Bidders’ Conference and Site VisitFebruary 20th 2019
![Page 2: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/2.jpg)
Opening Notes Sophia Katsely
![Page 3: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/3.jpg)
TimeSpokemanSubject
8:30 – 9:30Conference Registration
9:30 – 9:45Nir KugelOpening Notes
Tel Aviv Metropolitan LRT Network
9:45 – 10:00Koby RosenbergThe Green Line- Project Description and Tender SOW
10:00 – 10:20Sophia KatselyTender General Overview
10:20 – 10:50Galia Scherf ShmuelBidder Composition, Professional and General
Threshold Requirements
10:50 – 11:10Coffee Break
11:10 – 11:35Galia Scherf ShmuelMain Contract Issues
11:35 – 12:05Barak KirschnerFinancial Threshold Requirements, Price Proposal,
Payment Terms and Guarantees
12:05 – 12:30Antonis AntonatosGeneral Technical Requirements, Main Interfaces
12:30 – 13:30Lunch Break
13:30 – 15:30Site Visit
Agenda
3
![Page 4: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/4.jpg)
Scope of this Presentation
4
The information presented today, including in this presentation, is not exhaustive and only partially conveys the tender information.
The Tender Documents are much wider and each Bidder is to examine them fully and carefully.
Participants are encouraged to raise any query by way of RFC according to the ITB instructions.
In the event of any discrepancy between the presentation and the Tender Documents, the provisions of the Tender Documents shall prevail.
![Page 5: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/5.jpg)
Tel Aviv Metropolitan LRT NetworkNir Kugel
![Page 6: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/6.jpg)
The Green Line- Project DescriptionKoby Rosenberg
![Page 7: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/7.jpg)
The Green Line
• Expected to serve approximately 65 million passengers annually
• 39 km of twin tracks:
34.5 km at grade, 58 Stops
4.5 km underground in the center of Tel Aviv, 4 Stations.
• Two Depots at Holon and Herzliya.
7
![Page 8: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/8.jpg)
The Green Line- Split to Segments
8
![Page 9: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/9.jpg)
Project Map
9
Levinsky
Kaplan
Carlebach
Rabin
Arlozorov West
Nordau
station
![Page 10: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/10.jpg)
Tender Scope of Works
![Page 11: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/11.jpg)
Scope of Works
11
1. At grade works at Ibn Gvirol Street from Ibn Gvirol/Bnei Dan Junction to Nordau Shaft
2. Nordau Portal
3. Nordau Shaft
4. Twin TBM tunnels form Nordau Shaft to Carlebach Northern D. Wall
5. Cross Passages between TBM tunnels
6. Outer box for Arlozorov West underground station
7. Outer box for Rabin underground station
8. Outer box for Kaplan underground station
![Page 12: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/12.jpg)
Scope of Works / Cont.
12
9. Works required at Carlebach existing station and SRS (South Retrieving Shaft)
10. Twin TBM tunnel Levinsky Shaft to SRS Carlebach
11. Levinsky Launching Shaft and C&C section
12. Levinsky Station
13. Underpass at Har Zion \ Levinsky junction
14. Levinsky Portal
15. At grade work at Har Zion from Levinsky shaft to Salame junction
16. Purple Line LRT at grade infrastructure at Levinsky St. 150 m East and West
from the centerline of Har Zion St.
