Planning for the Futurepresented to
Sandusky Rotary Club
Thursday, March 3, 2011
-
8/7/2019 BGSU Master Plan
2/29
1965: Community establishes the COED committee and raises over $1M in2 months to establish a regional branch campus of BGSU serving Erie, Huron,and Ottawa Counties
1966: BGSU purchases 216.5 acres and names Firelands Campus of BowlingGreen State University
1968: 576 students attend classes on campus in the newly opened East (nowFoundation Hall) and West Buildings
1972: North Building opens to support community demands for technical education
and student demands for social/recreational spaces
2003: Cedar Point Center opens
2009: Clasen Welcome Center opens, providing expanded space for enrollmentservices and BGSU Bookstore
2011: New BGSU Firelands campus master plan presented to community
A BRIEF HISTORY
-
8/7/2019 BGSU Master Plan
3/29
-
8/7/2019 BGSU Master Plan
4/29
Four-Fold Academic Mission
Select BGSU bachelors degree and masters degreecompletion programs at the BGSU Firelands campus
serving place-bound students in the Firelands community
Technical and paraprofessional associate degrees whichprepare students for work settings
General education and pre-professional curricula designedto facilitate transfer to four-year institutions
Non-credit offerings to serve the personal and professional
development needs of the region
-
8/7/2019 BGSU Master Plan
5/29
BGSU Firelands Today
2,517 students
More than 3,400 degrees conferred
14 associate degrees , 8 bachelor degrees, 2 master degrees, one-year certificateprograms and workforce development offerings
54 full-time faculty members and 113 adjunct faculty, two Fulbright Scholars
Satellite courses and facilities at Norwalk HS, FRMC School of Nursing, andSandusky HS (fall 2011)
314 student computers , newly renovated MAC classroom, state-of-the-art distancelearning facilities
47-acre James H. McBride Arboretum
250-seat McBride Auditorium featuring Caryl Crane Childrens Theatre
Partners include Firelands Regional Medical Center, Lorain County CommunityCollege, Erie County Economic Development Corporation, Erie Metroparks
-
8/7/2019 BGSU Master Plan
6/29
-
8/7/2019 BGSU Master Plan
7/29
-
8/7/2019 BGSU Master Plan
8/29
-
8/7/2019 BGSU Master Plan
9/29
-
8/7/2019 BGSU Master Plan
10/29
-
8/7/2019 BGSU Master Plan
11/29
-
8/7/2019 BGSU Master Plan
12/29
4358 5098
-
8/7/2019 BGSU Master Plan
13/29
Continued Growth Expected
Colleges long-term (15+ years) strategic enrollment plan: Increaseenrollment from 2,500 students to 5,000 students
Projected annual growth: 4%
(Historical annual growth (15 year average): 6%)
Number of faculty will increase (currently 84 FTE)
2011: Shortage of academic and support space: 20,000 GSF
2025: Shortage of academic and support space: 140,000 GSF
-
8/7/2019 BGSU Master Plan
14/29
2025 Campus Master Plan Approved
Campus facilities need to be expanded to accommodate currentstudent population and projected enrollment growth
-
8/7/2019 BGSU Master Plan
15/29
-
8/7/2019 BGSU Master Plan
16/29
-
8/7/2019 BGSU Master Plan
17/29
-
8/7/2019 BGSU Master Plan
18/29
-
8/7/2019 BGSU Master Plan
19/29
A Master Plan Approved
Campus facilities need to be expanded to accommodate currentstudent population and projected enrollment growth
Consider community college partnerships to leverage southerncampus acreage to support educational mission of College
-
8/7/2019 BGSU Master Plan
20/29
-
8/7/2019 BGSU Master Plan
21/29
-
8/7/2019 BGSU Master Plan
22/29
-
8/7/2019 BGSU Master Plan
23/29
A Master Plan Approved
Campus facilities need to be expanded to accommodate currentstudent population and projected enrollment growth
Consider community college partnerships to leverage southerncampus acreage to support educational mission of College
Future landscaping should transition from College adjacent to anArboretum to College located on/in an Arboretum
-
8/7/2019 BGSU Master Plan
24/29
-
8/7/2019 BGSU Master Plan
25/29
-
8/7/2019 BGSU Master Plan
26/29
-
8/7/2019 BGSU Master Plan
27/29
A Master Plan Approved
Campus facilities need to be expanded to accommodate currentstudent population and projected enrollment growth
Consider community college partnerships to leverage southerncampus acreage to support educational mission of College
Future landscaping should transition from College adjacent to anArboretum to College located on/in an Arboretum
Continue excellent stewardship of existing campus
-