beyond 3d printing – new demand on electric infrastructure

16
Mark Stephens, PE, CEM, CP EnMS Senior Project Manager Advanced Manufacturing Workshop: Challenges for Tomorrow, Solutions Today June 4, 2014 Beyond 3D printing – new demand on electric infrastructure

Upload: tranphuc

Post on 29-Dec-2016

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Beyond 3D printing – new demand on electric infrastructure

Mark Stephens, PE, CEM, CP EnMS Senior Project Manager

Advanced Manufacturing Workshop:

Challenges for Tomorrow, Solutions Today June 4, 2014

Beyond 3D printing – new demand on electric infrastructure

Page 2: Beyond 3D printing – new demand on electric infrastructure

2 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Why Focus on 3D Printing?

•  3D Printing (Additive Manufacturing) is the most commonly recognizable piece of technology constituting advanced manufacturing.

•  10 Years ago, digital smart metering was recognized as smart grid itself (which was not true and often misleading).

• Similarly, we need to understand Additive Manufacturing as one of the first bricks of in which we will build and operate the smart factory.

Recent Collaboration with America Makes

Page 3: Beyond 3D printing – new demand on electric infrastructure

3 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Previous Successful Collaborative Efforts • EPRI has traditionally led research to

understand the customer end-use equipment for the utility sector: –  Base line Power Quality Requirements –  Power Requirements, and Energy

Intensity •  This work as has led End-Users, OEMs, and

Consultants need to better understand the PQ environment and utilize robust equipment and power system designs.

•  This research has also led to new Industry Standards (i.e. SEMI F47), improved equipment designs through collaboration, and important insights for everyone involved along the way.

Semiconductor Processing Equipment

CNC Machine

Tools

Chiller Systems

Food Processing

Plastic Extrusion

Page 4: Beyond 3D printing – new demand on electric infrastructure

4 © 2014 Electric Power Research Institute, Inc. All rights reserved.

SEMI F47-0706

Page 5: Beyond 3D printing – new demand on electric infrastructure

5 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Research Questions

• Power Quality & Reliability – How will these loads be different

from a PQ Standpoint? – What will PQ Sensitivities and

Contributions be? – What mitigation strategies will be

required?

•  Power & Energy – What will these loads look like from a

power standpoint? – What is the energy intensity of

additive manufacturing in comparison with traditional methods?

3D Printing Mfr Site(s)

Collaborators in Answering These Questions

EPRI Member Utilities

Page 6: Beyond 3D printing – new demand on electric infrastructure

6 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Injection Molding & Fused Deposition Modeling • Part cycle time in seconds or minutes • Hydraulic and Electronic motor drives (AC or DC) • Resistive SCR Heaters for Melt Pipe and Mold • Requires Cooling Water from local chiller or plant system •  PQ Performance Understood •  Power Profile and Energy Intensity Understood

• Part cycle time in minutes, hours, or days • Stepper Motor Drives • Resistive SCR Heaters for chamber • Requires compressed air & vacuum

(from Plant air or via internal pumps) •  PQ Performance Not Well Understood •  Power Profile and Energy Intensity Not Well understood

Injection Molding

FDM

Page 7: Beyond 3D printing – new demand on electric infrastructure

7 © 2014 Electric Power Research Institute, Inc. All rights reserved.

CNC (Subtractive) & Selective Laser Sintering (Additive)

• Part cycle time in seconds or minutes •  Multi-Axis Servo Drive •  Spindle Drive •  Requires Compressed Air •  PQ Performance Understood •  Power Profile and Energy Intensity Understood

SLS •  Part cycle time in minutes, hours, or days •  Stepper Motor Drives •  Laser System with Mirrors •  May require local chiller •  PQ Performance Not Well Understood •  Power Profile and Energy Intensity Not Well understood

CNC

Page 8: Beyond 3D printing – new demand on electric infrastructure

8 © 2014 Electric Power Research Institute, Inc. All rights reserved.

PQ Tests: Voltage Sag Tests

• Completed: – America Makes:

• FDM Machine • SLS Machine

– Confidential Manufacturer: • FDM Machine

• Planned in June 2014: – ORNL MDF

• Electron Beam Melting

• SLS Machine

EPRI & FirstEnergy Performing Voltage Sag Testing

At America Makes

Page 9: Beyond 3D printing – new demand on electric infrastructure

9 © 2014 Electric Power Research Institute, Inc. All rights reserved.

SLS Machine Test Result Excerpts… • No UPS in system design • Machine does not meet SEMI F47

• Estimated Shutdowns/Year* per based on plant location – Transmission ~ 6.6 – Sub T ~ 7.0 – Distribution ~ 11.6

• EPRI indentified simple improvements that will make the machine more robust

0% 10% 20% 30% 40% 50% 60% 70% 80% 90%

0 20 40 60

% N

omin

al V

olta

ge

Voltage Sag Duration (Cycles)

SLA Dropout

SEMI F47

* Based on findings from Transmission–Distribution Power Quality Report (TPQ-DPQ III) , EPRI May 2014

Page 10: Beyond 3D printing – new demand on electric infrastructure

10 © 2014 Electric Power Research Institute, Inc. All rights reserved.

FDM Machine Test Excerpts… •  At manufacturing site, FDM machines

contain both an internal UPS and are fed from an external 80kVA UPS.

•  This finding was curious until EPRI Conducted voltage sag testing of the machine downstream of the 80kVA UPS.