![Page 13: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/13.jpg)
Contractor’s Main Responsibilities
13
• Design
• Construction
• Health and Safety
• Permitting
• Interface Management
• Handover
• Defects Liability
![Page 14: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/14.jpg)
Tender General Overview Sophia Katsely
![Page 15: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/15.jpg)
15
Tender Publication
Last Date for Clarification Requests
Submission Date 15/05/2019
15/03/2019
10/12/2018
Main Tender Milestones
Last Date for Submission of Tender Security Draft
15/04/2019
![Page 16: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/16.jpg)
• Envelope No. 1 – “General Information & Threshold Requirements”
• Envelope No. 2 – “Price Proposal”
• Envelope No. 3 – “Foreign Contractors’ Industrial Cooperation Undertaking”
One Bid
Contents of the Bid
16
![Page 17: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/17.jpg)
Classified Projects
• Demonstration of compliance with the Professional Thresholds
• Notification to NTA at least 5 working days before the Bid
Submission Date
• To be submitted in a separate sealed envelope
• Projects regarded classified in any other state than Israel will be
deemed non-compliant
17
![Page 18: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/18.jpg)
18
Compliance with Threshold Requirements
Price Proposals Scored
Highest Final Score
Successful Bidder
Tender Evaluation Process
Pass/Fail
Lowest Price
![Page 19: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/19.jpg)
Reparation Sums
• Reimbursement of the 2nd ranked Bidder in a sum of up to 1 million ILS
• Reimbursement of the 3rd ranked Bidder in the sum of up to 500,000 ILS
The sum of entitlement shall be determined based on invoices, accountant's declaration or other proof of expense, at the discretion of NTA
Entitlement to this reparation shall become due 120 days after the Effective
Date or in accordance with Clause 11 of ITB
19
![Page 20: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/20.jpg)
Tender Price Estimate
• Shall have the meaning ascribed to such term in Sub-Regulation 17a of the Mandatory Tender Regulations 5753-1993, denoted therein as " שווי התקשרויותאמדן"
• Shall be deposited into the Tender Box by the Submission Date
• NTA’s right to conduct negotiations in the event that all Price Proposals exceed the Tender Price Estimate
20
![Page 21: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/21.jpg)
Conflict of Interest
• Prohibition of engaging any of NTA’s Advisors from Annex B for the purpose of the Tender
• Submission of Annex C form prior to the Submission Date which will include details of all Bidders’ prior, currently existing & future known engagements with:
any of NTA’s Advisors – not connected with Tender or the Project;
any other advisors (not in Annex B) engaged directly/indirectly by NTA
21
![Page 22: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/22.jpg)
Foreign Contractors’ Industrial Cooperation Undertaking
• Bidder which is a Foreign Supplier must fulfill the requirements of the Israeli Ministry of Economy represented by the Industrial Cooperation Authority ("ICA")
• The signature by NTA of the Contract with the Successful Bidder shall be subject to the approval of ICA
• ICA details of contact for any queries with respect:
22
Industrial Cooperation AuthorityMinistry of Economy86 Menachem Begin Rd.,P.O. Box 36049 Tel Aviv 67138, Israel.Tel: +(972) 3 7247514 Fax: +(972) 3 [email protected]
![Page 23: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/23.jpg)
Bidder Composition Galia Scherf Shmuel
![Page 24: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/24.jpg)
24
Composition of the Bidder
Bidder = Single Corporate Entity(not partnership and not a JV)
![Page 25: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/25.jpg)
Bidder Threshold Requirements - Professional Galia Scherf Shmuel
![Page 26: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/26.jpg)
26
Design and Construction of TBM Tunnels
• The TBM design and the detailed design of the TBM works
• Construction
• Design and Construction in one project
• Completion
• at least three (3) continuous kilometers
ProfessionalThreshold Requirements
![Page 27: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/27.jpg)
27
ProfessionalThreshold Requirements
Design and Construction of TBM Tunnels/Cont.
• EPBM or Slurry TBM operating in closed mode conditions
• Soft soil or sand
• Internal diameter is at least 5 m.
• precast concrete segmental lining installed by the TBM
• beneath groundwater level
• Constructed in a dense urban area
![Page 28: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/28.jpg)
28
Construction of Underground Structures
• Construction
• Completion
• at least two (2) Underground Structures.
• Cut & Cover
ProfessionalThreshold Requirements
![Page 29: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/29.jpg)
29
ProfessionalThreshold Requirements
Construction of Underground Structures
• Total internal space area is at least 3,000 sq.m.
