Ref. No. : PE/PG/BIF/E-5982/2018/CORRIGENDA/01 Date: 07.07.2018
Devendra Singh, Sr. Engineer/PG-I/PEM Power Project Engineering Institute Building
HRD & ESI Complex Plot No. 25, Sector -16 A,
BHEL-PEM,Noida-201301 (U.P.)
Tel No. 0120-4368877, 7503632335 Page 1 of 1
Project Engineering
Management Bharat Heavy Electricals Limited (A Govt. Of India Undertaking)
CORRIGENDA / ADDENDUM-01
PROJECT : 2X660 MW BIFPCL MAITREE KHULNA STPP-BANGLADESH
PACKAGE NAME: CONTROL VALVE (FDVs)
Our Ref : ENQUIRY No : PE/PG/BIF/E-5982/2018, Dtd- 28.06.2018
DUE DATE
17-July-2018
BY 02:00 PM (IST)
Please find below technical amendment:
REASON FOR AMENDMENT: Change in Pipe Size & Applicability of BBR Requirement.
SPECIFICATION No: PE-TS-421-145-I801B
S
No.
Sec / Clause
No. / Sheet
No.
Existing Clause
Revised Clause after Amendment
1.
Section-C
Datasheet-A
& B: Pipe
Size & BBR
Requirement
1. Datasheet –A & B:
Pipe Size: 210x42
2. Bangladesh Boiler
Act, 1923 with
amendments
Compliance &
essential Certificate:
Not required
1. Datasheet –A & B: Pipe Size: 210x45
2. Applicability of BBR Certificate &
Compliance with Bangladesh Boiler Act, 1923
with amendments
Refer updated Datasheet attached as Annexure I.
Accordingly, the bid submission of tender for CONTROL VALVE (FDVs) invited vide above Enquiry is
extended up to 17.07.2018 at 02:00 PM (IST).
Thanking You.
For & on Behalf of BHEL,