•  Machine was robust to voltage sags and found to meet SEMI F47 and IEC 61000-4-34

•  However, machine was found to go into a shutdown mode for any interruption 2 seconds and longer even when it could have continued powering unit for seconds longer –  Coincides with utility recloser timing on

the faulted feeder •  EPRI will work with OEM to recommend

increasing the timing past 2 seconds as the default to work in harmony with the utility power systems.

Faulted Feeder “A”

Adjacent Feeder “B”

Line to Ground

FaultProtectiveRelays

(reclosers)

Subs

tatio

n B

us

TD 1 TD 2

Initial Fault

Reclose Attempt 2

TD 3

Reclose Attempt 3

Reclose Attempt 1

TimeR

MS

Volta

ge

TD 1 TD 2

From Initial Fault Reclose Attempt 2

TD 3

Reclose Attempt 3

Reclose Attempt 1

Sag Event Sag Event Sag Event Sag Event

Time

RM

S Vo

ltage

Adjacent Feeder “B”

Faulted Feeder “A”

Page 11: Beyond 3D printing – new demand on electric infrastructure

11 © 2014 Electric Power Research Institute, Inc. All rights reserved.

FDM Machine Test Excerpts…

•  Testing at America Makes revealed the FDM machine continued to run, during voltage sags, but there was product deformation.

Page 12: Beyond 3D printing – new demand on electric infrastructure

12 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Power and Energy Intensity Test Results (10 tests Completed so Far)

Model  Type   Test  Loca/on   Make   Model   Material   Part   Density   Build  Time  

Average  Power  (W)  

Energy    (Wh)  

Part  Weight  (g)    

Energy  Intensity    (Wh/g)    

or    (kWh/kg)  

Energy  Intensity  (  BTUs/g)  

Energy  Intensity    (j/g)  or  (kj/kg)  

Desktop   ORNL  MDF   Stratasys   Maker  Bot    Replicator  2   PLA   NIST  Ar<fact   100%   5hr  42min   58.42   333   112   2.97                10.14              10,704    

Desktop   America  Makes   Lulzbot   TAZ  3   PLA   Octopus   50%   32  min   55   32   6   5.33                18.20              19,200    

Desktop   ORNL  MDF   Cubify   Cube  2   PLA   NIST  Ar<fact   50%  (Strong)   7hr  17min   46.41   338   51   6.63                22.61              23,859    

Desktop   ORNL  MDF   Stratasys   Maker  Bot  Replicator  2x   PLA   NIST  Ar<fact   100%   5hr  38min   123.02   693   99   7.00                23.88              25,200    

Desktop   ORNL  MDF   CMECNC   Rostock   PLA   NIST  Ar<fact   100%   5hr  26min   132.52   720   89   8.09                27.60              29,124    

Desktop   Confiden<al   Stratasys   Uprint  SE  Plus   ABS  M30   NIST  Ar<fact   100%   3hr  27  min   390   1270   94   13.51                46.10              48,638    

Floor   America  Makes   M-­‐Lab   ExOne   Metal   logo  par<al   100%   3hr  15  min   153   485   21   23.10                78.80              83,143    

Floor   America  Makes   Stratasys   Fortus  400MC   ABS  M30   NIST  Ar<fact   100%   4hr  23  min   1561   7368   96   76.75          261.87        276,300    

Floor   Confiden<al   Stratasys   Fortus  900MC   ABS  M30   NIST  Ar<fact   100%   4hr  23  min   2451   10626   96   110.69          377.67        398,475    

Floor   America  Makes  3D  

Systems  +  NESLAB  

SLS  S  Pro  60HDHS  +  Chiller  

SLS  Duraform  

PA  NIST  Ar<fact   100%   2hr  45  min   2451   16626   72   230.92          787.89        831,300    

Page 13: Beyond 3D printing – new demand on electric infrastructure

13 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Energy Intensity Test Samples

Page 14: Beyond 3D printing – new demand on electric infrastructure

14 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Plastics Additive Manufacturing Build Times & Average Power (NIST Artifact, 100% Dense)

5.70

3.45

0.06

2.45

0.00

1.00

2.00

3.00

4.00

5.00

6.00

Desktop FD

M

Desktop FD

M

Desktop FD

M

Desktop FD

M

Floor FDM

Floor FDM

Floor SLS

Hours

Average Power (kW)

Page 15: Beyond 3D printing – new demand on electric infrastructure

15 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Plastics Additive Manufacturing Energy Intensity (kWh/kg), NIST Artifact, 100% Dense

0.00

50.00

100.00

150.00

200.00

250.00

Desktop FD

M

Desktop FD

M

Desktop FD

M

Desktop FD

M

Floor FDM

Floor FDM

Floor SLS

Ener

gy In

tens

ity (k

Wh/

Kg)

Additive Manufacturing Machine Type

Finding: Desktop Units were able to produce the same NIST part at 1/10 to 1/20th the Energy Intensity of the

Floor Models.

Page 16: Beyond 3D printing – new demand on electric infrastructure

16 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Next Steps

•  Continue collaboration with SMLC, DOE, ORNL, America Makes, OEMs and others to leverage success.

•  Continue to understand these new loads through measurement of power and energy intensity.

•  Continue collection of PQ data through testing and measurements.

•  End goal is the development or adoption of a PQ standard for advanced manufacturing to help ensure equipment is robust to typical voltage sags and momentary interruptions seen on the electrical grid.