• The depth is at least 15 meters
• dewatering of groundwater
• diaphragm walls
• Constructed in a dense urban area
![Page 30: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/30.jpg)
30
ProfessionalThreshold Requirements
Experience as a Main Contractor
• The entity in direct contract with the Owner; or
• A subcontractor to the main contractor contracted directly to
the Owner
![Page 31: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/31.jpg)
31
ProfessionalThreshold Requirements
Registration and Classification
• A “registered contractor” with the following classifications:
• Field 100(Construction), Classification C-5• Field 200(Roads, Infrastructure and Development),
Classification C-5
• A “certified contractor for performing governmental works”
for each of the above fields and classifications
![Page 32: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/32.jpg)
32
The Bidder
The Parent Company of the Bidder holding
100%
A Sister Company
(Controlled by the same Parent Company which
holds 100% of the Bidder)
A Daughter Company
(Controlled by the Bidder)
A Major Subcontractor
(for Underground Structures only)
ProfessionalThreshold Requirements
Demonstrating Entities
![Page 33: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/33.jpg)
33
TBM TunnelsEntity X
Underground StructuresEntity X or Y
ProfessionalThreshold Requirements
Demonstrating Compliance with the Professional Threshold Requirements
• Each of the two Threshold Requirements (TBM Tunnels and Underground Structures) is to be demonstrated by one entity.
![Page 34: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/34.jpg)
Demonstrating Entity
(Parent)
The Bidder
Demonstrating Entity(Daughter)
Demonstrating Entity(Daughter)Demonstrating
Entity(Sister)
The Demonstrating Entity is responsible jointly and severallywith the Bidder for the execution of the respective Works (designand construction of TBM tunneling and/or construction of theStation Outer Box.
ProfessionalThreshold Requirements
Demonstrating Entities
34
![Page 35: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/35.jpg)
Major Subcontractor
Relevant to Underground Structures Only
Demonstrates compliance with all the experience
requirements
Can participate in one Bid only
The Bidder shall engage this entity for the construction of
the Station Outer Boxes
ProfessionalThreshold Requirements
35
Demonstrating Entities – Major Subcontractor
![Page 36: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/36.jpg)
36
Any entity which demonstrates compliance with the professional thresholds may rely on the experience of any of the following as its own experience:
Bidder / Demonstrating Entity / Major Subcontractor
Absorbed Company
Wholly Owned
Subsidiary
Joint Venture
ProfessionalThreshold Requirements
Attribution of Experience
![Page 37: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/37.jpg)
37
• 100% of its holdings are held by its parent company.• The professional experience of a Wholly Owned
Subsidiary is deemed to be that of its parent company.• A Wholly Owned Subsidiary is not required to fulfill the
role or to submit forms as a Demonstrating Entity• A demonstrating entity may rely on the experience of
any number of Wholly Owned Subsidiaries to demonstrate a Threshold Requirement
ProfessionalThreshold Requirements
Wholly Owned Subsidiary
![Page 38: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/38.jpg)
38
Wholly Owned Subsidiary B
Bidder/ Demonstrating Entity/ Major Subcontractor
Wholly Owned Subsidiary A
Wholly Owned Subsidiary C
Project I Project II Design
ProfessionalThreshold Requirements
Wholly Owned Subsidiary
![Page 39: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/39.jpg)
39
41
• The experience of a company which was fully absorbedby the demonstrating entity as a result of a merger
• The Surviving Company (the demonstrating entity) is attributed the experience of the Absorbed Company
• Subject to the proper submission of the form and the approvals required in the ITB.
ProfessionalThreshold Requirements
Attribution of Experience of an Absorbed Company
![Page 40: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/40.jpg)
40
• The demonstrating entity was a member of a Joint Venture inthe demonstrated project
• The demonstrating entity actually performed the activitiesrequired to demonstrate the Threshold Requirement
ProfessionalThreshold Requirements
Attribution of Experience of a Joint Venture
![Page 41: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/41.jpg)
Bidder Threshold Requirements - General
![Page 42: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/42.jpg)
42
General Threshold Requirements
• Tender Security of ILS 40 m
• Participation Fee of ILS 20 k
• Submission of the Industrial Cooperation Authority forms and compliance
with its requirements.
