Risk
General
Contractor
(D-B-B)
Complete
Construction
Documents
Performance
Requirements
35% to 95%
Construction
Documents
Schematic orDesign
DevelopmentDocuments
![Page 21: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/21.jpg)
21
Lump Sum vs. GMP Approach
GMP ContractLump Sum Contract
Lump Sum
Fee
GCs
Contingency
GMP
Fee
GCs
Cost
of the
Work
Final
Cost
of the
Work
Savings
![Page 22: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/22.jpg)
22
Lump Sum vs. GMP Approach
GMP ContractLump Sum Contract
Lump Sum
Fee
GCs
Contingency
GMP
Fee
GCs
Cost
of the
Work
Final
Cost
of the
Work
Loss
![Page 23: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/23.jpg)
23
Target Pricing
![Page 24: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/24.jpg)
24
Selection of Design and Construction Team
Set Team
• Facilities
• Finance
• Management
• Legal
• EHS
• Owner’s Rep
Identify Goals
• Uses & Needs
• Budget & Contingency
• Schedule & Milestones
• What’s Important
• What’s Unique
![Page 25: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/25.jpg)
25
Good Paperwork – RFQ / RFP
Uniform Requests
=
Uniform Submissions
![Page 26: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/26.jpg)
26
Required Submissions
• Firm Profile
• Insurance and Bonding
• Litigation History
• Financial Strength
• References
• Approach / Method
• Project Experience
• Current Workload
• Key Personnel / Staffing
• Agreement Comments
• Pricing Proposal
• Value Add Ideas
![Page 27: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/27.jpg)
27
Due Diligence Review
• Preliminary Research
• Firm Interviews
• Contact References
• Assemble Information
• Discuss and Evaluate
• Teamwork v. Price
![Page 28: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/28.jpg)
28
Project Partnering
• Communication Protocols
• ID Key Stakeholders
• Address Concerns
• Collaboration
• Team Work
• Project Success!
![Page 29: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/29.jpg)
29
• Project Sponsorship/Resources
• Project Delivery
• Facilitated GMP Process
• Contingency Management
• Insurance Review
• Dispute Resolution Issues
Tools to Enhance Project Success
![Page 30: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/30.jpg)
![Page 31: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/31.jpg)
Yippee-
Kai-Yay!
![Page 32: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/32.jpg)
32
Questions?
Robyn Minter SmyersPartner, Thompson [email protected]
Alan RitchiePartner, Thompson [email protected]
Heather BartziPartner, Thompson [email protected]
Erin LukeSenior Associate, Thompson [email protected]
![Page 33: Best Practices for Exceeding Project Goals and Reducing Risk on … · 2016-10-24 · 2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine 216.566.5830 Robyn.Smyers@ThompsonHine.com](https://reader033.vdocument.in/reader033/viewer/2022050115/5f4c183f23b16b6b6c69e2df/html5/thumbnails/33.jpg)
33
This presentation may be reproduced, in whole or in part, with the prior permission of Thompson Hine LLP and acknowledgement of itssource and copyright. This publication is intended to inform clients about legal matters of current interest. It is not intended as legal advice.Readers should not act upon the information contained in it without professional counsel.