ATEP IVC First Building ADVANCED TECHNOLOGY & EDUCATION PARK South Orange County Community College District BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location and layout has been surveyed Footings are being excavated Main electrical conduit into the building is being installed Survey of Building – Identifying building location and gridlines

Upload: others

Post on 25-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 · BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location

ATEP IVC First Building

ADVANCED TECHNOLOGY & EDUCATION PARK South Orange County Community College District

BI-WEEKLY PROGRESS UPDATE Through November 15, 2016

PROJECT STATUS:

Grading and pad elevation work completed

Building location and layout has been surveyed

Footings are being excavated

Main electrical conduit into the building is being installed

Survey of Building – Identifying building location and gridlines

Page 2: BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 · BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location

First Bucket of dirt removal for the IVC First Building at ATEP

Excavation of Building Footings

Page 3: BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 · BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location

Upcoming Activities: Complete excavation of all footings

Start underground plumbing system

Set anchor bolts

Conduits for main Electrical lines into building