• Approvals and Affidavits pursuant to the Public Entities Transaction Law
![Page 43: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/43.jpg)
Coffee Break
![Page 44: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/44.jpg)
Contract Main Issues
![Page 45: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/45.jpg)
Volume 1 - Invitation to Bid
Volume 2 - General Conditions of Contract + Annexes
Volume 3 - General Employer’s Requirements
Volume 4 - Specifications (including drawings)
Content of Contract
45
![Page 46: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/46.jpg)
General Principles of the Contract:
46
• Design Build
• Responsibilities of Primary Contractor on Site
• Lump Sum Contract
• Variations mechanism
• Sectional Completion
• Defects Liability Period (36 months from Project Taking-Over)
• Arbitration
![Page 47: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/47.jpg)
• A single price for all the Works and obligations under the Contract
• Payment according to Payment Milestones
• Adjustments in the event of changes in scope, or NTA’s risk events
• Additional payment in respect of Provisional Sums and Option works
Lump Sum Contract
47
![Page 48: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/48.jpg)
Provisional Sums
48
• Provisional Sums = items not to be priced by the Bidder
• A global sum is provided by NTA
• Adjusted in accordance with the final design of these items.
• Payment will be evaluated in accordance with the evaluation mechanism
in the contract
![Page 49: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/49.jpg)
Utilities Relocation
49
• Priced within the Lump Sum
• May extend beyond the Site
• Utility Detection Report is not complete and not exhaustive
• However, Variation Orders will be considered for “Unknown Utilities” Utilities discovered during the execution of the Works which are (1) not detailed in the
Contract or Statutory Plans; (2) were not identified prior to Bid Submission Date by anyRelevant Authority or utility owner; (3) are Unforeseeable; and (4) which requiretreatment or relocation;
Enhancement of utilities, as may be required by any of the utilities owners, which is notessential to the completion of the Works and which is Unforeseeable.
![Page 50: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/50.jpg)
Major Utilities Relocation Works
50
• For item #2 (water supply main pipe) only the direct works of the water supply main pipe relocation will be paid within the Provisional Sum
• Those works are being designed by NTA and the design will be handed over to the Contractor
• The Contractor shall complete engineering coordination if required and shall obtain all the required permits for those works
1. Super High Voltage lines: Relocation of existing twin super high voltage cables at Har Zion St. from KibbutzGaluyot Rd/Har Zion St. to the sub-station located at Begin St.
2. Water Supply Main Pipe: Relocation of existing main water supply (diam. 36") at Har Zion St. from Shalma Jct.to Salomon Jct.
3. Sewage Main Line: Relocation of existing main sewage pipe (diam. 800 mm) across Ibn Gabirol St. at DavidHamelech JCT (King David Jct.).
4. Main Drain Culvert: Relocation of existing Main Drain Culvert (Approx. 280x185 Cm) at Nordau Sq. area andfrom Shimon Hatarsi Jct. towards the South bank of the Yarkon River (Approx. 280x185 Cm).
![Page 51: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/51.jpg)
• Businesses and homes along the tunnel alignment and around the station boxes• The Contractor as the designer is responsible to minimize disruption• Some disruption may be unavoidable• If any structures or areas are to be evacuated, or access to any structures or areas are to
be disrupted, then the design shall demonstrate why it is unavoidable• Design which includes evacuation or other disruption to properties is to be submitted
at least 6 months in advance• NTA is to approve such design• The costs of relocating and accommodating occupants due to unavoidable disruption
which was approved by NTA, shall be the responsibility of NTA and shall be made directly by NTA to the third party
• Such measures are to be taken into account in the time schedule – no entitlement for extension of time.
