bidder’s conference october 1, 2015. introductions systems integration assessment current issues...

27
Systems Integration Project Bidder’s Conference October 1, 2015

Upload: alicia-morgan

Post on 02-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Systems Integration Project

Bidder’s ConferenceOctober 1, 2015

Page 2: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Presentation Outline

IntroductionsSystems Integration AssessmentCurrent IssuesProposed SolutionsProject TimelinesNext StepsSubmitted QuestionsOpen Discussion

Page 3: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Assessment

Scope: Assess the District’s need for technology enhancement and automation, and make recommendations

Interviewed over a dozen District staff including end users, IT personnel and managementReviewed internet/intranet and databasesDocumented the business caseResearched the possible solutions Provided recommendations

Page 4: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Assessment (continued)

MISSION: To achieve clean air goals by leading the region in protecting public health and the environment through

innovative and effective programs dedicated staffcommunity involvement, and public education

Page 5: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Business Case Conclusion

Improve productivity and communicationDirect more resources on developing innovative programsBetter communicate with and serve the public via improved website and expanded use of social mediaMore effectively plan operating and capital budgetsWork using mobile devicesRetain and attract talented staff

State of the Art system with automated and effective business processes would create ability to:

Page 6: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Current Issues

Business processes/systems have not been updated to modern technological standards

Losing experienced staff to retirement

Most business processes are manual and paper intensive

Operational data is maintained separately – fragmented, often redundant data entry, requires high maintenance

Website provides only static content, lacks customer self-service options

Fiscal planning/tracking is manual-intensive and primarily Excel spreadsheet driven

Lack of effective mobile solutions for field staff

Page 7: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

District Website

Page 8: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Stationary Sources

ApplicationSS

MS Access

Stationary Sources

AsbestosApplication Asbestos

MS AccessAsbestos

ComplaintApplication Complaint

MS AccessComplaint

Mobile Sources

Web App MS SQL Server

Mobile Sources

PERPApplication

Portable Equip.

MS Access

PERP

ViolationApplication

Violation

MS Access

Violation

Wood BurningApplication

Wood Burning

MS Access

Wood Burning

Application Xtender Document Scanning

Application

Application

Xtender Database

Web Xtenders Document

Retrieval Portal

Databases

Existing Databases Reports

Page 9: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Financial System

Page 10: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Combination of Manual and automated systems.

Current Revenue Side Business Process

Page 11: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted
Page 12: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Assessment Recommendations

Develop new internet and intranet sites

Implement web enabled Lines-of-Business (LOB) application with a centralized database

Implement an Enterprise Financial System

Integrate LOB application with the Financial System

Improve document management and control standards

Establish automated process workflows

Page 13: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Lines of Business

LOBsMobile Source, Asbestos

Stationary SourcePortable Equipment

Complaints, Violations Wood Burning

LUTRAN projectsAir Monitoring

ReportsPermitsInvoices

www.airquality.org

Collaboration

SharePoint Finance

Content Management

Proposed Solution

Finance

Unified Communication: email, video, voice, IM, presence

Databases

Page 14: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Website (Internet) Project

Focus:Customer self-service – data queries (permits, source locations, etc.), register complaints, permit and incentive program applications, public records requestsImprove appearance and ease of navigation Responsive design – adapts to different devicesEnhance content management capabilities

Page 15: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Data Integration Project

Focus:Increase efficiency by eliminating duplication of effort and automating review/approval processIncrease system performance, reliability & integrity of dataIntegrate with website to allow for enhanced customer self-serviceProvide mobile options for field staffConnect to financial systemReduced maintenance / troubleshooting / file storage

Page 16: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Application Received

Manual receipt written

Application information entered in S1DATA

including payment info

Folder labels printed

Folder created and given to

PC for assignment

PC logs application info into Excel

Payment logged in Excel

Application assigned to engineer via SS1DATA

Application folder given to engineer

Application reviewed for

completeness

Complete? Info received?

Info received

?

Incompleteness letter

prepared in MS Word

Incompleteness letter sent

Prepare Intent to Cancel letter

In MS Word

Supervisor approves Intent to Cancel letter

Engineer mails Intent to Cancel

letter

Cancel application

Yes

No

No

Yes

Engineer Performs

evaluationIn MS Word

Engineer Updates1SSDATA

Completeness letter prepared

in MS Word

Completeness letter sent by

engineer

Engineer prints evaluation and draft ATC and submits to

PC for review

PC reviews evaluation & ATC

Eval & ATC OK?

PC approves Eval & ATC and

returns to engineer

No

Engineer prepares final

ATC & cover letter and submits file

to manager

Manager reviews

Eval& ATC

Eval, ATC & letter

OK?

Manager returns file

to PC

PC discusses the corrections

w/engineer

Yes

No

Manager sigs ATC & Eval and returns file to

engineer

Engineer prepares ATC

for mailing

Admin staff (Daena) mails ATC & returns

folder to engineer

Engineer files the ATC

and waits for

Inspection & PO Process

ADMINISTRATION STAFF

SSD PROGRAM COORDINATORSSD PROGRAM SUPERVISORSSD PROGRAM MANAGER

SSD PERMIT ENGINEER

Yes

Application and ATC Process

Page 17: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Eval & ATC OK?