• Further terms within the Contract
Disruption and Evacuation of Properties
51
![Page 52: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/52.jpg)
• Station Entrances Boxes - evaluation in accordance with the mechanism of evaluating Variations
• Taking Care Period – payment of costs plus overhead and profit, subject to a monthly cap as stipulated in the contract
Optional Works
52
![Page 53: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/53.jpg)
Bidder Threshold Requirements- Financial Barak Kirschner
![Page 54: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/54.jpg)
54
TO – Turnover of the relevant fiscal year
t – Most recent Financial Statement (provided such is not earlier than for the year 2017)
Turnover 3 Latest Financial Statements
Average Annual Turnover => ILS 1,600,000,000
Financial Threshold Requirements
Average Turnover =𝑻𝑶𝒕 + 𝑻𝑶𝒕−𝟏 + 𝑻𝑶𝒕−𝟐
𝟑
![Page 55: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/55.jpg)
55
Cash Flow from Operating Activities
3 Latest Financial Statements
Average Annual Cash Flow from Operating Activities
Positive or equal to zero
Average Annual Cash Flow = 𝑪𝑭𝒕+𝑪𝑭𝒕−𝟏+𝑪𝑭𝒕−𝟐
𝟑
CF - The cash flow from operating activities for the relevant fiscal year
t – Most recent Financial Statement (provided such is not earlier than for the year 2017)
Financial Threshold Requirements
![Page 56: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/56.jpg)
56
Or
ABS [X] = Absolute value CFt = The cash flow from operating activities, in the Financial Statement of year t, provided such is not earlier than for the year 2017E = The equity on the last day of the fiscal year, based on the Financial Statement of year t, providedsuch is not earlier than for the year 2017
ABS [𝑪𝑭𝒕+𝑪𝑭𝒕−𝟏+𝑪𝑭𝒕−𝟐
𝟑]/ E < 25%
ABS [CFt] / E < 25%
In the event the Average Annual Cash Flow from Operating Activities is negative
Financial Threshold Requirements
![Page 57: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/57.jpg)
57
Equity *Latest Financial Statement
Minimum Equity ILS 400 million
Financial Threshold Requirements
* Most recent Financial Statement, provided such is not earlier than for the year 2017
![Page 58: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/58.jpg)
61
No Going Concern
Each of the following entities is not under any voluntary or involuntary bankruptcy process (liquidation or reorganization), or receivership or commencement of a similar insolvency proceedings, and its last Financial Statement does not include any Going Concern notice:
(a) The Bidder;
(b) A Demonstrating Entity and/or Major Subcontractor relied upon for demonstrating compliance with any of the Professional Threshold Requirements (if applicable); and
(c) A Parent Company relied upon for demonstrating compliance with the Financial Threshold Requirements (if applicable).
Financial Threshold Requirements
![Page 59: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/59.jpg)
Israeli GAAP
US GAAP
International Financial Reporting Standards (IFRS)
China Accounting Standards (CAS)
French GAAP
58
Financial Threshold Requirements
![Page 60: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/60.jpg)
Price Proposal
![Page 61: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/61.jpg)
Price Proposal
60
• The currencies of the Price Proposal shall be denoted in ILS entirely.
• The Price Proposal shall be exclusive of VAT.
• All submitted prices and rates shall be non-negative values
• For the purpose of evaluation of the Bid there shall be no indexation of prices
• The Price Proposal shall include all costs and expenses required for the execution of the Works, including all risks, liabilities and obligations set out or implied in the Bidding Documents
General Instructions
![Page 62: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/62.jpg)
61
Evaluation Formula – Temporary Score
TS = A + PS * (1-D)
• TS – Temporary Score
• A – Lump Sum Proposal (Price Proposal excluding the Provisional Sums)
• PS – Provisional Sums (ILS 317,000,000)
• D – Proposed Discount rate (Dekel and Netivei Israel Cost Index)
Price Proposal
![Page 63: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/63.jpg)
Evaluation Formula – Final Score
FS =LTS
Bidder i TS∗ 𝟏𝟎𝟎
• FS – Bidder’s Final Score in the range of 0 to 100 points
• D – Proposed Discount Rate
• LTS – The lowest Temporary Score (TS)
• Bidder (i) TS – Bidder i Temporary Score (TS)
The Bidder with the highest Final Score (FS) will be declared the Successful Bidder
62
Price Proposal
![Page 64: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/64.jpg)
• All payments will be paid in ILS
• ILS Coefficient basket of indices shall not be less than seventy percent (70%)
• EUR or USD Coefficient basket of indices shall not exceed thirty percent (30%)
Linkage Mechanism
Coefficient basket of
indices EUR USD ILS Total
Limitation No more than 30% No less than 70%
Israeli Labour cost index ___% ___% 100%
Exchange Rates on Base
Date
[To be completed
by NTA]
[To be completed
by NTA]1
Price Adjustment and Indexation- Coefficient basket of indices
![Page 65: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/65.jpg)
Value on Base Date – will be published by NTA 10 days prior to Bid Submission Date
Index Title CoefficientCountry
of OriginCurrency
ILS Only___%
(Max 100%)Israel ILS
Israeli CPI___%
(Max 100%)Israel ILS
Building Inputs for
Residential Building
(IRC)
___%
(Max 80%)Israel ILS
Paving and Bridging
Input Price (PBI)
___%
(Max 20%)Israel ILS
Linkage Mechanism
ILS Coefficient basket of indices table:
![Page 66: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/66.jpg)
Index Title Coefficient Country of Origin Currency
EUR Only___%
(Max 100%)European Union Euro
HICP___%
(Max 100%)European Union (28 Countries) Euro
Instructions and Limitations
EUR Coefficient basket of indices table:Value on Base Date – will be published by NTA 10 days prior to Bid Submission Date
![Page 67: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/67.jpg)
Index Title CoefficientCountry of
OriginCurrency
USD Only___%
(Max 100%)USA USD
US-CPI___%
(Max 100%)USA USD
Value on Base Date – will be published by NTA 10 days prior to Bid Submission Date
USD Coefficient basket of indices table:
Instructions and Limitations
![Page 68: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/68.jpg)
Payment Terms and Guarantees
![Page 69: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/69.jpg)
Lump Sum Proposal
Lump Sum Proposal
Payment Milestones (Annex 3)
Advance Payment
Deduction
Provisional Sums
Variation Order
Options
![Page 70: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/70.jpg)
Terms of Payment
• All other sums due to the Contractor in accordance with the Contract
(including in respect of Variation Orders and/or Works instructed under
Provisional Sums) shall become due as stipulated in the Contract or as
shall be instructed by NTA
• NTA may instruct that additional payments or deductions shall be
implemented by:
1. adjustment of the Payment Milestones under Annex 3;
2. definition of new payment milestones as may be applicable to the
additional payments, and/or
3. in respect of deductions, deduction from any sums due to the
Contractor, including from sums due as additional payment
![Page 71: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/71.jpg)
64
Lump Sum Proposal - Annex 3 – Payment Milestone
Milestone % out of Lump Sum Proposal prior to
Advance Payment deduction
MS Milestone DescriptionMilestone % out of Lump
Sum Proposal
Payment based on Completion of Milestone Pay (MP) /
Payment based on Progress of Work (PP)
BOI
TBM Procurement, mobilization and Disassembly
2.01TBM1 Machines Order
Placement 1.17% MP Placement of TBM order per approved design.
Stations Outer Boxes
0.4-0.2
Arlozorov West OB - Slurry Walls
3.20% PP
Including other retaining walls and temporary support elements needed. Buildings survey and monitoring of existing buildings. If required building reinforcement will be paid as a provisional sum. Payment will be pro rata to linear meter completion of the perimeter to the required depth.
Payment based on completion (MP) or progress (PP) in accordance to BOI instructions
![Page 72: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/72.jpg)
65
Annex 3 – Payment Milestone
Example (for illustration only):
Component Value
A Lump Sum Proposal ILS 1,000,000
Milestone Type Completion of Milestone Payment (MP)
B Milestone % out of Lump Sum Proposal 10%
C Advance Payment Deduction 12%
Interim Payment
ILS 1,000,000 X 10% X (100%-12%) = ILS 88,000
A B C
![Page 73: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/73.jpg)
Guarantee Amount Validity
Advance Payment
Guarantee(s)
• 1st - 5% out of the Accepted Price Proposal plus VAT
• 2nd – 5% out of the Accepted Price Proposal less deductions plus VAT
• Valid until the full repayment of the Advance Payment by the Contractor
Performance Guarantee
7% of the Contract Price• Issue prior to the Effective Date• Valid from the date of its issuance and until the
Project Taking Over Certificate
Defect Liability
Guarantee5% of the Contract Price
• Precondition for Project Taking Over Certificate• A year prior to the end of the Defects Liability
Period, shall be reduced to 2.5%• Valid until the lapse of two (2) months following the
lapse of the Defects Liability Period
• All Guarantees shall be denoted in ILS• All Guarantees will be linked to the Israeli Consumer Price Index (CPI)
Contract Guarantees
66
![Page 74: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/74.jpg)
General Technical Requirements Antonis Antonatos
![Page 75: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/75.jpg)
68
Mobilization Sites
• Potential mobilization sites have been identified
• For details see Volume 3, Chapter 13
• Preliminary coordination with the Tel Aviv municipality relating to
Permits and Approvals have been conducted
• Some of the mobilization sites will become available at a later date than
the Commencement Date, as described in Chapter 13, Annex C
![Page 76: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/76.jpg)
69
Mobilization Sites/Cont
• The Contractor’s main entitlements:
Secure the mobilization sites including obtaining any necessary
Permits and Approvals
Develop the Construction and Site Management Plan within the
time period defined in Volume 3, Chapter 4
Erect, maintain and handover or remove the different sites
According to Chapter 13 and NTA's Instructions
![Page 77: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/77.jpg)
70
Contractor Team
• Key PersonnelAll key personnel listed in Volume 3, Chapter 4, Table 1.3. shall be identified by
name, title and position. Approval of the Project Manager and the Design Manager is a pre-condition for the
signing of the Contract.