Application Received

Manual receipt written

Application information entered in S1DATA

including payment info

Folder labels printed

Folder created and given to

PC for assignment

PC logs application info into Excel

Payment logged in Excel

Application assigned to engineer via SS1DATA

Application folder given to engineer

Application reviewed for

completeness

Complete? Info received?

Info received?

Incompleteness letter prepared

in MS Word

Incompleteness letter sent

Prepare Intent to Cancel letter

In MS Word

Supervisor approves Intent to Cancel letter

Engineer mails Intent to Cancel

letter

Cancel application

Yes

No

No

Yes

Engineer Performs

evaluationIn MS Word

Engineer Updates1SSDATA

Completeness letter prepared

in MS Word

Completeness letter sent by

engineer

Engineer prints evaluation and draft ATC and submits to

PC for review

PC reviews evaluation & ATC

PC approves Eval & ATC and

returns to engineer

No

Engineer prepares final ATC & cover letter and submits

file to manager

Manager reviews

Eval& ATC

Eval, ATC & letter

OK?

Manager returns file to

PC

PC discusses the corrections

w/engineer

Yes

No

Manager sigs ATC & Eval and returns file to

engineer

Engineer prepares ATC

for mailing

Admin staff (Daena) mails ATC & returns

folder to engineer

Engineer files the ATC and waits for Inspection & PO Process

ADMINISTRATION STAFF

SSD PROGRAM COORDINATOR

SSD PROGRAM SUPERVISOR

SSD PROGRAM MANAGER

SSD PERMIT ENGINEER

Yes

Red represents manual steps eliminated or streamlined through automation

Page 18: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Financial System Project

Focus:Automated grant and fund managementTrack expenses by programPre-encumbrance and encumbrance recordingImprove reporting capabilities for enhanced budgeting and financial planningImprove internal controlsAutomate review/approval for efficiency and accuracy

Page 19: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Collaboration, Workflow, Document Management Project

Focus:Create sites for information sharing and enhanced ability for staff to collaborate on work products

Automate several manual processes Permit Applications and Renewals

Purchase Requests and Contracting

Travel Requests and Board Packages

Rule Development and Mobile Source Incentive Program Administration

Create central repository for District documents to facilitate collaboration, easy retrieval, version control and compliance with records retention schedules

Page 20: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Unified Communication Project

Focus:Conversations in one app—IM, audio and video calls, online meetings and sharingCollaborate from Office applications like Word and PowerPoint to start meetings and/or present whatever staff is working onSchedule meetings and see IM history in Outlook

Page 21: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Benefits

Customer • Enhanced self-service; reduced drive-time• Real-time data• More intuitive and improved navigation• Increased transparency

Staff • Eliminate duplication of effort and reduce likelihood of errors• More data driven decision-making • Better collaboration on work tasks and projects• Improved employee morale/retention• Increased flexibility to work using mobile devices• Improved training / knowledge transfer capabilities

Page 22: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Benefits (continued)

Financial • One-time expenditures, on-going gains in efficiency and accuracy• Increase capacity for growth without adding resources • Improved operating and capital budget planning & reporting• Reduced supply costs, e.g. paper, toner, file cabinets, etc.

Technical • Control of managing the process• Reduced data storage • Web accessible / centralized control / remote update capabilities• Interconnectivity to all enterprise systems• More secure, easier to maintain

Risk Reduction

• Improved document versioning and records management • Reduced reliance on individual knowledge

Page 23: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Systems Integration Project Timeline

Page 24: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Next Steps

October 2015 – Release RFP for Line of Business Database (LOB) and Finance Enterprise Systems

October 2015 – Contract Authorization to Board of DirectorsSharePoint Implementation (Website/Intranet/Workflow/Doc Mgmt)

Skype for Business Implementation (Unified Communication)

November 2015 – Begin SharePoint and Skype for Business Projects

January 2016 – Contract Authorization to Board of DirectorsLOB and Finance System Implementation

February 2016 – Begin LOB and Finance Projects

Page 25: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Submitted Questions

RFP Response and 20-page limit: Update RFP to reflect sections 9-18 count as part of 20-page limit. Bios/resumes for section 15 may also be attached and excluded from the 20-page limit

District desires the public websites (SMAQMD and CAPCOA) to be completed by August 1, 2016

It is anticipated that 8-10 business/functional users will update content/images on the public sites. IT staff will update content beyond their scope.

Interactive forms and workflow on the www.airquality.org site (to be determined, examples)

Page 26: Bidder’s Conference October 1, 2015. Introductions Systems Integration Assessment Current Issues Proposed Solutions Project Timelines Next Steps Submitted

Submitted Questions (continued)

CAPCOA websites:Public and private – requesting access for proposers to view private site

Hosted on Media Temple services – separate organization, stand-alone website maintained by CAPCOA staff

Reference to installation of Metalogix, Nintex, K2 and AgilePoint – District does not own any of these applications. Seeking recommendation from proposers on apps to support form development and workflow functionality

EMC AppExtender as part of this overall effort – desire is to migrate all document management to SP if feasible