• Other Team Members Other requirements for the Contractor team members are specified in the Contract.
• General Each Contractor Team should comply with the specific contract requirements. The Contractor shall submit the required details for each Team Member on time. All personnel shall be proficient in English or Hebrew. A SONO of the Engineer is required before the appointment/replacement of any
of the abovementioned personnel.
![Page 78: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/78.jpg)
Design Stages (Vol 3, Ch 5, Sec 5.3.1)
Stage 1 - Preliminary design Package – no later than 60 days from theCommencement Date.
Stage 2: Detailed Design Package including all needed permits,statutory and third parties' approval.
Stage 3: Construction Design Packages including the ConstructionDrawings, Shop Drawings and Installation drawings.
Stage 4: As-Built Design Packages including the As-Built Drawings
The design schedule will comply to Vol 2 contract Milestones.
71
Design Phases
![Page 79: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/79.jpg)
72
• The Time Schedule as per the Contractual Milestones is achievable yet
aggressive. NTA will insist on Contractor’s compliance with the schedule.
• The Contractor’s main responsibilities include, inter alia:
Appoint a competent Time Schedule Manager
Plan the Works so that all Contractual Milestones are achieved on time
Use Primavera P6 (version 7 or later), or another Schedule Software approved
by NTA, and Tilos software (version 10 or later)
Time Schedule
![Page 80: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/80.jpg)
73
Time Schedule/Cont.
The Contractor shall prepare a detailed Baseline Time Schedule and submit it
for the review of the Employer in two phases, as follows:
o Phase 1 shall be submitted within 30 days of the Commencement Date.
will describe in detail the design period and stages, and in general the
construction activities
o Phase 2 shall be submitted within 120 days of the Commencement Date
will detail also the construction period through to final Project completion
![Page 81: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/81.jpg)
74
Time Schedule/Cont.
The Contractor shall update, document and submit the Current Time Schedule
as required in the Contract
The Contractor shall submit a Monthly Progress Report in pdf format together
with an approved Schedule Software file of the Current Time Schedule
• The full scope of the general requirements related to the Time Schedule is
specified in Volume 3- Chapter 6
![Page 82: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/82.jpg)
Risk Management
75
• The Contractor’s main responsibilities include, inter alia:
Appoint a competent and experienced risk manager
Submit a detailed Risk Management Plan [RMP]
Conduct a detailed risk survey, incl. risk assessment and risk mitigation plans
Carry out on-going risk monitoring and control
Submit updated risk registers on a monthly basis
Conduct monthly risk review meetings with the Engineer
• The full scope of the general requirements related to Risk Management is
specified in Volume 3- Chapter 9
![Page 83: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/83.jpg)
76
Health and Safety
• The Contractor’s main responsibilities include, inter alia:
Present the Safety Management Plan
Present the Safety Staff names and CVs
Prior to commencing tunneling works, an Emergency Response Plan
coordinated and approved by the Local Fire Fighters Dept .
All the safety and emergency plan must meet the Israeli Standard IS5567
and ISO 18000 requirements
• A full scope of the general requirements related to Health and Safety is
detailed at Volume 3- Chapter 12, and Volume 2
![Page 84: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/84.jpg)
Quality Control
77
• The Contractor’s main responsibilities include, inter alia:
Present a Quality Control Company and Key Personnel
Prepare a Quality Plan Present a QC/QA Electronic Document Management
System
Select a site laboratory
Prepare Inspection and Test Plan
Control the Quality of the Construction and Document it
• A full scope of the general requirements related to Quality Management is
detailed at Vol. 3 Pt VII, Chapter 8
![Page 85: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/85.jpg)
78
• The Contractor’s main responsibilities include, inter alia:
Develop, implement and maintain an E&S Management Plan (ESMP)
Obtain all necessary permits and approvals, comply with existing permits
and approvals and the conditions specified therein
Comply with the Employer’s E&S policies as specified in the DSM and
QMS
Minimize the impact of the Works on the surrounding environment
Environment and Sustainability
![Page 86: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/86.jpg)
79
• Monitoring, Mitigation, Recording and Reporting on the following, but not limited to: Noise & Vibration Water and Wastewater Contaminated soil Recycling material Air Quality Pollution Control Trees and Biodiversity HAZMAT Waste handling
• A full scope of the general requirements related to Environment and Sustainability is detailed at Volume 3- Part VII Chapter 14
Environment and Sustainability/Cont.
![Page 87: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/87.jpg)
The Contractor’s main responsibilities include, inter alia:
• Establish RAMS Management System, and appoint competent RAMS manager
• Establish a RAMS management mechanism interfacing with Safety, Engineering, Construction
• Update the RAMS report as part of the As Built documentation to be handedover to the Client
• Interface and contribute with inputs to the RAMS management system of the PPP project, for the drafting of the final RAMS documentation of the Green Line project
RAMS
80
![Page 88: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/88.jpg)
81
• Subject to the delivery dates in Annex 1 (Site Delivery Dates)
• Approval of Contractor's Design Package Stage 3
• Secure all the required approvals and Permits from all the Relevant Authorities
• Site delivery- in the presence of NTA and the Contractor.
• The parties shall execute a delivery protocol
Delivery of Site
![Page 89: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/89.jpg)
Main Interfaces
![Page 90: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/90.jpg)
The Green Line- Infra 1 and Infra 2 Works
• This Contract includes the Infra 1 works in the underground section • Infra 2 works - a PPP Tender, expected to be issued in May 2019
• Infra 2 Works includes: Design and build of the Inner Boxes and Fit-out of the UG Stations Multi-tabular Technical rooms Upper structure (slab track and rails) Supply and installation of all the systems for the Green Line Design and build of the Depots Manufacture, supply and commissioning of all the rolling stock vehicles Maintenance of both the LRV fleet and the infrastructure of the
Green Line
83
![Page 91: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/91.jpg)
Interfaces with the PPP Contractor
• The split of work between the Contractor and the PPP Contractor is optimal and
aimed at minimizing interfaces and dependencies between the two contractors
• The feasibility of placing the Inner Box and the functional requirements within
the Outer Box was validated for the three Underground Stations
• The SOW of the PPP Contractor will be aligned with the SOW of the Contractor
• The entitlements of the Contractor regarding Interfaces and Permits are
detailed in the Contract Documents, inter alia in Volume 3 Chapter 7
(Interface Management) and Chapter 35 (Permits)
84
![Page 92: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/92.jpg)
The Contractor’s main responsibilities (Vol. 3, Chapter 7) include inter alia:
• Establish and maintain an interfaces Management System
• Submit a detailed Interfaces Management Plan
• Appoint a competent Interfaces Manager
• Chart all Internal and External Interfaces, in a detailed Interfaces Matrix.
• Appoint owners of interfaces to all critical interfaces
• Conduct interfaces workshops with the Engineer
Interface Management
85
![Page 93: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/93.jpg)
86
• Report and monitor the status of interfaces
• Verify and validate all interfaces and their impact on design
• Update and deliver as part of the As Built documentation the Baseline
Configuration reports
• Coordinate the work with interfacing contractors’ works
• Share Contractor’s design and manage all the interfaces with the PPP
Contractor
Interface Management/ Cont.
![Page 94: Bidders Conference and Site Visit - נת"ע · 2019-09-22 · Design and Construction of TBM Tunnels/Cont. • EPBM or Slurry TBM operating in closed mode conditions • Soft soil](https://reader036.vdocument.in/reader036/viewer/2022062922/5f098a887e708231d42751f1/html5/thumbnails/94.jpg)
Thank you!